Road structure based on hydrophobic material waterproof layer and its waterproof layer layout method

By using a hydrophobic material suspension to spray the water-isolating layer in the road structure, the problems of difficulty in extracting materials and high construction costs of the water-isolating layer are solved, effective prevention and control of groundwater and frost heave is achieved, project costs are reduced, and the quality of the road is improved. Stability and operational efficiency.

CN111424482BActive Publication Date: 2024-10-01NORTHEAST FORESTRY UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202010194277.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-03-13
Publication Date
2024-10-01
Estimated Expiration
2040-03-13

AI Technical Summary

Technical Problem

The difficulty in obtaining materials for the water-proof layer in the existing road structure and the high construction cost, especially in areas where aggregate materials are lacking, have affected the stability and operational efficiency of the road structure.

Method used

The water-proof layer structure and its layout method based on hydrophobic materials are used. By preparing a hydrophobic material suspension and spraying it on the surface of the roadbed, different layers of water-proof layers are set up to block groundwater and prevent frost heaving, replacing part of the thickness of the functional layer of granular materials. , using formulas to estimate the replacement thickness to adapt to different environmental conditions.

Benefits of technology

It can effectively prevent water damage and frost heave, keep the roadbed stable, reduce project costs, is convenient to construct, non-toxic and harmless, has good durability and water-blocking effect, and can adapt to different environmental conditions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111424482B_ABST
    Figure CN111424482B_ABST
Patent Text Reader

Abstract

A road structure based on a hydrophobic material waterproof layer and a method for laying out the waterproof layer thereof, which relates to the technical field of road construction. The present invention is to solve the problems of difficulty in obtaining materials for the waterproof layer in the existing road structure and high engineering cost. The road structure includes a surface layer, a base layer, a functional layer, a first hydrophobic material waterproof layer and a roadbed. The roadbed, the functional layer, the base layer and the surface layer are laid in sequence from bottom to top, and a first hydrophobic material waterproof layer is spread on the bottom surface of the roadbed. The method for laying out the waterproof layer includes: preparing a hydrophobic material suspension; spreading the waterproof layer. The present invention is used for road construction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of road construction, and in particular to a road structure based on a hydrophobic material waterproof layer and a method for laying out the waterproof layer. Background Art

[0002] Road projects not only have to bear the effects of wheel loads, but also are affected by natural environmental factors. Since the effects of vehicle loads and atmospheric factors on the road surface generally weaken with depth, road projects are usually multi-layer structures. Materials with higher strength that meet driving requirements are laid on the upper layer with greater stress, and materials with lower strength are laid on the lower layer with less stress, thus forming a road structure form in which materials of different specifications and requirements are used on the roadbed to lay the functional layer, base layer and surface layer respectively. In order to prevent frost heave and water damage in road projects and maintain the stability of the roadbed, in areas with rich water systems, high groundwater levels, large surface runoff and frequent atmospheric precipitation, a waterproof layer is usually set in the road structure layer. At present, the roadbed waterproofing is mainly made of crushed stone filling, but it is difficult to obtain materials in areas lacking granular materials, and the project cost increases. Summary of the invention

[0003] In order to solve the problems of difficulty in obtaining materials for the waterproof layer in the existing road structure and high engineering cost, the present invention further proposes a road structure based on a waterproof layer of hydrophobic material and a method for laying out the waterproof layer.

[0004] The technical solution adopted by the present invention to solve the above technical problems is:

[0005] The road structure based on the hydrophobic material waterproof layer includes a surface layer, a base layer, a functional layer, a first hydrophobic material waterproof layer and a roadbed. The roadbed, functional layer, base layer and surface layer are laid in sequence from bottom to top, and a first hydrophobic material waterproof layer is spread on the bottom of the roadbed.

