A combined hoisting wall and installation method
Through a combined lifting wall system, the prefabricated plate is securely fixed by using positioning bolts, springs and fixing sleeves, and the storage and maintenance of channel steel is achieved through telescopic rods and cleaning brushes, which solves the problems of low efficiency and unstableness of traditional lifting walls, and improves the construction efficiency and service life of channel steel.
Patent Information
- Application Number
- CN202011501009.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-12-17
- Publication Date
- 2025-06-03
- Estimated Expiration
- 2040-12-17
AI Technical Summary
Traditional lifting walls do not have combination functions, resulting in low construction efficiency, inconvenient matching of steel beams and channel steel, and unstable lifting methods, which can easily lead to slide and damage to the prefabricated boards.
A combined lifting wall system is adopted, including steel beams, channel steel, prefabricated plates and traction cables. The prefabricated plates are securely fixed by positioning bolts, springs and fixing sleeves, and the storage and maintenance of channel steel is achieved through telescopic rods and cleaning brushes.
It improves construction efficiency, achieves stable fixation of prefabricated plates, extends the service life of channel steel, and simplifies the supporting use of steel beams and channel steel.
Smart Images

Figure CN112554371B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of hoisting walls, and particularly relates to a combined hoisting wall and an installation method. Background Art
[0002] The hoisting wall is composed of two words, hoisting and wall. Hoisting generally refers to the installation and positioning of equipment by a crane or a hoisting mechanism. During the overhaul or repair process, various hoisting tools are used to change the position of equipment, workpieces, etc. The wall is mainly a barrier for construction. A precast slab is a type of wall. The hoisting wall refers to the steps of installing the wall during the installation process.
[0003] Traditional hoisting walls do not have a combined function. When constructing precast wall panels and hoisting the boards, they are hoisted one by one, which wastes time, reduces work efficiency, and is not conducive to large-scale operations. Traditional steel beams and channel steels do not have a supporting function and are usually used separately. When not in use, it is easy to cause the loss of steel beams and channel steels. And during the matching process, there is no function of cleaning and oiling the channel steels for maintenance. If the channel steels are not maintained in time after long-term use, the service life of the channel steels will be reduced. When traditional hoisting walls hoist precast slabs, they usually fix the precast slabs with screws or bolts. Such a hoisting method is not stable, easily causes the precast slabs to slip during hoisting, has a certain danger, and is easy to damage the precast slabs. Summary of the Invention
[0004] The purpose of the invention is to solve the problems that traditional hoisting walls do not have a combined function, when constructing precast wall panels and hoisting the boards, they are hoisted one by one, which wastes time, reduces work efficiency, and is not conducive to large-scale operations. Traditional steel beams and channel steels do not have a supporting function and are usually used separately. When not in use, it is easy to cause the loss of steel beams and channel steels. And during the matching process, there is no function of cleaning and oiling the channel steels for maintenance. If the channel steels are not maintained in time after long-term use, the service life of the channel steels will be reduced. When traditional hoisting walls hoist precast slabs, they usually fix the precast slabs with screws or bolts. Such a hoisting method is not stable, easily causes the precast slabs to slip during hoisting, has a certain danger, and is easy to damage the precast slabs, and to provide a combined hoisting wall and an installation method.
[0005] In order to achieve the above purpose, the invention adopts the following technical solutions:
[0006] A combined hoisting wall body, comprising a first precast slab, a second precast slab, a second precast slab and a steel beam. Fixed rings are fixedly installed on both the upper and lower surfaces of the steel beam. A traction steel cable is fixedly installed on the outer surface of the fixed ring. One end of the traction steel cable is fixedly installed with a tightening ring. One end of the traction steel cable fixedly installed through the fixed ring on the lower surface of the steel beam is fixedly installed with a cross block. A ring sleeve is fixedly installed on the outer surface of the traction steel cable. The cross block is inserted and installed inside the first precast slab and the second precast slab. The first precast slab and the second precast slab are fixedly connected by a channel steel. A threaded nut is fixedly installed on the inner wall of the channel steel. A positioning bolt is threadedly installed inside the threaded nut. An inner shell is sleeved on the outer surface of the positioning bolt. The inner part of the inner shell is filled with a first cleaning cotton. One end of the positioning bolt is clamped inside the first precast slab and the second precast slab.
