Industrialized construction system and construction method of bridge piers based on jacking frame

Through the industrialized construction system of bridge piers based on the jacking frame, the climbing system of the support columns is used to achieve lifting and lowering, which solves the problems of high safety risks and complicated construction procedures in the construction of high piers in traditional bridges, and achieves efficient steel reinforcement. Tying, concrete placement and curing reduce construction risks and the amount of finishing work.

CN113818348BActive Publication Date: 2024-10-08CCCC SECOND HARBOR ENGINEERING CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202110989460.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-08-26
Publication Date
2024-10-08
Estimated Expiration
2041-08-26

AI Technical Summary

Technical Problem

The construction of medium and high piers in traditional bridges has high safety risks, complex construction procedures, and poor operating conditions. A large number of embedded parts need to be installed on the piers, and the concrete strength needs to be equalized to lift the frame. The later modification work is large, and the hoisting equipment takes up a long time. etc. questions.

Method used

An industrialized construction system for bridge piers based on jacking frames is adopted, including support columns, construction platforms, hoisting systems, steel bar binding platforms, pouring systems and maintenance systems. The platform is lifted and lowered through the climbing system of the support columns, reducing Installation of embedded parts to improve construction efficiency.

Benefits of technology

It reduces construction risks, improves construction efficiency, realizes assembly line construction of pier column steel bar binding, concrete pouring and maintenance, reduces modification operations, and avoids construction risks caused by concrete strength limitations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113818348B_ABST
    Figure CN113818348B_ABST
Patent Text Reader

Abstract

The present invention discloses an industrialized construction system and construction method for bridge piers based on a jacking frame, including support columns and a construction platform; a plurality of support columns, which are distributed around the piers; the construction platform, including a hoisting system, a steel bar binding platform, a casting system and a maintenance system arranged from top to bottom; the hoisting system includes a track beam, a track, a limit baffle and a crane, the track beam is installed above the support column and cantilevered out of the support column, and is used to hoist standard sections, pier column steel bars and other miscellaneous materials required for construction, the track beam is provided with a track, and limit baffles are provided at both ends of the track, and the crane is movably installed on the track. The present invention realizes the assembly line construction of bridge piers by continuously climbing the support columns arranged around the piers with the pier body construction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of bridge construction, and more specifically, to an industrialized construction system and construction method for bridge piers based on a jacking frame. Background Art

[0002] In the construction of the bridge substructure, the traditional hanging method is generally used for medium and high piers. By pre-embedding the climbing cone in the pier, the load-bearing tripod is hung on the climbing cone to support the entire construction frame. The frame can be used as a platform for steel bar binding, template installation and concrete modification. The hanging frame and template system are repeatedly lifted and recycled with the assistance of the tower crane. Although the hanging method has the advantages of simple construction process and low cost, it has many hoisting operations, and the high-altitude docking of the frame requires manual assistance, which is difficult to install and has high safety risks; it works in an open-air environment and the progress is easily affected by the weather; a large number of embedded parts need to be installed on the pier, and the lifting frame needs to wait for the concrete strength and the amount of later modification work is large; it occupies the lifting and hoisting equipment for a long time and other defects. Summary of the invention

[0003] The purpose of the present invention is to overcome the shortcomings of the above technical background and provide an industrialized construction method for bridge piers based on a jacking frame.

[0004] In order to achieve these purposes and other advantages according to the present invention, there is provided an industrialized construction system for bridge piers based on a jacking frame, including support columns and a construction platform;

[0005] A number of supporting columns distributed around the pier;

[0006] The construction platform includes the hoisting system, steel bar binding platform, pouring system and maintenance system arranged from top to bottom;

[0007] The hoisting system comprises a track beam, a track, a limit baffle and an overhead travelling crane. The track beam is installed above the support column and cantilevers out of the support column. The track beam is provided with a track, and limit baffles are provided at both ends of the track. The overhead travelling crane is movably installed on the track.

