A natural gas pre-energized fracturing device and process
By using natural gas as energy-enhancing gas in fracturing technology and using the pressurization technology of primary tool wells and secondary tool wells, the problems of corrosiveness and low energy storage of energy-enhancing gas in the existing technology are solved, achieving high efficiency crude oil recovery and low cost high pressure gas injection.
Patent Information
- Application Number
- CN202010694007.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-07-17
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2040-07-17
AI Technical Summary
In the existing gas pre-energized fracturing technology, CO2 or N2 as energy-energized gas has problems such as corrosiveness, high gas injection cost, environmental pollution and low energy storage, and it is difficult to meet the requirements of large displacement and high pressure.
Using natural gas as energy-enhancing gas, natural gas is supercharged through primary tool wells and secondary tool wells, and multiple boosts are used to increase pressure, combined with the recycling of fracturing fluid, reducing dependence on compressors and achieving large-scale , high pressure gas injection.
Natural gas can be dissolved in crude oil, reduce viscosity, form mixed phase flooding, improve crude oil recovery, and reduce residual oil saturation. Natural gas sources are wide and cheap, meeting the needs of large displacement and high pressure.
Smart Images

Figure CN111749670B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of fracturing, and in particular to a natural gas pre-energized fracturing device and process. Background Art
[0002] Gas pre-energized fracturing technology refers to injecting a certain amount of gas into the perforation section after single-stage perforation and before staged fracturing on the basis of conventional water-based fracturing fluid, using the elastic energy of the gas and its ability to form a miscible drive with crude oil to replenish energy for the formation and improve the recovery rate of tight oil. At the same time, since the gas has basically no damage to the oil layer, it can improve the return efficiency of the fracturing fluid and reduce the damage of the fracturing fluid to the oil layer, thereby improving the seepage capacity of the fracture and increasing the production capacity of the oil well. At present, gas pre-energized fracturing mainly uses CO 2 or N 2 As an energizing gas, CO can improve the fracturing effect, but 2 or N 2 It will cause severe corrosion to ground equipment, pipelines and wellbore, and requires special equipment to produce. The gas injection cost is high. It is useless after extraction and has certain pollution to the environment. In addition, the gas injection is limited by the power of the compressor or high-pressure pump, resulting in low energy storage, low injection pressure and small displacement of a single gas injection. Summary of the invention
[0003] The purpose of the present invention is to overcome the shortcomings of the prior art and provide a natural gas pre-energized fracturing device and process, which uses natural gas as the energizing gas. Natural gas can be dissolved in crude oil to expand the crude oil and reduce viscosity; a miscible drive can be formed in the reservoir, the interfacial tension is reduced, the capillary number is increased, and the residual oil saturation is greatly reduced, thereby helping to improve the crude oil recovery rate; natural gas has a wide source, is low in price, is convenient and fast, and has the best benefits; a first-level tool well and a second-level tool well are used to pressurize the natural gas to increase the single gas storage capacity of the tool well. The pressurization effect is not limited by the power of the compressor, the single gas injection volume is large, and the dependence on the compressor is reduced. At the same time, the pressure can be further increased by multiple pressurizations to meet the requirements of large displacement and high pressure.
[0004] The objective of the present invention is achieved through the following technical measures: a natural gas pre-energized fracturing device, comprising a natural gas source, a compressor, a primary tool well, a secondary tool well, a fracturing vehicle, a liquid tank and a fracturing well, wherein the primary tool well and the secondary tool well are both provided with a gas phase inlet, a gas phase outlet, a liquid phase inlet and a liquid phase outlet, the natural gas source and the compressor are connected in sequence, the compressor is also connected to the gas phase inlets of the primary tool well and the secondary tool well, respectively, the gas phase outlets of the primary tool well and the secondary tool well are both connected to the fracturing well, the fracturing vehicle is connected to the liquid phase inlets of the primary tool well and the secondary tool well, respectively, the liquid phase outlets of the primary tool well and the secondary tool well are both connected to the liquid tank, there are more than one secondary tool well, and a plurality of secondary tool wells are connected in parallel.
[0005] Furthermore, the first-level tool well and the second-level tool well both include casing, oil pipes and wellheads. The wellheads are provided with a gas inlet, a gas outlet, a liquid inlet and a liquid outlet. The gas inlet and the gas outlet are respectively connected to one end of the casing, and the other end of the casing extends into the bottom of the well and is sealed. The liquid inlet and the liquid outlet are respectively connected to one end of the oil pipe, and the other end of the oil pipe extends into the casing and is connected to the casing.
