Optimal selection method for water, wind and solar planning schemes based on hierarchical optimization model
Through the method based on the stratified optimization model, the development plan set of wind power and photovoltaic power stations around the hydropower station is evaluated, and the output and power abandonment of water, wind and light planning systems are optimized, which solves the problem of planning system selection in the existing technology and realizes economicality and technical evaluation, improving optimization efficiency and feasibility.
Patent Information
- Application Number
- CN202111113246.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-09-23
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2041-09-23
AI Technical Summary
The existing technology is difficult to effectively consider the construction and preferred methods in actual operation of water, wind and light planning systems, especially in the different locations and capacity of wind power and photovoltaic power stations around hydropower stations, which makes it difficult to evaluate the economic and technical nature of the planning system. Moreover, the existing simulation methods are huge in number of decision variables and constraints, and are difficult to solve.
Using the optimization method of water, wind and light planning scheme set based on the stratified optimization model, the development scheme set of wind power stations and photovoltaic power stations is determined, and the medium- and long-term and short-term scheduling models are established to optimize the output curve of water, wind and light planning systems and Discard power, evaluate the total on-grid power and the discarded power, calculate the net income, and select the optimal planning scheme.
The economic and technical evaluation of water, wind and light planning systems has been realized, and the optimal capacity of complementary wind and photoelectric stations of hydropower stations has been determined, which has significantly reduced the number of optimization decision variables and constraints, improved the optimization solution speed and convergence rate, and provided Practical and feasible planning schemes were made.
Smart Images

Figure CN113947499B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of renewable energy power generation planning, and in particular to a method for optimizing a set of water, wind and light planning schemes based on a hierarchical optimization model. Background Art
[0002] With the continuous growth of energy demand and the increasing damage to the ecological environment caused by the long-term use of fossil fuels, the importance of renewable energy development has become increasingly clear. Hydropower, wind power and photovoltaic power are the main forms of renewable energy at present. Since the above three types of power stations are affected by climate and weather conditions, the output of hydropower stations, wind power stations and photovoltaic power stations are volatile and uncertain on different time scales. Among them, hydropower stations have different regulation capabilities in the short and long term, and can complement wind and photovoltaic stations in terms of output and transmission to achieve better safety and economic benefits. However, the water, wind and light complementary scheme is subject to multiple restrictions such as reservoir capacity, installed capacity, reservoir scheduling principles, power grid scheduling requirements, as well as the output characteristics, distribution, investment and operation economy of wind and photovoltaic power stations. Determining the water, wind and light complementary power generation scheme is a complex issue.
[0003] Patent CN107240932B discloses a photovoltaic capacity optimization method in a hydro-photovoltaic system that takes into account hydropower and photovoltaic grid-connected electricity prices and photovoltaic power abandonment and output deviation penalties for standby units; Patent CN107256450B discloses a simplified photovoltaic power station investment and operation cost model and considers the maximum total power generation and output guarantee rate constraints in the long-term operation stage of the hydro-photovoltaic system; Patent application CN110838733A discloses a photovoltaic capacity configuration method for a hydro-photovoltaic system based on a typical daily load and a photovoltaic daily output probability model using scenario reduction; Patent application CN110729767A discloses a wind and solar capacity configuration method for a hydro-power grid based on typical daily scenarios in spring, summer, autumn and winter; Patent application CN112165123A discloses a photovoltaic capacity calculation method for a small and medium-sized hydro-photovoltaic complementary system based on photovoltaic output and daily output simulation analysis under typical scenarios of reservoir runoff based on different weather probability models. Patent application CN112184016A discloses a method for determining the scale of a hydro-photovoltaic complementary integrated photovoltaic system based on the mutual capacity of a hydropower station and the estimation of the transmission channel. Current engineering practice lacks an optimization method that can effectively consider the construction and actual operation of water, wind and light planning systems.
[0004] In actual engineering, the locations and capacities of wind power and photovoltaic power plants that can be built around hydropower stations are different. The output characteristics of each wind power station and photovoltaic power station are also different. The aggregation plan needs to be determined according to the actual wind and photovoltaic construction plan, which will affect the economic efficiency of the construction and operation of the water, wind, and photovoltaic planning system. Hydropower stations have fluctuations of different natures in long and short cycles. The scheduling of reservoirs needs to be considered on a time scale of one year or many years. The real-time fluctuations in wind and photovoltaic output require accurate simulation of short-term operating conditions when planning the water, wind, and photovoltaic planning system. The existing simulation method only simulates and analyzes the multi-year operating status of the water, wind, and photovoltaic planning system hour by hour, which has the problem of a large number of decision variables and constraints that are difficult to solve. Summary of the invention
[0005] The purpose of the present invention is to provide a method for optimizing a set of water, wind and solar planning schemes based on a hierarchical optimization model, which can determine the optimal hydropower station complementary wind and photovoltaic power station capacity based on economic and technical evaluation of different water, wind and solar planning schemes during the construction of water, wind and solar complementary projects.
