An artificial intelligence alarm method for safe production in hydropower plants

Through the artificial intelligence method, deep learning neural network is used to analyze the operating status of hydropower plant equipment, which solves the problem of simple alarm mechanism in the existing technology, achieves more accurate and efficient equipment monitoring and early warning, reduces the burden of operation and maintenance personnel, and provides No one is on duty and few people are on duty provide the basis.

CN113887799BActive Publication Date: 2024-10-22BEIJING XJ ELECTRIC
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202111150022.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-09-29
Publication Date
2024-10-22
Estimated Expiration
2041-09-29

AI Technical Summary

Technical Problem

The alarm mechanism of the existing computer monitoring system of hydropower plants is simple, resulting in a large number of process data alarms. It is difficult for operators to confirm key information at the first time, and it is impossible to effectively monitor the operating status of equipment.

Method used

Using artificial intelligence methods, we analyze equipment operating status through historical data extraction and deep learning neural networks, establish equipment object models, extract working condition information and protection data, eliminate abnormal data, build pattern matchers and execution engines, and monitor equipment operation in real time. Trigger alarms and predict future trends.

Benefits of technology

It improves the accuracy and efficiency of the alarm mechanism, reduces the workload of operation and maintenance personnel, and lays the foundation for the realization of super-large hydropower units with unattended and few people on duty.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113887799B_ABST
    Figure CN113887799B_ABST
Patent Text Reader

Abstract

The embodiment of the present invention provides an artificial intelligence alarm method for safe production in a hydropower plant, the method comprising: a historical data extraction step, a neural network reasoning step, and a warning alarm output step. The technical solution of the present invention belongs to the field of artificial intelligence. The above technical solution combines artificial intelligence technology, adopts a neural network algorithm to automatically obtain the operating health standards of the hydropower plant, monitors and tracks the production equipment of the whole plant, and alarms the operating status of the equipment that deviates from the health standards, which greatly reduces the workload of the power station personnel and lays the foundation for realizing the "unmanned and less-staffed" operation of super-large hydropower units.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of information technology, and in particular to an artificial intelligence alarm method for safe production in a hydropower plant. Background Art

[0002] With the development of social informatization, various electronic devices are widely used in more and more fields; especially in various monitoring and surveillance fields, which can greatly improve the real-time nature of monitoring.

[0003] However, for a long time, the data alarm mechanism of the hydropower plant's computer monitoring system has been a simple state change and analog value limit alarm. The extensive alarm mechanism causes the monitoring system to generate a large number of process data alarms, such as repeated screen refresh alarms of analog value critical values ​​and equipment operation process state change alarms. A large amount of process data is piled up on the screen, making it impossible for operators to confirm key information in the first place. Summary of the invention

[0004] In view of the problems existing in the prior art in the field of hydropower station monitoring, the purpose of the embodiments of the present invention is to provide an artificial intelligence alarm method for safe production in a hydropower plant.

[0005] In order to solve the above problems, an embodiment of the present invention proposes an artificial intelligence alarm method for safe production of a hydropower plant, including: a historical data extraction step, a neural network reasoning step, and a warning alarm output step;

[0006] The historical data extraction steps include: establishing an equipment object model for the specific operating equipment of the hydropower plant, extracting the operating condition information and target information of the equipment; and extracting the protection data of the auxiliary equipment operation at the same time; eliminating obviously abnormal measurement data through variance and deviation calculation to form sample data;

[0007] The neural network reasoning steps include: establishing multiple sets of deep learning neural networks according to flood season, non-flood season and year; inputting the sample data into the corresponding deep learning neural network, completing sample training, so as to obtain a neural network reasoning engine with feature information; wherein the neural network reasoning process can construct a reasoning engine including: a pattern matcher, an agenda and an execution engine;

[0008] The early warning alarm output includes: according to the current month, the latest deep learning neural network of the flood season or non-flood season is used to process the operating data to obtain the health standard; the operating data of the equipment is monitored and tracked in real time, and a real-time alarm is triggered when the equipment operation deviates from the health standard; and according to the current month, the neural network inference engine of the flood season or non-flood season in different years is used to process the operating data respectively, and the changes in the health data of previous years are obtained to form new sample data; and a new deep learning neural network inference engine is established to train the new sample data, dig out the trend of equipment operation, predict the possible operation of the equipment in the next few years, and alarm when the predicted data of a future year exceeds the rated limit.

