Model box for simulating tunnel excavation, tunnel excavation simulation system and method

By designing an adjustable model box structure and a tunnel excavation simulation system, we solve the problem that the model box in the existing technology can only simulate a single working condition, realize the simulation and data recording of tunnel excavation in multiple working conditions, and improve the experimental efficiency. flexibility and resource utilization.

CN111751515BActive Publication Date: 2024-10-18CHANGSHA UNIVERSITY OF SCIENCE AND TECHNOLOGY
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202010668545.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-07-13
Publication Date
2024-10-18
Estimated Expiration
2040-07-13

AI Technical Summary

Technical Problem

The existing model box can only simulate one working condition, resulting in a waste of resources and inflexibility of experimental design, making it difficult to meet the simulation needs of tunnel excavation in multiple working conditions.

Method used

A model box with a top opening and a closed bottom is designed. It adopts a double-layer frame structure and transparent plates, combined with an adjusting bolt group and a semicircular bolt group. It can simulate a variety of tunnel excavation conditions and is equipped with a tunnel excavation simulation system and detection system. Device to realize various working conditions simulation and data recording of tunnel excavation process.

Benefits of technology

It realizes the simulation of tunnel excavation under various working conditions, avoids waste of resources, improves the practicality and data collection capabilities of the experiment, and enables designers to more accurately infer the safety and feasibility of actual construction plans.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111751515B_ABST
    Figure CN111751515B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of tunnel and underground engineering construction test, and in particular to a model box for simulating tunnel excavation, a tunnel excavation simulation system and a method, wherein the tunnel excavation model box comprises a box body (1) with an open top and a closed bottom, wherein both pairs of side walls of the box body (1) are double-layer frame structures, and the interlayer of the double-layer frame structure is suitable for accommodating a transparent plate; wherein a pair of oppositely disposed side walls are each provided with a transverse latch path; and the other pair of oppositely disposed side walls are each provided with a longitudinal latch path, wherein the transverse latch path and the longitudinal latch path are each suitable for accommodating a latch, wherein the latch comprises a position adjustment latch group (22) and a semicircular latch group (23); and after the transparent plate is matched with the interlayer and the latch is matched with each of the latch paths, the side walls can form an integrally closed structure. The model box for simulating tunnel excavation of the present invention can simulate tunnel excavation under various working conditions and has good practicality.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of tunnel and underground engineering construction test, and in particular to a model box for simulating tunnel excavation. In addition, the present invention also relates to a tunnel excavation simulation system and method. Background Art

[0002] Model test, which takes the principle of similarity as its theoretical basis, is an early developed, widely used, and intuitive research method for geotechnical media, engineering structures, and physical and mechanical properties.

[0003] Model tests can simulate various relatively complex boundary conditions, and can comprehensively and vividly present the overall picture of the stress and deformation mechanism, failure mechanism, morphology and instability stage under the joint action of engineering structures and related rock and soil masses.

[0004] For a long time, model test method has been an important means to study and solve large and complex tunnel engineering projects. For model test, the most critical part is the production of model box. At present, most model boxes in the existing technology can only simulate one working condition, resulting in great waste of model boxes.

[0005] In view of this, it is necessary to provide a model box for simulating tunnel excavation. Summary of the invention

[0006] The technical problem to be solved by the first aspect of the present invention is to provide a model box for simulating tunnel excavation. The model box for simulating tunnel excavation can simulate tunnel excavation under various working conditions, has strong practicality, and avoids the waste of resources caused by designing one model box for one working condition experiment.

[0007] The technical problem to be solved by the second aspect of the present invention is to provide a tunnel excavation simulation system, which can simulate the tunnel excavation process under various working conditions, and can detect and record various experimental data in the simulated tunnel excavation process, so as to demonstrate whether the actual construction plan is safe and feasible.

[0008] The problem to be solved by the third aspect of the present invention is to provide a tunnel excavation simulation method, which can simulate tunnel excavation under various working conditions and realize data recording of simulation experiments.

[0009] In order to solve the above technical problems, the present invention provides a model box for simulating tunnel excavation, characterized in that it includes a box body with an open top and a closed bottom, the two pairs of side walls of the box body are double-layer frame structures, and the interlayer of the double-layer frame structure is suitable for accommodating transparent plates; one pair of oppositely arranged side walls are provided with transverse latch paths in their respective middle areas; the other pair of oppositely arranged side walls are provided with longitudinal latch paths in their respective middle areas, and the transverse latch paths and the longitudinal latch paths are suitable for accommodating latches, and the latches include a position-adjusting latch group capable of adjusting the spacing of the simulated tunnel and a semicircular latch group capable of forming a simulated tunnel section; and after the transparent plate is matched with the interlayer of the double-layer frame structure and the latch is matched with the transverse latch path and the longitudinal latch path, each of the side walls can form a closed integral structure. The transparent plate in the interlayer facilitates the experimenter to observe the situation in the model box.

[0010] Specifically, the upper parts of the inner walls of the two pairs of side walls are each provided with an inner hard plate, wherein the pair of oppositely arranged side walls include a left side wall and a right side wall, and the transverse latch channel includes a first transverse latch channel provided on the left side wall and transversely penetrating the middle area thereof, and a second transverse latch channel provided on the right side wall and transversely penetrating the middle area thereof; a first transverse double-layer frame structure of the left side wall is provided on the upper side of the first transverse latch channel, and a second transverse double-layer frame structure of the left side wall is provided on the lower side of the first transverse latch channel; a first transverse double-layer frame structure of the right side wall is provided on the upper side of the second transverse latch channel, and a second transverse double-layer frame structure of the right side wall is provided on the lower side of the second transverse latch channel;

[0011] The other pair of oppositely arranged side walls includes a front side wall and a rear side wall, and the longitudinal latching path includes a first longitudinal latching path provided on the front side wall and running longitudinally through the middle area thereof, and a second longitudinal latching path provided on the rear side wall and running longitudinally through the middle area thereof; a first longitudinal double-layer frame structure of the front side wall is provided on the left side of the first longitudinal latching path, and a second longitudinal double-layer frame structure of the front side wall is provided on the right side of the first longitudinal latching path; a first longitudinal double-layer frame structure of the rear side wall is provided on the left side of the second longitudinal latching path, and a second longitudinal double-layer frame structure of the rear side wall is provided on the right side of the second longitudinal latching path. The structures of each pair of oppositely arranged side walls are the same, which is conducive to the standardization and generalization of latches and transparent plates.