[0007] As a further description of the above technical solution:
[0008] A first mounting shell is fixedly installed on the upper surface of the channel steel. An L-shaped rod is slidably installed on the inner wall of the first mounting shell. A second spring is arranged inside the first mounting shell.
[0009] As a further description of the above technical solution:
[0010] One end of the second spring is fixedly connected to the inner wall of the first mounting shell. The other end of the second spring is fixedly connected to the lower surface of the L-shaped rod. A fixed sleeve is fixedly installed at one end of the second spring.
[0011] As a further description of the above technical solution:
[0012] A partition is fixedly installed on the inner wall of the cross block. A side block is slidably installed on the inner wall of the cross block. A third spring is arranged inside the cross block. One end of the third spring is fixedly connected to the inner wall of the cross block. The other end of the third spring is fixedly connected to the side wall of the side block. One end of the side block is clamped inside a positioning cavity opened inside the second precast slab. A moving rod is fixedly installed on the upper surface of the side block. One end of the moving rod passes through and extends to the outside of the cross block.
[0013] As a further description of the above technical solution:
[0014] A top plate is fixedly installed on the upper surface of the second precast slab. A second mounting shell is fixedly installed on the side wall of the top plate. A plug pin is inserted inside the second mounting shell. One end of the plug pin is embedded inside a positioning hole opened inside the ring sleeve.
[0015] As a further description of the above technical solution:
[0016] The outer surface of the bolt is sleeved with a fourth spring. One end of the fourth spring is fixedly connected to the outer surface of the bolt, and the other end of the fourth spring is fixedly connected to the inner wall of the second mounting shell. Two second mounting shells are symmetrically mounted about the longitudinal center axis of the collar.
[0017] As a further description of the above technical solution:
[0018] A cover plate is rotatably mounted on the upper surface of the steel beam through a rotating shaft. The inner wall of the steel beam is in contact with the outer surface of the channel steel. A moving shaft is inserted and installed inside the cover plate. One end of the moving shaft passes through and extends into the cover plate and is fixedly installed with a cleaning brush. A convex block is fixedly installed on the lower surface of the cover plate. A connecting plate is fixedly installed on the upper surface of the steel beam. A telescopic rod is fixedly installed on the side wall of the connecting plate. A first spring is sleeved on the outer surface of the telescopic rod. Both ends of the first spring are fixedly connected to the outer surface of the telescopic rod. One end of the telescopic rod is fixedly installed with a top block, and the top block is inserted into a positioning hole opened inside the convex block.
[0019] As a further description of the above technical solution:
[0020] A second cleaning cotton is arranged on the inner wall of the steel beam. The upper surface of the second cleaning cotton is in contact with and presses against the lower surface of the channel steel. A side shell is fixedly installed on the side wall of the steel beam.
[0021] As a further description of the above technical solution:
[0022] A piston plate is slidably installed on the inner wall of the side shell. An extension shaft is inserted and installed inside the side shell. One end of the extension shaft is fixedly connected to the side wall of the piston plate. A fifth spring is sleeved on the outer surface of the extension shaft. One end of the fifth spring is fixedly connected to the outer surface of the extension shaft, and the other end of the fifth spring is fixedly connected to the outer surface of the side shell.
