A construction method suitable for rock-embedded construction of offshore wind power high pile cap foundation

The equipment, consisting of hydraulic cylinders, a frame, a hydraulic lifting mechanism, and a walking chassis, solved the problem of fixing the drilling rig angle and moving it during the rock-embedded construction of high-pile foundations for offshore wind power. It enabled automatic walking, angle adjustment, and simple hoisting, thus improving construction efficiency and quality.

CN111749259BActive Publication Date: 2024-11-08CCCC FIRST HARBOR ENGINEERING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202010567395.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-06-19
Publication Date
2024-11-08
Estimated Expiration
2040-06-19

AI Technical Summary

Technical Problem

In the current construction of rock-embedded high-pile foundations for offshore wind power, conventional drilling equipment has a fixed angle, is difficult to move, and is complex to operate, resulting in slow construction speed, high failure rate, and increased costs.

Method used

The equipment, consisting of hydraulic cylinders, a frame, a hydraulic lifting mechanism, and a walking chassis, combined with a power head, connecting drill rods, and a centralizer, enables the drilling rig to move automatically, adjust its angle, and be easily hoisted, thereby improving drilling efficiency.

Benefits of technology

It improved the efficiency and quality of rock-embedded construction of high-pile foundations for offshore wind power, ensured drilling accuracy, and reduced construction costs and complexity.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111749259B_ABST
    Figure CN111749259B_ABST
Patent Text Reader

Abstract

A construction method suitable for rock-embedded construction of offshore wind power high-pile foundation, including a hydraulic cylinder 1, a frame 2, a hydraulic lifting mechanism 3 and a walking chassis 4; wherein the hydraulic cylinder 1 and the frame 2 are hinged and movably connected through a hinge point B, the hydraulic cylinder 1 and the walking chassis 4 are hinged and movably connected through a hinge point A, the frame 2 and the walking chassis 4 are hinged and movably connected through a hinge point C, and the frame 2 is hydraulically extended and retracted by the hydraulic cylinder 1 to adjust the working angle of the frame 2; a hydraulic lifting mechanism 3 is arranged on the top of the frame 2, and the hydraulic lifting mechanism 3 can realize the self-lifting of simple auxiliary facilities. The present invention places the drilling rig on a matching rock-embedded platform and is applied to the rock-embedded construction of inclined piles. It has the advantages of automatic walking alignment, angle adjustment, simple lifting, accurate drilling, quick disassembly, simple operation, etc. on the platform, which ensures the quality of rock-embedded construction and improves the construction progress management.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention patent relates to the field of offshore wind power construction, specifically a construction method suitable for rock-embedded construction of offshore wind power high pile cap foundation. Background Art

[0002] In recent years, offshore wind power high pile caps have been widely used in offshore wind power projects due to their low requirements for ship machinery and equipment, sufficient raw materials for steel pipe piles, and many manufacturers. Due to the changeable seabed geology, steel pipe piles often need to be embedded in medium-differentiated rock layers during construction to meet the load-bearing requirements. At this time, rock-embedded drilling construction is required; the foundations of high pile caps are all inclined pile foundations, and rock-embedded construction has put forward higher requirements for drilling equipment and construction platforms. Conventional drilling rigs have many problems such as fixed drilling angles, mobile drilling rigs requiring the cooperation of ship-borne cranes, and complex drilling rig operations, which lead to slow construction speed, high failure rate, and increased construction costs. Summary of the invention

[0003] Therefore, in order to solve the above problems, the present invention patent provides a device and construction method suitable for the rock-embedded construction of offshore wind power high pile cap foundation, which can solve the problems of fixed angle, difficult movement, and complex operation of conventional drilling rigs, improve drilling efficiency, and ensure construction progress.

