A device and control method for displacement control of bare-laid submarine pipeline
Through the combination of concrete prefabricated blocks, anchor cables and fixing mechanisms, and the use of spiral pile and conduit technology, the problem of suspension and buckling of submarine pipelines is solved, the stable fixation of submarine pipelines is achieved, the cost and construction period are reduced, and the safety and load-bearing capacity are improved. the rationality of the mechanism.
Patent Information
- Application Number
- CN202011518851.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-12-21
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2040-12-21
AI Technical Summary
Submarine pipelines are prone to hanging, buckling and other phenomena in complex marine environments, leading to pipeline fatigue damage and oil and gas leakage. Existing technologies have problems such as high cost, long construction period, material waste and unreasonable load-bearing mechanism when ensuring the stability of submarine pipelines.
A combination device of concrete prefabricated blocks, anchor cables and fixing mechanisms is used to provide pull-out bearing capacity through spiral piles. The anchor cables control the maximum displacement of the submarine pipeline, and the conduit is injected with concrete to reinforce the soil foundation around the spiral piles to achieve stable fixation of the submarine pipeline.
It improves the safety and reliability of submarine pipelines, saves materials and construction period, realizes the scientific rationality of the load-bearing mechanism, provides better erosion prevention effects, and reduces construction costs.
Smart Images

Figure CN112502189B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to a displacement control device and a control method, and in particular to a displacement control device and a control method for a bare-laid submarine pipeline. Background Art
[0002] At present, submarine pipelines are the lifeline of offshore oil and gas gathering and production systems and are important facilities for the development of offshore oil and gas fields. However, due to the complex environment in the ocean, submarine pipelines often become suspended and buckled, which may cause lateral instability and vortex-induced vibration of the pipelines, leading to fatigue damage or even fracture of the pipelines. Not only will it cause a large amount of property losses, but more seriously, the leakage of oil and gas will cause immeasurable pollution to the marine environment.
[0003] In order to keep the pipeline on the seabed safe and stable, engineering measures such as pipe weighted concrete covering, pressure blocks or sandbags, anchor reinforcement, pile foundation and construction of concrete sinking bed are often adopted. Setting weights and sandbags on the pipeline can effectively solve the problem of suspended submarine pipelines, but its construction cost is high; in addition, the weights and sandbags exert a constant gravity on the pipeline, which will cause fatigue damage to the submarine pipeline; furthermore, the sinking trajectory of the weights and sandbags in the seawater is not easy to control, resulting in uncontrollable construction effect. Anchor reinforcement technology has the advantages of low cost and simple construction; but its bearing capacity is small and its service life is short. Pile foundation has high bearing capacity and can effectively eliminate the lateral and longitudinal movement of the pipeline, but its engineering cost is high, the construction is complex, and the overall design tends to be conservative, which causes material waste to a certain extent. In addition, as a rigid component, the anchor and pile foundation are subjected to extremely uncoordinated forces on each part of the component when bearing, the anchor end is subjected to greater force while the rest of the parts are subjected to less force, and the bearing capacity cannot be fully utilized. The concrete caisson is composed of a large number of concrete columns connected by polypropylene materials. It has a high bearing capacity and can effectively reinforce the submarine pipeline. It also has a good effect in preventing erosion. However, it still has the disadvantages of long construction period, complex process and high cost. Therefore, how to ensure the stability of the submarine pipeline while taking into account the requirements of project cost, construction period and reasonable structural bearing mechanism is an urgent problem to be solved in marine engineering. Summary of the invention
[0004] The purpose of the present invention is to provide a device and a control method for the displacement control of a bare submarine pipeline in order to effectively control the displacement of the submarine pipeline and solve the possible problems of suspension and buckling while taking into account the requirements of project cost, construction period, and reasonable structural bearing mechanism, thereby ensuring the safety and stability of the submarine pipeline.
[0005] The device for controlling the displacement of a bare submarine pipeline provided by the present invention comprises a concrete prefabricated block, an anchor cable and a fixing mechanism, wherein a concrete prefabricated block cover is arranged at the top of the submarine pipeline, the curvature of the concrete prefabricated block corresponds to the curvature of the submarine pipeline, a groove is opened on the upper surface of the concrete prefabricated block, the anchor cable is clamped in the groove, the lower end of the anchor cable is connected to the fixing mechanism, and the fixing mechanism is symmetrically arranged in the seabed on both sides of the submarine pipeline.
