House construction fully interspersed anti-collision system

By setting the opening and reserved time, overlapping and staggering positions on the attached lift scaffolding, the problem of collision between the attached lift scaffolding and the building interface is solved, efficient full interlude construction is achieved, and the construction cycle is shortened and the construction cycle is improved. Construction quality.

CN114135092BActive Publication Date: 2024-12-03CONSTR COMPANY OF CHINA RAILWAY NO 8 ENGNEERING GRP +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202111317655.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-11-09
Publication Date
2024-12-03
Estimated Expiration
2041-11-09

AI Technical Summary

Technical Problem

In the prior art, the attached liftable scaffolding is prone to collide with the building interface during construction, resulting in low construction efficiency, long construction period, high cost, and inability to effectively solve the collision problems in high-rise building construction.

Method used

Adopt aluminum mold + attached lift scaffolding + fully interspersed construction mode. By setting the opening and reserved time, the overlap and staggered position of the attachment points are ensured to ensure that the attached lift scaffolding is between the aluminum mold, construction elevator, and tower crane when it is raised and parked. No collisions, standardized construction is achieved.

Benefits of technology

It effectively avoids the collision between the attached lifting scaffolding and the building interface, shortens the construction cycle, improves construction efficiency, saves material use, and achieves green construction and energy conservation and emission reduction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114135092B_ABST
    Figure CN114135092B_ABST
Patent Text Reader

Abstract

The present invention discloses a fully interlaced anti-collision system for house construction, which adopts a construction mode of aluminum formwork + attached lifting scaffolding + fully interlaced construction. During the construction of the main structure, the decoration and renovation project is constructed simultaneously to achieve the interlaced construction of the main structure, decoration and renovation, electromechanical installation, door and window installation, and exterior wall paint, thereby achieving the effect of shortening the project construction life cycle. During the main construction process, standardized aluminum formwork, attached lifting scaffolding, intelligent high-speed elevators, and intelligent tower cranes are adopted to simulate the lifting of the attached lifting scaffolding without collision with the aluminum formwork, the tower crane, and the construction elevator, thereby achieving smooth cooperation between them and shortening the overall construction period.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention discloses a fully interlaced anti-collision system for building construction, and relates to the technical field of building engineering construction. Background Art

[0002] At present, the conventional main structure construction system has a high risk of external wall leakage, easy hollowing and cracking of masonry, low degree of standardization, and average project construction speed, which leads to quality rework at the construction site, many safety hazards, long construction period and high cost. At the same time, the current conventional construction mode of super high-rise residential buildings is wooden formwork + cantilevered protective scaffolding + segmented decoration and decoration. This construction mode has a long cycle, and the construction step distance of the traditional external protective frame cannot normally meet the single-layer construction flow step distance of the aluminum formwork. In the prior art, an attached liftable climbing frame device is used, but the climbing frame is prone to collision when rising or at the interface with the building, which seriously affects the efficiency of the main structure construction and the building interlaced construction, resulting in an extension of the total construction period. In the existing construction process, the main attached liftable scaffolding and aluminum formwork, construction elevator and tower crane have the following problems when they are rising and docked:

[0003] 1. When the attached liftable scaffold is in the ascending state (1) During the lifting process, the attached liftable scaffold collides with the reinforced back rib system of the external wall aluminum formwork; The lifting time of the attached liftable scaffold collides with the erection time of the aluminum formwork; (2) During the lifting process of the opening position of the attached liftable scaffold collides with the outer contour of the construction elevator position; (3) During the lifting process of the attached liftable scaffold, the scaffold bridge collides with the tower crane wall rod.

[0004] 2. When the attached liftable scaffold is in the docked state, (1) the base of the attached liftable scaffold collides with the aluminum formwork of the exterior wall; the step distance of the base of the attached liftable scaffold collides with the aluminum formwork of the exterior wall; the aluminum formwork structure lines collide with the walkway board of the attached liftable scaffold; (2) the opening position of the attached liftable scaffold collides with the attachment position of the construction elevator; (3) the machine position of the attached liftable scaffold collides with the interface of the tower crane attachment point.

