A construction method based on the lowering and dismantling of a mobile formwork frame
Through the combination of the mobile formwork vertical and horizontal movement system and the rotating base, the problem of insufficient clearance for formwork disassembly in the shoal area is solved, the main components of the formwork are quickly and safely dismantled, the construction cost and cycle are reduced, and a convenient construction method is provided. .
Patent Information
- Application Number
- CN202010215150.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-03-24
- Publication Date
- 2024-10-25
- Estimated Expiration
- 2040-03-24
AI Technical Summary
When the cast-in-place box girder mobile formwork was constructed in the shoal area, due to insufficient headroom, the traditional dismantling method had problems such as the main beam of the formwork weighing about 30 tons using an on-site 90T crawler crane, which was difficult to dismantle, took a long time, and affected subsequent construction.
The mobile formwork vertical and horizontal movement system is adopted, which is composed of a trolley, a horizontal movement track and a temporary support pad, combined with a rotating base, a hydraulic pump station and a hydraulic control system, to realize the convenient dismantling of the main components of the formwork, including lowering and pushing the formwork Longitudinal movement and grouped lateral movement ensure the safety and efficiency of the demolition process.
It achieves safe and rapid dismantling of the main components of the formwork, reduces the construction cycle and platform erection costs. It is suitable for shoal areas and other complex demolition scenarios, and provides economical and reliable construction technology.
Smart Images

Figure CN111395176B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of mobile formwork construction, and specifically to a construction method based on convenient lowering and dismantling of a mobile formwork. Background Art
[0002] The mobile formwork method for cast-in-place box beams is widely used in the in-situ construction of simple supported beams, continuous beams and other bridge types due to its short construction period and good integrity of the beam section. However, due to the large size of the components and the limitations of the construction site and construction equipment, the removal of the mobile formwork is still a major problem.
[0003] In the past decade, the following five methods have been used to dismantle mobile formwork in China: 1. The mobile formwork is lowered as a whole, and then dismantled and loaded onto ships using a floating crane; 2. The guide beams are first dismantled, and then the main beams are lifted to the bridge deck in groups using a large floating crane for dismantling; 3. The outer formwork system is first dismantled, and then the main beams are dismantled and lowered in sections; 4. Move forward / backward longitudinally, and dismantle the main components section by section in the air; 5. The entire formwork is withdrawn to the shore for dismantling. Among them, methods 1 and 2 require water transportation conditions or high clearance conditions, methods 3 and 4 have the disadvantages of long cycles and high safety risks, and method 5 is suitable for single-width formwork construction, which has a long cycle and many influencing factors.
[0004] For projects where the area near the closing part of the cast-in-place beam is a shallow area, floating cranes and other vessels cannot enter during the dismantling of the mobile formwork. The clearance between the bottom of the cast-in-place beam in the closing section and the pier surface is too small. If the above-mentioned conventional method is used to lower and dismantle the mobile formwork, there are problems such as the main components of the formwork main beam weighing about 30 tons being difficult to dismantle using the 90T crawler crane on site, a long dismantling cycle, and the impact on the linear construction period of the subsequent cast-in-place beams. In addition, a wider platform needs to be built, and the cost of platform construction and dismantling is high. Summary of the invention
[0005] The purpose of the present invention is to overcome the difficulties mentioned in the prior art in lowering and disassembling mobile formwork in small clearance areas in shallow areas, and the problem that a large number of sets will affect the linear construction period. The present invention provides a construction method for dismantling the mobile formwork after construction of a cast-in-place box girder mobile formwork method.
[0006] The technical solution adopted by the present invention to solve the technical problem is: a construction method based on the convenient lowering and dismantling of the mobile formwork, applying the mobile formwork longitudinal and transverse movement system to the formwork dismantling process, and conveniently dismantling the main components of the formwork, and the steps are as follows:
[0007] Step 1: Install the mobile formwork longitudinal and transverse system. Arrange the trolley, transverse track and temporary pads on the platform to form the mobile formwork longitudinal and transverse system. The two transverse tracks on both sides are required to be symmetrically arranged directly above the Bailey beam. The transverse track and temporary pads are required to be based on the highest point of the platform, and the lower part is raised. The deviation is controlled within the range of ±5mm. The surface needs to be affixed with stainless steel strips, polished and greased. The transverse track is required to be smooth, and the end reaction beam of the transverse track needs to be welded firmly. After the track is arranged in place, install the trolley for trial transverse movement to check the track size and transverse device performance.