[0008] The steel bar binding platform, casting system and maintenance system are divided into zones by the main frame erected between the support columns and the surrounding safety net. The steel bar binding platform is used as an operation platform for manual steel bar binding or steel bar component docking;

[0009] The casting system includes a material distribution system and a template system; the material distribution system includes a pump pipe and a material distribution rod; the pump pipe is integrated on the support column, and the material distribution rod is installed on the upper side of the main frame where the casting system area is located; the template system includes a template and a template frame, a moving device is provided at the bottom of the template frame, a slide rail is provided on the main frame, and the moving device is configured to be able to move horizontally along the slide rail of the main frame to realize opening and closing of the mold;

[0010] The curing system includes a spray curing system, which is located below the pouring area and performs spray curing on the poured sections.

[0011] Preferably, the support column comprises a support column base section, a support column transition section, a plurality of support column standard sections and a climbing system;

[0012] The support column base section is located at the bottom of the support column and is connected to the ground foundation; the support column standard section is disassembled and assembled through a climbing system to change the height of the support column itself; the support column transition section is located at the top of the support column;

[0013] The climbing system is mounted outside the supporting column and is used to disassemble and assemble the standard section to realize the lifting and lowering of the column;

[0014] Preferably, the pump tube is integrated on a standard section of the support column.

[0015] Preferably, a ceiling is installed above the hoisting system, and the ceiling is a structure that can be opened and closed automatically.

[0016] Preferably, the formwork support includes a base frame, an inner frame and an outer frame, the bottom of the inner frame is hinged to the base frame, the inner frame is connected to the formwork, the bottom of the outer frame is hinged to the telescopic assembly, and the other end of the telescopic assembly is hinged to the base frame.

[0017] Preferably, it further comprises a monitoring device, wherein the monitoring device comprises:

[0018] A lifting control module, which is connected to each climbing system;

[0019] A template control module, which is connected to each telescopic component and the moving device;

[0020] Display module, showing the overall operating status and monitoring parameters of the equipment.

[0021] A power supply module supplies power to the lifting control module, the template control module and the display module.

[0022] The present invention also provides an industrialized construction method for bridge piers using the system, comprising the following steps:

[0023] S1. Frame installation: The hoisting equipment installs the support column foundation section and several support column standard sections around the pier, then installs the climbing system, and gradually installs the support column transition section, hoisting system and ceiling. After the ceiling is installed, the support column standard section is hoisted to the climbing system through the hoisting system to realize the platform jacking until it reaches the initial working position;

[0024] During the lifting period, based on the control instructions of the lifting control module, the lifting speed of each climbing system is coordinated to ensure synchronous lifting and lowering. When the clearance height meets the requirements, the main support, formwork system and maintenance system can be installed, and the placing boom on the installed main support is connected to the pump pipe on the support column;

[0025] S2. Rebar construction: The hoisting system hoists the rebar parts from the ground to the rebar tying platform for connection or hoists the semi-finished rebar to the rebar tying platform for loose tying. After the rebar is tied, the standard section of the support column is installed through the climbing system to lift the construction platform upward by one section, so that the area where the rebar is tied corresponds to the casting system.

[0026] S3, concrete pouring: clean the formwork and apply the release agent. After the steel bar acceptance is completed, based on the control instructions of the formwork control module, control the movement of the moving device and the extension and retraction of the telescopic component to adjust the spatial position of the formwork to complete the mold closing; the lower end of the pump pipe is connected to the concrete supply device, and the concrete is pumped into the formwork in layers by the placing boom for pouring;

[0027] S4, demoulding and curing: The concrete is cured with the formwork until it reaches the demoulding strength and the construction of the previous section of steel bars is completed. The formwork control module controls the mold opening and lifts the construction platform upward as a whole. When the curing system reaches the new pouring section, demoulding and curing begins;

[0028] S5. Repeat steps S2 to S4 until the construction of all sections is completed.

