A foundation pit reverse construction method steel pipe structure column docking platform and docking method
By using screw and sleeve nut structures in the steel pipe structural column docking platform in the foundation pit reverse process, and combining the calibration of the level and laser level, the problems of low strength and poor stability of the traditional platform materials are solved, and high precision is achieved , safe connection effect.
Patent Information
- Application Number
- CN202010374562.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-05-06
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2040-05-06
AI Technical Summary
The traditional foundation pit reverse process steel pipe structural column docking platform material has low strength, difficulty in controlling verticality and poor stability, which poses safety risks.
Design a butt platform including the upper support frame and the lower support frame, use screw and sleeve nut structure for height adjustment, and accurately calibrate and inspect through level and laser level, combining trapezoidal screw and support steel plate to improve structural strength and stability sex.
It realizes safe, reliable and precise docking of the docking platform, improves docking accuracy and stability, reduces costs, and simplifies the operation process.
Smart Images

Figure CN111424674B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of foundation pit reverse construction method structural column construction, and in particular to a foundation pit reverse construction method steel pipe structural column docking platform and a docking method. Background Art
[0002] With the development of my country's economy, large-scale urban construction of high-rise building foundations and basements, large underground shopping malls, underground parking lots, subway stations, etc. are facing the problem of deep foundation pit engineering. The reverse construction method constructs the underground structure of the deep foundation pit layer by layer from top to bottom. Compared with the traditional deep foundation pit construction method, this unconventional construction has obvious advantages in environmental protection, resource conservation, construction period control and many other aspects.
[0003] When the reverse construction method is used, the underground structure foundation piles are constructed first, and steel pipe structural columns are one of the common forms. When constructing steel pipe structural columns, the accuracy is generally required to reach 1 / 300~1 / 500, and some even require 1 / 1000. In order to ensure that the high-precision requirements are met, full-casing full-rotation drilling rigs are generally used for positioning. Since the height of the full-casing full-rotation drilling rig is about 3.5m, the top elevation of the steel pipe pile is generally below the ground. In order to meet the positioning requirements of the drilling rig hole, the structural column is generally connected to the tool column for positioning during construction.
[0004] In order to meet the high-precision requirements for positioning the structural columns, the steel pipe structural columns and tool columns are generally made in the factory. In actual construction, when the length of the steel pipe structural columns of the foundation pit reverse construction method is too long, for the convenience of transportation, the steel structure factory generally adopts segmented production, and then transports it to the construction site for docking, including the docking between steel pipe columns and between steel pipe columns and tool columns.
[0005] The traditional splicing platform is composed of several splicing frames arranged at a certain interval. The splicing frames are generally made of channel steel and triangular iron, and are set at a distance of about 5m. They can accommodate two steel pipe columns at a time to work on the platform frame; when docking, the elevation of each frame is used, and the side baffles are on the same vertical plane and perpendicular to the horizontal plane of the platform to keep the central axes of the two sections of steel pipes on the same line.
[0006] However, the above technical solution has the following problems:
[0007] 1. Manufacturing materials: The traditional docking platform is welded by ordinary channel steel and triangle iron, which has low material strength, is easy to bend and rust;
[0008] 2. Verticality control: Since the rack is made of welding and has no height adjustment device, it needs to be adjusted by lifting with a crane and adding or removing gaskets. Therefore, the verticality control during the splicing of steel pipe columns depends entirely on the flatness of the ground and the experience of the construction workers.
[0009] 3. Stability: Since traditional racks are not fixed on the ground, when a crane is used to lower steel pipe columns, excessive local force may occur due to the offset of the center of gravity, which may cause the rack to deform and tip over, posing certain safety risks. Summary of the invention
[0010] In order to overcome the deficiencies of the prior art, the present invention aims to provide a safe, reliable and accurate on-site docking platform for steel pipe columns in a reverse construction method of a foundation pit, and summarizes a set of on-site docking and verticality control construction methods.
[0011] The technical solution adopted by the present invention to solve its technical problem is:
[0012] A foundation pit reverse construction steel pipe structure column docking platform, including an upper support frame and a lower support frame, the lower support frame is longitudinally provided with two groups of screw rods, the screw rods are threadedly connected with sleeve nuts, the upper support frame is integrally connected with a steel pipe sleeve, the screw rod part is inserted into the steel pipe sleeve and the lower end of the steel pipe sleeve is pressed against the upper end of the sleeve nut.
