An assembled ecological grid landscape corridor and its manufacturing and assembly method

Through the design of the prefabricated ecological grid landscape corridor, standard units and oyster shell fillers are used to woven bamboo strips and bamboo strips, the problems of construction difficulty and environmental damage in the existing technology are solved, and the rapid development of tidal beaches and redness are achieved. The woods are growing, enhancing the ecological tourism function.

CN112176946BActive Publication Date: 2025-01-10BEIBU GULF UNIV +1
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202011190467.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-10-30
Publication Date
2025-01-10
Estimated Expiration
2040-10-30

AI Technical Summary

Technical Problem

When the existing technology enhances the ecological function of coastal mangrove wetlands, restores mangrove forests and promotes the development of medium and low tide beaches, the project cost is high and the construction is difficult. Heavy machinery operations damage the soil of tide beaches, hindering the self-propagation of mangrove plants and offshore organisms. , an ecological tourism channel cannot be formed.

Method used

Using prefabricated ecological grid landscape corridor, through standard units made of bamboo strips and bamboo strips, the convex and concave embedding structure and slope design are used, combined with oyster breeding waste and shell filler to form a gap structure and reduce construction Difficulty and promotes sediment deposition.

Benefits of technology

The rapid and natural development of tidal beaches has been achieved, the mangroves suitable for forests have been increased, the mangroves are accelerated, the construction environment has been reduced, the construction environment has been damaged, the ecological tourism landscape corridor has been formed, and the coastal ecological environment purification and tourism value have been enhanced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112176946B_ABST
    Figure CN112176946B_ABST
Patent Text Reader

Abstract

The present invention discloses an assembled ecological grid landscape corridor and a manufacturing and assembly method thereof, belonging to the technical field of tidal flat management of wetland ecosystems. It includes multiple groups of standard units, which are connected and arranged in sequence according to lines, and a drainage outlet is arranged between two adjacent groups of standard units; each standard unit includes a main body standard component and a plurality of slope foot standard components, the front end of the main body standard component is provided with a convex portion, and the rear end of the main body standard component is provided with a concave portion; a plurality of slope foot standard components are clamped in the lower part of the main body standard component, and are located on the opposite sides of the convex portion of the main body standard component, and a slope surface is arranged on the slope foot standard component; gaps are opened on both the main body standard component and the slope foot standard component. The manufacturing and assembly method includes step S1: manufacturing of standard units; step S2: assembly of corridors; the present invention can promote the rapid and natural development of tidal flats, increase mangrove suitable forest beaches, and accelerate the self-propagation process of mangroves.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of wetland ecosystem tidal flat management, in particular to an assembled ecological grid landscape corridor and a manufacturing and assembly method thereof. Background Art

[0002] The low and medium tidal flats are the basic components of the coastal mangrove wetland ecosystem. They are the main habitats for a variety of fish, shrimps, shellfish, snails, seabirds and other animals in the near sea area. They also provide an extremely important suitable site environment for mangrove plants. The elevation of the tidal flat landform determines the species and number of mangrove plants distributed in the intertidal zone, and is a key parameter for controlling the survival of mangrove plants. In order to enhance the ecological functions of coastal mangrove wetlands, restore the species and number of mangroves, promote the natural expansion of mangroves, and further develop the landscape value of coastal mangrove wetlands, it is of great significance to take artificial green measures to accelerate sediment deposition, promote the rapid development of low and medium tidal flats, purify seawater, enhance typhoon protection, improve the ecological environment of coastal mangroves, and create a blue bay.

[0003] Mangrove coastal wetlands have become the scenic spot of modern coastal eco-tourism with their unique tourism resources. The construction of green artificial corridors in mid- and low-tidal flats can not only prevent waves and promote siltation, but is also an indispensable engineering measure in the development of coastal mangrove wetland eco-tourism.

