A lightweight partition wall and concrete beam integrated decoration structure and construction method thereof
By adopting integrated decoration structure of lightweight partition walls and concrete beams in green building systems, and using nail connection and plugging methods, the problems of complex installation, long time and unsightly appearance in the existing technology are solved, and the structure is simple , fast installation and beautiful appearance.
Patent Information
- Application Number
- CN202111414934.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-11-25
- Publication Date
- 2025-02-07
- Estimated Expiration
- 2041-11-25
AI Technical Summary
The existing green building system is complex during installation and has a long installation time, and it is difficult to achieve natural transition and connection during the renovation of partition walls and beams, and its appearance is not beautiful.
Adopt the integrated decoration structure of lightweight partition walls and concrete beams. By setting up the first connecting component and the second connecting component, and using nail connection and plugging, the ecological board and concrete beam are connected together to realize the partition wall body and concrete. Natural transition and connection of beams.
The installation structure is simplified, the installation time is shortened, and the natural transition and connection between partition walls and beams is achieved, with a beautiful appearance.
Smart Images

Figure CN113982147B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a lightweight partition wall and concrete beam integrated decoration structure and a construction method thereof. Background Art
[0002] The integration of building decoration has achieved a leap from rough housing to fine housing, which not only saves decoration costs and decoration materials, but also simplifies the construction process, saving manpower and time to a minimum. The integration of building decoration is in line with the guiding ideology of national green construction. The integration of building decoration can protect the environment, reduce pollution, and provide people with healthy, comfortable and efficient use space during the decoration process.
[0003] However, when installing the green building system currently in use, most of the connection positions need to be connected by welding, which has the problems of complex installation structure and long installation time. At the same time, the green building system currently in use is difficult to achieve natural transition and connection during the outer packaging decoration of partition walls and beams due to the influence of welding technology, and there is a problem of unsightly appearance. Summary of the invention
[0004] In view of this, the present invention provides a lightweight partition wall and concrete beam integrated decoration structure and a construction method thereof.
[0005] In order to solve the above technical problems, the technical solution of the present invention is: in the first aspect, the present invention provides an integrated decoration structure of a lightweight partition wall and a concrete beam, comprising a partition wall body and a concrete beam, the partition wall body is provided with longitudinal ribs, the top of the concrete beam is provided with a concrete floor slab, the outer side of the concrete beam is surrounded by a circle of ecological panels, the ecological panels are arranged in an open-top structure, the top of the ecological panels and the bottom wall of the concrete floor slab are abutted, the left inner wall of the ecological panel and the left wall of the concrete beam, the right inner wall of the ecological panel and the right wall of the concrete beam are connected together by setting a first connecting component, an installation notch is opened on the bottom outer wall of the ecological panel, a second connecting component for connecting with the longitudinal ribs is provided in the installation notch, and the partition wall body is connected to the concrete beam through the connection between the longitudinal ribs and the second connecting component.
[0006] Furthermore, the first connecting component includes a connecting piece, which is arranged on the left inner wall and the right inner wall of the ecological board and the left wall and the right wall of the concrete beam. The cross-section of the connecting piece is arranged in a hook-shaped structure, and a vertically arranged plug-in piece is provided on the bent hook portion of the connecting piece, and the plug-in piece is arranged in an array on the bent hook portion of the connecting piece along the length extension direction of the connecting piece. The connecting piece is also provided with a connecting hole, and the connecting hole is arranged on the connecting piece at a distance from the plug-in piece.
[0007] Furthermore, the first connecting component also includes a first nail, which passes through the self-connecting hole and penetrates into the left inner wall of the ecological board, the right inner wall of the ecological board, the left wall of the concrete beam and the right wall of the concrete beam to install the connecting part on the left inner wall of the ecological board, the right inner wall of the ecological board, the left wall of the concrete beam and the right wall of the concrete beam.
