A method for removing concrete support
By laying a roadbed box on the foundation pit support beam to form a temporary road, the pick-off machine removes the support beam on the road, solving the construction problems of traditional methods when the height difference is large or the floor slab load is insufficient, and it realizes convenient and fast concrete support removal, reducing the The construction difficulty and loading of the floor slabs improve construction efficiency and safety.
Patent Information
- Application Number
- CN202110543027.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-05-19
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2041-05-19
AI Technical Summary
The traditional foundation pit concrete support removal method is not applicable when the height difference between the floor slab and the support beam or the load strength of the floor slab is insufficient, resulting in increased construction difficulty and the weight of the pick-head machine adversely affects the floor slab.
Paving a roadbed box on the support beam forms a temporary road. The pick-in machine is driven on the road and crushing and dismantling the support beam. It is designed through the transfer holes and leaning parts of the roadbed box. The pick-in machine can move and transfer the roadbed box safely and stably and adjust. The travel position reduces construction difficulty and load on the floor.
It realizes convenient and rapid demolition without being restricted by the height difference between the floor slab and the support beam and the load strength of the floor slab, reducing the difficulty of concrete crushing construction, and improving construction efficiency and safety.
Smart Images

Figure CN113216210B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of building support removal, and in particular to a concrete support removal method. Background Art
[0002] With the acceleration of urbanization and the decreasing land resources, various types of urban buildings have begun to develop underground spaces. Specifically, the foundations of buildings are getting deeper and deeper. In particular, in recent years, there have been more and more ultra-deep foundation pit projects with large areas and complex plane shapes. Horizontal support in the pit is indispensable during the foundation pit construction process.
[0003] In traditional construction, the removal of foundation pit concrete supports is usually carried out using a pickaxe machine. The pickaxe machine travels on the floor slab to crush and remove the foundation pit concrete support beams above the floor slab. However, when the height difference between the floor slab and the support beam is too large, or when the pickaxe machine has an adverse effect on the floor slab due to its own weight, the traditional crushing method is no longer applicable.
[0004] In view of the above-mentioned related technologies, the inventor believes that it is necessary to provide a new method for removing foundation pit concrete supports. Summary of the invention
[0005] In order to more conveniently crush and dismantle the concrete supports of foundation pits, the present application provides a method for dismantling concrete supports, which is not limited by the height difference between the floor slab and the support beam, and is not limited by the bearing strength of the floor slab. It can more conveniently and quickly crush and dismantle the concrete supports of foundation pits, reducing the difficulty of concrete crushing construction.
[0006] A concrete support removal method provided in this application adopts the following technical solution:
[0007] In the first aspect, the present application provides a simple and convenient method for breaking concrete supports, which adopts the following technical solution:
[0008] A simple and convenient method for breaking concrete support, characterized in that it includes:
[0009] S1, construction preparation, laying the roadbed box on the supporting beams of the building to form a temporary road;
[0010] S2, placing the pick-head machine and transporting the pick-head machine to the temporary road formed by the roadbed boxes;
[0011] S3, break the support, the pick head machine breaks the support in front.
[0012] By adopting the above technical solution, the pickaxe machine travels above the support beam to crush and dismantle the support beam below, which facilitates the concrete crushing construction. The dismantling of the support beam is not limited by the height difference between the floor slab and the support beam, and reduces the load on the floor slab during the removal of the concrete support beam, which is beneficial to ensure the strength of the floor slab.
[0013] Optionally, S1 includes:
[0014] S11, laying roadbed boxes on the supporting beams of the building to form a temporary road;
[0015] S12, laying steel plates on the floor slab below the support beam to be removed;
[0016] S13, a steel pipe rack is set up at the location of the external wall reinforcement, and a protective plate is installed on the steel pipe rack for protection.
[0017] By adopting the above technical solution, the floor slabs and exterior wall steel bars can be protected while laying temporary roads to prevent them from being damaged by concrete fragments.
[0018] Optionally, S3 includes:
[0019] S31, breaking concrete to separate the concrete from the steel bars;
[0020] S32, cutting steel bars;
[0021] S33, the pick head machine moves backward, moves the roadbed box in front of the pick head machine to the rear of the pick head machine, and then repeats steps S31 and S32.
[0022] By adopting the above technical solution, the pick head machine gradually crushes the support beam by retreating, and the travel position of the pick head machine is adjusted by moving the roadbed box. There is no need to repeatedly lift the pick head machine, which speeds up the crushing efficiency of the support beam.