[0004] At present, the main method of using reinforced concrete or stone to build artificial seawalls and cofferdams to protect mangrove coasts and increase the elevation of low- and medium-tidal flats to increase the suitable mangrove forest beaches. The main advantage of this method is that it is fast, and it can be used to cofferdam and reclaim land as needed in the low- and medium-tidal flats at the front of the mangroves where the nearshore tidal wave flow is not very strong. The disadvantages are that the project cost is high, the construction is difficult, and the source of fillers is difficult. The use of heavy machinery and the external transportation of fillers cause serious damage to the soil structure of the tidal flats. Once this damage occurs, it will cause permanent loss of the tidal flats. At the same time, the hard weirs block the exchange of substances and energy inside and outside the dam, which is not only not conducive to the rapid self-propagation of mangrove plants, but also destroys the self-regulation function of mangrove coastal wetlands, is not conducive to the reproduction of near-shore organisms such as shrimps, shellfish, and snails, and cannot form an ecological tourism access channel. Therefore, an ecological corridor that can promote the rapid and natural development of tidal flats, increase the suitable mangrove forest beaches, and accelerate the self-propagation process of mangroves has become an urgent need. Summary of the invention

[0005] The purpose of the present invention is to provide an assembled ecological grid landscape corridor and its production and assembly methods to promote the rapid and natural development of tidal flats, increase mangrove-suitable beach areas, and accelerate the self-propagation process of mangroves in response to the above problems.

[0006] In order to achieve the above object, the technical solution adopted by the present invention is:

[0007] A prefabricated ecological grid landscape corridor comprises a plurality of groups of standard units, wherein the plurality of groups of standard units are connected and arranged in sequence according to a line, and a drainage outlet is arranged between two adjacent groups of standard units; each of the standard units comprises a main body standard component and a plurality of slope foot standard components, wherein a convex portion is arranged at the front end of the main body standard component, and a concave portion is arranged at the rear end of the main body standard component, and the convex portion matches the concave portion; the convex portion of the main body standard component is embedded in the concave portion of an adjacent main body standard component, and the concave portion is embedded in the convex portion of another adjacent main body standard component; a plurality of slope foot standard components are clamped at the lower part of the main body standard component and are located at opposite sides of the convex portion of the main body standard component, and a slope surface is arranged on the slope foot standard component, and one end on the slope surface and close to the main body standard component is higher than one end away from the slope surface and away from the main body standard component; and gaps are provided on both the main body standard component and the slope foot standard component.

[0008] Furthermore, a plurality of vertically penetrating slots are provided on the side of the main standard component, and a convex strip matching the slots is provided on the side of the slope foot standard component facing away from the slope surface, and the convex strip is engaged with the slots.

[0009] Furthermore, the slot is a dovetail slot.

[0010] Furthermore, the main body standard component adopts a frame made of bamboo pieces, and a mat surface woven from bamboo strips to form a first ecological grid bamboo box cage; the slope foot standard component adopts a frame made of bamboo pieces, and a mat surface woven from bamboo strips to form a second ecological grid bamboo box cage; the first ecological grid bamboo box cage and the second ecological grid bamboo box cage are filled with fillers with gaps.

[0011] Furthermore, the filler includes one or more of waste generated by oyster farming, oyster shells and shells.

[0012] Furthermore, the first ecological grid bamboo box cage and the filling inside thereof are solidified as a whole by using a fixing agent; the second ecological grid bamboo box cage and the filling inside thereof are solidified as a whole by using a fixing agent.

[0013] Furthermore, the lines are located on the same contour line.

[0014] A method for making and assembling an assembled ecological grid landscape corridor comprises the following steps:

[0015] Step S1: production of standard cells, as follows:

[0016] (1) The production of the main standard component comprises weaving the first bottom surface, the first top surface and the first side surface of the first ecological grid bamboo box cage with bamboo pieces and bamboo strips, leaving a spacing between the bamboo strips when weaving to form a gap in the outer layer of the main standard component; the front end of the first bottom surface is convex, the rear end of the first bottom surface is concave, and notches are arranged on both sides of the first bottom surface; the first side surface is arranged along the outer contour of the first bottom surface, the front end of the first side surface forms a convex part, the rear end of the first side surface forms a concave part, and the side part of the first side surface forms a slot; the first side surface is curled into a ring shape and the inner space of the ring is filled with fillers and vibrated, and the space between the fillers forms a gap inside the main standard component; the first top surface has the same contour as the first bottom surface, and the first top surface is tied to the upper opening of the first side surface after curling into a ring shape with bamboo strips; the first bottom surface, the first top surface, the first side surface and the filler are immersed in a curing agent, taken out and left to stand for complete curing;