[0008] Furthermore, the number and position of the connecting parts provided on the left inner wall of the ecological board are adapted to the number and position of the connecting parts provided on the left wall of the concrete beam. One connecting part provided on the left inner wall of the ecological board corresponds to one connecting part provided on the left wall of the concrete beam. The number and position of the connecting parts provided on the right inner wall of the ecological board are adapted to the number and position of the connecting parts provided on the right wall of the concrete beam. One connecting part provided on the right inner wall of the ecological board corresponds to one connecting part provided on the right wall of the concrete beam.
[0009] Furthermore, the connecting piece arranged on the left inner wall of the ecological board is arranged in the opposite direction to the connecting piece arranged on the left wall of the concrete beam, and the connecting piece arranged on the left wall of the concrete beam and the connecting piece installed on the left inner wall of the ecological board are connected together by mutual insertion of the bent hook parts, and the connecting piece arranged on the right inner wall of the ecological board and the connecting piece arranged on the right wall of the concrete beam are arranged in the opposite direction, and the connecting piece arranged on the right wall of the concrete beam and the connecting piece arranged on the right inner wall of the ecological board are connected together by mutual insertion of the bent hook parts.
[0010] Furthermore, the second connecting component includes a first angle code connecting piece and a second angle code connecting piece, and the first angle code connecting piece and the second angle code connecting piece are both arranged in an "L" shape. The second angle code connecting piece is arranged below the first angle code connecting piece, and one connecting arm of the first angle code connecting piece is connected to the left side wall of the installation notch, and the other connecting arm is connected to the concrete beam. One connecting arm of the second angle code connecting piece is connected to the right side wall of the installation notch, and the other connecting arm is connected to the connecting arm connecting the first angle code connecting piece and the concrete beam. The first angle code connecting piece is also provided with a first mounting hole on both connecting arms, and the second angle code connecting piece is also provided with a second mounting hole on both connecting arms.
[0011] Furthermore, the second connecting component also includes a second nail, which passes through the first mounting hole on one of the connecting arms of the first angle code connecting piece and penetrates into the left side wall of the mounting notch to install the connecting arm of the first angle code connecting piece on the left side wall of the mounting notch, and the second nail passes through the second mounting hole on one of the connecting arms of the second angle code connecting piece and penetrates into the right side wall of the mounting notch to install the connecting arm of the second angle code connecting piece on the right side wall of the mounting notch.
[0012] Furthermore, the second connecting component also includes a third nail, which passes through the second mounting hole on the other connecting arm of the second angle code connector, the first mounting hole on the other connecting arm of the first angle code connector, and penetrates into the concrete beam in sequence to connect the connecting arm of the second angle code connector to the connecting arm of the first angle code connector and the concrete beam, and connects the connecting arm of the first angle code connector to the concrete beam.
[0013] Furthermore, the first angle code connector and the second angle code connector form an installation groove in the installation notch, the structural size of which is adapted to the structural size of the longitudinal rib cross section.
[0014] In another aspect, the present invention provides a construction method for an integrated decoration structure of a lightweight partition wall and a concrete beam, comprising the following steps:
[0015] Step S1: installing a first corner code connector and a second corner code connector on the left side wall and the right side wall of the installation notch on the ecological board by using a second nail;
[0016] Step S2: installing a connector on the left inner wall and the right inner wall of the ecological board by using the first nail, and installing a connector on the left wall and the right wall of the concrete beam by using the first nail;
[0017] Step S3: Install the eco-board on the outside of the concrete beam, so that the connecting arm of the first corner code connector in the eco-board that is not installed on the installation notch is closely arranged with the bottom wall of the concrete beam, and the connectors on the left inner wall and the right inner wall of the eco-board are respectively plugged into the connectors on the left wall and the right wall of the concrete beam;
[0018] Step S4: A third nail is used to sequentially penetrate the second mounting hole of the connecting arm of the second angle code connector that is not mounted on the mounting notch, the first mounting hole of the connecting arm of the first angle code connector that is not mounted on the mounting notch, and penetrate into the concrete beam, thereby connecting the connecting arm of the second angle code connector to the first angle code connector, and connecting the first angle code connector to the concrete beam;
[0019] Step S5: insert the longitudinal ribs on the partition wall body into the installation grooves formed by the first angle code connector and the second angle code connector, thereby completing the integrated construction of the partition wall body and the concrete beam.