[0012] Preferably, the first transverse latching path and the second transverse latching path, at the side in contact with the corresponding double-layer frame structure, are each composed of two support plates with a length direction in the front-to-back direction and a width direction in the left-to-right direction, and a transverse gap suitable for passing the latching structure is formed between the two support plates;

[0013] The first longitudinal latching path and the second longitudinal latching path, on the side in contact with the corresponding double-layer frame structure, are each formed by two limit plates with a longitudinal length direction and a front-to-back width direction, and a longitudinal gap suitable for passing the latch structure is formed between the two limit plates;

[0014] The thickness of each support plate and each limit plate is consistent, both are H1; the gap width of the transverse gap is consistent with the gap width of the longitudinal gap; the widths of the first transverse latch channel, the second transverse latch channel, the first longitudinal latch channel and the second longitudinal latch channel are all equal.

[0015] Further, the latch structure is provided on two side surfaces of the latch that are arranged opposite to each other in the up-down direction, the latch structure is a protruding structure that runs through the length direction of the side surface, the width of the protruding structure is consistent with the width of the transverse gap and the longitudinal gap; the height of the protruding structure is H2;

[0016] The semicircular pin group is provided with a left semicircular pin and a right semicircular pin in pairs, and the left semicircular pin cooperates with the right semicircular pin to form a cross-section of a simulated tunnel; and the adjustment pin group includes adjustment pins of at least two lengths; the semicircular pin group includes a subway tunnel semicircular pin group whose cross-section of the simulated tunnel formed after cooperation is circular, and a mountain tunnel semicircular pin group whose cross-section of the simulated tunnel formed after cooperation is horseshoe-shaped, and the subway tunnel semicircular pin group includes subway tunnel semicircular pins of at least two sizes of cross-sections, and the mountain tunnel semicircular pin group includes mountain tunnel semicircular pins of at least two cross-section sizes.

[0017] Specifically, the transverse interlayers of the first transverse double-layer frame structure of the left side wall, the second transverse double-layer frame structure of the left side wall, the first transverse double-layer frame structure of the right side wall, and the second transverse double-layer frame structure of the right side wall are all suitable for accommodating the transparent plate, the transparent plate is a transverse tempered glass, and a transverse groove running through the length direction of the side is provided on one side of the transverse tempered glass that matches the transverse bolt path, and the groove width of the transverse groove is consistent with the gap width of the transverse gap;

[0018] The longitudinal interlayers of the first longitudinal double-layer frame structure of the front side wall, the second longitudinal double-layer frame structure of the front side wall, the first longitudinal double-layer frame structure of the rear side wall and the second longitudinal double-layer frame structure of the rear side wall are all suitable for accommodating the transparent plate, the transparent plate is a longitudinal tempered glass, and a longitudinal groove running through the length direction of the side is provided on one side of the longitudinal tempered glass that matches the longitudinally arranged bolt path, and the groove width of the longitudinal groove is consistent with the gap width of the longitudinal gap;

[0019] The depth of the transverse groove is consistent with the depth of the longitudinal groove, both of which are H3.

[0020] Preferably, the transverse tempered glass is inserted into the transverse interlayer along the front-to-back direction, and the side of the transverse tempered glass provided with the transverse groove matches the transverse gap; a connecting device suitable for opening and closing is provided at the transverse insertion end port of the transverse tempered glass inserted into the transverse interlayer, and the end of the transverse tempered glass inserted into the transverse interlayer is closed by a hard plate;

[0021] The longitudinal tempered glass is inserted into the longitudinal interlayer from top to bottom, and one side of the longitudinal groove on the longitudinal tempered glass matches the longitudinal gap; the longitudinal insertion end port where the longitudinal tempered glass is inserted into the longitudinal interlayer is also provided with the connecting device suitable for opening and closing, and the end where the longitudinal tempered glass is inserted into the longitudinal interlayer is the bottom of the box, and the bottom is closed by the bottom hard plate. It should be emphasized that the bottom hard plate is preferably a steel plate with sufficient thickness to prevent test errors caused by uneven settlement.

[0022] A second aspect of the present invention provides a tunnel excavation simulation system, characterized in that it includes:

[0023] A model box for simulating tunnel excavation, used to simulate the surrounding rock of the tunnel to be excavated;

[0024] Tunnel excavation simulation device, used to simulate the tunnel after excavation;

[0025] A surface settlement detection device is used to detect the settlement value of the upper surface of the filler in the model box;

[0026] A pressure loading device, used to load the filler in the model box;

[0027] Soil pressure detection device, used to measure the radial pressure and annular pressure at the arch crown and arch waist of the simulated tunnel;

[0028] A tunnel failure mode monitoring device, used to record the failure process of the filler in the model box when the simulated tunnel is excavated;

[0029] Tunnel structure simulation device is used to simulate the built tunnel.

[0030] Specifically, the tunnel excavation simulation device includes a rubber airbag, a ventilation hose, a precision pressure reducing valve and an air compressor; the rubber airbag is a cylindrical airbag and its outer diameter is consistent with the hole diameter of the simulated tunnel; the tunnel excavation simulation device controls the exhaust and pressure reduction of the rubber airbag through the precision pressure reducing valve to realize the excavation of the simulated tunnel;

[0031] The surface settlement detection device comprises a displacement sensor, wherein the displacement sensor is fixed on a cross bar, and the cross bar is fixed on the top of the model box for simulating tunnel excavation; or

[0032] The surface settlement detection device is a paper mass ruler arranged on the side wall of the model box for simulating tunnel excavation;

[0033] The pressure loading device comprises a reaction frame and a loading device, and a hard plate is placed between the pressure loading device and the upper surface of the filler;

[0034] The soil pressure detection device includes a micro soil pressure box and a static data acquisition instrument; the micro soil pressure box is electrically connected to the static data acquisition instrument; the micro soil pressure box is placed at the arch and waist of the cavern of the simulated tunnel, and can monitor the radial pressure information and the annular pressure information at the arch and the waist, and transmit the measured radial pressure information and the annular pressure information to the static data acquisition instrument;

[0035] The tunnel damage mode monitoring device includes a camera device, which is set to an interval shooting mode and can record the entire process of the damage of the filler during the simulated tunnel excavation;

[0036] The tunnel structure simulation device includes a polyvinyl chloride pipe, which can simulate the lining, and a strain gauge is attached to the polyvinyl chloride pipe, and a dial indicator is placed inside the polyvinyl chloride pipe; the strain gauge can measure the changes in strain and stress, and the dial indicator can measure the deformation degree of the simulated lining.

