New energy power station and control method and device thereof

By obtaining operating parameters in the new energy power station, the new energy power generation system and the energy storage system are controlled to respond to each other when performing frequency regulation and energy storage scheduling, which solves the problem of the energy storage system in the existing technology being unable to respond to scheduling, and realizes the new energy power station Parallel operation with the energy storage system improves the utilization rate of the energy storage system and the auxiliary service function of the grid.

CN114221383BActive Publication Date: 2024-10-18HEFEI SUNGROW RENEWABLE ENERGY SCI & TECH CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202111531241.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-12-14
Publication Date
2024-10-18
Estimated Expiration
2041-12-14

AI Technical Summary

Technical Problem

The existing serial control strategies of new energy power stations and energy storage systems cannot achieve multi-mode parallel operation, resulting in the energy storage system being unable to respond to dispatching instructions during frequency regulation of new energy power stations, reducing the utilization rate of the energy storage system and assisting the power grid. Service functions.

Method used

By obtaining the operating parameters of the power station, the new energy power generation system and the energy storage system are controlled to respond to each other when performing frequency regulation and energy storage scheduling, thereby achieving parallel operation of primary frequency regulation and energy storage scheduling. Specific methods include responding to energy storage dispatch instructions when the new energy power generation system performs frequency regulation, and performing frequency modulation when the energy storage system performs energy storage dispatch to improve the system's flexibility and auxiliary service capabilities.

Benefits of technology

It achieves joint frequency regulation and dispatching of new energy power generation systems and energy storage systems, improves the utilization rate of the energy storage system and its auxiliary service functions to the power grid, and meets the needs for stable operation of the power grid and clean energy acceptance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114221383B_ABST
    Figure CN114221383B_ABST
Patent Text Reader

Abstract

The embodiment of the present invention discloses a new energy power station and its control method and device. The method includes: obtaining the operating parameters of the power station; if the new energy power generation system performs a primary frequency modulation and receives a remote dispatching instruction, then controlling the energy storage system to perform energy storage dispatching according to the operating parameters, and controlling the new energy power generation system to maintain the primary frequency modulation; if the energy storage system performs energy storage dispatching and needs to perform a primary frequency modulation, then controlling the new energy power generation system to perform a primary frequency modulation according to the operating parameters, and controlling the energy storage system to maintain the execution of energy storage dispatching. Compared with the prior art, the embodiment of the present invention realizes the parallel operation of primary frequency modulation and energy storage dispatching, which improves the utilization rate of the energy storage system and the auxiliary service function of supporting the power grid.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The embodiments of the present invention relate to the field of renewable energy power generation technology, and in particular to a renewable energy power station and a control method and device thereof. Background Art

[0002] With the advancement of renewable energy power generation technology, the installed capacity of renewable energy power stations has increased rapidly. Correspondingly, the increase in the installed capacity of renewable energy power stations has an increasingly prominent impact on the stable operation of the power grid.

[0003] In the prior art, the solution of adding energy storage systems to new energy power stations is usually adopted to achieve grid stability, and the solution of adding energy storage systems to new energy power stations has become a trend. However, the problem is that the existing mode fusion of new energy power stations + energy storage adopts a serial control strategy, executes a single mode function according to the entry conditions, and cannot achieve multi-mode parallel operation. Specifically, the energy storage system can assist the new energy power station in power regulation (energy storage scheduling), but when the new energy power station performs a frequency modulation, the energy storage system cannot respond to the telecontrol scheduling command, which reduces the utilization rate of the energy storage system and the auxiliary service function of supporting the power grid. Summary of the invention

[0004] The embodiment of the present invention provides a new energy power station and a control method and device thereof to realize the parallel operation of primary frequency regulation and energy storage scheduling, improve the utilization rate of the energy storage system and support the auxiliary service functions of the power grid.

