A permanent and temporary combined retaining wall structure and construction method for quick on-site assembly
Through the Yonglin combined retaining wall structure using prefabricated components for rapid assembly in an emergency, the problem of the existing technology being unable to quickly construct the barrier and prevention structure is solved, and rapid maintenance of traffic and slope stability is achieved, and long-term safety is provided.
Patent Information
- Application Number
- CN202010976019.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-09-16
- Publication Date
- 2025-04-08
- Estimated Expiration
- 2040-09-16
AI Technical Summary
The prior art cannot quickly construct a barrier and prevention structure in emergency situations, and cannot meet the requirements of rapid traffic maintenance and disaster development.
The Yonglin-connected retaining wall structure is quickly assembled on site using prefabricated components, including a frame unit close to the slope of the roadbed and a protective net arranged outside the frame unit. It is connected by six-way pipe fittings to form an infinitely lengthened frame unit, and grouting and reinforcement are carried out when necessary.
It has achieved rapid rescue and maintenance, reduced the damage caused by landslides to roads and pedestrians, and further stabilized the slopes, which can quickly form permanent retaining wall support, providing long-term safety.
Smart Images

Figure CN111962556B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of roadbed traffic safety protection facilities, and in particular to a permanent and temporary combined retaining wall structure that can be quickly assembled on site and a construction method. Background Art
[0002] Continuous heavy rainfall triggered landslides and river surges, causing the riverside roadbed retaining structures to be washed away and smashed, and the special protective structures set up on the inner slopes to be damaged. In the emergency road maintenance section, the existing solution is to re-install the retaining structure on site, which takes a long time to rescue and obviously cannot meet the requirements of rapid road maintenance and curbing the development of disasters. How to quickly realize the construction of retaining structures is an urgent problem that the engineering community needs to solve. Summary of the invention
[0003] In order to solve the above-mentioned problems, the present invention provides a permanent and temporary combined retaining wall structure and a construction method that can be quickly assembled on site. By adopting this solution, the retaining wall can be assembled on site through prefabricated components, which saves rescue time, can be quickly formed in the maintenance stage, reduces the damage to roads and pedestrians caused by landslides, and further stabilizes the slope.
[0004] The technical solution adopted by the present invention is: a permanent and temporary combined retaining wall structure that can be quickly assembled on site, comprising a frame unit close to the roadbed slope and a protective net arranged outside the frame unit;
[0005] The frame unit includes a plurality of transverse tubes and a plurality of support units;
[0006] The support unit includes a transverse tube and a column unit, there are two column units, and the support unit is arranged along the width direction of the roadbed;
[0007] The column unit comprises a vertical tube and a six-way pipe fitting, the two ends of the horizontal tube are necked, one end of the vertical tube is necked, the sizes of the vertical tube and the horizontal tube are matched with the six-way pipe fitting, and the necked end of the vertical tube is inserted into the six-way pipe fitting;
[0008] The same sides of the two column units are connected by a transverse tube, and the two ends of the transverse tube are respectively inserted into the six-way pipe fittings on the same side of the two column units;
[0009] The plurality of support units are arranged along the length direction of the roadbed; the same sides of two adjacent support units are connected by a transverse pipe, and the two ends of the transverse pipe are respectively inserted into the six-way pipe fittings on the same side of the two support units.
[0010] When this scheme is in operation, the vertical pipe is connected with the six-way pipe fitting, wherein the vertical pipe and the six-way pipe fitting have matching sizes, the horizontal pipe is inserted into the six-way pipe fitting to form a column unit, one column unit is set close to the slope, and the other column unit is set away from the slope, the two column units are connected by the horizontal pipe, and the six-way pipe fittings inserted into the two column units form a support unit, and there are multiple support units, which are set along the length of the roadbed, and the two adjacent support units are connected by the horizontal pipe to further form a frame unit, wherein the four horizontal ports of the six-way pipe fitting are used to connect the horizontal pipe, and the two vertical ports are used to connect the vertical pipe, so the frame unit can be infinitely lengthened in theory. The frame unit should be set at the roadbed slope, and a protective net should be set outside the frame unit. When a landslide occurs, the falling rocks will fall directly into the frame unit, and the protective net can block the falling rocks alone, reducing the damage to the road and pedestrians.