[0006] To achieve the above purpose, the present invention has developed a method for optimizing a set of water, wind and light planning schemes based on a hierarchical optimization model, comprising the following steps:
[0007] Step 1), according to a number of wind power station sites and a number of photovoltaic power station sites to be developed around the hydropower station, determine a set of wind and solar development plans consisting of at least two of the wind power station sites and the photovoltaic power station sites;
[0008] Step 2) Complementing the hydropower station with each group of wind and solar development plans to form a water, wind and solar planning plan; calculating the total initial investment cost of each group of water, wind and solar planning plans according to the site composition factors in each group of wind and solar development plans;
[0009] Step 3), for each group of water, wind, and light planning schemes, respectively establish an upper medium- and long-term optimization scheduling model and a lower short-term optimization scheduling model; according to the upper medium- and long-term scheduling objectives, solve the optimal operation mode of the medium- and long-term scheduling model, and determine the output curve and abandoned power of the water, wind, and light planning systems in the medium and long term; according to the lower short-term scheduling objectives, solve the optimal operation mode of the short-term scheduling model, and determine the output curve and abandoned power of the water, wind, and light planning systems in the short term; finally, determine the total grid-connected power and abandoned power of the water, wind, and light planning systems during the assessment period;
[0010] There are two upper-level medium- and long-term dispatching goals: the first is to maximize the total power generation of the water, wind, and solar planning systems, and the second is to minimize the deviation of the total output of the water, wind, and solar planning systems from the load demand of the consumption market; there are two lower-level short-term dispatching goals: the first is to maximize the total power generation of the water, wind, and solar planning systems, and the second is to minimize the deviation of the total output of the water, wind, and solar planning systems from the load demand of the consumption market;
[0011] The medium- and long-term scheduling model is expressed as two objective functions:
[0012]
[0013] in,
[0014] F1 is the total grid-connected electricity during the assessment period, in MWh;
[0015] F2 is the cumulative value of the deviation of the average power per unit value on the grid from the load per unit value during the assessment period;
[0016] D is the total number of time periods;
[0017] ΔT d is the number of hours in period d;
[0018] N d is the average grid-connected power of the water, wind and solar planning systems in time period d, are the average outputs of the hydropower station, wind power station and photovoltaic power station in time period d, is the average power abandonment during period d, in MW;
[0019] Its per unit value is divided by N d By outbound transmission channel capacity;
[0020] is the per unit value of the average load power in the consumption market during the period d;
[0021] The short-term scheduling model is expressed as two objective functions:
[0022]
[0023] in,
[0024] F1'(d) is the total grid-connected power in period d, in MWh;
[0025] F′2(d) is the cumulative value of the deviation of the average per-unit power value of the grid during the period d from the per-unit value of the load;
[0026] T is the total number of short-term scheduling periods contained in the medium- and long-term scheduling cycle d period;
[0027] ΔTt is the short-term scheduling time interval, in h;
[0028] N d,t is the average grid-connected power of the water, wind and solar planning systems in period t during period d, are the average outputs of the hydropower station, wind power station and photovoltaic power station in the t period during the d period, is the average power abandonment power in period t during period d, in MW;
[0029] is its per unit value;
[0030] is the per unit value of the average load power in the consumption market during the period d [d, t-1~d, t];
[0031] Step 4), according to the total grid-connected power and abandoned power of each group of water, wind and solar planning systems during the assessment period, calculate the total electricity sales revenue of the water, wind and solar planning systems; calculate the total operation and maintenance costs of the water, wind and solar planning systems during the assessment period; according to the total electricity sales revenue, total operation and maintenance costs and total initial investment costs of the water, wind and solar planning systems during the assessment period, obtain the net income of each group of water, wind and solar planning schemes during the assessment period;
[0032] Step 5), comparing the economic and technical evaluations of each group of water, wind and light planning schemes, and selecting the best water, wind and light planning scheme in terms of engineering.
[0033] Furthermore, in step 2), the constituent factors of the site include the site, power generation capacity, unit cost of the wind power station, unit cost of the photovoltaic power station, power generation hours, voltage level of the collection line, length of the collection line and unit cost of the collection line.
[0034] Furthermore, in step 2), the total initial investment cost includes the initial investment cost of the wind power station, the photovoltaic power station, the hydropower station and the collection grid, and the total initial investment cost is determined according to traditional engineering experience and methods.