[0006] The method for laying out the waterproof layer of the road structure based on the hydrophobic material waterproof layer comprises the following steps:

[0007] Step 1: Prepare a hydrophobic material suspension: Use the effective substance of the hydrophobic material as the solute and water as the solvent to prepare a hydrophobic material suspension of a certain concentration that meets the water-blocking requirements of the road environment;

[0008] Step 2: Spread the waterproof layer: According to the different environments of the roadbed, set different layers of waterproof layers:

[0009] (I) When the roadbed is in a humid environment, 1 to 3 layers of waterproofing are set inside the road:

[0010] (II) When constructing a road cut, 1 to 3 waterproof layers are provided, wherein a first waterproof layer of hydrophobic material is provided on the bottom surface of the roadbed, and a first waterproof layer of hydrophobic material is spread on the bottom surface of the roadbed by spraying;

[0011] If the groundwater level in the area where the roadbed passes is high and the roadbed is built at a high height, a second hydrophobic material waterproof layer can be spread on the bottom surface of the functional layer composed of granular materials in the form of spraying according to actual needs to replace part of the thickness of the granular functional layer. The replacement thickness of the second hydrophobic material waterproof layer is less than or equal to 5 cm, and its replacement thickness can be estimated by the following formula:

[0012] h=(x-10)·A(X)

[0013] Wherein, in formula (X): h—thickness of the functional layer of the alternative granular material (cm);

[0014] x—effective substance concentration of the isolation layer (%);

[0015] A—comprehensive parameter, which is related to factors such as the amount of aquiclude material per unit area, the purity of the aquiclude material, the size of soil particles, gradation, and the location of the groundwater level;

[0016] If the groundwater level in the area where the roadbed passes is high and the roadbed is built at a low height, a third hydrophobic material waterproof layer can be spread in the lower part of the roadbed in the form of spraying according to actual needs, and the distance between the third hydrophobic material waterproof layer and the first hydrophobic material waterproof layer is 15cm to 25cm;

[0017] (I-II) When constructing the embankment, 1 to 3 waterproof layers are set, the first waterproof layer of hydrophobic material is set at the bottom surface of the roadbed, and a first waterproof layer of hydrophobic material is spread on the bottom surface of the roadbed in the form of spraying;

[0018] If the groundwater level in the area where the roadbed passes is high and the roadbed is built at a high height, a second hydrophobic material waterproof layer can be spread on the bottom surface of the functional layer composed of granular materials in the form of spraying according to actual needs to replace part of the thickness of the granular functional layer. The replacement thickness of the second hydrophobic material waterproof layer is less than or equal to 5 cm, and its replacement thickness can be estimated by formula (X);

[0019] If the groundwater level in the area where the roadbed passes is high and the roadbed is built at a low height, a third hydrophobic material waterproof layer can be spread in the lower part of the roadbed in the form of spraying according to actual needs, and the distance between the third hydrophobic material waterproof layer and the first hydrophobic material waterproof layer is 15cm to 25cm;

[0020] (II) When the roadbed is in a medium-humid environment, 1 to 2 layers of waterproof layers are set inside the road:

[0021] (II-I) When constructing a road cut, 1 to 2 waterproof layers are set. The first waterproof layer of hydrophobic material is set on the bottom surface of the roadbed. A layer of the first waterproof layer of hydrophobic material is spread on the bottom surface of the roadbed in the form of spraying; a layer of the second waterproof layer of hydrophobic material can be spread on the bottom surface of the functional layer composed of granular materials in the form of spraying according to the roadbed height and actual needs to replace a part of the thickness of the granular functional layer. The replacement thickness of the second waterproof layer of hydrophobic material is less than or equal to 5 cm, and its replacement thickness can be estimated by formula (X);

[0022] (II-II) When constructing an embankment, 1 to 2 waterproof layers are set. The first waterproof layer of hydrophobic material is set at the bottom surface of the roadbed. A layer of the first waterproof layer of hydrophobic material is spread on the bottom surface of the roadbed by spraying. According to the roadbed height and actual needs, a layer of the second waterproof layer of hydrophobic material can be spread on the bottom surface of the functional layer composed of aggregate by spraying to replace part of the thickness of the aggregate functional layer. The replacement thickness of the second waterproof layer of hydrophobic material is less than or equal to 5 cm, and its replacement thickness can be estimated by formula (X).

