A water regulation method applied to water conservancy projects

By establishing a water demand prediction model and dynamic change analysis, the problems of short time series and low reliability of conventional prediction methods in the water demand data are solved, and high-precision prediction and water resource scheduling of the water demand in the water-receiving area are achieved.

CN113902160BActive Publication Date: 2024-11-08FUJIAN FANGYANG WATER CONSERVANCY INVESTMENT DEV CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202111009778.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-08-31
Publication Date
2024-11-08
Estimated Expiration
2041-08-31

AI Technical Summary

Technical Problem

The conventional water resource prediction method has a short water demand data series in my country and is low in reliability, resulting in large workload and low prediction accuracy.

Method used

Establish a water demand prediction model, including historical data prediction model, domestic water demand prediction model, production water demand prediction model and ecological water demand prediction model, and combine the geographical location of each water supply reservoir and the dynamic change model of available water resources to provide water-receiving areas water demand for the following year is forecast and water resource dispatch.

Benefits of technology

Through multi-model prediction and dynamic change analysis, the workload is reduced, the prediction accuracy is improved, and accurate prediction of the water demand in the water-receiving area and efficient water resource scheduling are achieved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113902160B_ABST
    Figure CN113902160B_ABST
Patent Text Reader

Abstract

The invention discloses a water regulation method applied to a water conservancy hub project, comprising: establishing a water demand prediction model, and predicting the water demand of a water receiving area in the next year according to the water demand prediction model; obtaining the daily inflow, real-time water level, rainfall, and outflow data of each water supply reservoir in the water receiving area in previous years, and establishing a dynamic change model of available water resources of each water supply reservoir; and water resource dispatching in the water receiving area. The beneficial effects of the invention are: predicting the water demand of the water receiving area in the next year by establishing a water demand prediction model, establishing a dynamic change model of available water resources in combination with the daily inflow, real-time water level, rainfall, and outflow data in previous years, and dispatching water resources in the water receiving area according to the geographical location of each water supply reservoir, the dynamic change model of available water resources, and the prediction result of the water demand of the water receiving area in the next year. Compared with the traditional method, the workload is small and the prediction accuracy is high.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of water regulation, and in particular to a water regulation method applied to a water conservancy project. Background Art

[0002] Water storage capacity prediction is one of the important contents of water resources planning and management, and is also an important part of the optimization and scheduling management of water supply systems. Since the time series of water demand data in my country is short and the reliability is low, the conventional prediction methods such as quota method, time series, regression analysis and gray prediction are not only labor-intensive, but also difficult to guarantee the prediction accuracy. Summary of the invention

[0003] The purpose of this section is to summarize some aspects of embodiments of the present invention and briefly introduce some preferred embodiments. Some simplifications or omissions may be made in this section and the specification abstract and the invention title of this application to avoid blurring the purpose of this section, the specification abstract and the invention title, and such simplifications or omissions cannot be used to limit the scope of the present invention.

[0004] In view of the above existing problems, the present invention proposes a water regulation method applied to a water conservancy project.

[0005] Therefore, the technical problem solved by the present invention is that the conventional prediction method has a large workload and low prediction accuracy.

[0006] In order to solve the above technical problems, the present invention provides the following technical solutions: a water regulation method applied to a water conservancy project, the water regulation method comprising the following steps:

[0007] Establishing a water demand prediction model, the water demand prediction model includes a historical data prediction model, a domestic water demand prediction model, a production water demand prediction model, and an ecological water demand prediction model, and predicting the water demand of the receiving area in the next year based on the water demand prediction model;

[0008] Obtain the daily inflow, real-time water level, rainfall, and outflow data of each water supply reservoir in the water receiving area over the years, and establish a dynamic change model of available water resources in each water supply reservoir;

[0009] Water resources scheduling in the receiving area is carried out based on the geographical location of each water supply reservoir, the dynamic change model of available water resources and the forecast results of water demand in the receiving area for the next year.