[0011] Furthermore, there are multiple frame units, and the multiple frame units are stacked in sequence along the height direction of the roadbed slope.
[0012] When this scheme is put into operation, when a landslide or slope damage is serious, another frame unit can be stacked on top of the frame unit in turn according to the on-site conditions, and the two adjacent frame units in the height direction are connected by six-way pipe fittings.
[0013] Furthermore, it also includes a plurality of grouting pipes, which are inserted into the foundation through the vertical pipes in the frame unit, and the grouting pipes are located inside the vertical pipes.
[0014] In the specific operation of this scheme, since the interior of the vertical pipe and the six-way pipe fittings are hollow, a grouting pipe can be directly driven into the vertical pipe, driven into the foundation 2 to 3 meters, and grouting is performed to improve the stability of the frame unit;
[0015] Furthermore, the grouting pipe is inserted into the slope through a transverse pipe in the frame unit, and the grouting pipe is located inside the transverse pipe.
[0016] When this scheme is put into practice, when the landslide is more serious, a grouting pipe can be driven into the inside of the horizontal pipe in the frame unit, and then driven into the slope to grout the slope and reinforce the slope to prevent further development of collapse.
[0017] Furthermore, there are multiple vertical pipes in the column unit, and the multiple vertical pipes are stacked in sequence.
[0018] When this solution is put into operation, multiple vertical pipes can be arranged in the column unit, and each vertical pipe is connected in sequence. After reaching a certain height, the six-way pipe fittings are connected to save the cost of using horizontal pipes.
[0019] Furthermore, in order to improve the stability of the frame unit, it is configured as follows: the transverse pipe, six-way pipe fitting, vertical pipe and protective net are all made of steel material.
[0020] Furthermore, a permanent and temporary combined retaining wall structure and construction method for rapid on-site assembly includes the following steps:
[0021] S1: Factory prefabricated horizontal pipes, six-way pipe fittings, grouting pipes, vertical pipes and protective nets;
[0022] S2: Quickly assemble the frame units on the roadbed slope and increase the length of the frame units according to the damage of the roadbed slope on site.
[0023] S3: Install a protective net on the outside of the frame unit and fill the inside of the frame unit with gravel from the site;
[0024] S4: Insert grouting pipes into the vertical pipes in the frame unit, and insert the grouting pipes into the foundation for grouting.
[0025] S5: After grouting is completed and the road foundation is secured, the frame unit is externally formworked and concrete is poured to form a permanent retaining wall support.
[0026] Furthermore, S2 also includes the following sub-steps: when the roadbed slope at the site is severely damaged, the frame units can be stacked upwards in sequence according to the damage situation.
[0027] Furthermore, the S4 also includes the following sub-steps: when the slope collapses seriously, inserting a grouting pipe into the interior of the transverse pipe in the frame unit, and inserting the grouting pipe into the slope for grouting.
[0028] When this scheme is put into operation, a plurality of parts required in this scheme are prefabricated first, and then the parts are directly sent to the landslide section, and the frame unit can be directly assembled on site. In the existing scheme, it takes a lot of time to arrive at the landslide site and then start to make the rescue device, while this scheme can directly achieve the effect of rapid rescue, save rescue time, and enable the road to be quickly opened; when assembling the frame unit, the length of the frame unit should be reasonably lengthened according to the actual damage situation on site, and the frame unit can also be repeatedly stacked in the height direction. The structure of this device is simple and can be quickly assembled to achieve the effect of quickly opening the section; after the frame unit is assembled, a protective net is fixedly installed on the side of the frame unit to make the landslide The fallen gravel and the like directly enter the frame unit and will not fall out of the frame unit. In previous landslides, the fallen gravel and the like on site can be filled in the frame unit for storage. Then a grouting pipe is inserted into the vertical pipe in the frame unit and inserted 2-3m downward into the foundation for grouting to further stabilize the frame unit. If the slope collapses severely, a grouting pipe is also inserted into the inside of the horizontal pipe in the frame unit and the grouting pipe is inserted into the slope for grouting to reinforce the slope and prevent further collapse. Finally, after the grouting is completed and the roadbed is secured, the outside of the frame unit is supported by formwork and concrete is poured to form a permanent retaining wall support, which continuously stabilizes the mountain while providing safety for a long time.