[0013] By adopting the above technical solution, the staff rotates the sleeve nut. Since the sleeve nut is threadedly connected to the screw, the sleeve nut can move up and down on the screw, thereby raising or lowering the upper support frame; in actual docking work, the user needs to prepare several docking platforms, and then distribute the docking platforms in a straight line direction, and adjust the upper support frames of all docking platforms to the same preset height, and then use tools such as a crane to lift the steel pipe column and the tool column to the docking platform, so that the steel pipe column and the tool column can be docked under horizontal conditions, thereby avoiding objective non-horizontal factors affecting the verticality control when the steel pipe column and the tool column are docked; in addition, the docking work referred to in the present invention refers to the docking work between steel pipe columns or between steel pipe columns and tool columns.
[0014] Preferably, the screw comprises a threaded section and a non-threaded section, the non-threaded section is located at the upper end of the screw, and the non-threaded section is inserted into a steel pipe sleeve.
[0015] By adopting the above technical solution, the sleeve nut can be rotated to the top of the threaded section at most, but cannot be rotated to the unthreaded section, so that there is always an unthreaded section of the screw that is plugged into and matched with the steel pipe sleeve, avoiding the situation where the staff excessively rotates the sleeve nut and causes the screw to completely separate from the steel pipe sleeve.
[0016] Preferably, a plurality of rotating handles are horizontally connected to the side wall of the sleeve nut, and the screw is a trapezoidal screw with a pitch of 8 mm.
[0017] By adopting the above technical solution, the rotating handle is used to help the staff to rotate the sleeve nut; the use of the trapezoidal screw can improve the bearing capacity of the screw itself.
[0018] Preferably, the lower end of the screw rod is fixedly connected to a supporting steel plate, the supporting steel plate is integrally connected to a lower supporting frame, and the bottom of the lower supporting frame is fixed to a base steel plate.
[0019] By adopting the above technical solution, the supporting steel plate increases the contact area between the screw and the lower supporting frame, and the base steel plate increases the contact area between the lower supporting frame and the ground, both of which are used to evenly disperse the force.
[0020] Preferably, the upper support frame and the lower support frame are I-beam support frames cut and welded from 10 mm thick steel plates, and supporting steel bars are welded between the upper and lower planes of the lower support frame; the base steel plate is made of a steel plate with a size of 750 mm × 1500 mm and a thickness of 15 mm, and a lifting lug is provided on the base steel plate.
[0021] By adopting the above technical solution, the supporting steel bars can improve the structural strength of the lower supporting frame, and the lifting lugs are for facilitating the crane to lift the docking platform.
[0022] A method for butt jointing steel pipe structure columns in a foundation pit reverse construction method, which includes the following steps: processing, manufacturing and transportation of steel pipe columns and tool columns, installation of a butt joint platform, first leveling of the butt joint platform, hoisting and positioning, secondary leveling of the butt joint platform, butt joint inspection and welding and fixing.
[0023] The docking platform installation process includes the following steps:
[0024] S31. The distance between adjacent docking platforms is 5m. The number of docking platforms required is determined according to the length of the steel pipe column.
[0025] S32, defining installation positions according to the number of docking platforms, and placing the docking platforms in the defined installation positions in sequence;
[0026] S33, two expansion screws fixed to the ground are provided at the four corners of the docking platform, and threaded steel is welded to the ends of the two expansion screws to form four fixing fasteners to fix the four corners of the docking platform respectively;
[0027] The first leveling process of the docking platform includes the following steps:
[0028] S41, prepare a level, check the i-angle error of the level, and make sure that the i-angle error of the level does not exceed 15″;
[0029] S42, setting up a level in the middle of the area where all docking platforms are located, placing a level ruler on the upper support frame of each docking platform one by one, and rotating the sleeve nut of the docking platform to adjust all docking platforms to the designed height;
[0030] The secondary leveling process of the docking platform comprises the following steps:
[0031] S61. After the steel pipe column and tool column are hoisted to the docking platform, turn on the level;
[0032] S62. Use a level to recheck all docking platforms, rotate the sleeve nuts of the docking platforms, and adjust all docking platforms to the designed height.