[0017] (2) Production of standard components for the foot of the slope: the second bottom surface, the second top surface, the second side surface and the slope surface of the second ecological grid bamboo box cage are woven with bamboo pieces and bamboo strips. Spacing is left between the bamboo strips when weaving to form a gap in the outer layer of the standard components for the foot of the slope; one side of the second bottom surface is square, and a convex block is arranged on the other side; the middle part of the second side surface is a vertical surface arranged along the side of the second bottom surface where the convex block is arranged, the side part of the second side surface forms a convex strip, and the two ends of the second side surface are a trapezoidal structure for sealing, and the second side surface is connected to the first bottom surface. The slope surface is square, the lower end of the slope surface is tied with the bottom surface by bamboo strips, and the two sides of the slope surface are tied with the inclined surfaces of the trapezoidal structure by bamboo strips; the space formed by the second bottom surface, the second side surface and the slope surface is filled with fillers and compacted by vibration, the space between the fillers forms the gap inside the standard component of the slope foot, and the second top surface is tied with bamboo strips to the second side surface and the upper part of the slope surface; the second bottom surface, the second top surface, the second side surface, the slope surface and the fillers are immersed in a curing agent, taken out and left to stand for complete curing;

[0018] Step S2: Assembly of the corridor, as follows:

[0019] (1) Draw contour lines on the tidal flat, and place multiple groups of standard units in sequence along the contour lines;

[0020] (2) When placing the standard unit, first place the main standard component on the designated line and make the upper end surface of the main standard component horizontal; the convex part of the main standard component is embedded in the concave part of an adjacent main standard component, and the concave part is embedded in the convex part of another adjacent main standard component; the convex strip of the slope foot standard component is inserted into the slot of the main standard component, and the main standard component and the slope foot standard component are snap-fitted.

[0021] Furthermore, the curing agent is oxidized silica gel.

[0022] Furthermore, the immersion time of the slope foot standard component and the main body standard component during production is 3-5 seconds, and the curing time of the slope foot standard component and the main body standard component is greater than 24 hours.

[0023] Due to the adoption of the above technical solution, the present invention has the following beneficial effects:

[0024] 1. The main body standard components and the slope foot standard components of the present invention are both provided with gaps. When the tide is low, water accumulates in the gaps, and small animals can freely cross, lay eggs, and reproduce in the gaps, providing a better habitat for small animals and maintaining the integrity of the tidal flat ecosystem. The main body standard components are connected by recesses and protrusions to form an assembled structure. Manpower or small equipment can be used during construction. Therefore, the assembled structure can reduce the difficulty of construction in medium and low tidal flats, reduce environmental damage during the construction process, and protect tidal flats. By providing a drainage outlet, when high tides and waves come, the advance and retreat of the waves can be accelerated to prevent high tides and waves from causing damage to the entire corridor. The slope foot standard components are arranged on the landward side and the seaward side of the main standard components. When the ebb tide water level is lower than the top of the corridor, the slope surface on the landward side can buffer the impact of the water flow, and the water can slowly penetrate from the internal gaps of the main standard components and the slope foot standard components, thereby reducing the water flow speed in the tidal flat, facilitating the sedimentation of silt in the water flow, and having a good sand settling and silting promoting effect; during high tide, the slope surface on the seaward side can buffer the impact of the tide and prevent the tide from scouring the formed tidal flat. Therefore, the present invention can effectively accelerate the development of medium and low tidal flats, promote the rapid and natural development of tidal flats, increase the suitable mangrove forest beach, and accelerate the self-reproduction process of mangroves.

[0025] 2. The present invention has a simple structure, low cost, easy transportation and quick assembly. The raw materials used are domestic waste, which can be turned into treasure and has good environmental affinity. The construction process has little damage to the environment and has a strong wave-breaking effect. The substances and energy inside and outside the embankment can be exchanged freely. After construction, it can purify seawater, improve the ecological environment of the coastal zone, and serve to create a blue bay. Constructing an assembled ecological grid landscape corridor in the middle and low tidal flats to form a coastal viewing landscape corridor, people can walk on the landscape corridor to enjoy the scenery and play, enhance the landscape effect, have a good ecological tourism function, and enhance people's sense of participation in the landscape.

[0026] 3. The present invention improves the structural strength of the main standard components and the slope foot standard components through overall curing of the curing agent. The curing agent separates the manufacturing materials of the main standard components and the slope foot standard components from seawater, preventing the manufacturing materials from being corroded and causing the service life to be shortened, thereby increasing the service life of the entire invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a layout diagram of the present invention assembled on a tidal flat.