[0035] Furthermore, the constraints of the medium- and long-term scheduling model include:
[0036] a) Water balance constraints:
[0037]
[0038] b) Reservoir capacity and water level constraints:
[0039] V min <V d <V max
[0040] V1=V0
[0041] V D+1 =V end
[0042]
[0043] c) Downstream flow restriction:
[0044]
[0045] d) Hydropower output constraints:
[0046]
[0047] e) Transmission channel capacity constraints:
[0048]
[0049] in,
[0050] V d is the initial storage capacity of the reservoir in period d;
[0051] is the average inflow into the reservoir during period d;
[0052] is the average power generation flow in period d;
[0053] is the average water discharge during period d;
[0054] V min and V max are the minimum and maximum storage capacities of the reservoir subject to the upper and lower bounds of the water level during the assessment period;
[0055] V0 and V end are the initial and final storage capacities of the reservoir during the assessment period;
[0056] and They represent the lower and upper bound constraints of the reservoir during the assessment period respectively;
[0057] Q min and Q max They represent the minimum and maximum discharge flow constraints of the reservoir during the assessment period respectively;
[0058] and They represent the minimum and maximum power generation constraints of the hydropower unit during the assessment period respectively;
[0059] They represent the average output of the hydropower station, wind power station and photovoltaic power station in time period d, represents the average power abandonment during the period d;
[0060] N max Plan the maximum transmission capacity of the system transmission channels for water, wind and solar power;
[0061] The constraints of the short-term scheduling model include:
[0062] a) Water balance constraints:
[0063]
[0064] b) Reservoir capacity and water level constraints:
[0065] V t,min <V d,t <V t,max
[0066] V t,1 =V0
[0067] V t,T+1 =V end
[0068]
[0069] c) Downstream flow restriction:
[0070]
[0071] d) Hydropower output constraints:
[0072]
[0073] e) Transmission channel capacity constraints:
[0074]
[0075] in,
[0076] V d,t is the initial storage capacity of the reservoir in period t during period d;
[0077] is the average inflow into the reservoir during period t;
[0078] is the average water discharge in period t;
[0079] V t,min and V t,max are the minimum and maximum storage capacities of the reservoir subject to the upper and lower bounds of the water level in period t, respectively;
[0080] V0 and V end are the initial and final storage capacities of the reservoir in period d, respectively;
[0081] and They represent the lower and upper bound constraints of the reservoir in period t respectively;
[0082] Q t,min and Q t,max They represent the minimum and maximum discharge flow constraints of the reservoir in period t respectively;
[0083] and They represent the minimum and maximum power generation constraints of the hydropower unit in period t respectively;
[0084] N max Plan the maximum transmission capacity of the system transmission channels for water, wind and solar power.
[0085] Furthermore, the storage capacity of the reservoir at the end of the short-term dispatch period needs to be consistent with the medium- and long-term dispatch results, that is:
[0086] |V′ d+1 -V d,T | / V′ d+1 <ε
[0087] in,
[0088] V′ d+1 The initial reservoir water volume in the d+1 period is for medium- and long-term scheduling;
[0089] V d,T The reservoir water volume at t = d + T for short-term dispatch, i.e., the reservoir water volume at the end of period d;
[0090] ε is the allowable deviation between short-term scheduling results and medium- and long-term scheduling results.
[0091] Furthermore, in step 4), the total operation and maintenance cost includes the operation and maintenance costs of wind power stations, photovoltaic power stations, hydropower stations and grids under the water, wind and light planning schemes, and the operation and maintenance cost estimation method of the hydropower stations and grids is determined based on traditional engineering experience and methods.
[0092] Furthermore, in step 5), the economic evaluation includes evaluating the cost per kilowatt-hour, total investment return rate, and capital investment return rate under the water, wind, and solar planning schemes; the technical evaluation includes evaluating the spare capacity and peak-shaving capacity of the hydropower station under the water, wind, and solar planning schemes.
[0093] Furthermore, the hierarchical optimization model includes an upper-layer medium- and long-term optimization scheduling model and a lower-layer short-term optimization scheduling model.
[0094] The advantages of the present invention are:
[0095] 1. It can comprehensively consider the actual situation around the hydropower station and the feasibility of the project, and provide a practical and feasible set of wind and solar development plans consisting of at least two sites among the wind power station site and the photovoltaic power station site, so as to reduce the workload of plan evaluation and improve the feasibility of the optimization results;
[0096] 2. By establishing a long-term and short-term coordinated operation hierarchical optimization model for each group of water, wind and solar planning schemes, the long-term and short-term hourly optimal operating conditions of the water, wind and solar planning systems of this group are obtained respectively, and then the accurate grid-connected power and abandoned power of different planning schemes during the assessment period are obtained;
[0097] 3. The long-term and short-term coordinated operation model adopts a hierarchical optimization method, which can significantly reduce the number of single optimization decision variables and constraints, and improve the optimization solution speed and convergence rate.
[0098] The method for optimizing the set of water, wind and solar planning schemes based on a hierarchical optimization model of the present invention starts from the perspective of the planning and construction of wind and solar power stations complementary to hydropower stations in actual engineering, accurately simulates the long- and short-term operating conditions of different water, wind and solar planning systems, and conducts economic and technical evaluations to determine the optimal water, wind and solar planning and construction schemes. BRIEF DESCRIPTION OF THE DRAWINGS
[0099] Figure 1 It is a flow chart of a preferred embodiment of the method for selecting a water, wind and light planning scheme set based on a hierarchical optimization model proposed by the present invention;
[0100] Figure 2 Schematic diagram of the sites of wind and photovoltaic power stations that can be developed around the hydropower station, installed capacity and collection plan in the embodiment;
[0101] Figure 3 yes Figure 2 Hourly output curve of photovoltaic power station in;
[0102] Figure 4 yes Figure 2 Hourly output curve of wind power station in;
[0103] Figure 5 yes Figure 2 The deca-day water level curve of the hydropower station;
[0104] Figure 6 yes Figure 2 The total output curve of the water, wind and solar planning system in each decade in the water, wind and solar planning scheme [x1, x2, y1];
[0105] Figure 7 yes Figure 6 The hourly output and hourly power abandonment curves of water, wind and solar power in the first decade of the hydro, wind and solar power planning system. DETAILED DESCRIPTION
[0106] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0107] In the description of the present invention, it is necessary to understand that the terms "length", "width", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the invention.
