Method and apparatus for installing steel sheet piles in large diameter boulder and sandstone formations
By using a rotary drilling rig and a vibrating hammer to guide the hole, combined with a static pressure pile implanter and a steel sheet pile movable sampler, the problem of slow insertion speed and high construction safety risk of steel sheet piles in large-diameter boulder and sandstone strata has been solved, achieving high efficiency and high safety risk. Safe steel sheet pile construction significantly increases construction speed and reduces costs.
Patent Information
- Application Number
- CN202010526041.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-06-11
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2040-06-11
AI Technical Summary
In large-diameter boulder and sandstone strata, the insertion speed of steel sheet piles is slow and inefficient, and can easily lead to drill pipe wear and high construction safety risks. The existing static pressure pile planting machine has unsatisfactory construction results in such strata.
A rotary drilling rig and a vibrating hammer are used to guide the hole to form a steel casing, and then a static pressure pile planting machine and a steel sheet pile movable straightener are used to insert the steel sheet pile vertically through clay backfill and static load to ensure the stop of the steel sheet pile. Water effects and verticality.
Significantly improves the insertion speed and efficiency of steel sheet piles in large-diameter boulder and sandstone strata, reducing construction safety risks. The breakthrough time of a single pile is reduced from 3 hours to 20 minutes, the time for planting piles in place is about 70 minutes, and the construction speed is increased by 9 times. , the cost is reduced by 60%.
Smart Images

Figure CN111608192B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a method and a device for installing steel sheet piles in large-diameter boulder and sandstone formations. Background Art
[0002] Steel sheet piles are a type of support structure formed by continuous and tight interlocking, while cofferdams are temporary closed spaces surrounded by steel sheet piles, which can prevent water and soil from flowing in and ensure the smooth development of engineering construction inside the cofferdam (such as bridge piers or caps, etc.). Usually bridge piers are set below the water surface or riverbed, and cofferdams made of steel sheet piles can create ideal conditions for underwater cap construction. Steel sheet pile cofferdams have the advantages of high strength, good waterproof performance, variable shapes, and the ability to be constructed in deep water and reused.
[0003] The steel sheet piles for underwater cofferdams are usually driven by traditional pile drivers, which use their impact kinetic energy to penetrate the pile foundation. However, the technology of the pile driver cannot guarantee the water-stopping effect of the steel sheet piles and their verticality requirements. In addition, the driving speed of the steel sheet piles is slow, the rock layer at the bottom of the steel sheet piles is easily damaged, the hole skipping speed is slow, and the construction efficiency is low.
[0004] The static pressure pile driver is small, vibration-free and noise-free, and can effectively solve the problems of vibration and noise caused during the driving of cofferdam steel sheet piles.
[0005] However, under special geological conditions, it is difficult to implant steel sheet piles using the above process. For example, the G316 River Valley Hanjiang Highway Bridge and Connection Engineering PPP Project has a total length of 4701.5 m The main channel bridge is 420 meters long. m , the main bridge span combination is (110+200+110) m For some cable-stayed main bridges, the main bridge pier is located in the middle of the Han River. The main bridge pier is constructed with steel sheet pile cofferdam. The geological conditions in the Han River basin are complex, with thick pebble layers and many large-diameter boulders. According to drilling revelations, the rock (soil) layers in the main pier site area can be divided from top to bottom into: pebbles, boulders (Q4al+pl), strongly weathered fine sandstone (E2F), moderately weathered muddy siltstone (E2F), and strongly weathered muddy siltstone (E2F). That is, the strata in the main pier site area of the River Valley Bridge project are mainly composed of large-diameter boulders and sandstones. There are a large number of boulders in the main bridge site area, and the boulders generally have a particle size of 25.00 to 45.00. cm Between, up to 50.00 cm , content is about 45%, layer thickness is 3.5 m ~4.1 mIt is difficult for static pressure pile drivers to operate in this type of large boulder formation. Whether using a spiral drill rod to drill and press in or using a water jet and spiral drill device to press in, the effect of static pressure pile drivers is not ideal. It takes 3 hours for a single pile to break through the boulder layer, and it cannot play its advantages in dense sandstone. It is also very easy to cause serious wear of the drill rod and drill teeth, air compressor failure, and de-soldering of the auxiliary welding between the steel sheet pile and the drill rod, resulting in failure to plant piles and low efficiency.
[0006] Therefore, there is an urgent need for a solution and device that can effectively install steel sheet piles in large diameter boulder and sandstone formations. Summary of the invention
[0007] The purpose of the present invention is to design a method and device for installing steel sheet piles in large-diameter boulder and sandstone formations, which can improve the implantation speed and efficiency of steel sheet piles in large-diameter boulder and sandstone formations and reduce the safety risk of cofferdam construction.
[0008] For this purpose, a device for installing steel sheet piles in large-diameter boulder and sandstone formations is disclosed, comprising a casing construction measurement and positioning device, a steel sheet pile movable sample corrector and a mobile working platform.