[0009] Wherein, the historical data extraction step includes:

[0010] Obtain the action times Xi of the target equipment on day i from historical data; adopt the same method to obtain the operation data of n consecutive days within the target time interval to form the action times array X; obtain the middle value M of the array by variance calculation; traverse the array to calculate the deviation δXi of Xi to M, and when the deviation exceeds the rated value, Xi is considered invalid. This method is used to filter out invalid information in the equipment operation data to avoid the data impact caused by abnormal acquisition equipment, and obtain the effective action times array X'; obtain the working condition data Zi2...Zin at the corresponding time for all elements X'i of X', and assign X'i to Zi1 to form a characteristic two-dimensional array Z; the leakage data cannot be directly obtained from the operation data of the hydropower plant, but must be calculated through the statistical data of the action data of the pump group equipment related to the leakage. Therefore, the data is grouped and counted by day according to the equipment action analysis method, and the leakage data is calculated by the statistical results;

[0011] Obtain the action time Xi of the target equipment on day i from historical data; adopt the same method to obtain the operation data of n consecutive days within the target time interval to form an action time array X; obtain the middle value M of the array; traverse the array to calculate the deviation δXi of Xi to M. When the deviation exceeds the rated value, Xi is considered invalid, and the effective action time array X' is obtained; similarly, the effective stop time array Y' is obtained; the leakage volume Li on day i is obtained through the leakage volume calculation formula f(X'i, Y'i); thus, the leakage volume array L is obtained; for all elements Li of L, the operating condition data Zi2…Zin at the corresponding time are obtained, and Li is assigned to Zi1 to form a characteristic two-dimensional array Z.

[0012] Among them, the neural network reasoning steps include:

[0013] The sample array Z is input into the neural network inference engine for training; automatic learning is performed through error back propagation, and the connection weight of each node and the threshold of the corresponding node are modified until the error is less than the specified value.

[0014] Among them, in the neural network reasoning step, the neural network reasoning adopts the deductive method, including:

[0015] Starting from an initial fact, rules are continuously applied to draw conclusions or perform specified actions, where the fact is a warning or alarm. The deductive method includes:

[0016] Input the sample data Fact obtained through historical data extraction into the working memory;

[0017] Use Pattern Matcher to compare the rules and data Fact in the rule base Rule Base; if there is a conflict in the execution of the rules, that is, multiple rules are activated at the same time, put the conflicting rules into the conflict set Conflict Set;

[0018] Resolve conflicts and put the activated rules into the agenda in order to arrange them in a relevant order.

[0019] Use the rules in the Execution Engine agenda; repeat the above steps until all the rules in the agenda are executed.

[0020] The neural network reasoning process is an engine that determines whether the specified filter conditions contained in the rules match the real-time conditions at the runtime to execute the actions specified in the rules; including:

[0021] Information services receive events and convert them into information elements; information services receive events and generate information element objects; each information service generates information element objects corresponding to its own type; that is, each information element object generated by a specific information service based on information elements has the same format, but may have different attributes and rule sets;

[0022] The information element is passed to the queue manager: the information element is the basic building block of the rule engine. It is an object that contains all the information about a specific event; this information includes: the message, the application identifier that generated the event, the event that generated the event, the information element type, the related rule set, the common methods, the common attributes, and some system related information; the queue manager is used to manage the queues of information element objects from different information services;

[0023] The rule engine receives these information elements and applies the rules they carry to execute them until there are no more information elements in the queue manager.

[0024] Among them, the rule set is a collection of many rules; each rule contains a conditional filter and multiple actions; a conditional filter can contain multiple filter conditions; the conditional filter is a combination of multiple Boolean expressions, and the combined result is still a Boolean type; when the program is running, the action will be executed when the conditional filter value is true.

[0025] The neural network reasoning process is that the reasoning engine receives information elements from the queue manager in sequence and checks the rules in the rule set carried by the information elements according to the definition order of the rules; wherein the neural network reasoning process includes:

[0026] The rule engine checks the first rule and evaluates its condition filter. If the value is false, all actions related to this rule are ignored and the next rule is executed. If the filter value of the second rule is true, all actions related to this rule are executed in the order defined, and the next rule is executed after the execution is completed. After all the rules in the information element are executed, the information element will be destroyed, and then the next information element will be received from the queue manager.

[0027] Two special actions are not considered in this process: Discard Action and Include Action. If the Discard Action is executed, all the following rules in the information element where it is located will be skipped, and the information element where it is located will be destroyed. The rule engine will continue to receive the next information element in the queue manager. The Include Action is actually an action that includes other existing rule sets. If the Include Action is executed, the rule engine will pause and enter the included rule set. After the execution is completed, the rule engine will return to the original pause point to continue execution. This process will be performed recursively.

[0028] Among them, the early warning alarm output steps include:

[0029] Monitor and track the operation of the equipment in real time, and obtain the statistical data K' of the number of equipment actions on the day; at the same time, establish the working condition data array Z'1...Z'n, input Z' into the neural network to calculate the normal number of actions V under the working condition that the neural network believes; compare V with K', and issue an alarm when K' is greater than V;

[0030] Monitor and track the operation of the equipment in real time, and obtain the equipment leakage data K' for the day; at the same time, establish the working condition data array Z'1...Z'n, input Z' into the neural network to calculate the normal number of actions V under the working condition that the neural network believes; compare V with K', and issue an alarm when K' is greater than V.

[0031] Wherein, the method further comprises:

[0032] The human-machine interface reminder steps include: organizing the actual production equipment of the hydropower plant according to a tree structure, and the final layer of equipment objects carries the real-time data information of the monitoring system to form a model tree; when the alarm is triggered, the information related to the alarm is also counted and displayed according to the hierarchical relationship of the model tree.