[0020] Compared with the prior art, the advantages of the present invention are:
[0021] The present invention sets a first connecting component and a second connecting component. The first connecting component can connect the left inner wall and the right inner wall of the ecological board to the left wall and the right wall of the concrete beam respectively. The second connecting component can connect the longitudinal ribs on the partition body to the installation notch, so that the partition body and the concrete beam can be connected together. Compared with the prior art, there is no need to use welding technology for connection. The overall installation structure is simple and easy to install. Since there is no need to use welding technology, only the plug-in method is used, which can achieve a natural transition and connection between the partition body and the concrete beam during the outer package decoration. Compared with the prior art, it has the advantages of simple installation structure, shortened installation time and beautiful appearance. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for describing the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0023] Figure 1 It is a front cross-sectional view of the present invention;
[0024] Figure 2 It is a structural schematic diagram of the connecting member in the present invention;
[0025] Figure 3 This is the enlarged view of point A;
[0026] Figure 4 This is an enlarged view of point B;
[0027] Figure 5 It is a front cross-sectional view of Example 2 of the present invention.
[0028] Figure numerals: 1. partition wall body; 2. concrete beam; 3. longitudinal rib; 4. concrete floor; 5. ecological board; 6. first connecting component; 61. connecting piece; 62. hook portion; 63. plug-in piece; 64. connecting hole; 65. first nail; 7. installation notch; 8. second connecting component; 81. first angle code connecting piece; 82. second angle code connecting piece; 83. first installation hole; 84. second installation hole; 85. second nail; 86. third nail; 9. installation groove. DETAILED DESCRIPTION
[0029] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0030] Example 1: Please refer to Figures 1 to 4 The present embodiment provides an integrated decoration structure of a lightweight partition wall and a concrete beam, comprising a partition wall body 1 and a concrete beam 2. The partition wall body 1 is provided with longitudinal ribs 3. A concrete floor slab 4 is provided on the top of the concrete beam 2. A circle of ecological panels 5 is provided around the outer side of the concrete beam 2. The ecological panels 5 are arranged in an open-top structure. The top of the ecological panels 5 is abutted against the bottom wall of the concrete floor slab 4. The ecological panels 5 wrap the left side wall, the right side wall and the bottom wall of the concrete beam 2. The ecological panels 5 are the outer packaging decoration structure of the concrete beam 2. The left inner wall of the ecological panel 5 and the left side wall of the concrete beam 2, and the right inner wall of the ecological panel 5 and the right side wall of the concrete beam 2 are connected together by setting a first connecting component 6.