[0009] The tube construction measurement and positioning device is: a cross-shaped bracket is provided at the upper end of a square frame, the outer ends of the lower end surface of the cross-shaped bracket are respectively fixed to the middle of the four sides of the corresponding square frame, a bolt for prism connection is provided at the center point of the cross-shaped bracket, the lower parts of the four outer ends of the cross-shaped bracket are respectively welded to the midpoints of the four sides of the square frame, the axis of the bolt for prism connection coincides with the axis of the steel casing, and the middle of the inner side of the square frame is clamped on the outer wall of the upper end of the steel casing. The inner side of the square frame has the same length, and the lengths of the sides of the cross-shaped bracket are the same.
[0010] The steel sheet pile movable sample corrector is as follows: a longitudinal slide is arranged in a longitudinally arranged base, a guide groove channel is arranged at the front end of the base corresponding to the slide, the rear part of the slider is slidably fitted in the slide, and the front end of the slider passes through the guide groove channel and is located at the front end of the base. The bottom of the top pressure hydraulic cylinder is transversely fixed to the front end of the slider, and a through hole is arranged at the upper end of the base in the middle of the guide groove channel for the lifting hydraulic rod to slide through, the lifting hydraulic cylinder is fixed on the upper end surface of the base, and the front end of the lifting hydraulic rod passes through the through hole and is fixed to the middle of the upper end of the slider located in the slide, and two base connecting ears are arranged at intervals on both sides of the base.
[0011] The mobile working platform is: two I-beams arranged horizontally at a distance from each other are connected to each other through several steel columns and oblique steel columns arranged longitudinally at a distance from each other, and the middle parts of the outer ends of two fixed hoops arranged at a distance from each other are respectively fixed to one end of two horizontal I-beams to form a longitudinal support frame. The movable hoop and the fixed hoop are semi-cylindrical. One end of the movable hoop is connected to one end of the fixed hoop by a hinge, and the other end of the movable hoop is correspondingly provided with a docking ear to the other end of the fixed hoop. The longitudinal support frame is connected to the docking ears on the movable and fixed hoops by the third connecting bolt and the fixing nut so that the movable and fixed hoops are fixed to the steel trestle support piles. The two longitudinal support frames are respectively fixed to two adjacent steel trestle support piles by the movable and fixed hoops. The two ends of the two longitudinal support frames are respectively fixed to the two ends of the left and right horizontal support frames by a docking flange and a first connecting bolt. A fixing seat is provided at the middle of the inner side of the two longitudinal support frames and the left and right transverse support frames, and two fixing seat connecting ears are provided at intervals on both sides of the fixing seat, and the two sides of the base are fixed to the fixing seat connecting ears through the base connecting ears and the second connecting bolts, respectively. The upper ends of the two longitudinal support frames and the left and right transverse support frames are provided with a workbench. The inner wall diameter of the movable clamp and the fixed clamp after buckling is adapted to the diameter of the steel trestle support pile, and the inner peripheral wall of the movable clamp and the fixed clamp is provided with a rubber anti-slip layer.
[0012] A method for installing steel sheet piles in large-diameter boulder and sandstone formations using the device comprises the following steps:
[0013] (1) A steel trestle is constructed along the outer side of the designed cofferdam steel sheet piles to form a construction platform for the steel sheet piles on the river surface.
[0014] (2) Prepare on the construction platform a rotary drilling rig, a vibratory hammer, a static pressure pile driver and supporting equipment, two crawler cranes, steel casing and drill bits for the rotary drilling rig, steel sheet piles for the static pressure pile driver, casing construction measurement and positioning equipment, a mobile working platform and a movable sample calibrator for the steel sheet piles.
[0015] (3) The mobile working platform is installed on the inner side of the construction platform using two adjacent steel trestle support piles of the construction platform as support.
[0016] (4) Use a steel guide frame to install a steel casing with a diameter of 1.2 m along the designed cofferdam steel sheet pile position, and use a steel casing construction measurement and positioning device to detect the verticality of the installed steel casing in real time. The steel casing is installed by skip-hole installation and excavation.
[0017] (5) A rotary drilling rig with a drill bit of 1.0 m and a vibratory hammer of model DZ90 are used to excavate the boulder layer at the lower end of the steel casing and to drill a hole to the lower end of the steel casing through the boulder layer.
[0018] (a) First, use a vibrating hammer to hit the upper end surface of the steel casing and record the bottom elevation of the steel casing in detail.
[0019] (b) A rotary drilling rig is then used to drill into the steel casing to a rock layer no more than 20 cm outside the bottom of the steel casing to reduce the friction resistance of the side wall of the steel casing.
[0020] (c) Then continue to use a vibrating hammer to hit the upper end of the steel casing to move the steel casing down to the lead hole.
[0021] (d) Repeat steps (a) to (c) until the lower end of the steel casing passes through the boulder layer and enters the lower rock layer.
[0022] (6) Backfilling with clay: After the completion of the borehole, backfill clay into the space between the bottom surface of the steel casing and the middle space 0.5 m above the riverbed elevation outside the casing. The clay is transported in sandbags, backfilled manually and compacted with a rotary drill to keep the elevation of the backfilled clay 0.5 m higher than the riverbed elevation outside the casing.
