Modular arc steel formwork for cast-in-place half-pile construction and construction method

Through the assembly and pouring of modular arc-shaped steel forms in the half-pile area of ​​cast-in-place piles, the problems of construction quality and long construction period in the existing technology are solved, and efficient concrete use and construction speed are achieved.

CN111119172BActive Publication Date: 2024-10-18GUANGZHOU METRO DESIGN & RES INST CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202010015279.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-01-07
Publication Date
2024-10-18
Estimated Expiration
2040-01-07

AI Technical Summary

Technical Problem

The existing half-pile construction method of cast-in-place piles has difficulty in ensuring the quality, long construction period, waste of concrete and heavy transportation workload.

Method used

Modular arc-shaped steel forms are used and installed in the half-pile area by splicing standard units. Only the concrete in the half-pile area is poured to avoid cutting out excess concrete and shorten the construction period.

Benefits of technology

It improves the quality of half-pile construction, shortens the construction period, saves the amount of concrete and transportation workload, and has good economy and scope of application.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111119172B_ABST
    Figure CN111119172B_ABST
Patent Text Reader

Abstract

The present invention provides a modular arc steel mold for half-pile construction of a cast-in-place pile and a half-pile construction method. The modular arc steel mold is formed by splicing a plurality of standard units. The modular arc steel mold is installed in the empty pile area corresponding to the half-pile. The standard unit includes a shell. The interior of the shell is hollow. The shell is surrounded by a flat plate and an arc plate. The two ends of the flat plate are respectively connected to the two ends of the arc plate. The space where the shell is located is the empty pile area. The modular arc steel mold is used to form standard components for prefabrication, and is assembled during the construction process of the half-pile of the cast-in-place pile, so that it has modular conditions. The modular arc steel mold can adapt to the construction of half-piles of different heights and diameters in the project, and has a wide range of applications. At the same time, the modular arc steel mold can be recycled and reused. It can effectively improve the construction quality and construction speed of the half-pile, shorten the construction period, and improve the economy.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of rail transportation, and in particular to a modular arc-shaped steel mold for half-pile construction of a cast-in-place pile and a half-pile construction method. Background Art

[0002] At present, my country's underground projects are developing vigorously. Taking subway construction as an example, its lines are mostly located under the main roads of the city, passing through densely populated areas of the city. Stations are mostly located at level crossings with convenient transportation. The traffic volume is large, and the operation of urban traffic must be considered during the construction of underground projects. As the city develops more and more mature, the surrounding buildings are densely distributed. Due to the limited width of the road, the open-cut construction of underground projects will have a great impact on the passage of the city. In order to ensure traffic, underground projects in this situation usually adopt the cover excavation method or semi-cover excavation method, and provide traffic space above the cover plate.

[0003] The cover plate in the cover-excavation construction method is usually supported on the foundation pit retaining structure. The retaining structure usually adopts bored piles, and the cover plate is supported on the bored piles. The bored piles need to serve as the support points of the cover plate and bear the lateral soil pressure. Therefore, the cross-section of the bored pile at a certain height below the top of the pile is designed to be a semicircular arc or bow shape, which is called a half pile form.

[0004] The construction method of cast-in-place half pile in the prior art: Step 1: Figure 1 As shown, first install the steel cage in the hole area; Step 2: Figure 2 As shown, pour concrete into the hole area to form a circular cast-in-place pile; Step 3: Figure 3 As shown in the figure, the excess concrete on the circular cast-in-place pile is chiseled off to form a half cast-in-place pile. The quality of the half cast-in-place pile formed by this construction method is difficult to guarantee, the construction period is long, and the workload of chiseling off and transporting the excess concrete of the half cast-in-place pile is large, and a large amount of concrete is seriously wasted. Summary of the invention

[0005] The purpose of the present invention is to provide a modular arc steel form for half-pile construction of a cast-in-place pile and a half-pile construction method. The modular arc steel form is installed in the empty pile area corresponding to the half-pile, so that concrete is poured only in the half-pile area, and there is no need to chisel out excess concrete in the later stage, thereby ensuring the quality of half-pile construction and shortening the construction period.

[0006] In order to achieve the above object, the present invention provides the following technical solutions:

[0007] A modular arc-shaped steel formwork for half-pile construction of a cast-in-place pile, wherein the modular arc-shaped steel formwork is formed by splicing a plurality of standard units, and the modular arc-shaped steel formwork is installed in an empty pile area corresponding to the half-pile, wherein the standard unit comprises a shell, the interior of the shell is hollow, and the shell is formed by a flat plate and an arc-shaped plate, wherein two ends of the flat plate are respectively connected to two ends of the arc-shaped plate, and the space where the shell is located is the empty pile area.