[0033] Among them, the human-machine interface reminder step also includes: configuring the light sign on the alarm working interface, nodes at any level on the model tree can be configured on the interface, and different levels of alarm information are marked with different colors, thereby forming an intuitive alarm information display; and the alarm information is pushed via voice and App.

[0034] The beneficial effects of the present invention are:

[0035] The technical solution of the present invention belongs to the field of artificial intelligence. The above technical solution combines artificial intelligence technology, uses a neural network algorithm to automatically obtain the health standards of hydropower plant operation, monitors and tracks the production equipment of the entire plant, and alarms the operating status of equipment that deviates from the health standards, greatly reducing the workload of power station personnel and laying the foundation for realizing the "unmanned and less-staffed" operation of super-large hydropower units. BRIEF DESCRIPTION OF THE DRAWINGS

[0036] Figure 1 It is a schematic diagram of the hydropower plant safety production alarm method applied by the present invention;

[0037] Figure 2 This is a schematic diagram of the reasoning of the safety production alarm of a hydropower plant applied by the present invention;

[0038] Figure 3 It is a schematic diagram of the reasoning process of the present invention for applying the safety production of a hydropower plant;

[0039] Figure 4 It is a schematic diagram of the reasoning process of the hydropower plant safety production applied by the present invention;

[0040] Figure 5 This is a schematic diagram of a hydropower plant safety production alarm device applied by the present invention;

[0041] Figure 6 It is a schematic diagram of a neural network inference machine for safe production in a hydropower plant applied by the present invention. Specific embodiments

[0042] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0043] The method of the embodiment of the present invention is further described below with reference to the accompanying drawings.

[0044] like Figure 1-Figure 6 As shown, the embodiment of the present invention proposes an artificial intelligence alarm method for safe production of a hydropower plant, including: a historical data extraction step, a neural network reasoning step, and a warning alarm output step;

[0045] The historical data extraction steps include: establishing an equipment object model for the specific operating equipment of the hydropower plant, extracting the operating condition information and target information of the equipment; and extracting the protection data of the auxiliary equipment operation at the same time; eliminating obviously abnormal measurement data through variance and deviation calculation to form sample data;

[0046] The neural network reasoning steps include: establishing multiple sets of deep learning neural networks according to flood season, non-flood season and year; inputting the sample data into the corresponding deep learning neural network, completing sample training, so as to obtain a neural network reasoning engine with feature information; wherein the neural network reasoning process can construct a reasoning engine including: a pattern matcher, an agenda and an execution engine;

[0047] The early warning alarm output includes: according to the current month, the latest deep learning neural network of the flood season or non-flood season is used to process the operating data to obtain the health standard; the operating data of the equipment is monitored and tracked in real time, and a real-time alarm is triggered when the equipment operation deviates from the health standard; and according to the current month, the neural network inference engine of the flood season or non-flood season in different years is used to process the operating data respectively, and the changes in the health data of previous years are obtained to form new sample data; and a new deep learning neural network inference engine is established to train the new sample data, dig out the trend of equipment operation, predict the possible operation of the equipment in the next few years, and alarm when the predicted data of a future year exceeds the rated limit.

[0048] Wherein, the historical data extraction step includes:

[0049] Obtain the action times Xi of the target equipment on day i from historical data; adopt the same method to obtain the operation data of n consecutive days within the target time interval to form the action times array X; obtain the middle value M of the array by variance calculation; traverse the array to calculate the deviation δXi of Xi to M, and when the deviation exceeds the rated value, Xi is considered invalid. This method is used to filter out invalid information in the equipment operation data to avoid the data impact caused by abnormal acquisition equipment, and obtain the effective action times array X'; obtain the working condition data Zi2...Zin at the corresponding time for all elements X'i of X', and assign X'i to Zi1 to form a characteristic two-dimensional array Z; the leakage data cannot be directly obtained from the operation data of the hydropower plant, but must be calculated through the statistical data of the action data of the pump group equipment related to the leakage. Therefore, the data is grouped and counted by day according to the equipment action analysis method, and the leakage data is calculated by the statistical results;

[0050] Obtain the action time Xi of the target equipment on day i from historical data; adopt the same method to obtain the operation data of n consecutive days within the target time interval to form an action time array X; obtain the middle value M of the array; traverse the array to calculate the deviation δXi of Xi to M. When the deviation exceeds the rated value, Xi is considered invalid, and the effective action time array X' is obtained; similarly, the effective stop time array Y' is obtained; the leakage volume Li on day i is obtained through the leakage volume calculation formula f(X'i, Y'i); thus, the leakage volume array L is obtained; for all elements Li of L, the operating condition data Zi2…Zin at the corresponding time are obtained, and Li is assigned to Zi1 to form a characteristic two-dimensional array Z.

[0051] Among them, the neural network reasoning steps include:

[0052] The sample array Z is input into the neural network inference engine for training; automatic learning is performed through error back propagation, and the connection weight of each node and the threshold of the corresponding node are modified until the error is less than the specified value.