[0006] Steel plates are provided inside the precast concrete blocks to increase the shear strength of the precast concrete blocks so as to better transfer the load.
[0007] The fixing mechanism includes an anchor, a connector, a spiral pile and a conduit, wherein the anchor cable is connected to the spiral pile through the connector, the anchor is arranged in the inner cavity of the connector, the lower end of the anchor cable is fixed in the anchor, the upper end of the spiral pile is screwed to the bottom of the connector, the conduit and the anchor cable are arranged in parallel, the lower end of the conduit is located at the bottom of the connector and the upper part of the spiral pile, and the cement concrete transported in the conduit can be transported to the bottom of the connector and expanded to the soil foundation on both sides.
[0008] A buckle is provided between the catheter and the anchor cable for fastening.
[0009] The control method for displacement control of a bare-laid submarine pipeline provided by the present invention comprises the following steps:
[0010] Step 1: Before laying the submarine pipeline, the prefabricated concrete blocks are placed on the submarine pipeline and fixed with steel wire ropes to form a whole with the prefabricated concrete blocks;
[0011] Step 2: During the laying of the submarine pipeline, under the overall gravity of the submarine pipeline and the prefabricated concrete blocks, the lower part of the prefabricated concrete blocks and the submarine pipeline will sink into the seabed;
[0012] Step 3: After the submarine pipeline is laid, place the anchor cable with spiral piles at both ends in the groove of the precast concrete block, and then screw the spiral piles on both sides to the designed depth. At this time, do not tighten the anchor cable in the groove of the precast concrete block. Reserve the allowed degree of freedom of movement for the anchor cable, so that the anchor cable retains a certain length on the seabed, so that the submarine pipeline can move within the allowed range;
[0013] Step 4: inject the designed amount of concrete at the bottom of the connector through the conduit to reinforce the seabed around the spiral pile and increase the reliability of the spiral pile. Then tighten the anchor cable. After the construction is completed, recycle the wire rope described in step 1.
[0014] The working principle of the present invention is as follows:
[0015] The submarine pipeline displacement control device provided by the present invention is composed of a spiral pile, a guide tube, a connector, an anchor, an anchor cable and a concrete prefabricated block. The spiral pile is used as an anchor body to provide pull-out bearing capacity; the anchor cable is used to control the maximum displacement of the submarine pipeline. When the submarine pipeline is displaced by natural environmental loads such as waves, currents, and earthquakes, the anchor cable will gradually be tightened as the displacement increases in any direction. When the displacement reaches the limit safety distance, the anchor cable will tightly clamp the concrete prefabricated block. The natural environmental load will act on the anchor cable in the form of concentrated force, which will be transmitted to the spiral pile through the anchor cable and balanced with the pull-out bearing capacity of the spiral pile, thereby diffusing the load into the deep soil to achieve the purpose of controlling the displacement of the submarine pipeline and avoiding affecting its safety and stability due to excessive displacement of the submarine pipeline.
[0016] Beneficial effects of the present invention:
[0017] 1. High reliability: The invention provides pull-out bearing capacity by squeezing the soil above the screw pile, and has strong bearing capacity; the maximum displacement of the submarine pipeline is controlled by the length of the anchor cable, so that the submarine pipeline moves within a safe range, eliminating stress accumulation and ensuring its safety and reliability;
[0018] 2. Save materials: Existing methods of fixing submarine pipelines include engineering measures such as weighted concrete covering, pressure blocks or sandbags, anchor reinforcement, pile foundations, and construction of concrete sinking beds. In order to ensure or improve the safety and stability of the pipeline, it is generally achieved by increasing the number of heavy concrete and pressure blocks, the anchoring length of the anchor, the pile length or pile diameter, the thickness of the concrete sinking bed, etc., which is costly. However, the present invention only needs to screw the same size of piles into a deeper soil layer to obtain a greater pull-out bearing capacity, saving materials and reducing costs. In particular, since the shallow soil of the seabed is soft soil, the advantages of the present invention are more significant. In addition, the device described in the present invention can ensure the stability of submarine pipelines of considerable length through prefabricated concrete blocks, improve the anchoring efficiency, further save materials, and reduce costs.