[0037] The third aspect of the present invention provides a tunnel excavation simulation method, characterized in that it includes the following steps:

[0038] S1. A confined space having a filling port is provided to simulate a tunnel excavation area, and the confined space is suitable for inward observation through the peripheral wall of the confined space;

[0039] S2. at least one simulated tunnel opening with adjustable size is provided on the side wall of the confined space, and a simulated tunnel having the cross-sectional shape of the simulated tunnel opening is provided through the confined space with the simulated tunnel opening as the starting point, and the soil pressure at the designated position of the simulated tunnel and the deformation of the simulated tunnel are monitored in real time;

[0040] S3. Recording the settlement value of the surface layer of the simulated tunnel excavation area and the destruction process of the simulated tunnel excavation area during the simulated tunnel excavation.

[0041] Specifically, when two simulated tunnel openings with adjustable sizes are provided on the same side wall of the enclosed space, the lateral spacing between the two simulated tunnel openings with adjustable sizes is adjustable; when one simulated tunnel opening with adjustable size is provided on each of two adjacent side walls of the enclosed space, the longitudinal spacing between the two simulated tunnel openings with adjustable sizes is adjustable.

[0042] Through the above technical scheme, a tunnel excavation model box provided in the first aspect of the present invention realizes the simulation of tunnel excavation under various working conditions, avoids the waste of resources caused by designing a model box for an experiment under one working condition, and has strong practicality.

[0043] The second aspect of the present invention provides a tunnel excavation simulation system, which realizes the simulation of tunnel excavation under various working conditions through a model box for simulating tunnel excavation, a tunnel excavation simulation device and a pressure loading device, and monitors the experimental process and measures and records key experimental data through a surface settlement detection device, a soil pressure detection device, a tunnel failure mode monitoring device and a tunnel structure simulation device, so that designers can infer whether the actual construction plan is safe and feasible based on the data obtained from the experiment.

[0044] The third aspect of the present invention provides a tunnel excavation simulation method, which realizes the simulation of tunnel excavation under different working conditions by adjusting the lateral and longitudinal spacing between simulated tunnel openings with different cross-sectional shapes and adjustable cross-sectional sizes, and places corresponding detection devices at designated positions in the simulated tunnel to realize the measurement and recording of experimental data.

[0045] Other advantages of the present invention and the technical effects of the preferred embodiments will be further described in the following specific embodiments. BRIEF DESCRIPTION OF THE DRAWINGS

[0046] Figure 1 It is a schematic diagram of the assembly of a model box for simulating tunnel excavation according to the present invention;

[0047] Figure 2 It is a schematic diagram of an enlarged structure of a transverse gap in a model box for simulating tunnel excavation according to the present invention;

[0048] Figure 3 It is a schematic diagram of an enlarged structure of a longitudinal gap in a model box for simulating tunnel excavation according to the present invention;

[0049] Figure 4 It is a schematic diagram of the structure of transverse tempered glass in a model box for simulating tunnel excavation of the present invention;

[0050] Figure 5 It is a schematic diagram of the longitudinal tempered glass structure in a model box for simulating tunnel excavation of the present invention;

[0051] Figure 6 It is a schematic structural diagram of a position adjusting pin of one size in a position adjusting pin set of a model box for simulating tunnel excavation according to the present invention;

[0052] Figure 7 It is a structural schematic diagram of a pair of mutually cooperating semicircular latches in a semicircular latch set in a model box for simulating tunnel excavation of the present invention;

[0053] Figure 8 It is a schematic diagram of the cross-sectional shape of a pair of semicircular latches of a subway tunnel in a model box for simulating tunnel excavation according to the present invention after being matched;

[0054] Fig. 9 It is a schematic diagram of the cross-sectional shape of a pair of semicircular pins of a mountain tunnel after being matched in a model box for simulating tunnel excavation of the present invention;

[0055] Fig.10 It is a schematic diagram of the coordination of a protruding structure, a lateral gap and a lateral tempered glass in a model box for simulating tunnel excavation of the present invention;

[0056] Fig.11 It is a schematic diagram of the working of a pressure loading device in a tunnel excavation simulation system of the present invention;

[0057] Fig.12 It is a schematic diagram of simulation of a single-hole subway tunnel in a tunnel excavation simulation method of the present invention;

[0058] Fig.13 It is a schematic diagram of simulation of a double-hole subway tunnel in a tunnel excavation simulation method of the present invention;

[0059] Fig.14 It is a schematic diagram of simulation of a multi-hole subway tunnel group in a tunnel excavation simulation method of the present invention;

[0060] Fig.15 It is a schematic diagram of simulation of an upper-crossing subway tunnel in a tunnel excavation simulation method of the present invention;

[0061] Fig.16 It is a schematic diagram of simulation of underpass of a subway tunnel in a tunnel excavation simulation method of the present invention.

[0062] Description of Reference Numerals

[0063] 1-Box 11-Left side wall

[0064] 111-first transverse bolt path 112-left side wall first transverse double-layer frame structure left

[0065] 113- left side wall second transverse double-layer frame structure 12- right side wall

[0066] 121- second transverse bolt path 122- right side wall first transverse double-layer frame structure right

[0067] 123-right side wall second transverse double-layer frame structure 13-front side wall

[0068] 131-first longitudinal bolt channel 132-front side wall first longitudinal double-layer frame structure front

[0069] 133-front side wall second longitudinal double-layer frame structure 14-rear side wall

[0070] 141- second longitudinal bolt channel 142- rear side wall first longitudinal double-layer frame structure rear

[0071] 143-rear side wall second longitudinal double-layer frame structure 15-bottom hard plate

[0072] 16-Support plate 161-Horizontal gap

[0073] 17-Limiting plate 171-Longitudinal gap

[0074] 21- Raised structure 22- Adjustment pin assembly

[0075] 23- Semicircular latch set 231- Subway tunnel semicircular latch set

[0076] 232-Mountain Tunnel Semicircular Pin Set 31-Horizontal Tempered Glass

[0077] 311- horizontal groove 32- vertical tempered glass

[0078] 321-Longitudinal groove 4-Connection device

[0079] 51-reaction frame 52-loading device

[0080] 53-Hard Plate 6-Built Tunnel DETAILED DESCRIPTION

[0081] The specific implementation of the present invention is described in detail below in conjunction with the accompanying drawings. It should be understood that the specific implementation described here is only used to illustrate and explain the present invention, and is not used to limit the present invention.

