A kind of anti-seepage structure at river channel bridge pier and construction method thereof

By forming a burr layer on the bridge pier and bonding an anti-seepage layer, combining an anti-seepage geomembrane and a gravel layer, the problem of anti-seepage at the bridge pier is solved, effective sealing between the bridge pier and the river channel is achieved, and the anti-seepage effect is improved.

CN110644431BActive Publication Date: 2024-11-12BEIJING HUAHAO WATER CONSERVANCY & HYDROELECTRONIC PROJECT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201910888766.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-09-19
Publication Date
2024-11-12
Estimated Expiration
2039-09-19

AI Technical Summary

Technical Problem

In river channels with cross-river bridges, the anti-seepage structure at the bridge piers is prone to leakage, and the prior art is difficult to effectively prevent water leakage.

Method used

By forming a burr layer on the bridge pier and bonding the first anti-seepage layer and the second anti-seepage layer on it, combining the anti-seepage geomembrane and gravel layer, sealing with adhesive, forming a water stop ring to enhance the facade Anti-seepage effect.

Benefits of technology

The sealing between the bridge piers and the river channel is achieved, the anti-seepage effect is improved, the water level of the river is stable, and the water leakage is avoided.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN110644431B_ABST
    Figure CN110644431B_ABST
Patent Text Reader

Abstract

The present invention relates to an anti-seepage structure at a river channel bridge pier, and relates to the technical field of river channel anti-seepage, comprising a lower sand layer laid on the bottom of the river channel, an anti-seepage geomembrane layer laid on the lower sand layer and sleeved on the bridge pier, an upper sand layer arranged on the anti-seepage geomembrane layer, and a gravel layer arranged on the upper sand layer, a roughened layer is arranged between the upper sand layer and the lower sand layer on the outer peripheral wall of the bridge pier, an adhesive is applied on the roughened layer, a first anti-seepage layer ring-arranged on the roughened layer is bonded to the outside of the roughened layer by the adhesive, the lower end of the first anti-seepage layer extends downward to the anti-seepage geomembrane layer, a second anti-seepage layer sleeved on the bridge pier is bonded to the first anti-seepage layer, and an upper sand layer and a gravel layer are arranged on the second anti-seepage layer in sequence from bottom to top. The present invention has the advantage of good anti-seepage effect.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of river channel anti-seepage, and in particular to an anti-seepage structure at a river channel bridge pier and a construction method thereof. Background Art

[0002] Due to the low flow rate and limited width of the river, anti-seepage measures are generally required to ensure the water level in the river under the condition of limited water resources. Currently, a layer of anti-seepage geomembrane is generally laid in the river to prevent the water in the river from leaking to the bottom of the river. However, in some rivers with cross-river bridges, the piers are generally set in the river, and the anti-seepage structure of the river at the piers is prone to leakage. Summary of the invention

[0003] The first object of the present invention is to provide an anti-seepage structure at a river channel bridge pier, which has the advantage of good anti-seepage effect.

[0004] The above-mentioned object of the present invention is achieved through the following technical solutions:

[0005] A seepage-proof structure at a river channel pier comprises a lower sand layer laid on the bottom of the river channel, an anti-seepage geomembrane layer laid on the lower sand layer and sleeved on the pier, an upper sand layer arranged on the anti-seepage geomembrane layer, and a gravel layer arranged on the upper sand layer, a roughened layer is arranged on the outer peripheral wall of the pier between the upper sand layer and the lower sand layer, an adhesive is applied on the roughened layer, a first anti-seepage layer arranged in annularly on the roughened layer is bonded to the outside of the roughened layer by the adhesive, the lower end of the first anti-seepage layer extends downwardly to the anti-seepage geomembrane layer, a second anti-seepage layer sleeved on the pier is bonded to the first anti-seepage layer, and an upper sand layer and a gravel layer are arranged on the second anti-seepage layer in sequence from bottom to top.

[0006] By adopting the above technical scheme, a roughened layer is formed by roughening the pier, thereby facilitating the bonding of the first anti-seepage layer to the pier. The upper part of the first anti-seepage layer surrounds the pier and is sealed by bonding with an adhesive to seal the pier in the vertical direction. Then, a second anti-seepage layer sleeved on the pier is bonded to the first anti-seepage layer, and the pier is sealed in the horizontal direction by the second anti-seepage layer, thereby ensuring the sealing of the connection between the river channel and the pier, which has the advantage of good anti-seepage effect.

[0007] The present invention is further configured as follows: the first anti-seepage layer is rectangular, and comprises an integral part arranged around the roughened layer, and overlapping strips fixed side by side at the lower end of the integral part and overlapped on the anti-seepage geomembrane layer.

[0008] By adopting the above technical solution, the joints between the bridge pier and the anti-seepage geomembrane layer are vertically sealed by the whole part encircling the roughened layer, and the lap strips facilitate the surrounding arrangement of the first anti-seepage layer.

