Large-area high-altitude grid structure aluminum grid ceiling construction device and construction method
By designing a large-area high-altitude grid structure aluminum grille ceiling construction device, including a conversion layer, U-shaped operating platform and hoisting system, the problem that traditional ceiling methods are difficult to meet the construction of high-altitude grid structures is solved, and efficient, safe and environmentally friendly is achieved. Ceiling construction.
Patent Information
- Application Number
- CN202111553237.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-12-17
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2041-12-17
AI Technical Summary
Traditional ceiling methods and construction methods are difficult to meet the construction needs of large-area high-altitude grid structures, resulting in waste of resources, high construction costs and increased risks.
A large-area high-altitude grid structure aluminum grille ceiling construction device is designed, including a conversion layer, a U-shaped operating platform and a lifting system. The hoisting is realized through the winch, wire rope and pulley assembly, and the use of rubber pads and expansion pipe holes is ensured. Safety and stability, and use lift pallets for chunk assembly and adjustment.
It improves the efficiency of ceiling installation, simplifies construction operations, saves construction period and resources, reduces construction risks, and achieves the goal of green and environmentally friendly construction.
Smart Images

Figure CN114033189B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of suspended ceiling construction, and more specifically, to a large-area high-altitude grid structure aluminum grid suspended ceiling construction device and construction method. Background Art
[0002] With the development of the construction industry, the roof structure forms have become more diverse, among which the spherical grid structure is common in public buildings. However, due to its large span and high spatial height, the traditional ceiling method and construction method can no longer meet the requirements of its ceiling construction. Traditional ceiling method: the hanger is fixed on the lower chord; the traditional ceiling method includes setting up a scaffolding operation layer, using an aerial work vehicle, and using a hanging basket for construction. Although the above ceiling methods can solve the construction problems, they will increase the consumption of manpower, materials, and machines, increase the construction cost, and also increase the risks in the construction. Summary of the invention
[0003] An object of the present invention is to provide a large-area high-altitude grid structure aluminum grid ceiling construction device and method to solve the large-area high-altitude grid structure ceiling construction problem, improve the ceiling installation efficiency, simplify the ceiling operation, and save construction time.
[0004] In order to achieve the purpose and other advantages of the present invention, a large-area high-altitude grid structure aluminum grid ceiling construction device is provided, comprising:
[0005] The transfer layer is placed on the lower ball node inside the grid structure. The transfer layer is formed by crisscrossing longitudinal steel pipes and transverse steel pipes. The ends of the transfer layer are vertically fixed with fixing rods connected to the concrete main structure.
[0006] A U-shaped operating platform, which is placed on the conversion layer;
[0007] A hoisting system includes a winch, a steel wire rope, a pulley one, a pulley two, a pulley three, an adjusting rope and a lifting tray, wherein the pulley one and the pulley two are fixed at the same height to the upper chord or the web of the truss structure through a connecting rod, the pulley one and the pulley two are rotatably connected to the ends of the connecting rod, the pulley three is connected to the adjusting rope, the winch is placed on the ground, one end of the steel wire rope is connected to the winch, and the other end is connected to the lifting tray via the pulley one, the pulley two and the pulley three in sequence.
[0008] Preferably, in the large-area high-altitude grid structure aluminum grille ceiling construction device, a rubber pad is sleeved on the conversion layer at a position corresponding to the position of the lower ball node, and the conversion layer is placed on the lower ball node through the rubber pad.
[0009] Preferably, in the large-area high-altitude grid structure aluminum grille ceiling construction device, the fixing rod is provided with a plurality of expansion holes at intervals along its height direction, each expansion hole is arranged horizontally, and the fixing rod is fixedly connected to the concrete main structure through an expansion tube arranged in the expansion hole.
[0010] Preferably, in the large-area high-altitude grid structure aluminum grille ceiling construction device, the longitudinal steel pipes and the transverse steel pipes are both square steel pipes, the longitudinal steel pipes and the transverse steel pipes are fixedly connected by L-shaped steel plates and self-tapping screws, and the longitudinal steel pipes and the transverse steel pipes are fixedly connected by rectangular sleeves and self-tapping screws.
[0011] Preferably, in the large-area high-altitude grid structure aluminum grille ceiling construction device, the U-shaped operating platform is a U-shaped frame welded by vertical poles, longitudinal cross bars, cross bars, main diagonal braces and secondary diagonal braces, the main diagonal braces are arranged between adjacent vertical poles at both ends of the U-shaped frame, the secondary diagonal braces are arranged between the vertical poles and cross bars at both ends of the U-shaped frame, and a wire mesh is welded to the bottom of the U-shaped frame.