[0082] First of all, it should be noted that the following directional terms such as up, down, left, right, front and back are explained based on the relative positions of the components in the accompanying drawings, and are not intended to limit the specific structure; in addition, similar materials refer to the consistency of the mechanical properties of the geotechnical materials in the model box with those in the construction site.

[0083] like Figure 1As shown, a model box for simulating tunnel excavation provided by the first aspect of the present invention comprises a box body 1 with an open top and a closed bottom, wherein both pairs of side walls of the box body 1 are double-layer frame structures, and the interlayer of the double-layer frame structure is suitable for accommodating transparent plates; on one pair of oppositely arranged side walls, transverse latch paths are provided in their respective middle regions; on the other pair of oppositely arranged side walls, longitudinal latch paths are provided in their respective middle regions, and the transverse latch paths and the longitudinal latch paths are suitable for accommodating latches, wherein the latches comprise a position-adjusting latch group 22 capable of adjusting the spacing of the simulated tunnels and a semicircular latch group 23 capable of constituting the cross-section of the simulated tunnel; and after the transparent plate is matched with the interlayer of the double-layer frame structure and the latch is matched with the transverse latch path and the longitudinal latch path, each of the side walls can form a closed integral structure.

[0084] This basic technical solution can simulate various tunnel excavation conditions by arranging one or more pairs of semicircular pin groups 23 in different forms in the transverse pin path and the longitudinal pin path, so that the model box for simulating tunnel excavation of the present invention can be applied to tunnel excavation simulation experiments of various working conditions, avoiding the waste of resources caused by designing a different model box for each different working condition before the experiment, and has strong practicality. The double-layer frame structure and the design of the transparent plate contained in the interlayer of the double-layer frame structure facilitate the experimenters to observe the situation in the model box. Preferably, the double-layer frame structure can be formed by welding steel plates to ensure the strength of the double-layer frame structure, so that when the filler in the model box needs to be loaded, the double-layer frame structure will not affect the accuracy of the experiment due to deformation.

[0085] Specifically, Figure 1 As shown, the inner wall upper parts of the two pairs of side walls are provided with inner hard plates, and the left wall 11 and the right wall 12 which are arranged opposite to each other are provided with transverse latch paths, which specifically include a first transverse latch path 111 which is provided on the left wall 11 and transversely penetrates the middle area thereof, and a second transverse latch path 121 which is provided on the right wall 12 and transversely penetrates the middle area thereof; the first transverse latch path 111 is provided with a left wall first transverse double-layer frame structure 112 on the upper side, and the second transverse double-layer frame structure 113 on the left wall on the lower side; the second transverse latch path 121 is provided with a right wall first transverse double-layer frame structure 122 on the upper side, and the second transverse latch path 121 is provided with a right wall second transverse double-layer frame structure 123 on the lower side;

[0086] Another pair of oppositely arranged front side walls 13 and rear side walls 14 are both provided with longitudinal latch paths, which specifically include a first longitudinal latch path 131 provided on the front side wall 13 and running longitudinally through the middle area thereof, and a second longitudinal latch path 141 provided on the rear side wall 14 and running longitudinally through the middle area thereof; wherein a first longitudinal double-layer frame structure 132 of the front side wall is provided on the left side of the first longitudinal latch path 131, and a second longitudinal double-layer frame structure 133 of the front side wall is provided on the right side of the first longitudinal latch path 131; a first longitudinal double-layer frame structure 142 of the rear side wall is provided on the left side of the second longitudinal latch path 141, and a second longitudinal double-layer frame structure 143 of the rear side wall is provided on the right side of the second longitudinal latch path 141.

[0087] In actual application, it is preferred to make the structures of each pair of oppositely arranged side walls into the same design, which is conducive to the standardization and generalization of latches and transparent plates, which not only reduces the manufacturing difficulty of the model box for simulating tunnel excavation, but also saves manufacturing costs; an inner hard plate is provided on the upper part of the inner wall of each side wall, and the inner hard plate is preferably a steel plate. This design makes the structural strength of the model box for simulating tunnel excavation higher and not easy to be damaged when loading is required.

[0088] More specifically, if Figure 1 , Figure 2 and Figure 3 As shown, the first transverse latching path 111 and the second transverse latching path 121 are both formed by two support plates 16 with a length direction in the front-to-back direction and a width direction in the left-to-right direction at the sides contacting the double-layer frame structure corresponding to each of them, and a transverse gap 161 suitable for passing the latching structure is formed between the two support plates 16;

[0089] The first longitudinal latching path 131 and the second longitudinal latching path 141 are both formed by two limit plates 17 with a longitudinal length direction and a front-to-back width direction on one side in contact with the corresponding double-layer frame structure, and a longitudinal gap 171 suitable for passing the latch structure is formed between the two limit plates 17;

[0090] The thickness of each support plate 16 and each limit plate 17 is consistent with each other, which is H1; the gap width of the transverse gap 161 is consistent with the gap width of the longitudinal gap 171; the widths of the first transverse latch path 111, the second transverse latch path 121, the first longitudinal latch path 131 and the second longitudinal latch path 141 are all equal.

[0091] The gap width of the transverse gap 161 is consistent with the gap width of the longitudinal gap 171, so that the width of the pin structure on the pin can be standardized; the widths of the first transverse pin path 111, the second transverse pin path 121, the first longitudinal pin path 131 and the second longitudinal pin path 141 are all equal, so that the width of the pin can be standardized. This design allows the pins to be standardized, so that the pins in the transverse pin path and the longitudinal pin path can be interchangeable, which facilitates the arrangement of the pins before the experiment, reduces the difficulty of manufacturing the pin group, and saves manufacturing costs.