[0006] Furthermore, the fracturing truck is also connected to a liquid tank.
[0007] Furthermore, the natural gas source is a CNG tank truck or a natural gas transmission pipeline.
[0008] Furthermore, the gas phase inlet, gas phase outlet, liquid phase inlet, liquid phase outlet of the first tool well and the second tool well and the inlet end of the fracturing well are all provided with safety valves.
[0009] Furthermore, the safety valves can be remotely controlled.
[0010] A natural gas pre-energized fracturing process comprises the following steps:
[0011] (1) Gas injection into the primary tool well and the secondary tool well: The natural gas is pressurized by the compressor and transported to the gas phase inlets of the primary tool well and the secondary tool well, respectively. The primary tool well and the secondary tool well are filled with natural gas. At the same time, the natural gas discharges the fracturing fluid in the primary tool well and the secondary tool well into the liquid tank through the liquid phase outlets of the primary tool well and the secondary tool well;
[0012] (2) Secondary tool well pressurization: The fracturing truck transports the fracturing fluid to the primary tool well through the liquid phase inlet of the primary tool well. The fracturing fluid enters the primary tool well and discharges the natural gas from the gas phase outlet of the primary tool well through the gas phase outlet of the secondary tool well into the secondary tool well. The natural gas pressure in the secondary tool well increases. After the secondary tool well is pressurized, the natural gas source is re-injected into the primary tool well through the compressor, completing the single pressurization of the secondary tool well.
[0013] (3) Gas injection into the fracturing well: After the secondary tool well has been pressurized at least once, the fracturing truck first transports the fracturing fluid into the primary tool well through the liquid phase inlet of the primary tool well, and first discharges the natural gas in the primary tool well into the fracturing well through the gas phase outlet of the primary tool well. Then, the fracturing truck transports the fracturing fluid into the secondary tool well through the liquid phase inlet of the secondary tool well, and discharges the pressurized natural gas in the secondary tool well into the fracturing well through the gas phase outlet of the secondary tool well, thereby completing a single gas injection into the fracturing well.
[0014] Furthermore, after the secondary tool well is pressurized in step (2), the primary tool well is depressurized first, and then the natural gas source is re-injected into the primary tool well via the compressor.
[0015] Furthermore, when there are multiple secondary tool wells, after the primary tool well in step (2) injects gas into multiple secondary tool wells for pressurization, the natural gas source is re-injected into the primary tool well through the compressor to complete the single pressurization of the secondary tool well.
[0016] Furthermore, when there are multiple secondary tool wells, one of the secondary tool wells can pressurize any other secondary tool well.
[0017] Compared with the prior art, the present invention has the following beneficial effects: natural gas is used as the energizing gas, and the natural gas can be dissolved in crude oil to expand the crude oil and reduce the viscosity; a miscible drive can be formed in the reservoir, the interfacial tension is reduced, the capillary number is increased, and the residual oil saturation is greatly reduced, thereby helping to improve the crude oil recovery rate; natural gas is widely available, inexpensive, convenient, fast and has the best benefits; the first-level tool well and the second-level tool well are used to pressurize the natural gas to increase the single gas storage capacity of the tool well, the pressurization effect is not limited by the power of the compressor, the single gas injection volume is large, and the dependence on the compressor is reduced. At the same time, the pressure can be further increased through multiple pressurization to meet the requirements of large displacement and high pressure.
[0018] The present invention is described in detail below with reference to the accompanying drawings and specific embodiments. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a structural schematic diagram of a natural gas pre-energized fracturing device with one secondary tool well.
[0020] Figure 2 It is a structural schematic diagram of a natural gas pre-energized fracturing device with two secondary tool wells.