[0028] Figure 2 It is an assembly diagram of multiple standard units of the present invention.

[0029] Figure 3 It is a three-dimensional diagram of the main standard component of the present invention.

[0030] Figure 4 It is a three-dimensional diagram of the standard component of the slope foot of the present invention.

[0031] In the attached drawings, 1-standard unit, 2-drainage outlet, 3-contour line, 4-main body standard component, 5-slope foot standard component, 6-slot, 7-convex strip, 8-convex part, 9-concave part, 10-slope surface. Implementation

[0032] The specific implementation of the invention is further described below with reference to the accompanying drawings.

[0033] In the description of the present invention, it is necessary to understand that the terms "center", "length", "width", "up", "down", "vertical", "horizontal", "top", "bottom", "inside" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0034] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be directly connected or indirectly connected through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0035] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, a first feature being "above", "above" and "above" a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.

[0036] See also Figures 1 to 4, an assembled ecological grid landscape corridor, comprising a plurality of groups of standard units 1, which are connected and arranged in sequence according to lines, and a drainage outlet 2 is arranged between two adjacent groups of standard units 1; each standard unit 1 comprises a main body standard component 4 and a plurality of slope foot standard components 5, the main body standard component 4 is columnar, a gap is arranged in the main body standard component 4, a convex portion 8 is arranged at the front end of the main body standard component 4, and a concave portion 9 is arranged at the rear end of the main body standard component 4, and the convex portion 8 and the concave portion 9 match; the convex portion 8 of the main body standard component 4 is embedded with the concave portion 9 of an adjacent main body standard component 4, and the concave portion 9 is embedded with the convex portion 8 of another adjacent main body standard component 4; a plurality of slope foot standard components 5 are stuck at the lower part of the two opposite sides of the main body standard component 4, and a slope surface 10 is arranged on the slope foot standard component 5, and one end on the slope surface 10 and close to the main body standard component 4 is higher than one end away from the slope surface 10 and away from the main body standard component 4; gaps are arranged in both the main body standard component 4 and the slope foot standard component 5.

[0037] In this embodiment, the side of the main standard component 4 is provided with a plurality of slots 6 that pass through from top to bottom, and the side of the slope foot standard component 5 facing away from the slope surface 10 is provided with a convex strip 7 that matches the slot 6, and the convex strip 7 is engaged with the slot 6, and the slot 6 is a dovetail slot. The main standard component 4 adopts a frame made of bamboo pieces, and a mat surface woven from bamboo strips is enclosed to form a first ecological grid bamboo box cage; the slope foot standard component 5 adopts a frame made of bamboo pieces, and a mat surface woven from bamboo strips is enclosed to form a second ecological grid bamboo box cage; the first ecological grid bamboo box cage and the second ecological grid bamboo box cage are filled with fillers with gaps. The fillers include one or more of waste generated by oyster farming, oyster shells and shells. The first ecological grid bamboo box cage and the fillers inside it are solidified as a whole by a fixing agent; the second ecological grid bamboo box cage and the fillers inside it are solidified as a whole by a fixing agent. The line is located on the same contour line 3. Specifically, the height of the main standard component 4 is 0.5 meters, the width is 1 meter, and the side length connected to the slope foot standard component 5 is 1 meter; the length of the slope foot standard component 5 is 1 meter, the height is 0.25 meters, and the straight surface dimension of the slope foot standard component 5 is a rectangle with a length of 1 meter and a width of 0.36.

[0038] A method for making and assembling an assembled ecological grid landscape corridor comprises the following steps:

[0039] Step S1: Production of standard cell 1, specifically as follows:

[0040] (1) The main standard component 4 is made by weaving the first bottom surface, the first top surface and the first side surface of the first ecological grid bamboo box cage with bamboo pieces and bamboo strips. When weaving, a spacing is left between the bamboo strips to form a gap in the outer layer of the main standard component 4; the front end of the first bottom surface is convex, the rear end of the first bottom surface is concave, and notches are set on both sides of the first bottom surface; the first side surface is set along the outer contour of the first bottom surface, the front end of the first side surface forms a convex portion 8, the rear end of the first side surface forms a concave portion 9, and the side portion of the first side surface forms a slot 6; the first side surface is curled into a ring The ring-shaped inner space is filled with fillers and compacted by vibration. In this embodiment, the fillers are a mixed filler of equal volumes of waste, oyster shells and shells, and the gaps between the fillers form the gaps inside the main standard component 4; the first top surface has the same contour as the first bottom surface, and the first top surface is tied to the upper opening of the first side surface after curling into a ring shape with bamboo strips; the first bottom surface, the first top surface, the first side surface and the filler are immersed in a curing agent, taken out and left to stand for complete curing. During curing, the curing agent adheres to the surface of the entity and the gap will not be filled with the curing agent.