[0092] More specifically, if Figures 6 to 10 As shown, the two sides of the latch that are opposite to each other in the vertical direction are provided with latch structures, which are protruding structures 21 that penetrate the length direction of the side where they are located, and the width of the protruding structure 21 is consistent with the width of the horizontal gap 161 and the vertical gap 171; the height of the protruding structure 21 is H2. It should be noted that the spacing between the two side walls is consistent with the width of the horizontal latch channel and the vertical latch channel to ensure the sealing of the side walls;

[0093] The semicircular pin group 23 is provided with a left semicircular pin and a right semicircular pin in pairs, wherein the left semicircular pin cooperates with the right semicircular pin to form a cross-section of a simulated tunnel; and the adjustment pin group 22 includes adjustment pins of at least two lengths; the semicircular pin group 23 includes a subway tunnel semicircular pin group 231 whose cross-section of the simulated tunnel formed after cooperation is circular, and a mountain tunnel semicircular pin group 232 whose cross-section of the simulated tunnel formed after cooperation is horseshoe-shaped, and the subway tunnel semicircular pin group 231 includes subway tunnel semicircular pins of at least two sizes of cross-sections, and the mountain tunnel semicircular pin group 232 includes mountain tunnel semicircular pins of at least two cross-section sizes.

[0094] The bolt structure on the bolt runs through the length direction of the side where the bolt structure is located. On the one hand, it can easily make the force-bearing area of ​​the bolt structure on the bolt large and able to withstand a larger load; on the other hand, such a design makes it easier to improve the overall airtightness of the side wall after the bolt is inserted and matched with the transparent plate, so that the filler in the model box will not leak out from the side wall. In addition, the adjustment bolt group 22 includes at least two lengths of adjustment bolts, which can facilitate the adjustment of the spacing between the tunnel openings of the simulated tunnel; the semicircular bolt group 23 includes bolt groups that can form different tunnel sections, and each bolt group that forms different tunnel sections includes at least two section sizes to meet the tunnel simulation of different tunnel sections and tunnel simulation under different similarity ratios.

[0095] Preferably, if Figure 1 , Figure 4 , Figure 5 and Fig.10As shown, the transverse interlayers of the first transverse double-layer frame structure 112 of the left side wall, the second transverse double-layer frame structure 113 of the left side wall, the first transverse double-layer frame structure 122 of the right side wall and the second transverse double-layer frame structure 123 of the right side wall are all suitable for accommodating transparent plates, and the transparent plates are preferably transverse tempered glass 31, and the side of the transverse tempered glass 31 that cooperates with the transverse latch channel is provided with a transverse groove 311 running through the length direction of the side, and the groove width of the transverse groove 311 is consistent with the gap width of the transverse gap 161; the thickness of the transverse tempered glass 31 is consistent with the thickness of the transverse interlayer to ensure the airtightness of the side wall after cooperating with the latch.

[0096] The longitudinal interlayers of the first longitudinal double-layer frame structure 132 of the front side wall, the second longitudinal double-layer frame structure 133 of the front side wall, the first longitudinal double-layer frame structure 142 of the rear side wall and the second longitudinal double-layer frame structure 143 of the rear side wall are all suitable for accommodating transparent plates, and the transparent plates are preferably longitudinal tempered glass 32, and a longitudinal groove 321 is provided on the side of the longitudinal tempered glass 32 that cooperates with the longitudinally arranged bolt path, and runs through the length direction of the side, and the groove width of the longitudinal groove 321 is consistent with the gap width of the longitudinal gap 171; the thickness of the longitudinal tempered glass 32 is consistent with the thickness of the longitudinal interlayer to ensure the airtightness of the rear wall after cooperating with the bolt.

[0097] The depth of the transverse groove 311 is consistent with the depth of the longitudinal groove 321, both of which are H3. In actual use, the thickness of the support plate 16 and the limit plate 17 are both H1, the height of the protrusion structure 21 is H2, and the depth of the transverse groove 311 and the longitudinal groove 321 are consistent with each other, both of which are H3, which should satisfy H2 = H1 + H3. Fig.10 As shown, taking the cooperation between the protruding structure, the transverse gap 161 and the transverse tempered glass 31 as an example, the protruding height H2 of the protruding structure 21 is the sum of the thickness H1 of the support plate 16 and the depth H3 of the transverse groove 311, so that the three can be closely matched to ensure the integrity and airtightness of the side wall.

[0098] Preferably, if Figure 1 As shown, the transverse tempered glass 31 is inserted into the transverse interlayer along the front-to-back direction, and one side of the transverse groove 311 provided on the transverse tempered glass 31 matches the transverse gap 161; a connecting device 4 suitable for opening and closing is provided at the transverse insertion end port of the transverse tempered glass 31 inserted into the transverse interlayer, and the end of the transverse tempered glass 31 inserted into the transverse interlayer is closed by a hard plate;

[0099] The longitudinal tempered glass 32 is inserted into the longitudinal interlayer from top to bottom, and one side of the longitudinal groove 321 provided on the longitudinal tempered glass 32 matches the longitudinal gap 171; a connecting device 4 suitable for opening and closing is also provided at the longitudinal insertion end port of the longitudinal tempered glass 32 inserted into the longitudinal interlayer, and the end end of the longitudinal tempered glass 32 inserted into the longitudinal interlayer is the bottom of the box body 1, and the bottom of the box body 1 is closed by the bottom hard plate 15.

[0100] The connecting device 4 suitable for opening and closing is in an open state during the process of inserting the tempered glass into the interlayer. After the tempered glass is fully inserted into the interlayer, the connecting device 4 is closed and locked to ensure that the tempered glass is firmly fixed in the interlayer. Specifically, a preferred structure of the connecting device 4 is: an iron ring is welded on each of the steel plates on both sides of the double-layer frame structure, and after the tempered glass is installed, an iron bolt is inserted into the iron ring, and then the nut is tightened. The design structure is simple and easy to implement; the bottom hard plate 15 used to close the bottom of the box body 1 is preferably a steel plate with sufficient thickness to prevent test errors caused by uneven settlement.

[0101] A second aspect of the present invention provides a tunnel excavation simulation system, comprising:

[0102] A model box for simulating tunnel excavation, used to simulate the surrounding rock of the tunnel to be excavated;

[0103] Tunnel excavation simulation device, used to simulate the tunnel after excavation;

[0104] A surface settlement detection device is used to detect the settlement value of the upper surface of the filler in the model box;

[0105] A pressure loading device, used to load the filler in the model box;

[0106] Soil pressure detection device, used to measure the radial pressure and annular pressure at the arch crown and arch waist of the simulated tunnel;

[0107] Tunnel failure mode monitoring device, used to record the failure process of the filling material in the model box during the excavation of the simulated tunnel;

[0108] Tunnel structure simulation device is used to simulate the built tunnel.