[0004] The technical solution adopted by the present invention to solve its technical problem is:

[0005] A device suitable for rock-embedded construction of offshore wind power high-pile cap foundations, comprising a hydraulic cylinder 1, a frame 2, a hydraulic lifting mechanism 3 and a walking chassis 4; wherein the hydraulic cylinder 1 and the frame 2 are hingedly connected via a hinge point B, the hydraulic cylinder 1 and the walking chassis 4 are hingedly connected via a hinge point A, the frame 2 and the walking chassis 4 are hingedly connected via a hinge point C, and the frame 2 can adjust its working angle by hydraulically extending and retracting the hydraulic cylinder 1; a hydraulic lifting mechanism 3 is provided on the top of the frame 2, and the hydraulic lifting mechanism 3 can realize self-hoisting of simple auxiliary facilities.

[0006] The present invention also has the following additional technical features:

[0007] As a further specific optimization of the technical solution of the present invention: a power head 5 is arranged at the top of the large frame 2.

[0008] As a further specific optimization of the technical solution of the present invention: the drill bit 7 is connected to the power head 5 through a connecting drill rod, and the drill bit 7 and the connecting drill rod are matched with the borehole diameter.

[0009] As a further specific optimization of the technical solution of the present invention: a centralizer 8 is added to the connected drill pipe every 10 meters.

[0010] As a further specific optimization of the technical solution of the present invention: a winch 6 is installed on the top side of the large frame 2.

[0011] As a further specific optimization of the technical solution of the present invention: lifting legs 41 are provided at the four corners of the walking chassis 4, and automatic alignment walking is achieved through the lifting legs 41.

[0012] As a further specific optimization of the technical solution of the present invention: the lifting force of the hydraulic lifting mechanism 3 meets the auxiliary lifting requirements of the rock-embedded inclined pile construction of the high pile cap foundation under existing conditions, and the lifting force of the hydraulic lifting mechanism 3 is not unique, and can be adjusted and increased in time according to subsequent needs.

[0013] Compared with the prior art, the present invention has the following advantages:

[0014] Advantage 1: The present invention places the drilling rig on a matching rock-embedded platform and is used in the rock-embedded construction of inclined piles. It has the advantages of automatic walking and positioning on the platform, angle adjustment, simple lifting, precise drilling, quick disassembly, and simple operation, which ensures the quality of rock-embedded construction and improves construction progress management.

[0015] Advantage 2: The present invention can automatically walk and align on the platform, and the angle adjustment is automatically adjusted by a set of hydraulic cylinders 1, with an adjustment range of 8-12°; it is equipped with a 3.5-ton hydraulic lifting mechanism 3, and some simple auxiliary facilities can be automatically hoisted during the construction process;

[0016] Advantage 3: The present invention can automatically pressurize and drill to ensure the accuracy of drilling; the present invention has a fully hydraulic stepless speed change to reduce the impact damage of the drill rod and drilling tools; the drilling pressure of the present invention can be adjusted according to the working conditions to ensure the accuracy of the drilling inclination and aperture; the present invention has a tiltable power head to implement rapid disassembly and assembly of the drill rod; the present invention has a suspended power head and a tiltable frame to quickly lift and place the drilling tools and drill rod; the whole machine of the present invention is light in weight and small in size, and is easy to operate and use.

[0017] Additional aspects and advantages of the present invention will be given in part in the following description and in part will be obvious from the following description, or will be learned through practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0019] Figure 1 It is a schematic diagram of a drilling rig used for rock-embedded construction of offshore wind power high pile cap foundation of the present invention;

[0020] Figure 2 It is a schematic diagram of a power head 5 used for rock-embedded construction of offshore wind power high pile cap foundation of the present invention;

[0021] Figure 3 It is a schematic diagram of a winch 6 used for rock-embedded construction of offshore wind power high pile cap foundation of the present invention;

[0022] Figure 4 Schematic diagram of a drill bit 7 for rock-embedded construction of offshore wind power high pile cap foundation according to the present invention

[0023] Figure 5 Schematic diagram b of a drill bit 7 for rock-embedded construction of offshore wind power high pile cap foundation of the present invention;

[0024] Figure 6 It is a schematic diagram of a centralizer 8 used for rock-embedded construction of offshore wind power high-pile cap foundation of the present invention.