[0041] (2) Production of the standard component 5 for the foot of the slope: the second bottom surface, the second top surface, the second side surface and the slope surface 10 of the second ecological grid bamboo box cage are woven with bamboo pieces and bamboo strips. When weaving, a spacing is left between the bamboo strips to form a gap in the outer layer of the standard component 5 for the foot of the slope; one side of the second bottom surface is square, and a convex block is arranged on the other side; the middle part of the second side surface is a vertical surface arranged along the side where the convex block is arranged, and a convex strip 7 is formed on the side of the second side surface. The two ends of the second side surface are trapezoidal structures for sealing. The second side surface and the first bottom surface are tied together by bamboo strips; the slope surface 10 is square, and the lower end of the slope surface 10 and the bottom surface are tied together by bamboo strips. The two sides of the slope surface 10 are tied with the slope surface of the trapezoidal structure by bamboo strips; the space formed by the second bottom surface, the second side surface and the slope surface 10 is filled with fillers and compacted by vibration. In this embodiment, the fillers are mixed fillers of equal volumes of waste, oyster shells and shells, and the gaps between the fillers form the gaps inside the slope foot standard component 5. The second top surface is tied to the second side surface and the upper part of the slope surface 10 with bamboo strips; the second bottom surface, the second top surface, the second side surface, the slope surface 10 and the fillers are immersed in a curing agent, taken out and left to stand for complete curing. During curing, the curing agent adheres to the solid surface and the gaps will not be filled with the curing agent.

[0042] Step S2: Assembly of the corridor, as follows:

[0043] (1) Contour lines 3 are drawn on the tidal flat, and multiple groups of standard units 1 are placed in sequence along the contour lines 3;

[0044] (2) When placing the standard unit 1, first place the main standard component 4 on the designated line and make the upper end surface of the main standard component 4 horizontal; the convex portion 8 of the main standard component 4 is embedded in the concave portion 9 of an adjacent main standard component 4, and the concave portion 9 is embedded in the convex portion 8 of another adjacent main standard component 4; the convex strip 7 of the slope foot standard component 5 is inserted into the slot 6 of the main standard component 4, and the main standard component 4 and the slope foot standard component 5 are snap-fitted.

[0045] In this embodiment, the curing agent is oxidized silica gel. The immersion time of the slope foot standard component 5 and the main body standard component 4 during production is 3-5 seconds, and the curing time of the slope foot standard component 5 and the main body standard component 4 is greater than 24 hours.

[0046] The above description is a detailed description of the preferred feasible embodiments of the present invention, but the embodiments are not intended to limit the scope of the patent application of the present invention. All equivalent changes or modified changes completed under the technical spirit suggested by the present invention should fall within the patent scope covered by the present invention.

Claims

1. An assembled ecological grid landscape corridor, characterized by: The invention comprises a plurality of groups of standard units, wherein the plurality of groups of standard units are connected and arranged in sequence according to a line, and a drainage outlet is arranged between two adjacent groups of standard units; each of the standard units comprises a main body standard component and a plurality of slope foot standard components, wherein a convex portion is arranged at the front end of the main body standard component, and a concave portion is arranged at the rear end of the main body standard component, and the convex portion matches the concave portion; the convex portion of the main body standard component is embedded in the concave portion of an adjacent main body standard component, and the concave portion is embedded in the convex portion of another adjacent main body standard component; a plurality of slope foot standard components are clamped at the lower part of the main body standard component and are located at opposite sides of the convex portion of the main body standard component, and a slope surface is arranged on the slope foot standard component, and the slope surface and close to the slope surface One end of the main body standard component is higher than the end away from the slope surface and away from the main body standard component; gaps are opened on the main body standard component and the slope foot standard component; a number of vertically penetrating slots are arranged on the side of the main body standard component, and a convex strip matching the slot is arranged on the side of the slope foot standard component facing away from the slope surface, and the convex strip is engaged with the slot; the main body standard component adopts a frame made of bamboo pieces, and a mat surface woven with bamboo strips is used to form a first ecological grid bamboo box cage; the slope foot standard component adopts a frame made of bamboo pieces, and a mat surface woven with bamboo strips is used to form a second ecological grid bamboo box cage; the first ecological grid bamboo box cage and the second ecological grid bamboo box cage are filled with fillers with gaps.