[0108] The present invention provides a method for optimizing a set of water, wind and light planning schemes based on a hierarchical optimization model. Figure 1 As shown, the following steps are included:
[0109] Step 1) According to a number of wind power station sites and a number of photovoltaic power station sites to be developed around the hydropower station, a set of wind and solar development plans consisting of at least two of the wind power station sites and the photovoltaic power station sites is determined.
[0110] For example, the average flow rate of a hydropower station site is 144m 3 / s, with an average annual runoff of 4.54 billion m 3 The normal water level of the reservoir is 1140m, the operating control water level in the main flood season from June to August is 1138m, the operating control water level in the post-flood season from September to October is 1140m, the dead water level is 1076m, and the total storage capacity is 4.947 billion m 3 , regulating reservoir capacity 3.361 billion m 3 The total installed capacity is 600MW (3*200MW), the average annual power generation is 1.559 billion kWh, and the guaranteed output is 159.1MW.
[0111] According to the location of the hydropower station and the amount and distribution of wind and solar resources around it, through map surveys, fund collection, field investigations, and restrictive factor investigations, the locations and maximum installed capacities of wind and solar power stations that can be developed around the hydropower station are as follows: Figure 2 As shown in Figure 1, there are three photovoltaic power stations at [x1, x2, x3] and two wind power stations at [y1, y2]. The collection station and collection line are shown in Figure 1. Figure 2According to the site location and capacity combination, the set of wind and solar development plans that can be formed by the five sites includes 26 wind and solar development plans [X, Y], as follows: [x1, x2], [x1, x3], [x2, x3], [x1, x2, x3], [y1, y2], [x1, y1], [x2, y1], [x3, y1], [x1, y2], [x2, y2], [x3, y2], [x1, x 2, y1], [x1, x3, y1], [x2, x3, y1], [x1, x2, y2], [x1, x3, y2], [x2, x3, y2], [x1, x2, x3, y1] , [x1, x2, x3, y2], [x1, x2, y1, y2], [x1, x3, y1, y2], [x2, x3, y1, y2], [x1, x2, x3, y1, y2].
[0112] Step 2), the hydropower station is complemented with each group of wind and solar development plans to form a water, wind and solar planning plan; according to the wind and solar site composition factors in each group of water, wind and solar planning plans, the wind and solar aggregation plan is determined, and the total initial investment cost of each group of water, wind and solar planning plans is calculated.
[0113] In the above embodiment, the constituent factors of each site include the site, power generation capacity, unit cost of the wind power station or photovoltaic power station, power generation hours, voltage level of the collection line, length of the collection line (the distance from the site to the collection station) and unit cost of the collection line. The capacity, unit cost and power generation hours of the above three photovoltaic power stations and two wind power stations are shown in Table 1.
[0114] Table 1
[0115] Site Capacity(MW) Unit cost (10,000 yuan / MW) Power generation hours (h) <![CDATA[x1]]> 300 350 917 <![CDATA[x2]]> 350 340 917 <![CDATA[x3]]> 260 355 917 <![CDATA[y1]]> 200 720 2272 <![CDATA[y2]]> 250 730 2272
[0116] The voltage levels of the collection lines of the above three photovoltaic power stations and two wind power stations, the lengths of the collection lines, and the unit costs of the collection lines are shown in Table 2.
[0117] Table 2
[0118] Site Capacity(MW) Distance (km) Voltage level (kV) Unit cost (10,000 yuan / km) <![CDATA[x1]]> 300 6 220 240 <![CDATA[x2]]> 350 15 220 250 <![CDATA[x3]]> 260 15 220 220 <![CDATA[y1]]> 200 7 220 200 <![CDATA[y2]]> 250 18 220 210
[0119] The above 26 wind and solar development plans [X, Y] are respectively combined with hydropower stations to form 26 water, wind and solar planning plans. The total initial investment cost of each group of water, wind and solar planning plans is C in ([X,Y]), including the initial investment cost of wind power station, photovoltaic power station, hydropower station, and collection grid, can be expressed as:
[0120]
[0121] in represents the initial investment cost of the wind power station under the wind and solar development plan [X, Y], represents the initial investment cost of a photovoltaic power station under the wind and light development scheme [X,Y], and They represent the initial investment costs of the hydropower station and the grid under the wind and solar development plans [X, Y] respectively. The initial investment cost of the hydropower station can be determined based on information such as the investment estimation results of the hydropower station project.
[0122] Step 3), for each group of the water, wind, and light planning schemes, respectively establish an upper medium- and long-term optimization scheduling model and a lower short-term optimization scheduling model; according to the upper medium- and long-term scheduling objectives, solve the optimal operation mode of the medium- and long-term scheduling model, and determine the output curve and abandoned power of the water, wind, and light planning systems in the medium and long term; according to the lower short-term scheduling objectives, solve the optimal operation mode of the short-term scheduling model, and determine the output curve and abandoned power of the water, wind, and light planning systems in the short term; finally, determine the total grid-connected power and abandoned power of the water, wind, and light planning systems during the assessment period.