[0008] Step 2: After the mobile formwork is moved to the tail span, or before the tail span concrete is poured, some components need to be removed in advance due to the impact on mold closing or conflict with subsequent formwork construction. To facilitate the removal of the bottom support bracket, the second and last group of bottom formwork trusses (small shear force during the tail span construction) are not folded back, and the A and B sections of the bottom formwork trusses are connected with 12.5# I-beams when closing the mold.
[0009] Step 3: Before pouring the last two holes of a single set of formwork, gradually bury the reserved holes for the formwork and the fine rolled steel for anti-overturning. The reserved holes on the bridge deck and the pre-embedded fine rolled steel are reserved according to the drawings. After checking the position and size, the corresponding span concrete construction is carried out. After the last span concrete is poured, the C50 concrete is used to pour the leveling block at the base of the load-bearing beam. The position of the leveling block is accurately laid out with a total station. The actual height of the leveling block is based on the data measured by the on-site leveler.
[0010] Step 4: The first installation of the load-bearing beam is directly installed on the bridge deck with a large truck crane and accurately positioned. Transfer and installation of the same-width load-bearing beam: After the previous set of formwork lowering system is disassembled, the load-bearing beam is rotated 90 degrees with a rotating base, and then lifted to the installation position with two gantry cranes, centered and positioned, and then rotated until the center of the lifting point hole is aligned with the center of the lowering hole. Transfer and installation of different-width load-bearing beams: First, lift the load-bearing beam to the vicinity of the installation position with a gantry crane, then move the load-bearing beam to the right width with a hand winch, rotate 90 degrees, and finally lift it with a 90T crawler crane + gantry crane for precise positioning. After the load-bearing beam is leveled and installed in place, the gap between the bottom support pad and the leveling block and the bridge deck is filled with bearing grouting material to ensure good contact between the load-bearing surface. The bearing grouting material uses the same grouting material as the cast-in-place beam support, and the water-to-material ratio is strictly controlled according to the material design to ensure that the strength of the filling material is not lower than the strength of C50 concrete. Then two sets of anti-overturning fine-rolled steel are installed on the inner side of the load-bearing beam support pad to achieve a dual-effect anti-overturning effect.
[0011] Step 5: After the longitudinal and transverse prestressing of the cast-in-place beam is completed, the formwork is moved back 1.5 to 2 meters (preferably 1.5 meters) after the formwork is dropped, and the anchoring system of the formwork main beam is installed. The anchoring points of the load-bearing beam and the top of the formwork main beam are connected with steel strands. Each steel strand is pre-tightened by 10KN (30 bundles of Φ17.8 steel strands are used for a single hanging point). After the preparation work for lowering the formwork is completed, the formwork is first raised to a height of 5cm and stabilized for 30 minutes; check that each stress point is normal, the jack has no obvious pressure relief, the concrete pad under the bearing beam support has no crushing phenomenon, and the fine rolled steel has no looseness, etc., and then continue to stabilize the pressure for 12 hours. After checking that there are no obvious abnormalities in each item, proceed to the next process.
[0012] Step 6: After the test lifting and checking that the lifting point is properly loaded, first use a 20T hand chain hoist to fix the tail of one side of the bracket on the main beam of the formwork, and stabilize the tail of the other side of the bracket with the crawler hoist force, then remove the bracket to pull the fine rolled steel, and finally use three cranes (two car cranes + one crawler crane) to lift the bracket with the crawler hoist force and move it horizontally 70cm~100cm (preferably 70cm) out of the reserved hole (the risk of lifting and pulling is small, safe and controllable), and then lower it to the platform, and the remaining brackets are removed and lowered according to the method of step 6 above. After the main components are dismantled, they are hoisted to the platform and dismantled and transferred away.
