An LNG refueling device for improving the efficiency of LNG plunger pump
By designing an air refueling device connecting the LNG tank body, plunger pump, liquid refueling machine and submersible pump, the process is optimized by using the low-temperature shutdown valve, the problems of the LNG plunger pump pre-cooling time and the occurrence of gas stone are solved, and the gas refueling is improved efficiency.
Patent Information
- Application Number
- CN202110641546.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-06-09
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2041-06-09
AI Technical Summary
In existing LNG filling stations, there are insufficient design and use of LNG plunger pumps, resulting in too long pre-cooling time, impact on the generation of gas stones and smooth filling functions, affecting the use efficiency.
A gas filling device including an LNG tank body, a plunger pump, a liquid filler and a submersible pump is designed. It is connected through the inlet pipe, liquid phase pipe and a return pipe, and multiple low-temperature shut-off valves are set up to optimize the pre-cooling of the pump. and the air refueling process.
It effectively reduces pre-cooling losses, shortens the pre-cooling time of the plunger pump, and improves the use efficiency and air filling smoothness of the LNG plunger pump.
Smart Images

Figure CN113236967B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of LNG gas filling and use, in particular to an LNG gas filling device for improving the use efficiency of an LNG plunger pump. Background Art
[0002] At present, with the comprehensive promotion of LNG / L-CNG filling stations across the country, some filling stations have been in use for more than ten years. At first, most design units were in the stage of learning and exploring the filling process of LNG / L-CNG, and did not study the parameters, usage habits and methods of LNG plunger pumps in depth. Although the filling function can be completed in actual work, the shortcomings in the design, construction and use of plunger pumps have also paid some economic costs. First, the pre-cooling time of the LNG plunger pump is too long in the early stage of use, resulting in a large amount of EAG; second, the pre-cooling work at the front end of the LNG plunger pump is not done well, and gas stones are generated in the LNG plunger pump cavity, which stops the pump and interrupts the filling.
[0003] At present, many LNG filling stations have problems such as the LNG liquid phase pipeline being too long during the original design, the slope of the LNG liquid phase pipeline not being properly retained during on-site construction, and the height difference between the LNG storage tank outlet and the plunger pump inlet pipe being too small, which affects the efficiency of the LNG plunger pump and may even prevent the gas filling function from being completed smoothly. Summary of the invention
[0004] The purpose of the present invention is to solve the above problems and to design an LNG refueling device which can improve the use efficiency of the LNG plunger pump.
[0005] To achieve the above-mentioned purpose, the technical solution of the present invention is a LNG filling device for improving the use efficiency of an LNG plunger pump, comprising an LNG tank body, an LNG plunger pump, an LNG liquid filling machine and an LNG submersible pump, the LNG tank body and the LNG submersible pump being connected via a liquid inlet pipe, a three-way valve being installed at the outlet end of the LNG submersible pump, a first connecting pipe to the LNG liquid filling machine being installed at one end of the three-way valve, the LNG tank body and the LNG plunger pump being connected via an LNG liquid phase pipeline, a third connecting pipe connected to the LNG liquid phase pipeline being installed at the other end of the three-way valve.
[0006] The LNG liquid phase pipeline is provided with a first cryogenic stop valve.
[0007] A second low-temperature stop valve is installed on the third connecting pipe.
[0008] A third low-temperature stop valve is installed on the first connecting pipe.
[0009] A gas return pipe is connected between the LNG plunger pump and the LNG tank.