[0005] In a first aspect, an embodiment of the present invention provides a control method for a new energy power station, wherein the power station includes a new energy power generation system and an energy storage system, and the method includes:

[0006] Obtaining operating parameters of the power station;

[0007] If the new energy power generation system performs primary frequency modulation and receives a telecontrol dispatch instruction, the energy storage system is controlled to perform energy storage dispatch according to the operating parameters, and the new energy power generation system is controlled to maintain primary frequency modulation at the same time;

[0008] If the energy storage system executes energy storage scheduling and needs to perform a frequency modulation, the new energy power generation system is controlled to perform a frequency modulation according to the operating parameters, and at the same time, the energy storage system is controlled to maintain the execution of energy storage scheduling.

[0009] Optionally, the operating parameters include telecontrol dispatching power and total power station power;

[0010] Controlling the energy storage system to perform energy storage scheduling and controlling the new energy power generation system to maintain primary frequency modulation, including:

[0011] Calculate the new energy target power according to the telecontrol dispatching power and the total power of the power station;

[0012] The new energy power generation system is controlled to perform a frequency modulation according to the new energy target power, and the energy storage system is controlled to perform energy storage scheduling according to the telecontrol scheduling power.

[0013] Optionally, after calculating the new energy target power, the method further includes:

[0014] Determine whether the target power of the new energy source meets the power limit range; if so, execute the step of controlling the new energy power generation system to perform a frequency modulation according to the target power of the new energy source;

[0015] Otherwise, the step of controlling the new energy power generation system to maintain a frequency regulation according to the new energy target power of the previous control cycle.

[0016] Optionally, the power limit range includes an upper power limit value and a lower power limit value; wherein, the upper power limit value is determined according to the rated capacity of the model machine and the total rated capacity of the power station, and the lower power limit value is determined according to the rated capacity of the model machine and the total rated capacity of the power station.

[0017] Optionally, after calculating the new energy target power, the method further includes:

[0018] Determine whether the renewable energy power generation system meets the power actual generation requirement; if so, execute the step of controlling the renewable energy power generation system to perform a frequency modulation according to the renewable energy target power;

[0019] Otherwise, the step of controlling the new energy power generation system to maintain a frequency regulation according to the new energy target power of the previous control cycle.

[0020] Optionally, the operating parameters include power station frequency difference and telecontrol dispatching power;

[0021] Controlling the new energy power generation system to perform a frequency modulation, and controlling the energy storage system to maintain energy storage scheduling, including:

[0022] Calculating a primary frequency regulation amount according to the power station frequency difference;

[0023] Calculate the new energy target power according to the primary frequency regulation amount and the telecontrol dispatching power;

[0024] The new energy power generation system is controlled to perform a frequency modulation according to the new energy target power, and the energy storage system is controlled to maintain energy storage scheduling according to the remote scheduling power.

[0025] Optionally, the conditions for performing frequency modulation once when the energy storage system performs energy storage scheduling include:

[0026] The real-time frequency of the power station is greater than the upper limit value; accordingly, the power station frequency difference is the difference between the real-time frequency of the power station and the upper limit value;

[0027] Alternatively, the real-time frequency of the power station is lower than the lower limit; accordingly, the power station frequency difference is the difference between the real-time frequency of the power station and the lower limit.

[0028] Optionally, the operating parameters further include the total rated capacity, rated frequency and regulation rate of the power station;

[0029] The calculation method of the primary frequency modulation amount includes:

[0030] The primary frequency regulation amount is calculated according to the total rated capacity, the rated frequency, the regulation rate and the power station frequency difference.

[0031] Optionally, the operating parameters also include automatic power generation control and dispatching power;

[0032] The calculation method of the new energy target power includes:

[0033] Calculating a primary frequency regulation target power according to the automatic generation control dispatching power and the primary frequency regulation amount;

[0034] The new energy target power is calculated according to the primary frequency regulation target power and the telecontrol dispatching power.