[0029] Preferably, after the construction of the bridge piers is completed, the platform is dismantled: the roof is opened, the standard sections of the supporting columns are dismantled section by section, the supporting columns are lowered, and after they are lowered to a certain height, the maintenance system, casting system and steel bar binding platform are gradually dismantled. After they are lowered to the bottom section, a truck crane assists in dismantling the roof and lifting system, and finally the climbing system and the foundation section of the supporting columns are dismantled.

[0030] Preferably, before S1, the process also includes: construction of a cap, a foundation and embedded parts; and construction of the starting section of the pier body of 1 to 2 segments.

[0031] The present invention includes at least the following beneficial effects: The industrialized construction method of bridge piers based on the jacking frame of the present invention solves the problems of high safety risks, complex construction procedures and poor working conditions in the construction of high piers in traditional bridges, and realizes the assembly line construction of pier reinforcement binding, concrete pouring, maintenance and decoration procedures, thereby reducing construction risks and improving construction efficiency.

[0032] During the construction process, there is no need to install climbing embedded parts on the piers, which greatly reduces the modification work. The climbing timing is not limited by the concrete strength, which reduces the construction risk and improves the construction efficiency.

[0033] Other advantages, objectives and features of the present invention will be embodied in part through the following description, and in part will be understood by those skilled in the art through study and practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] Figure 1 It is the overall structure diagram of the frame of the bridge pier industrialized construction system based on the jacking frame of the present invention;

[0035] Figure 2 It is a structural diagram of the support column of the present invention;

[0036] Figure 3 It is the ceiling and hoisting system composition of the present invention;

[0037] Figure 4 It is a schematic diagram of the construction platform of the present invention;

[0038] Figure 5 It is a schematic diagram of the construction of the initial stage of the present invention;

[0039] Figure 6 It is a schematic diagram of the installation of the frame of the present invention;

[0040] Figure 7 The main support, formwork system and maintenance system of the present invention are installed;

[0041] Figure 8 It is a schematic diagram of the arrangement of the placing boom and the pump pipe of the present invention;

[0042] Fig. 9 It is a schematic diagram of the template support of the present invention.

[0043] Explanation of the reference numerals: 1—ceiling; 2—hoisting system; 3—rebar tying platform; 4—casting system; 5—maintenance system; 6—main support; 7—support column; 8—placement rod; 9—pump pipe; 10—climbing system; 11—transition section of support column; 12—standard section of support column; 13—foundation section of support column; 14—overhead crane; 15—track beam; 16—limit baffle; 17—track; 18—safety net; 19—formwork; 20—formwork support; 21—slide rail; 22—1~2 segment pier body; 23—automobile crane; 24 underframe; 25 inner frame; 26 outer frame, 27 telescopic assembly. DETAILED DESCRIPTION

[0044] The present invention is described in detail and completely below in conjunction with the accompanying drawings. A person of ordinary skill in the art will be able to implement the present invention based on these descriptions. Before describing the present invention in conjunction with the accompanying drawings, it should be particularly pointed out that the technical solutions and technical features provided in each part of the present invention, including the following description, can be combined with each other without conflict.

[0045] In addition, the embodiments of the present invention involved in the following description are generally only a part of the embodiments of the present invention, rather than all the embodiments. Therefore, based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.

[0046] The present invention is further described in detail below in conjunction with the accompanying drawings and implementations, and its specific implementation process is as follows:

[0047] like Figures 1 to 9 The present invention provides an industrialized construction system for bridge piers based on a jacking frame, including a support column 7 and a construction platform;

[0048] A plurality of support columns 7, which are distributed around the pier;

[0049] The construction platform includes a hoisting system 2, a steel bar binding platform 3, a pouring system 4 and a maintenance system 5 arranged from top to bottom;

[0050] The hoisting system 2 includes a rail 17 beam 15, a rail 17, a limit baffle 16 and a crane 14. The rail 17 beam 15 is installed above the support column 7 and cantilevered out of the support column 7, and is used to lift standard sections, pier column steel bars and other miscellaneous materials required for construction. The rail 17 beam 15 is provided with a rail 17, and limit baffles 16 are provided at both ends of the rail 17. The crane 14 is movably installed on the rail 17;