[0013] Step 7: Operate the LSDB105 hydraulic pump station of the overall lowering system to slowly and synchronously lower the formwork to the trolley pre-arranged on the platform, with a lowering rate of ≤1.5m / h. The synchronous balance accuracy is maintained within the range of ±10mm through the LSDKC(C)-16 hydraulic control system. During the lowering process, the cumulative descending height of each hanging point is also observed by measuring ropes; the measuring ropes are arranged on the side of the main beam wing plate of the corresponding hanging point, and the observers on the side read the readings according to the jack stroke, and the readings are based on the corresponding position of the bridge surface as the reference point. When the formwork is 0.5m away from the trolley slide, slow down the lowering speed to 0.5m / h and check for any abnormalities; when the formwork is 2cm away from the trolley slide, stop lowering, check whether the gaps between the trolleys are consistent, and then press the I-beams of the jacking auxiliary piers against the bottom of the main beam. Finally, completely lower the formwork to be supported by the trolley and jacking auxiliary pier on the platform.
[0014] Step 8: Lower the formwork into place, first remove the outer formwork system, the I-beam on the main beam top, etc.; then use the trolley on the trestle side to pull the transverse steel strand to move the single-side main beam horizontally by 0.3m to 1m to open the mold, and then remove the entire set of bottom formwork trusses.
[0015] Step nine: Then use the longitudinal cylinder on the trolley to push the six-section main beam on one side and move it longitudinally. After the first three main beams have enough space for transverse movement, remove the third joint. Then use the transverse cylinder on the trolley to repeatedly pull the steel strands anchored at the end of the transverse track to move the first three main beams transversely to the bottom of the pouring beam or the bottom of the adjacent moving formwork. Finally, use a gantry crane or crawler crane to remove the main beam. Use the same / similar method to move out and remove the remaining main beams.
[0016] Step 10: Strictly classify and store the dismantled mobile formwork components and transport them.
[0017] The beneficial effects of the present invention are as follows: the main process principle of the present invention is to firstly check and verify that the lowering system and the hanging points can meet the requirements through the overall trial lifting. After removing the bracket, the four jacks are synchronously controlled to be slowly lowered. The lowering control is monitored by the cumulative descent amount, the pressure of the control system, and the displacement to ensure that the forces of each hanging point are balanced and the components of the formwork itself are not damaged. After lowering to the right place and removing the external mold system, the outer main beam is first moved horizontally by 0.3m to open the mold and remove the bottom mold truss, and then the single-sided six-section main beam is pushed and moved longitudinally. During the longitudinal movement, there are temporary auxiliary piers, transverse tracks and other support forces. After the first three sections of the main beam have enough transverse space, the third joint is removed, and the first three sections of the main beam are moved horizontally to appear the pouring beam or the bottom of the adjacent mobile formwork, and then the sections are removed and transferred. The transverse movement is achieved by pulling the steel strands anchored on the reaction beam at the end of the transverse track by the transverse cylinder on the trolley. Finally, the remaining main beams are removed in a similar manner. The present invention can be applied to cast-in-place beam closure sections located in shallow areas, and the formwork removal clearance is small. The difficulty is so great that there is no precedent for the removal of mobile formwork at home and abroad. The present invention innovatively combines the concepts of bridge rotation construction and jacking construction with the longitudinal and transverse movement system of the formwork trolley and applies it to the mobile formwork lowering and removal process for the first time, making the originally complicated and difficult task convenient. The present invention can not only be used for the lowering and removal of mobile formworks with a large number of mobile formwork sets, small construction intervals between adjacent mobile formworks, shallow areas, and small clearances, but is also applicable to the lowering and removal of conventional formworks and the removal of large brackets, providing economical, reliable, and practical construction technology experience for similar projects in the future. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a flowchart of the present invention;
[0019] Figure 2 This is a diagram of a simple rotating base for a load-bearing beam used in the present invention;
[0020] Figure 3 This is a schematic diagram of the overall lowering of the mobile mold frame used in the present invention;
[0021] Figure 4 This is an assembly diagram of the top-pushing longitudinal shifting and grouped transverse shifting device used in the present invention;
[0022] Figure 5 It is a schematic diagram of the push and longitudinal shift device adopted by the present invention;
[0023] Figure 6 A schematic diagram of a transverse shifting device used in the present invention;
[0024] Figure 7 This is a design diagram of the auxiliary force bearing point for jacking and longitudinal shifting adopted by the present invention;
[0025] Figure 8 The design drawing of the frame platform on the bracket adopted by the present invention;
[0026] Fig. 9 This is a schematic diagram of the top-pushing longitudinal movement and grouped lateral movement process adopted by the present invention.