[0033] Preferably, the processing, manufacturing and transportation process of the steel pipe column and the tool column includes the following steps:
[0034] S11. Manufacture steel pipe columns and tool columns according to the structural and verticality requirements of the preset standards;
[0035] S12. If the length of the finished steel pipe column exceeds the transportation requirements, it shall be manufactured in sections and transported to the docking site in sections.
[0036] Preferably, between the processing, manufacturing and transportation process of the steel pipe column and the tool column and the installation process of the docking platform, a docking site hardening treatment process is also included, and the docking site hardening treatment process includes the following steps:
[0037] S21. Clean up the debris and slurry on the surface of the docking site;
[0038] S22, pouring 15cm thick C15 concrete floor, and the flatness of the foundation surface of the floor is controlled within 3mm within 10m, and the error is controlled within 5mm beyond 10m;
[0039] S23. After the floor surface is dry, use paint to mark the installation position of the docking platform.
[0040] Preferably, the hoisting and placing process comprises the following steps:
[0041] S51, installing two wooden dowels on the upper support frame of each docking platform;
[0042] S52, using a crane to respectively lift the steel pipe column and the tool column to be docked between two wooden tenons on the docking platform;
[0043] S53. Place the docking bolts in the alignment holes of the steel pipe column and the tool column, and tighten the docking bolts to 60%.
[0044] Preferably, the docking inspection process includes inspecting the vertical docking accuracy and the horizontal docking accuracy of the steel pipe column;
[0045] The vertical direction docking accuracy inspection includes the following specific steps:
[0046] S71. Set n measuring points along the length direction of the steel pipe column;
[0047] S72. Measure the height of the steel pipe column at each measuring point and record it as H 1 ,
[0048] H 2 , …, H n ;
[0049] S73, use Bessel's formula to calculate the error m 1 , if m 1 ≤1 / 600, then enter the horizontal docking accuracy check. If m 1 >1 / 600, loosen the butt bolts and readjust until m 1 ≤1 / 600;
[0050] The horizontal docking accuracy inspection includes the following specific steps:
[0051] S74, placing two laser levels on both sides of one end of the steel pipe column away from the tool column, and adjusting the positions of the two laser levels until the laser line is parallel to the axis of the steel pipe column, and the height of the laser line is consistent with the height of the axis of the steel pipe column;
[0052] S75. Select n measuring points along the length direction of the steel pipe column at both ends of the steel pipe column and near the butt joint between the steel pipe columns;
[0053] S76. Use a ruler with a horizontal bubble to measure the distance from the pipe wall on both sides of the steel pipe column to the laser lines of the two laser level gauges at the measuring point, and record them as L 1 , L 2 , …, L n and R 1 ,R 2 ,…,R n ;
[0054] S77, according to data L 1 , L 2 , …, L n , use the Bessel formula to calculate the left bending error m 2 , according to the data R 1 ,R 2 ,…,R n , use the Bessel formula to calculate the right bending error m 3 ;
[0055] S78, if m 2 and m 3 If the m is less than or equal to 1 / 600, the welding process will begin. 2 and m 3If any of them is greater than 1 / 600, loosen the butt bolts and readjust until m 2 and m 3 Are all less than or equal to 1 / 600.
[0056] The beneficial effects of the present invention are:
[0057] 1. Simple production and easy operation
[0058] The docking platform has a simple structure design, is easy to manufacture, and is convenient to lift, disassemble and operate;
[0059] 2. High positioning efficiency
[0060] Only need to manually adjust the lifting screw device to quickly complete the docking adjustment, which is simple and easy to operate with high positioning efficiency;
[0061] 3. High docking accuracy
[0062] Manually turn the sleeve nut to accurately control the height of the upper support frame. During the docking process, a precise level and laser level can be used to check and inspect the verticality. By adjusting the deviation, it can ensure that the docking meets the verticality requirements.