[0012] Preferably, in the large-area high-altitude grid structure aluminum grille ceiling construction device, the lifting tray includes a telescopic bottom plate, upright poles vertically arranged at the four corners of the telescopic bottom plate, and a lifting rope connecting the upright poles and the steel wire rope, wherein the upper portion of the upright pole is provided with a through hole penetrating the upright pole, one end of the lifting rope is connected to the telescopic bottom plate, and the other end is connected to a steel wire rope connecting fixture via the through hole, and the steel wire rope connecting fixture is connected to the steel wire rope.
[0013] Preferably, in the large-area high-altitude grid structure aluminum grille ceiling construction device, the telescopic bottom plate includes two longitudinal telescopic rods, two transverse telescopic rods and at least one auxiliary telescopic rod, the longitudinal telescopic rods and the transverse telescopic rods are welded end to end to form a rectangular structure, the four corners of the rectangular structure are welded with diagonal braces, the at least one auxiliary telescopic rod is arranged in the rectangular structure and is parallel to the transverse telescopic rod, and the two ends of each auxiliary telescopic rod are detachably connected to the longitudinal telescopic rod.
[0014] Preferably, in the large-area high-altitude grid structure aluminum grille ceiling construction device, a distance sensor is provided on the top of the erection rod, and the distance sensor is connected to the winch signal.
[0015] The present invention also provides a large-area high-altitude grid structure aluminum grid ceiling construction method, comprising:
[0016] Step 1: Assemble the transfer layer inside the grid structure and place the transfer layer on the lower ball node, and then fix the fixing rod at the end of the transfer layer to the concrete main structure;
[0017] Step 2: Place a U-shaped operating platform on the transfer layer and hang a safety net on the lower part of the grid structure;
[0018] Step 3: Place the winch in a fixed position on the ground, install pulley 1 and pulley 2 at the same height on the upper chord or web of the grid structure, connect one end of the wire rope to the winch, and connect the other end to the lifting tray via pulley 1, pulley 2 and pulley 3 in sequence;
[0019] Step 4: Trial pull, and formal pull after passing the test;
[0020] Step 5: Place the assembled aluminum alloy grille in the lifting tray, lift it to the designed elevation, and fine-tune the plane position of the lifting tray through the adjustment rope connected to the pulley three, and then connect the assembled aluminum alloy grille to the transfer layer;
[0021] Step 6: Adjust the positions of pulley 1 and pulley 2 on the grid structure;
[0022] Step 7. Repeat steps 5 and 6 until the ceiling project is completed.
[0023] The present invention has at least the following beneficial effects:
[0024] First, the transfer layer is placed inside the grid structure and placed on the lower ball node through a rubber pad. The transfer layer is fixed on the concrete main structure on all sides, which does not damage the ball node and ensures that the transfer layer does not move relative to the grid structure, while reducing the force exerted by the transfer layer on the grid node.
[0025] Second, the use of a U-shaped operating platform and the safety net hung at the bottom of the grid structure can ensure the safety of construction workers when working at heights.
[0026] Third, the use of the lifting pallet ensures the integrity of the ceiling when it is pre-assembled in blocks, ensuring that it is flat and not deformed. The length and width of the lifting pallet can be freely adjusted within a certain range to suit different lifting scenarios.
[0027] Fourth, during the ceiling installation process, the winch is fixed at a certain point on the ground, and the lifting position of the lifting pallet is adjusted only by adjusting the pulley block, which greatly improves the lifting efficiency.
[0028] Fifth, the installation and dismantling of the suspended ceiling construction device is simple. After the suspended ceiling is installed, there is no need to dismantle the transfer layer. You only need to dismantle the U-shaped operating platform and the lifting system. The U-shaped operating platform and the lifting system can generally meet the construction requirements after 3 hours of assembly and testing. It takes 1 hour to dismantle the device, and the U-shaped operating platform and the lifting system can be used in a turnover manner.
[0029] Sixth, the ceiling construction device and construction method of the present invention are low-carbon and environmentally friendly, saving resources. Compared with traditional ceiling methods and installation methods, they improve installation efficiency, are easier to operate, save construction time, and the device is not easily damaged during turnover. The components are relatively independent and can be partially replaced without causing waste, responding to the "four savings and one environmental protection" in green construction.