[0023] Optionally, the order of removing supports in step S3 is to first remove secondary supports such as connecting beams, and then remove primary supports such as beams, and to first remove non-reinforced slab strips and then remove reinforced slab strips.
[0024] By adopting the above technical solution, the disassembly sequence of the support beams is rationally designed to improve construction safety.
[0025] Optionally, S3 also includes: S34, when the last support beam is removed, the safety calculation of the last support beam is performed, and the uniformly distributed dead load F1 of the last support beam, the span L of the last support beam, the total weight of the pick head machine M2, and the total weight of the roadbed box M3 are obtained according to the on-site conditions, and the uniformly distributed live load F2 on the last support beam is calculated to be ((M1+M2) / 2) / L, and F2 is controlled <F1。
[0026] By adopting the above technical solution, it is ensured that the pickaxe machine can travel stably on the support beam during the demolition process.
[0027] In the second aspect, the present application provides a roadbed box for the above-mentioned construction method, which adopts the following technical solution:
[0028] A roadbed box comprises a hollow box body and a plurality of structural reinforcement members arranged in the box body, wherein a single structural reinforcement member is arranged along the length direction of the box body, and a plurality of structural reinforcement members are evenly distributed along the width direction of the box body, and a transfer hole is penetrated through the upper end surface of the box body.
[0029] By adopting the above technical solution, the roadbed box is erected between two supporting beams. When the roadbed box needs to be transferred to the rear side of the pick head machine, the gun head rod of the pick head machine is inserted into the transfer hole, and then the gun head is rotated to hook inward, and the body of the pick head machine is rotated to move the roadbed box to the rear side of the pick head machine.
[0030] Optionally, a leaning piece is fixed in the box, and the leaning piece is located on the side of the transfer hole away from the center line of the box width direction. A hanging abutment surface cooperating with the gun head rod of the pick head machine is provided on the side of the leaning piece close to the transfer hole, and the hanging abutment surface is an inclined surface with the lower end inclined toward the side away from the center line of the box width direction.
[0031] By adopting the above technical solution, by arranging a leaning piece in the box body, when the blasting head rod is hooked on the roadbed box, the blasting head rod abuts against the hanging abutting surface on the leaning piece, and the hooking structure between the blasting head rod and the box body is more stable and less likely to shake, thereby further ensuring stable and safe hooking and transportation of the roadbed box.
[0032] Optionally, an anti-slip pad is fixed on the hanging abutment surface of the leaning member.
[0033] By adopting the above technical solution, the roadbed box can be prevented from sliding relative to the blasting rod during transportation, thereby reducing safety risks.
[0034] Optionally, the transfer hole is located at the center of the length direction of the box body, and the transfer hole is located on one side of the center line of the width direction of the box body.
[0035] By adopting the above technical solution, when the roadbed box is hooked with the gun head rod, the center of gravity of the roadbed box is shifted to an inclined state, and the roadbed box can be hung on the gun head rod more stably, which facilitates the transportation of the roadbed box.
[0036] Optionally, two transfer holes are provided, and the two transfer holes are respectively located on both sides of the center line in the width direction of the box body.
[0037] By adopting the above technical solution, it is convenient to hook the roadbed box from different sides of the roadbed box, so that during the support breaking process, the pick head machine can continuously transport the roadbed box and continuously break the support beam.
[0038] In summary, the present application includes at least one of the following beneficial technical effects:
[0039] 1. A temporary road is formed by setting up a roadbed box on the supporting beam structure of the foundation pit. The pickaxe machine breaks the supporting beam below on the temporary road, which reduces the difficulty of breaking the supporting beam. The pickaxe machine does not travel on the floor slab, which can avoid the adverse effect of the pickaxe machine's own weight on the floor slab. It is particularly suitable for working conditions where the upper supporting beams are dense and the lower floor slab is too high from the supporting beams;
[0040] 2. By using a roadbed box with a transfer hole, the pickaxe machine can complete the transfer of the roadbed box. Concrete crushing construction workers can adjust the temporary road by themselves, and there is no need to frequently use a crane to adjust the position of the roadbed box, which facilitates construction, reduces manpower consumption, and improves construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0041] Figure 1 It is a process flow chart of a simple and convenient method for breaking concrete support disclosed in the present application;
[0042] Figure 2 It is a schematic diagram of the construction environment of a simple and convenient method for breaking concrete supports disclosed in the present application;
[0043] Figure 3 It is a schematic diagram of the overall structure of a roadbed box disclosed in the present application;
[0044] Figure 4 is along Figure 3 Sectional view of AA in the middle;
[0045] Figure 5 It is a schematic diagram of the transport state of a roadbed box disclosed in the present application.