[0023] Compared with the prior art, the present invention has the following beneficial effects:

[0024] The present invention proposes a road structure based on a hydrophobic material waterproof layer and a method for laying out the waterproof layer thereof. The hydrophobic material's water-repelling properties are utilized to prepare a hydrophobic material suspension, which is sprayed on the roadbed surface to block the capillary action of groundwater and the upward migration of water during the freezing process, thereby preventing water damage to the road structure and affecting road operations.

[0025] The waterproof layer of the present invention can replace or partially replace the granular functional layer, and is used to isolate the capillary phenomenon and frost heave migration of groundwater, maintain the stability of the roadbed, prevent and isolate water intrusion, and prevent the road structure from being damaged by water. It is non-toxic and harmless, has good durability, is easy to construct, has good water blocking effect, small engineering quantity, and low cost; the setting method is flexible, and the number of layers and the concentration of effective substances of the hydrophobic material can be adjusted according to needs. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 It is a schematic diagram of the overall structure of the road cutting in the present invention;

[0027] Figure 2 It is a schematic diagram of the overall structure of the embankment in the present invention. DETAILED DESCRIPTION

[0028] Specific implementation method 1: Combination Figure 1 to Figure 2 To illustrate this embodiment, the road structure based on the hydrophobic material waterproof layer described in this embodiment includes a surface layer 1, a base layer 2, a functional layer 3, a first hydrophobic material waterproof layer 4 and a roadbed 5. The roadbed 5, the functional layer 3, the base layer 2 and the surface layer 1 are laid in sequence from bottom to top, and a layer of the first hydrophobic material waterproof layer 4 is spread on the bottom surface of the roadbed 5.

[0029] In this embodiment, when the roadbed 5 is in a medium-humid environment, when building the embankment, a first hydrophobic material waterproof layer 4 is spread on the bottom surface of the roadbed 5 by spraying, and a second hydrophobic material waterproof layer 6 is spread on the bottom layer of the functional layer 3 as needed.

[0030] Specific implementation method 2: Combination Figure 1 to Figure 2 To explain this embodiment, the bottom layer of the functional layer 3 in this embodiment is paved with a second hydrophobic material waterproof layer 6. The undisclosed technical features in this embodiment are the same as those in the first embodiment.

[0031] In the present embodiment, when the roadbed 5 is in a humid environment, such as the groundwater level in the area through which the roadbed 5 passes is high and the construction height of the roadbed 5 is high, a layer of second hydrophobic material waterproof layer 6 can be sprayed on the bottom surface of the functional layer 3 composed of granular materials according to actual needs to replace a part of the thickness of the granular functional layer 3; when the roadbed 5 is in a medium-humid environment, a layer of second hydrophobic material waterproof layer 6 can be sprayed on the bottom surface of the functional layer 3 composed of granular materials according to the height of the roadbed 5 and actual needs to replace a part of the thickness of the granular functional layer 3.

[0032] Specific implementation method three: Combination Figure 1 to Figure 2 To explain this embodiment, a third hydrophobic material waterproof layer 7 is spread on the lower part of the roadbed 5 in this embodiment. The undisclosed technical features in this embodiment are the same as those in the second embodiment.

[0033] In this embodiment, if the roadbed 5 is in a humid environment and the groundwater level in the area through which the roadbed 5 passes is high, and the construction height of the roadbed 5 is low, a layer of third hydrophobic material waterproof layer 7 can be spread in the lower part of the roadbed 5 by spraying according to actual needs.