[0035] In a second aspect, an embodiment of the present invention further provides a control device for a new energy power station, wherein the new energy power station includes a new energy power generation system and an energy storage system, and the device includes:

[0036] A parameter acquisition module, used to acquire the operating parameters of the power station;

[0037] A primary frequency regulation response energy storage dispatching module is used to control the energy storage system to perform energy storage dispatching according to the operating parameters when the new energy power generation system performs primary frequency regulation and receives a telecontrol dispatching instruction, and at the same time control the new energy power generation system to maintain primary frequency regulation;

[0038] The energy storage scheduling executes a frequency modulation module, which is used to control the new energy power generation system to execute a frequency modulation according to the operating parameters when the energy storage system executes energy storage scheduling and needs to execute a frequency modulation, and at the same time control the energy storage system to maintain executing energy storage scheduling.

[0039] In a third aspect, an embodiment of the present invention further provides a new energy power station, comprising: a new energy power generation system, an energy storage system and a controller, wherein the controller is used to execute the control method of the new energy power station as described in any embodiment of the present invention.

[0040] Optionally, the new energy power generation system includes at least one of a photovoltaic system, a wind power system, a biomass energy system, a geothermal energy power generation system, a wave energy power generation system, an ocean current energy power generation system, a tidal energy power generation system and a hydrogen energy power generation system.

[0041] Embodiments of the invention The embodiments of the invention control the energy storage system to perform energy storage scheduling according to the operating parameters when the new energy power generation system performs a frequency modulation and receives a remote dispatching instruction, and at the same time controls the new energy power generation system to maintain a frequency modulation; when the new energy power generation system performs a frequency modulation, the energy storage system responds to the dispatching requirements, that is, the parallel operation of the frequency modulation + response scheduling is realized. And, the embodiments of the invention control the new energy power generation system to perform a frequency modulation according to the operating parameters when the energy storage system performs energy storage scheduling and needs to perform a frequency modulation, and at the same time controls the energy storage system to maintain the execution of energy storage scheduling; when the energy storage system responds to the scheduling, the new energy power generation system performs a frequency modulation, that is, when the energy storage system supports the power grid response scheduling, if a frequency disturbance occurs, the energy storage system can continue to support the power grid response scheduling power, and at the same time the new energy power generation system performs a frequency modulation, that is, the parallel operation of the response scheduling + the frequency modulation is realized. Therefore, the embodiments of the invention realize the primary frequency modulation and response scheduling of the new energy power generation system + energy storage, improve the utilization rate of the energy storage system and the auxiliary service function of supporting the power grid, which is conducive to the acceptance of clean energy, the regulation of the power system and the auxiliary services for the power grid. Furthermore, the embodiments of the present invention are helpful in satisfying the assessment requirements for energy storage response scheduling functions in power grid assessment requirements. BRIEF DESCRIPTION OF THE DRAWINGS

[0042] Figure 1 A schematic diagram of the structure of a new energy power station provided by an embodiment of the present invention;

[0043] Figure 2 A schematic diagram of the structure of another new energy power station provided by an embodiment of the present invention;

[0044] Figure 3 A schematic diagram of a control method for a new energy power station provided by an embodiment of the present invention;

[0045] Figure 4 A flowchart of a method for implementing a primary frequency modulation + response scheduling parallel operation provided by an embodiment of the present invention;

[0046] Figure 5 A flowchart of another method for implementing the parallel operation of primary frequency modulation + response scheduling provided by an embodiment of the present invention;

[0047] Figure 6 A flowchart of another method for implementing the parallel operation of primary frequency modulation + response scheduling provided by an embodiment of the present invention;

[0048] Figure 7 A flowchart of a method for implementing a primary frequency modulation + response scheduling parallel operation provided by an embodiment of the present invention;

[0049] Figure 8 A flowchart of a method for implementing parallel operation of response scheduling + primary frequency modulation provided by an embodiment of the present invention;

[0050] Fig. 9 A flowchart of another implementation method of response scheduling + primary frequency modulation running in parallel provided by an embodiment of the present invention;

[0051] Fig.10 A schematic structural diagram of a control device for a new energy power station provided in an embodiment of the present invention. DETAILED DESCRIPTION

[0052] The present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the present invention, rather than to limit the present invention. It should also be noted that, for ease of description, only parts related to the present invention, rather than all structures, are shown in the accompanying drawings.