[0053] Among them, in the neural network reasoning step, the neural network reasoning adopts the deductive method, including:

[0054] Starting from an initial fact, rules are continuously applied to draw conclusions or perform specified actions, where the fact is a warning or alarm. The deductive method includes:

[0055] Input the sample data Fact obtained through historical data extraction into the working memory;

[0056] Use Pattern Matcher to compare the rules and data Fact in the rule base Rule Base; if there is a conflict in the execution of the rules, that is, multiple rules are activated at the same time, put the conflicting rules into the conflict set Conflict Set;

[0057] Resolve conflicts and put the activated rules into the agenda in order to arrange them in a relevant order.

[0058] Use the rules in the Execution Engine agenda; repeat the above steps until all the rules in the agenda are executed.

[0059] The neural network reasoning process is an engine that determines whether the specified filter conditions contained in the rules match the real-time conditions at the runtime to execute the actions specified in the rules; including:

[0060] Information services receive events and convert them into information elements; information services receive events and generate information element objects; each information service generates information element objects corresponding to its own type; that is, each information element object generated by a specific information service based on information elements has the same format, but can have different attributes and rule sets;

[0061] The information element is passed to the queue manager: the information element is the basic building block of the rule engine. It is an object that contains all the information about a specific event; this information includes: the message, the application identifier that generated the event, the event that generated the event, the information element type, the related rule set, the common methods, the common attributes, and some system related information; the queue manager is used to manage the queues of information element objects from different information services;

[0062] The rule engine receives these information elements and applies the rules they carry to execute them until there are no more information elements in the queue manager.

[0063] Among them, the rule set is a collection of many rules; each rule contains a conditional filter and multiple actions; a conditional filter can contain multiple filter conditions; the conditional filter is a combination of multiple Boolean expressions, and the combined result is still a Boolean type; when the program is running, the action will be executed when the conditional filter value is true.

[0064] The neural network reasoning process is that the reasoning engine receives information elements from the queue manager in sequence and checks the rules in the rule set carried by the information elements according to the definition order of the rules; wherein the neural network reasoning process includes:

[0065] The rule engine checks the first rule and evaluates its condition filter. If the value is false, all actions related to this rule are ignored and the next rule is executed. If the filter value of the second rule is true, all actions related to this rule are executed in the order defined, and the next rule is executed after the execution is completed. After all the rules in the information element are executed, the information element will be destroyed, and then the next information element will be received from the queue manager.

[0066] Two special actions are not considered in this process: Discard Action and Include Action. If the Discard Action is executed, all the following rules in the information element where it is located will be skipped, and the information element where it is located will be destroyed. The rule engine will continue to receive the next information element in the queue manager. The Include Action is actually an action that includes other existing rule sets. If the Include Action is executed, the rule engine will pause and enter the included rule set. After the execution is completed, the rule engine will return to the original pause point to continue execution. This process will be performed recursively.

[0067] Among them, the early warning alarm output steps include:

[0068] Monitor and track the operation of the equipment in real time, and obtain the statistical data K' of the number of equipment actions on the day; at the same time, establish the working condition data array Z'1...Z'n, input Z' into the neural network to calculate the normal number of actions V under the working condition that the neural network believes; compare V with K', and issue an alarm when K' is greater than V;

[0069] Monitor and track the operation of the equipment in real time, and obtain the equipment leakage data K' for the day; at the same time, establish the working condition data array Z'1...Z'n, input Z' into the neural network to calculate the normal number of actions V under the working condition that the neural network believes; compare V with K', and issue an alarm when K' is greater than V.

[0070] Wherein, the method further comprises:

[0071] The human-machine interface reminder steps include: organizing the actual production equipment of the hydropower plant according to a tree structure, and the final layer of equipment objects carries the real-time data information of the monitoring system to form a model tree; when the alarm is triggered, the information related to the alarm is also counted and displayed according to the hierarchical relationship of the model tree.

[0072] Among them, the human-machine interface reminder step also includes: configuring the light sign on the alarm working interface, nodes at any level on the model tree can be configured on the interface, and different levels of alarm information are marked with different colors, thereby forming an intuitive alarm information display; and the alarm information is pushed via voice and App.

[0073] The purpose of the technical solution of the present invention is to provide an artificial intelligence alarm method for safe production in hydropower plants, which overcomes the shortcomings of the extensive and single alarm of the traditional hydropower plant computer monitoring system, can effectively improve the alarm mechanism and the work efficiency of operation and maintenance personnel, and enable operation and maintenance personnel to more efficiently control the operation status of the equipment in the whole plant. Specifically, its goals are:

[0074] (1) Provide a historical data extraction solution to provide key data samples such as equipment operating conditions and target information for the establishment of the equipment object model.

[0075] (2) Provide a neural network reasoning mechanism, form a deep learning neural network algorithm model library, complete sample training, and obtain a neural network reasoning engine with specific feature information.