[0034] Specific implementation method four: Combination Figure 1 to Figure 2 In this embodiment, the distance between the third hydrophobic material waterproof layer 7 and the first hydrophobic material waterproof layer 4 is 15 cm to 25 cm. The undisclosed technical features in this embodiment are the same as those in the third embodiment.

[0035] In this embodiment, during construction, after spreading the first hydrophobic material waterproof layer 4 , a roadbed 5 with a thickness of 15 cm to 25 cm is first laid, and then a third hydrophobic material waterproof layer 7 is spread, and then the roadbed 5 is continued to be laid.

[0036] As a preferred distance between the third hydrophobic material waterproof layer 7 and the first hydrophobic material waterproof layer 4 is 20 cm.

[0037] Specific implementation method five: Combination Figure 1 to Figure 2To explain this embodiment, the first hydrophobic material waterproof layer 4, the second hydrophobic material waterproof layer 6 and the third hydrophobic material waterproof layer 7 are all waterproof layers made of hydrophobic material suspension. The undisclosed technical features in this embodiment are the same as those in the fourth embodiment.

[0038] Specific implementation method six: Combination Figure 1 to Figure 2 This embodiment is described in which the hydrophobic material suspension is an organosilicon suspension. The undisclosed technical features in this embodiment are the same as those in the fifth embodiment.

[0039] Using silicone suspension as a water barrier has the following advantages:

[0040] 1. Good water barrier

[0041] The active genes in the silicone and the silicon (hydroxy) groups in the soil can form a hydrophobic coating film with high hydrophobic properties to prevent water from passing through;

[0042] 2. Environmentally friendly

[0043] The formed hydrophobic coating is non-toxic, harmless, non-polluting, and has stable chemical and thermal properties;

[0044] 3. Good durability

[0045] The organic silicon waterproof layer has stable performance, high temperature resistance, and corrosion resistance, and its service life can be up to 100 years;

[0046] 4. Convenient construction and simple process

[0047] It can be prepared into a suspension of a given concentration with water and applied by spraying. The operation time is short and the construction process is simple. The next step of construction can usually be carried out within 12 hours after construction.

[0048] 5. Good economy

[0049] This material is used for roadbed waterproof layer, the material cost is low, and it has economic advantages compared with similar waterproof layer materials.

[0050] Specific implementation method seven: Combination Figure 1 to Figure 2 To illustrate this embodiment, the effective substance concentration of the hydrophobic material suspension in this embodiment is greater than or equal to 10%. The undisclosed technical features in this embodiment are the same as those in the fifth embodiment.

[0051] In this embodiment, when the roadbed 5 is in a humid environment, the effective substance concentration of the hydrophobic material suspension in the third hydrophobic material waterproof layer 7 in the embankment can be appropriately reduced according to actual conditions.

[0052] Specific implementation method eight: Combination Figure 1 to Figure 2The present embodiment is described. The method for laying out the waterproof layer of the road structure based on the waterproof layer of the hydrophobic material described in the present embodiment comprises the following steps:

[0053] Step 1: Prepare a hydrophobic material suspension: Use the effective substance of the hydrophobic material as the solute and water as the solvent to prepare a hydrophobic material suspension of a certain concentration that meets the water-blocking requirements of the road environment;

[0054] Step 2: Spreading waterproof layer: According to the different environments of the roadbed 5, different layers of waterproof layer are set:

[0055] (I) When the roadbed 5 is in a humid environment, 1 to 3 layers of waterproof layers are set inside the road:

[0056] (II) When constructing a road cut, 1 to 3 waterproof layers are provided, a first waterproof layer 4 of a hydrophobic material is provided on the bottom surface of a roadbed 5, and a first waterproof layer 4 of a hydrophobic material is spread on the bottom surface of the roadbed 5 in the form of spraying;