[0023] The present invention also discloses a method for installing a combined hoisting wall, which specifically includes the following steps:
[0024] S1. Connection of precast slabs. Place the channel steel between the first precast slab and the second precast slab. Rotate the positioning bolt. The positioning bolt rotates and descends inside the threaded nut and rotates into the second precast slab, thereby realizing the fixation of the second precast slab. When it is necessary to disassemble the second precast slab, when the positioning bolt is turned out of the threaded nut, due to the elastic force of the second spring, the positioning bolt pops out, eliminating the need for manual removal. Moreover, the fixing sleeve has a certain limiting and fixing effect on the positioning bolt to prevent the positioning bolt from falling when not in use.
[0025] S2. Hoisting of the precast slab. Due to the elastic force of the third spring, the side block moves and is inserted into the positioning cavity. Then, pull the bolt pin. The movement of the bolt pin drives the contraction of the fourth spring and drives the bolt pin to be inserted into the inner part of the collar, thus further fixing the second precast slab;
[0026] S3. Matching and storage of the channel steel and the steel beam. When the wall panel does not need to be hoisted, place the channel steel inside the steel beam and rotate the cover plate. Due to the elastic forces of the telescopic rod and the first spring, the top block at one end of the telescopic rod is embedded inside the convex block to achieve the storage of the channel steel. Then, move the extension shaft. The movement of the moving shaft drives the cleaning brush to slide on the outer surface of the channel steel, thus cleaning the outer surface of the channel steel. After cleaning, press the moving shaft to move, driving the piston plate to move, and squeezing the antirust oil into the cleaning brush, thus performing antirust treatment on the channel steel.
[0027] In summary, due to the adoption of the above technical solutions, the beneficial effects of the present invention are:
[0028] 1. In the present invention, by installing a steel beam, a channel steel, a first precast slab, a second precast slab and a towing cable, rotate the positioning bolt. The positioning bolt rotates and descends inside the threaded nut and rotates into the second precast slab, thus fixing the second precast slab. When the second precast slab needs to be disassembled, when the positioning bolt is turned out from the threaded nut, due to the elastic force of the second spring, the positioning bolt pops out without the need for manual removal. And the fixing sleeve has a certain limit fixation on the positioning bolt to prevent the positioning bolt from falling when not in use, solving the problem that the traditional hoisting wall does not have a combined function. When constructing and hoisting the precast wall panel, it is hoisted one by one, wasting time, reducing work efficiency and being not conducive to large-area operation. It is more practical and has a higher work efficiency.
[0029] 2. In the present invention, by installing a third spring, a side block and a positioning cavity, when the first precast slab and the second precast slab need to be hoisted, due to the elastic force of the third spring, the side block moves and is inserted into the positioning cavity. Then, pull the bolt pin. The movement of the bolt pin drives the contraction of the fourth spring and drives the bolt pin to be inserted into the inner part of the collar, thus further fixing the second precast slab. This solves the problem that when the traditional hoisting wall hoists the precast slab, it usually fixes the precast slab by screws or bolts. Such a hoisting method is not stable, easily causes the precast slab to slide during hoisting, has a certain danger, and is easy to damage the precast slab. It is convenient for assembly and disassembly and is more convenient during hoisting;
[0030] 3. In the present invention, with the side shell, the fifth spring and the cleaning brush installed, when the wall panel does not need to be hoisted, the channel steel is placed inside the steel beam, and the cover plate is rotated. Due to the elastic force of the telescopic rod and the first spring, the top block at one end of the telescopic rod is embedded inside the convex block to achieve the storage of the channel steel. Then, the moving shaft is moved. The movement of the moving shaft drives the cleaning brush to slide on the outer surface of the channel steel, thereby realizing the cleaning of the outer surface of the channel steel. After the cleaning is completed, the moving shaft is pressed to move, driving the piston plate to move, and squeezing the antirust oil into the cleaning brush, thereby realizing the antirust treatment of the channel steel. This solves the problem that the traditional steel beam and channel steel do not have the function of supporting use, and they are usually used separately. When not in use, it is easy to cause the loss of the steel beam and channel steel, and there is no function of cleaning and oiling maintenance for the channel steel during the matching process. If the channel steel is not maintained in time after long-term use, the service life of the channel steel is extended. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 FIG. 6 is a schematic diagram of a partial internal structure of the front view of a combined hoisting wall proposed by the present invention;
[0032] Figure 2 FIG. 10 is an enlarged schematic diagram of the rear view of the combination of the channel steel and the steel beam in a combined hoisting wall proposed by the present invention;
[0033] Figure 3 FIG. 14 is an enlarged schematic diagram of the side view of the channel steel in a combined hoisting wall proposed by the present invention;
[0034] Figure 4 FIG. 18 is an enlarged schematic diagram of part A in a combined hoisting wall proposed by the present invention;
[0035] Figure 5 FIG. 22 is a perspective view of the steel beam in a combined hoisting wall proposed by the present invention;
[0036] Figure 6 FIG. 26 is a perspective view of the connecting plate and the telescopic rod in a combined hoisting wall proposed by the present invention.
