Pneumatic down-the-hole hammer horizontal directional drilling system and its construction method

By designing a horizontal directional drilling system for pneumatic submersible hammers, using the combined structure of drill rod and guide drill bit, efficient horizontal directional drilling in medium and hard rock layers is achieved, and the construction efficiency of existing equipment in medium and hard rock layers is solved. and environmental pollution problems have achieved efficient and environmentally friendly drilling results.

CN111636816BActive Publication Date: 2024-11-05LANG FANG PANGOLIN CONSTR MASCH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202010636614.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-07-03
Publication Date
2024-11-05
Estimated Expiration
2040-07-03

AI Technical Summary

Technical Problem

The existing pneumatic submersible hammer equipment cannot meet the horizontal directional drilling requirements in medium and hard rock formations, the construction efficiency is low and the use of mud leads to environmental pollution.

Method used

A pneumatic submersible hammer horizontal directional drilling system is designed, including a shell, drill rod, shock-proof rod chamber, oblique elbow, hammer body and guide drill bit, and the drill is controlled by the 360-degree slewing and local azimuth slewing of the drill rod. In the hole direction, the impact rotation rock breaking method is used, and compressed air is used as the power and slag discharge medium to avoid the use of mud.

Benefits of technology

It improves drilling efficiency by more than 5 times, reduces construction costs, realizes environmentally friendly slurry-free construction, extends the life of the drilling tool, and is suitable for medium-hard to extremely hard rock layers.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111636816B_ABST
    Figure CN111636816B_ABST
Patent Text Reader

Abstract

The present invention discloses a pneumatic down-the-hole hammer horizontal directional drilling system, comprising a housing, a drill rod, a shockproof probe rod bin connected to the drill rod, a deflection elbow connected to the shockproof probe rod bin, a hammer body connected to the deflection elbow, and a guide drill bit connected to the hammer body, wherein the guide drill bit is connected to the hammer body through a drill bit anti-detachment joint; the hammer body, the deflection elbow, the shockproof probe rod bin and the drill rod are all fixed inside the housing; the rear end of the drill bit anti-detachment joint is provided with a positioning spline, which is fixed inside the front end of the hammer body; the curvature of the deflection elbow is 1.0 degree or 1.5 degree. The present invention adopts the pneumatic down-the-hole hammer horizontal directional drilling system and its construction method of the above structure, which changes the current conventional construction process of the mud motor, improves the drilling efficiency by more than 5 times, does not require mud, is energy-saving and environmentally friendly, and improves the drilling efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of horizontal directional drilling, and in particular to a pneumatic down-the-hole hammer horizontal directional drilling system and a construction method thereof. Background Art

[0002] Horizontal directional drilling has a history of more than 20 years in my country, and the technology and equipment have been well developed. However, with the further development of my country's infrastructure, more and more pipelines need to be laid in medium and hard rock formations. Ordinary processes and equipment are difficult to implement in medium and hard rock formations, and the construction efficiency is low and the cost is extremely high. If the construction process of ordinary mud motors in soft rock formations is adopted, a large amount of mud will be consumed, and the treatment and dumping of mud will greatly pollute the environment, which is inconsistent with the current concept of environmental protection development. Now it is urgent to develop horizontal directional drilling technology and equipment in medium and hard rock formations.

[0003] The current pneumatic down-the-hole hammer construction method is the most efficient in rock-breaking drilling in medium-hard rock formations, but pneumatic down-the-hole hammers are usually used for vertical drilling. Horizontal directional drilling is very different from vertical well drilling. It requires not only drilling but also orientation. The existing pneumatic down-the-hole hammers cannot meet the above requirements. Ordinary down-the-hole hammers cannot be used for horizontal directional drilling because they rotate clockwise in the same direction during drilling and cannot achieve orientation. In view of the above reasons, it is necessary to design a pneumatic down-the-hole hammer horizontal directional drilling system and its construction method. Summary of the invention

[0004] The purpose of the present invention is to provide a pneumatic down-the-hole hammer horizontal directional drilling system and a construction method thereof, which changes the current conventional construction process of mud motors, improves the drilling efficiency by more than 5 times, does not require mud, is energy-saving and environmentally friendly, and improves the drilling efficiency.