[0027] Figure numerals: 1-limiting pin, 2-upper round steel plate of swivel device, 3-lower round steel plate of swivel device, 4-25 I-beam, 5-double-effect anti-overturning fine-rolled steel, 6-steel strand bundle (30φ17.8, 1860mpa), 7-through-type jack, 8-load-bearing beam, 9-cast-in-place box beam, 10-mobile formwork, 11-single-sided main beam, 12-trolley (integrated top-pushing longitudinal cylinder and transverse cylinder), 13-transverse track (double-piece 25 I-beam), 14-top-pushing longitudinal cylinder, 15-longitudinal sliding shoe, 16- Longitudinal shift orifice plate, 17-transverse shift cylinder, 18-transverse shift slide shoe, 19-transverse shift steel strand (single φ15.6, 1860mpa), 20-transverse shift reaction beam (double 25 I-beam), 21-self-anchoring anchor, clamp combination, 22-pushing longitudinal shift auxiliary force point, 23-double I-beam, 24-φ820mm steel casing, 25-formwork bottom form support rod, 26-support rod hinge seat, 27-bracket upper frame platform, 28-bracket upper frame, 29-double 56 I-beam, 30-φ820mm steel casing. DETAILED DESCRIPTION
[0028] The present invention will be further described below in conjunction with the accompanying drawings.
[0029] like Figures 1 to 9 As shown, a construction method based on the convenient lowering and dismantling of the mobile formwork is shown, in which the mobile formwork longitudinal and transverse movement system is applied to the formwork dismantling process to facilitate the dismantling of the main components of the formwork, and the steps are as follows:
[0030] Step 1. First, make preparations for construction, including construction measurement, the entry of machinery, personnel, materials, etc. and technical preparation; then set up the construction platform: arrange the trolley transverse track and temporary support pads on the platform according to the drawings to form a mobile formwork longitudinal and transverse movement system, as shown in the figure. The system includes a trolley, a transverse track, a transverse cylinder, a longitudinal cylinder, a longitudinal orifice plate and a transverse reaction beam. The longitudinal orifice plate is provided with a number of connecting holes. The trolley is slidably mounted on the transverse track, and the transverse cylinder and the longitudinal cylinder are mounted on the trolley; the piston rod of the transverse cylinder is connected to a transverse sliding shoe, the transverse sliding shoe is connected to one end of the transverse steel strand, and the other end of the transverse steel strand is connected to the transverse reaction beam, and the transverse cylinder pulls the transverse steel strand to make the trolley slide laterally along the transverse track; the piston rod of the longitudinal cylinder is connected to a longitudinal sliding shoe, and the longitudinal sliding shoe is connected to the longitudinal orifice plate through a pin. This device uses a top-pushing longitudinal system composed of longitudinal cylinders on the trolley and a transverse system composed of transverse cylinders on the trolley. It can move the large main components of the mobile formwork on a narrow platform to the bottom of the existing box beam or the adjacent formwork by top-pushing longitudinal movement and group transverse movement. The two transverse tracks on both sides are required to be symmetrically arranged directly above the Bailey beam. The transverse track and temporary support pad are required to be based on the highest point of the platform, and the lower part is raised. The deviation is controlled within the range of ±5mm. The surface needs to be affixed with stainless steel strips, polished and greased. The transverse track is required to be smooth, and the reaction beam at the end of the track needs to be welded firmly. After the track is in place, install the trolley for trial transverse movement to check the track size, transverse device performance, etc.