[0030] Other advantages, objectives and features of the present invention will be embodied in part through the following description, and in part will be understood by those skilled in the art through study and practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 It is a schematic diagram of the overall structure of a construction device according to an embodiment of the present invention;
[0032] Figure 2 is a schematic structural diagram of a conversion layer according to an embodiment of the present invention;
[0033] Figure 3 is a schematic structural diagram of a U-shaped operating platform according to an embodiment of the present invention;
[0034] Figure 4 is a schematic structural diagram of a lifting tray according to an embodiment of the present invention;
[0035] in, Figure 3 (a) is the main structural diagram of the U-shaped operating platform. Figure 3 (b) is a side view of the U-shaped operating platform. Figure 3 (c) is a top view of the U-shaped operating platform. Figure 4 (a) is a top view of the lifting tray. Figure 4 (b) is a schematic diagram of the main structure of the lifting tray. DETAILED DESCRIPTION
[0036] The present invention is further described in detail below in conjunction with embodiments and drawings so that those skilled in the art can implement the invention with reference to the description.
[0037] It should be understood that the terms such as “having”, “including” and “comprising” used herein do not exclude the existence or addition of one or more other elements or combinations thereof.
[0038] It should be noted that the experimental methods described in the following embodiments are conventional methods unless otherwise specified, and the reagents and materials are commercially available unless otherwise specified; in the description of the present invention, the terms "lateral", "longitudinal", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0039] like Figure 1-4 As shown, the present invention provides a large-area high-altitude grid structure aluminum grid ceiling construction device, comprising:
[0040] The transfer layer 1 is placed on the lower ball node 40 inside the grid structure 2. The transfer layer 1 is formed by connecting longitudinal steel pipes 3 and transverse steel pipes 4 in a crisscross pattern. The ends of the transfer layer 1 are vertically fixed with fixing rods 5 connected to the concrete main structure.
[0041] A U-shaped operating platform 6, which is placed on the conversion layer 1, and the U-shaped operating platform 6 is used to provide an operating station;
[0042] A hoisting system comprises a winch 7, a steel wire rope 8, a pulley 19, a pulley 2 10, a pulley 3 11, an adjusting rope 12 and a lifting tray 13, wherein the pulley 19 and the pulley 2 10 are fixed at the same height on the upper chord or the web of the grid structure 2 through a connecting rod, the pulley 19 and the pulley 2 10 are rotatably connected to the ends of the connecting rod, such as by a universal joint, so that the pulley 19 and the pulley 2 10 can rotate 360° around the connecting rod connected thereto, the pulley 3 11 is connected to the adjusting rope 12, and is used to adjust the planar position of the lifting tray 13, the winch 7 is placed on the ground, and the winch 7 is a forward and reverse winch that can be remotely controlled, one end of the steel wire rope 8 is connected to the winch 7, and the other end is connected to the lifting tray 13 via the pulley 19, the pulley 2 10 and the pulley 3 11 in sequence, and the lifting tray 13 is used to place the aluminum alloy grille assembled in blocks.
[0043] When the construction device of the present invention is used for ceiling construction, it includes: step 1, assembling a conversion layer inside the grid structure, and placing the conversion layer on the lower ball node, and then fixing the fixed rod at the end of the conversion layer to the concrete main structure; step 2, placing a U-shaped operating platform on the conversion layer, and fully hanging a safety net at the bottom of the grid structure; step 3, placing a winch at a fixed position on the ground, the winch does not change with the change of the hanging point position, and installing pulley 1 and pulley 2 at the same height on the upper chord or web of the grid structure, and then the steel wire One end of the rope is connected to the winch, and the other end is connected to the lifting tray via pulley one, pulley two and pulley three in sequence; step four, try lifting, and carry out formal lifting after passing the test; step five, place the assembled aluminum alloy grille in the lifting tray, lift it to the designed elevation, and fine-tune the plane position of the lifting tray through the adjustment rope connected to pulley three, and then connect the assembled aluminum alloy grille to the transfer layer; step six, adjust the position of pulley one and pulley two on the grid structure; step seven, repeat steps five and six until the ceiling project is completed.