[0008] Furthermore, in the above-mentioned modular arc-shaped steel mold, the flat plate and the arc-shaped plate are both placed vertically, and the upper end and the lower end of the shell are both open.

[0009] Furthermore, in the above-mentioned modular arc-shaped steel mold, the standard unit also includes stiffening ribs, and the stiffening ribs are arranged on the inner surface of the shell.

[0010] Furthermore, in the above-mentioned modular arc-shaped steel mold, the stiffening ribs surround the inner surface of the shell; preferably, the stiffening ribs are welded on the inner surface of the shell; preferably, the stiffening ribs are located in the middle of the shell in height.

[0011] Furthermore, in the above-mentioned modular arc-shaped steel mold, the standard unit also includes a plurality of positioning steel plates, and the plurality of positioning steel plates are evenly arranged on the inner surface of the upper end of the shell, and the positioning steel plates are used for positioning and connecting between two of the standard units.

[0012] Furthermore, in the above-mentioned modular arc-shaped steel mold, the positioning steel plate and the shell are welded together.

[0013] Furthermore, in the above-mentioned modular arc steel mold, the standard unit also includes a plurality of hooks, which are arranged on the inner surface of the shell; the plurality of hooks are evenly arranged on the inner surface of the shell, and the hooks are arranged on the upper section of the shell, and the hooks are used as lifting points when assembling and disassembling the standard unit.

[0014] Furthermore, the above-mentioned modular arc-shaped steel mold also includes a bottom steel plate. A plurality of the standard units are arranged up and down, and the bottom steel plate is arranged at the lower end of the lowest standard unit. The bottom steel plate fully covers the lower end of the lowest standard unit.

[0015] Furthermore, in the above modular arc-shaped steel formwork, a steel cage is placed in the area of ​​the half pile.

[0016] On the other hand, a method for constructing a half pile using the modular arc steel formwork is provided, wherein the cast-in-place pile comprises a half pile and a whole pile, wherein the whole pile is located below the half pile, and the empty pile area corresponds to the height of the half pile, and the empty pile area is located above the whole pile.

[0017] The semi-pile construction method comprises the following steps:

[0018] Install the steel cage, the setting area of ​​the steel cage is the area where the half pile is located and the area where the whole pile is located,

[0019] pouring concrete into the whole pile area to the bottom of the empty pile area,

[0020] Hoisting the standard unit provided with the bottom steel plate to the bottom of the empty pile area;

[0021] A plurality of the standard units are sequentially placed on top of the standard units that have been placed, until the top of the topmost standard unit is higher than the top design elevation of the half pile, thus completing the installation of the modular arc steel formwork.

[0022] pouring concrete into the half pile area,

[0023] After the initial setting of the concrete, all the standard units are dismantled from top to bottom to complete the construction.

[0024] It can be seen from the analysis that the present invention discloses a modular arc steel mold for half-pile construction of cast-in-place piles and a half-pile construction method, which uses the modular arc steel mold to form standard components for prefabrication and assembles them during the half-pile construction process, so that it has modular conditions. The modular arc steel mold can adapt to the construction of half-piles of different heights and diameters in the project, and has a wide range of applications. At the same time, the modular arc steel mold can be recycled and reused. It can effectively improve the quality and construction speed of half-pile construction, shorten the construction period, and improve economic efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] The drawings constituting a part of the present application are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. Among them:

[0026] Figure 1 It is a schematic diagram of step 1 of the half pile construction method in the prior art;

[0027] Figure 2 It is a schematic diagram of step 2 of the half pile construction method in the prior art;

[0028] Figure 3 It is a schematic diagram of step 3 of the half pile construction method in the prior art;

[0029] Figure 4 FIG. 4 is a schematic diagram of the structure of a standard cell according to an embodiment of the present invention.

[0030] Figure 5 The figure is a cross-sectional schematic diagram of a standard unit and a bottom cover steel plate according to an embodiment of the present invention.

[0031] Figure 6 FIG. 4 is a cross-sectional schematic diagram of a standard cell according to an embodiment of the present invention.

[0032] Figure 7 Book Figure 5 Schematic top view of .

[0033] Figure 8 It is a structural schematic diagram of an embodiment of the present invention.