[0053] The embodiments of the present invention provide a new energy power station, a control method for a new energy power station, and a control device for a new energy power station. The control method is implemented based on the new energy power station provided by any embodiment of the present invention and the application scenario. The new energy power station adopts the control method provided by any embodiment of the present invention to achieve the beneficial effects brought by the control method. The control method is executed by a control device, which can be implemented by software and / or hardware, and the control device is integrated in the control of the new energy power station.

[0054] In order to better illustrate the implementation principle of the control method provided by the embodiment of the present invention, the structure of the new energy power station is firstly described.

[0055] Figure 1 A schematic diagram of a new energy power station provided by an embodiment of the present invention. Figure 1, the new energy power station includes: a new energy power generation system 11, an energy storage system 12 and a controller 13. Among them, the new energy power generation system 11 refers to a system for generating electricity by developing and utilizing renewable energy sources that are different from conventional energy sources such as coal and oil on the basis of new technologies. The new energy power generation system 11 can be, for example, a photovoltaic system, a wind power system, a biomass energy system, a geothermal power generation system, a wave power generation system, an ocean current power generation system, a tidal power generation system and a hydrogen power generation system. Among them, the application technology of photovoltaic systems and wind power systems is the most mature and they are the most commonly used new energy power generation systems 11. The energy storage system 12 refers to a system that can store and output electrical energy. The energy storage system 12 can include, for example, multiple battery packs. The controller 13 can also be called a central controller 13 or a master controller 13, etc. The controller 13 can collect the operating parameters of the new energy power station and use a certain control strategy to control the new energy power generation system 11 and the energy storage system 12.

[0056] Figure 2 A schematic diagram of the structure of another new energy power station equipped with an energy storage system 12 provided in an embodiment of the present invention. Figure 2 On the basis of the above embodiments, optionally, the new energy power generation system 11 is a photovoltaic system 19, and correspondingly, the new energy power station is a photovoltaic storage power station. The photovoltaic storage power station also includes: a photovoltaic grid connection point 14, an energy storage grid connection point 15 and a photovoltaic storage grid connection point 16. Among them, the photovoltaic grid connection point 14 is connected between the photovoltaic system 19 and the photovoltaic storage grid connection point 16, the energy storage grid connection point 15 is connected between the energy storage system 12 and the photovoltaic storage grid connection point 16, and the photovoltaic storage grid connection point 16 is used to connect the photovoltaic storage power station to the grid. It can be seen that electric energy is transmitted between the photovoltaic system 19, the photovoltaic storage grid connection point 16, the energy storage grid connection point 15 and the energy storage system 12.

[0057] The photovoltaic power station also includes: a switch 17 and an automatic generation control system 18 (Automatic Generation Control, AGC). Among them, the switch 17 is connected to the photovoltaic system 19 for data transmission; the switch 17 is connected to the photovoltaic grid point 14 for data transmission; the switch 17 is connected to the energy storage system 12 for data transmission; the switch 17 is connected to the energy storage grid point 15 for data transmission; the switch 17 is connected to the automatic generation control system 18 for data transmission; the switch 17 is connected to the controller 13 for data transmission. Exemplarily, the operating parameters of the power station collected by the switch 17 include: automatic generation control dispatching power P AGC , telecontrol dispatch instruction I y , telecontrol dispatch power P y , total power station power P a (The total power of the photovoltaic power station is the total power of the photovoltaic power station), the power station frequency f a (The photovoltaic power station is the photovoltaic storage frequency), the total power of renewable energy generation P S(The total photovoltaic power of the photovoltaic power station) and the total energy storage power P e etc., and transmit the operating parameters of these power stations to the controller 13, and the controller 13 controls the photovoltaic system 19 and the energy storage system 12 according to the operating parameters of the power station. The automatic power generation control system 18 is also used to receive provincial dispatching data, and the switch 17 is also used to receive telecontrol dispatching instructions.

[0058] An embodiment of the present invention further provides a control method for a new energy power station, and the control method is applicable to the new energy power station provided by any embodiment of the present invention. Figure 3 A schematic diagram of a control method for a new energy power station provided by an embodiment of the present invention. Figure 3 , the control method comprises the following steps:

[0059] S110: Obtain operating parameters of the power station.