[0031] Step 2. Dismantling of affected parts before the construction of the tail span: After the mobile formwork is moved to the tail span, or before the concrete of the tail span is poured, some components need to be dismantled in advance due to the impact on mold closing or conflicts with subsequent formwork construction. The first section of the front guide beam and the first 10m section and the rear 10m outer formwork system can be dismantled, and the remaining components need to be dismantled after the tail span is tensioned or the formwork is lowered into place. To facilitate the removal of the bottom support bracket, the second and last group of bottom formwork trusses (small shear force during the construction of the tail span) will not be folded back, and the bottom formwork trusses A and B sections will be connected with 12.5 I-beams when closing the mold.
[0032] Step 3. Construction of the tail span: Before pouring the last two holes of the single set of formwork, gradually bury the reserved holes for the lowering of the formwork and the fine rolled steel for anti-overturning. The reserved holes on the bridge deck and the pre-embedded fine rolled steel are reserved according to the drawings. After checking the position and size, the corresponding span concrete construction is carried out. After the concrete pouring of the tail span is completed, the C50 concrete is used to pour the leveling block at the base of the load-bearing beam. The position of the leveling block is accurately laid out with a total station or total station. The actual height of the leveling block is based on the data measured by the on-site leveler.
[0033] Step 4. Installation of the load-bearing beam. The load-bearing beam is first installed by directly hoisting it onto the bridge deck with a large truck crane and accurately positioning it. When positioning, install a simple rotating base (such as Figure 2 As shown in the figure, after rotating it 90 degrees, it can be transferred by the bridge deck gantry crane. During installation, a simple rotating base can also be used to rotate it to position. After the load-bearing beam is leveled and installed in place, the gaps between the bottom support pad and the leveling block and the bridge deck are filled with support grouting material to ensure good contact between the load-bearing surfaces. The support grouting material uses the same grouting material as the cast-in-place beam support, and the water-to-material ratio is strictly controlled according to the material design to ensure that the strength of the filling material is not lower than the strength of C50 concrete.
[0034] Among them, the same width load-bearing beam is transferred and installed. After the previous set of formwork lowering system is disassembled, the load-bearing beam is rotated 90 degrees with a rotating base, and then lifted to the installation position with two gantry cranes, aligned and then rotated until the center of the lifting point hole is aligned with the center of the lowering hole.
[0035] Among them, the transfer and installation of different-width load-bearing beams. First, lift the load-bearing beam to the vicinity of the installation position with a gantry crane, then move the load-bearing beam to the right side with a hand winch, and finally lift it with a 90T crawler crane + gantry crane for precise positioning. After the load-bearing beam is leveled and installed in place, the gap between the bottom support pad and the leveling block and the bridge deck is filled with support grouting material to ensure good contact between the force-bearing surface. The support grouting material uses the same grouting material as the cast-in-place beam support, and the water-to-material ratio is strictly controlled according to the material design to ensure that the strength of the filling material is not lower than the strength of C50 concrete. Then install two sets of anti-overturning fine-rolled steel on the inner side of the load-bearing beam support pad to play a dual-effect anti-overturning role.
[0036] Step 5. Trial lifting of the formwork. After the longitudinal and transverse prestressing of the cast-in-place beam is completed, the formwork is moved back 1.5 to 2 meters (preferably 1.5 meters) and the anchoring system of the formwork main beam is installed. The anchoring points of the load-bearing beam and the top of the formwork main beam are connected with steel strands. Each steel strand is pre-tightened by 10KN (30 bundles of Φ17.8 steel strands are used for a single hanging point). After the preparation work for lowering the formwork is completed, the formwork is first lifted 5cm high and stabilized for 30 minutes; check that each stress point is normal, there is no obvious pressure relief on the jack, there is no crushing phenomenon on the concrete pad under the bearing beam support, and there is no loosening of the fine rolled steel, etc., and then continue to stabilize the pressure for 12 hours. After checking that there are no obvious abnormalities in each item, proceed to the next process.
[0037] Step 6. The bracket is lowered in situ: First, after the test lifting and checking that the lifting point is properly stressed, use a 20T hand chain hoist to fix the tail of one side of the bracket on the main beam of the formwork, and stabilize the tail of the other side of the bracket with the crawler hoist force, then remove the bracket to pull the fine rolled steel, and finally use three cranes (two car cranes + one crawler crane) to lift the bracket with the crawler hoist force and move it horizontally 70cm~100cm (preferably 70cm) out of the reserved hole (the risk of lifting and pulling is small, safe and controllable), and then lower it to the platform, and the remaining brackets are removed and lowered according to the method of step 6 above. After the main components are dismantled, they will be hoisted to the platform and dismantled and transferred away.