2. The assembled ecological grid landscape corridor according to claim 1 is characterized by: The slot is a dovetail slot.

3. The assembled ecological grid landscape corridor according to claim 1 is characterized by: The filler includes one or more of waste generated by oyster farming, oyster shells and shells.

4. The assembled ecological grid landscape corridor according to claim 1 is characterized by: The first ecological grid bamboo box cage and the filler therein are solidified as a whole by using a fixing agent; the second ecological grid bamboo box cage and the filler therein are solidified as a whole by using a fixing agent.

5. The assembled ecological grid landscape corridor according to claim 1 is characterized by: The lines are located on the same contour line.

6. A method for making and assembling an assembled ecological grid landscape corridor, characterized in that: The steps include: Step S1: production of standard cells, as follows: (1) The production of the main standard component comprises weaving the first bottom surface, the first top surface and the first side surface of the first ecological grid bamboo box cage with bamboo pieces and bamboo strips, leaving a spacing between the bamboo strips when weaving to form a gap in the outer layer of the main standard component; the front end of the first bottom surface is convex, the rear end of the first bottom surface is concave, and notches are arranged on both sides of the first bottom surface; the first side surface is arranged along the outer contour of the first bottom surface, the front end of the first side surface forms a convex part, the rear end of the first side surface forms a concave part, and the side part of the first side surface forms a slot; the first side surface is curled into a ring shape and the inner space of the ring is filled with fillers and vibrated, and the space between the fillers forms a gap inside the main standard component; the first top surface has the same contour as the first bottom surface, and the first top surface is tied to the upper opening of the first side surface after curling into a ring shape with bamboo strips; the first bottom surface, the first top surface, the first side surface and the filler are immersed in a curing agent, taken out and left to stand for complete curing; (2) Production of standard components for the foot of the slope: the second bottom surface, the second top surface, the second side surface and the slope surface of the second ecological grid bamboo box cage are woven with bamboo pieces and bamboo strips. Spacing is left between the bamboo strips when weaving to form a gap in the outer layer of the standard components for the foot of the slope; one side of the second bottom surface is square, and a convex block is arranged on the other side; the middle part of the second side surface is a vertical surface arranged along the side of the second bottom surface where the convex block is arranged, the side part of the second side surface forms a convex strip, and the two ends of the second side surface are a trapezoidal structure for sealing, and the second side surface is connected to the first bottom surface. The slope surface is square, the lower end of the slope surface is tied with the bottom surface by bamboo strips, and the two sides of the slope surface are tied with the inclined surfaces of the trapezoidal structure by bamboo strips; the space formed by the second bottom surface, the second side surface and the slope surface is filled with fillers and compacted by vibration, the space between the fillers forms the gap inside the standard component of the slope foot, and the second top surface is tied with bamboo strips to the second side surface and the upper part of the slope surface; the second bottom surface, the second top surface, the second side surface, the slope surface and the fillers are immersed in a curing agent, taken out and left to stand for complete curing; Step S2: Assembly of the corridor, as follows: (1) Draw contour lines on the tidal flat, and place multiple groups of standard units in sequence along the contour lines; (2) When placing the standard unit, first place the main standard component on the designated line and make the upper end surface of the main standard component horizontal; the convex part of the main standard component is embedded in the concave part of an adjacent main standard component, and the concave part is embedded in the convex part of another adjacent main standard component; the convex strip of the slope foot standard component is inserted into the slot of the main standard component, and the main standard component and the slope foot standard component are snap-fitted.

7. The method for making and assembling an assembled ecological grid landscape corridor according to claim 6 is characterized in that: The curing agent is oxidized silica gel.

8. The method for making and assembling an assembled ecological grid landscape corridor according to claim 7 is characterized in that: The immersion time of the slope foot standard component and the main body standard component during production is 3-5 seconds, and the curing time of the slope foot standard component and the main body standard component is greater than 24 hours.

Citation Information

Patent Citations

  • Fabricated ecological grid landscape corridor

    CN213740833U