[0029] The present invention has the following beneficial effects:
[0030] This solution provides a permanent and temporary combined retaining wall structure and construction method that can be quickly assembled on site. With this solution, the retaining wall can be assembled on site through prefabricated components, which saves rescue time and can be quickly formed during the maintenance phase, reducing the damage to roads and pedestrians caused by landslides and further stabilizing the slopes. The temporary frame unit can be supported by external formwork and poured with concrete to form a permanent retaining wall support, providing safety for a long time. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 A front view of a permanent and temporary combined retaining wall structure and a construction method for quick on-site assembly provided by the present invention;
[0032] Figure 2 A side view of a permanent and temporary combined retaining wall structure and a construction method for rapid on-site assembly provided by the present invention;
[0033] Figure 3 A schematic diagram of the structure of the transverse tube provided by the present invention;
[0034] Figure 4 A schematic diagram of the structure of the vertical pipe provided by the present invention;
[0035] Figure 5 A schematic diagram of the structure of a six-way pipe fitting provided by the present invention;
[0036] The reference numerals in the figure are: 1- horizontal pipe, 2- six-way pipe fitting, 3- grouting pipe, 4- vertical pipe, 5- protective net. DETAILED DESCRIPTION
[0037] The present invention is further described in detail below in conjunction with embodiments.
[0038] Example: Figures 1 to 5 As shown, a permanent and temporary combined retaining wall structure that can be quickly assembled on site includes a frame unit close to the roadbed slope and a protective net 5 arranged outside the frame unit;
[0039] The frame unit includes a plurality of transverse tubes 1 and a plurality of support units;
[0040] The support unit includes a transverse pipe 1 and a column unit, there are two column units, and the support unit is arranged along the width direction of the roadbed;
[0041] The column unit includes a vertical tube 4 and a six-way pipe fitting 2. The two ends of the horizontal tube 1 are necked, and one end of the vertical tube 4 is necked. The sizes of the vertical tube 4 and the horizontal tube 1 are matched with the six-way pipe fitting 2, and the necked end of the vertical tube 4 is inserted into the six-way pipe fitting 2.
[0042] The same sides of the two column units are connected by a transverse tube 1, and the two ends of the transverse tube 1 are respectively inserted into the six-way pipe fittings 2 on the same side of the two column units;
[0043] The plurality of support units are arranged along the length direction of the roadbed; the same sides of two adjacent support units are connected by a transverse pipe 1, and the two ends of the transverse pipe 1 are respectively inserted into the six-way pipe fittings 2 on the same sides of the two support units.
[0044] In this embodiment, the vertical pipe 4 is connected to the six-way pipe fitting 2, wherein the vertical pipe 4 and the six-way pipe fitting 2 are matched in size, the horizontal pipe 1 is inserted into the six-way pipe fitting 2 to form a column unit, one column unit is set near the slope, and the other column unit is set away from the slope, and the two column units are connected by the horizontal pipe 1, and the six-way pipe fittings 2 inserted into the two column units form a support unit, and there are multiple support units, which are set along the length direction of the roadbed, and the two adjacent support units are connected by the horizontal pipe 1 to further form a frame unit, wherein the four horizontal ports of the six-way pipe fitting 2 are used to connect the horizontal pipe 1, and the two vertical ports are used to connect the vertical pipe 4, so the frame unit can be infinitely lengthened in theory. The frame unit should be set at the roadbed slope, and a protective net 5 is set outside the frame unit. When a landslide occurs, the falling rocks will fall directly into the frame unit, and the protective net 5 can block the falling rocks alone, reducing the damage to the road and pedestrians.
[0045] Furthermore, there are multiple frame units, and the multiple frame units are stacked in sequence along the height direction of the roadbed slope.
[0046] In this embodiment, when the landslide or slope damage is serious, another frame unit can be stacked on top of the frame unit in sequence according to the on-site conditions, and the two adjacent frame units in the height direction are connected by a six-way pipe fitting 2.