[0038] Step 7. Operate the LSDB105 hydraulic pump station of the overall lowering system to slowly and synchronously lower the formwork to the trolley pre-arranged on the platform, with a lowering rate of ≤1.5m / h. The synchronous balance accuracy is maintained within the range of ±10mm through the LSDKC(C)-16 hydraulic control system. During the lowering process, the cumulative descending height of each hanging point is also observed by measuring ropes; the measuring ropes are arranged on the side of the main beam wing plate of the corresponding hanging point, and the observers on the side read the readings according to the jack stroke, and the readings are based on the corresponding position of the bridge surface as the reference point. When the formwork is 0.5m away from the trolley slide, slow down the lowering speed to 0.5m / h and check for any abnormalities; when the formwork is 2cm away from the trolley slide, stop lowering, check whether the gaps between the trolleys are consistent, and then press the I-beams of the jacking auxiliary piers against the bottom of the main beam. Finally, completely lower the formwork to be supported by the trolley and jacking auxiliary pier on the platform.
[0039] Step 8. Dismantling of the outer formwork system and small components: Lower the formwork frame into place, first dismantle the outer formwork system, I-beams on the top of the main beam, etc.; then use the trolley on the trestle side to pull the transverse steel strands to move the single-side main beam horizontally by 0.3m to 1m (preferably 0.3m) to open the mold, and dismantle the entire bottom formwork truss.
[0040] Step 9. Main beam removal: Use the longitudinal cylinder on the trolley to push and move the six-section main beam on one side longitudinally. After the first three main beams have enough space for transverse movement, remove the third joint. Then use the transverse cylinder on the trolley to repeatedly pull the steel strands anchored at the end of the transverse track to move the first three main beams transversely to the bottom of the pouring beam or the bottom of the adjacent movable formwork. Finally, use a gantry crane or crawler crane to remove the main beam. Use similar methods to move out and remove the remaining main beams.
[0041] Step 10. Strictly classify and store the dismantled mobile formwork components and transport them.
[0042] The main features of the present invention are the use of conventional turnover materials and equipment, strong operability, safety and reliability, and fast construction progress. Its main features are: 1. The load-bearing beam used for lowering the formwork as a whole weighs 30 tons. Except for the initial installation using a large automobile crane, the subsequent construction uses a simple rotating base to manually rotate the load-bearing beam 90° and then use a bridge deck gantry crane to convert and install it between the same width and different widths. The investment is small and the construction speed is fast. 2. The bracket has a small clearance for dismantling. Three cranes are used to lift and move it horizontally 70cm out of the reserved hole of the pier body, and then lower it to the pedestal. The construction speed is fast, the horizontal movement space is small, and the safety risk is controllable. 3. The main beam of the mobile formwork adopts the method of top-pushing longitudinal movement and grouped horizontal movement to move the main beam to the bottom of the existing beam or the mobile formwork, and then use a gantry crane or a crawler crane to dismantle it. Compared with the conventional method, there is one more method for dismantling the main beam, and the position can be moved, which is more convenient and flexible, with a fast construction speed, saving construction time and cost.
