A precast concrete pipe pile as a beam-column node of an upper column and a construction method thereof

The combination of precast concrete pipe piles and structural beams solves the problems of high cost and low fault tolerance of ordinary reinforced concrete precast columns, achieves convenience and safety in construction, and is suitable for prefabricated building structures.

CN112376705BActive Publication Date: 2024-10-08GUANGDONG JIANKE ARCHITECTURE DESIGN INST
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202011161796.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-10-27
Publication Date
2024-10-08
Estimated Expiration
2040-10-27

AI Technical Summary

Technical Problem

Existing ordinary reinforced concrete precast columns have high cost, high precision requirements and low fault tolerance, resulting in increased construction schedule and cost.

Method used

Precast concrete pipe piles are used as the connection points between upper columns and structural beams. Through the cooperation of steel rings and annular steel plates, combined with steel bar anchoring, beam-column nodes are formed to achieve construction convenience and safety, and different strengths can be selected according to needs. Grout and steel bars.

Benefits of technology

It reduces construction costs, improves construction progress and installation fault tolerance, has a wide range of applications, and is suitable for widespread promotion.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112376705B_ABST
    Figure CN112376705B_ABST
Patent Text Reader

Abstract

The present invention discloses an assembled concrete beam-column node with precast concrete pipe piles as upper columns and a construction method thereof. The upper columns are upper precast concrete pipe piles. The lower end surface of the upper precast concrete pipe piles has its own steel ring. The top of the structural beam located in the beam-column node area is provided with an annular steel plate. The middle openings of the steel ring and the annular steel plate correspond to the pile core holes of the upper precast concrete pipe piles. The lower surface of the steel ring is connected to the upper surface of the annular steel plate. A steel bar is provided in the beam-column node area. The upper end of the steel bar is connected to the annular steel plate, and the lower end extends downward into the beam-column node area for anchoring. A section of pipe pile that meets the requirements is cut from the standard pipe pile as the precast concrete pipe pile of the present invention. The section of pipe pile includes the bottom of the standard pipe pile, so that the pipe pile with the steel ring at the bottom can be used as a precast column in the beam-column node. The beam-column node connection method of the present invention is simple to operate, convenient to construct, safe and reliable, and has a low tolerance for construction and installation errors, which can speed up the construction progress and reduce the construction cost.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technology of assembled concrete building structure, and in particular relates to a beam-column node using a prefabricated concrete pipe pile as an upper column and a construction method thereof. Background Art

[0002] Article 3.0.3 of the "Assembly Evaluation Standard" (GB / T51129-2017) stipulates that the evaluation score of the main structure of an assembled building should be no less than 20 points. In the assembled building scoring table, the main structure has a full score of 50 points, among which the proportion of vertical components such as columns, supports, load-bearing walls, and ductile wall panels reaches 35% to 80%, and the score can be 20 to 30 points. The proportion of components such as beams, plates, stairs, balconies, and air-conditioning panels reaches 70% to 80%, and the score can be 10 to 20 points. If the vertical components are not prefabricated, the proportion of beams, plates, stairs, balconies, air-conditioning panels, etc. must reach 80%, which will bring great difficulties to the disassembly of the components. Therefore, vertical components are often prefabricated.

[0003] At present, among prefabricated vertical components, ordinary reinforced concrete prefabricated columns using sleeve grouting connection method are widely used. However, such ordinary reinforced concrete prefabricated columns have the following disadvantages:

[0004] ⑴ The cost is very high, usually three to four thousand yuan per cubic meter, and due to its large size, higher performance requirements are placed on the crane.

[0005] ⑵ Ordinary reinforced concrete precast columns use the sleeve grouting connection method, which places high demands on the manufacturing and installation accuracy of the precast columns. Ordinary reinforced concrete precast columns have a low fault tolerance rate. If there is an error in any link, the precast column may not be usable and needs to be remade by the precast component factory, which will undoubtedly affect the construction progress and increase the construction cost. Summary of the invention

[0006] The first object of the present invention is to provide a prefabricated concrete pipe pile as an assembled concrete beam-column node for upper columns, which is convenient to construct, safe and reliable, has a low tolerance for construction and installation errors, can speed up construction progress, and reduce construction costs.