[0005] To achieve the above-mentioned object, the present invention provides a pneumatic down-the-hole hammer horizontal directional drilling system, comprising a housing, a drill rod, a shockproof probe bar connected to the drill rod, a deflection elbow connected to the shockproof probe bar, a hammer body connected to the deflection elbow, and a guide drill bit connected to the hammer body, wherein the guide drill bit is connected to the hammer body through a drill bit anti-detachment joint;

[0006] The hammer body, the deflecting elbow, the anti-vibration probe chamber and the drill rod are all fixed inside the shell;

[0007] A positioning spline is provided at the rear end of the drill anti-drop joint, and the positioning spline is fixed inside the front end of the hammer body;

[0008] The curvature of the inclined elbow is 1.0 degree or 1.5 degree.

[0009] Preferably, the guide drill bit is configured as a circular structure, a duckbill structure, or an oblique palm structure.

[0010] Preferably, the number of the positioning splines is 12 or 24.

[0011] Preferably, the shockproof probe chamber includes an outer cabin body, an inner cabin outer shell arranged inside the outer cabin body, an inner cabin body arranged inside the inner cabin outer shell, and a guide instrument probe arranged inside the inner cabin body, and gas diverters and spring seats are arranged at both ends of the inner cabin outer shell, and a shock-absorbing spring is arranged on the spring seat.

[0012] Preferably, the front end of the inner cabin body is provided with an inner cabin front cap, the rear end of the inner cabin body is provided with an inner cabin rear cap, and the inner cabin rear cap and the inner cabin front cap are both fixed on the inner cabin outer shell.

[0013] A construction method of a pneumatic down-the-hole hammer horizontal directional drilling system comprises the following steps:

[0014] (1) The drilling rig applies drilling pressure to the drill pipe, the pneumatic down-the-hole hammer starts working, and the guide drill bit impacts the rock surface, causing the rock to break;

[0015] (2) If the drill rod rotates 360 degrees in all directions, it will drill in a straight line; if the drill rod does not rotate, the guide drill bit will stay in place and repeatedly break the rock;

[0016] (3) Operate the drilling rig to make the drill rod drive the guide drill bit to rotate 60 degrees clockwise first, and then 60 degrees counterclockwise. At this time, the guide drill bit deviates from the original direction under the action of the lateral force and enters a new trajectory for drilling;

[0017] (4) Control the rotation angle of local azimuth drilling and the frequency of omnidirectional rotation to control the inclination rate;

[0018] (5) When deflection drilling is required, a drilling method of feeding while performing local sector rotation is implemented. When deflection drilling is not required, a drilling method of feeding while performing full-circle rotation is implemented.

[0019] Preferably, when performing local rotary drilling in step (3), the upper half of the borehole cross section is elliptical and the lower half is semicircular; if the guide drill bit is stuck in an irregular borehole, full-scale 360-degree rotary drilling is performed.

[0020] Preferably, the guide drill bit is of an oblique palm type structure.

[0021] Preferably, the guide drill bit is used in conjunction with a bevel elbow, and the guide drill bit is a circular full-section cemented carbide guide drill bit.

[0022] Therefore, the pneumatic down-the-hole hammer horizontal directional drilling system and its construction method using the above structure have the following beneficial effects:

[0023] (1) The impact rotary rock breaking method is adopted, with large single impact energy, high slag discharge wind speed, clean hole bottom, no secondary crushing, improved hole bottom crushing conditions, and thus high drilling efficiency. The drilling speed can reach 0.6-0.8m / min in intact limestone formations, and even when deflecting, the drilling speed can reach 0.3-0.5m / min;

[0024] (2) Pneumatic down-the-hole hammer drilling adopts non-circulating dry operation. Compressed air is used as both power and slag removal medium. No mud is required and no pollution is caused to the environment.

[0025] (3) Compared with the mud motor guidance system, it has a faster rock breaking speed and higher drilling efficiency, especially for medium-hard rock. Its drilling speed is more than 5 times that of the mud motor, thus greatly reducing the construction cost;

[0026] (4) The down-the-hole hammer has a long service life. Generally, the guided construction length can reach 4,000-10,000 meters, which can greatly save the cost of drilling tools.