[0051] The steel bar binding platform 3, the pouring system 4 and the curing system 5 are partitioned by the main frame 6 erected between the support columns 7 and the surrounding safety net 18. The steel bar binding platform 3 is used as an operation platform for manual steel bar binding or steel bar component docking;

[0052] The pouring system 4 includes a material distribution system and a template 19 system; the material distribution system includes a pump pipe 9 and a distribution rod 8; the pump pipe 9 is integrated on the support column 7 and is installed and removed synchronously with the support column 7, and the distribution rod 8 is installed on the upper side of the main support 6 where the pouring system 4 area is located; the template 19 system includes a template 19 and a template support 20, a moving device is provided at the bottom of the template support 20, and a slide rail 21 is provided on the main support 6, and the moving device is configured to be able to move horizontally along the slide rail 21 of the main support 6 to realize opening and closing of the mold;

[0053] The curing system 5 comprises a spray curing system 5, which is located below the casting area and performs spray curing on the cast sections;

[0054] The technical solution may also include the following technical details to better achieve the technical effect: the support column 7 includes a support column base section 13, a support column transition section 11, a plurality of support column standard sections 12 and a climbing system 10;

[0055] The support column base section 13 is located at the bottom of the support column 7 and is connected to the ground foundation; the support column standard section 12 is interchangeable and detachable, and the support column standard section 12 is disassembled and assembled through the climbing system 10 to change the height of the support column 7; the support column transition section 11 is located at the top of the support column 7 and serves as the base of the hoisting system 2;

[0056] The climbing system 10 is mounted outside the support column 7 and is used to disassemble and assemble the standard section to realize the lifting and lowering of the column. The climbing system 10 is an existing equipment that can realize the installation of the support column standard section 12. Specifically, the support column standard section 12 is hoisted by the overhead crane, and then the upper and lower support column standard sections in the climbing system are removed and connected. After the lifting cylinders of each climbing system are synchronously lifted to a height of one section, the hoisted support column standard section 12 is introduced into the climbing system to align the position and connected with the upper and lower support column standard sections;

[0057] The present technical solution may also include the following technical details to better achieve the technical effect: the pump pipe 9 is integrated on the standard section 12 of the support column. As the standard section 12 of the support column is installed upwards section by section, the pump pipe 9 extends from the bottom to the top, and can simultaneously realize the pouring of the pouring area.

[0058] The present technical solution may further include the following technical details to better achieve the technical effect: a ceiling 1 is installed above the hoisting system 2, and the ceiling 1 is a structure that can be opened and closed automatically.

[0059] The present technical solution may also include the following technical details to better achieve the technical effect: the formwork support 20 includes a base frame 24, an inner frame 25 and an outer frame 26, the bottom of the inner frame is hinged to the base frame, the inner frame is connected to the formwork 19, the bottom of the outer frame is hinged to the telescopic assembly 27, and the other end of the telescopic assembly is hinged to the base frame.

[0060] This technical solution may also include the following technical details to better achieve the technical effect: it also includes a monitoring device, the monitoring device includes:

[0061] A lifting control module, which is connected to each climbing system 10, and coordinately controls the lifting speed of each climbing system 10 to ensure synchronous lifting and lowering;

[0062] The template 19 control module is connected to each telescopic assembly and moving device to adjust the relative position of the template 19 according to the linearity of the pier body;

[0063] Display module, showing the overall operating status and monitoring parameters of the equipment.

[0064] A power supply module supplies power to the lifting control module, the template 19 control module and the display module.