[0021] Among them, 1. CNG tank truck, 2. compressor, 3. first-level tool well, 4. second-level tool well, 5. fracturing truck, 6. liquid tank, 7. fracturing well, 8. first safety valve, 9. second safety valve, 10. third safety valve, 11. fourth safety valve, 12. sixth safety valve, 13. fifth safety valve, 14. seventh safety valve, 15. eighth safety valve, 16. ninth safety valve, 17. first and second-level tool wells, 18. second and second-level tool wells, 19. tenth safety valve, 20. eleventh safety valve, 21. twelfth safety valve, 22. thirteenth safety valve. DETAILED DESCRIPTION
[0022] like Figures 1 to 2As shown, a natural gas pre-energized fracturing device includes a natural gas source, a compressor 2, a primary tool well 3, a secondary tool well 4, a fracturing vehicle 5, a liquid tank 6 and a fracturing well 7. The primary tool well 3 and the secondary tool well 4 are both provided with a gas phase inlet, a gas phase outlet, a liquid phase inlet and a liquid phase outlet. The natural gas source is a CNG tanker 1 or a natural gas transmission pipeline. The natural gas source and the compressor 2 are connected in sequence, and the compressor 2 is also connected to the gas phase inlets of the primary tool well 3 and the secondary tool well 4 respectively. Specifically, the compressor 2 is used to inject natural gas into the primary tool well 3 and the secondary tool well 4. The gas phase outlets of the primary tool well 3 and the secondary tool well 4 are both connected to the fracturing well 7. Specifically, the primary tool well 3 and the secondary tool well 4 are used to inject natural gas into the fracturing well 7. The fracturing vehicle 5 is respectively connected to the liquid phase inlets of the primary tool well 3 and the secondary tool well 4, and the liquid phase outlets of the primary tool well 3 and the secondary tool well 4 are both connected to the liquid tank 6. There are more than one secondary tool well 4, and multiple secondary tool wells 4 are connected in parallel. The first-level tool well 3 and the second-level tool well 4 are used to pressurize the natural gas to increase the single gas storage capacity of the tool well. The pressurization effect is not limited by the power of the compressor, the single gas injection volume is large, and the dependence on the compressor 2 is reduced.
[0023] The first-level tool well 3 and the second-level tool well 4 both include casing, oil pipe and wellhead, and the wellhead is provided with a gas phase inlet, a gas phase outlet, a liquid phase inlet and a liquid phase outlet, the gas phase inlet and the gas phase outlet are respectively connected to one end of the casing, the other end of the casing extends into the bottom of the well and is sealed, the liquid phase inlet and the liquid phase outlet are respectively connected to one end of the oil pipe, the other end of the oil pipe extends into the casing and communicates with the casing. Specifically, the diameter, wall thickness and material of the casing and oil pipe of the first-level tool well 3 and the second-level tool well 4 as well as the well depth can be set according to the actual fracturing gas injection requirements. Natural gas can enter the casing from the gas phase inlet and discharge the fracturing fluid in the casing into the liquid tank through the oil pipe and the liquid phase outlet. The fracturing fluid can enter the oil pipe from the liquid phase inlet and can enter the casing from the oil pipe to discharge the natural gas in the casing from the gas phase outlet to the fracturing well 7. Moreover, the fracturing fluid can enter the oil pipe of the first-level tool well 3 from the liquid phase inlet of the first-level tool well 3 and enter the casing from the oil pipe to discharge the natural gas in the casing from the gas phase outlet of the first-level tool well 3 through the gas phase outlet of the second-level tool well 4 to the casing of the second-level tool well 4 to pressurize the second-level tool well 4.
[0024] The fracturing vehicle 5 is also connected to a liquid tank 6. The liquid tank 6 can supply liquid to the fracturing vehicle 5 to achieve the recycling of the fracturing fluid.
[0025] The gas phase inlet, gas phase outlet, liquid phase inlet, liquid phase outlet of the first-level tool well 3 and the second-level tool well 4 and the inlet end of the fracturing well 7 are all provided with safety valves. Specifically, a first safety valve 8 is provided between the compressor 2 and the gas phase inlet of the first-level tool well 3, a second safety valve 9 is provided between the compressor 2 and the gas phase inlet of the second-level tool well 4, a third safety valve 10 is provided between the gas phase outlet of the first-level tool well 3 and the fracturing well 7, a fourth safety valve 11 is provided between the gas phase outlet of the second-level tool well 4 and the fracturing well 7, a fifth safety valve 13 is provided between the fracturing vehicle 5 and the liquid phase inlet of the first-level tool well 3, a sixth safety valve 12 is provided between the fracturing vehicle 5 and the liquid phase inlet of the second-level tool well 4, a seventh safety valve 14 is provided between the liquid phase outlet of the first-level tool well 3 and the liquid tank 6, an eighth safety valve 15 is provided between the liquid phase outlet of the second-level tool well 4 and the liquid tank 6, a ninth safety valve 16 is provided at the inlet end of the fracturing well 7, and when there are multiple second-level tool wells 4, four safety valves are added for each additional second-level tool well 4.
[0026] The safety valves can be remotely controlled. The opening and closing of all safety valves can be remotely controlled by a remote control system, avoiding on-site manual operation, saving manpower, and reducing the safety risks of manual operation, with a high safety factor.
