Flexible production system for polyester products
By designing a flexible production system, we solve the problems of low efficiency and environmental pollution in the polyester production system during production conversion and slurry preparation, achieve flexible and efficient production of a variety of products, and reduce raw material losses and environmental pollution.
Patent Information
- Application Number
- CN202010563816.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-06-19
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2040-06-19
AI Technical Summary
The existing polyester production system needs to be converted when producing different polymer products, which takes a long time. The dispersion effect is poor during the slurry preparation process, the power consumption is high, and the PTA dust content in the exhaust gas is high, which poses safety hazards and environmental pollution problems.
A flexible production system is designed, including the first line of esterification and polycondensation and the second line of esterification and polycondensation. It adopts a multi-chamber structure slurry preparation tank and esterification kettle, and achieves uniform mixing and mixing of materials through a slurry transfer pump and an esterification material transfer pump. Circulation, combined with spray columns and cyclone separators to reduce dust emissions, and reduce equipment investment and floor space through improved vacuum systems.
It achieves flexible production of a variety of polyester products, shortens reaction time, improves material uniformity and production efficiency, reduces raw material loss and environmental pollution, and reduces equipment costs and energy consumption.
Smart Images

Figure CN113813866B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a polyester production system, in particular to a flexible production system for polyester products, and belongs to the technical field of chemical equipment. Background Art
[0002] The existing polyester production system includes slurry preparation device, esterification device, polycondensation device, etc., which can only produce one product at the same time. If different polymerization products need to be produced, it is necessary to switch production. When switching products, it takes a long time, many products are isolated, and the loss is large. The slurry at room temperature needs to react for about 4 hours at a reaction temperature of 250-260℃ in the esterification kettle, which is a long time.
[0003] In the traditional slurry configuration, the feed pipes of EG and catalyst are directly welded to the venting main pipe of the slurry preparation tank. The liquid EG and catalyst flow directly along the pipe wall into the slurry preparation tank, with a small contact area with raw materials such as granular terephthalic acid, resulting in poor dispersion effect. The liquid ethylene glycol (EG) and catalyst concentrated in a small local area after flowing into the slurry preparation tank can only be dispersed into granular terephthalic acid (PTA) or isophthalic acid (IPA) by forced stirring of the agitator. The dispersion effect is poor, the power consumption is high, and it is not conducive to uniform mixing of the slurry. In addition, the exhaust gas discharged from the slurry preparation tank contains a high content of PTA dust, which not only causes raw material loss, but also pollutes the surrounding environment and poses a safety hazard.
[0004] The polycondensation device is generally composed of a pre-polycondensation kettle, a second polycondensation kettle, a final polycondensation kettle and a spray system. The spray system is used to remove EG and oligomers produced during the polycondensation process. The tail gas from the pre-polycondensation kettle passes through the spray system and is vacuumed by a separate liquid ring vacuum pump. The tail gas from the second polycondensation kettle and the final polycondensation kettle passes through the spray system and is respectively connected to the third-stage jet pump and the first-stage jet pump of the vacuum unit. The vacuum of the reactor is adjusted by controlling the flow of the balance steam through a regulating valve, and the final tail gas is pumped out by a shared liquid ring vacuum pump.
[0005] The gas phase outlet of each polycondensation kettle is connected to the scraper condenser. The scraper condenser mainly includes a horizontal cylinder and a vertical cylinder. The vertical cylinder is connected to the upper part of the tail end of the horizontal cylinder. The inner cavity of the vertical cylinder is provided with a condensation nozzle, which is connected to the spray pipe. The top of the vertical cylinder is provided with a scraper exhaust port; the inner cavity of the horizontal cylinder is provided with a scraper rotor, which includes a rotor shaft and a scraper connected to the rotor shaft, and the scraper is adapted to the inner wall of the horizontal cylinder. A scraper air inlet is provided at the upper part of the head end of the horizontal cylinder, and a scraper medium outlet is provided at the lower part of the tail end of the horizontal cylinder; the scraper medium outlet is connected to the hot well through an atmospheric leg, the EG outlet at the bottom of the hot well is connected to the inlet of the spray circulation pump, and the outlet of the spray circulation pump is connected to the spray pipe through the EG circulation pipe.
[0006] When working, cold liquid EG is sprayed out in an umbrella shape from the condensation nozzle. When the liquid EG contacts the gaseous EG, it can absorb part of it, making it liquid and flowing downward. At the same time, the oligomers can be captured by the liquid EG and flow downward into the horizontal cylinder together with the EG. A certain liquid level is maintained in the horizontal cylinder. The scraper can scrape off the oligomers adhering to the inner wall of the horizontal cylinder. Finally, the oligomers and liquid EG are discharged from the scraper medium outlet, enter the hot well through the atmospheric leg pipe and the atmospheric leg, and the EG condensate is pumped out by the spray circulation pump and returns to the vertical cylinder for spraying through the EG circulation pipe and the spray pipe.
[0007] The above structure has the following disadvantages: 1. Two sets of liquid ring vacuum pumps are used, which has high investment cost and occupies a large area; 2. Due to the high vacuum requirement of the second polycondensation kettle and the fast vacuum gas speed, oligomers are easily precipitated at the inlet of the second-stage semi-jet pump, frequently causing blockage; high-temperature EG or EG steam is required for regular flushing. Each flushing will cause the vacuum degree of the second polycondensation kettle to fluctuate, affecting product quality. Summary of the invention
[0008] The purpose of the present invention is to overcome the problems existing in the prior art and provide a flexible production system for polyester products, which can produce traditional polyester products such as high gloss and semi-dull, and can also produce special products such as cationic, flame retardant, high shrinkage or bottle flakes at the same time.
[0009] In order to solve the above technical problems, a flexible production system of polyester products of the present invention comprises a first esterification polycondensation line and a second esterification polycondensation line, wherein the first esterification polycondensation line comprises a first slurry preparation tank, a first esterification kettle, a second esterification kettle, a first pre-polycondensation kettle, a first polycondensation kettle and a first final polycondensation kettle connected in series in sequence, and the discharge port of the first final polycondensation kettle is connected to a first pelletizer or a first spinning device through a melt delivery pump, and the second esterification polycondensation line comprises a second slurry preparation tank, a second esterification kettle, a second esterification kettle, a second pre-polycondensation kettle, a second polycondensation kettle and a second final polycondensation kettle connected in series in sequence, and the discharge port of the second final polycondensation kettle is connected to a first pelletizer or a first spinning device through a melt delivery pump. The second-line pelletizer or the second-line spinning equipment is connected; the PTA feed pipe is connected to the top of the first-line slurry preparation tank, and the IPA feed pipe is connected to the top of the second-line slurry preparation tank; the bottom outlet of the first-line esterification kettle is equipped with an esterification material delivery pump 1, and the bottom outlet of the second-line esterification kettle is equipped with an esterification material delivery pump 2, the outlet branch 1 of the esterification material delivery pump 1 is connected to the feed port of the first-line esterification kettle 2, the outlet branch 2 of the esterification material delivery pump 1 and the outlet of the esterification material delivery pump 2 are commonly connected to the feed port of the second-line esterification kettle 2, the second-line esterification kettle is a horizontal multi-chamber structure, and each chamber is respectively provided with a stirrer and an auxiliary material injection port, and each auxiliary material injection port is respectively connected to the auxiliary material supply pipe.
[0010] Compared with the prior art, the present invention has achieved the following beneficial effects: EG, PTA and catalyst are uniformly stirred in the first-line slurry preparation tank, and can also be self-circulated through the slurry delivery pump 1, and after being uniformly mixed, they are sent to the first-line esterification kettle by the slurry delivery pump 1 for esterification reaction; EG, IPA and catalyst are uniformly stirred in the second-line slurry preparation tank, and can also be self-circulated through the slurry delivery pump 2, and after being uniformly mixed, they are sent to the second-line esterification kettle by the slurry delivery pump 2 for esterification reaction; the esterified product of the first-line esterification kettle is sent out by the esterification material delivery pump 1, enters the first-line esterification kettle 2 for continuous reaction, and after condensation in the first-line pre-condensation kettle, the first-line condensation kettle 2 and the first-line final condensation kettle, is sent to the first-line pelletizer for pelletizing by the melt delivery pump 1 or sent to the first-line spinning equipment for spinning, so as to produce traditional polyester products such as high gloss and semi-dull. The esterification product of the second-line esterification kettle is delivered by the second esterification material delivery pump, mixed with the second material at the outlet of the first esterification material delivery pump, and then enters the second-line esterification kettle. The relevant special varieties of auxiliary materials can be added to any chamber of the second-line esterification kettle through the auxiliary material supply pipe. Under certain pressure, temperature and stirring conditions, further esterification reaction is carried out. After polycondensation in the second-line pre-condensation kettle, the second-line polycondensation kettle and the second-line final polycondensation kettle, it is sent to the second-line pelletizer for pelletizing or to the second-line spinning equipment for spinning by the melt delivery pump, which can produce special products such as cationic, flame retardant, high shrinkage or bottle flakes. Only one line can be operated, or the first and second lines can be operated at the same time. The production ratio of the two lines can be flexibly adjusted. When producing special products, it does not affect the production of conventional products and avoids conversion losses.