[0037] Legend: 1. Tightening ring; 2. Towing cable; 3. Extension shaft; 4. Side shell; 5. First precast slab; 6. Channel steel; 7. Positioning bolt; 8. Second precast slab; 9. Top block; 10. First spring; 11. Steel beam; 12. Fixed ring; 13. Moving shaft; 14. Second spring; 15. First mounting shell; 16. L-shaped rod; 17. Fixed sleeve; 18. Inner shell; 19. Threaded nut; 20. First cleaning cotton; 21. Side block; 22. Positioning cavity; 23. Third spring; 24. Partition board; 25. Cross block; 26. Ring sleeve; 27. Plug; 28. Fourth spring; 29. Second mounting shell; 30. Top plate; 31. Moving rod; 32. Telescopic rod; 33. Cover plate; 34. Fifth spring; 35. Connecting plate; 36. Protrusion; 37. Second cleaning cotton; 38. Cleaning brush; 39. Piston plate. Detailed implementation
[0038] The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. All other embodiments obtained by those of ordinary skill in the art based on the embodiments of the present invention without creative efforts shall fall within the protection scope of the present invention.
[0039] Please refer to Figure 1-6, the present invention provides a technical solution: a combined hoisting wall, including a first precast slab 5, a second precast slab 8, the second precast slab 8 and a steel beam 11. Fixed rings 12 are fixedly installed on both the upper and lower surfaces of the steel beam 11. A cover plate 33 is rotatably installed on the upper surface of the steel beam 11 through a rotating shaft. The inner wall of the steel beam 11 is in contact with the outer surface of a channel steel 6. A moving shaft 13 is inserted and installed inside the cover plate 33. One end of the moving shaft 13 passes through and extends into the cover plate 33 and is fixedly installed with a cleaning brush 38. A convex block 36 is fixedly installed on the lower surface of the cover plate 33. A connecting plate 35 is fixedly installed on the upper surface of the steel beam 11. A telescopic rod 32 is fixedly installed on the side wall of the connecting plate 35. A first spring 10 is sleeved on the outer surface of the telescopic rod 32. Both ends of the first spring 10 are fixedly connected to the outer surface of the telescopic rod 32. One end of the telescopic rod 32 is fixedly installed with a top block 9. The top block 9 is inserted and installed in a positioning hole formed inside the convex block 36. By installing the cover plate 33, the moving shaft 13, the convex block 36 and the telescopic rod 32, when the wall panel does not need to be hoisted, the channel steel 6 is placed inside the steel beam 11, and the cover plate 33 is rotated. Due to the elastic force of the telescopic rod 32 and the first spring 10, the top block 9 at one end of the telescopic rod 32 is embedded inside the convex block 36, realizing the storage of the channel steel 6. A second cleaning cotton 37 is arranged on the inner wall of the steel beam 11. The upper surface of the second cleaning cotton 37 contacts and presses against the lower surface of the channel steel 6. A side shell 4 is fixedly installed on the side wall of the steel beam 11. By installing the second cleaning cotton 37 and the side shell 4, when the wall panel does not need to be hoisted, the moving shaft 13 is further moved. The movement of the moving shaft 13 drives the cleaning brush 38 to slide on the outer surface of the channel steel 6, thereby realizing the cleaning of the outer surface of the channel steel 6. A piston plate 39 is slidably installed on the inner wall of the side shell 4. An extension shaft 3 is inserted and installed inside the side shell 4. One end of the extension shaft 3 is fixedly connected to the side wall of the piston plate 39. A fifth spring 34 is sleeved on the outer surface of the extension shaft 3. One end of the fifth spring 34 is fixedly connected to the outer surface of the extension shaft 3. The other end of the fifth spring 34 is fixedly connected to the outer surface of the side shell 4. After the cleaning is completed, the moving shaft 13 is further pressed to move, driving the piston plate 39 to move, and squeezing the antirust oil into the cleaning brush, realizing the maintenance of the channel steel 6;