[0123] In the above embodiment, the hydropower station is simulated for 370 days from December 27, 2014 to December 31, 2015. The 37 calendar decades are the simulation objects. The average monthly runoff of the reservoir during this period is shown in Table 3. The hourly output data of the photovoltaic power station and the wind power station during this period are shown in Table 3. Figure 3 and Figure 4 shown.
[0124] Table 3
[0125]
[0126]
[0127] For each group of water, wind and light planning schemes, the upper-level medium- and long-term optimization scheduling model of the water, wind and light planning system is established as follows:
[0128] There are two upper-level medium- and long-term dispatching goals: the first goal is to maximize the total power generation of the water, wind, and light planning system; the second goal is to minimize the deviation of the total output of the water, wind, and light planning system from the market load demand. When the electricity prices of water, wind, and light power generation are different, the first goal can be modified to the product of power generation and electricity price. The specific mathematical model can be expressed as:
[0129]
[0130]
[0131] in,
[0132]
[0133] F1 is the total grid-connected electricity during the assessment period, in MWh;
[0134] F2 is the cumulative value of the deviation of the average power per unit value on the grid from the load per unit value during the assessment period;
[0135] D is the total number of time periods;
[0136] ΔT d is the number of hours in period d;
[0137] N d is the average grid-connected power of the water, wind and solar planning systems in time period d, are the average outputs of the hydropower station, wind power station and photovoltaic power station in time period d, is the average power abandonment during period d, in MW;
[0138] Its per unit value is divided by N d By outbound transmission channel capacity;
[0139] is the per unit value of the average load power in the consumption market during the period d;
[0140] K is the comprehensive output coefficient of hydropower;
[0141] is the average power generation flow in period d;
[0142] H d is the average water head in period d;
[0143] C w , C p They are the planned capacity of wind power station and photovoltaic power station, in MW;
[0144] are the output power of wind power and photovoltaic power per MW in the planned site area in time period d. The constraints of the medium- and long-term optimization scheduling model include:
[0145] a) Water balance constraints:
[0146]
[0147] b) Reservoir capacity and water level constraints:
[0148] V min <V d <V max
[0149] V1=V0
[0150] V D+1 =V end
[0151]
[0152] c) Downstream flow restriction:
[0153]
[0154] d) Hydropower output constraints:
[0155]
[0156] e) Transmission channel capacity constraints:
[0157]
[0158] in,
[0159] V d is the initial storage capacity of the reservoir in period d;
[0160] is the average inflow into the reservoir during period d;
[0161] is the average power generation flow in period d;
[0162] is the average water discharge during period d;
[0163] V min and V max are the minimum and maximum storage capacities of the reservoir subject to the upper and lower bounds of the water level during the assessment period;
[0164] V0 and V end are the initial and final storage capacities of the reservoir during the assessment period;
[0165] and They represent the lower and upper bound constraints of the reservoir during the assessment period respectively;
[0166] Q min and Q max They represent the minimum and maximum discharge flow constraints of the reservoir during the assessment period respectively;
[0167] and They represent the minimum and maximum power generation constraints of the hydropower unit during the assessment period respectively;
[0168] They represent the average output of the hydropower station, wind power station and photovoltaic power station in time period d,
[0169] represents the average power abandonment during the period d;
[0170] N max Plan the maximum transmission capacity of the system transmission channels for water, wind and solar power.
[0171] For the second objective function (2) of the upper-level medium- and long-term scheduling, the total system output deviates from the minimum load demand and can be converted into a constraint condition. Then, the medium- and long-term optimization scheduling model can be converted into a single objective function (1).
[0172] The optimal operation mode of the above single objective function (1) is solved to obtain the upper-level ten-day output curve and ten-day abandoned power of the water, wind and solar planning systems.
[0173] For each group of water, wind and light planning schemes, the lower-level short-term optimization scheduling model of the water, wind and light planning system is established as follows:
[0174] The short-term dispatching target is the same as the medium- and long-term dispatching target: the first target is to maximize the total power generation of the water, wind, and light planning system, and the second target is to minimize the deviation of the total output of the water, wind, and light planning system from the market load demand. When the electricity prices of water, wind, and light power generation are different, the first target can be modified to the product of power generation and electricity price. The specific mathematical model can be expressed as:
[0175]
[0176]
[0177] in,
[0178] F1'(d) is the total on-grid electricity in time period d (i.e. [d, 0~d, T]), in MWh;
[0179] F′2(d) is the cumulative value of the deviation of the average power per unit value on the grid from the load per unit value in the time period d (i.e. [d, 0 ~ d, T]);
[0180] T is the total number of short-term scheduling periods contained in the medium- and long-term scheduling cycle d period;
[0181] ΔT t is the short-term scheduling time interval, in h;
[0182] N d,t is the average grid-connected power of the water, wind and solar planning systems in the d period [d, t-1~d, t], are the average outputs of the hydropower station, wind power station and photovoltaic power station in the period d [d, t-1~d, t], is the average abandoned power in the period d [d, t-1~d, t], in MW;
[0183] is its per unit value;
[0184] It is the per-unit value of the average load power in the market during the time period d [d, t-1~d, t].