[0031] The first connecting component 6 includes a connecting piece 61, which is arranged on the left inner wall and the right inner wall of the ecological board 5 and the left and right walls of the concrete beam 2, and the number and position of the connecting pieces 61 arranged on the left inner wall of the ecological board 5 are adapted to the number and position of the connecting pieces 61 arranged on the left wall of the concrete beam 2, and the number and position of the connecting pieces 61 arranged on the right inner wall of the ecological board 5 are adapted to the number and position of the connecting pieces 61 arranged on the right wall of the concrete beam 2; the cross-section of the connecting piece 61 is arranged in a hook-shaped structure, and a vertically arranged plug-in piece 63 is provided on the bent hook portion 62 of the connecting piece 61, and the plug-in piece 63 is arranged in an array on the bent hook portion 62 of the connecting piece 61 along the length extension direction of the connecting piece 61; one connecting piece 61 arranged on the left inner wall of the ecological board 5 corresponds to one connecting piece 61 arranged on the left wall of the concrete beam 2, and one arranged on The connecting piece 61 on the right inner wall of the ecological board 5 corresponds to a connecting piece 61 arranged on the right wall of the concrete beam 2. At the same time, the connecting piece 61 arranged on the left inner wall of the ecological board 5 is arranged in the opposite direction to the connecting piece 61 arranged on the left wall of the concrete beam 2. The connecting piece 61 arranged on the left wall of the concrete beam 2 is connected to the connecting piece 61 on the left inner wall of the ecological board 5 by mutual insertion of the hook portion 62, thereby connecting the left inner wall of the ecological board 5 to the left wall of the concrete beam 2. The connecting piece 61 on the right inner wall of the ecological board 5 is arranged in the opposite direction to the connecting piece 61 on the right wall of the concrete beam 2. The connecting piece 61 on the right wall of the concrete beam 2 is connected to the connecting piece 61 on the right inner wall of the ecological board 5 by mutual insertion of the hook portion 62, thereby connecting the right inner wall of the ecological board 5 to the right wall of the concrete beam 2;
[0032] In this embodiment, each connecting member 61 is provided with a connecting hole 64, and the connecting hole 64 is arranged on the connecting member 61 at a distance from the plug-in piece 63 to ensure that the plug-in piece 63 is unlikely to affect the installation of the connecting member 61. The first connecting component 6 also includes a first nail 65, which passes through the self-connecting hole 64 and penetrates the left inner wall of the ecological board 5, the right inner wall of the ecological board 5, the left wall of the concrete beam 2, and the right wall of the concrete beam 2 to fix the connecting member 61 on the left inner wall of the ecological board 5, the right inner wall of the ecological board 5, the left wall of the concrete beam 2, and the right wall of the concrete beam 2;
[0033] Through the above-mentioned arrangement, when the left inner wall and the right inner wall of the ecological board 5 are installed on the concrete beam 2, there is no need to use welding technology, and only nailing and plug-in methods are needed. The overall structure is simple and easy to install.
[0034] In this embodiment, the number of connecting parts 61 is 4 pairs, and 2 connecting parts 61 are arranged on the left inner wall and the right inner wall of the ecological board 5 and the left wall and the right wall of the concrete beam 2. The positions of the connecting parts 61 on the left inner wall and the right inner wall of the ecological board 5 and the left wall and the right wall of the concrete beam 2 are both in the middle and top positions of the corresponding wall surfaces, so as to ensure the reliability of the connection between the ecological board 5 and the concrete beam 2 when the connecting parts 61 on the left inner wall of the ecological board 5 and the connecting parts 61 on the left wall of the concrete beam 2 are plugged into each other, and when the connecting parts 61 on the right inner wall of the ecological board 5 and the connecting parts 61 on the right wall of the concrete beam 2 are plugged into each other. In actual use, the number of connecting parts 61 can be selected according to the actual height of the concrete beam 2. If the height of the concrete beam 2 is higher or lower, the number of connecting parts 61 can be appropriately increased or decreased.
