A unloading platform for construction

By designing a combined structure of hydraulically driven support rods and n-shaped embedded parts locking devices, the problem of insufficient load-bearing capacity of the existing unloading platform is solved, and a more efficient and safe building material transfer and installation process is achieved.

CN111219067BActive Publication Date: 2024-10-18SHAANXI CONSTR ENG SHENMU CONSTR CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202010171617.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-03-12
Publication Date
2024-10-18
Estimated Expiration
2040-03-12

AI Technical Summary

Technical Problem

The existing unloading platform for building construction has insufficient load-bearing capacity, resulting in frequent overturning during formwork removal operations for high-rise buildings, and the installation and disassembly process is dangerous and inefficient.

Method used

A structure including two parallel support rods, connecting rods and unloading platform is designed. The hydraulic rod drives the support rod and cooperates with the n-shaped embedded parts locking device to achieve stable fixing and unloading, increase the load-bearing capacity and simplify the installation process.

Benefits of technology

It improves the load-bearing capacity and installation safety of the unloading platform, ensures efficient transfer of building materials, and reduces construction difficulty and personnel risks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111219067B_ABST
    Figure CN111219067B_ABST
Patent Text Reader

Abstract

The present invention discloses a material unloading platform for construction, which comprises two support rods (1) arranged in parallel, the ends of the two support rods (1) are connected and fixed into a whole by two connecting rods (2), a material unloading platform (3) is installed above the two connecting rods (2), each support rod (1) is provided with a plurality of first ear seats (4) arranged equidistantly, the first ear seat (4) is rotatably connected and matched with the lower end of the first support rod (5) through a hinge shaft, a second ear seat (6) is installed on the top of the first support rod (5), the second ear seat (6) is rotatably connected and matched with the lower end of the second support rod (8) through a rotating shaft (7), and the upper end of the second support rod (8) is provided with a material unloading platform (3). The present invention has a simple structure, a stable and reliable fixing effect, a large load, is particularly suitable for the transportation of a large amount of building materials, has a high installation efficiency, and a high safety factor in the entire installation process.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field related to building construction equipment, and in particular to a material unloading platform for building construction. Background Art

[0002] In the later stage of construction, the main task is to remove the formwork. Since most of the existing buildings are high-rise or super-high-rise, the disassembled formwork and related supporting accessories need to be transported out one by one. The most common way to transport these related building materials is to first open a small hole in the protective foot net, and then install the relevant unloading platform. At present, the fixed installation structure of the unloading platform is mostly to insert two connecting rods into the n-shaped embedded parts embedded in the floor slab for fixing. The unloading platform of this structure can actually only cope with the axial tension of the connecting rod, and since the unloading platform is extended out of the protective net, each connecting rod is actually supported by two n-shaped embedded parts. First of all, the n-shaped embedded parts must bear the unloading The upward pulling force of the platform is the main reason for the poor bearing capacity of all existing unloading platforms. It is not uncommon for unloading platforms to overturn and cause casualties during construction and application. In response to this, some of our project departments require that a diagonal brace steel pipe must be installed at the bottom of the extended part of the unloading platform to the next floor. We have also tested this method under ballast, and it can at least increase the load of the existing platform by 50%. However, the operation of installing the diagonal brace steel pipe is very dangerous. The main reason is that the unloading platform is a protruding part of the entire main building, and the workers have to hang down in the air to set up the diagonal brace at the bottom of this protruding part. The construction is difficult and the work efficiency is low. Summary of the invention

[0003] The purpose of the present invention is to provide a material unloading platform for construction, which can effectively solve the problems existing in the background technology.

[0004] In order to solve the problems existing in the background technology, it comprises two support rods 1 arranged in parallel, the ends of the two support rods 1 are connected and fixed into a whole by two connecting rods 2, and a discharge platform 3 is installed above the two connecting rods 2; each support rod 1 is provided with a plurality of first ear seats 4 arranged at equal distances, and the first ear seat 4 is rotatably connected and matched with the lower end of the first support rod 5 through a hinge shaft, and a second ear seat 6 is installed on the top of the first support rod 5, and the second ear seat 6 is rotatably connected and matched with the lower end of the second support rod 8 through a rotating shaft 7, and the upper end of the second support rod 8 is provided with a screw rod 9 that can be screwed and matched therewith, and the upper end of the screw rod 9 is welded and fixed with a top plate 10;

[0005] A second ear seat 6 extends from one end of the rotating shaft 7 and is rotatably connected to a driving connecting rod 11. The end of the driving connecting rod 11 is fixedly connected to the piston shaft end of a hydraulic rod 12 as a whole. The end of the hydraulic rod 12 is fixedly connected to a connecting seat 13 as a whole. The connecting seat 13 is rotatably connected to the baffle plate of the unloading platform 3 through a rotating shaft.

[0006] The support rod 1 is provided with a locking device for docking with the N-shaped embedded part.