[0027] A natural gas pre-energized fracturing process comprises the following steps:
[0028] (1) Gas injection into the primary tool well 3 and the secondary tool well 4: The natural gas is pressurized by the compressor 2 and transported to the gas phase inlets of the primary tool well 3 and the secondary tool well 4, respectively. The primary tool well 3 and the secondary tool well 4 are filled with natural gas. At the same time, the natural gas discharges the fracturing fluid in the primary tool well 3 and the secondary tool well 4 into the liquid tank 6 through the liquid phase outlets of the primary tool well 3 and the secondary tool well 4;
[0029] (2) Pressurization of the secondary tool well 4: The fracturing truck 5 transports the fracturing fluid to the primary tool well 3 through the liquid phase inlet of the primary tool well 3. The fracturing fluid enters the primary tool well 3 and discharges the natural gas from the gas phase outlet of the primary tool well 3 through the gas phase outlet of the secondary tool well 4 into the secondary tool well 4. The natural gas pressure in the secondary tool well 4 increases. After the secondary tool well 4 is pressurized, the natural gas source is re-injected into the primary tool well 3 through the compressor 2, completing the single pressurization of the secondary tool well 4.
[0030] (3) Gas injection into the fracturing well: After the secondary tool well 4 is pressurized at least once, the pressurization times of the secondary tool well 4 can be selected according to the pressure bearing capacity of the secondary tool well 4 and the gas injection pressure requirement of the fracturing well 7. The fracturing truck 5 first delivers the fracturing fluid to the primary tool well 3 through the liquid phase inlet of the primary tool well 3, and first discharges the natural gas in the primary tool well 3 into the fracturing well 7 through the gas phase outlet of the primary tool well 3. Then, the fracturing truck 5 delivers the fracturing fluid to the secondary tool well 4 through the liquid phase inlet of the secondary tool well 4, and discharges the pressurized natural gas in the secondary tool well 4 into the fracturing well 7 through the gas phase outlet of the secondary tool well 4, thus completing a single gas injection into the fracturing well 7.
[0031] After the secondary tool well 4 is pressurized in step (2), the primary tool well 3 is first depressurized, and then the natural gas source is re-injected into the primary tool well 3 via the compressor 2. After the secondary tool well 4 is pressurized, the pressure of the fracturing fluid in the primary tool well 3 is the same as the pressure of the natural gas in the secondary tool well 4. Depressurizing the primary tool well 3 first can avoid damage to the compressor 2 when the compressor 2 re-injects natural gas into the primary tool well 3.
[0032] When there are multiple secondary tool wells 4, in step (2), after the primary tool well 3 respectively injects gas into the multiple secondary tool wells 4 for pressurization, the natural gas source is re-injected into the primary tool well 3 through the compressor 2 to complete the single pressurization of the secondary tool well 4. Specifically, the primary tool well 3 injects gas into the multiple secondary tool wells 4 in sequence, and after all the secondary tool wells 4 are pressurized, the natural gas source is re-injected into the primary tool well 3 through the compressor 2 to complete the single pressurization of all the secondary tool wells 4. Specifically, the number of pressurization times of the secondary tool well 4 can be selected according to the injection pressure requirement of the fracturing well 7.
[0033] When there are multiple secondary tool wells 4, one of the secondary tool wells 4 can increase the pressure of any other secondary tool well 4. Specifically, whether a single secondary tool well 4 needs to be used to increase the pressure of other secondary tool wells 4 can be determined according to the pressure bearing capacity of the secondary tool well 4 and the gas injection pressure requirement of the fracturing well 7.
[0034] Example 1
[0035] like Figure 1 As shown, this embodiment is a natural gas pre-energized fracturing device equipped with one secondary tool well 4.
[0036] A natural gas pre-energized fracturing device comprises a natural gas source, a compressor 2, a primary tool well 3, a secondary tool well 4, a fracturing truck 5, a liquid tank 6 and a fracturing well 7. The primary tool well 3 and the secondary tool well 4 are both provided with a gas phase inlet, a gas phase outlet, a liquid phase inlet and a liquid phase outlet. The natural gas source is a CNG tank truck 1. The natural gas source and the compressor 2 are connected in sequence. The compressor 2 is connected to the gas phase inlets of the primary tool well 3 and the secondary tool well 4 through a first safety valve 8 and a second safety valve 9, respectively. The gas phase outlets of the primary tool well 3 and the secondary tool well 4 are connected to the fracturing well 7 through a third safety valve 10 and a fourth safety valve 11, respectively. A ninth safety valve 16 is further provided between the third safety valve 10 and the fourth safety valve 11 and the fracturing well 7. The fracturing truck 5 is connected to the liquid phase inlets of the primary tool well 3 and the secondary tool well 4 through the fifth safety valve 13 and the sixth safety valve 12 respectively, and the liquid phase outlets of the primary tool well 3 and the secondary tool well 4 are connected to the liquid tank 6 through the seventh safety valve 14 and the eighth safety valve 15 respectively, and the fracturing truck 5 is also connected to the liquid tank 6.