[0011] As an improvement of the present invention, the outlet of the esterification material delivery pump 1 is also connected to the top circulation port of the first-line esterification kettle 1 through the esterification circulation pipe 1; the outlet of the esterification material delivery pump 2 is also connected to the top circulation port of the second-line esterification kettle 1 through the esterification circulation pipe 2. The esterified product with a qualified esterification rate discharged from the first-line esterification kettle 1 is returned to the first-line esterification kettle 1 for circulation through the esterification material delivery pump 1 and the esterification circulation pipe 1, which accelerates the reaction rate in the first-line esterification kettle 1, shortens the reaction time of the first-line esterification, and makes the material more uniform. Similarly, the esterified product with a qualified esterification rate discharged from the second-line esterification kettle 1 is returned to the second-line esterification kettle 1 for circulation through the esterification material delivery pump 2 and the esterification circulation pipe 2, which accelerates the reaction rate in the second-line esterification kettle 1, shortens the reaction time of the second-line esterification, and makes the material more uniform.
[0012] As a further improvement of the present invention, the exhaust ports of the first-line esterification kettle, the second-line esterification kettle and the first-line esterification kettle are connected to the air inlet of the first process tower, and an EG reflux pump is installed at the bottom of the first process tower. The outlet of the first EG reflux pump is connected to the top reflux port of the first-line esterification kettle, the second-line esterification kettle and the first-line esterification kettle through an EG reflux pipe; the exhaust port of the second-line esterification kettle is connected to the air inlet of the second process tower, and an EG reflux pump is installed at the bottom of the second process tower. The outlet of the second EG reflux pump is connected to the top reflux port of the second-line esterification kettle through an EG reflux pipe. The EG and water vapor discharged from the exhaust ports of the first-line esterification kettle, the second-line esterification kettle and the first-line esterification kettle are all distilled into the first process tower, and the EG at the bottom of the first process tower is refluxed to the first-line esterification kettle, the second-line esterification kettle and the first-line esterification kettle through the EG reflux pump. Since special materials are added to the second-line esterification kettle, an independent supporting process tower 2 is used to distill the EG and water vapor discharged from the second-line esterification kettle.
[0013] As a further improvement of the present invention, the powder inlet at the top of the second-line slurry preparation tank is connected to the IPA feed pipe, and a spray column extending vertically is also installed on the top of the second-line slurry preparation tank, the top of the spray column is connected to the preparation tank exhaust pipe, the outlet of the preparation tank exhaust pipe is connected to the air inlet of the cyclone separator, the top exhaust port of the cyclone separator is connected to the induced draft fan, and the bottom outlet of the cyclone separator is connected to the reflux port at the top of the second-line slurry preparation tank through the separator return valve and the powder reflux pipe; the inner cavity of the spray column is provided with an EG nozzle and a catalyst nozzle in sequence from top to bottom The EG nozzle is connected to the EG feed pipe, and the catalyst nozzle is connected to the catalyst feed pipe; the lower end of the spray column is inserted into the inner cavity of the second-line slurry preparation tank and is connected to a liquid distributor, the top of the middle section of the liquid distributor is connected to the lower port of the spray column and extends symmetrically along the radial direction of the second-line slurry preparation tank with the axis of the spray column as the center, the vertical cross-section of the liquid distributor is rhombus-shaped, and distributor sealing plates are respectively provided in the middle and lower parts of the two ends of the liquid distributor, and triangular exhaust gas outlets are respectively provided above the two distributor sealing plates, and a slit-shaped discharge port equal to the length of the liquid distributor is provided at the lower end of the liquid distributor.
[0014] Low-temperature EG enters the spray column from the EG feed pipe and is sprayed downward from the EG nozzle; high-temperature catalyst enters the spray column from the catalyst feed pipe and is sprayed downward from the catalyst nozzle; since the catalyst has a high temperature and a small flow rate, while the EG has a low temperature and a large flow rate, the catalyst nozzle is closer to the second-line slurry preparation tank, and the EG nozzle is arranged above the catalyst nozzle. During the downward spraying process of EG, it is mixed with the catalyst solution and falls into the middle section of the liquid distributor together. During the flow to both ends, the liquid is distributed downward along the slit-shaped discharge port, and the liquid level in the liquid distributor is lower than the height of the distributor sealing plate; IPA powder falls into the second-line slurry preparation tank from the IPA feed pipe and the powder inlet, and is easier to mix with the EG and catalyst evenly distributed along the radius under the action of the preparation tank agitator. The evenly mixed slurry enters the slurry delivery pump 2 from the bottom of the second-line slurry preparation tank, and the slurry delivery pump 2 delivers the configured slurry to the second-line esterification kettle 1 through the slurry output pipe for esterification reaction. Under the suction of the induced draft fan, the second-line slurry preparation tank maintains a slightly negative pressure state, which is convenient for the discharge of IPA powder and prevents the powder from overflowing due to positive pressure. The tail gas enters the upper part of the inner cavity of the liquid distributor from the two triangular tail gas outlets and enters the spray column upward. The floating IPA powder passes through the two-stage spraying of the catalyst nozzle and the EG nozzle during the upward process. Most of the IPA powder is captured and falls back into the second-line slurry preparation tank, reducing the dust content in the tail gas. A small amount of IPA powder enters the cyclone separator for separation. When the IPA powder deposited at the bottom of the cyclone separator accumulates to a certain amount, the separator return valve is opened and returned to the second-line slurry preparation tank through the powder return pipe, so that all of it can be reused, which not only reduces the loss of raw materials, but also improves the on-site working environment and avoids environmental pollution. The first-line slurry preparation tank can adopt a traditional structure or the same structure as the second-line slurry preparation tank. The powder inlet at the top of the first-line slurry preparation tank is connected to the PTA feed pipe.
[0015] As a further improvement of the present invention, the long diagonal line of the liquid material distributor extends along the vertical plane where the axis of the spray column is located, and the angle between the two top surfaces of the liquid material distributor is 30°; the greater the distance from the axis of the spray column, the wider the slit of the slit-shaped discharge port. This makes it easy for the powder falling on the top surface of the liquid material distributor to slide down and avoid accumulation on the upper surface of the liquid material distributor; the slit directly below the spray column is easier to drop, and the wider the slit with a longer flow distance, which is conducive to uniform discharge in the radial direction of the slurry preparation tank.
[0016] As a further improvement of the present invention, a preparation tank level meter is installed at the bottom of the second-line slurry preparation tank, a rotary feeding valve is provided on the IPA feed pipe, an EG flow meter and an EG flow control valve are installed on the EG feed pipe, and a catalyst flow meter and a catalyst flow control valve are installed on the catalyst feed pipe. The openings of the EG flow control valve and the catalyst flow control valve are both controlled by the flow of the rotary feeding valve, and the flow of the rotary feeding valve is controlled by the second-line slurry preparation tank level measured by the preparation tank level meter. When the flow of IPA increases, the openings of the EG flow control valve and the catalyst flow control valve increase in proportion, which can maintain an accurate molar ratio of EG, catalyst and IPA, and improve the preparation quality of the slurry.
[0017] As a further improvement of the present invention, the gas phase outlet of the second-line pre-polycondensation kettle is connected to the air inlet of the scraper condenser one, the gas phase outlet of the second-line polycondensation kettle is connected to the air inlet of the scraper condenser two, the gas phase outlet of the second-line final polycondensation kettle is connected to the air inlet of the scraper condenser three, the top exhaust port of the scraper condenser three is connected to the suction port of the first-level steam jet pump through the first-level vacuum pipe, the top exhaust port of the scraper condenser two is connected to the suction port of the second-level semi-steam jet pump through the second-level vacuum pipe, the top exhaust port of the scraper condenser one is connected to the suction port of the liquid ring pump through the third-level vacuum pipe and the vacuum regulating valve, the outlet of the first-level steam jet pump is connected to the air inlet of the first-level spray tank, and the first The exhaust port of the spray tank is connected to the suction port of the secondary steam jet pump, the outlets of the secondary steam jet pump and the secondary semi-steam jet pump are both connected to the air inlet of the secondary spray tank, the exhaust port of the secondary spray tank is connected to the suction port of the tertiary steam jet pump, the outlet of the tertiary steam jet pump is connected to the air inlet of the tertiary spray tank, and the exhaust port of the tertiary spray tank is connected to the suction port of the liquid ring pump; the top exhaust port of the scraper condenser II is also connected to the primary spray tank through a secondary auxiliary vacuum pipe, and an EG ring pipe is provided on the inner wall of the secondary auxiliary vacuum pipe at a certain interval, and nozzles are evenly distributed on the circumference of the EG ring pipe, and each EG ring pipe is connected to the EG circulation pipe of the scraper condenser II. The vacuum requirement of the second-line precondensation kettle is not high, generally 8-15KPa (A). The inlet vacuum of the liquid ring pump after the vacuum jet unit can be controlled at 5-20KPa, which can meet the vacuum requirement of the second-line precondensation kettle. Therefore, the exhaust port of the scraper condenser 1 is directly connected to the liquid ring pump after the vacuum jet unit through a regulating valve, canceling the original independent liquid ring pump of the second-line precondensation kettle, reducing the equipment investment cost and the occupation of the workshop area. The vacuum of the second-line polycondensation kettle is generally 0.8-1.5KPa (A), and the vacuum of the first-level spray tank is below 0.8KPa (A). The exhaust port of the scraper condenser 2 adds a secondary auxiliary vacuum pipe connected to the first-level spray tank, and a regulating valve is installed on the secondary vacuum pipe. The vacuum degree of the second-line polycondensation kettle is directly adjusted by the opening of the regulating valve, which can fully meet the vacuum requirements of the second-line polycondensation kettle. When the original secondary vacuum pipe is blocked and needs to be flushed, it can be switched to the secondary auxiliary vacuum pipe, so that the original secondary vacuum pipe and the secondary auxiliary vacuum pipe can serve as backup for each other to maintain the vacuum degree of the second line polycondensation kettle. The EG circulation pipe of the scraper condenser 2 is used to provide EG spray liquid to the nozzle of the EG ring pipe to achieve online annular spraying, which can further capture particles and condensable gases in the tail gas, reduce the load of the vacuum unit, and avoid the blockage of the secondary auxiliary vacuum pipe, making the vacuum system more stable. The spray liquid of the EG ring pipe flows back to the scraper condenser 2 with the help of the slope of the secondary auxiliary vacuum pipe. The vacuum degree of the second line final polycondensation kettle is generally 100-200Pa (A), so the top exhaust port of the scraper condenser 3 is connected to the primary steam jet pump with the largest suction force through the primary vacuum pipe. Since the diameter of the primary vacuum pipe is large, it is not easy to be blocked.