[0007] The locking device comprises a driving rod 14 parallel to the bracket rod 1, a slide groove 15 is provided on the driving rod 14 through which the first support rod 5 can pass through, a plurality of positioning shafts 16 corresponding to the first support rod 5 are fixedly installed in the slide groove 15, and a positioning slide groove 17 is provided on the first support rod 5 to slide with the positioning shaft 16, two first connecting plates 18 are welded and fixed to the outer edge of the driving rod 14, and a locking seat 19 is welded and fixed to the lower end of the first connecting plate 18, and a clamping seat 20 corresponding to the locking seat 19 is welded and fixed to the outer side surface of the bracket rod 1, and the clamping seat 20 is an L-shaped structure, and a hole is provided on the lower bottom surface of the locking seat 19 for the clamping seat 20 to pass through;

[0008] A second connecting plate 21 is welded and fixed to the inner edge of the driving rod 14, a guide rail 22 is welded and fixed to one side of the bottom of the second connecting plate 21, and a first guide slot 23 that can be slidably matched with the guide rail 22 is opened on the inner side of the bracket rod 1;

[0009] Under the drive of the hydraulic rod 12, when the first support rod 5 is perpendicular to the bracket rod 1, the locking seat 19 and the clamping seat 20 are buckled into one;

[0010] A driven connecting rod 25 which can be rotatably connected to the unloading platform 3 is installed on the inner side surface of the baffle plate. Several driven shafts 26 corresponding to the second support rod 8 are welded on one side of the driven connecting rod 25. The inner side surface of the second support rod 8 is provided with a second guide groove 27 which can slide and cooperate with the driven shaft 26 with clearance.

[0011] Symmetrically arranged bosses 24 are respectively welded and fixed on both sides of the lower bottom surface of the top plate 10 .

[0012] Due to the adoption of the above technical scheme, the present invention has the following beneficial effects: simple structure, stable and reliable fixing effect, large load, especially suitable for the transportation of large amounts of building materials, fast installation efficiency, and high safety factor of the entire installation process. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.

[0014] Figure 1 It is a schematic diagram of the decomposition structure of the present invention. DETAILED DESCRIPTION

[0015] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention.

[0016] See also Figure 1 , this specific embodiment is implemented by adopting the following technical scheme, which comprises two support rods 1 arranged in parallel, the ends of the two support rods 1 are connected and fixed into a whole by two connecting rods 2, a discharge platform 3 is installed above the two connecting rods 2, and each support rod 1 is provided with a plurality of first ear seats 4 arranged equidistantly, the first ear seat 4 is rotatably connected and matched with the lower end of the first support rod 5 through a hinge shaft, a second ear seat 6 is installed on the top of the first support rod 5, and the second ear seat 6 is rotatably connected and matched with the lower end of the second support rod 8 through a rotating shaft 7, and a screw rod 9 which can be screwed and matched therewith is provided at the upper end of the second support rod 8, and a top plate 10 is welded and fixed to the upper end of the screw rod 9;

[0017] A second ear seat 6 extends from one end of the rotating shaft 7 and is rotatably connected to a driving connecting rod 11. The end of the driving connecting rod 11 is fixedly connected to the piston shaft end of a hydraulic rod 12 as a whole. The end of the hydraulic rod 12 is fixedly connected to a connecting seat 13 as a whole. The connecting seat 13 is rotatably connected to the baffle plate of the unloading platform 3 through a rotating shaft.

[0018] The support rod 1 is provided with a locking device for docking with the N-shaped embedded part.

[0019] The locking device comprises a driving rod 14 parallel to the bracket rod 1, a slide groove 15 is provided on the driving rod 14 through which the first support rod 5 can pass through, a plurality of positioning shafts 16 corresponding to the first support rod 5 are fixedly installed in the slide groove 15, and a positioning slide groove 17 is provided on the first support rod 5 to slide with the positioning shaft 16, two first connecting plates 18 are welded and fixed to the outer edge of the driving rod 14, and a locking seat 19 is welded and fixed to the lower end of the first connecting plate 18, and a clamping seat 20 corresponding to the locking seat 19 is welded and fixed to the outer side surface of the bracket rod 1, and the clamping seat 20 is an L-shaped structure, and a hole is provided on the lower bottom surface of the locking seat 19 for the clamping seat 20 to pass through;

[0020] A second connecting plate 21 is welded and fixed to the inner edge of the driving rod 14, a guide rail 22 is welded and fixed to one side of the bottom of the second connecting plate 21, and a first guide slot 23 that can be slidably matched with the guide rail 22 is opened on the inner side of the bracket rod 1;

[0021] Under the drive of the hydraulic rod 12, when the first support rod 5 is perpendicular to the bracket rod 1, the locking seat 19 and the clamping seat 20 are buckled into one;

[0022] A driven connecting rod 25 that can be rotatably connected to the unloading platform 3 is installed on the inner side surface of the baffle plate. Several driven shafts 26 corresponding to the second support rod 8 are welded on one side of the driven connecting rod 25. A second guide groove 27 that can slide with the driven shaft 26 is provided on the inner side surface of the second support rod 8. In this embodiment, the lower end lengths of the second guide grooves 27 of each second support rod 8 in the same column are different. The farther away from the unloading platform 3, the longer the second guide grooves 27 on the second support rod 8. Of course, the upper end heights of the second guide grooves 27 are all consistent.