[0034] Fig. 9 This is a schematic structural diagram of a modular arc steel formwork installed in an empty pile area according to an embodiment of the present invention.

[0035] Fig.10 Schematic diagram of step 1 of a half pile construction method according to an embodiment of the present invention.

[0036] Fig.11 Schematic diagram of step 2 of the half pile construction method according to an embodiment of the present invention.

[0037] Fig.12 Schematic diagram of step 3 of the half pile construction method according to an embodiment of the present invention.

[0038] Fig.13 Schematic diagram of step 4 of the half pile construction method according to an embodiment of the present invention.

[0039] Fig.14 Schematic diagram of step 5 of the half pile construction method according to an embodiment of the present invention.

[0040] Fig.15 Schematic diagram of step 6 of the half pile construction method according to an embodiment of the present invention.

[0041] Explanation of the reference numerals: 1 empty pile area; 2 modular arc steel formwork; 3 standard unit; 31 flat plate; 32 arc plate; 33 stiffening rib; 34 positioning steel plate; 35 hook; 4 steel cage; 5 concrete; 6 ground; 7 bottom steel plate; 8 half pile; 9 whole pile. DETAILED DESCRIPTION

[0042] The present invention will be described in detail below with reference to the accompanying drawings and in conjunction with embodiments. Each example is provided by way of explanation of the present invention and does not limit the present invention. In fact, it will be clear to those skilled in the art that modifications and variations may be made in the present invention without departing from the scope or spirit of the present invention. For example, a feature shown or described as a part of one embodiment may be used in another embodiment to produce yet another embodiment. Therefore, it is desired that the present invention encompasses such modifications and variations within the scope of the appended claims and their equivalents.

[0043] In the description of the present invention, the terms "longitudinal", "lateral", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings. They are only for the convenience of describing the present invention and do not require that the present invention must be constructed and operated in a specific orientation. Therefore, they cannot be understood as limitations on the present invention. The terms "connected", "connected" and "set" used in the present invention should be understood in a broad sense. For example, they can be fixedly connected or detachably connected; they can be directly connected or indirectly connected through intermediate components. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to specific circumstances.

[0044] like Figures 4 to 15 As shown, according to an embodiment of the present invention, a modular arc steel mold for half-pile construction of a cast-in-place pile is provided, the half pile 8 is located below the ground 6, the modular arc steel mold 2 is spliced ​​by a plurality of standard units 3, the modular arc steel mold 2 is installed in the empty pile area 1 corresponding to the half pile 8, the standard unit 3 includes a shell, the interior of the shell is hollow, the shell is surrounded by a flat plate 31 and an arc plate 32, the flat plate 31 and the arc plate 32 are connected by welding or are an integrally formed structure, the two ends of the flat plate 31 are respectively connected to the two ends of the arc plate 32, and the space where the shell is located is the empty pile area 1.

[0045] like Fig.15 As shown, according to the actual situation of the project, when the cast-in-place pile includes a half pile 8 and a whole pile 9, the whole pile 9 is located below the half pile 8, the cross section of the half pile 8 corresponds to a part of the cross section of the whole pile 9, and the rest of the cross section area of ​​the whole pile 9 corresponds to the empty pile area 1, and the cross section of the half pile 8 and the cross section of the empty pile area 1 are combined to be the same as the cross section of the whole pile 9. The setting area of ​​the steel cage 4 is the area of ​​the half pile 8 and the area of ​​the whole pile 9.

[0046] A steel cage 4 is placed in the area of ​​the whole pile 9 and the half pile 8 of the cast-in-place pile, and concrete 5 is poured to form the whole pile 9 and the half pile 8 of the cast-in-place pile. The modular arc steel mold 2 is installed in the empty pile area 1 corresponding to the half pile 8. The outline of the cast-in-place pile is formed according to the design size, and when the concrete 5 reaches a certain strength after initial setting, all standard units 3 are disassembled from top to bottom in sequence to complete the construction of the half pile 8. The modular arc steel mold 2 of the present invention can avoid the removal of concrete in the area corresponding to the half pile 8, that is, avoids the removal of excess concrete in the empty pile area 1, and saves the amount of concrete, speeds up the project progress and saves costs.