[0018] As a further improvement of the present invention, the gas phase outlets of the two-line pre-polycondensation kettle, the second-line polycondensation kettle and the second-line final polycondensation kettle are respectively connected to the side wall inlet of the corresponding vacuum catcher, the top gas phase outlet of each vacuum catcher is respectively connected to the air inlet of the corresponding scraper condenser, the bottom outlet of each vacuum catcher is respectively connected to the top inlet of the corresponding vacuum collecting tank through an electric shut-off valve, the top air inlet of each vacuum collecting tank is also connected to the nitrogen pipe through a nitrogen valve, and a collecting tank discharge valve is provided at the bottom of each vacuum collecting tank; the medium outlet of each scraper condenser is respectively connected to the corresponding hot well through an atmospheric leg, the EG outlet of each hot well is respectively connected to the inlet of a spray circulation pump, the outlet of each spray circulation pump is connected to the inlet of a cooler, and the outlet of each cooler is respectively connected to the spray port of the corresponding scraper condenser through an EG circulation pipe. After the mixture of EG, water and oligomers is discharged from the gas phase outlet of the polycondensation kettle, it first enters the vacuum trap. Due to the reduction of gas velocity, the liquid oligomers are retained at the bottom of the vacuum trap under the action of gravity. EG, water and a small amount of oligomers enter the scraper condenser for spraying and replenishment. The condensed oligomers are discharged from the medium outlet of the scraper condenser along with EG, enter the hot well through the atmospheric leg for filtration, and the spray liquid EG is pumped out by the circulating pump, cooled in the cooler, and returned to the spray port of the scraper condenser for circulating spraying. When the vacuum catcher accumulates to a certain level, the electric shut-off valve is opened, and the nitrogen in the vacuum collection tank enters the vacuum catcher and is discharged from its gas phase outlet. The liquid oligomer enters the vacuum collection tank for storage. After a certain amount is stored, the nitrogen valve of the vacuum collection tank is opened to fill the vacuum collection tank with nitrogen. At the same time, the collection tank discharge valve at the bottom of the vacuum collection tank is opened to discharge the liquid oligomer into the collection tank. After the discharge is completed, nitrogen is continued to be introduced for about 10 seconds to nitrogen seal the vacuum collection tank, and then the nitrogen valve is closed. Since most of the oligomers are collected by the vacuum catcher, the spray liquid flow required by the scraper condenser will be greatly reduced, reducing energy consumption, and the stability of the vacuum system will be greatly improved; in addition, the amount of residue discharged from the scraper condenser into the hot well will be greatly reduced, the stability of the scraper operation will be improved, and the service life of the scraper will be greatly extended.
[0019] As a further improvement of the present invention, a hot well cover is provided on the top of the hot well, a longitudinal partition is provided along the longitudinal axis of the hot well to divide the inner cavity of the hot well into left and right halves, a left inner chamber and a right inner chamber are symmetrically provided on both sides of the middle section of the longitudinal partition, the outer side of the transverse wall panel of the left inner chamber is the left outer chamber, the outer side of the transverse wall panel of the right inner chamber is the right outer chamber, a conical hopper is provided at the bottom of the left inner chamber and the right inner chamber respectively, the lowest points of the two conical hoppers are respectively connected to the hot well slag discharge port, and the two hot well slag discharge ports extend downward to the outside of the bottom of the hot well respectively; the left outer chamber and the right outer chamber The bottom is provided with the hot well EG outlet respectively; the hot well top cover is plugged with two atmospheric legs, the lower ends of the two atmospheric legs are respectively inserted into the lower part of the inner cavity of the left inner chamber and the right inner chamber, the upper part of each transverse wall plate is respectively provided with an overflow port communicating with the corresponding outer chamber, the inner port of each overflow port is respectively covered with a filter plate, the left and right sides of each filter plate are respectively plugged into the vertical slot of the inner end face of the transverse wall plate, the outer port of each overflow port is respectively covered with an outwardly convex arc filter basket, the left and right sides of each arc filter basket are respectively plugged into the vertical slot of the outer end face of the transverse wall plate. EG and a small amount of oligomers flow into the lower part of the left inner chamber through the valve and pipeline at the bottom of the scraper condenser through the atmospheric leg on the left side, and at the same time play a liquid sealing role, EG flows upward after the first filtration of the filter plate, flows out, enters the inner cavity of the arc filter basket, and after the second filtration of the arc filter basket, enters the left outer chamber, flows out from the hot well EG outlet at the bottom of the left outer chamber, is pumped out by the circulation pump, and after cooling, is sent to the scraper condenser for circulation spraying. Impurities such as oligomers are blocked in the left inner chamber, fall into the conical hopper, and are discharged from the hot well slag outlet and enter the cleaning box. If the atmospheric leg on the left is blocked, the atmospheric leg on the right can be switched to work immediately, and the hot well EG outlet and the hot well slag outlet are also switched to work on the right side. This allows the spray system to operate long-term and stably, ensuring the normal operation of the polymerization device, avoiding shutdown processing due to atmospheric leg blockage, greatly reducing losses, and ensuring normal production operation. The filter plate is the first filtration to intercept larger impurities. The filter plate of the present invention is close to the top of the hot well, which is convenient for pulling out the filter plate for cleaning and also for reinstalling. The convex arc filter basket increases the filtration area and the storage space; the edges of the filter plate and the left and right sides of the arc filter basket are embedded in the vertical slots, which are convenient for pulling out, cleaning and assembly.
[0020] As a further improvement of the present invention, the two atmospheric legs are respectively located on both sides of the longitudinal partition and respectively pass through the central hole of the sealing seat. The two sealing seats are respectively welded on the top cover of the hot well. The stuffing box between the outer wall of the atmospheric leg and the inner wall of the sealing seat is respectively provided with stuffing, and the upper part of the stuffing is respectively provided with a stuffing gland, and the flange of the stuffing gland is connected to the flange of the sealing seat through a gland screw. Tighten the gland screw, and the stuffing is pressed in the stuffing box through the stuffing gland, which is not only sealed on the outer periphery of the atmospheric leg, but also can ensure that the atmospheric leg can slide freely vertically, and can automatically adapt to the expansion and contraction caused by the temperature change of the system.
[0021] As a further improvement of the present invention, the hot well slag discharge port is respectively connected to the cleaning box feeding port at the top of the cleaning box, and the cleaning box comprises a horizontal cylinder body closed at one end, and the front end of the cleaning box is hingedly provided with a cleaning box cover that can be opened and closed, and the outer periphery of the cylinder of the cleaning box is covered with a cleaning box jacket, and the inner cavity of the cleaning box is provided with a plurality of square filter drawers stacked in sequence from top to bottom, and the frames on the left and right sides of each square filter drawer are respectively supported in guide slide grooves by rollers, and each guide slide groove extends along the axial direction of the cleaning box and is respectively fixed on both sides of the inner wall of the cleaning box, and the bottom of the inner cavity of the cleaning box is provided with an arc bottom drawer, and the bottom of the arc bottom drawer is supported on the bottom of the inner wall of the cleaning box by rollers, and the bottoms of the arc bottom drawer and each square filter drawer are respectively provided with filter screens, and the mesh number of the lower filter screen is successively greater than the mesh number of the upper filter screen, and the lower end of the cleaning box feed port points to the central area of the top square filter drawer, and the bottom center of the cleaning box is provided with a cleaning box discharge port. The frame of each drawer is erected upward to prevent the mixture from overflowing from the surrounding of the filter screen. The guide chute is convenient for the square filter drawer to be pulled out, cleaned and put back, and can ensure that each square filter drawer is in a horizontal state; the arc bottom drawer is located at the arc bottom of the cleaning box and is in a stable and balanced state. The guide chute can be omitted and directly supported on the arc bottom of the cleaning box by rollers. The mixture of oligomers and EG enters the inner cavity of the cleaning box from the feeding port of the cleaning box, and first falls on the square filter drawer on the top layer to perform a coarse filtration on the mixture. The mesh of the top filter is large and has a strong liquid permeability. It will not be blocked and cause overflow. The largest slag is intercepted, and the slightly smaller slag all falls into the next layer for further filtration; in this way, the filtration accuracy is improved layer by layer, and the smallest slag is intercepted by the arc bottom drawer. After multiple layers of step-by-step filtration, the clean EG is discharged from the cleaning box drain port at the bottom of the cleaning box. Open the cover of the cleaning box, and you can pull out the square filter drawer or the curved bottom drawer for cleaning. Since the curved bottom drawer has the smallest holes and is most easily clogged, the frequency of cleaning can be higher than other square filter drawers. It is not necessary to pull out each layer for cleaning every time, which reduces the workload of cleaning and reduces the pollution to the on-site working environment. The curved bottom drawer is the deepest and has a high content, so it is not easy to cause overflow. Steam can be introduced into the cleaning box jacket to increase the temperature of the cleaning box cavity to avoid blockage caused by solidification of the medium. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] The present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments. The accompanying drawings are only provided for reference and explanation and are not intended to limit the present invention.