[0044] The suspended ceiling construction device of the present invention places the conversion layer inside the grid structure, and hoists the assembled aluminum alloy grille through a hoisting system. Construction workers stand on a U-shaped operating platform placed on the conversion layer to connect the assembled aluminum alloy grille with the conversion layer, eliminating the use of traditional scaffolding operations and heavy machinery, shortening the construction period, reducing the cost, and greatly improving the operability of safe construction. After the suspended ceiling construction is completed, there is no need to dismantle the conversion layer, only the U-shaped operating platform and the hoisting system need to be dismantled. The U-shaped operating platform and the hoisting system can also be circulated, which will not cause waste and save resources.
[0045] In another technical solution, in the large-area high-altitude grid structure aluminum grid ceiling construction device, a rubber pad is sleeved on the conversion layer 1 at a position corresponding to the position of the lower ball node 40, and the conversion layer 1 is placed on the lower ball node 40 through the rubber pad. Here, the ball node is protected by providing the rubber pad.
[0046] In another technical solution, in the large-area high-altitude grid structure aluminum grid ceiling construction device, the fixing rod 5 is provided with a plurality of expansion holes at intervals along its height direction, each expansion hole is arranged horizontally, and the fixing rod 5 is fixedly connected to the concrete main structure through an expansion tube 14 arranged in the expansion hole. Here, the fixing rod is fixedly connected to the concrete main structure through the expansion tube to ensure that the transfer layer does not move relative to the grid structure, and at the same time reduce the force of the transfer layer on the grid node.
[0047] In another technical solution, in the large-area high-altitude grid structure aluminum grille ceiling construction device, the longitudinal steel pipe 3 and the transverse steel pipe 4 are both square steel pipes, and the longitudinal steel pipe 3 and the transverse steel pipe 4 are fixedly connected by L-shaped steel plates 15 and self-tapping screws, and the longitudinal steel pipes 3 and the longitudinal steel pipes 3 and the transverse steel pipes 4 and the transverse steel pipes 4 are fixedly connected by rectangular sleeves 16 and self-tapping screws to facilitate the assembly of the transition layer.
[0048] Furthermore, the transition layer 1 and the suspended ceiling are fixedly connected by a Z-shaped steel plate 17, a hanger rod 18 and a nut 19, wherein one horizontal end of the Z-shaped steel plate 17 is fixedly connected to the transition layer 1 by a self-tapping screw, and the other horizontal end is provided with a screw hole, the hanger rod 18 is placed in the screw hole and fixedly connected to the nut 19, and the suspended ceiling and the transition layer are firmly connected by the Z-shaped steel plate and the hanger rod, thereby eliminating the welding work in traditional operations, facilitating the construction, and greatly improving the efficiency of the suspended ceiling installation.
[0049] In another technical solution, the large-area high-altitude grid structure aluminum grille ceiling construction device, the U-shaped operating platform 6 is a U-shaped frame welded by vertical poles 20, longitudinal cross bars 21, cross bars 22, main diagonal braces 23 and secondary diagonal braces 24, the main diagonal braces 23 are arranged between adjacent vertical poles 20 located at both ends of the U-shaped frame, the secondary diagonal braces 24 are arranged between the vertical poles 20 and the cross bars 22 located at both ends of the U-shaped frame, and a wire mesh 25 is welded at the bottom of the U-shaped frame to improve the protection performance of the operating platform while realizing the lightweight of the U-shaped operating platform to ensure construction safety.
[0050] In another technical solution, the large-area high-altitude grid structure aluminum grille ceiling construction device, the lifting tray 13 includes a telescopic bottom plate 26, a vertically arranged pole 27 at the four corners of the telescopic bottom plate, and a pulling rope 28 connecting the pole 27 and the wire rope 8, wherein the upper part of the pole 27 is provided with a through hole penetrating the pole 27, one end of the pulling rope 28 is connected to the telescopic bottom plate 26, and the other end is connected to a wire rope connection fixture 29 through the through hole, and the wire rope connection fixture 29 is connected to the wire rope 8. Here, by setting the bottom plate of the lifting tray as a telescopic bottom plate, the length and width direction of the bottom plate can be freely adjusted within a certain range to be suitable for different lifting scenes, especially for ceiling materials with longer main materials such as aluminum square tubes, and by setting poles at the ends of the telescopic bottom plate to adjust the height and inclination angle of the pulling rope, the problem of damage to the ceiling material caused by too small an angle during the lifting process is avoided.