[0185] The constraints of the short-term optimization scheduling model include:
[0186] a) Water balance constraints:
[0187]
[0188] b) Reservoir capacity and water level constraints:
[0189] V t,min <V d,t <V t,max
[0190] V t,1 =V0
[0191] V t,T+1 =V end
[0192]
[0193] c) Downstream flow restriction:
[0194]
[0195] d) Hydropower output constraints:
[0196]
[0197] e) Transmission channel capacity constraints:
[0198]
[0199] in,
[0200] V d,t is the initial storage capacity of the reservoir in period t during period d;
[0201] is the average inflow into the reservoir during period t;
[0202] is the average water discharge in period t;
[0203] V t,min and V t,max are the minimum and maximum storage capacities of the reservoir subject to the upper and lower bounds of the water level in period t, respectively;
[0204] V0 and V end are the initial and final storage capacities of the reservoir in period d, respectively;
[0205] and They represent the lower and upper bound constraints of the reservoir in period t respectively;
[0206] Q t,min and Q t,max They represent the minimum and maximum discharge flow constraints of the reservoir in period t respectively;
[0207] and They represent the minimum and maximum power generation constraints of the hydropower unit in period t respectively;
[0208] N max Plan the maximum transmission capacity of the system transmission channels for water, wind and solar power.
[0209] The constraints of short-term scheduling in terms of water balance, reservoir capacity and water level, downstream flow, hydropower output and transmission channel capacity are the same as those of medium- and long-term scheduling, and corresponding changes are made to the corresponding time intervals.
[0210] In addition, the storage capacity of the reservoir at the end of the short-term dispatch period (i.e. the corresponding reservoir water level) needs to maintain a certain consistency with the medium- and long-term dispatch results, that is:
[0211] |V′ d+1 -V d,T | / V′ d+1 <ε
[0212] in,
[0213] V′ d+1 The initial reservoir water volume in the d+1 period is for medium- and long-term scheduling;
[0214] V d,T The reservoir water volume at t = d + T for short-term dispatch, i.e., the reservoir water volume at the end of period d;
[0215] ε is the allowable deviation between short-term scheduling results and medium- and long-term scheduling results.
[0216] For the second objective function (4) of the short-term optimization scheduling model, the total system output deviates from the minimum load demand and can be transformed into a constraint condition. Then the short-term optimization scheduling model can be transformed into a single objective function (3).
[0217] The optimal operation mode of the above single objective function (3) is solved to obtain the lower-level hourly output curve and hourly abandoned power of the water, wind and solar planning systems.
[0218] According to the upper-level ten-day output curve and ten-day abandoned power of the water, wind and solar planning systems and the lower-level hourly output curve and hourly abandoned power of the water, wind and solar planning systems, the total online power and abandoned power of the water, wind and solar planning systems during that period are determined.
[0219] Taking the water, wind and solar planning scheme [x1, x2, y1] as an example: the wind and solar installed capacities are x1: 300MW, x2: 300MW, y1: 200MW respectively, the optimization solution is used to obtain the optimal operation mode of the system for that year. Figure 5 As shown; the total output curve of water, wind and solar planning system by ten days is as follows Figure 6 As shown; the hourly power curves of the planned water, wind and solar systems and power abandonment in the first decade are as follows Figure 7 As shown in the figure. The total grid-connected electricity of the water, wind and solar planning scheme [x1, x2, y1] from December 27, 2014 to December 31, 2015 was 2.3404 billion kWh, of which hydropower generation was 1.3423 billion kWh and abandoned electricity was 6.7 million kWh. During this period, the historical grid-connected electricity of the hydropower station was 1.31 billion kWh.
[0220] Step 4), according to the total grid-connected power and abandoned power of each group of water, wind and solar planning systems during the assessment period, calculate the total electricity sales revenue of the water, wind and solar planning systems; calculate the total operation and maintenance costs of the water, wind and solar planning systems during the assessment period; according to the total electricity sales revenue, total operation and maintenance costs and total initial investment costs of the water, wind and solar planning systems during the assessment period, obtain the net income of each group of the water, wind and solar planning schemes during the assessment period.
[0221] The net income of each group of water, wind and solar planning schemes is the total electricity sales income minus the total initial investment cost (including the initial investment cost of wind power stations, photovoltaic power stations, hydropower stations, and collection grids) and operation and maintenance costs, which can be expressed as:
[0222] P = C f ([X,Y])-C in ([X,Y])-C om ([X,Y])
[0223]
[0224] Where [X, Y] represents a set of wind and solar development plans, including site, capacity and other information; C f ([X,Y]) and C om ([X,Y]) represents the total electricity sales revenue and operation and maintenance costs under the wind and solar development plans [X,Y] respectively; f T represents the on-grid electricity price, and F1'(d,[X,Y]) represents the on-grid electricity in period d under the wind and solar development scheme [X,Y]; and They represent the operation and maintenance costs of wind power stations, photovoltaic power stations, hydropower stations and power grids under the wind and solar development plans [X, Y] respectively. The estimation method of the operation and maintenance costs of hydropower stations and power grids is similar to the initial investment cost and can be determined based on traditional engineering experience and methods.