[0035] An installation notch 7 is provided on the front outer wall of the ecological board 5, and a second connecting component 8 for connecting the longitudinal ribs 3 is provided in the installation notch 7. The partition wall body 1 is connected to the concrete beam 2 through the connection between the longitudinal ribs 3 and the second connecting component 8;
[0036] The second connection assembly 8 includes a first angle code connection member 81 and a second angle code connection member 82, the first angle code connection member 81 and the second angle code connection member 82 are both arranged in an "L" shape, the second angle code connection member 82 is arranged below the first angle code connection member 81, the vertically arranged connection arm of the first angle code connection member 81 is connected to the left side wall of the installation notch 7, the horizontally arranged connection arm of the first angle code connection member 61 is connected to the bottom wall of the concrete beam 2, the vertically arranged connection arm of the second angle code connection member 82 is connected to the right side wall of the installation notch 7, and the horizontally arranged connection arm of the second angle code connection member 82 is connected to the horizontally arranged connection arm of the first angle code connection member 81;
[0037] In this embodiment, the first angle code connector 81 and the second angle code connector 82 are arranged in an array on the two side walls of the installation gap 7 along the length extension direction of the ecological board 5. The distribution positions of the first angle code connector 81 and the second angle code connector 82 on the two side walls of the installation gap 7 meet the requirement that one first angle code connector 81 corresponds to one second angle code connector 82. The specific number of the first angle code connector 81 and the second angle code connector 82 is selected according to the actual length of the ecological board 5. The two connecting arms of the first angle code connector 81 are both provided with a first mounting hole 83, and the two connecting arms of the second angle code connector 82 are both provided with a second mounting hole 84. The second connecting component 8 also includes a second nail 85 and a third nail 86. The second nail 85 passes through the first mounting hole 83 on the connecting arm vertically arranged from the first angle code connector 81 and The first angle code connector 81 is inserted into the left side wall of the installation notch 7 to install the connecting arm of the first angle code connector 81 on the left side wall of the installation notch 7. The second nail 85 passes through the second mounting hole 84 on the vertically arranged connecting arm of the second angle code connector 82 and penetrates into the right side wall of the installation notch 7 to install the connecting arm of the second angle code connector 82 on the right side wall of the installation notch 7. The third nail 86 passes through the second mounting hole 84 on the horizontally arranged connecting arm of the second angle code connector 82 and the first mounting hole 83 on the horizontally arranged connecting arm of the first angle code connector 81 in sequence and penetrates into the bottom wall of the concrete beam 2 to fix the connecting arm of the second angle code connector 82 and the horizontally arranged connecting arm of the first angle code connector 81 together, and can also fix the horizontally arranged connecting arm of the first angle code connector 81 to the concrete beam 2.
[0038] To ensure the connection effect, the first angle code connector 81 and the second angle code connector 82 form an installation groove 9 in the installation notch 7, the structural size of which is adapted to the cross-sectional structural size of the longitudinal rib 3. The partition wall body 1 can be connected to the concrete beam 2 by inserting the longitudinal rib 3 into the installation groove 9.
[0039] Through the above-mentioned arrangement, when installing the bottom wall of the ecological board 5 on the concrete beam 2, it is only necessary to connect one of the connecting arms of the first angle code connector 81 and the second angle code connector 82 to the side walls on both sides of the installation notch 7 by using nails, and then connect the other connecting arms of the first angle code connector 81 and the second angle code connector 82 together and connect them to the concrete beam 2. When connecting the partition wall body 1 to the concrete beam 2, it is only necessary to insert the longitudinal rib 3 into the installation groove 9, and there is no need to use welding technology, so that a natural transition and connection can be achieved during the outer packaging and decoration of the partition wall body 1 and the concrete beam 2.
[0040] Example 2: Please refer to Figures 2 to 5The present embodiment provides an integrated decoration structure of a lightweight partition wall and a concrete beam, including the integrated decoration structure provided in Embodiment 1. The difference between the present embodiment and Embodiment 1 is that, in the present embodiment, the height of the concrete beam 2 is relatively low. Therefore, the number of connectors 61 is 4. One connector 61 is provided on the left inner wall and the right inner wall of the ecological board 5 and the left and right walls of the concrete beam 2. The positions of the connectors 61 on the left inner wall and the right inner wall of the ecological board 5 and the left and right walls of the concrete beam 2 are all at the top of the corresponding wall surfaces. Since the height of the concrete beam 2 is relatively low, the number of connectors 61 is reduced, thereby reducing the waste of resources.