[0009] The present invention is further configured as follows: the second anti-seepage layer is in a circular ring shape, and one end of the second anti-seepage layer is disconnected, a sealing tape is pasted at the disconnected portion, and one end of the sealing tape abuts against the bridge pier.

[0010] By adopting the above technical solution, the whole part and the overlap strip are sealed by the second anti-seepage layer, so that the bridge pier and the anti-seepage geomembrane layer are sealed in the horizontal direction.

[0011] The present invention is further configured such that: the first anti-seepage layer is bonded to the anti-seepage geomembrane layer by an adhesive.

[0012] By adopting the above technical solution, the first anti-seepage layer is closely attached to the anti-seepage geotextile layer, with good anti-seepage effect and high flatness, which is convenient for the later setting of the second anti-seepage layer.

[0013] The present invention is further configured as follows: the first anti-seepage layer and the second anti-seepage layer are anti-seepage geotextiles.

[0014] By adopting the above technical solution, the material is the same as that of river channel anti-seepage, and the overlapping effect and anti-seepage effect are better.

[0015] The present invention is further configured as follows: the adhesive is KS glue.

[0016] By adopting the above technical scheme, KS glue is suitable for bonding between anti-seepage geomembranes and anti-seepage geomembranes, and between anti-seepage geomembranes and concrete. It is insoluble in water and has good anti-seepage effect itself.

[0017] The present invention is further configured as follows: the upper end of the roughened layer is cast to form a water stop ring fixed on the pier, and the upper end of the first anti-seepage layer abuts against the bottom of the water stop ring.

[0018] By adopting the above technical solution, the anti-seepage effect in the vertical direction of the pier is increased.

[0019] A second object of the present invention is to provide a method for constructing an anti-seepage structure at a river channel pier, comprising the following steps:

[0020] S1. Excavate the river channel to the bottom elevation and roughen the bridge piers set in the river channel;

[0021] S2. Lay a lower sand layer at the bottom of the river channel, and lay an anti-seepage geomembrane on the lower sand layer. The anti-seepage geomembrane is laid in an overlapping manner at the bridge piers;

[0022] S3. Take a rectangular anti-seepage geomembrane, cut the lower part evenly at intervals to form overlapping strips, apply a layer of adhesive on the back of the whole part, adhere the whole part to the roughened part of the pier, fold the overlapping strips and attach them to the anti-seepage geomembrane layer and bond them with adhesive;

[0023] S4. Take a circular anti-seepage geomembrane, cut off one end of it, apply adhesive on the back, make it surround the bridge pier and bond it to the lower end of the whole part and the lap strip, and make the sealing tape bonded to the cut part of the second anti-seepage layer;

[0024] S5. Lay a sand layer and a gravel layer on the anti-seepage geomembrane layer in sequence.

[0025] The present invention is further configured as follows: before step S2, a water stop ring is cast around the circumference of the bridge pier at the upper end of the roughened layer to form a water stop ring.

[0026] In summary, the beneficial technical effects of the present invention are:

[0027] 1. The roughening layer is formed by roughening the pier, so that the first anti-seepage layer is bonded to the pier. The upper part of the first anti-seepage layer is surrounded by the pier and sealed by adhesive to seal the pier vertically. Then, the second anti-seepage layer is bonded to the first anti-seepage layer. The second anti-seepage layer is sealed in the horizontal direction of the pier to ensure the sealing of the connection between the river channel and the pier, which has the advantage of good anti-seepage effect.

[0028] 2. The whole part is wrapped around the roughened layer to seal the joint between the bridge pier and the anti-seepage geomembrane layer vertically, and then the lower part of the first anti-seepage layer is folded over and tightly bonded to the anti-seepage geomembrane layer through the lap strip, and then the second anti-seepage layer is bonded to the whole part, so as to seal the bridge pier in the horizontal direction. The lap strip is convenient for the first anti-seepage layer to be arranged around;

[0029] 3. By setting a water stop ring, the anti-seepage effect in the vertical direction of the pier is increased. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] Figure 1 It is a schematic diagram of the structure of the present invention;

[0031] Figure 2 is a cross-sectional view of the present invention;

[0032] Figure 3 It is a schematic structural diagram of the present invention protruding the first anti-seepage layer;

[0033] Figure 4 It is a schematic structural diagram of the present invention protruding the second anti-seepage layer.

[0034] In the figure, 1, lower sand layer; 2, anti-seepage geomembrane layer; 3, upper sand layer; 4, gravel layer; 5, roughened layer; 6, first anti-seepage layer; 61, integral part; 62, lap strip; 7, second anti-seepage layer; 8, sealing tape; 9, water stop ring; 10, bridge pier. DETAILED DESCRIPTION

[0035] The present invention is further described in detail below in conjunction with the accompanying drawings.