[0225] In this embodiment, the annual operation and maintenance costs of the photovoltaic power station, wind power station and transmission line are calculated according to Table 4.
[0226] Table 4
[0227]
[0228] In this embodiment, the hydropower station has been built for many years, and its total initial investment cost, operation and maintenance cost, and hydropower sales revenue can be determined, and all abandoned electricity is counted as wind and solar abandoned electricity. Take the hydropower, wind, and solar planning scheme [x1, x2, y1] as an example: the wind and solar installed capacities are x1: 300MW, x2: 300MW, y1: 200MW, respectively. The total initial investment cost under the optimal operation mode of the hydropower, wind, and solar planning system is 3.5708 billion yuan. Calculated based on a full investment of 20 years of operation, the average annual investment is 178.54 million yuan; the annual sales revenue is 396.56 million yuan (the wind and solar grid-connected electricity price is uniformly 0.4 yuan / kWh); the annual operation and maintenance cost is 52.91 million yuan.
[0229] Step 5), compare the economic and technical evaluation of each group of water, wind and light planning schemes, and select the water, wind and light planning and construction scheme that meets the technical performance requirements and has the best economic performance.
[0230] Based on the total initial investment cost, annual grid-connected power, annual operation and maintenance cost and net income data of each group of water, wind and solar planning schemes, the economic parameters such as the cost per kilowatt-hour, total investment return rate, capital investment return rate and so on of each group of water, wind and solar planning schemes can be obtained, and the technical impact of the group of water, wind and solar planning schemes on the reserve capacity, peak-shaving capacity and other technical factors of the hydropower station can be analyzed.
[0231] A comprehensive analysis is made of the economic and technical impacts of the above 26 groups of water, wind and solar planning schemes, and the water, wind and solar planning scheme that meets the technical requirements and is the best in terms of economy is selected as the optimal construction plan for the wind and solar power stations complementary to the hydropower stations.
[0232] In this embodiment, the economic calculation and technical impact analysis of 26 water, wind and solar planning schemes consisting of 5 sites are performed, and the optimal construction scheme is obtained: water, wind and solar planning scheme [x1, x2, y1], the wind and solar installed capacities are x1: 300MW, x2: 300MW, y1: 200MW respectively, and the corresponding grid scheme is as follows: Figure 2 Medium thick line section.
[0233] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A method for optimizing a set of water, wind and light planning schemes based on a hierarchical optimization model, characterized in that: The steps include: Step 1), according to a number of wind power station sites and a number of photovoltaic power station sites to be developed around the hydropower station, determine a set of wind and solar development plans consisting of at least two of the wind power station sites and the photovoltaic power station sites; Step 2) Complementing the hydropower station with each group of wind and solar development plans to form a water, wind and solar planning plan; calculating the total initial investment cost of each group of water, wind and solar planning plans according to the site composition factors in each group of wind and solar development plans; Step 3), for each group of water, wind, and light planning schemes, respectively establish an upper medium- and long-term optimization scheduling model and a lower short-term optimization scheduling model; according to the upper medium- and long-term scheduling objectives, solve the optimal operation mode of the medium- and long-term scheduling model, and determine the output curve and abandoned power of the water, wind, and light planning systems in the medium and long term; according to the lower short-term scheduling objectives, solve the optimal operation mode of the short-term scheduling model, and determine the output curve and abandoned power of the water, wind, and light planning systems in the short term; finally, determine the total grid-connected power and abandoned power of the water, wind, and light planning systems during the assessment period; There are two upper-level medium- and long-term dispatching goals: the first is to maximize the total power generation of the water, wind, and solar planning systems, and the second is to minimize the deviation of the total output of the water, wind, and solar planning systems from the load demand of the consumption market; there are two lower-level short-term dispatching goals: the first is to maximize the total power generation of the water, wind, and solar planning systems, and the second is to minimize the deviation of the total output of the water, wind, and solar planning systems from the load demand of the consumption market; The medium- and long-term scheduling model is expressed as two objective functions: in, F1 is the total grid-connected electricity during the assessment period, in MWh; F2 is the cumulative value of the deviation of the average power per unit value on the grid from the load per unit value during the assessment period; D is the total number of time periods; ΔT d is the number of hours in period d; N d is the average grid-connected power of the water, wind and solar planning systems in time period d, are the average outputs of the hydropower station, wind power station and photovoltaic power station in time period d, is the average power abandonment during period d, in MW; Its per unit value is divided by N d By outbound transmission channel capacity; is the per unit value of the average load power in the consumption market during the period d; The short-term scheduling model is expressed as two objective functions: in, F1'(d) is the total grid-connected power in period d, in MWh; F2'(d) is the accumulated value of the deviation of the average per-unit power value of the grid during the period d from the per-unit value of the load; T is the total number of short-term scheduling periods contained in the medium- and long-term scheduling cycle d period; ΔT t is the short-term scheduling time interval, in h; N d,t is the average grid-connected power of the water, wind and solar planning systems in period t during period d, are the average outputs of the hydropower station, wind power station and photovoltaic power station in the t period during the d period, is the average power abandonment power in period t during period d, in MW; is its per unit value; is the per unit value of the average load power in the consumption market during the period d [d, t-1~d, t]; Step 4), according to the total grid-connected power and abandoned power of each group of water, wind and solar planning systems during the assessment period, calculate the total electricity sales revenue of the water, wind and solar planning systems; calculate the total operation and maintenance costs of the water, wind and solar planning systems during the assessment period; according to the total electricity sales revenue, total operation and maintenance costs and total initial investment costs of the water, wind and solar planning systems during the assessment period, obtain the net income of each group of water, wind and solar planning schemes during the assessment period; Step 5), compare the economic and technical evaluations of each group of water, wind and light planning schemes, and select the water, wind and light planning and construction scheme that meets the technical performance requirements and has the best economy.