[0010] As a preferred solution of the water regulation method applied to water conservancy projects described in the present invention, the historical data prediction model obtains water demand data of previous years, establishes a dynamic change model of water demand of previous years, and predicts the water demand of next year through the dynamic change model of water demand of previous years.

[0011] As a preferred solution of the water regulation method applied to a water conservancy project described in the present invention, the establishment of a dynamic change model of water demand over the years includes:

[0012] Obtain the actual water demand data of previous years, calculate the change rate between the actual water demand of adjacent previous years, take this year's actual water demand data as the initial water demand data, and calculate The value of w0 is the initial water demand, w1 is the actual water demand in the previous year, When the value of is greater than the first preset value, further calculations are made The value of i is the actual water demand in the previous year, if When the value of is less than or equal to the first preset value, the average water demand change rate from last year to this year is calculated. Predict the water demand for next year based on the average water demand change rate and the actual water demand data for this year;

[0013] when When the value of is less than or equal to the first preset value, further calculation If the value of If the values ​​of are all less than or equal to the first preset value, further calculation If the value of If at least one of the values ​​of is greater than the first preset value, the average water demand change rate is calculated, and the water demand for next year is predicted based on the actual water demand data of this year.

[0014] like If the values ​​of are all less than or equal to the first preset value, further calculation And so on, until If at least one of the values ​​of is greater than the first preset value, the average water demand change rate is calculated using the water demand data from this year to the previous i-1 years, and then the water demand for next year is predicted based on the actual water demand data for this year.

[0015] As a preferred scheme of the water regulation method applied to water conservancy projects described in the present invention, the domestic water demand prediction model is based on the changing trend of domestic water use of residents in similar areas, combined with the domestic water use data, income level data, and water price data of the receiving areas, and adopts the quota method to predict the domestic water demand of urban residents and rural residents respectively.

[0016] As a preferred solution of the water regulation method applied to a water conservancy project described in the present invention, the method of using the quota method to predict the living water demand of urban residents and rural residents respectively includes:

[0017] Based on historical domestic water use data and population data statistics over the years, the per capita water consumption of people of all ages in the water-receiving areas is determined. Combined with the growth change rate of people of all age groups, the population data changes of all age groups in the next year are predicted. The predicted domestic water demand is calculated based on the predicted data of people of all age groups in the next year and the per capita water consumption of people of all age groups.

[0018] As a preferred scheme of the water regulation method applied to water conservancy projects described in the present invention, wherein: the production water demand prediction model includes an agricultural prediction model, an industrial prediction model, a construction industry prediction model, a tertiary industry prediction model and other prediction models, and collects irrigation area, per-mu water consumption quota, number of industrial enterprises, average water consumption quota of industrial enterprises, number of projects under construction in the construction industry, average water consumption quota of unit projects in the construction industry, number of tertiary industries, average water consumption quota of tertiary industries, number of other types and average water consumption quota of other types, and calculates the agricultural water demand, industrial water demand, construction industry water demand and tertiary industry water demand of the receiving area based on the collected data.

[0019] As a preferred solution of the water regulation method applied to the water conservancy project described in the present invention, wherein: the calculation of the agricultural water demand, industrial water demand, construction water demand and tertiary industry water demand of the water receiving area based on the collected data includes:

[0020] Based on the irrigation area, number of industrial enterprises, number of construction projects in progress, number of tertiary industries, and other types of quantities in the water-receiving area over the years, the data change trend is analyzed, and the agricultural water demand, industrial water demand, construction water demand, and tertiary industry water demand in the water-receiving area are calculated based on the change trend and quota data. The quota data include the per-mu water consumption quota, the average water consumption quota of industrial enterprises, the average water consumption quota of unit projects in the construction industry, the average water consumption quota of the tertiary industry, and the average water consumption quota of other types.