[0063] 4. Safe and reliable
[0064] The base of the docking platform is placed on a hardened ground, which can effectively prevent structural column deviation and accidental safety accidents caused by uneven settlement;
[0065] The base is equipped with a 10mm thick base steel plate, and is fixed with expansion screws and threaded steel to prevent the platform from sliding under force and improve the safety and stability of the platform; the manual screw lift uses a trapezoidal thread screw with a self-locking function, and a 95mm long non-threaded part is set at the upper end of the trapezoidal screw thread screw, which can effectively control the danger of platform instability caused by excessive rise of the regulator;
[0066] 5. Low overall cost
[0067] The docking platform is homemade, the materials are economical, and only 2 to 3 people are needed to operate it. The platform is easy to disassemble and assemble, can be reused, and has a low overall cost. BRIEF DESCRIPTION OF THE DRAWINGS
[0068] The present invention is further described below in conjunction with the accompanying drawings and embodiments.
[0069] Figure 1 It is a structural schematic diagram of the docking platform in the present invention;
[0070] Figure 2 It is a schematic diagram of the structure of the screw rod and the sleeve nut in the present invention;
[0071] Figure 3 This is the front view of the present invention when checking the vertical docking accuracy;
[0072] Figure 4 This is a top view of the present invention when checking the horizontal docking accuracy.
[0073] The descriptions of the reference numerals in the figures are as follows:
[0074] 1. Docking platform; 101. Upper support frame; 102. Lower support frame; 103. Screw; 104. Sleeve nut; 105. Steel pipe sleeve; 106. Rotating handle; 107. Support steel plate; 108. Base steel plate; 109. Support steel bar; 110. Lifting lug; 2. Steel pipe column; 3. Tool column; 4. Laser level. DETAILED DESCRIPTION
[0075] The following will clearly and completely describe the concept, specific structure and technical effects of the present invention in combination with the embodiments and drawings, so as to fully understand the purpose, characteristics and effects of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, other embodiments obtained by technicians in this field without creative work are all within the scope of protection of the present invention. In addition, all the connection / connection relationships involved in the patent do not refer to the direct connection of components, but refer to the formation of a better connection structure by adding or reducing connection accessories according to the specific implementation situation. The various technical features in the invention can be combined interchangeably without conflicting with each other.
[0076] The traditional way to complete the docking work of steel columns and tool columns is to use an ordinary docking platform. It is necessary to use tools such as gaskets and the construction experience of the staff to complete the adjustment of the horizontality of all docking platforms. In addition, it is easy to produce excessive local force due to the offset of the center of gravity, which can easily cause the frame to deform and tip over.
[0077] In order to solve the above technical problems, the present invention provides a foundation pit reverse construction method steel pipe structure column docking platform and a foundation pit reverse construction method steel pipe structure column docking method.
[0078] A foundation pit reverse construction steel pipe structure column docking platform, such as Figure 1 and Figure 2 As shown, it includes an upper support frame 101 and a lower support frame 102. The lower support frame 102 is longitudinally provided with two sets of screw rods 103. The screw rods 103 are threadedly connected with sleeve nuts 104. The upper support frame 101 is integrally connected with a steel pipe sleeve 105. The screw rods 103 are partially inserted into the steel pipe sleeve 105 and the lower end of the steel pipe sleeve 105 is pressed against the upper end of the sleeve nut 104.
[0079] Specific working principle: the staff rotates the sleeve nut 104. Since the sleeve nut 104 is threadedly connected to the screw rod 103, the sleeve nut 104 can move up and down on the screw rod 103, thereby raising or lowering the upper support frame 101; in actual docking work, the user needs to prepare several docking platforms 1, and then distribute the docking platforms 1 in a straight line direction, and adjust the upper support frames 101 of all docking platforms 1 to the same preset height, and then use tools such as a crane to lift the steel pipe column 2 and the tool column 3 to the docking platform 1, so that the steel pipe column 2 and the tool column 3 can be docked under horizontal conditions, thereby avoiding objective non-horizontal factors affecting the verticality control of the steel pipe column 2 and the tool column 3 when docking; in addition, the docking work referred to in the present invention refers to the docking work between steel pipe columns 2 and steel pipe columns 2 or between steel pipe columns 2 and tool columns 3.
