A method for replacing the side plate of a conveyor device in a high-speed steel preparation process

By cutting and removing the old side plates in the high-speed steel preparation process and fixing the new side plates under high temperature environment, the problems of inconvenience and insufficient stability during the replacement of the side plates of the conveyor device are solved, and the convenience and stability of replacement are achieved, avoiding the Material waste and operational complexity.

CN114029697BActive Publication Date: 2024-11-05FUDA SPECIAL STEEL GROUP WORKS JIANGSU
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202111322988.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-11-09
Publication Date
2024-11-05
Estimated Expiration
2041-11-09

AI Technical Summary

Technical Problem

In the high-speed steel preparation process, there are problems inconvenient replacement of the whole piece and the split replacement cannot ensure the firmness and stability of the connection position, resulting in waste of materials and complex operation.

Method used

By determining the actual position and size of the old side panels for cutting and dismantling, lifting the new side panels using lifting devices and making fixed connections under high temperature environments, ensuring stable installation of the new side panels, and forming anti-slip textures and coating anti-rust on the surface layer, optimize the operability and stability of the replacement process.

Benefits of technology

The convenience of the replacement process and material savings are achieved, the firm connection and stability of the new side panels are ensured, and the complexity of the integrated replacement and the splicing gap problem of split replacement are avoided.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114029697B_ABST
    Figure CN114029697B_ABST
Patent Text Reader

Abstract

The present invention provides a method for replacing the side plate of a conveying device in a high-speed steel preparation process, which solves the problems in the prior art that it is inconvenient to replace the whole plate and that the firmness and stability of the connection position cannot be guaranteed during split replacement. Direct cutting and removal are determined according to the actual position and size, and then the plate is transported by a lifting device, and then fixedly connected in a high-temperature environment. The replacement is convenient and the operability is strong. Compared with the integral side plate, the replacement of the whole plate saves materials and work hours and is easy to operate. Compared with the split side plate, the replacement position connection is more stable and firm and there is no splicing gap.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of high-speed steel, and in particular to a method for replacing a side plate of a conveyor device in a high-speed steel preparation process. Background Art

[0002] With the continuous development of human technology, the demand for equipment materials in the fields of aerospace transportation and shipping is also increasing. The emergence of high-speed steel has effectively made up for this defect. Drill bits made of high-speed steel have many advantages and are widely used. In the process of high-speed steel preparation, whether it is the process of blank forming or the process of finished product forming, it is necessary to use a conveying device to realize the transportation of blanks or finished products. In order to avoid unexpected escape from the conveying route, side panels need to be installed on both sides of the conveying route. In order to effectively protect the blanks or finished products conveyed inside, the side panel installation position needs to be as close to the conveying device as possible without being synchronized with the conveyor belt or conveyor chain. In the prior art, the blanks or finished products will inevitably deviate during the conveying process, thus causing damage to the side panels on both sides of the conveying route. When the damage reaches a certain degree, the side panels need to be replaced in time. The existing side panels are often selected as integral or split installation types. The side panels themselves are heavy and need to be transported by lifting devices such as cranes. The integral side panels need to be replaced as a whole, which is complicated, and the split side panels cannot guarantee the firmness and stability of the connection position when they are replaced. Summary of the invention

[0003] In view of the defects and shortcomings in the above-mentioned prior art, the present invention provides a method for replacing the side plate of a conveyor device in a high-speed steel preparation process.

[0004] The technical solution adopted by the present invention is:

[0005] A method for replacing a side plate of a conveyor in a high-speed steel production process, characterized in that it comprises the following steps:

[0006] S1: Determine the actual position and replacement size of the old side plate to be replaced in the conveying route of the conveyor;

[0007] S2: Cut and remove the old side panels within the replacement range from the conveying route of the conveyor;

[0008] S3: lift the old side panel by the lifting device and remove it from the conveying route, then lift the new side panel by the lifting device and lift the new side panel to the gap position of the old side panel in the conveying route;

[0009] S4: Adjust the installation position of the new side panel according to the preset requirements;

[0010] S5: First, fix the new side plate on the top of the conveying route of the conveying device, and then align the two ends of the new side plate with the side plate positions at the notch positions on both sides;

[0011] S6: Align the two ends of the new side panel with the joining surfaces of the side panels at the notch positions on both sides, press and heat, and then fix and connect the two ends of the new side panel with the side panels at the notch positions on both sides;

[0012] S7: After the environment is heated and kept warm until the two ends of the new side plate are connected to the side plates at the notches on both sides, the connection position is cooled by air cooling;

[0013] S8: forming a non-slip texture on the inner surface of the new side panel;

[0014] S9: Apply an anti-rust layer to the inner and outer surfaces of the new side panels, and perform surface smoothness treatment after coating;

[0015] S10: The conveyor runs to detect the stability of the new side panel installation, removes the tooling and moves it back to the lifting device.