[0005] The utility model patent application with application number CN201921275457.8 discloses an adjustable scaffold for house construction, including a base plate and a loading plate, the upper surface of the base plate is fixedly connected with a support rod, there are four support rods arranged in a rectangular shape on the upper surface of the base plate, the side of the support rod is fixedly connected with a fixed plate, and the upper surface of the fixed plate is provided with a forward and reverse motor; by providing a forward and reverse motor, a threaded rod and a threaded tube, people can start the forward and reverse motor by controlling a switch in the process of adjusting the height of the device, the forward and reverse motor drives the threaded rod, and the threaded rod drives the threaded tube to move, and under the action of the forward and reverse motor and the threaded rod, the threaded tube drives the loading plate to move, so that people can adjust the height of the device more easily, thereby realizing the operation of the device in environments with different heights. However, the application has no climbing attachment function, and cannot be applied to the construction of high-rise buildings. At the same time, there is no reliable and effective solution to solve the problem of avoiding collision with the building interface during the construction process of the scaffolding during the ascent or docking. Summary of the invention

[0006] In order to solve the above problems, the present invention discloses a fully interlaced anti-collision system for house construction, which adopts an aluminum mold + attached lifting scaffolding + fully interlaced construction construction mode. During the construction of the main structure, the decoration and renovation project is constructed simultaneously to achieve the interlaced construction of the main structure, decoration and renovation, electromechanical installation, door and window installation, and exterior wall paint, so as to shorten the project construction life cycle. During the main construction process, standardized aluminum molds, attached lifting scaffolding, intelligent high-speed elevators, and intelligent tower cranes are used to simulate the lifting of the attached lifting scaffolding without collision with the aluminum mold, tower crane, and construction elevator, so as to achieve smooth cooperation with each other and shorten the overall construction period.

[0007] This application adopts an attached lifting scaffolding to ensure the main aluminum formwork construction and interspersed construction. The attached lifting scaffolding is used for a single-layer lifting time of a high-rise building for 4 hours. Through a fully interspersed construction system, it is used in ordinary high-rise buildings to realize the main body, doors and windows, circuit lighting, interior decoration, basements, gardens, and exterior wall interspersed construction. After the main body is sealed, the decoration delivery conditions are met in 180 days; while ensuring a reasonable construction period for a single process, it improves the efficiency of the main structure construction and interspersed construction, shortening the overall construction period by 6 to 8 months.

[0008] The technical solution adopted by the present invention is as follows:

[0009] The invention discloses a fully interlaced anti-collision system for building construction, comprising an attached lifting scaffold, the attached lifting scaffold climbs along with the construction progress of the main body of the building construction floor, the real-time construction layer of the main body of the building construction floor is N layers, the attached lifting scaffold comprises two states of rising and stopping, when the attached lifting scaffold is in the rising state, an opening and a reserved time are set at the collision position with an aluminum mold, a construction elevator and a tower crane, and when the attached lifting scaffold is in the stopping state, an attachment point overlap and a staggered position are set at the collision position with the aluminum mold, the construction elevator and the tower crane.

[0010] Furthermore, when the attached lifting scaffold is in the ascending state, the gap between the inner walkway board edge line of the attached lifting scaffold and the back rib of the outer wall aluminum formwork is set to 8-12 cm, the distance between the inner walkway edge line and the outer shear wall main structure edge line is set to 25-35 cm, the adjacent built floor of the real-time construction layer of the main body of the building construction floor is the N-1 floor, the aluminum formwork of the N-1 floor external shear wall is removed, and the installation of the N-1 floor external shear wall is 70%-90% completed, and the attached lifting scaffold climbs with the main body of the floor.

[0011] Furthermore, when the attached lifting scaffold is in the ascending state, the attached lifting scaffold has an opening of 4.2-4.6 meters, and the construction elevator climbs through the opening of the attached lifting scaffold.

[0012] Furthermore, when the attached lifting scaffold is in the rising state, the attached lifting scaffold is positioned according to the tower crane attachment point, and walkway plates are arranged on both sides of the tower crane attachment point to form a bridge. During the rising process of the attached lifting scaffold, the bridge is lifted and opened, and the attached lifting scaffold passes through the tower crane attachment point without colliding with the tower crane.

[0013] Furthermore, when the attached lifting scaffold is in a docked state, the attached lifting scaffold overlaps with the exterior wall aluminum formwork, and the exterior wall aluminum formwork is provided with two aluminum formwork single plates, so that the aluminum formwork at the base position of the attached lifting scaffold is separated from the exterior wall large plate; the step distance of the attached lifting scaffold base is synchronized with the real-time construction step distance of the main body of the building construction floor; the horizontal extension section of the attached lifting scaffold base should be larger than the outline setting of the building facade lines.