[0023] Symmetrically arranged bosses 24 are respectively welded and fixed on both sides of the lower bottom surface of the top plate 10 .

[0024] The working principle and implementation process of the technical solution in this specific implementation method are further explained below in conjunction with the figure:

[0025] First, according to the spacing between the various holders 20, embedded parts are placed when pouring the floor slab, and the embedded parts still use the existing n-shaped embedded parts;

[0026] During operation, firstly, the floor height of the floor should be roughly measured, and the screw rod 9 should be adjusted to the corresponding height (slightly lower than the floor height), and then the four holders 20 should be respectively inserted into the corresponding n-shaped embedded parts, and then the hydraulic rod 12 is started to drive the driving connecting rod 11 to move in a linkage manner. During the movement, the driving connecting rod 11 drives the first supporting rod 5 and the second supporting rod 8 in the same column to move in a linkage manner until the first supporting rod 5 and the second supporting rod 8 are kept vertically with the bracket rod 1. During this process, the driving rod 14 locks the n-shaped embedded part between the holder 20 and the locking seat 19 through the first connecting plate 18, so as to achieve the purpose of fixing the n-shaped embedded part in the axial direction;

[0027] Finally, the boss 24 is hit with a hammer to make the top plate 10 tightly against the ceiling, thereby achieving the purpose of vertical fixation.

[0028] When storing, it should be noted that the top plate 10 should be loosened at least 10 cm first, and then the hydraulic rod 12 should be retracted to prevent the top plate 10 from damaging the protective layer of the ceiling and affecting the later main body acceptance.

[0029] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.

Claims

1. A material unloading platform for construction, comprising two support rods (1) arranged in parallel, the ends of the two support rods (1) being connected and fixed into a whole by two connecting rods (2), and a material unloading platform (3) being installed above the two connecting rods (2); characterized in that Each support rod (1) is provided with a plurality of first ear seats (4) arranged at equal intervals, the first ear seat (4) is rotatably connected to the lower end of the first support rod (5) via a hinge shaft, a second ear seat (6) is installed on the top of the first support rod (5), the second ear seat (6) is rotatably connected to the lower end of the second support rod (8) via a rotating shaft (7), the upper end of the second support rod (8) is provided with a screw rod (9) screwed thereto, and a top plate (10) is welded and fixed to the upper end of the screw rod (9); A second ear seat (6) extends from one end of the rotating shaft (7) and is rotatably connected to a driving connecting rod (11). The end of the driving connecting rod (11) is fixedly connected to the piston shaft end of a hydraulic rod (12) as a whole. The end of the hydraulic rod (12) is fixedly connected to a connecting seat (13) as a whole. The connecting seat (13) is rotatably connected to the baffle plate of the unloading platform (3) through the rotating shaft. The support rod (1) is provided with a locking device for docking with the N-shaped embedded part; The locking device comprises a driving rod (14) parallel to the support rod (1), the driving rod (14) is provided with a sliding groove (15) through which the first support rod (5) passes, a plurality of positioning shafts (16) corresponding to the first support rod (5) are fixedly installed in the sliding groove (15), the first support rod (5) is provided with a positioning sliding groove (17) which is slidably matched with the positioning shaft (16), two first connecting plates (18) are welded and fixed at the outer edge of the driving rod (14), a locking seat (19) is welded and fixed at the lower end of the first connecting plate (18), a clamping seat (20) corresponding to the locking seat (19) is welded and fixed at the outer side surface of the support rod (1), the clamping seat (20) is an L-shaped structure, and a hole is provided on the lower bottom surface of the locking seat (19) for the clamping seat (20) to pass through; A second connecting plate (21) is welded and fixed at the inner edge of the driving rod (14), a guide rail (22) is welded and fixed at one side of the bottom of the second connecting plate (21), and a first guide slot (23) is provided on the inner side surface of the bracket rod (1) to be slidably matched with the guide rail (22); Under the drive of the hydraulic rod (12), when the first support rod (5) is perpendicular to the support rod (1), the locking seat (19) and the clamping seat (20) are buckled into one; A driven connecting rod (25) is installed on the inner side surface of the baffle plate of the unloading platform (3) and is rotatably connected thereto. A plurality of driven shafts (26) corresponding to the second support rod (8) are welded on one side of the driven connecting rod (25). A second guide groove (27) is provided on the inner side surface of the second support rod (8) and is slidably matched with the driven shaft (26) in a clearance. Symmetrically arranged bosses (24) are respectively welded and fixed on both sides of the lower bottom surface of the top plate (10).

Citation Information

Patent Citations

  • Discharging platform for building construction

    CN212105180U