[0043] The main process principle of the present invention is to first check and verify that the lowering system and hanging points can meet the requirements through overall trial lifting. After removing the bracket, the four jacks are synchronously controlled to slowly lower. The lowering control is monitored by the cumulative descent amount, the pressure of the control system, and the displacement to ensure that the forces on each hanging point are balanced and the components of the formwork itself are not damaged. After lowering to the right place and removing the external mold system, the outer main beam is first moved horizontally by 0.3m to open the mold and remove the bottom mold truss. Then the six-section main beam on one side is pushed and moved longitudinally. During the longitudinal movement, there are temporary auxiliary piers, transverse tracks and other supports. After the first three main beams have enough space for transverse movement, the third joint is removed, and the first three main beams are moved horizontally to appear the pouring beam or the bottom of the adjacent mobile formwork, and then removed and transferred in sections. The transverse movement is achieved by pulling the steel strands anchored on the reaction beam at the end of the transverse track by the transverse cylinder on the trolley. Finally, the remaining main beams are removed in a similar manner. The present invention is suitable for the lowering and dismantling of conventional mobile formworks or the dismantling of large brackets, and is more effective in the lowering and dismantling of mobile formworks with a large number of sets, small construction intervals between adjacent mobile formworks, shallow areas, and small clearances. In the process of transferring and installing the load-bearing beams used for lowering the formwork, a simple rotating base is added to directly simplify this originally difficult problem, which not only saves the temporary rental fee of a large truck crane, but also directly eliminates the safety risks of hoisting.
[0044] This project applies the concept of bridge jacking construction to the formwork removal process, constructs auxiliary stress points, and makes full use of the formwork's own vertical and horizontal movement system to group the formwork main beams and horizontally move them to form cast beams or formwork bottoms, making the originally complex process simpler and more convenient, and the linear construction period of adjacent formwork cast-in-place beams is not affected. The specific economic benefit comparison analysis is shown in the following table:
[0045] Economic Benefit Comparison Table
[0046]
[0047] The lowering and removal of mobile formwork is the key and difficult part of the mobile formwork method for cast-in-place beam construction. The closing section of the cast-in-place beam in this project is located in a shallow area, and the clearance for formwork removal is small. The difficulty is so great that there is no precedent for the removal of mobile formwork at home and abroad. This project innovatively applies the concepts of bridge rotation construction and jacking construction to the lowering and removal process of mobile formwork for the first time, making the originally complicated and difficult task convenient. The present invention can not only be used for the lowering and removal of mobile formwork in areas with a large number of mobile formwork sets, small construction intervals between adjacent mobile formworks, shallow areas, and small clearances, but is also applicable to the lowering and removal of conventional formworks and the removal of large brackets, providing economical, reliable, and practical construction technology experience for similar projects in the future.
[0048] The above is only a preferred embodiment of the present invention, and should not be used to limit the scope of the present invention. That is, all simple equivalent changes and modifications made according to the scope of the patent application and the content of the invention description of the present invention are still within the scope of the patent of the present invention.
Claims
1. A convenient mobile formwork lowering and dismantling construction method, characterized in that: Apply the mobile formwork vertical and horizontal movement system to the formwork dismantling process to facilitate the dismantling of the main components of the formwork. The steps are as follows: Step 1. Arrange the trolley, transverse track and temporary support pads on the platform to form a mobile mold frame longitudinal and transverse movement system; Step 2. After the mobile mold frame is moved to the tail span, the second and last group of bottom mold trusses are not folded back, and the A and B sections of the bottom mold trusses are connected with I-beams when closing the mold; Step 3. Before pouring the last two holes of a single set of formwork, gradually bury the reserved holes for lowering the formwork and the fine rolled steel for anti-overturning; after the concrete pouring of the tail span is completed, pour the leveling block with C50 concrete at the base of the load-bearing beam; Step 4. The load-bearing beam is first installed by using a large truck crane to directly hoist it onto the bridge deck and accurately position it; Step 5. After the longitudinal and transverse prestressing of the cast-in-place beam is completed, the formwork is dropped and the entire formwork is moved back 1.5 to 2 meters. The anchor points of the load-bearing beam and the top of the formwork main beam are connected with steel strands, and each steel strand is pre-tightened; Step 6. After the test lifting and checking that the lifting point is properly stressed, fix the tail of the bracket on one side to the main beam of the formwork with a hand chain hoist, and stabilize the tail of the bracket on the other side with the force of the first crawler hoist. Then remove the bracket to pull the fine rolled steel. Finally, use the car crane and the second crawler crane to lift the bracket separated from the first crawler hoist and move it horizontally 70cm to 100cm out of the reserved hole, and then lower it to the bearing platform. Remove the remaining brackets and lower them according to the method in this step. After the main components are removed, lift them to the platform and dismantle them and move them away; Step 7. Operate the hydraulic pump station of the overall lowering system to slowly and synchronously lower the entire set of mobile formwork to the trolley pre-arranged on the platform; Step 8. Lower the formwork into place, first remove the outer formwork system and the I-beam on the top of the main beam; then use the trolley on the trestle side to pull the horizontal steel strands horizontally by 0.3m to 1m to open the mold, and remove the entire bottom formwork truss; Step 9. Use the longitudinal cylinder on the trolley to push the six-section main beam on one side and move it longitudinally. When the first three main beams have enough space for transverse movement, remove the third joint. Then use the transverse cylinder on the trolley to repeatedly pull the steel strands anchored at the end of the transverse track to move the first three main beams transversely to the bottom of the pouring beam or the bottom of the adjacent movable formwork. Finally, use a gantry crane or crawler crane to remove the main beam. Use the same method to move out and remove the remaining main beams.