[0010] An LNG filling device that improves the use efficiency of an LNG plunger pump manufactured using the technical solution of the present invention can reasonably reduce the loss caused by pre-cooling the LNG liquid phase pipeline, shorten the pre-cooling time of the LNG plunger pump, and improve the use efficiency of a traditional LNG plunger pump device. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] Figure 1 It is a structural schematic diagram of an LNG filling device for improving the use efficiency of an LNG plunger pump according to the present invention;
[0012] In the figure, 1. LNG tank; 2. LNG plunger pump; 3. LNG submersible pump; 4. liquid inlet pipe; 5. three-way valve; 6. LNG liquid adding machine; 7. LNG liquid phase pipeline; 8. third connecting pipe; 9. first cryogenic stop valve; 10. second cryogenic stop valve; 11. third cryogenic stop valve; 12. return air pipe. DETAILED DESCRIPTION
[0013] The present invention will be described in detail below in conjunction with the accompanying drawings. Figure 1 As shown, an LNG filling device for improving the use efficiency of an LNG plunger pump comprises an LNG tank body 1, an LNG plunger pump 2, an LNG liquid filling machine 6 and an LNG submersible pump 3. The LNG tank body 1 and the LNG submersible pump 3 are connected via a liquid inlet pipe 4, a three-way valve 5 is installed at the outlet end of the LNG submersible pump 3, one end of the three-way valve 5 is installed with a first connecting pipe to the LNG liquid filling machine 6, the LNG tank body 1 and the LNG plunger pump 2 are connected via an LNG liquid phase pipeline 7, a third connecting pipe 8 connected to the LNG liquid phase pipeline 7 is installed at the other end of the three-way valve 5; a first low-temperature stop valve 9 is installed on the LNG liquid phase pipeline 7; a second low-temperature stop valve 10 is installed on the third connecting pipe; a third low-temperature stop valve 11 is installed on the first connecting pipe; a return air pipe 12 is connected between the LNG plunger pump 2 and the LNG tank body 1.
[0014] The characteristics of this embodiment are that it includes an LNG tank body 1, an LNG plunger pump 2, an LNG liquid adding machine 6 and an LNG submersible pump 3. The LNG tank body 1 and the LNG submersible pump 3 are connected by a liquid inlet pipe 4. A three-way valve 5 is installed at the outlet end of the LNG submersible pump 3. One end of the three-way valve 5 is installed with a first connecting pipe to the LNG liquid adding machine 6. The LNG tank body 1 and the LNG plunger pump 2 are connected by an LNG liquid phase pipeline 7. The other end of the three-way valve 5 is installed with a third connecting pipe 8 connected to the LNG liquid phase pipeline 7. This can reasonably reduce the loss of natural gas, reduce the loss of natural gas in the pre-cooling pipeline, and improve the utilization efficiency of traditional devices.
[0015] In this embodiment, an LNG liquid phase pipeline is led out from the outlet of the LNG submersible pump and connected to the LNG plunger pump inlet pipeline, and a first cryogenic stop valve 9, a second cryogenic stop valve 10 and a third cryogenic stop valve 11 are respectively provided. When the conventional process is used to refuel the LNG filling machine and the L-CNG filling machine, the second cryogenic stop valve 10 should be closed, and the first cryogenic stop valve 9 and the third cryogenic stop valve 11 should be opened to perform the refueling operation; when the precooling time of the LNG plunger pump is too long or the pump often stops due to gas stones, the first cryogenic stop valve 9 and the third cryogenic stop valve 11 should be closed, and the second valve 10 should be opened to use the original LNG submersible pump to precool the pipeline.
[0016] The above technical solutions only reflect the preferred technical solutions of the technical solutions of the present invention. Some changes that may be made to certain parts thereof by technicians in this technical field all reflect the principles of the present invention and fall within the protection scope of the present invention.
Claims
1. An LNG refueling device for improving the use efficiency of an LNG plunger pump, comprising an LNG tank (1), an LNG plunger pump (2), an LNG refueling machine (6) and an LNG submersible pump (3), characterized in that: The LNG tank body (1) and the LNG submersible pump (3) are connected via a liquid inlet pipe (4); a three-way valve (5) is installed at the outlet end of the LNG submersible pump (3); one end of the three-way valve (5) is installed with a first connecting pipe connected to the LNG liquid filling machine (6); the LNG tank body (1) and the LNG plunger pump (2) are connected via an LNG liquid phase pipeline (7); the other end of the three-way valve (5) is installed with a third connecting pipe (8) connected to the LNG liquid phase pipeline (7); The LNG liquid phase pipeline (7) is provided with a first cryogenic stop valve (9); A gas return pipe (12) is connected between the LNG plunger pump (2) and the LNG tank body (1).
2. The LNG refueling device for improving the use efficiency of the LNG plunger pump according to claim 1, characterized in that: A second low-temperature stop valve (10) is installed on the third connecting pipe.
3. The LNG refueling device for improving the use efficiency of the LNG plunger pump according to claim 1, characterized in that: A third low-temperature stop valve (11) is installed on the first connecting pipe.
Citation Information
Patent Citations
LNG (Liquefied Natural Gas) filling device for improving use efficiency of LNG plunger pump
CN215174126U