[0036] Embodiment 1:

[0037] Reference Figure 1 and Figure 2 , is an anti-seepage structure for 10 river piers disclosed in the present invention, comprising a lower sand layer 1, which is laid at the bottom of the river and has a thickness of 20 cm, and an anti-seepage geomembrane layer 2 is laid on the lower sand layer 1. When the anti-seepage geomembrane layer 2 is laid at the pier 10, it is laid in an overlapping manner, with an overlapping length of 20-40 cm, and two overlapping anti-seepage geomembranes are provided with holes for the pier 10 to pass through. An upper sand layer 3 is laid on the anti-seepage geomembrane layer 2, and the thickness of the upper sand layer 3 is 20 cm. A gravel layer 4 is backfilled on the upper sand layer 3.

[0038] A roughened layer 5 is provided between the upper sand layer 3 and the lower sand layer 1 on the outer peripheral wall of the bridge pier 10, and an adhesive is applied on the roughened layer 5. A first anti-seepage layer 6 is bonded to the outside of the roughened layer 5 by the adhesive. The upper part of the first anti-seepage layer 6 surrounds the roughened layer 5, and the lower part extends to the anti-seepage geomembrane layer 2, and is bonded to the anti-seepage geomembrane layer 2 by the adhesive, and overlaps with the anti-seepage geomembrane layer 2, with an overlap length of 20cm-40cm. A second anti-seepage layer 7 sleeved on the bridge pier 10 is bonded to the first anti-seepage layer 6, and an upper sand layer 3 and a gravel layer 4 are sequentially arranged on the second anti-seepage layer 7 from bottom to top.

[0039] The roughening layer 5 is formed by roughening the pier 10, so as to facilitate the bonding of the first anti-seepage layer 6 to the pier 10. The upper part of the first anti-seepage layer 6 surrounds the pier 10 and is sealed by adhesive to seal the pier 10 in the vertical direction. Then, the second anti-seepage layer 7 sleeved on the pier 10 is bonded to the first anti-seepage layer 6, and the pier 10 is sealed in the horizontal direction by the second anti-seepage layer 7, so as to ensure the sealing of the connection between the river channel and the pier 10, which has the advantage of good anti-seepage effect.

[0040] Reference Figure 3 The first anti-seepage layer 6 is rectangular and includes an integral part 61 arranged around the roughened layer 5 and a lap strip 62 fixed side by side at the lower end of the integral part 61 and overlapped on the anti-seepage geomembrane layer 2. When in use, the lower part of the first anti-seepage layer 6 is cut evenly at intervals to form a plurality of lap strips 62. The integral part 61 is wrapped around the roughened layer 5 to vertically seal the joint between the pier 10 and the anti-seepage geomembrane layer 2, and then the lap strip 62 is used to fold the lower part of the first anti-seepage layer 6 tightly onto the anti-seepage geomembrane layer 2, and then the second anti-seepage layer 7 is bonded to the integral part 61, so that the pier 10 is sealed in the horizontal direction, and the lap strip 62 is convenient for the first anti-seepage layer 6 to be arranged around.

[0041] Combination Figure 1 and Figure 4The second anti-seepage layer 7 is in a circular ring shape, and one end of the second anti-seepage layer 7 is disconnected, and a sealing tape 8 is bonded at the disconnection point. The sealing tape 8 is an anti-seepage geotextile, and one end of the sealing tape 8 is provided with a groove with the same curvature as the pier 10, and the groove abuts against the pier 10. When in use, the second anti-seepage layer 7 is used to seal the integral part 61 and the lap strip 62, thereby sealing the pier 10 and the anti-seepage geomembrane layer 2 in the horizontal direction.

[0042] The first anti-seepage layer 6 and the second anti-seepage layer 7 are anti-seepage geotextiles, and the adhesive is KS glue.

[0043] Reference Figure 1 Furthermore, a water stop ring 9 is cast on the upper end of the roughened layer 5 and fixed on the pier 10. When the first anti-seepage layer 6 is laid, the upper end of the first anti-seepage layer 6 is abutted against the bottom of the water stop ring 9 to reduce the vertical force on the first anti-seepage layer 6 and increase the anti-seepage effect in the vertical direction of the pier 10.

[0044] Embodiment 2:

[0045] A method for constructing an anti-seepage structure at 10 locations on a river pier comprises the following steps:

[0046] S1. The river channel is excavated to the designed elevation of the bottom surface and compacted by rolling. The bridge piers 10 arranged in the river channel are roughened, and the roughening range is the thickness of the lower sand layer 1 to the upper sand layer 3. After the roughening is completed, concrete is poured on the upper end of the roughened layer 5 using a template to form a water stop ring 9.