[0076] (3) Provide a method for analyzing the health trend of equipment operation, which can meet the output of current health alarms and future prediction and warning.

[0077] (4) Provide a human-computer interface application method that can quickly output alarm point information to the human-computer interaction interface.

[0078] The technical solution of the present invention combines artificial intelligence technology and uses a neural network algorithm to automatically obtain the health standards of hydropower plant operation, monitor and track the production equipment of the entire plant, and alarm the operating status of equipment that deviates from the health standards, which greatly reduces the workload of power station personnel and lays the foundation for realizing the "unmanned and less-staffed" operation of super-large hydropower units. Specifically, the artificial intelligence alarm method for safe production of hydropower plants in the technical solution of the present invention includes: historical data extraction steps, neural network reasoning steps, early warning alarm output steps, and human-machine interface reminder steps;

[0079] Wherein, the historical data extraction includes:

[0080] For the specific operating equipment of the hydropower plant, the equipment object model is established to extract the operating condition information and target information of the equipment. In addition to the conventional equipment operation data, the protection data of the auxiliary equipment operation is also extracted. The statistical method is applied to eliminate the obviously abnormal measurement data through variance and deviation calculation to prevent the data abnormality caused by the acquisition failure from affecting the analysis results. Finally, the equipment operation data with statistical significance is obtained to form sample data.

[0081] The neural network reasoning includes: according to the particularity of the operation of hydropower station equipment, several groups of deep learning neural networks are established according to the flood season, non-flood season and year, sample data is input into the neural network, sample training is completed, and a neural network reasoning machine with characteristic information is obtained. The process of neural network reasoning can build a reasoning engine, including a pattern matcher, an agenda and an execution engine.

[0082] Among them, the early warning alarm output includes: according to the current month, the latest flood season or non-flood season neural network is used to process the working condition data to obtain the health standard; real-time monitoring and tracking of the equipment's operating data, when the equipment operation deviates from the health standard, trigger a real-time alarm. According to the current month, the flood season or non-flood season neural network inference machine in different years is used to process the working condition data respectively, and the changes in the health data in the past few years are obtained to form new sample data. A new neural network inference machine is established to train the samples, dig out the trend of equipment operation, predict the possible operation of the equipment in the next few years, and alarm when the predicted data in a future year exceeds the rated limit.

[0083] Among them, the human-machine interface reminder includes: organizing the actual production equipment of the hydropower plant according to the tree structure, and the final layer of equipment objects carries the real-time data information of the monitoring system to form a model tree. When the alarm is triggered, the relevant information is also counted and displayed according to the hierarchical relationship of the model tree. Configure the light sign in the alarm work interface, and the nodes of any level on the model tree can be configured on the interface, and different levels of alarm information are marked with different colors, thereby forming an intuitive alarm information display. At the same time, the alarm information is pushed through voice and App to enhance the user experience.

[0084] The artificial intelligence alarm device for safe production of hydropower plants according to the present application includes: a historical data extraction module for collecting multi-source heterogeneous data of equipment object models; a neural network inference engine for tentative reasoning interpretation and conclusion proof; a early warning alarm output module for monitoring and tracking the early warning alarm output of key points of equipment deviation from historical normal operating status data; and a human-machine interface reminder module for users to experience in different ways after the early warning alarm of the hydropower plant is triggered.

[0085] Furthermore, the neural network inference engine includes: a rule base (Rule Base), which is used to construct rules and is the knowledge base (knowledge base); a working memory (Working Memory), which is used to receive objects (Fact); and an inference engine (Inference Engine), which is used to start from an initial fact and continuously apply rules to draw conclusions.

[0086] Furthermore, the inference engine includes a pattern matcher for determining the selection of execution rules and the timing of executing the rules; an agenda for setting the execution order of the selected rules; and an execution engine for executing rules and other actions.

[0087] 3. Advantages and effects: The advantages of the present invention are:

[0088] (1) More accurately reflect the equipment operating status.

[0089] (2) The alarm is more accurate and faster.

[0090] (3) Reduce the burden of on-site maintenance work.

[0091] (4) Optimize the safe production process of hydropower plants.

[0092] According to an embodiment of the present invention, an artificial intelligence alarm method for safe production in a hydropower plant is provided.

[0093] Prioritize the artificial intelligence alarm method for safe production in hydropower plants by realizing an organic combination of historical data extraction, neural network reasoning, early warning alarm output, and human-machine interface reminder. Figure 1 As shown, the method comprises the following steps:

[0094] (1) Historical data extraction

[0095] The number of actions Xi of the target equipment on day i is obtained from historical data; the same method is used to obtain the operation data of n consecutive days within the target time interval to form an action number array X; the middle value M of the array is obtained by variance calculation; the array is traversed to calculate the deviation δXi of Xi to M. When the deviation exceeds the rated value, Xi is considered invalid. This method is used to filter out invalid information in the equipment operation data to avoid the data impact caused by abnormal collection equipment, and obtain the valid action number array X'; for all elements X'i of X', the operating condition data Zi2…Zin at the corresponding time are obtained, and X'i is assigned to Zi1 to form a characteristic two-dimensional array Z.