2. The method for optimizing a set of water, wind and light planning schemes based on a hierarchical optimization model according to claim 1 is characterized in that: In step 2), the constituent factors of the site include the site, power generation capacity, unit cost of the wind power station, unit cost of the photovoltaic power station, power generation hours, voltage level of the collection line, length of the collection line and unit cost of the collection line.
3. The method for optimizing a set of water, wind and light planning schemes based on a hierarchical optimization model according to claim 1 is characterized in that: In step 2), the total initial investment cost includes the initial investment cost of the wind power station, the photovoltaic power station, the hydropower station and the collection grid, and the total initial investment cost is determined according to traditional engineering experience and methods.
4. The method for optimizing a set of water, wind and light planning schemes based on a hierarchical optimization model according to claim 1 is characterized in that: The constraints of the medium- and long-term scheduling model include: a) Water balance constraints: b) Reservoir capacity and water level constraints: V min <V d <V max V1=V0 V D+1 =V end c) Downstream flow restriction: d) Hydropower output constraints: e) Transmission channel capacity constraints: in, V d is the initial storage capacity of the reservoir in period d; is the average inflow into the reservoir during period d; is the average power generation flow in period d; is the average water discharge during period d; V min and V max are the minimum and maximum storage capacities of the reservoir subject to the upper and lower bounds of the water level during the assessment period; V0 and V end are the initial and final storage capacities of the reservoir during the assessment period; and They represent the lower and upper bound constraints of the reservoir during the assessment period respectively; Q min and Q max They represent the minimum and maximum discharge flow constraints of the reservoir during the assessment period respectively; and They represent the minimum and maximum power generation constraints of the hydropower unit during the assessment period respectively; They represent the average output of the hydropower station, wind power station and photovoltaic power station in time period d, represents the average power abandonment during the period d; N max Plan the maximum transmission capacity of the system transmission channels for water, wind and solar power; The constraints of the short-term scheduling model include: a) Water balance constraints: b) Reservoir capacity and water level constraints: V t,min <V d,t <V t,max V t,1 =V0 V t,T+1 =V end c) Downstream flow restriction: d) Hydropower output constraints: e) Transmission channel capacity constraints: in, V d,t is the initial storage capacity of the reservoir in period t during period d; is the average inflow into the reservoir during period t; is the average water discharge in period t; V t,min and V t,max are the minimum and maximum storage capacities of the reservoir subject to the upper and lower bounds of the water level in period t, respectively; V0 and V end are the initial and final storage capacities of the reservoir in period d, respectively; and They represent the lower and upper bound constraints of the reservoir in period t respectively; Q t,min and Q t,max They represent the minimum and maximum discharge flow constraints of the reservoir in period t respectively; and They represent the minimum and maximum power generation constraints of the hydropower unit in period t respectively; N max Plan the maximum transmission capacity of the system transmission channels for water, wind and solar power.
5. The method for optimizing a set of water, wind and light planning schemes based on a hierarchical optimization model according to claim 4 is characterized in that: The storage capacity of the reservoir at the end of the short-term dispatch period needs to be consistent with the medium- and long-term dispatch results, that is: |V′ d+1 -V d,T | / V′ d+1 <ε in, V′ d+1 The initial reservoir water volume in the d+1 period is for medium- and long-term scheduling; V d,T The reservoir water volume at t = d + T for short-term dispatch, i.e., the reservoir water volume at the end of period d; ε is the allowable deviation between short-term scheduling results and medium- and long-term scheduling results.
6. The method for optimizing a set of water, wind and light planning schemes based on a hierarchical optimization model according to claim 1, characterized in that: In step 4), the total operation and maintenance cost includes the operation and maintenance costs of wind power stations, photovoltaic power stations, hydropower stations and grids under the water, wind and light planning schemes. The operation and maintenance cost estimation method of the hydropower stations and grids is determined based on traditional engineering experience and methods.
7. The method for optimizing a set of water, wind and light planning schemes based on a hierarchical optimization model according to claim 1, characterized in that: In step 5), the economic evaluation includes evaluating the cost per kilowatt-hour, total investment return rate, and capital investment return rate under the water, wind, and solar planning schemes; the technical evaluation includes evaluating the spare capacity and peak-shaving capacity of the hydropower station under the water, wind, and solar planning schemes.
8. The method for optimizing a set of water, wind and light planning schemes based on a hierarchical optimization model according to claim 1 is characterized in that: The hierarchical optimization model includes an upper-layer medium- and long-term optimization scheduling model and a lower-layer short-term optimization scheduling model.