[0025] Explanation of reference numerals: hydraulic cylinder 1; frame 2; hydraulic lifting mechanism 3; walking chassis 4; lifting legs 41; power head 5; winch 6; drill bit 7; straightener 8. DETAILED DESCRIPTION

[0026] The exemplary embodiments disclosed in the present invention will be described in more detail below with reference to the accompanying drawings. These embodiments are intended to enable a more thorough understanding of the present invention and to fully convey the scope of the present invention to those skilled in the art. Although the exemplary embodiments disclosed in the present invention are shown in the accompanying drawings, it should be understood that the present invention should not be limited by the embodiments described herein.

[0027] A device suitable for rock-embedded construction of offshore wind power high-pile foundation, comprising a hydraulic cylinder 1, a frame 2, a hydraulic lifting mechanism 3 and a walking chassis 4; wherein the hydraulic cylinder 1 and the frame 2 are hinged and movably connected via a hinge point B, the hydraulic cylinder 1 and the walking chassis 4 are hinged and movably connected via a hinge point A, the frame 2 and the walking chassis 4 are hinged and movably connected via a hinge point C, and the frame 2 can adjust its working angle by hydraulic extension and retraction of the hydraulic cylinder 1; a hydraulic lifting mechanism 3 is arranged on the top of the frame 2, the lifting force of the hydraulic lifting mechanism 3 is 3.5 tons, and the hydraulic lifting mechanism 3 can realize self-hoisting of simple auxiliary facilities.

[0028] The top of the large frame 2 is provided with a power head 5. A drill bit 7 is connected to the power head 5 through a connecting drill rod, and the drill bit 7 and the connecting drill rod are matched with the borehole diameter.

[0029] A centralizer 8 is added to the connected drill rod every 10 meters. In order to ensure that the drill bit 7 does not have eccentricity and tilt beyond the specifications and design requirements after drilling to the tip of the steel pipe pile, a centralizer 8 is added to the drill rod every 10 meters in the steel pipe pile.

[0030] A winch 6 is installed on the top side of the frame 2. The conduit uses a conduit with an outer diameter of φ325. The bottom section of a single set of conduits is 4m long, the standard section is 2m, and auxiliary conduits of 0.5m and 1m are also provided. The length of the conduit should be increased or decreased according to the length of the pile; a centralizer is installed at eight meters at the bottom of the conduit to ensure that the conduit is not stuck in the cage during installation; the conduit is assembled straight, and is hoisted, extended, and lowered in sections by the winch 6.

[0031] Lifting legs (41) are arranged at the four corners of the walking chassis (4), and walking plates (42) are arranged at the middle positions of the four lower parts of the walking chassis (4). Automatic alignment walking is achieved by alternately cooperating between the lifting legs (41) and the walking plates (42).

[0032] A construction method for equipment suitable for rock-embedded construction of offshore wind power high-pile cap foundations, comprising the following steps:

[0033] Step 1: Transportation by barge: After the steel pipe piles are sunk, the pile heads are processed and the rock-embedded platform and drilling equipment are transported to the construction site by barge.

[0034] Step ②: Hoist the rock-embedded platform: Hoist the rock-embedded platform onto the steel pipe piles by a crane ship and reinforce it.

[0035] Step 3: Install the drilling rig: Use a crane ship to lift the drilling rig onto the rock-embedded platform and place it inside the steel pipe piles.

[0036] Step ④ drilling construction: the drill bit 7 is inserted into the steel pipe pile to perform drilling construction, the drill rod is increased to reach the designed elevation depth, and the slag in the pile is cleared through the reverse circulation device.

[0037] Step ⑤: Clean the hole and install the steel cage: After the hole is completed and accepted by the supervisor, the hole is cleaned. After cleaning the hole, the steel cage is hoisted and the concrete conduit is lowered.