[0040] A traction cable 2 is fixedly installed on the outer surface of the fixed ring 12. One end of the traction cable 2 is fixedly installed with a tightening ring 1. One end of the traction cable 2 fixedly installed on the lower surface of the steel beam 11 through the fixed ring 12 is fixedly installed with a cross block 25. A partition 24 is fixedly installed on the inner wall of the cross block 25. A side block 21 is slidably installed on the inner wall of the cross block 25. A third spring 23 is arranged inside the cross block 25. One end of the third spring 23 is fixedly connected to the inner wall of the cross block 25, and the other end of the third spring 23 is fixedly connected to the side wall of the side block 21. One end of the side block 21 is embedded in the positioning cavity 22 opened inside the second precast slab 8. A moving rod 31 is fixedly installed on the upper surface of the side block 21. One end of the moving rod 31 passes through and extends outside the cross block 25. By installing the partition 24, the side block 21 and the third spring 23, when it is necessary to hoist the first precast slab 5 and the second precast slab 8, due to the elastic force of the third spring 23, the side block 21 is driven to move and inserted into the positioning cavity 22. Then, the bolt 27 is pulled. The movement of the bolt 27 drives the fourth spring 28 to contract, and drives the bolt 27 to be inserted into the inner part of the collar 26, thereby further realizing the fixation of the second precast slab 8. A top plate 30 is fixedly installed on the upper surface of the second precast slab 8. A second mounting shell 29 is fixedly installed on the side wall of the top plate 30. The bolt 27 is inserted into the second mounting shell 29. One end of the bolt 27 is embedded in the positioning hole opened inside the collar 26. By installing the top plate 30, the second mounting shell 29 and the bolt 27, the bolt 27 inside the second mounting shell 29 is embedded in the inner part of the collar 26, further fixing the second precast slab 8;
[0041] A fourth spring 28 is sleeved on the outer surface of the bolt 27. One end of the fourth spring 28 is fixedly connected to the outer surface of the bolt 27, and the other end of the fourth spring 28 is fixedly connected to the inner wall of the second mounting shell 29. Two second mounting shells 29 are symmetrically installed about the longitudinal center axis of the collar 26. By installing the fourth spring 28, the elastic force of the fourth spring 28 drives the bolt 27 to be inserted into the inner part of the collar 26 to realize the positioning function;
[0042] The outer surface of the traction steel cable 2 is fixedly mounted with a ring sleeve 26, the cross block 25 is inserted and mounted inside the first prefabricated plate 5 and the second prefabricated plate 8, the first prefabricated plate 5 and the second prefabricated plate 8 are fixedly connected by a channel steel 6, the inner wall of the channel steel 6 is fixedly mounted with a threaded cap 19, the upper surface of the channel steel 6 is fixedly mounted with a first mounting shell 15, the inner wall of the first mounting shell 15 is slidably mounted with an L-shaped rod 16, the interior of the first mounting shell 15 is provided with a second spring 14, by installing the first mounting shell 15, the L-shaped rod 16 and the second spring 14, when the positioning bolt 7 is turned out from the threaded cap 19, the elastic force of the second spring 14 drives the positioning bolt 7 to pop out, and the fixing sleeve 17 has a certain limit fixation on the positioning bolt 7 to prevent the positioning bolt 7 from falling when it is not needed;
[0043] One end of the second spring 14 is fixedly connected to the inner wall of the first mounting shell 15, and the other end of the second spring 14 is fixedly connected to the lower surface of the L-shaped rod 16. A fixing sleeve 17 is fixedly installed at one end of the second spring 14, and the L-shaped rod 16 is moved by installing the second spring 14, and the positioning bolt 7 is fixed by installing the fixing sleeve 17;