[0109] Specifically, Fig.11 As shown, the tunnel excavation simulation device includes a rubber airbag, a ventilation hose, a precision pressure reducing valve and an air compressor; wherein the rubber airbag is a cylindrical airbag and its outer diameter is consistent with the hole diameter of the simulated tunnel; the tunnel excavation simulation device controls the exhaust and pressure reduction of the rubber airbag through the precision pressure reducing valve to realize the excavation of the simulated tunnel;

[0110] The surface settlement detection device includes a displacement sensor, which is fixed on a crossbar, and the crossbar is fixed on the top of a model box for simulating tunnel excavation; or

[0111] The surface settlement detection device is a paper mass ruler installed on the side wall of the model box used to simulate tunnel excavation. When the simulated tunnel is shallow and does not need to be loaded by a pressure loading device, a displacement sensor is used for measurement. When the simulated tunnel is deep and needs to be loaded by a pressure loading device, a paper mass ruler is used for measurement because the displacement sensor is not convenient to arrange.

[0112] The pressure loading device includes a reaction frame 51 and a loading device 52. A hard plate 53 is placed between the pressure loading device and the upper surface of the filler. The hard plate 53 can make the filler in the model box bear force evenly to avoid stress concentration;

[0113] The soil pressure detection device includes a micro soil pressure box and a static data acquisition instrument; the micro soil pressure box is electrically connected to the static data acquisition instrument; the micro soil pressure box is placed at the arch and waist of the cavern of the simulated tunnel, and can monitor the radial pressure information and the annular pressure information at the arch and waist, and transmit the measured radial pressure information and the annular pressure information to the static data acquisition instrument;

[0114] The tunnel damage mode monitoring device includes a camera device, which is set to an interval shooting mode and can record the entire process of filler damage during simulated tunnel excavation;

[0115] The tunnel structure simulation device includes a polyvinyl chloride pipe, which can simulate the lining, and a strain gauge is attached to the polyvinyl chloride pipe, and a dial indicator is placed in the pipe of the polyvinyl chloride pipe; the strain gauge can measure the change of strain and stress, and the dial indicator can measure the deformation degree of the simulated lining.

[0116] A third aspect of the present invention provides a tunnel excavation simulation method, comprising the following steps:

[0117] S1. A confined space with a filling port is provided to simulate a tunnel excavation area, and the confined space is suitable for inward observation through the peripheral wall of the confined space;

[0118] S2. at least one simulated tunnel opening with adjustable size is provided on the side wall of the confined space, and a simulated tunnel having the cross-sectional shape of the simulated tunnel opening is provided through the confined space with the simulated tunnel opening as the starting point, and the soil pressure at the designated position of the simulated tunnel and the deformation of the simulated tunnel are monitored in real time;

[0119] S3. Record the settlement values ​​of the surface layer of the simulated tunnel excavation area and the destruction process of the simulated tunnel excavation area during the simulated tunnel excavation.

[0120] Specifically, when two simulated tunnel openings with adjustable sizes are provided on the same side wall of the confined space, the lateral spacing between the two simulated tunnel openings with adjustable sizes is adjustable; when one simulated tunnel opening with adjustable size is provided on each of two adjacent side walls of the confined space, the longitudinal spacing between the two simulated tunnel openings with adjustable sizes is adjustable.

[0121] The working conditions that can be simulated by the model box for simulating tunnel excavation and their corresponding preferred simulation methods are as follows:

[0122] The first one, such as Figure 8 Fig. 9 and Fig.12 As shown, according to the cross-sectional shape of the simulated tunnel, a corresponding semicircular pin group is selected, such as a subway tunnel semicircular pin group 231 whose cross-sectional shape of the simulated tunnel formed after matching is circular to simulate the development of the subway tunnel; a mountain tunnel semicircular pin group 232 whose cross-sectional shape of the simulated tunnel formed after matching is horseshoe-shaped to simulate the excavation of the mountain tunnel.

[0123] The second method is to select semicircular pins of different cross-sectional sizes according to the similarity ratio after selecting the tunnel section form, so as to simulate the excavation of simulated tunnels under different similarity ratios. It should be emphasized here that the filler in the model box used to simulate tunnel excavation is similar material, and the ratio of similar materials needs to be determined according to the similarity ratio of the experiment. When the similarity ratio changes, the ratio of similar materials also needs to change.

[0124] The third type, such as Fig.13 and 14 As shown, at least two pairs of semicircular pins are arranged in the transverse pin path of the model box for simulating tunnel excavation, and the transverse spacing between each pair of semicircular pins is adjusted by adjusting the position of the pins to realize the simulated excavation of double-hole tunnels or multi-hole tunnel groups with different tunnel spacings.

[0125] It should be noted that the above three working conditions only use the horizontal bolt path, and do not involve the longitudinal bolt path to complete the model test, so the longitudinal bolt path needs to be blocked with a positioning bolt. In addition, the size of the model box used to simulate tunnel excavation should be made according to the working conditions of the multi-hole tunnel group excavation. Therefore, the model box used to simulate tunnel excavation is larger for the first two working conditions of only single-hole excavation. Therefore, when conducting the test, too much similar material needs to be filled, which is easy to cause waste. Therefore, considering the boundary effect, wooden boards can be used to separate the model box used to simulate tunnel excavation to have enough space to accurately complete the test, so as to reduce the waste of similar materials.

[0126] The fourth type, such as Fig.15 and Fig.16As shown, an existing tunnel is set on the transverse bolt track. The existing tunnel can be any of the above three working conditions. A tunnel to be excavated is set on the longitudinal bolt track. The longitudinal distance between the tunnel to be excavated and the existing tunnel is adjusted by the adjustment bolt. If the tunnel to be excavated is above the existing tunnel, the simulated excavation of the upper tunnel can be realized; if the tunnel to be excavated is below the existing tunnel, the simulated excavation of the underpass tunnel can be realized. When this design method is adopted, since the lower space of the existing tunnel is large, under the condition of considering the boundary effect, a cushion block can be used to reduce the lower space and prevent the waste of similar materials. It should be noted that if the existing tunnel is a single-hole tunnel and the tunnel to be excavated is an upper tunnel, the existing tunnel can be set on the longitudinal bolt track, and the tunnel to be excavated can be set on the transverse bolt track. In this way, the lower space can be fully utilized and the waste of similar materials can be reduced.