[0014] Furthermore, when the attached lifting scaffold is in a parked state, the uppermost attachment point of the construction elevator is arranged at the top of the opening position of the attached lifting scaffold, and the attached lifting scaffold machine positions are arranged on both sides of the opening position.

[0015] Furthermore, when the attached lifting scaffold is in a docked state, the attached lifting scaffold is staggered with the tower crane attachment point, and the attached lifting scaffold is arranged on both sides of the bridge to balance the bearing capacity at both ends of the bridge.

[0016] Furthermore, a detachable inner cantilever plate is arranged on the walkway plate of the attached lifting scaffolding, and the attached lifting scaffolding prevents collision with the aluminum mold and positions the outer contour of the aluminum mold.

[0017] The technical effects of the present invention are as follows:

[0018] The invention discloses a fully interlaced anti-collision system for house construction, which effectively solves the problem of collision between attached lifting scaffolding and building interface, determines and solves the lifting time of attached lifting scaffolding, the setting of the base position of attached lifting scaffolding, the setting and positioning of bridge of attached lifting scaffolding, the opening position of attached lifting scaffolding, the embedded position of tower crane attached wall, and the positioning of construction elevator supporting wall. In particular, the collision problem between attached lifting scaffolding and tower crane, construction elevator, and aluminum mold before and during the project lifting is solved, which ensures the safety of climbing frame, construction elevator, tower crane, and aluminum mold in use, ensures the smooth progress of interlaced construction, and saves the construction period of the project.

[0019] The details are as follows:

[0020] 1. The collision between the attached lifting scaffolding and the tower crane of the present invention is solved by accurately simulating the climbing process of the intelligent climbing frame and setting a lifting bridge on the walkway board of the intelligent climbing frame.

[0021] 2. The collision position between the attached lifting scaffold of the present invention and the construction elevator is solved by setting a notch on the walkway board of the attached lifting scaffold. The attached lifting scaffold is opened to study the specific position of the construction elevator rising into the two layers inside the climbing frame, providing a vertical transportation channel for indoor installation and decoration, ensuring the synchronization of indoor installation and main structure construction.

[0022] 3. The collision between the attached lifting scaffolding and the aluminum formwork of the present invention is solved by accurately positioning the outer contour of the aluminum formwork reinforcement solution and by setting a detachable inner cantilever plate on the walkway board of the attached lifting scaffolding.

[0023] 4. The fully interlaced anti-collision system for house construction of the present invention reduces the use of formwork and wooden planks. At the same time, the shear wall is free of plastering and the ground is free of leveling, which saves the use of materials in traditional construction methods. The wooden formwork saving rate and the plastering-free rate can reach more than 90%, which greatly reduces the use of wood, cement, sand and water, and achieves the energy efficiency of saving materials and water. In terms of energy saving, the exterior wall insulation system has achieved a separate design without insulation, and finally achieves the effect of green construction, energy saving and emission reduction.

[0024] 5. The present invention improves the installation efficiency between various installation projects in the later stage, avoids common quality problems such as leakage of external walls and hollow plastering in the later stage, and achieves the goal of early construction by interspersing various processes. Compared with the traditional construction method, it saves 6 to 7 months of construction time, achieving the goal of efficient construction and comprehensively improving construction quality. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a schematic diagram of the anti-collision structure of the attached lifting scaffold and the tower crane of the present invention;

[0026] Figure 2 It is a schematic diagram of the anti-collision structure of the attached lifting scaffold and the external wall aluminum formwork of the present invention;

[0027] Figure 3 It is a schematic diagram of the anti-collision facade structure of the attached lifting scaffold and the construction elevator of the present invention;

[0028] Figure 4 It is a schematic diagram of the structure of the detachable inner cantilever plate of the present invention.

[0029] In the figure: 1-tower crane, 2-inner walkway plate, 3-external shear wall, 4-walkway plate, 5-detachable inner cantilever plate, 6-upper attachment point of construction elevator. DETAILED DESCRIPTION

[0030] The present invention will be described in detail below in conjunction with the accompanying drawings.

[0031] In order to make the purpose, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments.