[0027] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 It is a structural schematic diagram of an embodiment of a pneumatic down-the-hole hammer horizontal directional drilling system of the present invention;

[0029] Figure 2 It is a partial enlarged view of an embodiment of a pneumatic down-the-hole hammer horizontal directional drilling system of the present invention;

[0030] Figure 3 It is a structural schematic diagram of a shock-proof probe bin of an embodiment of a pneumatic down-the-hole hammer horizontal directional drilling system of the present invention;

[0031] Figure 4 Illustration of the oblique palm structure guide drill bit drilling a guide hole Figure 1 ;

[0032] Figure 5 Illustration of the oblique palm structure guide drill bit drilling a guide hole Figure 2 ;

[0033] in, Figure 4 The thin, tilted arrow in the middle represents the lateral force, the thick arrow above represents the original direction, and the thick arrow below represents the new direction. DETAILED DESCRIPTION

[0034] The technical solution of the present invention is further described below through the accompanying drawings and embodiments.

[0035] The present invention provides a pneumatic down-the-hole hammer horizontal directional drilling system, comprising a housing, a drill rod 1, a shockproof probe rod compartment 2 connected to the drill rod 1, a deflecting elbow 3 connected to the shockproof probe rod compartment 1, a hammer body 4 connected to the deflecting elbow 3, and a guide drill bit 5 connected to the hammer body 4, wherein the guide drill bit 5 is connected to the hammer body 4 through a drill bit anti-detachment joint 6; the hammer body 4, the deflecting elbow 3, the shockproof probe rod compartment 2 and the drill rod 1 are all fixed inside the housing; the rear end of the drill bit anti-detachment joint 6 is provided with a positioning spline 7, and the positioning spline 7 is fixed inside the front end of the hammer body 4; the curvature of the deflecting elbow 3 is 1.0 degrees or 1.5 degrees. The guide drill bit 5 is set to a circular structure or a duckbill structure or an oblique palm structure. The number of the positioning splines 7 is 12 or 24. The impact drill bit for soft rock formations needs to be made into an oblique palm type guide drill bit to facilitate changing the drilling direction in the rock formation. Ordinary down-the-hole hammers rotate clockwise in the same direction during drilling. In the directional drilling process of the present invention, the down-the-hole hammer needs to be driven by the drill rod to swing and drill. The down-the-hole hammer needs to swing left and right around the directional axis to drill. Therefore, the drilling hammer needs to have a hammer head anti-slip function, which is achieved by an anti-slip short circuit installed in front of the down-the-hole hammer. The directional drilling guide instrument determines the orientation angle of the guide drill bit through the 12 o'clock position on the clock face, so the positioning splines of the hammer body and the drill bit need to be 12 or 24, so that it can correspond to the 12 o'clock position of the guide instrument, and can ensure that the 12 o'clock position of the guide drill bit is consistent with the instrument.

[0036] The anti-vibration probe bar 2 comprises an outer cabin 21, an inner cabin jacket 22 arranged inside the outer cabin 21, an inner cabin 23 arranged inside the inner cabin jacket 22, and a guide instrument probe bar 24 arranged inside the inner cabin 23. Gas diverters 25 and spring seats 26 are arranged at both ends of the inner cabin jacket 22, and a shock absorbing spring 27 is arranged on the spring seat 26. An inner cabin front cap 28 is arranged at the front end of the inner cabin 23, and an inner cabin rear cap 29 is arranged at the rear end of the inner cabin 23. Both the inner cabin rear cap 29 and the inner cabin front cap 28 are fixed on the inner cabin jacket 22. There are many sensors and magnetic signal transmitters in the signal transmitting probe bar of the horizontal directional drilling guide instrument, and strong vibration is not allowed. When the down-the-hole hammer is drilling, the impact frequency is high and the vibration amplitude is large, so the anti-vibration probe bar must be able to play a shock absorbing role on the probe bar to prevent it from being damaged by vibration. The front of the deflection elbow is connected to the hammer body of the down-the-hole hammer through a threaded connection, and the back is connected to the anti-vibration probe bar 28. There are locating pins at the rear end of the inner cabin front cap and the bevel elbow. The position of the locating pin is consistent with the direction of the bend. There is a locating groove at the front and back of the gas diverter. The two locating grooves are in the same straight line. Insert the locating pins of the inner cabin front cap and the bevel elbow into the locating groove of the gas diverter respectively to ensure that the 12 o'clock position of the probe is aligned with the bend of the bevel elbow. The rear end of the outer cabin is closed and the front end is fixed by the bevel elbow. The outer cabin is processed with more than 3 signal transmission grooves and gas lifting channels.