[0021] As a preferred scheme of the water regulation method applied to water conservancy projects described in the present invention, the ecological water demand prediction model is based on the urban ecological environment water demand and the rural ecological environment water demand. The urban ecological environment water demand includes urban river and lake water replenishment, green space water demand, and environmental sanitation water demand. The rural ecological environment water demand includes groundwater replenishment, artificial protective forest and grass water use, and wetland protection and restoration water use. The ecological water demand is predicted by combining the total length of the river and the average ecological water consumption quota per unit length of the river.

[0022] As a preferred solution of the water regulation method applied to a water conservancy project described in the present invention, the prediction of the water demand of the receiving area in the next year according to the water demand prediction model further includes:

[0023] Calculate the total predicted water demand of the living water demand prediction model, the production water demand prediction model, and the ecological water demand prediction model, combine the predicted water demand of the next year of the historical data prediction model, and further calculate the value of α1*X1+α2*X2 to obtain the final predicted water demand of the next year, where X1 is the total predicted water demand, X2 is the predicted water demand of the next year, α1+α2=1, and both α1 and α2 are not 0.

[0024] As a preferred solution of the water regulation method applied to the water conservancy project described in the present invention, the water resource regulation of the receiving area is carried out in combination with the geographical location of each water supply reservoir, the dynamic change model of available water resources and the forecast result of the water demand of the receiving area in the next year, including:

[0025] The functional relationships between daily inflow, rainfall, daily outflow and real-time water level are established respectively. Combined with the upstream and downstream relationships between the water supply reservoirs, water resources are dispatched for the receiving areas based on the final water demand forecast for the next year.

[0026] The beneficial effects of the present invention are as follows: by establishing a water demand prediction model, the water demand of the receiving area in the next year is predicted; by combining the daily inflow flow, real-time water level, rainfall, and outflow flow data of previous years, a dynamic change model of available water resources is established; and according to the geographical location of each water supply reservoir, the dynamic change model of available water resources and the prediction results of the water demand of the receiving area in the next year, water resources scheduling is carried out in the receiving area. Compared with traditional methods, the workload is small and the prediction accuracy is high. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for describing the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative labor. Among them:

[0028] Figure 1 The present invention is a schematic diagram of the steps of a water regulation method applied to a water conservancy project. DETAILED DESCRIPTION

[0029] In order to make the above-mentioned purposes, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are described in detail below in conjunction with the drawings of the specification. Obviously, the described embodiments are part of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary persons in the art without creative work should fall within the scope of protection of the present invention.

[0030] In the following description, many specific details are set forth to facilitate a full understanding of the present invention, but the present invention may also be implemented in other ways different from those described herein, and those skilled in the art may make similar generalizations without violating the connotation of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed below.

[0031] Secondly, the term "one embodiment" or "embodiment" as used herein refers to a specific feature, structure, or characteristic that may be included in at least one implementation of the present invention. The term "in one embodiment" that appears in different places in this specification does not necessarily refer to the same embodiment, nor does it refer to a separate or selective embodiment that is mutually exclusive with other embodiments.

[0032] The present invention is described in detail with reference to schematic diagrams. When describing the embodiments of the present invention, for the sake of convenience, the cross-sectional diagrams showing the device structure will not be partially enlarged according to the general scale, and the schematic diagrams are only examples, which should not limit the scope of protection of the present invention. In addition, in actual production, the three-dimensional dimensions of length, width and depth should be included.

[0033] At the same time, in the description of the present invention, it should be noted that the directions or positional relationships indicated by the terms "upper, lower, inner and outer" are based on the directions or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as limiting the present invention. In addition, the terms "first, second or third" are only used for descriptive purposes and cannot be understood as indicating or implying relative importance.