[0047] Although it is called a half pile 8 in the present application, it does not limit the empty pile area 1 to be exactly 50% of the cross-sectional area of ​​the whole pile 9, but means that a part of the area (half pile 8) is provided with a steel cage 4, and the other part of the area (empty pile area 1) is not provided with a steel cage 4. As for the ratio of the area provided with a steel cage 4 to the area not provided with a steel cage 4, it can be determined according to actual needs. Moreover, although Fig.15 The empty pile area 1 shown is located at the upper right corner of the entire cast-in-place pile, but the position of the empty pile area 1 is not limited thereto and can be set at any position according to actual needs. For example, the outer boundary line of the cross section of the empty pile area 1 can be a minor arc, a semicircle or a major arc, and the shape of the arc plate 32 of the modular arc steel mold 2 corresponds to the outer boundary line of the cross section of the empty pile area 1.

[0048] Preferably, the height of the standard unit 3 is 0.5m to 1m. Such a setting enables the standard unit 3 to be prefabricated as a standard component, facilitates the installation, disassembly and transportation of the standard unit 3, and enables the modular arc steel mold 2 to be suitable for the construction of half piles 8 of different heights, with modular conditions. The height of the standard unit 3 can be adjusted accordingly in combination with the size of the half pile 8. The outer diameter of the arc plate 32 is the same as the outer diameter of the half pile 8 on the same cross section.

[0049] Preferably, the thickness of the flat plate 31 is 10 mm to 20 mm, and the thickness of the arc plate 32 is 8 mm to 20 mm. Such an arrangement enables the standard unit 3 to have good spatial rigidity and bearing capacity. When the half pile 8 is poured with concrete, the standard unit 3 will basically not be deformed, thereby enabling the construction of the half pile 8 to proceed smoothly.

[0050] Furthermore, if Figure 4 and Figure 6 As shown, the flat plate 31 and the arc-shaped plate 32 are both placed vertically, and the upper and lower ends of the shell are both open. Such an arrangement facilitates the docking of two adjacent standard units 3.

[0051] Furthermore, if Figures 5 to 7 As shown, the standard unit 3 further includes a stiffening rib 33, which is arranged on the inner surface of the shell. The arrangement of the stiffening rib 33 can enhance the spatial anti-deformation capability of the flat plate 31.

[0052] Furthermore, the stiffening ribs 33 surround the inner surface of the shell; preferably, the stiffening ribs 33 are welded on the inner surface of the shell; preferably, the stiffening ribs 33 are located in the middle of the shell in height. Such an arrangement can improve the overall anti-deformation ability of the modular arc steel mold 2, prevent the modular arc steel mold 2 from deforming during the construction process, and make the modular arc steel mold 2 recyclable. When the height of the standard unit 3 is greater than 1m, stiffening ribs 33 can be added inside the standard unit 3 to ensure the spatial anti-deformation ability and bearing capacity of the standard unit 3. Preferably, the material of the stiffening ribs 33 is steel, and the thickness of the stiffening ribs 33 is 8mm-20mm. Such an arrangement enables the standard unit 3 to meet the spatial anti-deformation requirements and bearing capacity requirements when pouring concrete.

[0053] Furthermore, if Figures 4 to 7 The standard unit 3 shown in the figure also includes a plurality of positioning steel plates 34, which are evenly arranged on the inner surface of the upper end of the shell, the bottom end of the positioning steel plates 34 is connected to the inner surface of the upper end of the shell, and the top end of the positioning steel plates 34 extends above the top end of the standard unit 3. The positioning steel plates 34 are used for positioning and connecting two standard units 3. Preferably, there are 5 to 9 positioning steel plates 34, and such arrangement can prevent relative displacement at the connection between the two standard units 3, thereby ensuring effective positioning connection. The number of positioning steel plates 34 can be adjusted according to the size of the arc steel mold. In one embodiment of the present invention, seven positioning steel plates 34 are arranged on the inner surface of the upper end of the shell, of which three positioning steel plates 34 are evenly arranged on the flat plate 31 and the other four positioning steel plates 34 are evenly arranged on the arc plate 32. When the modular arc steel mold 2 is assembled, the positioning steel plates 34 on the lower standard unit 3 are inserted into the upper standard unit 3 to realize the positioning connection of the two standard units 3 and enhance the out-of-plane stiffness at the connection between the two standard units 3.