[0080] The screw 103 includes a threaded section and a non-threaded section. The non-threaded section is located at the upper end of the screw 103, and the non-threaded section is inserted into the steel pipe sleeve 105; the sleeve nut 104 can at most be rotated to the top of the threaded section, but cannot be rotated to the non-threaded section, so that there is always an non-threaded section of the screw 103 that is plugged into the steel pipe sleeve 105, avoiding the situation where the staff excessively rotates the sleeve nut 104 and causes the screw 103 to completely separate from the steel pipe sleeve 105.
[0081] The side wall of the sleeve nut 104 is horizontally connected with a plurality of rotating handles 106 . The screw rod 103 is a trapezoidal screw rod 103 , and its pitch is 8 mm. The rotating handle 106 is used to help the staff rotate the sleeve nut 104 . The use of the trapezoidal screw rod 103 can improve the bearing capacity of the screw rod 103 itself.
[0082] The lower end of the screw rod 103 is fixedly connected to a supporting steel plate 107, and the supporting steel plate 107 is integrally connected to the lower supporting frame 102, and the bottom of the lower supporting frame 102 is fixed on a base steel plate 108; the supporting steel plate 107 increases the contact area between the screw rod 103 and the lower supporting frame 102, and the base steel plate 108 increases the contact area between the lower supporting frame 102 and the ground, both of which are used to evenly disperse the force.
[0083] The upper support frame 101 and the lower support frame 102 are both I-beam support frames cut and welded from 10 mm thick steel plates, and support steel bars 109 are welded between the upper and lower planes of the lower support frame 102; the base steel plate 108 is made of a steel plate with a size of 750 mm × 1500 mm and a thickness of 15 mm, and a lifting lug 110 is provided on the base steel plate 108. The support steel bars 109 can improve the structural strength of the lower support frame 102, and the lifting lug 110 is to facilitate the crane to lift the docking platform 1.
[0084] The docking platform 1 provided by the present invention can be manufactured at the docking site, and the used parts are all available for purchase. Therefore, the present invention specifically provides the specifications of each part.
[0085] 1. Base
[0086] (1) The base includes a base steel plate 108, an I-beam lower support frame 102 and a lifting lug 110. The base steel plate 108 is welded to the lower support frame 102, and mainly serves as a bearing structure and a supporting and stabilizing function at the bottom of the docking platform 1.
[0087] (2) Base steel plate 108: Made of 15 mm steel plate with a size of 750 mm × 1500 mm, it provides a supporting force foundation for the platform.
[0088] (3) Lower support frame 102: It is a non-standard I-beam, cut and welded from a 10 mm thick steel plate, with a plane size of 165 mm × 90 mm (length × width); in order to increase the bearing capacity of the lower part of the adjusting bolt structure, a supporting steel bar 109 (threaded steel bar Φ25 mm, length: 145 mm) is welded below the center of the supporting steel plate 107.
[0089] (4) Lifting lug 110: Provides lashing for lifting and handling, and is cut and welded from 10 mm steel plate.
[0090] 2. Lifting structure
[0091] (1) The lifting structure includes a screw rod 103 with a supporting base plate, a sleeve nut 104 with a rotating handle 106, and an I-beam upper support frame 101 with a steel pipe sleeve 105.
[0092] (2) Screw 103 with supporting base plate: The material of screw 103 is Tr55×8 alloy tool steel, with a length of 225 mm, a nominal diameter of 55 mm, and a pitch of 8 mm. The upper end of screw 103 is set as a non-threaded section, and the length of the non-threaded section is 95 mm to ensure the stability and safety of the screw 103 and the upper support frame 101. The supporting steel plate 107 is cut from a 20 mm thick steel plate and has a size of 155 mm×150 mm, which provides support for screw 103. Screw 103 is welded at the center of the supporting steel plate 107 to evenly disperse the force on the bolt.
[0093] (3) Sleeve nut 104 with rotating handle 106: The rotating handle 106 is three Φ12mm threaded steel bars, which are welded to the side wall of the sleeve nut 104 at equal intervals. The sleeve nut 104 is made of alloy tool steel, with a trapezoidal thread with a nominal diameter of 55mm and a pitch of 8mm, which meets the self-locking condition, an outer diameter of 80mm, and a sleeve height of 60mm.