[0032] In this embodiment, the data used are preferred solutions, but are not used to limit the present invention;

[0033] Example 1

[0034] The present embodiment provides a fully interlaced anti-collision system for building construction, including an attached lifting scaffolding, which climbs along with the construction progress of the main body of the building construction floor, and the real-time construction layer of the main body of the building construction floor is N layers. The attached lifting scaffolding includes two states: rising and docking. In the rising state, the attached lifting scaffolding is provided with an opening and a reserved time at the collision position with the aluminum form, the construction elevator and the tower crane. In the docking state, the attached lifting scaffolding is provided with an attachment point overlap and a staggered position at the collision position with the aluminum form, the construction elevator and the tower crane.

[0035] In this embodiment, preferably, when the attached lifting scaffolding is in the rising state, a gap of 10 cm is set between the edge line of the inner walkway board of the attached lifting scaffolding and the back rib of the outer wall aluminum formwork, and a distance of 30 cm is set between the edge line of the inner walkway and the edge line of the outer shear wall main structure. Furthermore, a back rib width of 15 cm, a formwork thickness of 5 cm, and a 10 cm reserved rising gap of the attached lifting scaffolding are set; the adjacent built floor of the real-time construction layer of the main body of the building construction floor is the N-1 floor, the aluminum formwork of the external shear wall of the N-1 floor is dismantled, and the installation of the external shear wall of the N layer is 70%-90% completed, that is, on the second day after the concrete pouring of the N layer is completed, the attached lifting scaffolding climbs with the main body of the floor.

[0036] In this embodiment, preferably, when the attached lifting scaffold is in the ascending state, the attached lifting scaffold has an opening of 4.4 meters, so as to ensure that the construction elevator can climb through the opening of the attached lifting scaffold.

[0037] In this embodiment, when the attached lifting scaffold is in the ascending state, the attached lifting scaffold is positioned according to the tower crane attachment point, and walkway boards are arranged on both sides of the tower crane attachment point to form a bridge. Preferably, the length of a single walkway board is 2 meters. During the ascending process of the attached lifting scaffold, the bridge is lifted and opened, and the attached lifting scaffold passes through the tower crane attachment point without colliding with the tower crane.

[0038] In this embodiment, when the attached lifting scaffold is in the docked state, the attached lifting scaffold overlaps with the exterior wall aluminum formwork, and the exterior wall aluminum formwork is provided with two aluminum formwork single plates, so that the aluminum formwork at the base position of the attached lifting scaffold is separated from the exterior wall large plate, ensuring that the installation of the attached lifting scaffold base and the assembly of the aluminum formwork large plate do not conflict; the step distance of the attached lifting scaffold base is synchronized with the real-time construction step distance of the main body of the building construction floor, ensuring that the attached lifting scaffold base has a structure to be attached; the horizontal extension section of the attached lifting scaffold base should be larger than the outline setting of the house facade line, ensuring that the attached lifting scaffold walkway plate does not overlap with the building structure line.

[0039] In this embodiment, when the attached lifting scaffold is in the docked state, the uppermost attachment point of the construction elevator is set at the top of the opening position of the attached lifting scaffold, and the attached lifting scaffold is set on both sides of the opening position to avoid being set in the construction elevator area.

[0040] In this embodiment, when the attached lifting scaffold is in the docked state, the attached lifting scaffold is staggered with the tower crane attachment point, and the attached lifting scaffold is arranged on both sides of the bridge to balance the bearing capacity at both ends of the bridge.

[0041] Example 2

[0042] The present embodiment discloses a fully interpenetrating anti-collision system for building construction, including a fully interpenetrating construction system, the fully interpenetrating construction system includes fully interpenetrating construction of the exterior walls of the building and fully interpenetrating construction of the interior walls of the building, the exterior wall interpenetration is divided into paint interpenetration and door and window interpenetration; the interior interpenetration is divided into four parts: civil engineering interpenetration, secondary structure interpenetration, installation interpenetration, and decoration interpenetration.

[0043] In this embodiment, the fully interspersed construction system includes an attached lifting scaffolding, which climbs with the progress of the main building. Before the climbing frame is lifted, the exterior wall decoration project is completed and only the exterior wall paint is left. At the same time, the exterior window frame installation is completed; the scaffolding has good sealing at high altitudes, and the construction of the exterior wall paint primer avoids pollution to the walls of the lower floors; the scaffolding body has a high turnover and reuse rate, which saves a lot of manpower and material resources and speeds up the construction progress.