[0037] Example 1

[0038] A construction method of a pneumatic down-the-hole hammer horizontal directional drilling system comprises the following steps:

[0039] (1) When drilling the pilot hole 8 in the weathered rock formation or the rock formation with medium hardness or lower, an inclined palm type carbide pilot drill bit is used. The driving drill applies drilling pressure to the drill pipe, the down-the-hole hammer starts working, and the drill bit alloy impacts the rock surface, causing the rock to break.

[0040] (2) If the drill rod rotates 360 degrees in all directions, it will drill in a straight line, which is similar to normal rock drilling. If the drill rod does not rotate, the drill bit will stay in place and repeatedly break the rock, and the rock powder cannot be effectively discharged from the bottom of the hole, so no footage can be formed.

[0041] (3) Operate the drilling rig to make the drill rod drive the guide drill bit to rotate 60 degrees clockwise first, and then 60 degrees counterclockwise. At this time, the guide drill bit deviates from the original direction under the action of the lateral force and enters a new trajectory for drilling; because only local rotation drilling is performed, the cross section of the drill hole is irregular. The upper half of the drill hole cross section is elliptical and the lower half is semicircular. After repeated local rotation drilling for several times, the drill bit may be stuck in the irregular drill hole. At this time, full-scale 360-degree rotation drilling should be performed to adjust the cross section of the drill hole.

[0042] (4) Controlling the rotation angle of local azimuth drilling and the frequency of omnidirectional rotation can effectively control the inclination rate, as shown in Table 1.

[0043] (5) When deflection drilling is required, a drilling method of feeding while performing local sector rotation is implemented. When deflection drilling is not required, a drilling method of feeding while performing full-circle rotation is implemented.

[0044] The above construction method is aimed at guided drilling in weathered rock formations and rock formations with medium hardness or lower.

[0045] Table 1

[0046] Control Methods Effect Expand the sector angle of the local rotation Slow down the slope rate and make it less likely for the drill bit to get stuck. Reduce the sector angle of the local rotation Increasing the inclination rate will easily cause the drill bit to get stuck. Increase the number of consecutive full-circle revolutions Slow down the slope rate and make it less likely for the drill bit to get stuck. Reduce the number of consecutive full-circle revolutions Increasing the inclination rate will easily cause the drill bit to get stuck. Increase the frequency or number of revolutions of the full circle Slow down the slope rate and make it less likely for the drill bit to get stuck. Reduce the frequency or number of full-circle revolutions Increasing the inclination rate will easily cause the drill bit to get stuck.

[0047] Example 2

[0048] A construction method of a pneumatic down-the-hole hammer horizontal directional drilling system comprises the following steps:

[0049] (1) In medium-hard rock to hard rock formations, a round full-section carbide pilot drill bit should be used. When using this drill bit for pilot hole drilling, a deflection elbow must be used in conjunction with the deflection elbow. The curvature of the deflection elbow is shown in Table 2, so that deflection drilling can be performed.

[0050] (2) If the drill rod rotates 360 degrees in a full circle, it will perform straight drilling, which is similar to general rock drilling. If the drill rod does not rotate (similar to non-excavation pilot hole drilling in the soil layer), the pilot drill bit will stay in place and repeatedly crush the rock, and the rock powder cannot be effectively discharged from the bottom of the hole, so no footage can be formed.

[0051] (3) Operate the drilling rig so that the drill pipe drives the bend and the drill bit to make a partial azimuth rotation, 60 degrees clockwise, and then 60 degrees counterclockwise. At this time, the guide drill bit deviates from the original direction under the action of the lateral force and enters a new trajectory for drilling.

[0052] (4) Since only local rotary drilling is performed, the cross section of the borehole is irregular. After repeated local rotary drilling, the drill bit may be stuck in the curved borehole. At this time, full-scale 360-degree rotary drilling should be performed to trim the borehole trajectory curve and make it smooth, which is conducive to the rotation of the drill string in the hole.

[0053] (5) Controlling the sector rotation angle of local azimuth drilling and the frequency of full-circle rotation can effectively control the inclination rate.