[0057] If the groundwater level in the area where the roadbed 5 passes is high and the construction height of the roadbed 5 is high, a second hydrophobic material waterproof layer 6 can be spread on the bottom surface of the functional layer 3 composed of granular materials in the form of spraying according to actual needs to replace a part of the thickness of the granular functional layer 3. The replacement thickness of the second hydrophobic material waterproof layer 6 is less than or equal to 5 cm, and its replacement thickness can be estimated by the following formula:

[0058] h=(x-10)·A(X)

[0059] Wherein, in formula (X): h—thickness of the functional layer of the alternative granular material (cm);

[0060] x—effective substance concentration of the isolation layer (%);

[0061] A—comprehensive parameter, which is related to factors such as the amount of aquiclude material per unit area, the purity of the aquiclude material, the size of soil particles, gradation, and the location of the groundwater level;

[0062] If the groundwater level in the area where the roadbed 5 passes is high and the construction height of the roadbed 5 is low, a third hydrophobic material waterproof layer 7 can be spread in the lower part of the roadbed 5 in the form of spraying according to actual needs, and the distance between the third hydrophobic material waterproof layer 7 and the first hydrophobic material waterproof layer 4 is 15cm to 25cm;

[0063] (I-II) When constructing the embankment, 1 to 3 waterproof layers are set, and the first waterproof layer 4 of the hydrophobic material is set at the bottom surface of the roadbed 5, and a layer of the first waterproof layer 4 of the hydrophobic material is spread on the bottom surface of the roadbed 5 in the form of spraying;

[0064] If the groundwater level in the area where the roadbed 5 passes is high and the construction height of the roadbed 5 is high, a second hydrophobic material waterproof layer 6 can be spread on the bottom surface of the functional layer 3 composed of granular materials in the form of spraying according to actual needs to replace a part of the thickness of the granular functional layer 3. The replacement thickness of the second hydrophobic material waterproof layer 6 is less than or equal to 5 cm, and its replacement thickness can be estimated by formula (X);

[0065] If the groundwater level in the area where the roadbed 5 passes is high and the construction height of the roadbed 5 is low, a third hydrophobic material waterproof layer 7 can be spread in the lower part of the roadbed 5 in the form of spraying according to actual needs, and the distance between the third hydrophobic material waterproof layer 7 and the first hydrophobic material waterproof layer 4 is 15cm to 25cm;

[0066] (II) When the roadbed 5 is in a medium-humid environment, 1 to 2 layers of waterproof layers are set inside the road:

[0067] (II-I) When constructing a road cut, 1 to 2 waterproof layers are set, and a first waterproof layer 4 of a hydrophobic material is set on the bottom surface of the roadbed 5. A layer of the first waterproof layer 4 of a hydrophobic material is spread on the bottom surface of the roadbed 5 in the form of spraying; a layer of a second waterproof layer 6 of a hydrophobic material can be spread on the bottom surface of the functional layer 3 composed of granular materials in the form of spraying according to the height of the roadbed 5 and actual needs, replacing a part of the thickness of the granular functional layer 3. The replacement thickness of the second waterproof layer 6 of a hydrophobic material is less than or equal to 5 cm, and its replacement thickness can be estimated by formula (X);

[0068] (II-II) When constructing an embankment, 1 to 2 waterproof layers are set. A first hydrophobic waterproof layer 4 is set at the bottom of the roadbed 5. A first hydrophobic waterproof layer 4 is spread on the bottom of the roadbed 5 by spraying. According to the height of the roadbed 5 and actual needs, a second hydrophobic waterproof layer 6 is spread on the bottom of the functional layer 3 composed of granular materials by spraying to replace a part of the thickness of the granular functional layer 3. The replacement thickness of the second hydrophobic waterproof layer 6 is less than or equal to 5 cm, and its replacement thickness can be estimated by formula (X).

[0069] In this embodiment, A is related to factors such as the amount of waterproof layer material per unit area, the purity of the waterproof layer material, the size of soil particles, the gradation, the location of the groundwater level, etc., and is determined through experimental tests.