[0054] The width, height and thickness of the positioning steel plate 34 can be adjusted accordingly according to the size of the standard unit 3. Preferably, the width of the positioning steel plate 34 is 100mm-400mm, the thickness of the positioning steel plate 34 is 10mm-20mm, the height of the positioning steel plate 34 is 200mm-400mm, half of the height of the positioning steel plate 34 is connected to the inner surface of the upper end of the shell by welding, and the other half of the height of the positioning steel plate 34 extends into the standard unit 3 above it. Such a setting can ensure that the bottom end of the positioning steel plate 34 is firmly connected to the top end of the shell during the concrete pouring process, thereby ensuring that there is basically no relative displacement at the connection between the two standard units 3, while providing a positioning connection between the standard units 3 and ensuring the out-of-plane stiffness of the connection at the standard unit 3. In one embodiment of the present invention, the height of the positioning steel plate 34 is 200mm, the upper section of the positioning steel plate 34 extends upward from the top end of the shell by 100mm, and the lower section of the positioning steel plate 34 is connected to the upper end of the shell by a height of 100mm.

[0055] Furthermore, the positioning steel plate 34 is welded to the shell, which can make the connection between the positioning steel plate 34 and the shell more firm.

[0056] Furthermore, if Figure 7 As shown, the standard unit 3 also includes a plurality of hooks 35, which are arranged on the inner surface of the shell; the plurality of hooks 35 are evenly arranged on the inner surface of the shell. Preferably, three hooks 35 are evenly arranged on the inner surface of the shell, one of which is located on the flat plate 31, and the other two hooks 35 are located on the arc plate 32. The hook 35 is arranged on the upper section of the shell and above the stiffening rib 33. The hook 35 is used as a lifting point when assembling and disassembling the standard unit 3. When the modular arc steel mold 2 is assembled, the standard unit 3 can be sequentially lifted to the empty pile area 1 corresponding to the half pile 8 through the hook 35.

[0057] Furthermore, the standard unit 3 also includes a bottom steel plate 7, such as Figure 8 As shown, a plurality of standard units 3 are arranged up and down, and a bottom steel plate 7 is arranged at the lower end of the lowest standard unit 3, and the bottom steel plate 7 fully covers the lower end of the lowest standard unit 3. Such an arrangement can enhance the anti-deformation ability of the lowest standard unit 3, and prevent the concrete 5 from entering the interior of the modular arc steel mold 2 from the lowest standard unit 3 when pouring the half-pile concrete 5. Preferably, the thickness of the bottom steel plate 7 is 8mm-20mm, and the thickness of the bottom steel plate 7 can be adjusted according to the requirements of strength and rigidity, so as to save costs while ensuring strength and rigidity.

[0058] Furthermore, the bottom cover steel plate 7 is welded to the standard unit 3. This arrangement ensures that the bottom cover steel plate 7 is firmly connected to the standard unit 3.

[0059] On the other hand, a method for constructing a half pile using a modular arc steel formwork 2 in an underground project is disclosed, wherein the cast-in-place pile includes a half pile and a whole pile, the whole pile is located below the half pile, the empty pile area corresponds to the height of the half pile, and the empty pile area is located above the whole pile, and the method includes the following steps:

[0060] Step 1: If Fig.10 As shown, a steel cage 4 is installed, and the setting area of ​​the steel cage 4 is the area where the half pile 8 is located and the area where the whole pile 9 is located.

[0061] Step 2: If Fig.11As shown, concrete 5 is poured into the whole pile 9 area to the bottom of the empty pile area 1. Because if the concrete of the whole pile 9 at the bottom is poured through the space of the half pile 8 after the modular arc steel form 2 is installed, it is difficult to ensure the quality of the concrete pouring in the whole pile 9, so the concrete of the whole pile 9 at the bottom is poured before the modular arc steel form 2 is installed. The modular arc steel form 2 is placed after the concrete of the whole pile 9 is poured first to ensure the quality of the concrete pouring of the whole pile 9.

[0062] Step 3: If Fig.12 As shown, the standard unit 3 provided with the bottom steel plate 7 is hoisted to the bottom of the empty pile area 1;

[0063] Step 4: Fig.13 As shown, several standard units 3 are placed in sequence on the standard unit 3 installed in step 3 until the top of the uppermost standard unit 3 is higher than the top design elevation of the half pile 8, and the installation of the modular arc steel formwork 2 is completed. During the placement of the standard units 3, two adjacent standard units 3 are positioned and connected by positioning steel plates 34.

[0064] Step 5: Fig.14 As shown, concrete 5 is poured into the region of the half pile 8 .

[0065] Step 6: Fig.15 As shown, after the concrete 5 initially sets and reaches a certain strength, when the surface and edges of the concrete 5 are guaranteed not to be damaged, all standard units 3 are disassembled from top to bottom in sequence to complete the construction.