[0023] (7) Removal of steel casing and initial load-bearing of static pressure pile driver: Remove the pressed steel casing, leaving a section that allows the reaction base plate at the bottom of the static pressure pile driver to clamp the fixed pressed steel casing. The reaction base plate of the static pressure pile driver clamps the upper ends of several fixed pressed steel casings, and uses the static load to implant a steel sheet pile along the backfill clay line.
[0024] (8) Use a static pressure pile driver to carry out the steel sheet pile planting operation along the backfill clay line until the static pressure pile driver can switch to clamp several steel sheet piles that have been pressed into the ground and press the next pile into the ground to complete the cofferdam steel sheet pile line, and then remove the remaining section of the pressed steel casing.
[0025] (9) Use a static pressure pile driver to carry out the steel sheet pile planting operation along the backfill clay line until the steel sheet pile cofferdam is completed. During the steel sheet pile pressing process, use a steel sheet pile movable straightener on the mobile working platform to straighten the inclined steel sheet pile. The steel sheet pile movable straightener presses the upper end of the steel sheet pile in the inclined direction until the steel sheet pile is in the correct position.
[0026] (10) Separate the movable and fixed clamps from the steel trestle support piles, and move the mobile work platform to the next construction pile position with the help of a crane. Repeat steps (1) to (9) until the steel sheet pile cofferdam is completed.
[0027] The diameter of the steel casing is 1.2m, and the diameter of the installed steel casing is the same as the center line of the designed cofferdam steel sheet pile.
[0028] The skip-hole installation is that the distance between the center points of adjacent steel casings installed for the first time is 1.8m, the steel casing installed for the second time is located in the middle of the two adjacent steel casings installed for the first time, and the peripheries of the adjacent steel casings installed for the first time and the second time overlap by 0.3m.
[0029] The method of using a steel sheet pile movable corrector to correct the inclination of the steel sheet pile during the steel sheet pile pressing process is:
[0030] (a) If the steel sheet pile is tilted outward from the cofferdam, then: the base of the steel sheet pile movable sample corrector is fixed on the fixed seat of the mobile working platform opposite to the steel sheet pile tilted outward from the cofferdam, the ejection hydraulic rod of the steel sheet pile movable sample corrector is held at the middle of the upper end of the steel sheet pile tilted outward or at the middle of the upper end of the pressure head of the static pressure pile driver, and the steel sheet pile is implanted by the pressure head of the static pressure pile driver, the movable hydraulic cylinder and the ejection hydraulic cylinder are started, and the deviation is slowly corrected by the slight displacement of the steel sheet pile pressed by the ejection hydraulic rod, and the steel sheet pile is implanted and adjusted at the same time, and the tilted steel sheet pile is corrected under the pressure of the ejection hydraulic cylinder of the steel sheet pile movable sample corrector.
[0031] (b) If the steel sheet pile is tilted inwardly toward the cofferdam, then: the base of the movable steel sheet pile straightener is fixed on the fixed seat of the mobile working platform opposite to the steel sheet pile tilted inwardly toward the cofferdam, the ejection hydraulic rod of the movable steel sheet pile straightener is held at the middle of the upper end of the inwardly tilted steel sheet pile or at the middle of the upper end of the pressure head of the static pressure pile driver, and as the pressure head of the static pressure pile driver implants the steel sheet pile, the movable hydraulic cylinder and the ejection hydraulic cylinder are started, and the deviation is slowly corrected by the slight displacement of the steel sheet pile pressed by the ejection hydraulic rod, and the steel sheet pile is implanted and adjusted at the same time, and the tilted steel sheet pile is corrected under the pressure of the ejection hydraulic cylinder of the movable steel sheet pile straightener.
[0032] (c) If the steel sheet pile is tilted in the forward direction, then: the base of the steel sheet pile movable sample corrector is fixed on the fixed seat of the mobile working platform opposite to the steel sheet pile in the forward direction, the ejection hydraulic rod of the steel sheet pile movable sample corrector is held at the middle of the upper end of the steel sheet pile in the forward direction or at the middle of the upper end of the pressure head of the static pressure pile driver, and as the pressure head of the static pressure pile driver implants the steel sheet pile, the movable hydraulic cylinder and the ejection hydraulic cylinder are started, and the deviation is slowly corrected by the slight displacement of the steel sheet pile pressed by the ejection hydraulic rod, and the steel sheet pile is implanted and adjusted at the same time, and the inclined steel sheet pile is corrected under the pressure of the ejection hydraulic cylinder of the steel sheet pile movable sample corrector.
[0033] The above device and method achieve the purpose of the present invention.
[0034] The present invention can improve the speed and efficiency of implanting steel sheet piles in large-diameter boulder and sandstone formations, and reduce the safety risk of cofferdam construction.