[0070] Specific implementation method nine: Combination Figure 1 to Figure 2The present embodiment is described. In the present embodiment, when the roadbed 5 is in a humid environment: in the road cutting, the effective substance concentration of the hydrophobic material suspension in the first hydrophobic material waterproof layer 4 is greater than or equal to 15%, and the effective substance concentration of the hydrophobic material suspension in the second hydrophobic material waterproof layer 6 is the same as the effective substance concentration of the hydrophobic material suspension in the first hydrophobic material waterproof layer 4; in the embankment, the effective substance concentration of the hydrophobic material suspension in the first hydrophobic material waterproof layer 4 is greater than or equal to 10%, the effective substance concentration of the hydrophobic material suspension in the second hydrophobic material waterproof layer 6 is the same as the effective substance concentration of the hydrophobic material suspension in the first hydrophobic material waterproof layer 4, and the effective substance concentration of the hydrophobic material suspension in the third hydrophobic material waterproof layer 7 can be adjusted according to the roadbed 5. The soil particle size and gradation are lower than the effective substance concentration of the hydrophobic material suspension in the first hydrophobic material waterproof layer 4; when the roadbed 5 is in a medium-humid environment: in the road cut, the effective substance concentration of the hydrophobic material suspension in the first hydrophobic material waterproof layer 4 is greater than or equal to 10%, and the effective substance concentration of the hydrophobic material suspension in the second hydrophobic material waterproof layer 6 is the same as or lower than the effective substance concentration of the hydrophobic material suspension in the first hydrophobic material waterproof layer 4; in the embankment, the effective substance concentration of the hydrophobic material suspension in the first hydrophobic material waterproof layer 4 is greater than or equal to 10%, and the effective substance concentration of the hydrophobic material suspension in the second hydrophobic material waterproof layer 6 is the same as or lower than the effective substance concentration of the hydrophobic material suspension in the first hydrophobic material waterproof layer 4. The undisclosed technical features in this embodiment are the same as those in the eighth specific embodiment.

[0071] When the roadbed 5 is in a humid environment: in the road cutting, the effective substance concentration of the hydrophobic material suspension in the first hydrophobic material waterproof layer 4 is greater than or equal to 15%, and the effective substance concentration of the hydrophobic material suspension in the second hydrophobic material waterproof layer 6 can be the same as or similar to the effective substance concentration of the hydrophobic material suspension in the first hydrophobic material waterproof layer 4; in the embankment, the effective substance concentration of the hydrophobic material suspension in the first hydrophobic material waterproof layer 4 is greater than or equal to 10%, the effective substance concentration of the hydrophobic material suspension in the second hydrophobic material waterproof layer 6 can be the same as or similar to the effective substance concentration of the hydrophobic material suspension in the first hydrophobic material waterproof layer 4, and the effective substance concentration of the hydrophobic material suspension in the third hydrophobic material waterproof layer 7 can be adjusted according to the soil particle size and The grading condition is appropriately lower than the effective substance concentration of the hydrophobic material suspension of the first hydrophobic material waterproof layer 4; when the roadbed 5 is in a medium-humid environment: in the road cutting, the effective substance concentration of the hydrophobic material suspension of the first hydrophobic material waterproof layer 4 is greater than or equal to 10%, and the effective substance concentration of the hydrophobic material suspension of the second hydrophobic material waterproof layer 6 is the same as or appropriately lower than the effective substance concentration of the hydrophobic material suspension of the first hydrophobic material waterproof layer 4; in the embankment, the effective substance concentration of the hydrophobic material suspension of the first hydrophobic material waterproof layer 4 is greater than or equal to 10%, and the effective substance concentration of the hydrophobic material suspension of the second hydrophobic material waterproof layer 6 is the same as or appropriately lower than the effective substance concentration of the hydrophobic material suspension of the first hydrophobic material waterproof layer 4.