[0094] (4) I-beam upper support frame 101 with steel pipe sleeve 105: It is cut and welded from 10 mm steel plate, with dimensions of waist height 165 mm × leg width 150 mm × waist thickness 10 mm.
[0095] In order to improve the docking accuracy of the docking work, the present invention also provides a foundation pit reverse construction method for steel pipe structure columns.
[0096] A method for butt jointing steel pipe structure columns in a foundation pit reverse construction method, which sequentially comprises a processing, manufacturing and transportation process S1 of steel pipe columns and tool columns, a hardening treatment process S2 of a butt joint site, a butt joint platform installation process S3, a first leveling process S4 of a butt joint platform, a hoisting and positioning process S5, a secondary leveling process S6 of a butt joint platform, a butt joint inspection process S7 and a welding and fixing process S8.
[0097] 1. Processing, manufacturing and transportation of steel pipe columns and tool columns S1
[0098] This process includes the following steps:
[0099] S11, manufacturing the steel pipe column 2 and the tool column 3 according to the requirements of the structure and verticality in the preset standards;
[0100] S12. If the length of the finished steel pipe column 2 exceeds the transportation requirements, it is manufactured in sections and transported in sections to the docking site.
[0101] In addition, after the steel pipe column 2 is transported to the docking site, it is stacked in the designated area according to the construction zoning map, stacked in categories, and laid flat in a single layer on a stand, and fixed with wooden dowels to prevent rolling.
[0102] 2. Hardening treatment process S2
[0103] This process includes the following steps:
[0104] S21. Clean up the debris and slurry on the surface of the docking site;
[0105] S22, pouring 15cm thick C15 concrete floor, and the flatness of the foundation surface of the floor is controlled within 3mm within 10m, and within 5mm beyond 10m;
[0106] S23. After the floor surface is dry, use paint to mark the installation position of the docking platform 1.
[0107] 3. Docking platform installation process S3
[0108] This process includes the following steps:
[0109] S31. The distance between adjacent docking platforms 1 is 5m. The number of required docking platforms 1 is determined according to the length of the steel pipe column 2.
[0110] S32, defining installation positions according to the number of docking platforms 1, and placing the docking platforms 1 in the defined installation positions in sequence;
[0111] S33. Two expansion screws fixed to the ground are provided at the four corners of the docking platform 1, and threaded steel is welded to the ends of the two expansion screws to form four fixing fasteners to fix the four corners of the base steel plate 108 respectively.
[0112] The expansion screws and threaded steel bars in step S33 can be Figure 1 It can be seen at the four corners of the base steel plate 108.
[0113] 4. Docking platform initial leveling process S4
[0114] This process includes the following steps:
[0115] S41, prepare a level, check the i-angle error of the level, and make sure that the i-angle error of the level does not exceed 15″;
[0116] S42, set up a level in the middle of the area where all docking platforms 1 are located, place a level ruler on the upper support frame 101 of each docking platform 1 one by one, and rotate the sleeve nut 104 of the docking platform 1 to adjust all docking platforms 1 to the designed height.
[0117] 5. Lifting and positioning process S5
[0118] This process includes the following steps:
[0119] S51, installing two wooden dowels on the upper support frame 101 of each docking platform 1;
[0120] S52, using a crane to respectively lift the steel pipe column 2 and the tool column 3 to be docked between two wooden tenons of the docking platform 1;
[0121] S53, placing the butt bolts in the alignment holes of the steel pipe column 2 and the tool column 3, and tightening the butt bolts to 60%.
[0122] 6. Secondary leveling process of docking platform S6
[0123] This process includes the following steps:
[0124] S61, after the steel pipe column 2 and the tool column 3 are hoisted to the docking platform 1, turn on the level;
[0125] S62. Use a level to check all docking platforms 1 again, rotate the sleeve nuts 104 of the docking platforms 1, and adjust all docking platforms 1 to the designed height.
[0126] VII. Docking Inspection Process S7
[0127] This process includes vertical and horizontal docking accuracy checks on the steel pipe column 2.