[0007] The first object of the present invention is achieved through the following technical scheme: a prefabricated concrete beam-column node with precast concrete pipe piles as upper columns, comprising upper columns, lower concrete components and structural beams, wherein the upper columns, lower concrete components and structural beams are located between the beam-column node area, characterized in that the upper columns are upper precast concrete pipe piles, the lower end faces of the upper precast concrete pipe piles have their own steel rings, an annular steel plate is provided at the top of the structural beam located in the beam-column node area, the middle openings of the steel ring and the annular steel plate correspond to the pile core holes of the upper precast concrete pipe piles, the lower surface of the steel ring is connected to the upper surface of the annular steel plate, a plurality of steel bars are provided in the beam-column node area, the upper ends of the steel bars are connected to the lower surface of the annular steel plate, and the lower ends extend downward into the beam-column node area for anchoring.

[0008] The present invention uses precast concrete pipe piles as upper columns and is assembled and connected with structural beams to form beam-column nodes. The precast concrete pipe piles are rigidly connected to the nodes to meet the stiffness requirements. The present invention uses precast concrete pipe piles as upper precast columns. A section of pipe piles that meets the requirements can be cut from the produced standard pipe piles, and the section of pipe piles includes the bottom of the standard pipe piles, so that the section of pipe piles with steel rings at the bottom can also be used as precast columns for use in beam-column nodes. Moreover, the present invention does not need to produce precast columns according to different axial forces, bending moments and lengths required in different actual projects, so that mass production is achieved and the cost is low. The beam-column node connection method of the present invention is simple to operate, convenient to construct, safe and reliable, and has a low tolerance for construction and installation errors, which can speed up the construction progress and reduce the construction cost. In addition, the present invention uses precast concrete pipe piles as precast columns of prefabricated concrete building structures. The production technology of precast concrete pipe piles is mature, the cost is low, and the installation is easy, which is conducive to the development of prefabrication. Moreover, suitable pipe piles can be used according to actual needs, and grouting materials or concrete of any strength can be selected for grouting as needed. Any type of prestressed or non-prestressed steel bars can also be used. Therefore, the present invention has a wide range of applications and is suitable for widespread promotion and use.

[0009] The lower layer concrete component of the present invention is a foundation, a lower layer cast-in-place column, a lower layer prefabricated ordinary concrete column or a lower layer prefabricated concrete pipe pile.

[0010] The outer diameter of the annular steel plate of the present invention is greater than the outer diameter of the steel ring.

[0011] As an improvement of the present invention, the prefabricated concrete beam-column node includes dowel bars, which pass through the beam-column node area and extend into the upper precast concrete pipe piles and the lower concrete components for anchoring.

[0012] As a preferred embodiment of the present invention, the dowel bars are a steel cage mainly composed of a plurality of connecting steel bars and stirrups, wherein the connecting steel bars pass through the beam-column node area and extend into the pile cores of the upper precast concrete pipe piles and the lower precast concrete pipe piles for anchoring respectively, and the connecting steel bars are distributed along the periphery of the pile cores, and the stirrups hold the connecting steel bars.

[0013] As an implementation mode of the present invention, the dowel bars are arranged along the entire length of the pile cores of the upper precast concrete pipe piles and the lower precast concrete pipe piles.

[0014] As another embodiment of the present invention, the dowel bars extend a section into the pile cores of the upper precast concrete pipe piles and the lower precast concrete pipe piles.

[0015] As a preferred embodiment of the present invention, the annular steel plate is located between the plate reinforcement or beam stirrups of the structural beam and the beam surface. If the distance between the two is small, the annular steel plate can also be slightly higher than the beam surface and can be flattened during decoration.

[0016] The concrete grade of the beam-column node area of ​​the present invention is the same as the concrete grade of the structural beam, and the cross-section of the beam-column node area is greater than or equal to the cross-section of the precast concrete pipe pile.

[0017] In the case where there is a large difference in the concrete strength of the beam and column, if the concrete grade of the beam-column node area is the same as the concrete grade of the structural beam, when the strength of the column is very large, the node is prone to damage. In order to solve this problem, the existing practice is to cast the node and the beam separately using concrete of different grades. However, this practice has the disadvantages of inconvenient construction and low construction efficiency. The beam-column node of the present invention performs appropriate area enlargement according to its different bearing capacity to enhance the bearing capacity of the node and reduce the possibility of node damage. The beam-column node can use concrete of the same strength as the structural beam, so that it can be cast in one go, which is convenient for construction and efficient.