[0035] Compared with the prior art, the present invention has the following advantages and positive effects:
[0036] (1) The present invention utilizes and maximizes the respective advantages of rotary drilling rigs, vibratory hammers and static pressure pile drivers in forming underwater steel sheet pile cofferdams in large-diameter boulder and sandstone formations. The rotary drilling rig and vibratory hammer are first used to pass through the underwater large-diameter boulder layer, and then the static pressure pile driver is used to statically press the steel sheet piles to form the cofferdam. The impact kinetic energy of the rotary drilling rig and the vibratory hammer is used to achieve the pile foundation penetrating the underwater large-diameter boulder layer. The static pressure pile driver is then used to statically press the steel sheet piles and the deviation correction method and equipment are used to correct the inclination of the steel sheet piles, thereby ensuring the water-stopping effect of the steel sheet pile cofferdam and the verticality requirements. This method of using a rotary drilling rig and a vibratory hammer to guide the hole steel casing to follow through the underwater large-diameter boulder layer, backfilling with clay, and then using a static pressure pile driver to perform the steel sheet pile implantation operation greatly improves the implantation speed and efficiency of the steel sheet piles. The present invention can reduce the average construction time of a single steel sheet pile breaking through the boulder layer to about 20 minutes, and the time it takes to plant the piles is about 70 minutes. The speed of steel sheet pile construction is greatly accelerated, and the wear and tear of mechanical equipment due to the boulder layer is also greatly reduced. Calculations show that the present invention can reduce construction costs by 60% and increase construction speed by more than 9 times.
[0037] (2) The present invention can reduce the safety risk of cofferdam construction. The device and method of the present invention can greatly improve the accuracy of steel sheet pile implantation. The one-time implantation accuracy of steel sheet piles reaches 99.9%, which reduces the safety risk of cofferdam construction. The present invention has low implementation cost and short equipment layout time, which can greatly improve construction speed and reduce construction costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0038] Figure 1 It is a structural schematic diagram of the casing construction measurement and positioning device of the present invention.
[0039] Figure 2 It is a structural schematic diagram of the steel sheet pile movable sample corrector of the present invention.
[0040] Figure 3 It is a schematic diagram of the top structure of the mobile working platform of the present invention.
[0041] Figure 4 It is a side structural schematic diagram of the mobile working platform of the present invention.
[0042] Figure 5 It is a schematic diagram of the steel sheet pile structure for correcting outward inclination of the present invention. DETAILED DESCRIPTION
[0043] like Figures 1 to 4 As shown, a device for installing steel sheet piles in large-diameter boulder and sandstone formations includes a casing construction measurement and positioning device 1, a steel sheet pile movable sample corrector 2 and a mobile working platform 3.
[0044] like Figure 1As shown, the casing construction measurement and positioning device can accurately position the measuring prism at the center of the upper end of the steel casing, track the steel casing measurement in real time, and ensure the accuracy and verticality of the steel casing position.
[0045] The tube construction measurement and positioning device is as follows: a cross-shaped bracket 11 is provided at the upper end of a square frame 12, and the outer ends of the lower end surface of the cross-shaped bracket are respectively fixed to the middle of the four sides of the corresponding square frame as a whole, and a bolt 13 for prism connection is provided at the center point of the cross-shaped bracket. The lower parts of the four outer ends of the cross-shaped bracket are respectively welded to the midpoints of the four sides of the square frame. The axis of the bolt for prism connection coincides with the axis of the steel casing. The middle part of the inner side of the square frame is clamped on the outer wall of the upper end of the steel casing. The inner side of the square frame has the same length, and the lengths of the sides of the cross-shaped bracket are the same. The square frame and the cross-shaped bracket can be made of square-edged wood or square steel pipes.
[0046] When in use, first place the measuring prism on the bolt at the center point of the cross bracket, and then clamp the inner frame edge of the square frame on the outer wall of the upper end of the steel casing. Measure the center position of the steel casing to ensure that the center of the prism coincides with the center of the steel casing; when the steel casing is lowered and driven in, track and measure the center coordinate value of the steel casing represented by the prism in real time, compare it with the design coordinates of the pile foundation center to calculate the deviation value, and adjust the position of the steel casing according to the deviation value; after the steel casing is driven in, check the coordinates of the center point of the steel casing again to ensure that the installation accuracy of the steel casing meets the tolerance requirements. After use, remove the tube construction measurement and positioning device, which can be used repeatedly.
[0047] like Figure 2 As shown, the active steel sheet pile straightener is used to straighten the inclined steel sheet pile 6 being implanted during the operation of the static pressure pile driver.
[0048] The steel sheet pile movable sample corrector 2 is as follows: a longitudinal slideway 24 is provided in a longitudinally arranged base 29, and a guide groove channel 28 is provided at the front end of the base corresponding to the slideway. The rear part of the slider 23 is slidably fitted in the slideway, and the front end of the slider passes through the guide groove channel and is located at the front end of the base. The bottom of the top-pressing hydraulic cylinder 26 is transversely fixed to the front end of the slider by bolts. The top-pressing rod 27 of the top-pressing hydraulic cylinder is horizontally arranged, and is used to support the middle part of the upper end of the steel sheet pile 6 or the middle part of the upper end of the pressure head 51 of the static pressure pile driver 5. A through hole is provided at the upper end of the base in the middle of the guide groove channel for the lifting hydraulic rod 25 to slide through, and the lifting hydraulic cylinder 21 is fixed to the upper end surface of the base by connecting studs 22. The front end of the lifting hydraulic rod passes through the through hole and is fixed to the middle part of the upper end of the slider located in the slideway. Two base connecting ears 210 are provided at intervals on both sides of the base.