[0072] Although the present invention is described herein with reference to specific embodiments, it should be understood that these embodiments are merely examples of the principles and applications of the present invention. It should therefore be understood that many modifications may be made to the exemplary embodiments and that other arrangements may be devised without departing from the spirit and scope of the present invention as defined by the appended claims. It should be understood that the various dependent claims and features described herein may be combined in a manner different from that described in the original claims. It should also be understood that features described in conjunction with individual embodiments may be used in other described embodiments.

Claims

1. A method for laying a waterproof layer of a road structure based on a hydrophobic material waterproof layer, characterized in that: The road structure based on the hydrophobic material waterproof layer comprises a surface layer (1), a base layer (2), a functional layer (3), a first hydrophobic material waterproof layer (4) and a roadbed (5); the roadbed (5), the functional layer (3), the base layer (2) and the surface layer (1) are laid in sequence from bottom to top, and a first hydrophobic material waterproof layer (4) is spread on the bottom surface of the roadbed (5); A second hydrophobic material waterproof layer (6) is spread on the bottom layer of the functional layer (3); A third water-repellent material waterproof layer (7) is spread on the lower part of the roadbed (5); The first hydrophobic material water-proof layer (4), the second hydrophobic material water-proof layer (6) and the third hydrophobic material water-proof layer (7) are all water-proof layers made of hydrophobic material suspension; The hydrophobic material suspension is an organosilicon suspension; The method comprises the following steps: Step 1: Prepare a hydrophobic material suspension: Use the effective substance of the hydrophobic material as the solute and water as the solvent to prepare a hydrophobic material suspension of a certain concentration that meets the water-blocking requirements of the road environment; Step 2: Spreading waterproof layer: According to the different environments of the roadbed (5), different numbers of waterproof layers are set: (I) When the roadbed (5) is in a wet environment, 1 to 3 layers of waterproofing are set inside the road: (II) When constructing a road cut, 1 to 3 waterproof layers are provided, a first waterproof layer (4) of a hydrophobic material is provided on the bottom surface of a roadbed (5), and a first waterproof layer (4) of a hydrophobic material is spread on the bottom surface of the roadbed (5) in a spraying manner; If the groundwater level in the area where the roadbed (5) passes is high and the roadbed (5) is built at a high height, a second hydrophobic material waterproof layer (6) can be spread on the bottom surface of the functional layer (3) composed of granular materials in the form of spraying according to actual needs to replace a part of the thickness of the granular functional layer (3). The replacement thickness of the second hydrophobic material waterproof layer (6) is less than or equal to 5 cm. The replacement thickness can be estimated by the following formula: h =( x -10)·A (X) Among them, in formula (X): h —Thickness of the functional layer of the alternative granular material (cm); x —Effective substance concentration of the isolation layer (%); A—comprehensive parameter, which is related to factors such as the amount of aquiclude material per unit area, the purity of the aquiclude material, the size of soil particles, gradation, and the location of the groundwater level; If the groundwater level in the area where the roadbed (5) passes is high and the construction height of the roadbed (5) is low, a third hydrophobic material waterproof layer (7) can be spread in the lower part of the roadbed (5) in the form of spraying according to actual needs, and the distance between the third hydrophobic material waterproof layer (7) and the first hydrophobic material waterproof layer (4) is 15 cm to 25 cm; (I-II) When constructing the embankment, 1 to 3 waterproof layers are provided, a first waterproof layer (4) of a hydrophobic material is provided at the bottom surface of the roadbed (5), and a first waterproof layer (4) of a hydrophobic material is spread on the bottom surface of the roadbed (5) in a spraying manner; If the groundwater level in the area where the roadbed (5) passes is high and the construction height of the roadbed (5) is high, a second hydrophobic material waterproof layer (6) can be spread on the bottom surface of the functional layer (3) composed of granular materials in the form of spraying according to actual