[0060] The operating parameters of the power station include control instructions, state parameters, and set thresholds. The control instructions may be, for example, the automatic power generation control dispatching power P AGC , Telecontrol Dispatch Command I y and telecontrol dispatch power P y etc.; the state parameter may be, for example, the total power of the power station P a (The total power of the photovoltaic power station is the total power of the photovoltaic power station), the power station frequency f a (The photovoltaic power station is the photovoltaic storage frequency), the total power of renewable energy generation P S (The total photovoltaic power of the photovoltaic power station) and the total energy storage power P e etc.; the threshold value may be, for example, the power upper limit value P max , power lower limit P min , actual power dead zone λ, primary frequency modulation rate δ, frequency upper limit f H and the lower frequency limit f L wait.

[0061] S120: If the new energy power generation system performs primary frequency modulation and receives a telecontrol dispatch instruction, the energy storage system is controlled to perform energy storage dispatch according to the operating parameters, and the new energy power generation system is controlled to maintain primary frequency modulation.

[0062] S130: If the energy storage system executes energy storage scheduling and needs to perform a frequency modulation, the new energy power generation system is controlled to perform a frequency modulation according to the operating parameters, and the energy storage system is controlled to maintain the execution of energy storage scheduling.

[0063] In S120 and S130, primary frequency regulation refers to the control process of limiting the change of grid frequency and maintaining the grid frequency stable by controlling the increase or decrease of the active power of the renewable energy power generation system when the grid frequency deviates from the rated value (grid frequency disturbance). Primary frequency regulation is achieved by controlling the renewable energy power generation system. When the output power of the renewable energy power generation system is greater than the total power consumed by the load, the grid frequency rises; when the output power of the renewable energy power generation system is less than the total power consumed by the load, the grid frequency decreases. Telecontrol dispatch refers to the process of automatically monitoring, coordinating, regulating and controlling the various components, local systems or the entire system of the power system locally or remotely through signal and data transmission systems. Telecontrol dispatch is achieved by the response of the energy storage system, which provides telecontrol dispatch power.

[0064] It can be seen that primary frequency regulation and response dispatch are two control methods. In the prior art, a single mode function is executed according to the entry conditions, and the parallel operation of primary frequency regulation and response dispatch cannot be realized. Specifically, in the prior art, when the new energy power generation system performs primary frequency regulation, the energy storage system cannot respond to the dispatch; and when the energy storage system responds to the dispatch, the new energy power generation system cannot perform primary frequency regulation.

[0065] The embodiment of the present invention realizes through S120 that when the new energy power generation system performs a primary frequency modulation, the energy storage system responds to the scheduling requirements, that is, the parallel operation of primary frequency modulation + response scheduling is realized; through S130, the new energy power generation system performs a primary frequency modulation when the energy storage system responds to scheduling, that is, when the energy storage system supports the power grid response scheduling, if a frequency disturbance occurs, the energy storage system can continue to support the power grid response scheduling power, and at the same time the new energy power generation system performs a primary frequency modulation, that is, the parallel operation of response scheduling + primary frequency modulation is realized. Therefore, the embodiment of the present invention realizes the primary frequency modulation and response scheduling of the new energy power generation system + energy storage, improves the utilization rate of the energy storage system and the auxiliary service function of supporting the power grid, and is conducive to the realization of clean energy acceptance, power system regulation and auxiliary services for the power grid. In addition, the embodiment of the present invention is conducive to meeting the assessment requirements for the energy storage response scheduling function in the power grid assessment requirements.

[0066] In the above embodiments, there are multiple implementations of S120 and S130, several of which are described below, but are not intended to limit the present invention.

[0067] Figure 4 A flowchart of a method for implementing a primary frequency modulation + response scheduling parallel operation provided by an embodiment of the present invention. Figure 4 In one embodiment of the present invention, optionally, controlling the energy storage system to perform energy storage scheduling and controlling the new energy power generation system to maintain primary frequency regulation (primary frequency regulation + response scheduling running in parallel) includes the following steps:

[0068] S121. Calculate the target power of new energy sources based on the telecontrol dispatching power and the total power of the power station.