[0049] like Figure 3 and Figure 4As shown, the mobile working platform 3 is: two I-beams 36 arranged horizontally at a distance from each other are connected to each other through several steel columns and oblique steel columns 316 arranged longitudinally at a distance from each other, and the middle of the outer ends of the two fixed hoops 32 arranged at a distance from each other are respectively fixed to one end of the two horizontal I-beams to form a longitudinal support frame. The movable hoop 31 and the fixed hoop are semi-cylindrical. One end of the movable hoop is connected to one end of the fixed hoop by a hinge 311. The other end of the movable hoop is correspondingly provided with a docking ear 38 to the other end of the fixed hoop. The longitudinal support frame is connected to the docking ears on the movable and fixed hoops by the third connecting bolt 312 and the fixing nut 313 to fix the movable and fixed hoops on the steel trestle support pile 4, otherwise, the movable and fixed hoops are separated from the steel trestle support pile to move to the next construction pile position for construction. The two longitudinal support frames are fixed to two adjacent steel trestle support piles by the movable and fixed hoops respectively. The inner wall diameter of the movable clamp and the fixed clamp after buckling is adapted to the diameter of the steel trestle support pile. The inner peripheral wall of the movable clamp and the fixed clamp is provided with a rubber anti-skid layer with a thickness of 3 to 5 mm, which is used for the movable and fixed clamps to clamp with the steel trestle support pile.
[0050] The two ends of the two longitudinal support frames are respectively fixedly connected to the two ends of the left transverse support frame 315 and the right transverse support frame 35 by means of a docking flange 314, a first connecting bolt 34 and a fixing nut; that is, docking flanges are also provided at the corresponding positions of the docking flanges at the two ends of the left and right transverse support frames and the two longitudinal support frames, and the two are fixed as a whole by means of a first connecting bolt and a fixing nut, so as to realize the docking of the left and right transverse support frames with the two ends of the two longitudinal support frames.
[0051] The inner middle part of the two longitudinal support brackets and the left and right transverse support brackets is provided with a fixing seat 37 by welding, and two fixing seat connecting ears 39 are provided at intervals on both sides of the fixing seat. The two sides of the base of the steel sheet pile movable sample corrector are fixed to the fixing seat connecting ears by the base connecting ears, the second connecting bolts 310 and the fixing nuts, so as to facilitate the base bearing pressure of the steel sheet pile movable sample corrector to be transmitted to each supporting bracket through the fixing seat.
[0052] The upper ends of the two longitudinal support brackets and the left and right transverse support brackets are provided with working platforms 33 to facilitate personnel to stand on them for construction work.
[0053] A method for installing steel sheet piles in large-diameter boulder and sandstone formations using the device comprises the following steps:
[0054] (1) A steel trestle is constructed along the outer side of the designed cofferdam steel sheet piles to form a construction platform for the steel sheet piles on the river surface. The steel trestle is supported by a large number of steel trestle support piles4.
[0055] (2) Prepare on the construction platform a rotary drilling rig, a vibratory hammer, a static pressure pile driver and supporting equipment, two crawler cranes, steel casing and drill bits for the rotary drilling rig, steel sheet piles for the static pressure pile driver, casing construction measurement and positioning equipment, a mobile working platform and a movable sample calibrator for the steel sheet piles.
[0056] (3) The mobile work platform 3 is installed on the inner side of the construction platform using two adjacent steel trestle support piles of the construction platform as support; that is, the mobile work platform is fixed on the two adjacent steel trestle support piles through four movable and fixed clamps of two longitudinal support frames, and the mobile work platform can be lifted by a crane to between the two adjacent steel trestle support piles, and then the movable and fixed clamps are fixed to the two adjacent steel trestle support piles by tightening the third connecting bolts and fixing nuts. Otherwise, the movable and fixed clamps are separated from the steel trestle support piles to move the mobile work platform to the next construction pile position for construction.
[0057] (4) Use the existing steel guide frame and crane to install a steel casing with a diameter of 1.2m along the designed cofferdam steel sheet pile position. Use the steel casing construction measurement and positioning device 1 to detect the verticality of the installed steel casing in real time. The steel casing is installed by skipping holes and excavation. The diameter of the steel casing is 1.2m, and the diameter of the installed steel casing is the same as the center line of the designed cofferdam steel sheet pile.
[0058] The skip-hole installation is that the distance between the center points of adjacent steel casings installed for the first time is 1.8m, the steel casing installed for the second time is located in the middle of the two adjacent steel casings installed for the first time, and the peripheries of the adjacent steel casings installed for the first time and the second time overlap by 0.3m.
[0059] (5) A rotary drilling rig with a drill bit of 1.0 m and a vibratory hammer of model DZ90 are used to excavate the boulder layer at the lower end of the steel casing, and a hole is drilled to the lower end of the steel casing through the boulder layer.
[0060] (a) First, use a vibrating hammer to hit the upper end surface of the steel casing and record the bottom elevation of the steel casing in detail.
[0061] (b) A rotary drilling rig is then used to drill into the steel casing to a rock layer no more than 20 cm outside the bottom of the steel casing to reduce the friction resistance of the side wall of the steel casing.