[0037] The first-level tool well 3 and the second-level tool well 4 both include casing, oil pipe and wellhead. The wellhead is provided with a gas phase inlet, a gas phase outlet, a liquid phase inlet and a liquid phase outlet. The gas phase inlet and the gas phase outlet are respectively connected to one end of the casing, and the other end of the casing extends into the bottom of the well and is sealed. The liquid phase inlet and the liquid phase outlet are respectively connected to one end of the oil pipe, and the other end of the oil pipe extends into the casing and is connected to the casing.
[0038] The first safety valve 8 , the second safety valve 9 , the third safety valve 10 , the fourth safety valve 11 , the fifth safety valve 13 , the sixth safety valve 12 , the seventh safety valve 14 , the eighth safety valve 15 and the ninth safety valve 16 can all be remotely controlled.
[0039] Working principle:
[0040] Gas injection in the first-level tool well 3 and the second-level tool well 4: close the third safety valve 10, the fourth safety valve 11, the fifth safety valve 13, the sixth safety valve 12 and the ninth safety valve 16, open the first safety valve 8, the second safety valve 9, the seventh safety valve 14 and the eighth safety valve 15, the natural gas in the CNG tank truck 1 is compressed by the compressor 2, enters the first-level tool well 3 through the first safety valve 8, and the fracturing fluid in the first-level tool well 3 is discharged from the seventh safety valve 14 to the liquid tank 6, and the first-level tool well 3 is injected with gas. At the same time, the compressed natural gas enters the second-level tool well 4 through the second safety valve 9, and the fracturing fluid in the second-level tool well 4 is discharged from the eighth safety valve 15 to the liquid tank 6, and the second-level tool well 4 is injected with gas.
[0041] Pressurization of the secondary tool well 4: close the first safety valve 8, the second safety valve 9, the sixth safety valve 12, the seventh safety valve 14, the eighth safety valve 15 and the ninth safety valve 16, open the fifth safety valve 13, the third safety valve 10 and the fourth safety valve 11, the fracturing truck 5 injects the fracturing fluid into the primary tool well 3, the natural gas in the primary tool well 3 is discharged to the secondary tool well 4 through the third safety valve 10 and the fourth safety valve 11 by the fracturing fluid, the natural gas in the secondary tool well 4 is pressurized, and the single pressurization of the secondary tool well 4 is completed, then close the third safety valve 10, the fourth safety valve 11 and the fifth safety valve 13, open the seventh safety valve 14, the fracturing fluid in the primary tool well 3 enters the liquid tank 6 through the seventh safety valve 14, the primary tool well 3 is depressurized, and after the pressure is released, the first safety valve 8 is opened, the natural gas is compressed by the compressor 2, enters the primary tool well 3 through the first safety valve 8, and the fracturing fluid in the primary tool well 3 is discharged to the liquid tank 6 through the seventh safety valve 14, and the primary tool well 3 is re-injected with gas.
[0042] Gas injection into fracturing well 7: close the first safety valve 8, the second safety valve 9, the fourth safety valve 11, the sixth safety valve 12, the seventh safety valve 14 and the eighth safety valve 15, open the fifth safety valve 13, the third safety valve 10 and the ninth safety valve 16, the fracturing truck 5 injects the fracturing fluid into the primary tool well 3 through the fifth safety valve 13 and discharges the natural gas in the primary tool well 3 into the fracturing well 7 through the third safety valve 10 and the ninth safety valve 16, completing the gas injection into the primary tool well 3. Then close the fifth safety valve 13 and the third safety valve 10, open the sixth safety valve 12 and the fourth safety valve 11, the fracturing truck 5 injects the fracturing fluid into the secondary tool well 4 through the sixth safety valve 12 and discharges the natural gas in the secondary tool well 4 into the fracturing well 7 through the fourth safety valve 11 and the ninth safety valve 16, completing the gas injection into the secondary tool well 4, and realizing the single gas injection into the fracturing well 7.