[0069] Among them, the telecontrol dispatch is responded by the energy storage system, and the telecontrol dispatch power P y This is the target power that the energy storage system needs to achieve. New energy target power P sp It refers to the target power that the new energy power generation system needs to achieve. The new energy target power P sp The power P can be dispatched by telecontrol y And the total power of the power station P a Calculation shows that, for example, the total power plant power P a and telecontrol dispatch power P y The target power of new energy can be obtained by subtracting sp .

[0070] S122. Control the new energy power generation system to perform a frequency modulation according to the new energy target power, and control the energy storage system to perform energy storage scheduling according to the telecontrol scheduling power.

[0071] Among them, the new energy target power P sp The calculation takes into account the needs of telecontrol dispatching. Therefore, it can meet the needs of primary frequency regulation and telecontrol dispatching at the same time, which is conducive to the parallel operation of primary frequency regulation and telecontrol dispatching.

[0072] Through S121-S122, the energy storage system is controlled to execute energy storage scheduling, while the new energy power generation system is controlled to maintain primary frequency regulation.

[0073] Figure 5 A flowchart of another method for implementing the parallel operation of primary frequency modulation + response scheduling provided by an embodiment of the present invention. Figure 5 Based on the above embodiments, the embodiment of the present invention takes into account the power limit condition. The specific steps are as follows:

[0074] S121. Calculate the target power of new energy sources based on the telecontrol dispatching power and the total power of the power station.

[0075] S123, determine whether the target power of the new energy source meets the power limit range; if so, execute S124; otherwise, execute S125.

[0076] The power limit range is related to the design capacity of the new energy power station. Operation beyond the power limit range will affect the life of the new energy power generation system and even cause operational failures. Optionally, the power limit range includes a power upper limit value P max And the power lower limit P min , new energy target power P sp Need to satisfy the inequality relationship P max ≤P sp ≤Pnin Among them, the power upper limit value P nax According to the rated capacity of the sample machine L m and the total rated capacity of the power station to determine L a , power lower limit P min According to the rated capacity of the sample machine L m and the total rated capacity of the power station L a OK. Power upper limit value P max And the power lower limit P min The determination of can be determined by an empirical formula, which is not limited in the present invention.

[0077] S124, controlling the new energy power generation system to perform a frequency modulation according to the new energy target power of this control cycle, and controlling the energy storage system to perform energy storage scheduling according to the telecontrol scheduling power.

[0078] Among them, this step is the specific implementation method of S122 when the power limit range is met. If the new energy target power P sp Meeting the power limit range indicates that the new energy power generation system can meet the new energy target power P sp , so that the new energy target power P of this control cycle can be sp Control the renewable energy power generation system to perform primary frequency regulation.

[0079] S125. Control the new energy power generation system to maintain primary frequency modulation according to the new energy target power of the previous control cycle, and control the energy storage system to perform energy storage scheduling according to the telecontrol scheduling power.

[0080] Among them, this step is a specific implementation method of S122 when the power limit range is not met. If the new energy target power P sp The power limit range is not met, indicating that the new energy power generation system cannot meet the new energy target power P sp , so that the new energy target power P of the previous control cycle can be sp_0 Control the renewable energy power generation system to perform a frequency modulation to maintain the stable operation of the renewable energy power generation system.

[0081] Through S121-S125, the control energy storage system of the additional power limit condition is implemented to execute energy storage scheduling, and at the same time, the new energy power generation system is controlled to maintain the primary frequency regulation function. Among them, S124 and S125 are the control energy storage system of the new energy target power P sp When the power limit range is met / not met, there are two specific implementations of S122.

[0082] Figure 6 A flowchart of another method for implementing the parallel operation of primary frequency modulation + response scheduling provided by an embodiment of the present invention. Figure 6Based on the above embodiments, the embodiment of the present invention takes into account the actual power transmission condition. The specific steps are as follows:

[0083] S121. Calculate the target power of new energy sources based on the telecontrol dispatching power and the total power of the power station.