[0023] Figure 1 The figure is a flow chart of the flexible production system of the polyester product of the present invention.
[0024] Figure 2 It is a detailed flow chart of the second-line slurry preparation tank in the present invention.
[0025] Figure 3 for Figure 2 Cross-sectional view of the liquid distributor.
[0026] Figure 4 Flow chart of the vacuum system in the present invention.
[0027] Figure 5 It is a flow chart of the scraper spray system in the present invention.
[0028] Figure 6 for Figure 5 Front view of the medium heat well.
[0029] Figure 7 for Figure 6 Top view after removing the atmospheric legs.
[0030] Figure 8 for Figure 7 Sectional view along AA.
[0031] Fig. 9 for Figure 6 A partial enlarged view of the .
[0032] Fig.10 for Figure 5 Front view of the cleaning box.
[0033] Fig.11 for Fig.10 Left view of .
[0034] In the figure: 1-1. Slurry preparation tank of the first line; 1-2. Slurry preparation tank of the second line; 1a. Powder inlet; 1b. Spray column; 1c. Liquid material distributor; 1c1. Distributor sealing plate; 1c2. Triangular tail gas outlet; 1c3. Slit-shaped discharge port; 1d. Cyclone separator; 1e. Induced draft fan; 2a. One kettle of esterification of the first line; 2b. One kettle of esterification of the second line; 3a. Two kettles of esterification of the first line; 3b. Two kettles of esterification of the second line; 4a. Precondensation kettle of the first line; 4b. Precondensation kettle of the second line; 5a. Two kettles of polycondensation of the first line; 5b . Second line polycondensation kettle; 6a. First line final polycondensation kettle; 6b. Second line final polycondensation kettle; 7. Scraper condenser; 7a. Scraper condenser one; 7b. Scraper condenser two; 7c. Scraper condenser three; 8. Hot well; 8a. Hot well slag outlet; 8b. Hot well EG outlet; 8c. Hot well material level meter outlet; 8d. Hot well temperature meter outlet; 8e. Hot well top cover; 8e1. Hot well manhole cover; 8f. Longitudinal partition; 8g. Horizontal wall panel; 8h1. Left inner chamber; 8h2. Right inner chamber; 8j1. Left outer chamber; 8j2. Right Outer chamber; 8k. Sealing seat; 8k1. Packing; 8k2. Packing gland; 8m. Filter plate; 8m1. Filter plate handle; 8n. Curved filter basket; 8n1. Filter basket handle; 8p. Conical hopper; 8q. Atmospheric leg; 9. Vacuum catcher; 10. Vacuum collecting tank; 11. Cleaning box; 11a. Cleaning box feed port; 11b. Cleaning box exhaust port; 11c. Cleaning box drain port; 11d. Cleaning box cover; 11e. Cleaning box jacket; 11e1. Cleaning box jacket lower interface; 11e2. Jacket upper interface Interface; 11f. Square filter drawer; 11g. Curved bottom drawer; 11h. Roller; 11j. Guide chute; 11k. Searchlight port; 11m. Glass mirror observation port; 11n. Multi-pipeline interface; 12a. Process tower 1; 12b. Process tower 2; 13a. First line pelletizer; 13b. Second line pelletizer; 14a. First line spinning equipment; 14b. Second line spinning equipment; G1. EG feed pipe; G2. Catalyst feed pipe; G3a. PTA feed pipe; G3b. IPA feed pipe; G4. Auxiliary material supply pipe; G5. Third-stage vacuum pipe; G6a. Second-stage vacuum pipe; G6b. Second-stage auxiliary vacuum pipe; G7. First-stage vacuum pipe; G8. EG circulation pipe; G9. EG steam pipe; G10. Nitrogen pipe; G11a. Heat medium oil supply pipe; G11b. Heat medium oil return pipe; B1a. Slurry delivery pump 1; B1b. Slurry delivery pump 2; B2a. Esterification material delivery pump 1; B2b. Esterification material delivery pump 2; B3a. EG reflux pump 1; B3b.EG reflux pump 2; B4a. Melt delivery pump 1; B4b. Melt delivery pump 2; B5. Spray circulation pump; C1. Cooler; P1. First-stage steam jet pump; P2. Second-stage steam jet pump; P3. Second-stage semi-steam jet pump; P4. Third-stage steam jet pump; P5. Liquid ring pump; J1. First-stage spray tank; J2. Second-stage spray tank; J3. Third-stage spray tank; LT1. Preparation tank level gauge; LT2. Catcher level gauge; F1.EG flow meter; F2. Catalyst flow meter; V1. EG flow control valve; V2. Catalyst flow control valve; V3. Rotary feeding valve; V4. Electric shut-off valve; V5. Nitrogen valve; V6. Collection tank discharge valve; V7. Flushing valve. DETAILED DESCRIPTION
[0035] like Figure 1 As shown, the flexible production system of the polyester product of the present invention comprises an esterification polycondensation line and an esterification polycondensation line. The esterification polycondensation line comprises a first-line slurry preparation tank 1-1, a first-line esterification kettle 2a, a second-line esterification kettle 3a, a first-line pre-polycondensation kettle 4a, a first-line polycondensation kettle 5a and a first-line final polycondensation kettle 6a which are sequentially connected in series. The discharge port of the first-line final polycondensation kettle 6a is connected to a first-line pelletizer 13a or a first-line spinning device 14a through a melt delivery pump 1B4a. The esterification polycondensation line 2 comprises a second-line slurry preparation tank 1-2, a second-line esterification kettle 2b, a second-line esterification kettle 3b, a second-line pre-polycondensation kettle 4b, a second-line polycondensation kettle 5b and a second-line final polycondensation kettle 6b which are sequentially connected in series. The discharge port of the second-line final polycondensation kettle 6b is connected to a second-line pelletizer 13b or a first-line spinning device 14a through a melt delivery pump 1B4b. The second-line spinning equipment 14b is connected; the PTA feeding pipe G3a is connected to the top of the first-line slurry preparation tank 1-1, and the IPA feeding pipe G3b is connected to the top of the second-line slurry preparation tank 1-2; the bottom outlet of the first-line esterification kettle 2a is installed with an esterification material delivery pump B2a, and the bottom outlet of the second-line esterification kettle 2b is installed with an esterification material delivery pump B2b, the outlet branch one of the esterification material delivery pump B2a is connected to the feed port of the first-line esterification kettle 3a, the outlet branch two of the esterification material delivery pump B2a and the outlet of the esterification material delivery pump B2b are commonly connected to the feed port of the second-line esterification kettle 3b, the second-line esterification kettle 3b is a horizontal multi-chamber structure and each chamber is respectively provided with an agitator and an auxiliary material injection port, and each auxiliary material injection port is respectively connected to the auxiliary material supply pipe G4.
[0036] EG, PTA and catalyst are uniformly stirred in the first-line slurry preparation tank 1-1, and can also be self-circulated by a slurry delivery pump B1a. After uniform mixing, they are sent to the first-line esterification kettle 2a by a slurry delivery pump B1a for esterification reaction; EG, IPA and catalyst are uniformly stirred in the second-line slurry preparation tank 1-2, and can also be self-circulated by a slurry delivery pump B1b. After uniform mixing, they are sent to the second-line esterification kettle 2b by a slurry delivery pump B1b for esterification reaction; the esterified product of the first-line esterification kettle 2a is sent out by an esterification material delivery pump B2a, and the first route enters the first-line esterification kettle 3a for further reaction. After polycondensation in the first-line pre-polycondensation kettle 4a, the first-line polycondensation kettle 5a and the first-line final polycondensation kettle 6a, it is sent to the first-line pelletizer 13a for pelletizing or to the first-line spinning equipment 14a for spinning by a melt delivery pump B4a, so as to produce traditional polyester products such as high gloss and semi-dull.