[0043] Example 2
[0044] Embodiment 2 is a natural gas pre-energized fracturing device with two secondary tool wells 4. Different from Embodiment 1, the natural gas pre-energized fracturing device further includes a tenth safety valve 19, an eleventh safety valve 20, a twelfth safety valve 21 and a thirteenth safety valve 22, the secondary tool well 4 includes a first secondary tool well 17 and a second secondary tool well 18, the first secondary tool well 17 and the second secondary tool well 18 are connected in parallel, the compressor 2 is connected to the gas phase inlet of the first secondary tool well 17 through the second safety valve 9, the compressor 2 is connected to the gas phase inlet of the second secondary tool well 18 through the tenth safety valve 19, the gas phase outlet of the first secondary tool well 17 is connected to the fracturing well 7 through the fourth safety valve 11, the gas phase outlet of the second secondary tool well 18 is connected to the fracturing well 7 through the eleventh safety valve 20, and a ninth safety valve 16 is further provided between the third safety valve 10, the fourth safety valve 11 and the eleventh safety valve 20 and the fracturing well 7. The fracturing truck 5 is connected to the liquid phase inlet of the first secondary tool well 17 through the sixth safety valve 12, and the fracturing truck 5 is connected to the liquid phase inlet of the second secondary tool well 18 through the twelfth safety valve 21. The liquid phase outlet of the first secondary tool well 17 is connected to the liquid tank 6 through the eighth safety valve 15, and the liquid phase outlet of the second secondary tool well 18 is connected to the liquid tank 6 through the thirteenth safety valve 22.
[0045] The first safety valve 8, the second safety valve 9, the third safety valve 10, the fourth safety valve 11, the fifth safety valve 13, the sixth safety valve 12, the seventh safety valve 14, the eighth safety valve 15, the ninth safety valve 16, the tenth safety valve 19, the eleventh safety valve 20, the twelfth safety valve 21 and the thirteenth safety valve 22 can all be remotely controlled.
[0046] Working principle:
[0047] Gas injection in the first-level tool well 3 and the second-level tool well 4: close the third safety valve 10, the fourth safety valve 11, the fifth safety valve 13, the sixth safety valve 12, the ninth safety valve 16, the eleventh safety valve 20 and the twelfth safety valve 21, open the first safety valve 8, the second safety valve 9, the seventh safety valve 14, the eighth safety valve 15, the tenth safety valve 19 and the thirteenth safety valve 22, the natural gas in the CNG tank truck 1 is compressed by the compressor 2, enters the first-level tool well 3 through the first safety valve 8, and the fracturing fluid in the first-level tool well 3 is discharged from the seventh safety valve 14 to the liquid tank 6, and the first-level tool well 3 is injected with gas. At the same time, the compressed natural gas enters the first and second-level tool wells 17 through the second safety valve 9, and the fracturing fluid in the first and second-level tool wells 17 is discharged from the eighth safety valve 15 to the liquid tank 6, and the first and second-level tool wells 17 are injected with gas. At the same time, the compressed natural gas enters the second-level tool well 18 through the tenth safety valve 19 and discharges the fracturing fluid in the second-level tool well 18 into the liquid tank 6 through the thirteenth safety valve 22, and the second-level tool well 18 is injected with gas.
[0048] Secondary tool well pressurization: close the first safety valve 8, the second safety valve 9, the sixth safety valve 12, the seventh safety valve 14, the eighth safety valve 15, the ninth safety valve 16, the tenth safety valve 19, the eleventh safety valve 20, the twelfth safety valve 21 and the thirteenth safety valve 22, open the fifth safety valve 13, the third safety valve 10 and the fourth safety valve 11, the fracturing truck 5 injects fracturing fluid into the primary tool well 3, the natural gas in the primary tool well 3 is discharged to the first and second tool wells 17 by the fracturing fluid through the third safety valve 10 and the fourth safety valve 11, and the The natural gas in the first and second level tool wells 17 is pressurized to complete single pressurization of the first and second level tool wells 17, and then the third safety valve 10, the fourth safety valve 11 and the fifth safety valve 13 are closed, and the seventh safety valve 14 is opened, and the fracturing fluid in the first level tool well 3 enters the liquid tank 6 through the seventh safety valve 14, and the first level tool well 3 is depressurized. After the pressure is released, the first safety valve 8 is opened, and the natural gas is compressed by the compressor 2 and enters the first level tool well 3 through the first safety valve 8, and the fracturing fluid in the first level tool well 3 is discharged to the liquid tank 6 through the seventh safety valve 14, and the first level tool well 3 is re-injected with gas. Close the first safety valve 8, the second safety valve 9, the fourth safety valve 11, the sixth safety valve 12, the seventh safety valve 14, the eighth safety valve 15, the ninth safety valve 16, the tenth safety valve 19, the twelfth safety valve 21 and the thirteenth safety valve 22, open the fifth safety valve 13, the third safety valve 10 and the eleventh safety valve 20, the fracturing truck 5 injects fracturing fluid into the first-level tool well 3, the natural gas in the first-level tool well 3 is discharged to the second-level tool well 18 by the fracturing fluid through the third safety valve 10 and the eleventh safety valve 20, the natural gas in the second-level tool well 18 is pressurized, and the second The secondary tool well 18 is pressurized once, and then the third safety valve 10, the eleventh safety valve 20 and the fifth safety valve 13 are closed, and the seventh safety valve 14 is opened. The fracturing fluid in the primary tool well 3 enters the liquid tank 6 through the seventh safety valve 14, and the primary tool well 3 is depressurized. After the pressure is released, the first safety valve 8 is opened, and the natural gas is compressed by the compressor 2 and enters the primary tool well 3 through the first safety valve 8, and the fracturing fluid in the primary tool well 3 is discharged to the liquid tank 6 through the seventh safety valve 14, and the primary tool well 3 is re-injected with gas, realizing the single pressurization process of the first and second secondary tool wells 17 and the second and second secondary tool wells 18.