[0096] The leakage data cannot be obtained directly from the operation data of the hydropower plant, but must be calculated through the statistical data of the action data of the leakage-related pump equipment. Therefore, the data is grouped and counted by day according to the equipment action analysis method, and the leakage data is calculated based on the statistical results.

[0097] Obtain the action time Xi of the target equipment on day i from historical data; adopt the same method to obtain the operation data of n consecutive days within the target time interval to form an action time array X; obtain the middle value M of the array; traverse the array to calculate the deviation δXi of Xi to M. When the deviation exceeds the rated value, Xi is considered invalid, and the effective action time array X' is obtained; similarly, the effective stop time array Y' is obtained; the leakage volume Li on day i is obtained through the leakage volume calculation formula f(X'i, Y'i); thus, the leakage volume array L is obtained; for all elements Li of L, the operating condition data Zi2…Zin at the corresponding time are obtained, and Li is assigned to Zi1 to form a characteristic two-dimensional array Z.

[0098] (2) Neural network reasoning:

[0099] The sample array Z is input into the neural network inference engine for training. Through error back propagation, automatic learning is performed to modify the connection weight of each node and the threshold of the corresponding node until the error is less than the specified value. In this way, the connection weight and threshold are determined, and the characteristic information distribution is stored in the neural network.

[0100] (3) Warning alarm output:

[0101] Monitor and track the operation of the equipment in real time, and obtain the statistical data K' of the number of equipment actions on the day; at the same time, establish the working condition data array Z'1...Z'n, input Z' into the neural network to calculate the normal number of actions V under the working condition that the neural network believes; compare V with K', and issue an alarm when K' is greater than V.

[0102] Monitor and track the operation of the equipment in real time, and obtain the equipment leakage data K' for the day; at the same time, establish the working condition data array Z'1...Z'n, input Z' into the neural network to calculate the normal number of actions V under the working condition that the neural network believes; compare V with K', and issue an alarm when K' is greater than V.

[0103] A similar method is used to monitor and track the running time and stop time of the equipment, and to issue an alarm for data that deviates from the historical normal operating status.

[0104] (4) Human-machine interface reminder

[0105] When the early warning alarm is triggered, the early warning alarm is counted and displayed according to the pre-arranged model tree hierarchy. In the alarm work interface, the light sign is configured. Nodes at any level on the model tree can be configured on the interface, and different levels of alarm information are marked with different colors, thus forming an intuitive alarm information display. At the same time, the alarm information is pushed through voice and App.

[0106] Prioritizes the use of deductive reasoning in neural network reasoning, i.e. starting from an initial fact (warning or alarm), continuously applying rules to draw conclusions (or perform specified actions), such as Figure 2 As shown, the method comprises the following steps:

[0107] (1) The sample data (Fact) obtained through historical data extraction is input into the working memory (WorkingMemory).

[0108] (2) Use the Pattern Matcher to compare the rules and data in the Rule Base.

[0109] (3) If there is a conflict in the execution of rules, that is, multiple rules are activated at the same time, the conflicting rules are placed in the conflict set.

[0110] (4) Resolve conflicts and place the activated rules into the agenda in order to arrange them in a relevant order.

[0111] (5) Use the rules in the Execution Engine Agenda. Repeat steps (2) to (5) until all the rules in the Agenda are executed.

[0112] Preferably, the neural network reasoning process is an engine that performs the actions specified in the rules based on the specified filter conditions contained in the rules and determines whether they match the real-time conditions at the runtime. Figure 3 As shown, the neural network reasoning process includes the following steps:

[0113] (1) Information services receive events and convert them into information elements.

[0114] Information services receive events and generate information element objects. Each information service generates information element objects of its own type. That is, each information element object generated by a specific information service based on information elements has the same format, but can have different attributes and rule sets. It should be noted that many different information services can be run on a machine, and different instances of the same information service can also be run. But in any case, each information service only generates information elements of its own type.

[0115] (2) The information element is passed to the queue manager

[0116] The information element is the basic building block of the rule engine. It is an object that contains all the information about a specific event. This information includes: the message, the application identifier that generated the event, the event that generated the event, the information element type, the related rule set, the common method, the common attributes, and some system related information.

[0117] The queue manager is used to manage queues of information element objects from different information services.

[0118] (3) The rule engine receives these information elements and applies the rules they carry to execute them until there are no more information elements in the queue manager.

[0119] First, a rule set is a collection of rules. Each rule contains a conditional filter and multiple actions. A conditional filter can contain multiple filter conditions. The conditional filter is a combination of multiple Boolean expressions, and the result of the combination is still a Boolean type. When the program is running, the action will be executed when the conditional filter value is true.