[0084] S126, determine whether the target power of the new energy source meets the actual power generation; if so, execute S127; otherwise, execute S128.

[0085] The rated capacity of the renewable energy power generation system is the sum of the rated outputs of each generator. However, due to load changes, line scheduling, maintenance of some units, or light intensity, wind power, etc., the renewable energy power generation system may not reach the rated output. At this time, it is necessary to consider the actual output of the renewable energy power generation system, that is, the actual power output. sp The actual power P rp When judging, consider the actual power P rp The margin of the actual power can be set to the dead zone λ, according to the actual power P rp and the actual power dead zone λ to determine the new energy target power P sp Whether the actual power is met.

[0086] S127. Control the new energy power generation system to perform a frequency modulation according to the new energy target power of this control cycle, and control the energy storage system to perform energy storage scheduling according to the telecontrol scheduling power.

[0087] This step is similar to S124 and is a specific implementation method of S122 when the actual power generation is met. If the target power of the new energy source P sp Meeting the actual power generation indicates that the new energy power generation system can meet the new energy target power P sp , so that the new energy target power P of this control cycle can be sp Control the renewable energy power generation system to perform primary frequency regulation.

[0088] S128. Control the new energy power generation system to maintain primary frequency modulation according to the new energy target power of the previous control cycle, and control the energy storage system to perform energy storage scheduling according to the telecontrol scheduling power.

[0089] This step is similar to S125 and is a specific implementation method of S122 when the actual power generation is not met. If the new energy target power P sp Failure to meet the actual power generation indicates that the new energy power generation system cannot meet the new energy target power P sp , so that the new energy target power P of the previous control cycle can be sp_0 Control the renewable energy power generation system to perform a frequency modulation to maintain the stable operation of the renewable energy power generation system.

[0090] Through S121, S126-S128, the control energy storage system of the additional power actual generation condition is implemented to execute energy storage scheduling, and at the same time, the new energy power generation system is controlled to maintain the primary frequency regulation function. Among them, S127 and S128 are the control energy storage system of the new energy target power P sp When the actual power transmission requirement is met / not met, there are two specific implementations of S122.

[0091] Figure 7 A flowchart of a method for implementing a primary frequency modulation + response scheduling parallel operation provided by an embodiment of the present invention. Figure 7 In one embodiment of the present invention, optionally, during a frequency modulation process of the new energy power generation system, the control method includes the following steps:

[0092] S12A, determine whether a remote control dispatch instruction is received; if so, execute S12B, otherwise execute S12G.

[0093] S12B, according to the telecontrol dispatch power P y And the total power of the power station P a Calculate the target power P of new energy sp .

[0094] S12C, according to the rated capacity of the sample machine L m and the total rated capacity of the power station to determine L a Determine the power upper limit value P max And the power lower limit P min .

[0095] S12D, determine the new energy target power P sp Is it between the upper limit value P max And the power lower limit P min If so, execute S12E, otherwise execute S12G.

[0096] S12E, issue new energy target power P sp To new energy power generation system.

[0097] S12F, send telecontrol dispatch power P y to the energy storage system; among them, the telecontrol dispatch power P y is the target power of energy storage.

[0098] S12G, according to the new energy target power P of the previous control cycle sp_0 Control the renewable energy power generation system to maintain primary frequency regulation.

[0099] Through S12A-S12G, the energy storage system responds to the scheduling needs when the new energy power generation system performs primary frequency regulation, that is, the parallel operation of primary frequency regulation + response scheduling is realized.

[0100] Figure 8 A flowchart of a method for implementing a response scheduling + primary frequency modulation parallel operation provided by an embodiment of the present invention. Figure 8 In one embodiment of the present invention, optionally, controlling the new energy power generation system to perform a primary frequency modulation, and controlling the energy storage system to maintain energy storage scheduling (response scheduling + primary frequency modulation running in parallel), includes the following steps:

[0101] S131. Calculate the primary frequency regulation amount according to the power station frequency difference.