[0049] Gas injection into the fracturing well: close the first safety valve 8, the second safety valve 9, the fourth safety valve 11, the sixth safety valve 12, the seventh safety valve 14, the eighth safety valve 15, the tenth safety valve 19, the eleventh safety valve 20, the twelfth safety valve 21 and the thirteenth safety valve 22, open the fifth safety valve 13, the third safety valve 10 and the ninth safety valve 16, and the fracturing truck 5 injects the fracturing fluid into the first-level tool well 3 through the fifth safety valve 13 and discharges the natural gas in the first-level tool well 3 into the fracturing well 7 through the third safety valve 10 and the ninth safety valve 16, completing the gas injection into the first-level tool well 3. Then close the fifth safety valve 13 and the third safety valve 10, open the sixth safety valve 12 and the fourth safety valve 11, and the fracturing truck 5 injects the fracturing fluid into the first-level and second-level tool wells 17 through the sixth safety valve 12 and discharges the natural gas in the first-level and second-level tool wells 17 into the fracturing well 7 through the fourth safety valve 11 and the ninth safety valve 16, completing the gas injection into the first-level and second-level tool wells 17. Then the fourth safety valve 11 and the sixth safety valve 12 are closed, the twelfth safety valve 21 and the eleventh safety valve 20 are opened, and the fracturing truck 5 injects the fracturing fluid into the second secondary tool well 18 through the twelfth safety valve 21 and discharges the natural gas in the second secondary tool well 18 into the fracturing well 7 through the eleventh safety valve 20 and the ninth safety valve 16, completing the gas injection into the second secondary tool well 18. A single gas injection into the fracturing well 7 is achieved.
[0050] In the actual operation process, during the process of pressurizing the secondary tool well 4, after the first secondary tool well 17 and the second secondary tool well 18 are pressurized, the first safety valve 8, the second safety valve 9, the third safety valve 10, the fifth safety valve 13, the seventh safety valve 14, the eighth safety valve 15, the ninth safety valve 16, the tenth safety valve 19, the twelfth safety valve 21 and the thirteenth safety valve 22 can be closed, and the sixth safety valve 12, the fourth safety valve 11 and the eleventh safety valve 22 can be opened according to the pressure bearing capacity of the first secondary tool well 17 and / or the second secondary tool well 18 and the gas injection pressure requirement of the fracturing well 7. 0, so that the fracturing fluid can discharge the pressurized natural gas in the first and second level tool wells 17 into the second and second level tool wells 18 for re-pressurization, or close the first safety valve 8, the second safety valve 9, the third safety valve 10, the fifth safety valve 13, the sixth safety valve 12, the seventh safety valve 14, the eighth safety valve 15, the ninth safety valve 16, the tenth safety valve 19 and the thirteenth safety valve 22, and open the twelfth safety valve 21, the fourth safety valve 11 and the eleventh safety valve 20, so that the fracturing fluid can discharge the pressurized natural gas in the second and second level tool wells 18 into the first and second level tool wells 17 for re-pressurization.
[0051] Those skilled in the art should understand that the present invention is not limited to the above embodiments, and the above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, and these changes and improvements fall within the scope of the present invention to be protected. The scope of protection of the present invention is defined by the attached claims and their equivalents.