[0018] When the beam-column node area is small, the anchoring length of the steel bar set in the beam-column node area may be insufficient. In order to increase the anchoring length, the lower end of the steel bar of the present invention is bent. When the anchoring length of the steel bar is sufficient, the lower end may not be bent, that is, the steel bar is in a vertical straight line.

[0019] The cross-sectional shape of the beam-column node area of ​​the present invention is rectangular, rhombus or circular, and other shapes may also be adopted according to actual engineering needs. It is flexible to use and convenient for actual installation and operation.

[0020] The structural beams described in the present invention are prefabricated beams, cast-in-place beams or composite beams.

[0021] Preferably, the precast concrete pipe piles of the present invention are PHC / PC / PRCI / PRCII hollow pipe piles with prestressed or non-prestressed steel bars, and any other strength and model of pipe piles can also be used.

[0022] The second object of the present invention is to provide a construction method for an assembled concrete beam-column node using the above-mentioned precast concrete pipe piles as upper columns.

[0023] The second object of the present invention is achieved by the following technical solution: a construction method of an assembled concrete beam-column node using precast concrete pipe piles as upper columns, characterized in that it specifically includes the following steps:

[0024] S1. Install the casting molds for the lower concrete components and beams and slabs;

[0025] S2. Install the annular steel plate on the top of the structural beam at the beam-column node area;

[0026] S3. Weld steel bars on the lower surface of the annular steel plate, and extend the lower end of the steel bars into the beam-column node area for anchoring;

[0027] S4, installing the upper precast concrete pipe piles, and welding the lower surface of the steel ring of the upper precast concrete pipe piles to the upper surface of the annular steel plate;

[0028] S5. Grouting is performed from the upper end of the upper precast concrete pipe pile into the pile core hole, that is, the pile core, beam-column node area and lower concrete components of the upper precast concrete pipe pile are poured at one time.

[0029] The present invention adopts prefabricated concrete pipe piles as the template for on-site pouring, and the construction is simple and convenient.

[0030] Compared with the prior art, the present invention has the following significant effects:

[0031] (1) The present invention uses precast concrete pipe piles as upper columns to be assembled and connected with structural beams to form beam-column nodes. The precast concrete pipe piles are rigidly connected to the nodes to meet the rigidity requirements.

[0032] (2) The present invention uses precast concrete pipe piles as precast columns, and standard pipe piles can be selected according to different axial forces required in different practical projects. Moreover, a section of pipe piles that meets the requirements can be cut from the produced standard pipe piles according to the different lengths required in different practical projects, and the section of pipe piles includes the bottom of the standard pipe piles, so that the section of pipe piles with a steel ring at the bottom can also be used as a precast column for use in beam-column joints. There is no need to produce precast columns according to different axial forces, bending moments and lengths required in different practical projects, so the present invention can achieve mass production and has low cost.

[0033] ⑶ The present invention adopts precast concrete pipe piles as the template for on-site pouring. The beam-column node connection method is simple to operate, convenient to construct, safe and reliable, and has a low fault tolerance rate for construction and installation, which can speed up the construction progress and reduce the construction cost.

[0034] (4) The present invention uses precast concrete pipe piles as precast columns of assembled concrete building structures. The production technology of precast concrete pipe piles is mature, the cost is low, and the installation is easy, which is conducive to the development of assembly.

[0035] ⑸ The beam-column node of the present invention is appropriately enlarged in area according to its different bearing capacity to enhance the bearing capacity of the node and reduce the possibility of node damage. The beam-column node can use concrete with the same strength as the structural beam, so it can be poured in one time, which is convenient for construction and high in efficiency.

[0036] (6) The present invention can use pipe piles of other strengths such as PHC / PC with prestressed or non-prestressed steel bars according to actual engineering needs, and can select grouting materials or concrete of any strength for grouting as needed, and can also use any type of prestressed or non-prestressed steel bars. Therefore, the present invention has a wide range of applications and is suitable for widespread promotion and use. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] The present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.