[0041] Example 3: Please refer to Figures 1 to 5 This embodiment provides a construction method of a lightweight partition wall and concrete beam integrated decoration structure, comprising the following steps:
[0042] Step S1: The first angle code connector 81 and the second angle code connector 82 are respectively installed on the left side wall and the right side wall of the installation notch 7 on the ecological board 5 by using the second nail 85. The specific installation method is: by placing the first angle code connector 81 and the second angle code connector 82 at the positions where they need to be installed on the left side wall and the right side wall of the installation notch 7, and then using a gun to drive the second nail 85 into the first installation hole 83 and the second installation hole 84 on the vertically arranged connecting arm of the first angle code connector 81 and the second angle code connector 82, the installation can be completed;
[0043] Step S2: Select the installation position of the connector 61 on the eco-board 5 and the concrete beam 2 according to the height of the eco-board 5 and the concrete beam 2, and then install the connector 61 on the left inner wall and the right inner wall of the eco-board 5 by using the first nail 65, and install the connector 61 on the left wall and the right wall of the concrete beam 2 by using the first nail 65. The specific installation method is: by placing the connector 61 at the position where it needs to be installed on the left inner wall and the right inner wall of the eco-board 5 and the left wall and the right wall of the concrete beam 2, and then use a gun to connect the connector 61 The installation is completed by driving the first nail 65 into the hole 64. In the present embodiment, the method for manufacturing the connector 61 is as follows: a rectangular iron sheet of suitable length is selected, and then a tooth-like structure is cut out at the upper edge of the rectangular iron sheet and arranged in an array along the length extension direction of the rectangular iron sheet to form a plug-in sheet 63. Then, the upper side of the rectangular iron sheet is folded toward the direction close to the lower side of the rectangular iron sheet to form a hook portion 62. Then, a connecting hole 64 is punched on the rectangular iron sheet to be spaced apart from the plug-in sheet 63. At this point, the connector 61 is completed.
[0044] Step S3: Install the eco-board 5 on the outside of the concrete beam 2, so that the first angle code connector 81 on the left side wall of the installation notch 7 in the eco-board 5 is transversely arranged with its connecting arm close to the bottom wall of the concrete beam 2, and the connectors 61 on the left inner wall and the right inner wall of the eco-board 5 are respectively plugged into the connectors 61 on the left wall and the right wall of the concrete beam 2;
[0045] Step S4: by using the third nail 86 to sequentially pass through the second mounting hole 84 on the transversely arranged connecting arm of the second angle code connector 82, the first mounting hole 83 on the transversely arranged connecting arm of the first angle code connector 81 and penetrate into the bottom wall of the concrete beam 2, so as to connect the connecting arm of the second angle code connector 82 with the first angle code connector 81, and also connect the first angle code connector 81 with the concrete beam 2, the specific method is: align the second mounting hole 84 on the transversely arranged connecting arm of the second angle code connector 82 with the first mounting hole 83 on the transversely arranged connecting arm of the first angle code connector 81, and then use a gun to drive the nail into the second mounting hole 84 on the transversely arranged connecting arm of the second angle code connector 82 and the first mounting hole 83 on the transversely arranged connecting arm of the first angle code connector 81, and the installation is completed;
[0046] Through the aforementioned steps S1 to S4, the first angle code connector 81 and the second angle code connector 82 can connect the bottom wall of the ecological board 5 with the bottom wall of the concrete beam 2, and the connector 61 can connect the left inner wall and the right inner wall of the ecological board 5 with the left wall and the right wall of the concrete beam 2, so that the ecological board 5 can be well installed on the concrete beam 2, ensuring that the ecological board 5 is not easy to fall off from the concrete beam 2;
[0047] Step S5: insert the longitudinal rib 3 on the partition wall body 1 into the installation groove 9 formed by the first angle code connector 81 and the second angle code connector 82, thus completing the integrated construction of the partition wall body 1 and the concrete beam 2, and then proceed with other subsequent construction operations.
[0048] In the description of the present invention, it is necessary to understand that the terms "coaxial", "bottom", "one end", "top", "middle", "the other end", "upper", "one side", "top", "inside", "front", "center", "both ends" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0049] In the present invention, unless otherwise clearly stipulated and limited, the terms such as "installation", "setting", "connection", "fixation" and "screw-on" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium; it can be the internal connection of two elements or the interaction relationship between two elements. Unless otherwise clearly defined, ordinary technicians in this field can understand the specific meanings of the above terms in the present invention according to the specific circumstances.