[0120] Preferably, the neural network reasoning process is that the reasoning engine receives information elements from the queue manager in sequence and checks the rules in the rule set carried by the information element according to the order in which the rules are defined. Figure 4 As shown, the neural network reasoning process includes:

[0121] (1) The rule engine checks the first rule and evaluates its condition filter. If the value is false, all actions associated with this rule are ignored and the next rule is executed. If the filter value of the second rule is true, all actions associated with this rule are executed in the order defined, and the next rule is executed after the execution is completed. After all the rules in the information element are executed, the information element will be destroyed and the next information element will be received from the queue manager.

[0122] (2) Two special actions are not considered in this process: Discard Action and Include Action. If the Discard Action is executed, all the following rules in the information element where it is located will be skipped and the information element where it is located will be destroyed. The rule engine will continue to receive the next information element from the queue manager. The Include Action is actually an action that includes other existing rule sets. If the Include Action is executed, the rule engine will pause and enter the included rule set. After the execution is completed, the rule engine will return to the original pause point to continue execution. This process will be performed recursively.

[0123] According to an embodiment of the present invention, an artificial intelligence alarm device for safe production in a hydropower plant is also provided.

[0124] Prioritize the artificial intelligence alarm device for safe production of hydropower plants, such as Figure 5 As shown, it includes: a historical data extraction module, which is used to collect multi-source heterogeneous data of the equipment object model; a neural network inference engine, which is used for tentative reasoning interpretation and conclusion proof; a warning alarm output module, which is used to monitor and track the deviation of the key points of the equipment from the historical normal operating status data; a human-machine interface reminder module, which is used for different user experiences after the hydropower plant warning alarm is triggered.

[0125] Preferably, a neural network inference engine, such as Figure 6 As shown in the figure, it includes: Rule Base, which is used to build rules and is the knowledge base; Working Memory, which is used to receive objects (Fact); Inference Engine, which is used to continuously apply rules to draw conclusions from an initial fact. Among them, the Inference Engine includes Pattern Matcher, which is used to determine the selection and timing of executing rules; Agenda, which is used to set the execution order of selected rules; Execution Engine, which is used to execute rules and other actions.

[0126] In order to improve the effectiveness of alarms and the work efficiency of maintenance personnel, and enable maintenance personnel to more efficiently control the operation status of the entire plant equipment, comprehensive alarms with logical combinations as trigger conditions have gradually emerged. Comprehensive alarms mainly use an object-oriented approach, putting related information together to form a logical object, and determining the necessity of an alarm through a logical combination or sequential combination of related signal states.

[0127] The above is a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principles of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.

Claims

1. An artificial intelligence alarm method for safe production in a hydropower plant, characterized in that: include: Historical data extraction step, neural network reasoning step, and early warning alarm output step; The historical data extraction steps include: establishing an equipment object model for the specific operating equipment of the hydropower plant, extracting the operating condition information and target information of the equipment; and extracting the protection data of the auxiliary equipment operation at the same time; eliminating obviously abnormal measurement data through variance and deviation calculation to form sample data; The neural network reasoning steps include: establishing multiple sets of deep learning neural networks according to flood season, non-flood season and year; inputting the sample data into the corresponding deep learning neural network, completing sample training, so as to obtain a neural network reasoning engine with feature information; wherein the neural network reasoning process can construct a reasoning engine including: a pattern matcher, an agenda and an execution engine; The early warning alarm output includes: according to the current month, the latest deep learning neural network of the flood season or non-flood season is used to process the working condition data to obtain the health standard; real-time monitoring and tracking of the equipment operation data, when the equipment operation deviates from the health standard, triggering a real-time alarm; and according to the current month, the neural network inference engine of the flood season or non-flood season in different years is used to process the working condition data respectively, to obtain the changes in the health data of previous years and form new sample data; and a new deep learning neural network inference engine is established to train the new sample data, dig out the trend of equipment operation, predict the possible operation of equipment in the next few years, and alarm when the predicted data of a future year exceeds the rated limit; Among them, the neural network reasoning steps include: Input the sample array Z into the neural network inference engine for training; perform automatic learning through error back propagation, modify the connection weight of each node and the threshold of the corresponding node until the error is less than the specified value; Among them, neural network reasoning adopts deductive methods, including: Starting from an initial fact, rules are continuously applied to draw conclusions or perform specified actions, where the fact is a warning or alarm. The deductive method includes: Input the sample data Fact obtained through historical data extraction into the working memory; Use Pattern Matcher to compare the rules and data Fact in the rule base Rule Base; if there is a conflict in the execution of the rules, that is, multiple rules are activated at the same time, put the conflicting rules into the conflict set Conflict Set; Resolve conflicts and put the activated rules into the agenda in order to arrange them in a relevant order; Use the rules in the Execution Engine agenda; repeat the above steps until all the rules in the agenda are executed.