[0019] 3. Reasonable bearing mechanism: Compared with the situation that the forces on each cross section of the component are greatly different and uncoordinated when the rigid components such as anchor rods and pile foundations are bearing, the device described in the present invention transmits the load through the flexible component-anchor cable, and the spiral piles provide the pull-out bearing capacity, which ensures the bearing capacity and increases the service life of the component to a certain extent. In addition, compared with the engineering measures such as adding concrete covering, pressure blocks or sandbags to the pipeline to apply a constant load to the pipeline, the device described in the present invention will only apply a restraining force to the pipeline when the displacement of the pipeline is too large, that is, it needs to be restricted, effectively reducing the fatigue of the pipeline, and the bearing mechanism is scientific and reasonable.
[0020] 4. Save construction time: Compared with existing anchor reinforcement, pile foundation, concrete sinking bed and other technologies that need grouting and curing to provide bearing capacity, the present invention uses spiral piles as anchor bodies, which can provide bearing capacity after being screwed in. Concrete is then injected into the lower part of the connecting head to ensure the reliability of the spiral piles. The next step of construction can be carried out without waiting for the final setting of the concrete, which can effectively save construction time.
[0021] 5. Prevention of erosion: The prefabricated concrete block cover of the present invention is arranged on the submarine pipeline, which has a good effect of preventing erosion. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 This is a front view of the overall structure of the displacement control device of the present invention.
[0023] Figure 2 It is a side view of the overall structure of the displacement control device of the present invention.
[0024] Figure 3 It is a top view of the concrete prefabricated block of the present invention.
[0025] The annotations in the image above are as follows:
[0026] 1. Prefabricated concrete block 2. Anchor cable 3. Submarine pipeline 4. Groove 5. Steel plate 6. Anchor
[0027] 7. Connector 8. Screw pile 9. Conduit 10. Cement concrete 11. Clip. DETAILED DESCRIPTION
[0028] See also Figures 1 to 3 As shown:
[0029] The device for controlling the displacement of a bare submarine pipeline provided by the present invention comprises a concrete prefabricated block 1, an anchor cable 2 and a fixing mechanism, wherein the concrete prefabricated block 1 is covered on the top of a submarine pipeline 3, the curvature of the concrete prefabricated block 1 corresponds to the curvature of the submarine pipeline 3, a groove 4 is provided on the upper surface of the concrete prefabricated block 1, the anchor cable 2 is clamped in the groove 4, the lower end of the anchor cable 2 is connected to the fixing mechanism, and the fixing mechanism is symmetrically arranged in the seabed on both sides of the submarine pipeline 3.
[0030] A steel plate 5 is provided inside the precast concrete block 1 to increase the shear strength of the precast concrete block 1 so as to better transfer the load.
[0031] The fixing mechanism includes an anchor 6, a connector 7, a screw pile 8 and a conduit 9, wherein the anchor cable 2 is connected to the screw pile 8 through the connector 7, the anchor 6 is arranged in the inner cavity of the connector 7, the lower end of the anchor cable 2 is fixedly connected to the anchor 6, the upper end of the screw pile 8 is screwed to the bottom of the connector 7, the conduit 9 is arranged in parallel with the anchor cable 2, the lower end of the conduit 9 is located at the bottom of the connector 7 and the upper part of the screw pile 8, and the cement concrete 10 transported in the conduit 9 can be transported to the bottom of the connector 7 and expand to the soil foundation on both sides.
[0032] A buckle 11 is provided between the conduit 9 and the anchor cable 2 for fastening.
[0033] The control method for displacement control of a bare-laid submarine pipeline provided by the present invention comprises the following steps:
[0034] Step 1: Before laying the submarine pipeline 3, the prefabricated concrete block 1 is placed on the submarine pipeline 3 and fixed with a steel wire rope so that the prefabricated concrete block 1 and the submarine pipeline 3 form a whole;
[0035] Step 2: During the laying of the submarine pipeline 3, under the overall gravity of the submarine pipeline 3 and the prefabricated concrete block 1, the lower part of the prefabricated concrete block 1 and the submarine pipeline 3 will sink into the seabed;
[0036] Step 3: After the submarine pipeline 3 is laid, the anchor cable 2 with screw piles 8 at both ends is placed in the groove 4 of the precast concrete block 1, and then the screw piles 8 on both sides are screwed into the designed depth. At this time, the anchor cable 2 should not be tightly clamped in the groove 4 of the precast concrete block 1. The anchor cable 2 should be allowed to have a certain degree of freedom of movement, so that the anchor cable 2 retains a certain length on the seabed, so that the submarine pipeline 3 can move within the allowed range;
[0037] Step 4: inject the designed and measured cement concrete 10 at the bottom of the connector 7 through the conduit 9 to reinforce the seabed around the screw pile 8 and increase the reliability of the screw pile 8, then tighten the anchor cable 2. After the construction is completed, recycle the wire rope described in step 1.