[0044] In this embodiment, the fully interspersed construction system includes a vertical construction slag transportation system and a horizontal water cutoff system. The vertical construction slag transportation system uses the flue shaft to set up a vertical construction slag transportation channel on the floor or a fixed construction slag transportation channel on the facade to ensure that the construction slag on each floor is transferred to the next floor in time and the channel is used as a concrete pump pipe washing pump channel to provide sufficient working surface for subsequent construction.

[0045] Furthermore, the horizontal water interception system realizes the floor water interception system for dry and wet zoning construction of the floor, ensuring the normal interlacing of all process working surfaces; (1) All reserved openings on the floor, including water and electricity wells, flues, and air wells, are covered with mortar edge templates and painted with a uniform safety warning color. (2) All water sources on the floor are drained to the collection pool and then discharged through pipes. For water interception at the staircase, 110PVC plastic pipes are used to be divided into two for on-site installation. (3) Preferably, U-shaped water interception grooves are purchased for the exterior wall and arranged continuously along the four sides of the exterior wall, with a slope of 1%. A drainage pipe is added at the lowest point to drain the water to the nearest water collection point, and the water is discharged through the permanent drainage pipes on the floor to avoid pollution of the exterior wall during concrete pouring and ensure the normal interlacing construction of the exterior wall.

[0046] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A fully interlaced anti-collision system for building construction, including an attached lifting scaffold, which climbs with the construction progress of the main building floor of the building, and the main building floor of the building is N layers in real time, characterized in that: The attached lifting scaffolding includes two states: rising and stopping. When the attached lifting scaffolding is in the rising state, an opening and a reserved time are set at the collision position with the aluminum mold, the construction elevator and the tower crane (1). When the attached lifting scaffolding is in the stopping state, an attachment point overlap and a staggered position are set at the collision position with the aluminum mold, the construction elevator and the tower crane (1). When the attached lifting scaffold is in the ascending state, the gap between the edge line of the inner walkway plate (2) of the attached lifting scaffold and the back rib of the outer wall aluminum formwork is set to 8-12 cm, and the distance between the edge line of the inner walkway plate (2) and the edge line of the main structure of the outer shear wall (3) is set to 25-35 cm. The adjacent built floor of the real-time construction layer of the main body of the building construction floor is the N-1 floor. The aluminum formwork of the outer shear wall of the N-1 floor has been removed, and the installation of the outer shear wall of the N floor has been completed by 70%-90%. The attached lifting scaffold climbs with the main body of the floor; When the attached lifting scaffold is in the ascending state, the opening of the attached lifting scaffold is 4.2-4.6 meters, and the construction elevator climbs through the opening of the attached lifting scaffold; When the attached lifting scaffold is in a docked state, the attached lifting scaffold overlaps with the exterior wall aluminum formwork, and the exterior wall aluminum formwork is provided with two aluminum formwork single plates, so that the aluminum formwork at the base of the attached lifting scaffold is separated from the exterior wall large plate; the step distance of the attached lifting scaffold base is synchronized with the real-time construction step distance of the main body of the building construction floor; the horizontal extension section of the attached lifting scaffold base should be greater than the outline setting of the exterior facade line of the house; A detachable inner cantilever plate (5) is arranged on the walkway plate of the attached lifting scaffolding, and the attached lifting scaffolding prevents collision with the aluminum mold and positions the outer contour of the aluminum mold.

2. The fully interlaced anti-collision system for building construction according to claim 1 is characterized in that: When the attached lifting scaffold is in an ascending state, the attached lifting scaffold is positioned according to the attachment point of the tower crane (1), and walkway plates (4) are arranged on both sides of the attachment point of the tower crane (1) to form a bridge. During the ascending process of the attached lifting scaffold, the bridge is lifted and opened, and the attached lifting scaffold passes through the attachment point of the tower crane (1) without colliding with the tower crane (1).

3. The fully interlaced anti-collision system for building construction according to claim 2 is characterized in that: When the attached lifting scaffold is in a parked state, the upper attachment point (6) of the construction elevator is arranged at the top of an opening position of the attached lifting scaffold, and the attached lifting scaffold machine positions are arranged on both sides of the opening position.

4. The fully interlaced anti-collision system for building construction according to claim 3 is characterized in that: When the attached lifting scaffold is in a docked state, the attached lifting scaffold position and the tower crane (1) attachment point are staggered, and the attached lifting scaffold position is arranged on both sides of the bridge, so that the bearing capacity at both ends of the bridge is balanced.