[0044] The internal thread of the threaded cap 19 is installed with a positioning bolt 7, the outer surface of the positioning bolt 7 is sleeved with an inner shell 18, the interior of the inner shell 18 is filled with a first cleaning cotton 20, and one end of the positioning bolt 7 is embedded in the first prefabricated plate 5 and the second prefabricated plate 8.
[0045] The present invention also discloses a combined hanging wall installation method, which specifically comprises the following steps:
[0046] S1, connection of prefabricated panels, placing the channel steel 6 on the first prefabricated panel 5 and the second prefabricated panel 8, rotating the positioning bolt 7, the positioning bolt 7 rotates and descends inside the threaded cap 19, and rotates to the inside of the second prefabricated panel 8, thereby fixing the second prefabricated panel 8. When the second prefabricated panel 8 needs to be removed, when the positioning bolt 7 is turned out from the threaded cap 19, the positioning bolt 7 is ejected due to the elastic force of the second spring 14, and no manual removal is required, and the fixing sleeve 17 has a certain limit fixation on the positioning bolt 7 to prevent the positioning bolt 7 from falling when it is not needed;
[0047] S2, the hoisting of the prefabricated panel, due to the elastic force of the third spring 23, the side block 21 is moved and inserted into the interior of the positioning cavity 22, and then the latch 27 is pulled, the movement of the latch drives the fourth spring 28 to contract, and drives the latch 27 to be inserted into the interior of the ring sleeve 26, thereby further fixing the second prefabricated panel 8;
[0048] S3. The cooperation and storage of the channel steel 6 and the steel beam 11. When the wall panel does not need to be hoisted, place the channel steel 6 inside the steel beam 11, and rotate the cover plate 33. Due to the elastic forces of the telescopic rod 32 and the first spring 10, the top block 9 at one end of the telescopic rod 32 is embedded inside the convex block 36 to achieve the storage of the channel steel 6. Then move the moving shaft 13. The movement of the moving shaft 13 drives the cleaning brush 38 to slide on the outer surface of the channel steel 6, so as to clean the outer surface of the channel steel 6. After cleaning, press the extension shaft 3 to move, driving the piston plate 39 to move, and squeezing the antirust oil into the cleaning brush, so as to perform antirust treatment on the channel steel 6.
[0049] Working principle: When in use, rotate the positioning bolt 7. The positioning bolt 7 rotates and descends inside the threaded nut 19 and rotates into the second precast slab 8, so as to fix the second precast slab 8. When the second precast slab 8 needs to be disassembled, when the positioning bolt 7 is removed from the threaded nut 19, due to the elastic force of the second spring 14, the positioning bolt 7 pops out, and the fixing sleeve 17 has a certain limit fixation on the positioning bolt 7 to prevent the positioning bolt 7 from falling when not in use. When the first precast slab 5 and the second precast slab 8 need to be hoisted, due to the elastic force of the third spring 23, the side block 21 moves and is inserted into the positioning cavity 22. Then pull the bolt 27. The movement of the bolt 27 drives the fourth spring 28 to contract and drives the bolt 27 to be inserted into the inside of the collar 26, so as to further fix the second precast slab 8. When the wall panel does not need to be hoisted, place the channel steel 6 inside the steel beam 11, and rotate the cover plate 33. Due to the elastic forces of the telescopic rod 32 and the first spring 10, the top block 9 at one end of the telescopic rod 32 is embedded inside the convex block 36 to achieve the storage of the channel steel 6. Then move the moving shaft 13. The movement of the moving shaft 13 drives the cleaning brush 38 to slide on the outer surface of the channel steel 6, so as to clean the outer surface of the channel steel 6. After cleaning, press the moving shaft 13 to move, driving the piston plate 39 to move, and squeezing the antirust oil into the cleaning brush.