[0054] Table 2

[0055] name Technical specifications Applicable stratum Slanted elbow 1.0 degrees Medium to very hard rock formations, when a smaller build rate is required. Slanted elbow 1.5 degrees Medium to very hard rock formations, when medium build rate is required.

[0056] Therefore, the present invention adopts the pneumatic down-the-hole hammer horizontal directional drilling system and its construction method of the above structure, which changes the current conventional construction process of mud motors, improves the drilling efficiency by more than 5 times, and does not require mud, is energy-saving and environmentally friendly, and improves the drilling efficiency.

[0057] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that they can still modify or replace the technical solution of the present invention with equivalents, and these modifications or equivalent replacements cannot cause the modified technical solution to deviate from the spirit and scope of the technical solution of the present invention.

Claims

1. A construction method of a pneumatic down-the-hole hammer horizontal directional drilling system, characterized in that: It comprises a shell, a drill rod, a shockproof probe rod bin connected to the drill rod, a deflecting elbow connected to the shockproof probe rod bin, a hammer connected to the deflecting elbow, and a guide drill bit connected to the hammer body, wherein the guide drill bit is connected to the hammer body through a drill bit anti-detachment joint; the hammer body, the deflecting elbow, the shockproof probe rod bin and the drill rod are all fixed inside the shell; a positioning spline is provided at the rear end of the drill bit anti-detachment joint, and the positioning spline is fixed inside the front end of the hammer body; the curvature of the deflecting elbow is 1.0 degree or 1.5 degree; The following steps are involved: (1) The drilling rig applies drilling pressure to the drill pipe, the pneumatic down-the-hole hammer starts working, and the guide drill bit impacts the rock surface, causing the rock to break; (2) If the drill rod rotates 360 degrees in all directions, it will drill in a straight line; if the drill rod does not rotate, the guide drill bit will stay in place and repeatedly break the rock; (3) Operate the drilling rig to make the drill rod drive the guide drill bit to rotate 60 degrees clockwise first, and then 60 degrees counterclockwise. At this time, the guide drill bit deviates from the original direction under the action of the lateral force and enters a new trajectory for drilling; (4) Control the rotation angle of local azimuth drilling and the frequency of omnidirectional rotation to control the inclination rate; (5) When deflection drilling is required, a drilling method of feeding and performing local sector rotation is implemented; when deflection drilling is not required, a drilling method of feeding and performing full-circle rotation is implemented; When performing local rotation drilling in step (3), the upper half of the borehole cross section is elliptical and the lower half is semicircular; if the guide drill bit is stuck in an irregular borehole, full-scale 360-degree rotation drilling is performed.

2. The construction method of a pneumatic down-the-hole hammer horizontal directional drilling system according to claim 1, characterized in that: The guide drill bit is configured as a circular structure, a duckbill structure, or an oblique palm structure.

3. The construction method of a pneumatic down-the-hole hammer horizontal directional drilling system according to claim 1, characterized in that: The number of the positioning splines is 12 or 24.

4. The construction method of a pneumatic down-the-hole hammer horizontal directional drilling system according to claim 1, characterized in that: The shockproof probe chamber includes an outer cabin body, an inner cabin outer shell arranged inside the outer cabin body, an inner cabin body arranged inside the inner cabin outer shell, and a guide instrument probe arranged inside the inner cabin body, and gas diverters and spring seats are arranged at both ends of the inner cabin outer shell, and a shock-absorbing spring is arranged on the spring seat.

5. The construction method of a pneumatic down-the-hole hammer horizontal directional drilling system according to claim 4 is characterized in that: The front end of the inner cabin body is provided with an inner cabin front cap, and the rear end of the inner cabin body is provided with an inner cabin rear cap. Both the inner cabin rear cap and the inner cabin front cap are fixed on the inner cabin outer shell.

6. The construction method of a pneumatic down-the-hole hammer horizontal directional drilling system according to claim 1, characterized in that: The guide drill bit is of an oblique palm type structure.

7. The construction method of a pneumatic down-the-hole hammer horizontal directional drilling system according to claim 1, characterized in that: The guide drill bit is used in conjunction with a bevel elbow, and the guide drill bit is a circular full-section cemented carbide guide drill bit.