[0034] In the present invention, unless otherwise clearly specified and limited, the terms "install, connect, connect" should be understood in a broad sense, for example: it can be a fixed connection, a detachable connection or an integral connection; it can also be a mechanical connection, an electrical connection or a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0035] Example 1

[0036] Reference Figure 1 This embodiment provides a water regulation method applied to a water conservancy project, the method comprising the following steps:

[0037] Establishing a water demand prediction model, the water demand prediction model includes a historical data prediction model, a domestic water demand prediction model, a production water demand prediction model, and an ecological water demand prediction model, and predicting the water demand of the receiving area in the next year based on the water demand prediction model;

[0038] Obtain the daily inflow, real-time water level, rainfall, and outflow data of each water supply reservoir in the water receiving area over the years, and establish a dynamic change model of available water resources in each water supply reservoir;

[0039] Water resources scheduling in the receiving area is carried out based on the geographical location of each water supply reservoir, the dynamic change model of available water resources and the forecast results of water demand in the receiving area for the next year.

[0040] This method can solve the following problems: Water demand forecasting is one of the important contents of water resources planning and management, and is also an important part of the optimal scheduling and management of water supply systems. Since the time series of water demand data in my country is short and the reliability is low, conventional forecasting methods such as quota method, time series, regression analysis and gray forecasting are not only labor-intensive, but also difficult to guarantee the forecast accuracy.

[0041] Based on the above problems, this method first establishes multiple water demand prediction models, including historical data prediction model, living water demand prediction model, production water demand prediction model, and ecological water demand prediction model.

[0042] (1) Historical data prediction model

[0043] Based on the actual water demand data of the receiving areas in previous years, the water demand data for the next year can be predicted. The change rate calculation method of the actual water demand data of previous years can be used. Based on the calculation results and combined with the actual water demand data of this year, the water demand data for the next year can be predicted.

[0044] (2) Domestic water demand prediction model

[0045] Based on the current domestic water use survey and water-saving level analysis, according to the predicted results of development indicators, combined with water resources conditions and water supply capacity construction, reference to the local standard "Industry Water Use Quota", reference to the changing trends of domestic water use of residents in similar regions, combined with consideration of local domestic water use habits, income levels, water prices, etc., comprehensive formulation of reasonable urban domestic water quotas and rural domestic water quotas, the quota method is used to predict the urban and rural residents' domestic water demand respectively.

[0046] (3) Production water demand prediction model

[0047] Production water demand is divided into agricultural water demand, industrial water demand, construction water demand, tertiary industry water demand, and other types of production water demand. Agricultural water demand includes farmland irrigation, forest and fruit land irrigation, and pasture irrigation water demand, which is estimated based on irrigation quotas and irrigation water utilization coefficients. Combined with crop composition and demand in different growth periods, irrigation systems, and monthly precipitation distribution processes, combined with typical surveys, a monthly irrigation water distribution process is proposed. The water demand for poultry and livestock breeding can be predicted according to the development indicators of large and small livestock and poultry and the average daily water consumption of livestock. Industrial water demand is combined with the number of industrial enterprises and the average water consumption quota of industrial enterprises. Construction water demand is combined with the number of construction projects under construction and the average water consumption quota of unit projects in the construction industry. The tertiary industry water demand is combined with the number of tertiary industries and the average water consumption quota of the tertiary industry. Other types of production water demand are combined with the number of other types and the average water consumption quota of other types to predict production water demand.

[0048] (4) Ecological water demand prediction model

[0049] The water demand for the ecological environment outside the river channel refers to the amount of water that needs to be artificially supplemented to protect, restore or build the ecological environment of a given area. The water demand for the ecological environment outside the river channel is consumable water use, which is divided into the water demand for the prosperous ecological environment (including water replenishment for urban rivers and lakes, water demand for green spaces, water demand for environmental sanitation, etc.) and the water demand for the rural ecological environment (including groundwater replenishment, water use for artificial protective forests and grasslands, water use for wetland protection and restoration, etc.).

[0050] The functional relationships between daily inflow, rainfall, daily outflow and real-time water level are established respectively. Combined with the upstream and downstream relationships between the water supply reservoirs, water resources are dispatched for the receiving areas according to the forecast results of water demand for the next year.