[0047] S2. Lay a 20cm lower sand layer 1 at the bottom of the river channel. Lay the lower sand layer 1 in layers and compact it. Lay an anti-seepage geomembrane on the lower sand layer 1. The anti-seepage geomembrane is tightly attached to the lower sand layer 1. The anti-seepage geomembrane should be spliced ​​by hot-melt welding with an overlap width of 20-40cm. The anti-seepage geomembrane is laid in an overlapping manner at the bridge pier 10. Before laying, holes are opened on the anti-seepage geomembrane on both sides of the bridge pier 10 for inserting the bridge pier 10.

[0048] S3. Take a rectangular anti-seepage geomembrane, cut the lower part at even intervals to form overlapping strips 62, apply a layer of adhesive on the back of the integral part 61, wrap the integral part 61 around the bridge pier 10, glue it to the roughened part, and make the upper end of the integral part 61 abut against the bottom of the water stop ring 9, fold the overlapping strips 62 and fit them on the anti-seepage geomembrane layer 2 and bond them with adhesive.

[0049] S4. Take a circular impermeable geomembrane, cut off one end of it, apply adhesive on the back, so that it surrounds the bridge pier 10 and is bonded to the lower end of the integral part 61 and the lap strip 62, and then use the sealing tape 8 to bond and seal the broken part of the second impermeable layer 7, wherein the second impermeable layer 7 covers the perforations on the impermeable geomembrane layer 2.

[0050] S5. Lay the sand layer 3 and the gravel layer 4 on the anti-seepage geomembrane layer 2 in sequence and compact them.

[0051] The embodiments of this specific implementation method are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Therefore, any equivalent changes made based on the structure, shape, and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A method for constructing an anti-seepage structure at a river pier. Features: The invention comprises a lower sand layer (1) laid on the bottom of a river channel, an anti-seepage geomembrane layer (2) laid on the lower sand layer (1) and sleeved on a bridge pier (10), an upper sand layer (3) arranged on the anti-seepage geomembrane layer (2), and a gravel layer (4) arranged on the upper sand layer (3); a roughened layer (5) is arranged between the upper sand layer (3) and the lower sand layer (1) on the outer peripheral wall of the bridge pier (10); an adhesive is applied on the roughened layer (5); a first anti-seepage layer (6) arranged around the roughened layer (5) is bonded to the outside of the roughened layer (5) by the adhesive; the lower end of the first anti-seepage layer (6) extends downward to the anti-seepage geomembrane layer (2); a second anti-seepage layer (7) sleeved on the bridge pier (10) is bonded to the first anti-seepage layer (6); and an upper sand layer (3) and a gravel layer (4) are arranged on the second anti-seepage layer (7) in sequence from bottom to top; The first anti-seepage layer (6) is rectangular, and comprises an integral part (61) arranged around the roughened layer (5) and a lap joint strip (62) fixedly arranged side by side at the lower end of the integral part (61) and lap jointed on the anti-seepage geomembrane layer (2); The second anti-seepage layer (7) is in the shape of a ring, and one end of the second anti-seepage layer (7) is disconnected, a sealing tape (8) is pasted to the disconnected portion, and one end of the sealing tape (8) is in contact with the bridge pier (10); The first anti-seepage layer (6) is bonded to the anti-seepage geomembrane layer (2) by an adhesive; The first anti-seepage layer (6) and the second anti-seepage layer (7) are anti-seepage geotextiles; The upper end of the roughened layer (5) is cast to form a water stop ring (9) fixed on the pier (10), and the upper end of the first anti-seepage layer (6) abuts against the bottom of the water stop ring (9); A method for constructing an anti-seepage structure at a river channel pier comprises the following steps: S1, excavating the river channel to the bottom elevation, and roughening the bridge piers (10) arranged in the river channel; S2, laying a lower sand layer (1) at the bottom of the river channel, laying an anti-seepage geomembrane on the lower sand layer (1), and laying the anti-seepage geomembrane in an overlapping manner at the bridge pier (10); S3, take a rectangular anti-seepage geomembrane, cut the lower part at even intervals to form overlapping strips (62), apply a layer of adhesive on the back of the whole part (61), adhere the whole part (61) to the roughened part of the pier (10), fold the overlapping strips (62) and attach them to the anti-seepage geomembrane layer (2) and use adhesive to bond them; S4, take a circular impermeable geomembrane, cut off one end of it, apply adhesive to the back, make it surround the bridge pier (10) and bond it to the lower end of the integral part (61) and the lap strip (62), and make the sealing tape (8) bonded to the cut part of the second impermeable layer (7); S5, laying a sand layer (3) and a gravel layer (4) in sequence on the anti-seepage geomembrane layer (2); Before step S2, a water stop ring (9) is cast around the circumference of the bridge pier (10) at the upper end of the roughened layer (5).

2. A method for constructing an anti-seepage structure at a river pier according to claim 1, Features: The adhesive is KS glue.