[0038] Step ⑥ pouring concrete: pouring concrete in the steel pipe piles through a mixing boat, and removing the conduit after pouring is completed.

[0039] Step 7: Removing the rock-embedded platform: After completing the drilling and pouring of concrete for all steel pipe piles, move the rock-embedded platform away from the steel pipe piles.

[0040] The construction method of the equipment applicable to the rock-embedded construction of offshore wind power high pile cap foundation comprises the following steps:

[0041] Step 1: Transportation by barge: After the steel pipe piles are sunk, a temporary operation platform for cutting the pile heads is set up using the steel pipe piles. The designed pile top elevation is measured using GPS and the cutting line is drawn. The pile heads are cut to the designed elevation so that a horizontal plane is formed on the pile top to facilitate the installation and positioning of the rock-embedded platform. After the rock-embedded platform is welded at the dock, it is hoisted onto the barge as a whole by a crane ship, and the rock-embedded platform and drilling rig equipment are transported to the construction site by the barge.

[0042] Step ② Hoist the rock-embedded platform: After the rock-embedded platform is transported to the predetermined location via a barge, a crane ship is used to hoist the rock-embedded platform onto the steel pipe piles during installation. The steel pipe piles and the rock-embedded platform are securely fixed using a connection system. During the hoisting process, attention should be paid to controlling the hoisting deviation to ensure that the steel pipe piles are evenly stressed.

[0043] Step ③ Install the drilling rig: After the installation of the rock-embedded platform is completed, the drilling rig is hoisted onto the rock-embedded platform by the barge crane unit for assembly, the power head 5 is installed on the frame 2, and moved to the pile position; when installing the drill rod, first measure the inclination of the drill rod with an inclinometer in two directions to control the deviation of the drill rod inclination within 1%; when adjusting the angle of the drilling rig by the hydraulic cylinder 1, use a spirit level to check the horizontality of the wedge-shaped pad of the base, and use a steel plate to pad and level the wedge-shaped pad, and use a theodolite to check the inclination of the turntable; after the drilling rig is in place, ensure that the axial center of the drill rod, the center of the turntable, and the axial center of the pile are in the same straight line.

[0044] Step ④ Drilling construction: The drilling rig uses a drill bit 7 and a connected drill rod that match the diameter of the drill hole; the drill bit 7 is connected to the power head 5 through the drill rod. In order to ensure that the drill bit 7 does not have eccentricity and inclination that exceeds the specifications and design requirements after drilling to the tip of the steel pipe pile, a straightener 8 is added to the drill rod inside the steel pipe pile every 10 meters to ensure that the drill bit 7 does not sag after it leaves the tip of the steel pipe pile, ensuring that the inclination of the drill hole meets the requirements; the drill bit 7 is drilled to the designed elevation by increasing the length of the drill rod.

[0045] Step ⑤ Clean the hole and install the steel cage: After the hole reaches the designed depth, first test the depth, and then clean the hole after it meets the requirements; the hole is cleaned by pump suction reverse circulation process; that is, after the drilling rig stops working, it is stopped for about two hours to allow the suspended matter in the hole to settle to the bottom of the hole, and then the sediment in the hole is cleaned out.

[0046] After the steel cage is processed at the dock, in order to facilitate marine transportation and installation, the steel cage is manufactured in sections and must meet the specifications and design requirements. The stirrups and main bars must be spot welded firmly. The main reinforcement connection of the steel cage is carried out according to the design requirements and is transported to the site by barge after completion.

[0047] The steel cage is installed by crawler crane of square barge crane unit. Single-strand double-track wire rope is used to lower the steel cage. When the steel cage is installed, the wire rope fixed on the top of the drilling rig is untied, and the winch 6 pulls the wire rope in the hole to the hole.