[0050] The above is only a preferred specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any person skilled in the art within the technical scope disclosed by the present invention, according to the technical solution of the present invention and its inventive concept, makes equivalent substitutions or changes, and all should be covered within the protection scope of the present invention.
Claims
1. A combined hoisting wall body, comprising a first precast slab (5), a second precast slab (8) and a steel beam (11), characterized in that, fixed rings (12) are fixedly installed on both the upper and lower surfaces of the steel beam (11), a traction steel cable (2) is fixedly installed on the outer surface of the fixed ring (12), one end of the traction steel cable (2) is fixedly installed with a tightening ring (1), one end of the traction steel cable (2) fixedly installed through the fixed ring (12) on the lower surface of the steel beam (11) is fixedly installed with a cross block (25), a ring sleeve (26) is fixedly installed on the outer surface of the traction steel cable (2), the cross block (25) is inserted and installed inside the first precast slab (5) or the second precast slab (8), the first precast slab (5) and the second precast slab (8) are fixedly connected by a channel steel (6), a threaded nut (19) is fixedly installed on the inner wall of the channel steel (6), a positioning bolt (7) is threadedly installed inside the threaded nut (19), an inner shell (18) is sleeved on the outer surface of the positioning bolt (7), a first cleaning cotton (20) is filled inside the inner shell (18), and one end of the positioning bolt (7) is clamped inside the first precast slab (5) or the second precast slab (8); a first mounting shell (15) is fixedly installed on the upper surface of the channel steel (6), an L-shaped rod (16) is slidably installed on the inner wall of the first mounting shell (15), and a second spring (14) is arranged inside the first mounting shell (15); one end of the second spring (14) is fixedly connected to the inner wall of the first mounting shell (15), the other end of the second spring (14) is fixedly connected to the lower surface of the L-shaped rod (16), and a fixed sleeve (17) is fixedly installed at one end of the second spring (14); a cover plate (33) is rotatably installed on the upper surface of the steel beam (11) through a rotating shaft, the inner wall of the steel beam (11) is attached to the outer surface of the channel steel (6), a moving shaft (13) is inserted and installed inside the cover plate (33), one end of the moving shaft (13) passes through and extends into the cover plate (33) and is fixedly installed with a cleaning brush (38), a convex block (36) is fixedly installed on the lower surface of the cover plate (33), a connecting plate (35) is fixedly installed on the upper surface of the steel beam (11), a telescopic rod (32) is fixedly installed on the side wall of the connecting plate (35), a first spring (10) is sleeved on the outer surface of the telescopic rod (32), both ends of the first spring (10) are fixedly connected to the outer surface of the telescopic rod (32), and one end of the telescopic rod (32) is fixedly installed with a top block (9), and the top block (9) is inserted into a positioning hole opened inside the convex block (36).
2. A combined hoisting wall body according to claim 1, characterized in that, The inner wall of the transverse block (25) is fixedly installed with a partition plate (24). A side block (21) is slidably installed on the inner wall of the transverse block (25). A third spring (23) is arranged inside the transverse block (25). One end of the third spring (23) is fixedly connected to the inner wall of the transverse block (25), and the other end of the third spring (23) is fixedly connected to the side wall of the side block (21). One end of the side block (21) is embedded inside a positioning cavity (22) formed inside the second precast slab (8). A moving rod (31) is fixedly installed on the upper surface of the side block (21), and one end of the moving rod (31) passes through and extends outside the transverse block (25).