[0128] like Figure 3 As shown, the vertical docking accuracy inspection includes the following specific steps:
[0129] S71, setting n measuring points along the length direction of the steel pipe column 2;
[0130] S72. Measure the height of the steel pipe column 2 at each measuring point and record them as H 1 , H 2 , …, H n ;
[0131] S73, use Bessel's formula to calculate the error m 1 , if m 1 ≤1 / 600, then enter the horizontal docking accuracy check. If m 1 >1 / 600, loosen the butt bolts and readjust until m 1 ≤1 / 600;
[0132] like Figure 4 As shown in the figure, the horizontal docking accuracy inspection includes the following specific steps:
[0133] S74, placing two laser levels 4 on both sides of the end of the steel pipe column 2 away from the tool column 3, and adjusting the positions of the two laser levels 4 so that the laser lines emitted by them are parallel to the axis of the steel pipe column 2, and the height of the laser lines is consistent with the height of the axis of the steel pipe column 2;
[0134] S75, along the length direction of the steel pipe column 2, at both ends of the steel pipe column 2 and near the butt joint position between the steel pipe column 2 and the steel pipe column 2, select n measuring points;
[0135] S76. Use a ruler with a horizontal bubble to measure the distance from the pipe wall on both sides of the steel pipe column 2 to the laser lines of the two laser level meters 4 at the measuring point, and record them as L 1 , L 2 , …, L n and R 1 ,R 2 ,…,R n ;
[0136] S77, according to data L 1 , L 2 , …, L n , use the Bessel formula to calculate the left bending error m 2 , according to the data R 1 ,R 2 ,…,R n, use the Bessel formula to calculate the right bending error m 3 ;
[0137] S78, if m 2 and m 3 If the m is less than or equal to 1 / 600, the welding process will begin. 2 and m 3 If any of them is greater than 1 / 600, loosen the butt bolts and readjust until m 2 and m 3 Are all less than or equal to 1 / 600.
[0138] 8. Welding and fixing process S8
[0139] This process is carried out after the docking inspection process and can be fixed by conventional welding. It is prohibited to put any weight on the docking platform during welding.
[0140] The above is a specific description of the preferred implementation of the present invention, but the invention is not limited to the embodiments. Those skilled in the art can make various equivalent modifications or substitutions without violating the spirit of the present invention. These equivalent modifications or substitutions are all included in the scope defined by the claims of this application.
Claims
1. A method for butt jointing steel pipe structure columns in a foundation pit reverse construction method, characterized in that: It includes the processing, manufacturing and transportation process of the steel pipe column and the tool column, the installation process of the docking platform, the first leveling process of the docking platform, the hoisting process, the secondary leveling process of the docking platform, the docking inspection process and the welding and fixing process; The docking platform installation process includes the following steps: S31. The distance between adjacent docking platforms is 5m. The number of docking platforms required is determined according to the length of the steel pipe column. S32, defining installation positions according to the number of docking platforms, and placing the docking platforms in the defined installation positions in sequence; S33, two expansion screws fixed to the ground are provided at the four corners of the docking platform, and threaded steel is welded to the ends of the two expansion screws to form four fixing fasteners to fix the four corners of the docking platform respectively; The first leveling process of the docking platform includes the following steps: S41, prepare a level, check the i-angle error of the level, and make sure that the i-angle error of the level does not exceed 15″; S42, setting up a level in the middle of the area where all docking platforms are located, placing a level ruler on the upper support frame of each docking platform one by one, and rotating the sleeve nut of the docking platform to adjust all docking platforms to the designed height; The secondary leveling process of the docking platform comprises the following steps: S61. After the steel pipe column and tool column are hoisted to the docking platform, turn on the level; S62. Use a level to recheck all docking platforms, rotate the sleeve nuts of the docking platforms, and adjust all docking platforms to the designed height; The docking inspection process includes vertical docking accuracy inspection and horizontal docking accuracy inspection of the steel pipe column; The vertical direction docking accuracy inspection includes the following specific steps: S71. Set n measuring points along the length direction of the steel pipe column; S72. Measure the height of the steel pipe column at each measuring point and record them in turn as , , …, ; S73, using Bessel's formula to obtain the error ,like , then enter the horizontal docking accuracy check, if , then loosen the docking bolts and readjust until ; The horizontal docking