[0038] Figure 1 is a plan view of embodiment 1 of the present invention;

[0039] Figure 2 yes Figure 1 Middle AA section;

[0040] Figure 3 is a cross-sectional view of embodiment 2 of the present invention;

[0041] Figure 4 is a cross-sectional view of embodiment 3 of the present invention;

[0042] Figure 5 is a plan view of embodiment 4 of the present invention;

[0043] Figure 6 yes Figure 5 Middle BB section;

[0044] Figure 7 is a plan view of embodiment 5 of the present invention;

[0045] Figure 8 It is a plan view of Example 6 of the present invention. DETAILED DESCRIPTION

[0046] Example 1

[0047] like Figure 1 , 2 As shown, it is an assembled concrete beam-column node of the present invention with a precast concrete pipe pile as an upper column, including an upper column, a lower concrete component and a structural beam 3, and a beam-column node area 4 is formed between the upper column, the lower concrete component and the structural beam 3. The upper column is an upper precast concrete pipe pile 1, and in this embodiment, the lower concrete component is a lower precast concrete pipe pile 2, and the structural beam 3 can be a precast beam, a cast-in-place beam or a composite beam. The upper precast concrete pipe pile 1 and the lower precast concrete pipe pile 2 can be PHC / PC / PRCI / PRCII hollow pipe piles with prestressed or non-prestressed steel bars. The lower end surface of the upper precast concrete pipe pile 1 has its own steel ring 5, and the top of the structural beam 3 located in the beam-column node area 4 is provided with an annular steel plate 6, and the middle openings of the steel ring 5 and the annular steel plate 6 correspond to the pile core holes of the upper and lower precast concrete pipe piles, and the outer diameter of the annular steel plate 6 is larger than the outer diameter of the steel ring 5, and the lower surface of the steel ring 5 is welded to the upper surface of the annular steel plate 6, and a steel bar 7 is provided in the beam-column node area 4, and the upper end of the steel bar 7 is welded to the lower surface of the annular steel plate 6 and arranged along its circumference, and the lower end extends downward into the beam-column node area 4 for anchoring, and in this embodiment, the steel bar 7 is a vertically arranged straight line, and its anchoring length is sufficient to achieve stable anchoring. In other embodiments, when the beam-column node area is small and the anchoring length of the steel bar is insufficient, in order to increase the anchoring length, the lower end of the steel bar can be bent.

[0048] The assembled concrete beam-column joint of this embodiment also includes dowel bars, which pass through the beam-column joint area and extend into the pile cores of the upper precast concrete pipe pile 1 and the lower precast concrete pipe pile 2 for anchoring, respectively. The appropriate dowel bar type can be selected according to the actual situation. In this embodiment, the dowel bar is a steel cage mainly composed of a plurality of connecting steel bars 8 and stirrups 9, and can also be other dowel bar types. The connecting steel bars 8 pass through the beam-column joint area 4 and extend into the pile cores of the upper precast concrete pipe pile 1 and the lower precast concrete pipe pile 2 for anchoring, and the connecting steel bars 8 are distributed along the periphery of the pile core, and the stirrups 9 hold the connecting steel bars 8. The steel cage extends a section into the pile cores of the upper precast concrete pipe pile 1 and the lower precast concrete pipe pile 2.

[0049] The lower end of the upper precast concrete pipe pile 1 is rigidly connected to the structural beam 3, that is, the lower end of the upper precast concrete pipe pile 1 is connected to the structural beam 3 through the annular steel plate 6, steel bars 7, steel cage and grouting material (or concrete), which is a rigid connection.

[0050] No mortar layer is provided between the upper end of the lower precast concrete pipe pile 2 and the beam-column node area 4 and between the lower end of the upper precast concrete pipe pile 1 and the beam-column node area 4 .

[0051] The assembled concrete beam-column node of the present invention can form a structural system with other common frames, diagonal braces and shear walls.

[0052] In general, the strength of beams and columns is quite different. If the node area uses the same grade of concrete as the beam, the applicant has verified in laboratory tests and site tests that when the strength of the column is very high, the node will be damaged. However, in actual engineering, the node should not be damaged. If the node uses the same grade of concrete as the column, the strength of the node and the beam concrete will be different, and the node and the beam need to be cast separately, which is very inconvenient.