3. A combined hoisting wall according to claim 2, wherein, a top plate (30) is fixedly installed on the upper surface of the second precast slab (8). A second mounting shell (29) is fixedly installed on the side wall of the top plate (30). A bolt (27) is inserted inside the second mounting shell (29), and one end of the bolt (27) is embedded in a positioning hole formed inside a collar (26).
4. A combined hoisting wall according to claim 3, wherein, a fourth spring (28) is sleeved on the outer surface of the bolt (27). One end of the fourth spring (28) is fixedly connected to the outer surface of the bolt (27), and the other end of the fourth spring (28) is fixedly connected to the inner wall of the second mounting shell (29). Two second mounting shells (29) are symmetrically installed about the longitudinal center axis of the collar (26).
5. A combined hoisting wall according to claim 4, wherein, a second cleaning cotton (37) is arranged on the inner wall of the steel beam (11). The upper surface of the second cleaning cotton (37) contacts and presses against the lower surface of the channel steel (6). A side shell (4) is fixedly installed on the side wall of the steel beam (11).
6. A combined hoisting wall according to claim 5, wherein, a piston plate (39) is slidably installed on the inner wall of the side shell (4). An extension shaft (3) is inserted and installed inside the side shell (4). One end of the extension shaft (3) is fixedly connected to the side wall of the piston plate (39). A fifth spring (34) is sleeved on the outer surface of the extension shaft (3). One end of the fifth spring (34) is fixedly connected to the outer surface of the extension shaft (3), and the other end of the fifth spring (34) is fixedly connected to the outer surface of the side shell (4).
7. A method for installing a combined hoisting wall according to claim 6, wherein, specifically includes the following steps: S1. Connection of precast slabs: Place the channel steel (6) between the first precast slab (5) and the second precast slab (8). Rotate the positioning bolt (7). The positioning bolt (7) rotates and descends inside the threaded cap (19) and rotates into the second precast slab (8), thus fixing the second precast slab (8). When it is necessary to disassemble the second precast slab (8), when the positioning bolt (7) is removed from the threaded cap (19), due to the elastic force of the second spring (14), the positioning bolt (7) is ejected without the need for manual removal. And the fixing sleeve (17) has a certain limit and fixation on the positioning bolt (7) to prevent the positioning bolt (7) from falling when not in use. S2. Hoisting of precast slabs: Due to the elastic force of the third spring (23), the side block (21) moves and is inserted into the positioning cavity (22). Then pull the bolt (27). The movement of the bolt drives the fourth spring (28) to contract and drives the bolt (27) to be inserted into the inner ring sleeve (26), thus further fixing the second precast slab (8). S3. Cooperation and storage of the channel steel (6) and the steel beam (11): When the wall panel does not need to be hoisted, place the channel steel (6) inside the steel beam (11). Rotate the cover plate (33). Due to the elastic force of the telescopic rod (32) and the first spring (10), the top block (9) at one end of the telescopic rod (32) is embedded in the convex block (36) to achieve the storage of the channel steel (6). Then move the moving shaft (13). The movement of the moving shaft (13) drives the cleaning brush (38) to slide on the outer surface of the channel steel (6), thus cleaning the outer surface of the channel steel (6). After cleaning, press the extension shaft (3) to move, driving the piston plate (39) to move, and squeezing the antirust oil into the cleaning brush to achieve the antirust treatment of the channel steel (6).
Citation Information
Patent Citations
Lifting appliance for lifting steel sheet pile
CN211687920U
Combined hoisting wall
CN215630803U
Wall panel, building unit, and method of suspending building unit
JP1998245893A