[0051] Example 2

[0052] Reference Figure 1 This embodiment provides a water regulation method applied to a water conservancy project, by acquiring water demand data over the years, establishing a dynamic change model of water demand over the years, and predicting the water demand for the next year through the dynamic change model of water demand over the years.

[0053] The establishment of a dynamic change model of water demand over the years includes:

[0054] Obtain the actual water demand data of previous years, calculate the change rate between the actual water demand of adjacent previous years, take this year's actual water demand data as the initial water demand data, and calculate The value of w0 is the initial water demand, w1 is the actual water demand in the previous year, When the value of is greater than the first preset value, further calculations are made The value of i is the actual water demand in the previous year, if When the value of is less than or equal to the first preset value, the average water demand change rate from last year to this year is calculated. Predict next year's water demand based on average water demand change rate and this year's actual water demand data;

[0055] when When the value of is less than or equal to the first preset value, further calculation If the value of If the values ​​of are all less than or equal to the first preset value, further calculation If the value of If at least one of the values ​​of is greater than the first preset value, the average water demand change rate is calculated, and the water demand for next year is predicted based on the actual water demand data of this year.

[0056] like If the values ​​of are all less than or equal to the first preset value, further calculation And so on, until If at least one of the values ​​of is greater than the first preset value, the average water demand change rate is calculated using the water demand data from this year to the previous i-1 years, and then the water demand for next year is predicted based on the actual water demand data for this year.

[0057] By obtaining the actual water demand data of previous years, analyzing the water demand change rate over the years, taking this year's water demand data as the initial value, calculating the water demand change rate between this year and last year, and then calculating the water demand change rate between last year and the year before last, and so on, we can get multiple sets of water demand change rate data. Generally, over a long period of time, there will not be a large difference in the water demand change rate. However, at a time point when society is developing rapidly, there may be large fluctuations in actual water demand data. By calculating the water demand change rate between two adjacent years and comparing it with the preset value, if the calculated water demand change rate is less than the preset value, it means that the actual water demand data fluctuation between the two adjacent years is not large, and the water demand change rate between the two years can be The water demand change rate is used as the basic data set, and then the actual water demand change rate of last year and the year before last is calculated, and the fluctuation of water demand data of last year and the year before last is analyzed, because the water demand change rate may continue to increase or decrease within a certain period of time. If only the water demand change rate of last year and the year before last is referred to, it can only mean that the fluctuation between the actual water demand data of last year and the year before last is not large, but it cannot show the change between the actual water demand data of the year before last and this year. Therefore, while comparing the water demand change rate of last year and the year before last with the preset value, the actual water demand change rate and preset value between this year and the year before last are also compared, and the water demand change rate that meets the conditions is put into the basic data set until it does not meet the conditions, and then the average value of the water demand change rate in the basic data set is calculated.

[0058] The domestic water demand prediction model is based on the changing trend of domestic water use of residents in similar areas, combined with the domestic water use data, income level data, and water price data of the receiving areas, and uses the quota method to predict the domestic water demand of urban and rural residents respectively.

[0059] The quota method is used to predict the living water demand of urban and rural residents, including:

[0060] Based on historical domestic water use data and population data statistics over the years, the per capita water consumption of people of all ages in the water-receiving areas is determined. Combined with the growth change rate of people of all age groups, the population data changes of all age groups in the next year are predicted. The predicted domestic water demand is calculated based on the predicted data of people of all age groups in the next year and the per capita water consumption of people of all age groups.

[0061] The production water demand prediction model includes agricultural prediction model, industrial prediction model, construction industry prediction model, tertiary industry prediction model and other prediction models. It collects data on irrigation area, average water consumption quota per mu, number of industrial enterprises, average water consumption quota of industrial enterprises, number of projects under construction in the construction industry, average water consumption quota per unit project in the construction industry, number of tertiary industries, average water consumption quota of tertiary industries, number of other types and average water consumption quota of other types. The agricultural water demand, industrial water demand, construction industry water demand and tertiary industry water demand of the receiving area are calculated based on the collected data.