[0051] In another technical solution, the large-area high-altitude grid structure aluminum grille ceiling construction device, the telescopic base plate 26 includes two longitudinal telescopic rods 30, two transverse telescopic rods 31 and at least one auxiliary telescopic rod 32, the longitudinal telescopic rods 30 and the transverse telescopic rods 31 are welded end to end to form a rectangular structure, the four corners of the rectangular structure are welded with diagonal braces 33, the at least one auxiliary telescopic rod 32 is arranged in the rectangular structure and is parallel to the transverse telescopic rod 31, and the two ends of each auxiliary telescopic rod 32 are respectively detachably connected to the longitudinal telescopic rod 30 to realize the longitudinal and transverse adjustment of the telescopic base plate.
[0052] Furthermore, the longitudinal telescopic rod 30 , the transverse telescopic rod 31 and the auxiliary telescopic rod 32 have the same structure, and all include a rectangular tube 34 and rectangular sleeves 35 at both ends thereof. The rectangular tube 34 is sleeved in the rectangular sleeve 35 and fixed thereto by fixing screws 36 and fixing nuts 37 .
[0053] In another technical solution, in the large-area high-altitude grid structure aluminum grid ceiling construction device, a distance sensor 38 is provided on the top of the erection rod 27, and the distance sensor 38 is connected to the signal of the hoist 7. Here, by adding a distance sensor connected to the hoist signal, the distance sensor is used to sense the distance from the lifting tray to the bottom of the grid. After reaching the set distance, the signal is transmitted to the hoist, so that the hoist automatically slows down, so that the lifting tray is slowly and stably pulled up, ensuring the safety of the pulling process.
[0054] The present invention also provides a large-area high-altitude grid structure aluminum grid ceiling construction method, comprising:
[0055] Step 1: Assemble the conversion layer 1 inside the grid structure 2, and place the conversion layer 1 on the lower ball node 40, and then fix the fixing rod 5 at the end of the conversion layer 2 to the concrete main structure;
[0056] Step 2: Place a U-shaped operating platform 6 on the conversion layer 1, and hang a safety net 39 on the lower part of the grid structure 2;
[0057] Step 3: Place the winch 7 at a fixed position on the ground, install pulley 1 9 and pulley 2 10 at the same height on the upper chord or web of the grid structure 2, and then connect one end of the wire rope 8 to the winch 7, and the other end to the lifting tray 13 through pulley 1 9, pulley 2 10 and pulley 3 11 in sequence;
[0058] Step 4: Trial pull, and formal pull after passing the test;
[0059] Step 5: Place the assembled aluminum alloy grille in the lifting tray 13, lift it to the designed elevation, and fine-tune the plane position of the lifting tray 13 through the adjustment rope 12 connected to the pulley 3 11, and then connect the assembled aluminum alloy grille to the conversion layer 1;
[0060] Step 6: Adjust the positions of pulley 1 9 and pulley 2 10 on the grid structure 2;
[0061] Step 7. Repeat steps 5 and 6 until the ceiling project is completed.
[0062] Furthermore, after the ceiling construction is completed, there is no need to dismantle the transfer layer 1, and only the U-shaped operating platform 6 and the hoisting system need to be dismantled.
[0063] The construction method of the suspended ceiling of the present invention is low-carbon, environmentally friendly, and saves resources. Compared with traditional suspended ceiling methods and installation methods, it improves installation efficiency, is easier to operate, saves construction time, and the device is not easily damaged during turnover use. The components are relatively independent and the components can be partially replaced without causing waste, which responds to the "four savings and one environmental protection" in green construction.
[0064] Although the embodiments of the present invention have been disclosed as above, they are not limited to the applications listed in the specification and the implementation modes, and they can be fully applied to various fields suitable for the present invention. For those familiar with the art, additional modifications can be easily implemented. Therefore, without departing from the general concept defined by the claims and the scope of equivalents, the present invention is not limited to the specific details and the illustrations shown and described herein.
Claims
1. A large-area high-altitude grid structure aluminum grid ceiling construction device, characterized in that: include: The transfer layer is placed on the lower ball node inside the grid structure. The transfer layer is formed by crisscrossing longitudinal steel pipes and transverse steel pipes. The ends of the transfer layer are vertically fixed with fixing rods connected to the concrete main structure. A U-shaped operating platform, which is placed on the conversion layer; A hoisting system includes a winch, a steel wire rope, a pulley one, a pulley two, a pulley three, an adjusting rope and a lifting tray, wherein the pulley one and the pulley two are fixed at the same height to the upper chord or the web of the truss structure through a connecting rod, the pulley one and the pulley two are rotatably connected to the ends of the connecting rod, the pulley three is connected to the adjusting rope, the winch is placed on the ground, one end of the steel wire rope is connected to the winch, and the other end is connected to the lifting tray via the pulley one, the pulley two and the pulley three in sequence.