[0047] Furthermore, it also includes a plurality of grouting pipes 3 , which are inserted into the foundation through the vertical pipes 4 in the frame unit, and the grouting pipes 3 are located inside the vertical pipes 4 .
[0048] In this embodiment, since the interior of the vertical pipe 4 and the six-way pipe fitting 2 are both hollow, the grouting pipe 3 can be directly driven into the vertical pipe 4, and the grouting pipe 3 is driven into the foundation 2 to 3m, and grouting is performed to improve the stability of the frame unit;
[0049] Furthermore, the grouting pipe 3 is inserted into the slope through the transverse pipe 1 in the frame unit, and the grouting pipe 3 is located inside the transverse pipe 1 .
[0050] In this embodiment, when the landslide is more serious, a grouting pipe 3 may be driven into the inside of the transverse pipe 1 in the frame unit, and the grouting pipe 3 may be driven into the slope to grout the slope and reinforce the slope to prevent further collapse.
[0051] Furthermore, there are multiple vertical pipes 4 in the column unit, and the multiple vertical pipes 4 are stacked in sequence.
[0052] In this embodiment, a plurality of vertical pipes 4 may be provided in the column unit, and each vertical pipe 4 is connected in sequence, and after reaching a certain height, the six-way pipe fitting 2 is connected, thereby saving the cost of using the horizontal pipe 1 .
[0053] In this embodiment, in order to improve the stability of the frame unit, it is configured as follows: the horizontal pipe 1, the six-way pipe fitting 2, the vertical pipe 4 and the protective net 5 are all made of steel material.
[0054] In this embodiment, a permanent and temporary combined retaining wall structure and construction method for rapid on-site assembly includes the following steps:
[0055] S1: Factory prefabricated horizontal pipe 1, six-way pipe fitting 2, grouting pipe 3, vertical pipe 4 and protective net 5;
[0056] S2: Quickly assemble the frame units on the roadbed slope and increase the length of the frame units according to the damage of the roadbed slope on site.
[0057] S3: Install a protective net 5 on the outside of the frame unit and fill the inside of the frame unit with gravel on site;
[0058] S4: insert the grouting pipes 3 into the vertical pipes 4 in the frame unit, and insert the grouting pipes 3 into the foundation for grouting.
[0059] S5: After grouting is completed and the road foundation is secured, the frame unit is externally formworked and concrete is poured to form a permanent retaining wall support.
[0060] In this embodiment, S2 further includes the following sub-steps: when the roadbed slope at the site is severely damaged, the frame units can be stacked upwards in sequence according to the damage situation.
[0061] In this embodiment, S4 further includes the following sub-steps: when the slope collapses seriously, a grouting pipe 3 is inserted into the interior of the transverse pipe 1 in the frame unit, and the grouting pipe 3 is inserted into the slope for grouting.
[0062] In this embodiment, a plurality of parts required in this scheme are prefabricated first, and then the parts are directly sent to the landslide section, and the frame unit can be directly assembled on site. In the existing scheme, it takes a lot of time to make the rescue device from the time of arriving at the landslide site, while this scheme can directly achieve the effect of rapid rescue, save rescue time, and enable the road to be quickly opened; when assembling the frame unit, the length of the frame unit should be reasonably lengthened according to the actual damage on site, and the frame unit can also be repeatedly stacked in the height direction. The structure of this device is simple and can be quickly assembled to achieve the effect of quickly opening the road section; after the frame unit is assembled, the protective net 5 is fixedly installed on the side of the frame unit to prevent the debris from falling from the landslide from being Stones and the like can directly enter the frame unit and will not fall out of the frame unit. In the previous landslide, the broken stones and the like that have slid down on site can be filled in the frame unit for storage; then the grouting pipe 3 is inserted into the vertical pipe 4 in the frame unit and inserted downward into the foundation 2-3m to perform grouting to further stabilize the frame unit. If the slope collapses seriously, the grouting pipe 3 is also inserted into the inside of the horizontal pipe 1 in the frame unit, and the grouting pipe 3 is inserted into the slope for grouting to reinforce the slope to prevent further development of the collapse; finally, after the grouting is completed and the road foundation is secured, the outside of the frame unit is supported by formwork and concrete is poured to form a permanent retaining wall support, which continuously stabilizes the mountain while providing safety for a long time.