[0016] As a further preferred embodiment of the present invention, in the step S1, in the conveying route of the conveying device, the replacement size of the old side panel determined is larger than the actual size of the old side panel to be removed.

[0017] As a further preferred embodiment of the present invention, in step S2, after the old side panels are cut and removed from the conveying route of the conveying device, the edges of the side panels left at the removal position need to be trimmed and polished.

[0018] As a further preferred embodiment of the present invention, in step S3, the same lifting device is used to lift the new side panel and the old side panel in sequence, or different lifting devices are used to lift the new side panel and the old side panel at the same time.

[0019] As a further preferred embodiment of the present invention, in step S4, the interface parts on both sides of the new side panels need to be trimmed and polished.

[0020] As a further preferred embodiment of the present invention, in step S5, when aligning the two ends of the new side panel with the side panels at the notches on both sides, the new side panel is placed inside the side panels at the notches on both sides.

[0021] As a further preferred embodiment of the present invention, in step S6, after pressing and heating for 5-10 minutes, the two ends of the new side panel are fixedly connected to the side panels at the notched positions on both sides.

[0022] As a further preferred embodiment of the present invention, the anti-skid texture in step S8 can be any one or more combinations of anti-skid convex points, anti-skid convex blocks, and anti-skid strips.

[0023] As a further preferred embodiment of the present invention, the surface smoothness treatment after coating in step S9 needs to satisfy that the surface protrusion size is less than 2 mm.

[0024] As a further preferred embodiment of the present invention, when detecting the installation stability of the new side panel in step S10, the conveying device needs to run for 30-60 minutes.

[0025] Compared with the prior art, the present invention has the following beneficial effects:

[0026] (1) The present invention provides a method for replacing the side plate of a conveyor device in a high-speed steel preparation process, which solves the problems in the prior art that it is inconvenient to replace the whole piece and that the stability of the connection position cannot be guaranteed when the split type is replaced. The side plate is directly cut and removed according to the actual position and size, and then transported by a lifting device, and then fixed and connected in a high temperature environment. The replacement is convenient and the operability is strong. Compared with the integral side plate, the replacement of the whole piece saves materials and work hours and is easy to operate. Compared with the split side plate, the replacement position connection is more stable and firm and there is no splicing gap. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a flow chart of the steps of the replacement method of the present invention. DETAILED DESCRIPTION

[0028] The present invention will now be described in further detail with reference to the accompanying drawings. These drawings are simplified schematic diagrams, which only illustrate the basic structure of the present invention in a schematic manner, and therefore only show the components related to the present invention.

[0029] See also Figure 1 A method for replacing a side plate of a conveyor device in a high-speed steel preparation process provided by the present invention comprises the following steps:

[0030] S1: Determine the actual position and replacement size of the old side panel to be replaced in the conveying route of the conveying device; in this embodiment, in the conveying route of the conveying device, the replacement size of the old side panel determined is larger than the actual size of the old side panel to be removed, so that a part of the excess size is used for the installation of the new side panel and the fixed connection with the old side panels on both sides of the installation position;

[0031] S2: Cut and remove the old side panels within the replacement range from the conveying route of the conveyor; after the old side panels are cut and removed from the conveying route of the conveyor, the edges of the side panels left at the removal position need to be trimmed and polished, so as to facilitate overlapping placement and fixed connection with the new side panels, while also avoiding possible connection damage caused by the cutting section;

[0032] S3: Lift the old side panel by a lifting device and remove it from the conveying route, then lift the new side panel by a lifting device and lift the new side panel to the gap of the old side panel in the conveying route; during lifting, the new side panel and the old side panel can be lifted successively by the same lifting device, thereby saving the use and installation cost of one crane, or different lifting devices can be used to lift the new side panel and the old side panel at the same time, thereby saving lifting time;

[0033] S4: Adjust the installation position of the new side panel according to the preset requirements; in this process, the interface parts on both sides of the new side panel also need to be trimmed and polished, so as to facilitate the overlapping placement and fixed connection with the old side panel, and at the same time avoid possible damage during the installation process caused by the sharp parts of the edge of the new side panel;

[0034] S5: First fix the new side plate on the top of the conveying route of the conveying device, and then align the two ends of the new side plate with the side plates at the notch positions on both sides; when aligning the two ends of the new side plate with the side plates at the notch positions on both sides, place the new side plate on the inner side of the side plates at the notch positions on both sides, so that when the conveyed blanks or finished products are offset, it is ensured that the blanks and finished products will hit the new side plate first at the connection position between the new side plate and the side plates at the notch positions on both sides, thereby providing reliable protection for the blanks or finished products transported on the conveying device;

[0035] S6: Align the two ends of the new side panel with the joining surfaces of the side panels at the notch positions on both sides, press and heat, and then fix the two ends of the new side panel with the side panels at the notch positions on both sides; after pressing and heating for 5-10 minutes, fix the two ends of the new side panel with the side panels at the notch positions on both sides, so as to fully combine the new side panel with the old side panel. In this embodiment, the method of fixing the two ends of the new side panel with the side panels at the notch positions on both sides is selected by welding;

[0036] S7: After the environment is heated and kept warm until the two ends of the new side panels are connected to the side panels at the notches on both sides, the connection position is cooled by air cooling. While cooling, the air cooling can also clean the environment of the connection position by blowing away impurities, dust and debris.