[0062] (c) Then continue to use a vibrating hammer to hit the upper end of the steel casing to move the steel casing down to the lead hole.
[0063] (d) Repeat steps (a) to (c) until the lower end of the steel casing passes through the boulder layer and enters the lower rock layer.
[0064] (6) Backfilling with clay: After the completion of the borehole, backfill clay into the space between the bottom surface of the steel casing and the middle space 0.5m above the riverbed elevation outside the casing. The clay is transported in sandbags, backfilled manually, and compacted with a rotary drill to keep the elevation of the backfilled clay 0.5m higher than the riverbed elevation outside the casing. This prevents the clay elevation in the hole from being insufficient after the steel casing is removed.
[0065] (7) Removal of steel casing and initial load-bearing of static pressure pile driver: Remove the pressed steel casing, leaving a section that allows the reaction base plate at the bottom of the static pressure pile driver to clamp the fixed pressed steel casing. The reaction base plate of the static pressure pile driver clamps the upper ends of several fixed pressed steel casings, and uses the static load to implant a steel sheet pile along the backfill clay line.
[0066] (8) Use a static pressure pile driver to carry out the steel sheet pile planting operation along the backfill clay line until the static pressure pile driver can switch to clamp several steel sheet piles that have been pressed into the ground and press the next pile into the ground to complete the cofferdam steel sheet pile line, and then remove the remaining section of the pressed steel casing.
[0067] (9) Use a static pressure pile driver to carry out the steel sheet pile planting operation along the backfill clay line until the steel sheet pile cofferdam is completed. During the steel sheet pile pressing process, use a steel sheet pile movable straightener on the mobile working platform to straighten the inclined steel sheet pile. The steel sheet pile movable straightener presses the upper end of the steel sheet pile in the inclined direction until the steel sheet pile is in the correct position.
[0068] like Figure 5 As shown, the method of using a steel sheet pile movable corrector to correct the inclination of the steel sheet pile during the steel sheet pile pressing process is:
[0069] (a) If the pile body of the steel sheet pile 6 is inclined outward from the cofferdam, then: the base of the steel sheet pile movable sample corrector is fixed on the fixed seat of the mobile working platform opposite to the steel sheet pile inclined outward from the cofferdam, the ejection hydraulic rod of the steel sheet pile movable sample corrector is held at the middle of the upper end of the steel sheet pile inclined outward or the middle of the upper end of the pressure head of the static pressure pile driver, and as the pressure head of the static pressure pile driver implants the steel sheet pile, the movable hydraulic cylinder and the ejection hydraulic cylinder are started, and the movable hydraulic rod of the movable hydraulic cylinder drives the sliding block to move downward at the same speed as the speed at which the pressure head 51 of the static pressure pile driver implants the steel sheet pile, so that the ejection hydraulic cylinder also moves downward synchronously, and the deviation is slowly corrected by the slight displacement of the ejection hydraulic rod pressing the steel sheet pile, while the static pressure pile driver implants the steel sheet pile, the ejection hydraulic cylinder drives the ejection hydraulic rod to adjust the pressing steel sheet pile, and the inclined steel sheet pile is corrected under the pressure of the ejection hydraulic cylinder of the steel sheet pile movable sample corrector.
[0070] (b) If the steel sheet pile is tilted inwardly toward the cofferdam, then: the base of the movable steel sheet pile straightener is fixed on the fixed seat of the mobile working platform opposite to the steel sheet pile tilted inwardly toward the cofferdam, the ejection hydraulic rod of the movable steel sheet pile straightener is held at the middle of the upper end of the inwardly tilted steel sheet pile or at the middle of the upper end of the pressure head of the static pressure pile driver, and as the pressure head of the static pressure pile driver implants the steel sheet pile, the movable hydraulic cylinder and the ejection hydraulic cylinder are started, and the deviation is slowly corrected by the slight displacement of the steel sheet pile pressed by the ejection hydraulic rod, and the steel sheet pile is implanted and adjusted at the same time, and the tilted steel sheet pile is corrected under the pressure of the ejection hydraulic cylinder of the movable steel sheet pile straightener.
[0071] (c) If the steel sheet pile is tilted in the forward direction, then: the base of the steel sheet pile movable sample corrector is fixed on the fixed seat of the mobile working platform opposite to the steel sheet pile in the forward direction, the ejection hydraulic rod of the steel sheet pile movable sample corrector is held at the middle of the upper end of the steel sheet pile in the forward direction or at the middle of the upper end of the pressure head of the static pressure pile driver, and as the pressure head of the static pressure pile driver implants the steel sheet pile, the movable hydraulic cylinder and the ejection hydraulic cylinder are started, and the deviation is slowly corrected by the slight displacement of the steel sheet pile pressed by the ejection hydraulic rod, and the steel sheet pile is implanted and adjusted at the same time, and the inclined steel sheet pile is corrected under the pressure of the ejection hydraulic cylinder of the steel sheet pile movable sample corrector.
[0072] (10) Separate the movable and fixed clamps from the steel trestle support piles, and move the mobile work platform to the next construction pile position with the help of a crane. Repeat steps (1) to (9) until the steel sheet pile cofferdam is completed.