2. The artificial intelligence alarm method for safe production of hydropower plants according to claim 1 is characterized in that: The historical data extraction step comprises: Obtain the action times Xi of the target equipment on day i from historical data; adopt the same method to obtain the operation data of n consecutive days within the target time interval to form the action times array X; obtain the middle value M of the array by variance calculation; traverse the array to calculate the deviation δXi of Xi to M, and when the deviation exceeds the rated value, Xi is considered invalid. This method is used to filter out invalid information in the equipment operation data to avoid the data impact caused by abnormal acquisition equipment, and obtain the effective action times array X'; obtain the working condition data Zi2...Zin at the corresponding time for all elements X'i of X', and assign Xi to Zi1 to form a characteristic two-dimensional array Z; the leakage data cannot be directly obtained from the operation data of the hydropower plant, but must be calculated through the statistical data of the action data of the pump group equipment related to the leakage. Therefore, the data is grouped and counted by day according to the equipment action analysis method, and the leakage data is calculated by the statistical results; Obtain the action time Xi of the target equipment on day i from historical data; adopt the same method to obtain the operation data of n consecutive days within the target time interval to form an action time array X; obtain the middle value M of the array; traverse the array to calculate the deviation δXi of Xi to M. When the deviation exceeds the rated value, Xi is considered invalid, and the effective action time array X' is obtained; similarly, the effective stop time array Y' is obtained; the leakage volume Li on day i is obtained through the leakage volume calculation formula f(X'i, Y'i); thus, the leakage volume array L is obtained; for all elements Li of L, the operating condition data Zi2…Zin at the corresponding time are obtained, and Li is assigned to Zi1 to form a characteristic two-dimensional array Z.

3. The artificial intelligence alarm method for safe production of hydropower plants according to claim 1 is characterized in that: The neural network reasoning process is an engine that performs the actions specified in the rules based on the specified filter conditions contained in the rules and determines whether they match the real-time conditions at runtime; including: Information services receive events and convert them into information elements; information services receive events and generate information element objects; each information service generates information element objects corresponding to its own type; that is, each information element object generated by a specific information service based on information elements has the same format, but may have different attributes and rule sets; The information element is passed to the queue manager: the information element is the basic building block of the rule engine. It is an object that contains all the information about a specific event; this information includes: the message, the application identifier that generated the event, the event that generated the event, the information element type, the related rule set, the common methods, the common attributes, and some system related information; the queue manager is used to manage the queues of information element objects from different information services; The rule engine receives these information elements and applies the rules they carry to execute them until there are no more information elements in the queue manager.

4. The artificial intelligence alarm method for safe production of hydropower plants according to claim 1 is characterized in that: A rule set is a collection of many rules; each rule contains a conditional filter and multiple actions; a conditional filter can contain multiple filter conditions; a conditional filter is a combination of multiple Boolean expressions, and the result of the combination is still a Boolean type; when the program is running, the action will be executed when the conditional filter value is true.

5. The artificial intelligence alarm method for safe production of hydropower plants according to claim 1 is characterized in that: The neural network reasoning process is that the reasoning engine receives information elements from the queue manager in sequence and checks the rules in the rule set carried by the information elements according to the definition order of the rules; wherein the neural network reasoning process includes: The rule engine checks the first rule and evaluates its condition filter. If the value is false, all actions related to this rule are ignored and the next rule is executed. If the filter value of the second rule is true, all actions related to this rule are executed in the order defined, and the next rule is executed after the execution is completed. After all the rules in the information element are executed, the information element will be destroyed, and then the next information element will be received from the queue manager. Two special actions are not considered in this process: Discard Action and Include Action. If the Discard Action is executed, all the following rules in the information element where it is located will be skipped, and the information element where it is located will be destroyed. The rule engine will continue to receive the next information element in the queue manager. The Include Action is actually an action that includes other existing rule sets. If the Include Action is executed, the rule engine will pause and enter the included rule set. After the execution is completed, the rule engine will return to the original pause point to continue execution. This process will be performed recursively.

6. The artificial intelligence alarm method for safe production of hydropower plants according to claim 1 is characterized in that: The early warning alarm output steps include: Monitor and track the operation of the equipment in real time, and obtain the statistical data K' of the number of equipment actions on the day; at the same time, establish the working condition data array Z'1...Z'n, input Z' into the neural network to calculate the normal number of actions V under the working condition that the neural network believes; compare V with K', and issue an alarm when K' is greater than V; Monitor and track the operation of the equipment in real time, and obtain the equipment leakage data K' for the day; at the same time, establish the working condition data array Z'1...Z'n, input Z' into the neural network to calculate the normal number of actions V under the working condition that the neural network believes; compare V with K', and issue an alarm when K' is greater than V.

7. The artificial intelligence alarm method for safe production of hydropower plants according to claim 1 is characterized in that: The method further comprises: The human-machine interface reminder steps include: organizing the actual production equipment of the hydropower plant according to a tree structure, and the final layer of equipment objects carries the real-time data information of the monitoring system to form a model tree; when the alarm is triggered, the information related to the alarm is also counted and displayed according to the hierarchical relationship of the model tree.

8. The artificial intelligence alarm method for safe production of hydropower plants according to claim 7 is characterized in that: The human-machine interface reminder step also includes: configuring a light sign on the alarm working interface, nodes at any level on the model tree can be configured on the interface, and different levels of alarm information are marked with different colors, thereby forming an intuitive alarm information display; and the alarm information is pushed via voice and App.