[0065] An industrialized construction method for bridge piers using the system comprises the following steps:

[0066] S1, such as Figure 6 As shown, the frame is installed: the support column base section 13 and several support column standard sections 12 are installed around the pier by a lifting device such as a car crane 23, and then the climbing system 10 is installed, and the support column transition section 11, the lifting system 2 and the ceiling 1 are gradually installed. After the ceiling 1 is installed, the support column standard section 12 is lifted to the climbing system 10 by the lifting system 2 to realize the platform jacking until it reaches the initial working position;

[0067] like Figure 7 As shown, during the jacking period, based on the control instructions of the lifting control module, the lifting speed of each climbing system 10 is coordinated to ensure synchronous jacking and descent. After the clearance height meets the requirements, the main support 6, the template 19 system and the maintenance system 5 can be installed, and the placing rod 8 on the installed main support 6 is connected to the pump pipe 9 on the support column 7;

[0068] S2, steel bar construction: the hoisting system 2 hoists steel bar parts from the ground to the steel bar binding platform 3 for docking or hoists semi-finished steel bars to the steel bar binding platform 3 for loose binding; after the steel bar binding is completed, the standard section of the support column is installed through the climbing system to lift the construction platform upward by one section as a whole, so that the area where the steel bar binding is completed now corresponds to the casting system;

[0069] S3, concrete pouring: clean the formwork 19 and apply a release agent. After the steel bar acceptance is completed, the movement of the moving device and the extension and retraction of the telescopic component are controlled based on the control instructions of the formwork 19 control module, so as to adjust the spatial position of the formwork 19 to complete the mold closing; the lower end of the pump pipe 9 is connected to the concrete supply device, and the concrete is pumped into the formwork 19 in layers by the placing boom 8 for pouring;

[0070] S4, demoulding, lifting, and curing: The concrete is cured with the mold until it reaches the demoulding strength and the construction of the previous section of steel bars is completed. The template 19 control module controls the mold opening and lifts the construction platform upward as a whole. When the curing system reaches the new pouring section, demoulding and curing begins;

[0071] S5. Repeat steps S2 to S4 until the construction of all sections is completed.

[0072] The technical solution may also include the following technical details to better achieve the technical effect: After the construction of the bridge pier is completed, the platform is dismantled: the dismantling is the reverse process of the installation, the ceiling 1 is opened, the standard section 12 of the supporting column is dismantled section by section, the supporting column 7 is lowered, and after it is lowered to a certain height, the maintenance system 5, the pouring system 4 and the steel bar binding platform 3 are gradually dismantled. After it is lowered to the bottom section, the automobile crane 23 assists in dismantling the ceiling 1 and the lifting system 2, and finally the climbing system 10 and the supporting column base section 13 are dismantled.

[0073] This technical solution may also include the following technical details to better achieve the technical effect: Figure 5 As shown, before S1, the following also includes: construction of the cap, foundation and embedded parts; and construction of the starting section of the 1-2 segment pier body 22.

[0074] Although the embodiments of the present invention have been disclosed as above, they are not limited to the applications listed in the specification and the implementation modes. They can be fully applied to various fields suitable for the present invention. For those familiar with the art, additional modifications can be easily implemented. Therefore, without departing from the general concept defined by the claims and the scope of equivalents, the present invention is not limited to the specific details and the embodiments shown and described herein.