[0048] The conduit uses a conduit with an outer diameter of φ325. The bottom section of a single set of conduits is 4m long, the standard section is 2m, and it is equipped with auxiliary conduits of 0.5m and 1m in length. The length of the conduit should be increased or decreased according to the different pile lengths; a centralizer is installed eight meters at the bottom of the conduit to ensure that the conduit is not stuck in the cage during installation; the conduit is assembled straight, and is hoisted, extended, and lowered in sections by winch 6.

[0049] Step ⑥ pouring concrete: concrete is poured by pumping it into the steel pipe piles using a mixing ship. During the pouring process, the conduit is removed by a winch 6 to ensure that the burial depth does not exceed 6 meters; after the concrete reaches the designed elevation, the remaining conduit is removed by a winch 6, cleaned and waits for the next use.

[0050] Step 7: Dismantle the rock-embedded platform: remove the construction equipment and materials on the top surface of the rock-embedded platform to the barge, and lift the rock-embedded platform to the barge by the crane ship and transport it to the next position.

[0051] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention are clearly and completely described above in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings herein can be arranged and designed in various different configurations.

[0052] Therefore, the above detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

Claims

1. A construction method suitable for rock-embedded construction of offshore wind power high pile cap foundation, characterized by: Equipment suitable for rock-embedded construction of offshore wind power high-pile cap foundations, comprising a hydraulic cylinder (1), a frame (2), a hydraulic lifting mechanism (3) and a walking chassis (4); wherein the hydraulic cylinder (1) and the frame (2) are hingedly connected via a hinge point B, the hydraulic cylinder (1) and the walking chassis (4) are hingedly connected via a hinge point A, the frame (2) and the walking chassis (4) are hingedly connected via a hinge point C, and the frame (2) can adjust the working angle of the frame (2) through the hydraulic extension and retraction of the hydraulic cylinder (1); a hydraulic lifting mechanism (3) is arranged on the top of the frame (2), and the hydraulic lifting mechanism (3) can realize the self-hoisting of simple auxiliary facilities; The construction method applicable to the rock-embedded construction of offshore wind power high pile cap foundation includes the following steps: Step 1: Barge transportation: After the steel pipe piles are sunk, a temporary operation platform for cutting the pile heads is set up using the steel pipe piles. The designed pile top elevation is measured using GPS and a cutting line is drawn. The pile heads are cut to the designed elevation so that a horizontal plane is formed on the pile top to facilitate the installation and positioning of the rock-embedded platform. After the rock-embedded platform is welded at the dock, it is hoisted onto the barge as a whole by a crane ship, and the rock-embedded platform and drilling rig equipment are transported to the construction site by the barge. Step ② Hoisting the rock-embedded platform: After the rock-embedded platform is transported to the predetermined position by barge, a crane ship is used to hoist the rock-embedded platform onto the steel pipe piles during installation. The steel pipe piles and the rock-embedded platform are firmly fixed using a connection system. During the hoisting process, attention should be paid to controlling the hoisting deviation to ensure that the steel pipe piles are evenly stressed. Step 3: Install the drilling rig: After the installation of the rock-embedded platform is completed, the drilling rig is hoisted onto the rock-embedded platform by a barge crane for assembly, the power head (5) is installed on the frame (2), and moved to the pile position; when installing the drill rod, first use an inclinometer to measure the inclination of the drill rod in two directions, so that the deviation of the inclination of the drill rod is controlled within 1%; when adjusting the angle of the drilling rig by the hydraulic cylinder (1), use a level ruler to check the horizontality of the wedge-shaped pad of the base, and use a steel plate to pad the wedge-shaped pad to level it, and use a theodolite to check the inclination of the turntable; after the drilling rig is in place, ensure that the axial center of the drill rod, the center of the turntable, and the axial center of the pile are in the same straight line; Step ④ Drilling construction: The drilling machine uses a drill bit (7) and a connected drill rod that match the diameter of the drill hole; the drill bit (7) is connected to the power head (5) through the drill rod. In order to ensure that the drill bit (7) does not have eccentricity and inclination that exceeds the specifications and design requirements after drilling to the tip of the steel pipe pile, a straightener 8 is added to the drill rod every 10 meters in the steel pipe pile to ensure that the drill bit (7) does not sag after leaving the tip of the steel pipe pile, ensuring that the inclination of the drill hole meets the requirements; the drill bit (7) is drilled to the designed elevation position by increasing the length of the drill rod; Step 5: Clean the hole and install the steel cage: After the hole reaches the designed depth, first test the depth, and clean the hole after it meets the requirements; the hole is cleaned by pump suction reverse circulation process; that is, after the drilling rig stops working, it is stopped for about two hours to let the suspended matter in the hole settle to the bottom of the hole, and then the sediment in the hole is cleaned out; After the steel cage is processed at the dock, in order to facilitate marine transportation and installation, the steel cage is made in sections and must meet the specifications and design requirements. The stirrups and main bars must be spot welded firmly. The main bars of the steel cage are connected according to the design requirements. After the production is completed, it is transported to the site by barge. The steel cage is installed by a crawler crane of a square barge crane unit. A single-strand double-track steel wire rope is used to lower the steel cage. When the steel cage is installed, the steel wire rope fixed on the top of the drilling rig is untied, and the winch (6) pulls the steel wire rope in the hole to the hole. The conduit adopts a conduit with an outer diameter of φ325. The bottom section of a single conduit is 4m long, the standard section is 2m, and auxiliary conduits of 0.5m and 1m are provided. The length of the conduit should be increased or decreased according to the length of the pile. A centralizer is installed at 8 meters at the bottom of the conduit to ensure that the conduit does not get stuck in the cage during installation. The conduit is assembled straight, and is hoisted and extended and lowered section by section by winch 6. Step ⑥ pouring concrete: The concrete is poured by pumping it into the steel pipe pile using a mixing ship. During the pouring process, the conduit is removed by a winch 6 to ensure that the buried depth does not exceed 6 meters. After the concrete reaches the designed elevation, the remaining conduit is removed by a winch (6), cleaned and waited for the next use. Step 7: Dismantle the rock-embedded platform: remove the construction equipment and materials on the top surface of the rock-embedded platform to the barge, and lift the rock-embedded platform to the barge by the crane ship and transport it to the next position.