[0050] The above are only typical examples of the present invention. In addition, the present invention may have many other specific implementations. Any technical solutions formed by equivalent replacement or equivalent transformation fall within the scope of protection required by the present invention.
Claims
1. A lightweight partition wall and concrete beam integrated decoration structure, comprising a partition wall body (1) and a concrete beam (2), wherein the partition wall body (1) is provided with longitudinal ribs (3), and the top of the concrete beam (2) is provided with a concrete floor slab (4), characterized in that: The concrete beam (2) is surrounded by a circle of ecological panels (5), the ecological panels (5) being arranged in an open-top structure, the top of the ecological panels (5) being arranged in contact with the bottom wall of the concrete floor slab (4), the left inner wall of the ecological panels (5) being connected to the left wall of the concrete beam (2), and the right inner wall of the ecological panels (5) being connected to the right wall of the concrete beam (2) by means of a first connecting component (6), a mounting notch (7) being arranged on the bottom outer wall of the ecological panels (5), a second connecting component (8) being arranged in the mounting notch (7) for connecting with the longitudinal ribs (3), and the partition wall body (1) being connected to the concrete beam (2) by means of the connection between the longitudinal ribs (3) and the second connecting component (8); The first connection component (6) comprises a connection piece (61), which is arranged on the left inner wall and the right inner wall of the ecological board (5) and the left wall and the right wall of the concrete beam (2); the cross section of the connection piece (61) is arranged in a hook-shaped structure; a plug-in piece (63) arranged vertically is arranged on the hook portion (62) of the connection piece (61); and the plug-in piece (63) is arranged in an array on the hook portion (62) of the connection piece (61) along the length extension direction of the connection piece (61); and a connection hole (64) is also provided on the connection piece (61); and the connection hole (64) is arranged on the connection piece (61) at a distance from the plug-in piece (63); The second connection component (8) comprises a first angle code connection piece (81) and a second angle code connection piece (82). The first angle code connection piece (81) and the second angle code connection piece (82) are both arranged in an "L" shape. The second angle code connection piece (82) is arranged below the first angle code connection piece (81). One of the connection arms of the first angle code connection piece (81) is connected to the left side wall of the installation notch (7), and the other connection arm is connected to the concrete beam (2). One of the connection arms of the second angle code connection piece (82) is connected to the right side wall of the installation notch (7), and the other connection arm is connected to the connection arm connecting the first angle code connection piece (81) and the concrete beam (2). The two connection arms of the first angle code connection piece (81) are both provided with a first installation hole (83), and the two connection arms of the second angle code connection piece (82) are both provided with a second installation hole (84).
2. The integrated decoration structure of lightweight partition wall and concrete beam according to claim 1 is characterized by: The first connection assembly (6) further comprises a first nail (65), which passes through the self-connection hole (64) and penetrates into the left inner wall of the ecological board (5), the right inner wall of the ecological board (5), the left wall of the concrete beam (2) and the right wall of the concrete beam (2) so as to install the connection piece (61) on the left inner wall of the ecological board (5), the right inner wall of the ecological board (5), the left wall of the concrete beam (2) and the right wall of the concrete beam (2).
3. The integrated decoration structure of lightweight partition wall and concrete beam according to claim 1 is characterized by: The number and position of the connecting pieces (61) provided on the left inner wall of the ecological board (5) are compatible with the number and position of the connecting pieces (61) provided on the left wall of the concrete beam (2); one connecting piece (61) provided on the left inner wall of the ecological board (5) corresponds to one connecting piece (61) provided on the left wall of the concrete beam (2); the number and position of the connecting pieces (61) provided on the right inner wall of the ecological board (5) are compatible with the number and position of the connecting pieces (61) provided on the right wall of the concrete beam (2); one connecting piece (61) provided on the right inner wall of the ecological board (5) corresponds to one connecting piece (61) provided on the right wall of the concrete beam (2).