[0062] The agricultural water demand, industrial water demand, construction water demand and tertiary industry water demand of the water receiving area are calculated based on the collected data, including:

[0063] Based on the irrigation area, number of industrial enterprises, number of construction projects in progress, number of tertiary industries, and number of other types in the receiving area over the years, we analyze the data change trends, and calculate the agricultural water demand, industrial water demand, construction water demand, and tertiary industry water demand in the receiving area based on the change trends and quota data. The quota data include the per-mu water consumption quota, the average water consumption quota of industrial enterprises, the average water consumption quota of unit projects in the construction industry, the average water consumption quota of the tertiary industry, and the average water consumption quota of other types.

[0064] The ecological water demand prediction model is based on the urban ecological environment water demand and the rural ecological environment water demand. The urban ecological environment water demand includes water replenishment for urban rivers and lakes, water demand for green spaces, and water demand for environmental sanitation. The rural ecological environment water demand includes groundwater replenishment, water use for artificial protective forests and grasslands, and water use for wetland protection and restoration. The ecological water demand is predicted based on the total length of the river and the average ecological water consumption per unit length of the river.

[0065] The forecast of water demand in the receiving area for the next year based on the water demand forecast model also includes:

[0066] The total predicted water demand of the domestic water demand prediction model, the production water demand prediction model, and the ecological water demand prediction model is calculated, and the predicted water demand of the next year of the historical data prediction model is combined. The final predicted water demand of the next year is obtained by further calculating the value of α1*X1+α2*X2, wherein X1 is the total predicted water demand, X2 is the predicted water demand of the next year, α1+α2=1, and both α1 and α2 are not 0. The historical data prediction model is used to analyze the overall water demand data to obtain a predicted water demand of the next year. The domestic water demand prediction model, the production water demand prediction model, and the ecological water demand prediction model are used to further refine the prediction conditions of the water demand, and the predicted water demand values ​​under multiple prediction models are obtained by calculation. The predicted water demand values ​​under multiple prediction models are then summed and calculated to obtain the total predicted water demand of the next year. The total predicted water demand and the predicted water demand of the next year are then processed by weighted average to obtain the final predicted water demand of the next year.

[0067] Combined with the geographical location of each water supply reservoir, the dynamic change model of available water resources and the forecast results of the water demand of the receiving area in the next year, the water resources dispatch of the receiving area includes:

[0068] The functional relationships between daily inflow, rainfall, daily outflow and real-time water level are established respectively. Combined with the upstream and downstream relationships between the water supply reservoirs, water resources are dispatched for the receiving areas based on the final water demand forecast for the next year.

[0069] It should be appreciated that embodiments of the present invention may be implemented or enforced by computer hardware, a combination of hardware and software, or by computer instructions stored in a non-transitory computer-readable memory. The method may be implemented in a computer program using standard programming techniques - including a non-transitory computer-readable storage medium configured with a computer program, wherein the storage medium so configured causes the computer to operate in a specific and predefined manner - according to the methods and drawings described in the specific embodiments. Each program may be implemented in a high-level procedural or object-oriented programming language to communicate with a computer system. However, if desired, the program may be implemented in an assembly or machine language. In any case, the language may be a compiled or interpreted language. In addition, the program may be run on a programmed ASIC for this purpose.

[0070] Furthermore, the operations of the processes described herein may be performed in any suitable order unless otherwise indicated herein or otherwise clearly contradicted by context. The processes described herein (or variations and / or combinations thereof) may be performed under the control of one or more computer systems configured with executable instructions, and may be implemented as code (e.g., executable instructions, one or more computer programs, or one or more applications) that is executed collectively on one or more processors, by hardware, or a combination thereof. The computer program includes a plurality of instructions that may be executed by one or more processors.