[0073] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be directly connected or indirectly connected through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0074] In conclusion, the present invention can improve the speed and efficiency of steel sheet pile implantation in large-diameter boulder and sandstone formations, reduce the safety risk of cofferdam construction, and can be widely used.
Claims
1. A device for installing steel sheet piles in large diameter boulder and sandstone formations, characterized in that: The device for installing steel sheet piles in large-diameter boulder and sandstone formations comprises a casing construction measurement and positioning device, a steel sheet pile movable sample corrector and a mobile working platform; the casing construction measurement and positioning device comprises: a cross-shaped bracket is arranged at the upper end of a square frame, the outer end portions of the lower end surface of the cross-shaped bracket are respectively fixed to the middle parts of the four sides of the corresponding square frame as a whole, a bolt for connecting a prism is arranged at the center point of the cross-shaped bracket, the lower parts of the four outer ends of the cross-shaped bracket are respectively welded to the midpoints of the four sides of the square frame, the axis line of the bolt for connecting the prism coincides with the axis line of the steel casing, and the middle part of the inner side of the square frame is clamped in The outer wall of the upper end of the steel casing; the steel sheet pile movable sample corrector is: a longitudinal slide is arranged in the longitudinally arranged base, a guide groove channel is arranged at the front end of the base corresponding to the slide, the rear part of the slider is slidably fitted in the slide, the front end of the slider passes through the guide groove channel and is located at the front end of the base, the bottom of the top pressure hydraulic cylinder is transversely fixed to the front end of the slider, and a through hole is arranged on the upper end of the base in the middle of the guide groove channel for the lifting hydraulic rod to slide through, the lifting hydraulic cylinder is fixed on the upper end surface of the base, the front end of the lifting hydraulic rod passes through the through hole and is fixed to the middle part of the upper end of the slider located in the slide, and two base connecting ears are arranged on both sides of the base at a distance; the movable The movable working platform is: two I-beams arranged horizontally at an interval between each other are connected as a whole through several steel columns and oblique steel columns arranged longitudinally at an interval, the middle parts of the outer ends of two fixed hoops arranged at an interval between each other are respectively fixed to one end of two horizontal I-beams to form a longitudinal support frame, the movable hoop and the fixed hoop are semi-cylindrical, one end of the movable hoop is connected to one end of the fixed hoop by a hinge, and the other end of the movable hoop is correspondingly provided with a docking ear, and the longitudinal support frame is connected to the docking ears on the movable and fixed hoops by a third connecting bolt and a fixing nut so that the movable and fixed hoops are fixed on On the steel trestle support piles; the two longitudinal support frames are fixed on the two adjacent steel trestle support piles by movable and fixed clamps respectively, the two ends of the two longitudinal support frames are fixedly connected to the two ends of the left and right transverse support frames by docking flanges and first connecting bolts respectively, the two longitudinal support frames and the left and right transverse support frames are provided with fixed seats in the middle of the inner sides, and two fixed seat connecting ears are provided on both side edges of the fixed seats at an interval, the two side edges of the base are fixed to the fixed seat connecting ears by base connecting ears and second connecting bolts respectively, and the upper ends of the two longitudinal support frames and the left and right transverse support frames are provided with working tables.
2. The device according to claim 1, characterized in that: The inner side lengths of the square frame are the same, and the lengths of the sides of the cross-shaped bracket are the same.
3. The device according to claim 1, characterized in that: The inner wall diameter of the movable clamp and the fixed clamp after being buckled is adapted to the diameter of the steel trestle support pile, and the inner peripheral wall of the movable clamp and the fixed clamp is provided with a rubber anti-skid layer.