[0046] Figure numerals: 1. roadbed box; 11. box body; 111. transfer hole; 12. structural reinforcement; 13. leaning member; 131. hanging abutment surface; 14. anti-slip mat; 2. floor protection plate; 3. steel pipe rack; 4. protective plate; 5. pickaxe machine; 6. support beam; 7. floor; 8. water spray pipe; 9. gun head rod. DETAILED DESCRIPTION
[0047] The following is combined with Figure 1-4 This application is described in further detail.
[0048] On the one hand, the embodiment of the present application discloses a simple and convenient method for breaking concrete support, referring to Figure 1 and Figure 2 ,include:
[0049] S1, construction preparation;
[0050] S11, laying a plurality of roadbed boxes 1 on the supporting beams 6 of the building to form a temporary road;
[0051] S12, laying a steel plate on the floor slab below the support beam 6 to be removed, the steel plate serving as the floor protection plate 2;
[0052] S13, erecting a steel pipe frame 3 at the location of the outer wall reinforcement, and erecting a protective plate 4 on the steel pipe frame 3 for protection, and the old formwork, steel plate, etc. on site can be used as the protective plate 4;
[0053] S14, a water spray pipe 8 is installed on the floor slab, with the water spray port of the water spray pipe 8 facing the support removal area, so as to spray water during the support removal to reduce dust.
[0054] S2, place the pick-head machine 5 and transport it to the temporary road formed by the roadbed box 1.
[0055] S3, breaking support;
[0056] S31, breaking concrete to separate the concrete from the steel bars;
[0057] S32, cutting steel bars;
[0058] S33, the pick head machine 5 moves backward, moves the roadbed box 1 in front of the pick head machine 5 to the rear of the pick head machine 5, and then repeats steps S31 and S32;
[0059] S34, when the last support beam 6 is dismantled, a safety calculation is performed on the last support beam 6. According to the on-site conditions, the uniformly distributed dead load F1 of the last support beam 6, the span L of the last support beam 6, the total weight M2 of the pickaxe machine 5, and the total weight M3 of the roadbed box 1 are obtained. The uniformly distributed live load F2 on the last support beam 6 is calculated to be ((M1+M2) / 2) / L.
[0060] S4, waste removal, lifting the waste steel bars and waste concrete out of the foundation pit.
[0061] In step S3, the order of removing the support beam 6 is to first remove the secondary supports such as the connecting beam, and then remove the main supports such as the beam, and first remove the non-reinforced plate belt area and then remove the reinforced plate belt.
[0062] The implementation principle of a simple and convenient method for breaking concrete supports disclosed in an embodiment of the present application is as follows: a temporary road is formed by erecting a roadbed box 1 on a support beam 6, and a pickaxe machine 5 can travel on the temporary road so as to break the support beam 6 below. The difficulty of breaking the support beam 6 is reduced, and the construction is more convenient. At the same time, since the pickaxe machine 5 is directly constructed on the support beam 6, it will not be restricted by the height difference between the floor slab and the support beam 6, and the self-weight of the pickaxe machine 5 will not cause damage to the floor slab during construction.
[0063] On the other hand, the present application discloses a roadbed box 1 for the above concrete support breaking method, referring to Figure 3 and Figure 4 , including a box body 11, a structural reinforcement member 12 fixed in the box body 11, and a leaning member 13 fixed in the box body 11; the box body 11 is a rectangular shell formed by welding and fixing multiple steel plates; the structural reinforcement member 12 is an I-beam arranged in the box body 11, and the upper flange and the lower flange of the I-beam are respectively abutted against the upper and lower end steel plates of the box body 11, and the flange of the I-beam and the box body 11 can be connected and fixed by bolt fasteners; the structural reinforcement member 12 is arranged along the length direction of the box body 11, and a total of five structural reinforcement members 12 are arranged, and the five structural reinforcement members 12 are evenly distributed along the width direction of the box body 11; two circular transfer holes 111 are opened through the upper end surface of the box body 11, and the two transfer holes 111 are both located on the center line of the length direction of the box body 11, and the two transfer holes 111 are symmetrically arranged on both sides of the center line of the width direction of the box body 11.