[0071] Further, the method can be implemented in any type of computing platform that is operably connected to a suitable computer, including but not limited to a personal computer, a minicomputer, a mainframe, a workstation, a network or distributed computing environment, a separate or integrated computer platform, or in communication with a charged particle tool or other imaging device, etc. Aspects of the present invention can be implemented in machine-readable code stored on a non-transitory storage medium or device, whether removable or integrated into a computing platform, such as a hard disk, an optical read and / or write storage medium, a RAM, a ROM, etc., so that it can be read by a programmable computer, and when the storage medium or device is read by the computer, it can be used to configure and operate the computer to perform the process described herein. In addition, the machine-readable code, or part thereof, can be transmitted via a wired or wireless network. When such media includes instructions or programs that implement the steps described above in conjunction with a microprocessor or other data processor, the invention described herein includes these and other different types of non-transitory computer-readable storage media. When programmed according to the methods and techniques described in the present invention, the present invention also includes the computer itself. The computer program can be applied to input data to perform the functions described herein, thereby converting the input data to generate output data stored in a non-volatile memory. The output information can also be applied to one or more output devices such as a display. In a preferred embodiment of the present invention, the converted data represents a physical and tangible object, including a specific visual depiction of the physical and tangible object produced on a display.

[0072] As used in this application, the terms "component", "module", "system", etc. are intended to refer to a computer-related entity, which can be hardware, firmware, a combination of hardware and software, software, or software in operation. For example, a component can be, but is not limited to: a process running on a processor, a processor, an object, an executable file, a thread in execution, a program, and / or a computer. As an example, an application running on a computing device and the computing device can both be components. One or more components can exist in a process and / or thread in execution, and a component can be located in a computer and / or distributed between two or more computers. In addition, these components can be executed from various computer-readable media having various data structures thereon. These components can communicate in a local and / or remote process manner, such as according to a signal having one or more data packets (e.g., data from a component that interacts with another component in a local system, a distributed system, and / or interacts with other systems in a signal manner through a network such as the Internet).

[0073] It should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solutions of the present invention may be modified or replaced by equivalents without departing from the spirit and scope of the technical solutions of the present invention, which should all be included in the scope of the claims of the present invention.

Claims

1. A water regulation method applied to a water conservancy project, characterized in that: The water adjustment method comprises the following steps: Establishing a water demand prediction model, the water demand prediction model includes a historical data prediction model, a domestic water demand prediction model, a production water demand prediction model, and an ecological water demand prediction model, and predicting the water demand of the receiving area in the next year based on the water demand prediction model; Obtain the daily inflow, real-time water level, rainfall, and outflow data of each water supply reservoir in the water receiving area over the years, and establish a dynamic change model of available water resources in each water supply reservoir; Carry out water resource dispatching in the water receiving area in combination with the geographical location of each water supply reservoir, the dynamic change model of available water resources and the forecast result of water demand in the water receiving area in the next year; The historical data prediction model obtains water demand data of previous years, establishes a dynamic change model of water demand of previous years, and predicts the water demand of next year through the dynamic change model of water demand of previous years; The establishment of a dynamic change model of water demand over the years includes: Obtain the actual water demand data of previous years, calculate the change rate between the actual water demand of adjacent previous years, take this year's actual water demand data as the initial water demand data, and calculate The value of w0 is the initial water demand, w1 is the actual water demand in the previous year, When the value of is greater than the first preset value, further calculations are made The value of i is the actual water demand in the previous year, if When the value of is less than or equal to the first preset value, the average water demand change rate from last year to this year is calculated. Predict the water demand for next year based on the average water demand change rate and the actual water demand data for this year; when When the value of is less than or equal to the first preset value, further calculation If the value of If the values ​​of are all less than or equal to the first preset value, further calculation If the value of If at least one of the values ​​of is greater than the first preset value, the average water demand change rate is calculated, and the water demand for next year is predicted based on the actual water demand data of this year. like If the values ​​of are all less than or equal to the first preset value, further calculation And so on, until If at least one of the values ​​of is greater than the first preset value, the average water demand change rate is calculated using the water demand data from this year to the previous i-1 years, and then the water demand for next year is predicted based on the actual water demand data for this year.