4. A method for installing steel sheet piles in large diameter boulder and sandstone formations using the apparatus of claim 1, characterized in that: The steps include: (1) Build a steel trestle along the outer side of the designed cofferdam steel sheet piles to form a construction platform for the steel sheet piles on the river surface; (2) Prepare on the construction platform a rotary drilling rig, a vibratory hammer, a static pressure pile driver and supporting equipment, two crawler cranes, steel casing and drill bits for the rotary drilling rig, steel sheet piles for the static pressure pile driver, casing construction measurement and positioning equipment, a mobile working platform and a movable sample calibrator for steel sheet piles; (3) Using two adjacent steel trestle support piles of the construction platform as support, install the mobile working platform on the inner side of the construction platform; (4) Use a steel guide frame to install a steel casing with a diameter of 1.2m along the designed cofferdam steel sheet pile position, and use a steel casing construction measurement and positioning device to detect the verticality of the installed steel casing in real time. The steel casing is installed by skipping holes and excavation; (5) Use a rotary drilling rig with a drill bit of 1.0 m and a vibratory hammer of model DZ90 to excavate the boulder layer at the lower end of the steel casing and lead a hole to the lower end of the steel casing through the boulder layer; (a) First, use a vibrating hammer to hit the upper end surface of the steel casing and record the bottom elevation of the steel casing in detail; (b) Then, a rotary drilling rig is used to drill into the steel casing to a rock layer no more than 20 cm outside the bottom of the steel casing to reduce the friction resistance of the side wall of the steel casing; (c) Then continue to use a vibrating hammer to hit the upper end of the steel casing to move the steel casing downward to lead the hole; (d) Repeat steps (a) to (c) until the lower end of the steel casing passes through the boulder layer and enters the lower rock layer; (6) Backfilling with clay: After the completion of the borehole, backfill clay into the space between the inner bottom of the steel casing and the middle space 0.5 m above the riverbed elevation outside the casing. The clay is transported in sandbags, backfilled manually, and compacted with a rotary drill to keep the elevation of the backfilled clay 0.5 m higher than the riverbed elevation outside the casing; (7) Removal of steel casing and initial load-bearing of static pressure pile driver: Remove the pressed steel casing, leaving a section that allows the reaction base plate at the bottom of the static pressure pile driver to clamp the fixed pressed steel casing. The reaction base plate of the static pressure pile driver clamps the upper ends of several fixed pressed steel casings, and uses static load to implant a steel sheet pile along the backfill clay line; (8) Use a static pile driver to carry out the steel sheet pile planting operation along the backfill clay line until the static pile driver can switch to clamp several steel sheet piles that have been pressed into the ground and press the next pile into the ground to complete the cofferdam steel sheet pile line, and then remove the remaining section of the pressed steel casing; (9) Use a static pressure pile driver to carry out the steel sheet pile planting operation along the backfill clay line until the steel sheet pile cofferdam is completed. During the steel sheet pile pressing process, use a steel sheet pile movable sample straightener on the mobile working platform to straighten the inclined steel sheet pile. The steel sheet pile movable sample straightener presses the upper end of the steel sheet pile in the inclined direction until the steel sheet pile is in the correct position; (10) Separate the movable and fixed clamps from the steel trestle support piles, and move the mobile work platform to the next construction pile position with the help of a crane. Repeat steps (1) to (9) until the steel sheet pile cofferdam is completed.
5. The method according to claim 4, characterized in that: The diameter of the steel casing is 1.2m, and the diameter of the installed steel casing is the same as the center line of the designed cofferdam steel sheet pile.
6. The method according to claim 4, characterized in that: The skip-hole installation is that the distance between the center points of adjacent steel casings installed for the first time is 1.8m, the steel casing installed for the second time is located in the middle of the two adjacent steel casings installed for the first time, and the peripheries of the adjacent steel casings installed for the first time and the second time overlap by 0.3m.
7. The method according to claim 4, characterized in that: The method of using a steel sheet pile movable corrector to correct the inclination of the steel sheet pile during the steel sheet pile pressing process is: (a) If the steel sheet pile is tilted outward from the cofferdam, then: the base of the steel sheet pile movable sample corrector is fixed on the fixed seat of the mobile working platform opposite to the steel sheet pile tilted outward from the cofferdam, the ejection hydraulic rod of the steel sheet pile movable sample corrector is held at the middle of the upper end of the steel sheet pile tilted outward or at the middle of the upper end of the pressure head of the static pressure pile driver, and the steel sheet pile is implanted with the pressure head of the static pressure pile driver, the movable hydraulic cylinder and the ejection hydraulic cylinder are started, and the slight displacement of the steel sheet pile is pressed by the ejection hydraulic rod to slowly correct the deviation, and the steel sheet pile is implanted and adjusted at the same time, and the tilted steel sheet pile is corrected under the pressure of the ejection hydraulic cylinder of the steel sheet pile movable sample corrector; (b) If the steel sheet pile is tilted inwards towards the cofferdam, then: the base of the steel sheet pile movable sample corrector is fixed on the fixed seat of the mobile working platform opposite to the steel sheet pile tilted inwards towards the cofferdam, the ejection hydraulic rod of the steel sheet pile movable sample corrector is held at the middle of the upper end of the steel sheet pile tilted inwards or at the middle of the upper end of the pressure head of the static pressure pile driver, and the steel sheet pile is implanted with the pressure head of the static pressure pile driver, the movable hydraulic cylinder and the ejection hydraulic cylinder are started, and the slight displacement of the steel sheet pile is pressed by the ejection hydraulic rod to slowly correct the deviation, and the steel sheet pile is implanted and adjusted at the same time, so that the tilted steel sheet pile is corrected under the pressure of the ejection hydraulic cylinder of the steel sheet pile movable sample corrector; (c) If the steel sheet pile is tilted in the forward direction, then: the base of the steel sheet pile movable sample corrector is fixed on the fixed seat of the mobile working platform opposite to the steel sheet pile in the forward direction, the ejection hydraulic rod of the steel sheet pile movable sample corrector is held at the middle of the upper end of the steel sheet pile in the forward direction or at the middle of the upper end of the pressure head of the static pressure pile driver, and as the pressure head of the static pressure pile driver implants the steel sheet pile, the movable hydraulic cylinder and the ejection hydraulic cylinder are started, and the deviation is slowly corrected by the slight displacement of the steel sheet pile pressed by the ejection hydraulic rod, and the steel sheet pile is implanted and adjusted at the same time, and the inclined steel sheet pile is corrected under the pressure of the ejection hydraulic cylinder of the steel sheet pile movable sample corrector.