Claims

1. An industrialized construction system for bridge piers based on a jacking frame, characterized in that: Including support columns and construction platforms; A number of supporting columns distributed around the pier; The construction platform includes the hoisting system, steel bar binding platform, pouring system and maintenance system arranged from top to bottom; The hoisting system comprises a track beam, a track, a limit baffle and an overhead travelling crane. The track beam is installed above the support column and cantilevers out of the support column. The track beam is provided with a track, and limit baffles are provided at both ends of the track. The overhead travelling crane is movably installed on the track. The steel bar binding platform, casting system and maintenance system are divided into zones by the main frame erected between the support columns and the surrounding safety net. The steel bar binding platform is used as an operation platform for manual steel bar binding or steel bar component docking; The casting system includes a material distribution system and a template system; the material distribution system includes a pump pipe and a material distribution rod; the pump pipe is integrated on the support column, and the material distribution rod is installed on the upper side of the main frame where the casting system area is located; the template system includes a template and a template frame, a moving device is provided at the bottom of the template frame, a slide rail is provided on the main frame, and the moving device is configured to be able to move horizontally along the slide rail of the main frame to realize opening and closing of the mold; The curing system includes a spray curing system located below the pouring area for spray curing the poured sections; The support column comprises a support column base section, a support column transition section, a plurality of support column standard sections and a climbing system; The support column base section is located at the bottom of the support column and is connected to the ground foundation; the support column standard section is disassembled and assembled through a climbing system to change the height of the support column itself; the support column transition section is located at the top of the support column; The climbing system is mounted outside the supporting column and is used to disassemble and assemble the standard section to realize the lifting and lowering of the column; The pump pipe is integrated on the standard section of the support column; The template support comprises a base frame, an inner frame body and an outer frame body, the bottom of the inner frame body is hinged to the base frame, the inner frame body is connected to the template, the bottom of the outer frame body is hinged to the telescopic assembly, and the other end of the telescopic assembly is hinged to the base frame; Monitoring equipment, including: A lifting control module, which is connected to each climbing system; A template control module, which is connected to each telescopic component and the moving device; Display module, which displays the overall operating status and monitoring parameters of the equipment; A power supply module supplies power to the lifting control module, the template control module and the display module.

2. The bridge pier industrial construction system based on the jacking frame according to claim 1 is characterized in that: A ceiling is installed above the hoisting system, and the ceiling is a structure that can be opened and closed automatically.

3. An industrialized construction method for bridge piers using the system of claim 2, characterized in that: The following steps are involved: S1. Frame installation: The hoisting equipment installs the support column foundation section and several support column standard sections around the pier, then installs the climbing system, and gradually installs the support column transition section, hoisting system and ceiling. After the ceiling is installed, the support column standard section is hoisted to the climbing system through the hoisting system to realize the platform jacking until it reaches the initial working position; During the lifting period, based on the control instructions of the lifting control module, the lifting speed of each climbing system is coordinated to ensure synchronous lifting and lowering. When the clearance height meets the requirements, the main support, formwork system and maintenance system can be installed, and the placing boom on the installed main support is connected to the pump pipe on the support column; S2. Rebar construction: The hoisting system hoists the rebar parts from the ground to the rebar tying platform for connection or hoists the semi-finished rebar to the rebar tying platform for loose tying. After the rebar is tied, the standard section of the support column is installed through the climbing system to lift the construction platform upward by one section, so that the area where the rebar is tied corresponds to the casting system. S3, concrete pouring: clean the formwork and apply the release agent. After the steel bar acceptance is completed, based on the control instructions of the formwork control module, control the movement of the moving device and the extension and retraction of the telescopic component to adjust the spatial position of the formwork to complete the mold closing; the lower end of the pump pipe is connected to the concrete supply device, and the concrete is pumped into the formwork in layers by the placing boom for pouring; S4, demoulding and curing: The concrete is cured with the formwork until it reaches the demoulding strength and the construction of the previous section of steel bars is completed. The formwork control module controls the mold opening and lifts the construction platform upward as a whole. When the curing system reaches the new pouring section, demoulding and curing begins; S5. Repeat steps S2 to S4 until all sections are constructed.

4. The construction method according to claim 3, characterized in that: After the construction of the bridge piers is completed, the platform is dismantled: the roof is opened, the standard sections of the supporting columns are dismantled section by section, the supporting columns are lowered, and after they are lowered to a certain height, the maintenance system, pouring system and steel bar binding platform are gradually dismantled. After they are lowered to the bottom section, a truck crane assists in dismantling the roof and lifting system, and finally the climbing system and the foundation section of the supporting column are dismantled.

5. The construction method according to claim 3, characterized in that: The process before S1 also includes: construction of cap, foundation and embedded parts; and construction of the starting section of the pier body of 1~2 segments.