[0053] In order to solve the above problems, when the difference between the concrete grade of the beam-column node area and the concrete grade of the precast concrete pipe pile is greater than 5MPa, the concrete grade of the beam-column node area 4 of the present invention is the same as the concrete grade of the structural beam 3, and the cross section of the beam-column node area 4 is larger than the cross section of the precast concrete pipe pile. In other embodiments, according to actual conditions, the cross section of the beam-column node area can also be equal to the cross section of the precast concrete pipe pile. In this embodiment, the cross section of the beam-column node area 4 is square, and its area is larger than the cross section of the precast concrete pipe pile. That is, compared with the existing beam-column node, the applicant has concluded through theoretical analysis and calculation that the beam-column node can be appropriately enlarged in area according to its different bearing capacity, so as to enhance the bearing capacity of the node and reduce the possibility of node damage. In this way, the beam-column node can use concrete with the same strength as the structural beam, so that it can be poured in one time, which is convenient for construction and efficient.

[0054] The construction process of this embodiment is:

[0055] S1. Install the lower precast concrete pipe piles 2 or the casting molds of the foundation and beam slab.

[0056] S2. Install the annular steel plate 6 at the top of the structural beam 3 in the beam-column node area 4, specifically between the beam-slab reinforcement or beam stirrups 10 and the beam surface; if this position is too small, the annular steel plate can be slightly higher than the beam surface and can be leveled during decoration.

[0057] S3. A section of steel bar 7 is welded on the lower surface of the annular steel plate 6. The steel bar 7 extends into the beam-column node area 4. If the anchoring length is sufficient, no bending is required. If the anchoring length is insufficient, the steel bar 7 can be bent according to actual needs to increase the anchoring length.

[0058] S4, insert the steel cage into the pile core hole of the lower precast concrete pipe pile 2, then install the upper precast concrete pipe pile 1, and pour appropriate concrete into the pile core hole of the upper precast concrete pipe pile, so as to cast the pile core, nodes and beams of the upper and lower precast concrete pipe piles.

[0059] There is no mortar layer between the upper precast concrete pipe piles and the lower precast concrete pipe piles and the nodes.

[0060] Example 2

[0061] like Figure 3 As shown, the difference between this embodiment and embodiment 1 is that the dowel bars are arranged along the entire length of the pile cores of the upper precast concrete pipe piles 1 and the lower precast concrete pipe piles 2 .

[0062] Example 3

[0063] like Figure 4 As shown, the difference between this embodiment and embodiment 1 is that no inserted steel bars are provided in the pile cores of the upper precast concrete pipe pile 1 and the lower precast concrete pipe pile 2. Therefore, whether to insert steel bars in the pile core can be selected according to the actual construction situation.

[0064] Example 4

[0065] like Figure 5 , 6 As shown, the difference between this embodiment and embodiment 1 is that the area of ​​the beam-column node is not enlarged.

[0066] Example 5

[0067] like Figure 7 As shown, the difference between this embodiment and embodiment 1 is that: in this embodiment, the area of ​​the beam-column node is appropriately enlarged according to the actual bearing capacity of the beam-column node, and the cross-sectional shape of the beam-column node area 4 is a diamond shape, which can enhance the bearing capacity of the node and reduce the possibility of node damage. The beam-column node and the structural beam use concrete of the same strength and can be cast in one time.

[0068] Example 6

[0069] like Figure 8 As shown, the difference between this embodiment and embodiment 1 is that: in this embodiment, the area of ​​the beam-column node is appropriately enlarged according to the actual bearing capacity of the beam-column node, and the cross-sectional shape of the beam-column node area 4 is circular, which can enhance the bearing capacity of the node and reduce the possibility of node damage. The beam-column node and the structural beam use concrete of the same strength and can be cast in one time.

[0070] In other embodiments, a suitable shape may be adopted for the beam-column joint according to actual engineering requirements, so that the shape is flexible to use and convenient for actual installation operations.

[0071] In other embodiments, pipe piles of other strengths and types such as PHC / PC with or without prestressed steel bars may be used according to actual engineering needs.

[0072] In other embodiments, grouting material or concrete of any strength may be selected for grouting as required.

[0073] In other embodiments, any type of prestressed or non-prestressed steel bars may be used as required. The steel bars may be of any type, quantity, strength, etc. suitable for actual needs;

[0074] In other embodiments, the structural beams are prefabricated beams or composite beams, and the construction method is similar to that of Embodiment 1. The beam-column nodes are all cast on site, and the specific steps can be adjusted according to the actual site conditions and the types of structural beams.