[0127] The experimental process of the tunnel excavation simulation experiment using the present invention is as follows:

[0128] First, insert the tempered glass into the interlayer and close the connecting device to fix the tempered glass. Arrange the adjustment pins and semicircular pins at the required positions according to the working conditions to be simulated in the experiment, and match similar materials in a similar ratio. In order to further ensure the airtightness, the gap between the tempered glass and the steel plate can also be filled with foam glue.

[0129] Subsequently, the model box for simulating tunnel excavation is fixed, and after the inside of the model box for simulating tunnel excavation is cleaned, a layer of detergent is applied on the inner wall of the model box for simulating tunnel excavation to reduce the friction between the surrounding rock material and the tempered glass during deformation and destruction, and similar materials are added to the model box for simulating tunnel excavation in self-compacting layers according to the rain method. In this process, the pressure box and the built-in air bag are buried at the specified position, and the pressure box, static data acquisition and computer are connected and debugged, and the initial readings are recorded. The air bag should remain cylindrical during the filling process.

[0130] Then, when the loading of similar materials is completed, install the camera device and check whether the shooting position is reasonable and whether the picture is clear; install a displacement sensor on the top of the model box, or set a paper mass ruler on the outer wall of the model box used to simulate tunnel excavation, check the initial data and record the experimental data.

[0131] Finally, the tunnel excavation simulation device is controlled to simulate tunnel excavation and record various data after tunnel excavation; the obtained data is sorted and analyzed to draw experimental conclusions.

[0132] The preferred embodiments of the present invention are described in detail above with reference to the accompanying drawings, but the present invention is not limited thereto. Within the technical concept of the present invention, the technical solution of the present invention can be subjected to a variety of simple modifications, including the combination of various specific technical features in any appropriate manner. In order to avoid unnecessary repetition, the present invention will not further describe various possible combinations. However, these simple modifications and combinations should also be regarded as the contents disclosed by the present invention and belong to the protection scope of the present invention.

Claims

1. A model box for simulating tunnel excavation, characterized in that: The invention comprises a box (1) with an open top and a closed bottom, wherein both pairs of side walls of the box (1) are double-layer frame structures, and the interlayer of the double-layer frame structure is suitable for accommodating a transparent plate; one pair of oppositely disposed side walls is provided with a transverse latch path in the middle region of each pair; the other pair of oppositely disposed side walls is provided with a longitudinal latch path in the middle region of each pair, and the transverse latch path and the longitudinal latch path are suitable for accommodating latches, and the latches comprise a position-adjusting latch group (22) capable of adjusting the spacing of a simulated tunnel and a semicircular latch group (23) capable of forming a simulated tunnel section; and after the transparent plate is matched with the interlayer of the double-layer frame structure and the latches are matched with the transverse latch path and the longitudinal latch path, each of the side walls can form a closed integral structure; An inner hard plate is provided at the upper part of the inner wall of each of the two pairs of side walls, and the pair of oppositely arranged side walls comprises a left side wall (11) and a right side wall (12), and the transverse latch path comprises a first transverse latch path (111) provided on the left side wall (11) and extending transversely through the middle area thereof, and a second transverse latch path (121) provided on the right side wall (12) and extending transversely through the middle area thereof; a first transverse double-layer frame structure (112) of the left side wall is provided on the upper side of the first transverse latch path (111), and a second transverse double-layer frame structure (113) of the left side wall is provided on the lower side of the first transverse latch path (111); a first transverse double-layer frame structure (122) of the right side wall is provided on the upper side of the second transverse latch path (121), and a second transverse double-layer frame structure (123) of the right side wall is provided on the lower side of the second transverse latch path (121); The other pair of oppositely arranged side walls comprises a front side wall (13) and a rear side wall (14); the longitudinal latch path comprises a first longitudinal latch path (131) provided on the front side wall (13) and extending longitudinally through the middle region thereof, and a second longitudinal latch path (141) provided on the rear side wall (14) and extending longitudinally through the middle region thereof; a first longitudinal double-layer frame structure (132) of the front side wall is provided on the left side of the first longitudinal latch path (131), and a second longitudinal double-layer frame structure (133) of the front side wall is provided on the right side of the first longitudinal latch path (131); a first longitudinal double-layer frame structure (142) of the rear side wall is provided on the left side of the second longitudinal latch path (141), and a second longitudinal double-layer frame structure (143) of the rear side wall is provided on the right side of the second longitudinal latch path (141); The latch structure is provided on two side surfaces of the latch that are arranged opposite to each other in the up-down direction. The latch structure is a protruding structure (21) that runs through the length direction of the side surface. The width of the protruding structure (21) is consistent with the width of the transverse gap (161) and the longitudinal gap (171). The protruding height of the protruding structure (21) is H2. The semicircular pin group (23) is provided with a left semicircular pin and a right semicircular pin in pairs, the left semicircular pin and the right semicircular pin being matched to form a simulated tunnel cross section; and the position adjustment pin group (22) comprises position adjustment pins of at least two lengths; the semicircular pin group (23) comprises a subway tunnel semicircular pin group (231) whose simulated tunnel cross section is circular after matching, and a mountain tunnel semicircular pin group (232) whose simulated tunnel cross section is horseshoe-shaped after matching, and the subway tunnel semicircular pin group (231) comprises subway tunnel semicircular pins of cross sections of at least two sizes, and the mountain tunnel semicircular pin group (232) comprises mountain tunnel semicircular pins of at least two cross section sizes.

2. The model box for simulating tunnel excavation according to claim 1, characterized in that: The first transverse latching path (111) and the second transverse latching path (121) are each formed of two support plates (16) whose length direction is the front-to-back direction and whose width direction is the left-to-right direction, at the sides contacting the double-layer frame structure corresponding to each of them, and a transverse gap (161) suitable for passing the latching structure is formed between the two support plates (16); The first longitudinal latching path (131) and the second longitudinal latching path (141) are each formed of two limit plates (17) with a longitudinal length direction and a front-to-back width direction on the sides thereof in contact with the corresponding double-layer frame structure, and a longitudinal gap (171) suitable for passing the latching structure is formed between the two limit plates (17); The thickness of each of the support plates (16) and each of the limit plates (17) is consistent, both being H1; the gap width of the transverse gap (161) is consistent with the gap width of the longitudinal gap (171); and the widths of the first transverse latch path (111), the second transverse latch path (121), the first longitudinal latch path (131) and the second longitudinal latch path (141) are all equal.