[0037] The esterified product of the second-line esterification kettle 2b is delivered by the esterification material delivery pump B2b, mixed with the second-way material at the outlet of the esterification material delivery pump B2a, and then enters the second-line esterification kettle 3b. The relevant special varieties of auxiliary materials can be added to any chamber of the second-line esterification kettle 3b through the auxiliary material supply pipe G4. Under certain pressure, temperature and stirring conditions, the esterification reaction is further carried out. After polycondensation in the second-line pre-condensation kettle 4b, the second-line polycondensation kettle 5b and the second-line final polycondensation kettle 6b, it is sent to the second-line pelletizer 13b for pelletizing or to the second-line spinning equipment 14b for spinning by the melt delivery pump B4b, and special products such as cationic, flame retardant, high shrinkage or bottle flakes can be produced. Only one line can be operated, or the first and second lines can be operated at the same time. The production ratio of the two lines can be flexibly adjusted. When producing special products, it does not affect the production of conventional products and avoids conversion losses.
[0038] The outlet of the esterification material delivery pump B2a is also connected to the top circulation port of the first-line esterification kettle 2a through the esterification circulation pipe. The esterified product with a qualified esterification rate discharged from the first-line esterification kettle 2a is returned to the first-line esterification kettle 2a for circulation through the esterification material delivery pump B2a and the esterification circulation pipe, which speeds up the reaction rate in the first-line esterification kettle 2a, shortens the reaction time of the first-line esterification, and makes the material more uniform.
[0039] The outlet of the esterification material delivery pump B2b is also connected to the top circulation port of the second-line esterification kettle 2b through the esterification circulation pipe 2. The esterified product with qualified esterification rate discharged from the second-line esterification kettle 2b is returned to the second-line esterification kettle 2b through the esterification material delivery pump B2b and the esterification circulation pipe 2 for circulation, which speeds up the reaction rate in the second-line esterification kettle 2b, shortens the reaction time of the second-line esterification, and makes the material more uniform.
[0040] The exhaust ports of the first-line esterification kettle 2a, the second-line esterification kettle 3a and the second-line esterification kettle 2b are connected to the air inlet of the process tower 12a. The bottom of the process tower 12a is equipped with an EG reflux pump B3a. The outlet of the EG reflux pump B3a is connected to the top reflux ports of the first-line esterification kettle 2a, the second-line esterification kettle 3a and the second-line esterification kettle 2b through an EG reflux pipe. The EG and water vapor discharged from the exhaust ports of the first-line esterification kettle 2a, the second-line esterification kettle 3a and the second-line esterification kettle 2b enter the process tower 12a for rectification. The EG at the bottom of the process tower 12a is refluxed to the first-line esterification kettle 2a, the second-line esterification kettle 3a and the second-line esterification kettle 2b through the EG reflux pump B3a.
[0041] The exhaust port of the second-line esterification kettle 3b is connected to the air inlet of the second process tower 12b. The bottom of the second process tower 12b is equipped with an EG reflux pump 2B3b, and the outlet of the EG reflux pump 2B3b is connected to the top reflux port of the second-line esterification kettle 3b through an EG reflux pipe. Since special materials are added to the second-line esterification kettle 3b, it is independently equipped with a second process tower 12b to distill the EG and water vapor discharged from the second-line esterification kettle 3b.
[0042] like Figure 2 , Figure 3 As shown, the powder inlet 1a at the top of the second-line slurry preparation tank 1-2 is connected to the IPA feed pipe G3b, and a spray column 1b extending vertically is also installed on the top of the second-line slurry preparation tank 1-2, and the top of the spray column 1b is connected to the preparation tank exhaust pipe, and the outlet of the preparation tank exhaust pipe is connected to the air inlet of the cyclone separator 1d, and the top exhaust port of the cyclone separator 1d is connected to the induced draft fan 1e, and the bottom outlet of the cyclone separator 1d is connected to the reflux port at the top of the second-line slurry preparation tank 1-2 through the separator return valve and the powder reflux pipe; the inner cavity of the spray column 1b is provided with an EG nozzle and a catalyst nozzle from top to bottom, and the EG nozzle is connected to the EG feed pipe. G1 is connected, and the catalyst nozzle is connected to the catalyst feed pipe G2; the lower end of the spray column 1b is inserted into the inner cavity of the second-line slurry preparation tank 1-2 and is connected to the liquid distributor 1c, the top of the middle section of the liquid distributor 1c is connected to the lower port of the spray column 1b and extends symmetrically along the radial direction of the second-line slurry preparation tank 1-2 with the axis of the spray column as the center, the vertical cross-section of the liquid distributor 1c is rhombus-shaped, and distributor sealing plates 1c1 are respectively provided in the middle and lower parts of the two ends of the liquid distributor 1c, and triangular exhaust gas outlets 1c2 are respectively provided above the two distributor sealing plates 1c1, and a slit-shaped discharge port 1c3 of the same length as the liquid distributor 1c is provided at the lower end of the liquid distributor 1c.
[0043] Low-temperature EG enters the spray column 1b from the EG feed pipe G1 and is sprayed downward from the EG nozzle; high-temperature catalyst enters the spray column 1b from the catalyst feed pipe G2 and is sprayed downward from the catalyst nozzle; since the catalyst has a high temperature and a small flow rate, and the EG has a low temperature and a large flow rate, the catalyst nozzle is closer to the second-line slurry preparation tank 1-2, and the EG nozzle is arranged above the catalyst nozzle. During the downward spraying process, EG is mixed with the catalyst solution and falls into the middle section of the liquid material distributor 1c together. During the flow to both ends, the material is discharged along the slit shape. Port 1c3 distributes liquid downward, and the liquid level in the liquid distributor 1c is lower than the height of the distributor sealing plate 1c1; IPA powder falls into the second-line slurry preparation tank 1-2 from the IPA feed pipe G3b and the powder inlet 1a, and is easier to mix with the EG and catalyst evenly distributed along the radius under the action of the preparation tank agitator. The evenly mixed slurry enters the slurry delivery pump 2 B1b from the bottom of the second-line slurry preparation tank 1-2, and the slurry delivery pump 2 B1b delivers the prepared slurry to the second-line esterification kettle 2b through the slurry output pipe for esterification reaction. Under the suction action of the induced draft fan 1e, the second-line slurry preparation tank 1-2 maintains a slightly negative pressure state, which is convenient for the discharge of IPA powder and prevents the powder from overflowing due to positive pressure. The tail gas enters the upper part of the inner cavity of the liquid distributor 1c from the two triangular tail gas outlets 1c2, and goes upward into the spray column 1b. The floating IPA powder passes through the two-stage spraying of the catalyst nozzle and the EG nozzle during the upward process. Most of the IPA powder is captured and falls back into the second-line slurry preparation tank 1-2, reducing the dust content in the tail gas. A small amount of IPA powder enters the cyclone separator 1d for separation. When the IPA powder deposited at the bottom of the cyclone separator 1d accumulates to a certain amount, the separator return valve is opened and the powder returns to the second-line slurry preparation tank 1-2 through the powder reflux pipe, so that it can be fully reused, which not only reduces the loss of raw materials, but also improves the on-site working environment and avoids environmental pollution.
[0044] The long diagonal line of the liquid distributor 1c extends along the vertical plane where the axis of the spray column is located, and the angle between the two top surfaces of the liquid distributor 1c is 30°, so that the powder falling on the top surface of the liquid distributor 1c can easily slide down and avoid accumulation on the upper surface of the liquid distributor 1c.
[0045] The greater the distance from the spray column axis, the wider the slot of the slot-shaped discharge port 1c3. The slot directly below the spray column 1b is easier to drop material, and the wider the slot with a longer flow distance, the more conducive to uniform material drop in the radial direction of the slurry preparation tank.
[0046] like Figure 2As shown, a preparation tank level gauge LT1 is installed at the bottom of the second-line slurry preparation tank 1-2, a rotary feeding valve V3 is provided on the IPA feeding pipe G3b, an EG flowmeter F1 and an EG flow control valve V1 are installed on the EG feeding pipe G1, and a catalyst flowmeter F2 and a catalyst flow control valve V2 are installed on the catalyst feeding pipe G2. The openings of the EG flow control valve V1 and the catalyst flow control valve V2 are both controlled by the flow of the rotary feeding valve V3, and the flow of the rotary feeding valve V3 is controlled by the second-line slurry preparation tank level measured by the preparation tank level gauge LT1. When the flow of IPA increases, the openings of the EG flow control valve V1 and the catalyst flow control valve V2 increase in proportion, which can keep an accurate molar ratio of EG, catalyst and IPA, and make the preparation quality of the slurry higher.
[0047] The first-line slurry preparation tank 1-1 can adopt a traditional structure, or can adopt the same structure and process as the second-line slurry preparation tank 1-2. The powder inlet at the top of the first-line slurry preparation tank 1-1 is connected to the PTA feed pipe G3a.