[0038] The working principle of the present invention is as follows:
[0039] The submarine pipeline displacement control device provided by the present invention is composed of a screw pile 8, a guide tube 9, a connector 7, an anchor 6, an anchor cable 2 and a concrete prefabricated block 1. The screw pile 8 is used as an anchor body to provide pull-out bearing capacity; the anchor cable 2 controls the maximum displacement of the submarine pipeline 3. When the submarine pipeline 3 is displaced by natural environmental loads such as waves, currents, and earthquakes, the anchor cable 2 will be gradually tightened as the displacement increases in any direction. When the displacement reaches the limit safety distance, the anchor cable 2 will tightly clamp the concrete prefabricated block 1, and the natural environmental load will act on the anchor cable 2 in the form of concentrated force, which will be transmitted to the screw pile 8 through the anchor cable 2 and balanced with the pull-out bearing capacity of the screw pile 8, thereby diffusing the load into the deep soil, so as to achieve the purpose of controlling the displacement of the submarine pipeline 3 and avoid affecting its safety and stability due to excessive displacement of the submarine pipeline 3.
Claims
1. A control method for displacement control of a bare submarine pipeline, comprising a concrete prefabricated block, an anchor cable and a fixing mechanism, wherein a concrete prefabricated block cover is arranged at the top of the submarine pipeline, the curvature of the concrete prefabricated block corresponds to the curvature of the submarine pipeline, a groove is provided on the upper surface of the concrete prefabricated block, the anchor cable is clamped in the groove, the lower end of the anchor cable is connected to the fixing mechanism, and the fixing mechanism is symmetrically arranged in the seabed on both sides of the submarine pipeline, characterized in that: The fixing mechanism includes an anchor, a connector, a spiral pile and a guide tube, wherein the anchor cable is connected to the spiral pile through the connector, the anchor cable is arranged in the inner cavity of the connector, the lower end of the anchor cable is fixed in the anchor cable, the upper end of the spiral pile is screwed to the bottom of the connector, the guide tube and the anchor cable are arranged in parallel, the lower end of the guide tube is located at the bottom of the connector and the upper part of the spiral pile, and the cement concrete transported in the guide tube can be transported to the bottom of the connector and expand to the soil foundation on both sides; The steps of the control method for displacement control of bare-laid submarine pipeline are as follows: Step 1: Before laying the submarine pipeline, the prefabricated concrete blocks are placed on the submarine pipeline and fixed with steel wire ropes to form a whole with the prefabricated concrete blocks; Step 2: During the laying of the submarine pipeline, under the overall gravity of the submarine pipeline and the prefabricated concrete blocks, the lower part of the prefabricated concrete blocks and the submarine pipeline will sink into the seabed; Step 3: After the submarine pipeline is laid, place the anchor cable with spiral piles at both ends in the groove of the precast concrete block, and then screw the spiral piles on both sides to the designed depth. At this time, do not tighten the anchor cable in the groove of the precast concrete block. Reserve the allowed degree of freedom of movement for the anchor cable, so that the anchor cable retains a certain length on the seabed, so that the submarine pipeline can move within the allowed range; Step 4: inject the designed amount of concrete at the bottom of the connector through the conduit to reinforce the seabed around the spiral pile and increase the reliability of the spiral pile. Then tighten the anchor cable. After the construction is completed, recycle the wire rope described in step 1.
2. A control method for displacement control of a bare-laid submarine pipeline according to claim 1, characterized in that: A steel plate is arranged inside the concrete prefabricated block to increase the shear strength of the concrete prefabricated block.
3. A control method for displacement control of a bare-laid submarine pipeline according to claim 1, characterized in that: A buckle is arranged between the conduit and the anchor cable for fastening.
Citation Information
Patent Citations
An underwater tunnel and an underwater mooring apparatus to moor the underwater tunnel
CN1077765A
Adjustable anchor cable device for anchoring suspended tunnel pipe body
CN109653248A
Device for controlling displacement of bare-laid submarine pipeline
CN213897217U
Method for manufacturing a flexible mat-like component for protecting, ballasting and supporting submarine pipelines and cables, and component obtained with the method
EP0881334A1
Method for constructing a foundation pile for offshore constructions and foundation pile for offshore structures
EP2796620A2