2. The water regulation method applied to a water conservancy project according to claim 1, characterized in that: The domestic water demand prediction model is based on the trend of domestic water use of residents in similar areas, combined with domestic water use data, income level data, and water price data of the receiving areas, and uses the quota method to predict the domestic water demand of urban and rural residents respectively.

3. The water regulation method applied to a water conservancy project according to claim 2 is characterized in that: The water demand forecast for urban and rural residents using the quota method includes: Based on historical domestic water use data and population data statistics over the years, the per capita water consumption of people of all ages in the water-receiving areas is determined. Combined with the growth change rate of people of all age groups, the population data changes of all age groups in the next year are predicted. The predicted domestic water demand is calculated based on the predicted data of people of all age groups in the next year and the per capita water consumption of people of all age groups.

4. The water regulation method applied to a water conservancy project according to claim 3 is characterized in that: The production water demand prediction model includes an agricultural prediction model, an industrial prediction model, a construction industry prediction model, a tertiary industry prediction model and other prediction models, which collect information on irrigation area, per-mu water consumption quota, the number of industrial enterprises, the average water consumption quota of industrial enterprises, the number of projects under construction in the construction industry, the average water consumption quota of unit projects in the construction industry, the number of tertiary industries, the average water consumption quota of the tertiary industry, the number of other types and the average water consumption quota of other types, and calculate the agricultural water demand, industrial water demand, construction industry water demand and tertiary industry water demand in the receiving area based on the collected data.

5. The water regulation method applied to a water conservancy project according to claim 4 is characterized in that: The calculation of agricultural water demand, industrial water demand, construction water demand and tertiary industry water demand in the water receiving area based on the collected data includes: Based on the irrigation area, number of industrial enterprises, number of construction projects in progress, number of tertiary industries, and other types of quantities in the water-receiving area over the years, the data change trend is analyzed, and the agricultural water demand, industrial water demand, construction water demand, and tertiary industry water demand in the water-receiving area are calculated based on the change trend and quota data. The quota data include the per-mu water consumption quota, the average water consumption quota of industrial enterprises, the average water consumption quota of unit projects in the construction industry, the average water consumption quota of the tertiary industry, and the average water consumption quota of other types.

6. The water regulation method applied to a water conservancy project according to claim 5 is characterized in that: The ecological water demand prediction model is based on the urban ecological environment water demand and the rural ecological environment water demand. The urban ecological environment water demand includes water replenishment of urban rivers and lakes, water demand of green spaces, and water demand for environmental sanitation. The rural ecological environment water demand includes groundwater replenishment, water use for artificial protective forests and grasslands, and water use for wetland protection and restoration. The ecological water demand is predicted by combining the total length of the river and the average ecological water consumption quota per unit length of the river.

7. The water regulation method applied to a water conservancy project according to claim 6 is characterized in that: The forecasting of the water demand of the receiving area in the next year according to the water demand forecasting model also includes: Calculate the total predicted water demand of the living water demand prediction model, the production water demand prediction model, and the ecological water demand prediction model, combine the predicted water demand of the next year of the historical data prediction model, and further calculate the value of α1*X1+α2*X2 to obtain the final predicted water demand of the next year, where X1 is the total predicted water demand, X2 is the predicted water demand of the next year, α1+α2=1, and both α1 and α2 are not 0.

8. The water regulation method applied to a water conservancy project according to claim 7, characterized in that: The water resource dispatching of the receiving area in combination with the geographical location of each water supply reservoir, the dynamic change model of available water resources and the forecast result of the water demand of the receiving area in the next year includes: The functional relationships between daily inflow, rainfall, daily outflow and real-time water level are established respectively. Combined with the upstream and downstream relationships between the water supply reservoirs, water resources are dispatched for the receiving areas based on the final water demand forecast for the next year.