accuracy inspection includes the following specific steps: S74, placing two laser levels on both sides of one end of the steel pipe column away from the tool column, and adjusting the positions of the two laser levels until the laser line is parallel to the axis of the steel pipe column, and the height of the laser line is consistent with the height of the axis of the steel pipe column; S75. Select n measuring points along the length direction of the steel pipe column at both ends of the steel pipe column and near the butt joint between the steel pipe columns; S76. Use a ruler with a level bubble to measure the distance from the pipe wall on both sides of the steel pipe column to the laser lines of the two laser level gauges at the measuring point, and record them as , , …, and , ,…, ; S77, according to the data , , …, , the left bending error is obtained by using the Bessel formula , according to the data , ,…, , the right bending error is obtained by using the Bessel formula ; S78, if and If the values are less than or equal to 1 / 600, the welding process will begin. and If any of them is greater than 1 / 600, loosen the butt bolts and readjust until and All less than or equal to 1 / 600; The docking platform includes an upper support frame and a lower support frame. The lower support frame is longitudinally provided with two sets of screws, and the screws are threadedly connected with sleeve nuts. The upper support frame is integrally connected with a steel pipe sleeve. The screw portion is inserted into the steel pipe sleeve and the lower end of the steel pipe sleeve is pressed against the upper end of the sleeve nut.
2. The method for butt jointing steel pipe structure columns in a foundation pit reverse construction method according to claim 1 is characterized in that: The processing, manufacturing and transportation process of the steel pipe column and tool column includes the following steps: S11. Manufacture steel pipe columns and tool columns according to the structural and verticality requirements of the preset standards; S12. If the length of the finished steel pipe column exceeds the transportation requirements, it shall be manufactured in sections and transported to the docking site in sections.
3. The method for butt jointing steel pipe structure columns in a foundation pit reverse construction method according to claim 1 is characterized in that: Between the processing, manufacturing and transportation process of the steel pipe column and the tool column and the installation process of the docking platform, a docking site hardening treatment process is also included, and the docking site hardening treatment process includes the following steps: S21. Clean up the debris and slurry on the surface of the docking site; S22, pouring 15cm thick C15 concrete floor, and the flatness of the foundation surface of the floor is controlled within 3mm within 10m, and the error is controlled within 5mm beyond 10m; S23. After the floor surface is dry, use paint to mark the installation position of the docking platform.
4. The method for butt jointing steel pipe structure columns in a foundation pit reverse construction method according to claim 1, characterized in that: The hoisting and placing process comprises the following steps: S51, installing two wooden dowels on the upper support frame of each docking platform; S52, using a crane to respectively lift the steel pipe column and the tool column to be docked between two wooden tenons on the docking platform; S53. Place the docking bolts in the alignment holes of the steel pipe column and the tool column, and tighten the docking bolts to 60%.
5. The method for butt jointing steel pipe structure columns in a foundation pit reverse construction method according to claim 1, characterized in that: The screw rod comprises a threaded section and a non-threaded section, wherein the non-threaded section is located at the upper end of the screw rod and is inserted into a steel pipe sleeve.
6. The method for butt jointing steel pipe structure columns in a foundation pit reverse construction method according to claim 1, characterized in that: The side wall of the sleeve nut is horizontally connected with a plurality of rotating handles. The screw rod is a trapezoidal screw rod, and its pitch is 8 mm.
7. The method for butt jointing steel pipe structure columns in a foundation pit reverse construction method according to claim 1, characterized in that: The lower end of the screw rod is fixedly connected to a supporting steel plate, the supporting steel plate is integrally connected to the lower supporting frame, and the bottom of the lower supporting frame is fixed to the base steel plate.
8. The method for butt jointing steel pipe structure columns in a foundation pit reverse construction method according to claim 7, characterized in that: The upper support frame and the lower support frame are both I-beam support frames cut and welded from 10mm thick steel plates, and supporting steel bars are welded between the upper and lower planes of the lower support frame; the base steel plate is made of a steel plate with a size of 750mm×1500mm and a thickness of 15mm, and a lifting lug is provided on the base steel plate.