2. A convenient mobile formwork lowering and dismantling construction method according to claim 1, characterized in that: In step one, the two transverse tracks on both sides are required to be arranged symmetrically just above the Bailey beam. The transverse tracks and temporary supports are required to be based on the highest point of the platform, with the lower part raised and the tracks kept level. The deviation is controlled within the range of ±5mm. The surface needs to be affixed with stainless steel strips, polished and greased. The transverse tracks are required to be smooth, and the end reaction beams of the transverse tracks need to be welded firmly.
3. A convenient mobile formwork lowering and dismantling construction method according to claim 1, characterized in that: In step 4, the steps for transferring and installing the same width load-bearing beam are as follows: after the disassembly of the previous set of formwork lowering system is completed, the load-bearing beam is rotated 90 degrees using a rotating base, and then lifted to the installation position using a gantry crane, centered and positioned, and then rotated until the center of the lifting point hole is aligned with the center of the lowering hole.
4. A convenient mobile formwork lowering and dismantling construction method according to claim 1, characterized in that: In step four, the steps for transferring and installing the load-bearing beams of different widths are as follows: first, lift the load-bearing beam with a gantry crane to the vicinity of the installation position, then use a hand winch to move the load-bearing beam to the right width, rotate it 90 degrees, and then lift it with a crawler crane and a gantry crane for precise positioning.
5. According to claim 1, a convenient mobile formwork lowering and dismantling construction method is characterized in that: In step 4, after the load-bearing beam is leveled and installed in place, the gaps between the bottom support pad and the leveling block and the bridge deck are densely filled with bearing grouting material to ensure good contact between the load-bearing surfaces.
6. A convenient mobile formwork lowering and dismantling construction method according to claim 5, characterized in that: In step four, the same grouting material as the cast-in-place beam support is used for the support grouting material. The water-to-material ratio is strictly controlled according to the material design to ensure that the strength of the filling material is not lower than the strength of C50 concrete. Then, two sets of anti-overturning fine-rolled steel are installed on the inner side of the load-bearing beam support.
7. A convenient mobile formwork lowering and dismantling construction method according to claim 1, characterized in that: In step five, after the preparations for lowering the formwork are completed, first lift the formwork for a trial and stabilize it for 30 minutes; check that all stress points are normal, there is no obvious pressure relief on the jack, there is no crushing of the concrete pad under the support beam, and there is no looseness of the high-rolled steel, then continue to stabilize the pressure for 12 hours. After checking that there are no obvious abnormalities in any items, proceed to the next process.
8. The method for lowering and dismantling a mobile formwork based on convenience according to claim 1 is characterized in that: In step seven, the synchronous balance accuracy is maintained within the range of ±10mm through the hydraulic control system. The cumulative descent height of each hanging point is also observed through the measuring rope during the lowering process. The measuring rope is arranged on the side of the main beam wing plate of the corresponding hanging point. When the formwork is 0.5m away from the trolley slide, the lowering speed is slowed down to 0.5m / h. When the formwork is 2cm away from the trolley slide, the lowering is stopped to check whether the gaps between the trolleys are consistent, and then the I-beam of the jacking auxiliary pier is pressed against the bottom of the main beam. Finally, the formwork is completely lowered to be supported by the trolley and the jacking auxiliary pier on the platform.