[0075] The implementation modes of the present invention are not limited to these. Based on the above contents of the present invention, according to the common technical knowledge and customary means in the art, without departing from the above basic technical ideas of the present invention, the present invention may also make other various forms of modification, replacement or change, all of which fall within the scope of protection of the present invention.

Claims

1. An assembled concrete beam-column node with precast concrete pipe piles as upper columns, comprising an upper column, a lower concrete member and a structural beam, wherein the upper column, the lower concrete member and the structural beam form a beam-column node area, characterized in that: The upper column is an upper precast concrete pipe pile, and the lower end surface of the upper precast concrete pipe pile has its own steel ring. The top of the structural beam located in the beam-column node area is provided with an annular steel plate, and the middle openings of the steel ring and the annular steel plate correspond to the pile core holes of the upper precast concrete pipe pile. The lower surface of the steel ring is welded to the upper surface of the annular steel plate, and a plurality of steel bars are provided in the beam-column node area. The upper end of the steel bar is connected to the lower surface of the annular steel plate, and the lower end extends downward into the beam-column node area for anchoring; the outer diameter of the annular steel plate is larger than the outer diameter of the steel ring; the annular steel plate is located between the plate reinforcement or beam stirrup of the structural beam and the beam surface, or the annular steel plate is located above the plate reinforcement or beam stirrup of the structural beam, and the annular steel plate is higher than the beam surface.

2. The precast concrete pipe pile according to claim 1 is used as a prefabricated concrete beam-column node of the upper column, characterized in that: The lower layer concrete component is a foundation, a lower layer cast-in-place column, a lower layer prefabricated ordinary concrete column or a lower layer prefabricated concrete pipe pile.

3. The precast concrete pipe pile according to claim 2 is used as a prefabricated concrete beam-column node of the upper column, characterized in that: The assembled concrete beam-column node comprises dowel bars, which pass through the beam-column node area and extend into the upper precast concrete pipe piles and the lower concrete components for anchoring respectively.

4. The precast concrete pipe pile according to claim 3 is used as a prefabricated concrete beam-column node of the upper column, characterized in that: The dowel bars are a steel cage mainly composed of a number of connecting steel bars and stirrups, wherein the connecting steel bars pass through the beam-column node area and extend into the pile cores of the upper precast concrete pipe piles and the lower precast concrete pipe piles for anchoring respectively, and the connecting steel bars are distributed along the periphery of the pile cores, and the stirrups hold the connecting steel bars.

5. The precast concrete pipe pile according to claim 4 is used as a prefabricated concrete beam-column node of the upper column, characterized in that: The dowel bars are arranged along the entire length of the pile cores of the upper precast concrete pipe piles and the lower precast concrete pipe piles, or the dowel bars extend into the pile cores of the upper precast concrete pipe piles and the lower precast concrete pipe piles for a section.

6. The precast concrete pipe pile according to claim 5 is used as a prefabricated concrete beam-column node of the upper column, characterized in that: The concrete grade of the beam-column node area is the same as the concrete grade of the structural beam, and the cross-section of the beam-column node area is greater than or equal to the cross-section of the precast concrete pipe pile.

7. The precast concrete pipe pile as claimed in claim 6 is used as a prefabricated concrete beam-column node of the upper column, characterized in that: The steel bars arranged in the beam-column node area are vertically arranged in a straight line or bent at their lower ends; the cross-sectional shape of the beam-column node area is rectangular, diamond or circular; the structural beam is a precast beam, a cast-in-place beam or a composite beam; the precast concrete pipe piles are PHC / PC / PRCI / PRCII hollow pipe piles with or without prestressed steel bars.

8. A construction method for a prefabricated concrete beam-column node using the precast concrete pipe piles as claimed in claim 1 as upper columns, characterized in that The specific steps include: S1. Install the casting molds for the lower concrete components and beams and slabs; S2. Install the annular steel plate on the top of the structural beam located at the beam-column node area; S3. Weld steel bars on the lower surface of the annular steel plate, and extend the lower end of the steel bars into the beam-column node area for anchoring; S4, installing the upper precast concrete pipe piles, and welding the lower surface of the steel ring of the upper precast concrete pipe piles to the upper surface of the annular steel plate; S5. Grouting is performed from the upper end of the upper precast concrete pipe pile into the pile core hole, that is, the pile core, beam-column node area and lower concrete components of the upper precast concrete pipe pile are poured at one time.