3. The model box for simulating tunnel excavation according to claim 1, characterized in that: The transverse interlayers of the first transverse double-layer frame structure (112) of the left side wall, the second transverse double-layer frame structure (113) of the left side wall, the first transverse double-layer frame structure (122) of the right side wall, and the second transverse double-layer frame structure (123) of the right side wall are all suitable for accommodating the transparent plate, the transparent plate is a transverse tempered glass (31), and a transverse groove (311) is provided on one side of the transverse tempered glass (31) that matches the transverse bolt path and runs through the length direction of the side, and the groove width of the transverse groove (311) is consistent with the gap width of the transverse gap (161); The longitudinal interlayers of the first longitudinal double-layer frame structure (132) of the front side wall, the second longitudinal double-layer frame structure (133) of the front side wall, the first longitudinal double-layer frame structure (142) of the rear side wall, and the second longitudinal double-layer frame structure (143) of the rear side wall are all suitable for accommodating the transparent plate, the transparent plate is a longitudinal tempered glass (32), and a longitudinal groove (321) is provided on one side of the longitudinal tempered glass (32) that matches the longitudinally arranged bolt path and runs through the length direction of the side, and the groove width of the longitudinal groove (321) is consistent with the gap width of the longitudinal gap (171); The depth of the transverse groove (311) is consistent with the depth of the longitudinal groove (321), both being H3.

4. The model box for simulating tunnel excavation according to claim 3, characterized in that: The transverse tempered glass (31) is inserted into the transverse interlayer in the front-to-back direction, and one side of the transverse groove (311) provided on the transverse tempered glass (31) matches the transverse gap (161); a connecting device (4) suitable for opening and closing is provided at the transverse insertion end of the transverse tempered glass (31) inserted into the transverse interlayer, and the end of the transverse tempered glass (31) inserted into the transverse interlayer is closed by a hard plate; The longitudinal tempered glass (32) is inserted into the longitudinal interlayer from top to bottom, and one side of the longitudinal groove (321) provided on the longitudinal tempered glass (32) matches the longitudinal gap (171); the connecting device (4) suitable for opening and closing is also provided at the longitudinal insertion end of the longitudinal tempered glass (32) inserted into the longitudinal interlayer, and the end where the longitudinal tempered glass (32) is inserted into the longitudinal interlayer is the bottom of the box body (1), and the bottom is closed by a bottom hard plate (15).

5. A tunnel excavation simulation system, characterized in that: include: The model box for simulating tunnel excavation according to any one of claims 1 to 4, used for simulating the surrounding rock of the tunnel to be excavated; Tunnel excavation simulation device, used to simulate the tunnel after excavation; A surface settlement detection device is used to detect the settlement value of the upper surface of the filler in the model box; A pressure loading device, used to load the filler in the model box; Soil pressure detection device, used to measure the radial pressure and annular pressure at the arch crown and arch waist of the simulated tunnel; A tunnel failure mode monitoring device, used to record the failure process of the filler in the model box when the simulated tunnel is excavated; Tunnel structure simulation device is used to simulate the built tunnel.

6. The tunnel excavation simulation system according to claim 5, characterized in that: The tunnel excavation simulation device comprises a rubber airbag, a ventilation hose, a precision pressure reducing valve and an air compressor; the rubber airbag is a cylindrical airbag and its outer diameter is consistent with the hole diameter of the simulated tunnel; the tunnel excavation simulation device controls the exhaust and pressure reduction of the rubber airbag through the precision pressure reducing valve to realize the excavation of the simulated tunnel; The surface settlement detection device comprises a displacement sensor, wherein the displacement sensor is fixed on a cross bar, and the cross bar is fixed on the top of the model box for simulating tunnel excavation; or The surface settlement detection device is a paper mass ruler arranged on the side wall of the model box for simulating tunnel excavation; The pressure loading device comprises a reaction frame (51) and a loading device (52), and a hard plate (53) is placed between the pressure loading device and the upper surface of the filler; The soil pressure detection device includes a micro soil pressure box and a static data acquisition instrument; the micro soil pressure box is electrically connected to the static data acquisition instrument; the micro soil pressure box is placed at the arch and waist of the cavern of the simulated tunnel, and can monitor the radial pressure information and the annular pressure information at the arch and the waist, and transmit the measured radial pressure information and the annular pressure information to the static data acquisition instrument; The tunnel damage mode monitoring device includes a camera device, which is set to an interval shooting mode and can record the entire process of the damage of the filler during the simulated tunnel excavation; The tunnel structure simulation device includes a polyvinyl chloride pipe, which can simulate the lining, and a strain gauge is attached to the polyvinyl chloride pipe, and a dial indicator is placed inside the polyvinyl chloride pipe; the strain gauge can measure the changes in strain and stress, and the dial indicator can measure the deformation degree of the simulated lining.

7. A tunnel excavation simulation method, implemented by using the model box for simulating tunnel excavation according to any one of claims 1 to 4, or the tunnel excavation simulation system according to claim 5 or 6, characterized in that: The steps include: S1. A confined space having a filling port is provided to simulate a tunnel excavation area, and the confined space is suitable for inward observation through the peripheral wall of the confined space; S2. at least one simulated tunnel opening with adjustable size is provided on the side wall of the confined space, and a simulated tunnel having the cross-sectional shape of the simulated tunnel opening is provided through the confined space with the simulated tunnel opening as the starting point, and the soil pressure at the designated position of the simulated tunnel and the deformation of the simulated tunnel are monitored in real time; S3. Recording the settlement value of the surface layer of the simulated tunnel excavation area and the destruction process of the simulated tunnel excavation area during the simulated tunnel excavation.

8. The tunnel excavation simulation method according to claim 7, characterized in that: When two simulated tunnel openings with adjustable sizes are arranged on the same side wall of the enclosed space, the lateral spacing between the two simulated tunnel openings with adjustable sizes is adjustable; when one simulated tunnel opening with adjustable size is arranged on each of two adjacent side walls of the enclosed space, the longitudinal spacing between the two simulated tunnel openings with adjustable sizes is adjustable.