[0063] The specific implementation methods described above further illustrate the objectives, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above description is only a specific implementation method of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.
Claims
1. A permanent and temporary combined retaining wall structure that can be quickly assembled on site, characterized in that: It includes a frame unit close to the roadbed slope and a protective net (5) arranged outside the frame unit; The frame unit comprises a plurality of transverse tubes (1) and a plurality of support units; The support unit comprises a transverse pipe (1) and a column unit, wherein the column units are two and the support unit is arranged along the width direction of the roadbed; The column unit comprises a vertical tube (4) and a six-way pipe fitting (2), the two ends of the horizontal tube (1) are necked, and one end of the vertical tube (4) is necked, the dimensions of the vertical tube (4) and the horizontal tube (1) are matched with the six-way pipe fitting (2), and the necked end of the vertical tube (4) is inserted into the six-way pipe fitting (2); The same sides of the two column units are connected via a transverse tube (1), and the two ends of the transverse tube (1) are respectively inserted into the six-way pipe fittings (2) on the same sides of the two column units; A plurality of the support units are arranged along the length direction of the roadbed; the same sides of two adjacent support units are connected by a transverse pipe (1), and the two ends of the transverse pipe (1) are respectively inserted into the six-way pipe fittings (2) on the same sides of the two support units; There are multiple frame units, and the multiple frame units are stacked in sequence along the height direction of the roadbed slope; It also comprises a plurality of grouting pipes (3), wherein the grouting pipes (3) are inserted into the foundation through the vertical pipes (4) in the frame unit, and the grouting pipes (3) are located inside the vertical pipes (4); After the grouting is completed, the frame unit is externally formworked and concrete is poured to form a permanent retaining wall support.
2. The permanent and temporary combined retaining wall structure that can be quickly assembled on site according to claim 1 is characterized in that: The grouting pipe (3) is inserted into the slope through the transverse pipe (1) in the frame unit, and the grouting pipe (3) is located inside the transverse pipe (1).
3. The permanent and temporary combined retaining wall structure that can be quickly assembled on site according to claim 1 is characterized in that: There are multiple vertical pipes (4) in the column unit, and the multiple vertical pipes (4) are stacked in sequence.
4. The permanent and temporary combined retaining wall structure that can be quickly assembled on site according to claim 1 is characterized in that: The horizontal pipe (1), the six-way pipe fitting (2), the vertical pipe (4) and the protective net (5) are all made of steel.
5. A construction method for a permanent and temporary combined retaining wall structure that can be quickly assembled on site according to any one of claims 1 to 4, characterized in that: The following steps are involved: S1: factory-prefabricated horizontal pipe (1), six-way pipe fittings (2), grouting pipe (3), vertical pipe (4) and protective net (5); S2: Quickly assemble the frame unit on the roadbed slope and increase the length of the frame unit according to the damage of the roadbed slope on site; S3: Install a protective net on the outside of the frame unit and fill the inside of the frame unit with gravel from the site; S4: inserting grouting pipes (3) into the vertical pipes (4) in the frame unit, and inserting the grouting pipes (3) into the foundation to perform grouting; S5: After grouting is completed and the road foundation is secured, the frame unit is externally formworked and concrete is poured to form a permanent retaining wall support.
6. The construction method of a permanent and temporary combined retaining wall structure for rapid on-site assembly according to claim 5, characterized in that: The S2 also includes the following sub-steps: when the roadbed slope at the site is severely damaged, the frame units can be stacked upwards in sequence according to the damage situation.
7. The construction method of a permanent and temporary combined retaining wall structure for rapid on-site assembly according to claim 5, characterized in that: The S4 further comprises the following sub-steps: when the slope collapses seriously, inserting a grouting pipe (3) into the interior of the horizontal pipe (1) in the frame unit, and inserting the grouting pipe (3) into the slope to perform grouting.