[0064] refer to Figure 4 and Figure 5 A leaning piece 13 is provided in the box body 11, and the leaning piece 13 is located on the side of the transfer hole 111 away from the center line of the box body 11 in the width direction. A hanging abutment surface 131 cooperating with the gun head rod 9 of the pick head machine 5 is provided on the side of the leaning piece 13 close to the transfer hole 111, and the hanging abutment surface 131 is an inclined surface with the lower end inclined toward the side away from the center line of the box body 11 in the width direction, so as to be in an inclined state; an anti-skid pad 14 is fixed on the hanging abutment surface 131 of the leaning piece 13, and the anti-skid pad 14 is fixed on the hanging abutment surface 131 of the leaning piece 13 by bolts, and the anti-skid pad 14 is made of hard rubber, and the side of the anti-skid pad 14 away from the hanging abutment surface 131 is set to a concave arc abutment surface that is in contact with the contour of the gun head rod 9, so as to enhance friction and prevent the roadbed box 1 from swinging left and right.
[0065] The working principle of a roadbed box 1 disclosed in an embodiment of the present application is as follows: by opening a transfer hole 111, the blasting rod 9 of the pick head machine 5 is inserted into the transfer hole 111, and by rotating the hook to hang the roadbed box 1, the vehicle body is rotated to transfer the roadbed box 1 from the front of the pick head machine 5 to the rear of the pick head machine 5, so as to transfer the roadbed box 1 and continuously crush the support beam 6 without repeatedly mobilizing equipment such as a vehicle crane and a tower crane; by eccentrically setting the transfer hole 111, the stability of the roadbed box 1 is improved when the blasting rod 9 hangs the roadbed box 1; by arranging a leaning member 13 in the roadbed box 1, the blasting rod 9 can be more fully in contact with the roadbed box 1 as a whole, thereby preventing the roadbed box 1 from shaking or moving relative to the blasting rod 9 during transportation.
[0066] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A method for removing a concrete support, characterized in that: include: S1, construction preparation, laying the roadbed box (1) on the supporting beam (6) of the building to form a temporary road; S2, placing the pick head machine (5), and transporting the pick head machine to the temporary road formed by the roadbed box (1); S3, breaking the support, the pick head machine (5) breaks the support in front; S3 includes: S31, breaking concrete to separate the concrete from the steel bars; S32, cutting the steel bars; S33, the pick head machine (5) retreats, the pick head machine (5) moves the roadbed box (1) in front of itself to the rear of itself, and then repeats steps S31 and S32; S34, when the last support beam (6) is removed, a safety calculation is performed on the last support beam (6), and according to the on-site conditions, the uniformly distributed dead load F1 of the last support beam (6), the span L of the last support beam (6), the total weight M2 of the pick head machine (5), the total weight M3 of the roadbed box (1), and the uniformly distributed live load F2 on the last support beam (6) is calculated to be ((M1+M2) / 2) / L), and F2 is controlled <F1; The roadbed box (1) comprises a hollow box body (11) and a plurality of structural reinforcement members (12) arranged in the box body (11), wherein a single structural reinforcement member (12) is arranged along the length direction of the box body (11), and the plurality of structural reinforcement members (12) are evenly distributed along the width direction of the box body (11); a transfer hole (111) is formed through the upper end surface of the box body (11); a leaning member (13) is fixed in the box body (11), and the leaning member (13) is located on a side of the transfer hole (111) away from a center line of the box body (11) in the width direction; and a side of the leaning member (13) close to the transfer hole (111) is provided with a The pick head rod (9) of the pick head machine (5) cooperates with a hanging abutment surface (131), wherein the hanging abutment surface (131) is an inclined surface with the lower end inclined toward a side away from the center line of the width direction of the box body (11), and an anti-slip pad (14) is fixed on the hanging abutment surface (131) of the leaning member (13); the transfer hole (111) is located at the center position of the box body (11) in the length direction, and the transfer hole (111) is located on one side of the center line of the width direction of the box body (11); two transfer holes (111) are provided, and the two transfer holes (111) are respectively located on both sides of the center line of the width direction of the box body (11).
2. A method for removing a concrete support according to claim 1, characterized in that: S1 includes: S11, laying a roadbed box (1) on the supporting beam (6) of the building to form a temporary road; S12, laying a steel plate on the floor slab below the support beam (6) to be removed; S13, a steel pipe frame (3) is set up at the location of the external wall reinforcement, and a protective plate (4) is set up on the steel pipe frame (3) for protection.
3. A method for removing a concrete support according to any one of claims 1-2, characterized in that: The order of removing supports in step S3 is to first remove the secondary supports of the connecting beams, then remove the main supports of the beams, first remove the non-reinforced slab belt area, and then remove the reinforced slab belt.