[0048] like Figure 4 As shown, the gas phase outlet of the second-line pre-polycondensation kettle 4b is connected to the air inlet of the scraper condenser 1 7a, the gas phase outlet of the second-line polycondensation kettle 5b is connected to the air inlet of the scraper condenser 2 7b, the gas phase outlet of the second-line final polycondensation kettle 6b is connected to the air inlet of the scraper condenser 3 7c, the top exhaust port of the scraper condenser 3 7c is connected to the suction port of the first-level steam jet pump P1 through the first-level vacuum pipe G7, the top exhaust port of the scraper condenser 2 7b is connected to the suction port of the second-level semi-steam jet pump P3 through the second-level vacuum pipe G6a, the top exhaust port of the scraper condenser 1 7a is connected to the suction port of the liquid ring pump P5 through the third-level vacuum pipe G5 and the vacuum regulating valve, the outlet of the first-level steam jet pump P1 is connected to the air inlet of the first-level spray tank J1, the first-level spray tank The exhaust port of J1 is connected to the suction port of the secondary steam jet pump P2, the outlets of the secondary steam jet pump P2 and the secondary semi-steam jet pump P3 are both connected to the air inlet of the secondary spray tank J2, the exhaust port of the secondary spray tank J2 is connected to the suction port of the tertiary steam jet pump P4, the outlet of the tertiary steam jet pump P4 is connected to the air inlet of the tertiary spray tank J3, and the exhaust port of the tertiary spray tank J3 is connected to the suction port of the liquid ring pump P5; the top exhaust port of the scraper condenser 7b is also connected to the primary spray tank J1 through the secondary auxiliary vacuum pipe G6b, and an EG ring pipe is provided on the inner wall of the secondary auxiliary vacuum pipe G6b at a certain interval, and nozzles are evenly distributed on the circumference of the EG ring pipe, and each EG ring pipe is connected to the EG circulation pipe G8 of the scraper condenser 7b.
[0049] The vacuum requirement of the second-line precondensation reactor 4b is not high, generally 8-15KPa (A), and the inlet vacuum of the liquid ring pump P5 after the vacuum jet unit can be controlled at 5-20KPa, which can meet the vacuum requirement of the second-line precondensation reactor 4b. Therefore, the exhaust port of the scraper condenser 7a is directly connected to the liquid ring pump P5 after the vacuum jet unit through a regulating valve, canceling the original independent liquid ring pump of the second-line precondensation reactor 4b, reducing the equipment investment cost and the occupation of the workshop area. The vacuum of the second-line polycondensation reactor 5b is generally 0.8-1.5KPa (A), and the vacuum of the first-level spray tank J1 is below 0.8KPa (A). The exhaust port of the scraper condenser 7b is increased by a second-level auxiliary vacuum pipe G6b connected to the first-level spray tank J1, and a regulating valve is installed on the second-level auxiliary vacuum pipe G6b. The vacuum degree of the second-line polycondensation reactor 5b is directly adjusted by the opening of the regulating valve, which can fully meet the vacuum requirements of the second-line polycondensation reactor 5b. When the original secondary vacuum pipe G6a is blocked and needs to be flushed, it can be switched to the secondary auxiliary vacuum pipe G6b, so that the original secondary vacuum pipe G6a and the secondary auxiliary vacuum pipe G6b can serve as backup for each other to maintain the vacuum degree of the second line polycondensation kettle 5b stable. The EG circulation pipe G8 of the scraper condenser 2 7b is used to provide EG spray liquid to the nozzle of the EG ring pipe to achieve online annular spraying, which can further capture particles and condensable gases in the tail gas, reduce the load of the vacuum unit, and avoid the blockage of the secondary auxiliary vacuum pipe G6b, making the vacuum system more stable. The spray liquid of the EG ring pipe flows back to the scraper condenser 2 7b with the help of the slope of the secondary auxiliary vacuum pipe G6b. The vacuum degree of the second line final polycondensation kettle 6b is generally 100-200Pa (A), so the top exhaust port of the scraper condenser 3 7c is connected to the primary steam jet pump P1 with the largest suction force through the primary vacuum pipe G7. Since the diameter of the primary vacuum pipe G7 is large, it is not easy to be blocked.
[0050] The end of the secondary vacuum pipe G6a is connected to the EG steam pipe G9 through a flushing valve V7. By opening the flushing valve V7 regularly, the EG steam can be used to clean the secondary vacuum pipe G6a and the secondary semi-steam jet pump P3 to eliminate blockage.
[0051] like Figure 5As shown, the gas phase outlets of the second-line pre-polycondensation kettle 4b, the second-line polycondensation kettle 5b and the second-line final polycondensation kettle 6b are respectively connected to the side wall inlet of the corresponding vacuum catcher 9, the top gas phase outlet of each vacuum catcher 9 is respectively connected to the air inlet of the corresponding scraper condenser 7, the bottom outlet of each vacuum catcher 9 is respectively connected to the top inlet of the corresponding vacuum collecting tank 10 through an electric shut-off valve V4, the top air inlet of each vacuum collecting tank 10 is also connected to the nitrogen pipe G10 through a nitrogen valve V5, and a collecting tank discharge valve V6 is provided at the bottom of each vacuum collecting tank 10; the medium outlet of each scraper condenser 7 is respectively connected to the corresponding hot well 8 through an atmospheric leg, the EG outlet of each hot well 8 is respectively connected to the inlet of a spray circulation pump B5, the outlet of each spray circulation pump B5 is connected to the inlet of a cooler C1, and the outlet of each cooler C1 is respectively connected to the spray port of the corresponding scraper condenser 7 through an EG circulation pipe G8.
[0052] After the mixture of EG, water and oligomers is discharged from the gas phase outlet of the polycondensation reactor, it first enters the vacuum catcher 9. Due to the reduction of gas velocity, under the action of gravity, the liquid oligomers are retained at the bottom of the vacuum catcher 9, and EG, water and a small amount of oligomers enter the scraper condenser 7 for spraying and replenishment. The condensed oligomers are discharged from the medium outlet of the scraper condenser 7 along with EG, enter the hot well 8 for filtration through the atmospheric leg, and the spray liquid EG is pumped out by the circulating pump, cooled by the cooler C1, and then returned to the spray port of the scraper condenser 7 for circulating spraying. When the vacuum catcher 9 accumulates to a certain liquid level, the electric shut-off valve V4 is opened, the nitrogen in the vacuum collection tank 10 enters the vacuum catcher 9 and is discharged from its gas phase outlet, and the liquid oligomer enters the vacuum collection tank 10 for storage. After a certain amount is stored, the nitrogen valve V5 of the vacuum collection tank 10 is opened to fill the vacuum collection tank 10 with nitrogen, and the collection tank discharge valve V6 at the bottom of the vacuum collection tank 10 is opened to discharge the liquid oligomer into the collection tank. After the discharge is completed, nitrogen is continued to be introduced for about 10 seconds to nitrogen seal the vacuum collection tank 10, and then the nitrogen valve V5 is closed. Since most of the oligomers are collected by the vacuum catcher 9, the spray liquid flow required by the scraper condenser will be greatly reduced, reducing energy consumption, and the stability of the vacuum system will be greatly improved; in addition, the amount of residue discharged from the scraper condenser into the hot well 8 will be greatly reduced, the stability of the scraper operation will be improved, and the service life of the scraper will be greatly extended.
[0053] The outer walls of the vacuum catcher 9 and the vacuum collection tank 10 are respectively wound with half-tube heaters, the lower inlets of the two half-tube heaters are respectively connected to the heat medium oil supply pipe G11a, and the upper outlets of the two half-tube heaters are respectively connected to the heat medium oil return pipe G11b. By heating the heat medium, the vacuum catcher 9 and the vacuum collection tank 10 can be kept above the melting point of various media, ensuring that various media maintain fluidity and avoiding solidification blockage.
[0054] The middle section of the side wall of the vacuum trap 9 is equipped with a trap level gauge LT2. The opening and closing of the electric shut-off valve V4 is controlled by the trap level gauge LT2. The vacuum collection tank 10 is equipped with a pressure sensor. When the liquid level in the vacuum trap 9 reaches the height of the trap level gauge LT2, the electric shut-off valve V4 opens to drain the liquid. The pressure of the vacuum collection tank 10 can be observed through the pressure sensor to determine the completion of its nitrogen sealing and the formation of negative pressure.
[0055] The esterification polycondensation line 1 can use the traditional vacuum pumping system, or can use the same vacuum pumping system as the esterification polycondensation line 2.
[0056] like Figure 6 , Figure 7 , Figure 8 and Fig. 9 As shown, a hot well cover 8e is provided on the top of the hot well 8, and a longitudinal partition 8f is provided along the longitudinal axis of the hot well 8 to divide the hot well cavity into left and right halves. A left inner chamber 8h1 and a right inner chamber 8h2 are symmetrically provided on both sides of the middle section of the longitudinal partition 8f. Transverse wall panels 8g are provided at the front and rear of the left inner chamber 8h1 and the right inner chamber 8h2, respectively. The outer space of the left inner chamber 8h1 is the left outer chamber 8j1, and the outer space of the right inner chamber 8h2 is the right outer chamber 8j2. Conical hoppers 8p are provided at the bottom of the left inner chamber 8h1 and the right inner chamber 8h2, respectively. The lowest points of the two conical hoppers 8p are connected to hot well slag discharge ports 8a, respectively. The two hot well slag discharge ports 8a extend downward to the outside of the bottom of the hot well 8 and are respectively connected to the cleaning box 11.
[0057] A hot well EG outlet 8b is respectively provided at the bottom of the left outer chamber 8j1 and the right outer chamber 8j2; two air legs 8q are inserted on the hot well top cover 8e, and the lower ends of the two air legs 8q are respectively inserted into the lower parts of the inner cavities of the left inner chamber 8h1 and the right inner chamber 8h2; an overflow port communicating with the corresponding outer chamber is respectively provided at the upper part of each horizontal wall panel 8g, and the inner port of each overflow port is respectively covered with a filter plate 8m, and the left and right sides of each filter plate 8m are respectively inserted into the vertical slots on the inner end face of the horizontal wall panel 8g; the outer port of each overflow port is respectively covered with an outwardly convex arc filter basket 8n, and the left and right sides of each arc filter basket 8n are respectively inserted into the vertical slots on the outer end face of the horizontal wall panel 8g.