4. The integrated decoration structure of lightweight partition wall and concrete beam according to claim 3 is characterized by: The connecting piece (61) provided on the left inner wall of the ecological board (5) is arranged in the opposite direction to the connecting piece (61) provided on the left wall of the concrete beam (2); the connecting piece (61) provided on the left wall of the concrete beam (2) and the connecting piece (61) provided on the left inner wall of the ecological board (5) are connected together by plugging into each other through a hook portion (62); the connecting piece (61) provided on the right inner wall of the ecological board (5) and the connecting piece (61) provided on the right wall of the concrete beam (2) are arranged in the opposite direction to the connecting piece (61) provided on the right wall of the concrete beam (2); the connecting piece (61) provided on the right inner wall of the ecological board (5) and the connecting piece (61) provided on the right inner wall of the ecological board (5) are connected together by plugging into each other through a hook portion (62).
5. The integrated decoration structure of lightweight partition wall and concrete beam according to claim 2 is characterized by: The second connecting assembly (8) further comprises a second nail (85), the second nail (85) passing through a first mounting hole (83) on one of the connecting arms of the first angle code connecting member (81) and penetrating into the left side wall of the mounting notch (7) to mount the first angle code connecting member (81) on the left side wall of the mounting notch (7), and the second nail (85) passing through a second mounting hole (84) on one of the connecting arms of the second angle code connecting member (82) and penetrating into the right side wall of the mounting notch (7) to mount the second angle code connecting member (82) on the right side wall of the mounting notch (7).
6. The integrated decoration structure of lightweight partition wall and concrete beam according to claim 5 is characterized by: The second connection assembly (8) further comprises a third nail (86), which passes through the second mounting hole (84) on the other connecting arm of the second angle code connector (82), the first mounting hole (83) on the other connecting arm of the first angle code connector (81) in sequence, and penetrates into the concrete beam (2) to connect the connecting arm of the second angle code connector (82) to the connecting arm of the first angle code connector (81) connecting the concrete beam (2), and to connect the connecting arm of the first angle code connector (81) to the concrete beam (2).
7. The integrated decoration structure of lightweight partition wall and concrete beam according to claim 6 is characterized by: The first angle code connecting piece (81) and the second angle code connecting piece (82) form an installation groove (9) in the installation notch (7) whose structural size is adapted to the cross-sectional structural size of the longitudinal rib (3).
8. A construction method for the integrated decoration structure of lightweight partition wall and concrete beam according to claim 7, characterized in that: The following steps are involved: Step S1: installing the first corner code connector (81) and the second corner code connector (82) on the left side wall and the right side wall of the installation notch (7) on the ecological board (5) by using the second nail (85); Step S2: installing the connecting piece (61) on the left inner wall and the right inner wall of the ecological board (5) by using the first nail (65), and installing the connecting piece (61) on the left wall and the right wall of the concrete beam (2) by using the first nail (65); Step S3: installing the ecological board (5) on the outer side of the concrete beam (2), so that the connecting arm of the first angle code connecting piece (81) in the ecological board (5) not installed on the installation notch (7) is closely arranged with the bottom wall of the concrete beam (2), and the connecting pieces (61) on the left inner wall and the right inner wall of the ecological board (5) are respectively plugged into the connecting pieces (61) on the left wall and the right wall of the concrete beam (2); Step S4: The third nail (86) is sequentially passed through the second mounting hole (84) on the connecting arm of the second angle code connector (82) not mounted on the mounting notch (7), the first mounting hole (83) on the connecting arm of the first angle code connector (81) not mounted on the mounting notch (7), and penetrated into the concrete beam (2), thereby connecting the connecting arm of the second angle code connector (82) and the first angle code connector (81), and connecting the first angle code connector (81) and the concrete beam (2); Step S5: inserting the longitudinal rib (3) on the partition wall body (1) into the installation groove (9) formed by the first angle code connector (81) and the second angle code connector (82), thus completing the integrated construction of the partition wall body (1) and the concrete beam (2).
Citation Information
Patent Citations
Light partition wall and concrete beam integrated decoration structure
CN216689940U