needs to replace a part of the thickness of the granular functional layer (3). The replacement thickness of the second hydrophobic material waterproof layer (6) is less than or equal to 5 cm, and the replacement thickness can be estimated by formula (X); If the groundwater level in the area where the roadbed (5) passes is high and the construction height of the roadbed (5) is low, a third hydrophobic material waterproof layer (7) can be spread in the lower part of the roadbed (5) in the form of spraying according to actual needs, and the distance between the third hydrophobic material waterproof layer (7) and the first hydrophobic material waterproof layer (4) is 15 cm to 25 cm; (II) When the roadbed (5) is in a medium-humid environment, 1 to 2 layers of waterproofing are set inside the road: (II-I) When constructing a road cut, 1 to 2 waterproof layers are provided, wherein a first waterproof layer (4) of a hydrophobic material is provided on the bottom surface of a roadbed (5), and a first waterproof layer (4) of a hydrophobic material is spread on the bottom surface of the roadbed (5) by spraying; a second waterproof layer (6) of a hydrophobic material can be spread on the bottom surface of a functional layer (3) composed of granular materials by spraying according to the height of the roadbed (5) and actual needs, to replace a portion of the thickness of the functional layer (3) composed of granular materials, and the replacement thickness of the second waterproof layer (6) of a hydrophobic material is less than or equal to 5 cm, and the replacement thickness can be estimated by formula (X); (II-II) When constructing the embankment, 1 to 2 waterproof layers are set, and the first waterproof layer (4) of the hydrophobic material is set at the bottom surface of the roadbed (5). A layer of the first waterproof layer (4) of the hydrophobic material is spread on the bottom surface of the roadbed (5) in the form of spraying; according to the height of the roadbed (5) and actual needs, a layer of the second waterproof layer (6) of the hydrophobic material can be spread on the bottom surface of the functional layer (3) composed of the granular material in the form of spraying to replace a part of the thickness of the functional layer (3) composed of the granular material. The replacement thickness of the second waterproof layer (6) of the hydrophobic material is less than or equal to 5 cm, and its replacement thickness can be estimated by formula (X); When the roadbed (5) is in a humid environment: in the road cut, the effective substance concentration of the hydrophobic material suspension in the first hydrophobic material waterproof layer (4) is greater than or equal to 15%, and the effective substance concentration of the hydrophobic material suspension in the second hydrophobic material waterproof layer (6) is the same as the effective substance concentration of the hydrophobic material suspension in the first hydrophobic material waterproof layer (4); in the embankment, the effective substance concentration of the hydrophobic material suspension in the first hydrophobic material waterproof layer (4) is greater than or equal to 10%, the effective substance concentration of the hydrophobic material suspension in the second hydrophobic material waterproof layer (6) is the same as the effective substance concentration of the hydrophobic material suspension in the first hydrophobic material waterproof layer (4), and the effective substance concentration of the hydrophobic material suspension in the third hydrophobic material waterproof layer (7) can be adjusted according to the soil particle size and The gradation is lower than the effective substance concentration of the hydrophobic material suspension in the first hydrophobic material waterproof layer (4); when the roadbed (5) is in a medium-humid environment: in the road cutting, the effective substance concentration of the hydrophobic material suspension in the first hydrophobic material waterproof layer (4) is greater than or equal to 10%, and the effective substance concentration of the hydrophobic material suspension in the second hydrophobic material waterproof layer (6) is the same as or lower than the effective substance concentration of the hydrophobic material suspension in the first hydrophobic material waterproof layer (4); in the embankment, the effective substance concentration of the hydrophobic material suspension in the first hydrophobic material waterproof layer (4) is greater than or equal to 10%, and the effective substance concentration of the hydrophobic material suspension in the second hydrophobic material waterproof layer (6) is the same as or lower than the effective substance concentration of the hydrophobic material suspension in the first hydrophobic material waterproof layer (4).