[0058] EG and a small amount of oligomers flow into the lower part of the left inner chamber 8h1 through the valve and pipeline at the bottom of the scraper condenser through the left atmospheric leg 8q, which plays a liquid sealing role at the same time. EG flows upward through the filter plate 8m for the first filtration and then flows out, enters the inner cavity of the arc filter basket 8n, and enters the left outer chamber 8j1 after secondary filtration by the arc filter basket 8n, flows out from the hot well EG outlet 8b at the bottom of the left outer chamber 8j1, is pumped out by the circulating pump B5, and is sent to the scraper condenser for circulation spraying after cooling. Impurities such as oligomers are blocked in the left inner chamber 8h1, fall into the conical hopper 8p, and are discharged from the hot well slag outlet 8a and enter the cleaning box 11. If the left atmospheric leg 8q is blocked, it can be immediately switched to the right atmospheric leg 8q to work, and the hot well EG outlet 8b and the hot well slag outlet 8a are also switched to work on the right side, so that the spray system can operate long-term and stably, ensuring the normal operation of the polymerization device, avoiding parking due to the blockage of the atmospheric leg 8q, greatly reducing losses, and ensuring normal production operation.
[0059] The filter plate 8m is used for the first filtration to intercept larger impurities. The filter plate 8m of the present invention is close to the top of the vacuum seal tank, which is convenient for pulling out the filter plate 8m for cleaning and also for reinstalling. The convex arc filter basket 8n increases both the filtration area and the container space; the edges of the filter plate 8m and the left and right sides of the arc filter basket 8n are embedded in the vertical slots, which are convenient for pulling out, cleaning and assembly.
[0060] Each arc filter basket 8n extends to the lower part of the corresponding outer chamber, and the arc surface and bottom of each arc filter basket 8n are provided with filter screens, which further increases the filtering area of the arc filter basket 8n, so that the arc filter basket 8n only needs to be cleaned once after the system has been working for several days, thus reducing the cleaning workload.
[0061] Two hot well manhole covers 8e1 are symmetrically arranged at the position far away from the longitudinal partition 8f on the horizontal axis of the hot well top cover 8e, and each pair of filter plates 8m and arc filter baskets 8n are respectively located below the openings of the hot well manhole covers 8e1. When the hot well manhole cover 8e1 is opened, the filter plates 8m and arc filter baskets 8n can be pulled out for cleaning, and the filter plates 8m and arc filter baskets 8n can be inserted back after cleaning, and then the hot well manhole cover 8e1 is reset, avoiding the overall disassembly of the hot well top cover 8e, and reducing the workload during cleaning.
[0062] The tops of the filter plates 8m and the arc filter basket 8n are provided with handles respectively. The filter plates 8m can be easily inserted and pulled out through the filter plate handles 8m1, and the arc filter basket 8n can be easily inserted and pulled out through the filter basket handles 8n1.
[0063] The left inner chamber 8h1, the right inner chamber 8h2, the left outer chamber 8j1 and the right outer chamber 8j2 are respectively provided with hot well material level meter ports 8c, which can display and monitor the material levels of the inner and outer chambers in real time on the DCS. When the atmospheric leg 8q is blocked, the DCS will issue an alarm message in real time, so that the DCS personnel can quickly arrange on-site personnel to deal with it.
[0064] The bottom of both sides of the hot well 8 are provided with hot well thermometer ports 8d, which can display the temperature of EG in real time on the DCS.
[0065] The two air legs 8q are located on both sides of the longitudinal partition 8f, and pass through the central hole of the sealing seat 8k respectively. The two sealing seats 8k are welded on the hot well top cover 8e respectively. The stuffing box between the outer wall of the air leg 8q and the inner wall of the sealing seat is provided with a packing 8k1 respectively. The upper part of the packing 8k1 is provided with a packing gland 8k2 respectively. The flange of the packing gland 8k2 is connected to the flange of the sealing seat 8k through a gland screw. Tighten the gland screw, and the packing 8k1 is pressed tightly in the stuffing box through the packing gland 8k2, which is not only sealed on the outer periphery of the air leg 8q, but also can ensure that the air leg 8q can slide freely vertically, and can automatically adapt to the expansion and contraction caused by the temperature change of the system.
[0066] like Fig.10 , Fig.11 As shown, the cleaning box 11 includes a horizontal cylinder with one end closed, a front port of the cleaning box 11 is hinged with a cleaning box cover 11d that can be opened and closed, the outer periphery of the cylinder of the cleaning box 11 is covered with a cleaning box jacket 11e, and the inner cavity of the cleaning box 11 is provided with a plurality of square filter drawers 11f stacked in sequence from top to bottom, and the frames on the left and right sides of each square filter drawer 11f are respectively supported in a guide slot 11j by a roller 11h, and each guide slot 11j extends along the axial direction of the cleaning box 11 and is respectively fixed on both sides of the inner wall of the cleaning box 11, and the bottom of the inner cavity of the cleaning box 11 is provided with an arc bottom drawer 11f. 1g, the bottom of the arc-shaped bottom drawer 11g is supported on the bottom of the inner wall of the cleaning box 11 through a roller 11h, and the bottoms of the arc-shaped bottom drawer 11g and each square filter drawer 11f are respectively provided with filter screens, and the mesh number of the lower filter screen is successively larger than the mesh number of the upper filter screen, and a cleaning box feed port 11a and a cleaning box exhaust port 11b are provided at the top of the cleaning box 11, the upper end of the cleaning box feed port 11a is connected to the hot well slag discharge port 23a, and the lower end of the cleaning box feed port 11a points to the central area of the top square filter drawer 11f, and a cleaning box discharge port 11c is provided at the bottom center of the cleaning box 11.
[0067] The frame of each drawer is erected upward to prevent the mixture from overflowing from the surrounding of the filter screen. The guide chute 11j is convenient for the square filter drawer 11f to be drawn out, cleaned and put back, and can ensure that each square filter drawer 11f is in a horizontal state. The arc bottom drawer 11g is located at the arc bottom of the cleaning box 11 and is in a stable and balanced state. The guide chute 11j can be omitted and it can be directly supported on the arc bottom of the cleaning box 11 by the roller 11h. The mixture of oligomer and EG enters the inner cavity of the cleaning box 11 from the cleaning box feed port 11a, and first falls on the square filter drawer 11f on the top layer to perform a rough filtration on the mixture. The mesh of the top filter screen is large and has a strong liquid permeability, so it will not be blocked and cause overflow. The largest slag is intercepted, and the slightly smaller slag all falls into the next layer for further filtration. In this way, the filtration accuracy is improved layer by layer, and the finest slag is intercepted by the arc bottom drawer 11g. After multiple layers of step-by-step filtration, the clean EG is discharged from the cleaning box discharge port 11c at the bottom of the cleaning box 11. By opening the cleaning box cover 11d, the square filter drawer 11f or the curved bottom drawer 11g can be pulled out for cleaning. Since the curved bottom drawer 11g has the smallest holes and is most likely to be clogged, the frequency of cleaning can be higher than that of other square filter drawers 11f. It is not necessary to pull out each layer for cleaning every time, thereby reducing the workload of cleaning and reducing the pollution to the on-site working environment. The curved bottom drawer 11g is the deepest and has a high content, so it is not easy to cause overflow.
[0068] A searchlight port 11k and a glass mirror observation port 11m are respectively provided on the left and right sides of the cleaning box exhaust port 11b. Light is emitted from the searchlight port 11k, and the internal retention state can be observed from the glass mirror observation port 11m on the other side, so as to accurately determine the cleaning time.
[0069] The bottom of the cleaning box jacket 11e is connected to a cleaning box jacket lower interface 11e1, and the top of the cleaning box jacket 11e is connected to a jacket upper interface 11e2, so that steam can be introduced into the cleaning box jacket 11e, and the steam enters from the top jacket upper interface 11e2, and condensed water is discharged from the bottom cleaning box jacket lower interface 11e1 to increase the temperature of the inner cavity of the cleaning box 11 and avoid blockage caused by medium solidification.
[0070] The top of the cleaning box 11 is also provided with a multi-pipe interface 11n, which can be used for pressure measurement, replenishing liquid or inert gas protection, etc.