[0037] S8: forming an anti-skid texture on the inner surface of the new side panel; the anti-skid texture may be selected from any one or more combinations of anti-skid convex points, anti-skid convex blocks, and anti-skid strips according to actual use needs, and the function of the anti-skid texture is to provide sufficient deceleration when the blank or finished product hits the inner wall of the side panel during transportation deviation; the setting position and interval distance of the anti-skid texture are determined according to empirical data;

[0038] S9: coating the inner and outer surfaces of the new side panel with an anti-rust layer, and performing a surface smoothness treatment after coating; in this embodiment, the surface smoothness treatment after coating needs to satisfy that the surface protrusion size is less than 2 mm, so as to avoid affecting the formation position of the anti-slip texture due to the excessive size of the surface protrusion;

[0039] S10: The conveyor runs to detect the installation stability of the new side panel, removes the tooling and moves it back to the lifting device; to ensure stable and effective installation, the conveyor needs to run for 30-60 minutes when detecting the installation stability of the new side panel.

[0040] Based on the above ideal embodiments of the present invention, the relevant staff can make various changes and modifications without departing from the technical concept of the present invention through the above description. The technical scope of the present invention is not limited to the contents of the specification, and its technical scope must be determined according to the scope of the claims.

Claims

1. A method for replacing a side plate of a conveyor in a high-speed steel production process, characterized in that: The following steps are involved: S1: Determine the actual position and replacement size of the old side plate to be replaced in the conveying route of the conveyor; S2: Cut and remove the old side panels within the replacement range from the conveying route of the conveyor; S3: lift the old side panel by the lifting device and remove it from the conveying route, then lift the new side panel by the lifting device and lift the new side panel to the gap of the old side panel in the conveying route; S4: Adjust the installation position of the new side panel according to the preset requirements; S5: First, fix the new side plate on the top of the conveying route of the conveying device, and then align the two ends of the new side plate with the side plate positions at the notch positions on both sides; S6: Align the two ends of the new side panel with the joining surfaces of the side panels at the notch positions on both sides, press and heat, and then fix and connect the two ends of the new side panel with the side panels at the notch positions on both sides; S7: After the environment is heated and kept warm until the two ends of the new side plate are connected to the side plates at the notches on both sides, the connection position is cooled by air cooling; S8: forming a non-slip texture on the inner surface of the new side panel; S9: Apply an anti-rust layer to the inner and outer surfaces of the new side panels, and perform surface smoothness treatment after coating; S10: The conveyor device is operated to detect the stability of the new side panel installation, and the tooling is removed and moved back to the lifting device; In the step S1, in the conveying route of the conveying device, the replacement size of the old side panel determined is larger than the actual size of the old side panel to be removed; In the step S2, after the old side panels are cut and removed from the conveying route of the conveying device, the edges of the side panels left at the removal position need to be trimmed and polished; In step S4, the interface parts on both sides of the new side plate need to be trimmed and polished; In the step S5, when the two ends of the new side panel are aligned with the side panels at the notch positions on both sides, the new side panel is placed inside the side panels at the notch positions on both sides; The anti-skid texture in step S8 can be any one or more combinations of anti-skid bumps, anti-skid blocks, and anti-skid strips.

2. The method for replacing the side plate of a conveyor in a high-speed steel manufacturing process according to claim 1, characterized in that: In step S3, the new side panel and the old side panel are hoisted successively by using the same hoisting device, or the new side panel and the old side panel are hoisted simultaneously by using different hoisting devices.

3. The method for replacing the side plate of a conveyor in a high-speed steel production process according to claim 1, characterized in that: In the step S6, after pressing and heating for 5-10 minutes, the two ends of the new side plate are fixedly connected to the side plates at the notch positions on both sides.

4. The method for replacing the side plate of a conveyor in a high-speed steel production process according to claim 1, characterized in that: In step S9, the surface smoothness after coating must satisfy the requirement that the surface protrusion size is less than 2 mm.

5. The method for replacing the side plate of a conveyor in a high-speed steel production process according to claim 1, characterized in that: When checking the installation stability of the new side panel in step S10, the conveying device needs to run for 30-60 minutes.

Citation Information

Patent Citations

  • Method for replacing bridge bearing without traffic interruption and special device thereof

    CN101230563A

  • Replacement construction technology of whole groups of turnouts within closed point changed from existing railway station

    CN107460795A

  • Structural design and replacement method of separated split slotted rope trough plate

    CN112551407A

  • Inner cover repair bracket of cover type annealing furnace

    CN203238310U

  • Equipment replacing method, equipment carry-in method and equipment piping connecting method