2. The large-area high-altitude grid structure aluminum grid ceiling construction device according to claim 1 is characterized in that: A rubber pad is sleeved on the conversion layer at a position corresponding to the position of the lower ball node, and the conversion layer is placed on the lower ball node through the rubber pad.
3. The large-area high-altitude grid structure aluminum grid ceiling construction device according to claim 1 is characterized in that: The fixing rod is provided with a plurality of expansion holes at intervals along the height direction thereof, each expansion hole is arranged horizontally, and the fixing rod is fixedly connected to the concrete main structure through an expansion tube arranged in the expansion hole.
4. The large-area high-altitude grid structure aluminum grid ceiling construction device according to claim 1 is characterized in that: The longitudinal steel pipes and transverse steel pipes are both square steel pipes, and are fixedly connected to each other via L-shaped steel plates and self-tapping screws. The longitudinal steel pipes are fixedly connected to each other, and the transverse steel pipes are fixedly connected to each other via rectangular sleeves and self-tapping screws.
5. The large-area high-altitude grid structure aluminum grid ceiling construction device according to claim 1 is characterized in that: The U-shaped operating platform is a U-shaped frame welded from vertical poles, longitudinal cross bars, cross bars, main diagonal braces and secondary diagonal braces. The main diagonal braces are arranged between adjacent vertical poles at both ends of the U-shaped frame, and the secondary diagonal braces are arranged between the vertical poles and cross bars at both ends of the U-shaped frame. A wire mesh is welded to the bottom of the U-shaped frame.
6. The large-area high-altitude grid structure aluminum grid ceiling construction device according to claim 1 is characterized in that: The lifting tray includes a telescopic bottom plate, vertically arranged upright poles at the four corners of the telescopic bottom plate, and a lifting rope connecting the upright poles and the steel wire rope, wherein the upper portion of the upright poles is provided with a through hole penetrating the upright poles, one end of the lifting rope is connected to the telescopic bottom plate, and the other end is connected to a steel wire rope connecting fixture via the through hole, and the steel wire rope connecting fixture is connected to the steel wire rope.
7. The large-area high-altitude grid structure aluminum grid ceiling construction device according to claim 6 is characterized in that: The telescopic base plate includes two longitudinal telescopic rods, two transverse telescopic rods and at least one auxiliary telescopic rod. The longitudinal telescopic rods and the transverse telescopic rods are welded end to end to form a rectangular structure. Diagonal braces are welded at the four corners of the rectangular structure. The at least one auxiliary telescopic rod is arranged in the rectangular structure and is parallel to the transverse telescopic rods. Both ends of each auxiliary telescopic rod are detachably connected to the longitudinal telescopic rods.
8. The large-area high-altitude grid structure aluminum grid ceiling construction device according to claim 6, characterized in that: A distance sensor is arranged on the top of the erecting rod, and the distance sensor is connected with the winch signal.
9. The construction method of the large-area high-altitude grid structure aluminum grid ceiling construction device according to claim 1, characterized in that: include: Step 1: Assemble the transfer layer inside the grid structure and place the transfer layer on the lower ball node, and then fix the fixing rod at the end of the transfer layer to the concrete main structure; Step 2: Place a U-shaped operating platform on the transfer layer and hang a safety net on the lower part of the grid structure; Step 3: Place the winch in a fixed position on the ground, install pulley 1 and pulley 2 at the same height on the upper chord or web of the grid structure, connect one end of the wire rope to the winch, and connect the other end to the lifting tray via pulley 1, pulley 2 and pulley 3 in sequence; Step 4: Trial pull, and then formal pull after passing the test; Step 5: Place the assembled aluminum alloy grille in the lifting tray, lift it to the designed elevation, and fine-tune the plane position of the lifting tray through the adjustment rope connected to the pulley three, and then connect the assembled aluminum alloy grille to the transfer layer; Step 6: Adjust the positions of pulley 1 and pulley 2 on the grid structure; Step 7. Repeat steps 5 and 6 until the ceiling project is completed.