Claims
1. A natural gas pre-energized fracturing device, characterized in that: It includes a natural gas source, a compressor, a primary tool well, a secondary tool well, a fracturing vehicle, a liquid tank and a fracturing well. The primary tool well and the secondary tool well are both provided with a gas phase inlet, a gas phase outlet, a liquid phase inlet and a liquid phase outlet. The natural gas source and the compressor are connected in sequence. The compressor is also connected to the gas phase inlets of the primary tool well and the secondary tool well respectively. The gas phase outlets of the primary tool well and the secondary tool well are both connected to the fracturing well. The fracturing vehicle is connected to the liquid phase inlets of the primary tool well and the secondary tool well respectively. The liquid phase outlets of the primary tool well and the secondary tool well are both connected to the liquid tank. The gas phase outlet of the primary tool well is connected to the gas phase outlet of the secondary tool well. The primary tool well is used to inject gas into the fracturing well and pressurize the secondary tool well. There are more than one secondary tool wells. When there are multiple secondary tool wells, the multiple secondary tool wells are connected in parallel.
2. The natural gas pre-energized fracturing device according to claim 1, characterized in that: The first-level tool well and the second-level tool well both include casing, oil pipe and wellhead. The wellhead is provided with a gas phase inlet, a gas phase outlet, a liquid phase inlet and a liquid phase outlet. The gas phase inlet and the gas phase outlet are respectively connected to one end of the casing, and the other end of the casing extends into the bottom of the well and is sealed. The liquid phase inlet and the liquid phase outlet are respectively connected to one end of the oil pipe, and the other end of the oil pipe extends into the casing and is connected to the casing.
3. The natural gas pre-energized fracturing device according to claim 1, characterized in that: The fracturing vehicle is also connected to a liquid tank.
4. The natural gas pre-energized fracturing device according to claim 1, characterized in that: The natural gas source is a CNG tank truck or a natural gas transmission pipeline.
5. The natural gas pre-energized fracturing device according to claim 1, characterized in that: The gas phase inlet, gas phase outlet, liquid phase inlet, liquid phase outlet of the first-level tool well and the second-level tool well and the inlet end of the fracturing well are all provided with safety valves.
6. The natural gas pre-energized fracturing device according to claim 5, characterized in that: The safety valves can be remotely controlled.
7. A natural gas pre-energized fracturing process, based on the natural gas pre-energized fracturing device according to any one of claims 1 to 6, characterized in that: The steps include: (1) Gas injection into the primary tool well and the secondary tool well: natural gas is pressurized by a compressor and transported to the gas phase inlets of the primary tool well and the secondary tool well, respectively. The primary tool well and the secondary tool well are filled with natural gas. At the same time, the natural gas discharges the fracturing fluid in the primary tool well and the secondary tool well into the liquid tank through the liquid phase outlets of the primary tool well and the secondary tool well; (2) Secondary tool well pressurization: The fracturing truck transports the fracturing fluid to the primary tool well through the liquid phase inlet of the primary tool well. The fracturing fluid enters the primary tool well and discharges the natural gas from the gas phase outlet of the primary tool well through the gas phase outlet of the secondary tool well into the secondary tool well. The natural gas pressure in the secondary tool well increases. After the secondary tool well is pressurized, the natural gas source is re-injected into the primary tool well through the compressor, completing the single pressurization of the secondary tool well. (3) Gas injection into the fracturing well: After the secondary tool well has been pressurized at least once, the fracturing truck first transports the fracturing fluid into the primary tool well through the liquid phase inlet of the primary tool well, and first discharges the natural gas in the primary tool well into the fracturing well through the gas phase outlet of the primary tool well. Then, the fracturing truck transports the fracturing fluid into the secondary tool well through the liquid phase inlet of the secondary tool well, and discharges the pressurized natural gas in the secondary tool well into the fracturing well through the gas phase outlet of the secondary tool well, thereby completing a single gas injection into the fracturing well.
8. The natural gas pre-energized fracturing process according to claim 7, characterized in that: After the secondary tool well is pressurized in step (2), the primary tool well is depressurized first, and then the natural gas source is re-injected into the primary tool well via the compressor.
9. The natural gas pre-energized fracturing process according to claim 7, characterized in that: When there are multiple secondary tool wells, in step (2), after the primary tool well is pressurized by gas injection into multiple secondary tool wells respectively, the natural gas source is re-injected into the primary tool well through the compressor to complete the single pressurization of the secondary tool well.
10. The natural gas pre-energized fracturing process according to claim 7, characterized in that: When there are multiple secondary tool wells, one of the secondary tool wells can boost the pressure of any other secondary tool well.