[0066] From the above description, it can be seen that the above embodiments of the present invention achieve the following technical effects:

[0067] 1. The modular arc steel mold 2 is used to form standard components for prefabrication and assembly, which has modular conditions.

[0068] 2. In actual projects, the modular arc steel mold 2 can be prefabricated with modular arc steel molds 2 of different diameters according to the whole piles 9 and half piles 8 of cast-in-place piles of different diameters, so that the modular arc steel mold 2 can adapt to the construction of half piles 8 of different heights and different diameters, and has a wide range of applications. At the same time, the modular arc steel mold 2 can be recycled.

[0069] 3. It can effectively improve the construction quality and speed of the half pile 8, shorten the construction period and improve the economy.

[0070] Compared with the prior art, the modular arc steel formwork 2 of the present invention can avoid the chiseling of the concrete 5 in the empty pile area 1, reduce the amount of chiseling of excess concrete 5 and the amount of concrete 5 used, and has good comprehensive economic benefits and promotion prospects.

[0071] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A half-pile construction method for a cast-in-place pile, characterized in that: The cast-in-place pile includes a half pile and a whole pile, wherein the whole pile is located below the half pile, and the empty pile area corresponds to the height of the half pile, and the empty pile area is located above the whole pile. The semi-pile construction method comprises the following steps: Install a steel cage, wherein the steel cage is installed in the area where the half pile is located and the area where the whole pile is located, Pour concrete into the area where the whole pile is located to the bottom of the empty pile area, Hoisting the standard unit provided with the bottom steel plate to the bottom of the empty pile area; A plurality of the standard units are sequentially placed on top of the standard units that have been placed, until the top of the topmost standard unit is higher than the top design elevation of the half pile, thus completing the installation of the modular arc steel formwork. pouring concrete into the half pile area, After the concrete has initially set, all the standard units are dismantled from top to bottom to complete the construction; The modular arc steel formwork is formed by splicing a plurality of standard units, and the modular arc steel formwork is installed in the empty pile area corresponding to the half pile. The standard unit comprises a shell, the interior of the shell is hollow, the shell is surrounded by a flat plate and an arc-shaped plate, two ends of the flat plate are respectively connected to two ends of the arc-shaped plate, and the space where the shell is located is the empty pile area.

2. The half-pile construction method of cast-in-place pile according to claim 1, characterized in that: The flat plate and the curved plate are both placed vertically, The upper end and the lower end of the shell are both open.

3. The half-pile construction method of cast-in-place pile according to claim 1, characterized in that: The standard unit further includes a stiffening rib, and the stiffening rib is arranged on the inner surface of the shell.

4. The half-pile construction method of cast-in-place pile according to claim 3, characterized in that: The stiffening rib surrounds the inner surface of the shell.

5. The half-pile construction method of cast-in-place pile according to claim 4, characterized in that: The stiffening ribs are welded on the inner surface of the shell; The stiffening rib is located in the middle of the shell in terms of height.

6. The half-pile construction method of cast-in-place pile according to claim 2, characterized in that: The standard unit also includes a number of positioning steel plates. A plurality of positioning steel plates are evenly arranged on the inner surface of the upper end of the shell, and the positioning steel plates are used for positioning and connecting two standard units.

7. The half-pile construction method of cast-in-place pile according to claim 6, characterized in that: The positioning steel plate is connected to the shell by welding.

8. The half-pile construction method of cast-in-place pile according to claim 1, characterized in that: The standard unit also includes a plurality of hooks, which are arranged on the inner surface of the shell; A plurality of the hooks are evenly arranged on the inner surface of the shell. The hook is arranged on the upper section of the shell, The hook is used as a lifting point when assembling and disassembling the standard unit.

9. The half-pile construction method of cast-in-place pile according to claim 1, characterized in that: It also includes a bottom steel plate. A plurality of said standard cells are arranged vertically, The bottom cover steel plate is arranged at the lower end of the lowest standard unit. The bottom steel plate completely covers the lower end of the standard unit located at the bottom.

10. The half-pile construction method of a cast-in-place pile according to any one of claims 1 to 9, characterized in that: A steel cage is placed in the area of ​​the half pile.

Citation Information

Patent Citations

  • Half circular pile construction equipment

    CN207749515U

  • Modular arc-shaped steel die for half-pile construction of cast-in-place pile

    CN211922610U