Claims
1. A flexible production system for polyester products, comprising an esterification polycondensation line, wherein the esterification polycondensation line comprises a slurry preparation tank, a first esterification kettle, a second esterification kettle, a pre-polycondensation kettle, a second polycondensation kettle and a final polycondensation kettle connected in series, wherein the discharge port of the final polycondensation kettle is connected to a pelletizer or a spinning device via a melt delivery pump, characterized in that: The second esterification polycondensation line includes a second-line slurry preparation tank, a second-line esterification kettle, a second-line esterification kettle, a second-line pre-polycondensation kettle, a second-line polycondensation kettle and a second-line final polycondensation kettle connected in series in sequence. The discharge port of the second-line final polycondensation kettle is connected to a second-line pelletizer or a second-line spinning device through a melt delivery pump 2; a PTA feed pipe is connected to the top of the first-line slurry preparation tank, and an IPA feed pipe is connected to the top of the second-line slurry preparation tank; the bottom of the first-line esterification kettle is connected to the bottom of the second-line esterification kettle. The outlet of the first esterification material delivery pump is installed at the bottom, and the outlet of the second-line esterification kettle is installed at the bottom outlet. The outlet branch of the first esterification material delivery pump is connected to the feed inlet of the first-line esterification kettle, and the outlet branch of the first esterification material delivery pump and the outlet of the second esterification material delivery pump are connected to the feed inlet of the second-line esterification kettle. The second-line esterification kettle is a horizontal multi-chamber structure, and each chamber is respectively provided with a stirrer and an auxiliary material injection port, and each auxiliary material injection port is respectively connected to an auxiliary material supply pipe; The powder inlet at the top of the second-line slurry preparation tank is connected to the IPA feed pipe, and a spray column extending vertically is also installed on the top of the second-line slurry preparation tank. The top of the spray column is connected to the preparation tank exhaust pipe, and the outlet of the preparation tank exhaust pipe is connected to the air inlet of the cyclone separator. The top exhaust port of the cyclone separator is connected to the induced draft fan, and the bottom outlet of the cyclone separator is connected to the reflux port at the top of the second-line slurry preparation tank through the separator return valve and the powder reflux pipe; the inner cavity of the spray column is provided with an EG nozzle and a catalyst nozzle in sequence from top to bottom, and the EG nozzle The head is connected to the EG feeding pipe, and the catalyst nozzle is connected to the catalyst feeding pipe; the lower end of the spray column is inserted into the inner cavity of the second-line slurry preparation tank and is connected to a liquid distributor, the top of the middle section of the liquid distributor is connected to the lower port of the spray column and extends symmetrically along the radial direction of the second-line slurry preparation tank with the axis of the spray column as the center, the vertical cross-section of the liquid distributor is rhombus-shaped, and distributor sealing plates are respectively provided in the middle and lower parts of the two ends of the liquid distributor, and triangular exhaust gas outlets are respectively provided above the two distributor sealing plates, and a slit-shaped discharge port equal to the length of the liquid distributor is provided at the lower end of the liquid distributor.
2. The flexible production system for polyester products according to claim 1, characterized in that: The outlet of the esterification material delivery pump 1 is also connected to the top circulation port of the first-line esterification kettle through the esterification circulation pipe 1; the outlet of the esterification material delivery pump 2 is also connected to the top circulation port of the second-line esterification kettle through the esterification circulation pipe 2.
3. The flexible production system for polyester products according to claim 1, characterized in that: The exhaust ports of the first-line esterification kettle, the second-line esterification kettle and the first-line esterification kettle are commonly connected to the air inlet of the first process tower; an EG reflux pump one is installed at the bottom of the first process tower, and the outlet of the EG reflux pump one is connected to the top reflux ports of the first-line esterification kettle, the second-line esterification kettle and the first-line esterification kettle through an EG reflux pipe; the exhaust port of the second-line esterification kettle is connected to the air inlet of the second process tower; an EG reflux pump two is installed at the bottom of the second process tower, and the outlet of the EG reflux pump two is connected to the top reflux port of the second-line esterification kettle through an EG reflux pipe.
4. The flexible production system for polyester products according to claim 1, characterized in that: The long diagonal line of the liquid distributor extends along the vertical plane where the axis of the spray column is located, and the angle between the two top surfaces of the liquid distributor is 30°; the greater the distance from the axis of the spray column, the wider the slit of the slit-shaped discharge port.
5. The flexible production system for polyester products according to claim 1, characterized in that: A preparation tank level gauge is installed at the bottom of the second-line slurry preparation tank, a rotary feeding valve is provided on the IPA feed pipe, an EG flowmeter and an EG flow control valve are installed on the EG feed pipe, and a catalyst flowmeter and a catalyst flow control valve are installed on the catalyst feed pipe. The openings of the EG flow control valve and the catalyst flow control valve are both controlled by the flow of the rotary feeding valve, and the flow of the rotary feeding valve is controlled by the liquid level of the second-line slurry preparation tank measured by the preparation tank level gauge.
6. The flexible production system for polyester products according to any one of claims 1 to 5, characterized in that: The gas phase outlet of the second-line pre-polycondensation kettle is connected to the air inlet of the scraper condenser one, the gas phase outlet of the second-line polycondensation kettle is connected to the air inlet of the scraper condenser two, the gas phase outlet of the second-line final polycondensation kettle is connected to the air inlet of the scraper condenser three, the top exhaust port of the scraper condenser three is connected to the suction port of the first-level steam jet pump through the first-level vacuum pipe, the top exhaust port of the scraper condenser two is connected to the suction port of the second-level semi-steam jet pump through the second-level vacuum pipe, the top exhaust port of the scraper condenser one is connected to the suction port of the liquid ring pump through the third-level vacuum pipe and the vacuum regulating valve, the outlet of the first-level steam jet pump is connected to the air inlet of the first-level spray tank, the exhaust port of the first-level spray tank is connected to the suction port of the second-level semi-steam jet pump. The outlet of the scraper condenser II is connected to the suction port of the secondary steam jet pump, the outlets of the secondary steam jet pump and the secondary semi-steam jet pump are both connected to the air inlet of the secondary spray tank, the exhaust port of the secondary spray tank is connected to the suction port of the tertiary steam jet pump, the outlet of the tertiary steam jet pump is connected to the air inlet of the tertiary spray tank, and the exhaust port of the tertiary spray tank is connected to the suction port of the liquid ring pump; the top exhaust port of the scraper condenser II is also connected to the primary spray tank through a secondary auxiliary vacuum pipe, an EG ring pipe is provided on the inner wall of the secondary auxiliary vacuum pipe at a certain interval, nozzles are evenly distributed on the circumference of the EG ring pipe, and each EG ring pipe is connected to the EG circulation pipe of the scraper condenser II.
7. The flexible production system for polyester products according to claim 6, characterized in that: The gas phase outlets of the two-line pre-polycondensation kettle, the second-line polycondensation kettle and the second-line final polycondensation kettle are respectively connected to the side wall inlet of the corresponding vacuum catcher, the top gas phase outlet of each vacuum catcher is respectively connected to the air inlet of the corresponding scraper condenser, the bottom outlet of each vacuum catcher is respectively connected to the top inlet of the corresponding vacuum collecting tank through an electric shut-off valve, the top air inlet of each vacuum collecting tank is also connected to the nitrogen pipe through a nitrogen valve, and a collecting tank discharge valve is provided at the bottom of each vacuum collecting tank; the medium outlet of each scraper condenser is respectively connected to the corresponding hot well through an atmospheric leg, the EG outlet of each hot well is respectively connected to the inlet of a spray circulation pump, the outlet of each spray circulation pump is connected to the inlet of a cooler, and the outlet of each cooler is respectively connected to the spray port of the corresponding scraper condenser through an EG circulation pipe.
8. The flexible production system for polyester products according to claim 7, characterized in that: The top of the hot well is provided with a hot well cover, and a longitudinal partition is provided along the longitudinal axis of the hot well to divide the inner cavity of the hot well into left and right halves. A left inner chamber and a right inner chamber are symmetrically provided on both sides of the middle section of the longitudinal partition. The outer side of the transverse wall panel of the left inner chamber is the left outer chamber, and the outer side of the transverse wall panel of the right inner chamber is the right outer chamber. Conical hoppers are provided at the bottom of the left inner chamber and the right inner chamber, respectively. The lowest points of the two conical hoppers are respectively connected to hot well slag discharge ports, and the two hot well slag discharge ports extend downward to the outside of the bottom of the hot well, respectively. The bottoms of the left outer chamber and the right outer chamber are respectively provided with The hot well EG outlet; the two atmospheric legs are plugged into the hot well top cover, the lower ends of the two atmospheric legs are respectively inserted into the lower parts of the inner cavities of the left inner chamber and the right inner chamber, the upper part of each horizontal wall panel is respectively provided with an overflow port communicated with the corresponding outer chamber, the inner port of each overflow port is respectively covered with a filter plate, the left and right sides of each filter plate are respectively plugged into the vertical slots on the inner end face of the horizontal wall panel, the outer port of each overflow port is respectively covered with an outwardly convex arc filter basket, the left and right sides of each arc filter basket are respectively plugged into the vertical slots on the outer end face of the horizontal wall panel.
9. The flexible production system for polyester products according to claim 8, characterized in that: The two atmospheric legs are respectively located on both sides of the longitudinal partition and pass through the central hole of the sealing seat respectively. The two sealing seats are respectively welded on the hot well top cover. The stuffing boxes between the outer wall of the atmospheric leg and the inner wall of the sealing seat are respectively provided with packings. The upper part of the packing is respectively provided with a packing gland. The flange of the packing gland is connected to the flange of the sealing seat through a gland screw.
10. The flexible production system for polyester products according to claim 8, characterized in that: The hopper is a container that is hinged on the top of the container and is used for conveying information to the user. The container is sealed with a plastic bag and a plastic bag cover is provided at the bottom of the container. The container is sealed with a plastic bag and a plastic bag cover is provided at the bottom of the container.