2. The construction method for rock-embedded construction of offshore wind power high pile cap foundation according to claim 1 is characterized by: A power head (5) is arranged at the top of the large frame (2).

3. The construction method applicable to rock-embedded construction of offshore wind power high pile cap foundation according to claim 1 is characterized by: The drill bit (7) is connected to the power head (5) via a connecting drill rod, and the drill bit (7) and the connecting drill rod are matched with the diameter of the drill hole.

4. The construction method for rock-embedded construction of offshore wind power high pile cap foundation according to claim 3 is characterized by: A centralizer (8) is added to the connected drill pipe every 10 meters.

5. The construction method applicable to rock-embedded construction of offshore wind power high pile cap foundation according to claim 1, characterized in that: A winch (6) is installed on the top side of the large frame (2).

6. The construction method for rock-embedded construction of offshore wind power high pile cap foundation according to claim 1, characterized in that: Lifting legs (41) are arranged at the four corners of the walking chassis (4), and walking plates (42) are arranged at the middle positions of the four lower parts of the walking chassis (4). Automatic alignment walking is achieved by alternately cooperating between the lifting legs (41) and the walking plates (42).

7. The construction method for rock-embedded construction of offshore wind power high pile cap foundation according to claim 1, characterized in that: The lifting force of the hydraulic lifting mechanism (3) meets the auxiliary lifting requirements of the rock-embedded inclined pile construction of the high pile cap foundation under existing conditions, and the lifting force of the hydraulic lifting mechanism (3) is not unique and can be adjusted and increased in a timely manner according to subsequent needs.