[0102] The initiation condition of the primary frequency modulation is related to the frequency disturbance. Optionally, the conditions for executing the primary frequency modulation when the energy storage system executes the energy storage scheduling include: the real-time frequency f of the power station is greater than the upper limit f H Or less than the lower limit f L If the power station real-time frequency f is greater than the upper limit f H (f>f H ); accordingly, the power station frequency difference is the power station real-time frequency f and the upper limit value f H If the real-time frequency f of the power station is lower than the lower limit f L (f <f L ); accordingly, the power station frequency difference is the power station real-time frequency f and the lower limit f L Since the power station frequency can be adjusted by adjusting the power of the renewable energy power generation system, the primary frequency regulation amount ΔP f is a variable used to adjust the power of the renewable energy power generation system, and the primary frequency regulation ΔP f Related to the power station frequency difference.

[0103] S132. Calculate the target power of new energy according to the primary frequency regulation amount and the telecontrol dispatching power.

[0104] Among them, the new energy target power P sp It refers to the target power that needs to be achieved in the renewable energy power generation system. Due to different operation modes, the renewable energy target power P in this step is sp The calculation method of is also different from the calculation method in S121. sp The power P can be dispatched by automatic power generation control AGC , telecontrol dispatch power P y and the primary frequency modulation ΔP f Etc. calculated.

[0105] S133, controlling the new energy power generation system to perform a frequency modulation according to the new energy target power, and controlling the energy storage system to maintain the energy storage scheduling according to the telecontrol scheduling power.

[0106] Among them, the new energy target power P sp The calculation takes into account the needs of telecontrol dispatching. Therefore, it can meet the needs of primary frequency regulation and telecontrol dispatching at the same time, which is conducive to the parallel operation of primary frequency regulation and telecontrol dispatching.

[0107] Through S131-S133, it is realized to control the new energy power generation system to perform primary frequency modulation, and at the same time control the energy storage system to maintain the function of executing energy storage scheduling.

[0108] In the mode of response scheduling + primary frequency modulation running in parallel, optionally, the primary frequency modulation amount ΔP f The calculation method includes: according to the total rated capacity P N , rated frequency f N , the adjustment rate δ and the power station frequency difference, calculate the primary frequency adjustment ΔP f For example, if the real-time frequency f of the power station is lower than the lower limit f L (f <f L ), primary frequency modulation ΔP f With the power station real-time frequency f, lower limit value f L , total rated capacity P N , rated frequency f N , the modulation rate δ is related; if the real-time frequency f of the power station is higher than the upper limit f H (f <f H ), primary frequency modulation ΔP f With the power station real-time frequency f, upper limit value f H , total rated capacity P N , rated frequency f N , and the adjustment rate δ.

[0109] In the response scheduling + primary frequency modulation parallel operation mode, optionally, the new energy target power P sp The calculation method includes: according to the automatic power generation control dispatching power P AGC and the primary frequency modulation ΔP f , calculate the frequency modulation target power P f ; According to the primary frequency modulation target power P f and telecontrol dispatch power P y , calculate the new energy target power P sp Among them, the primary frequency regulation is to automatically control the dispatching power P AGC Based on the primary frequency modulation ΔP f is the adjustment amount. For example, the automatic power generation control dispatching power P AGC and the primary frequency modulation ΔP f The sum can be used to obtain the frequency modulation target power P f . New energy target power P sp Comprehensively consider the primary frequency modulation target power P fand telecontrol dispatch power P y , which can simultaneously meet the needs of response scheduling and primary frequency modulation. For example, the primary frequency modulation target power P f Subtract telecontrol dispatch power P y The new energy target power P can be obtained sp .

[0110] It should be noted that in the above embodiment, the new energy target power P sp The calculation method can be used for the new energy power generation system in the limited generation state or the unlimited generation state. The automatic generation control dispatching power P in the limited generation state and the unlimited generation state AGC If the power is in the limited state, the automatic power generation control dispatch power P AGC The automatic generation control dispatching power P received in real time during this control cycle AGC ; If it is in the unlimited generation state, the automatic generation control dispatch power P AGC The automatic generation control dispatching power P of the last control cycle AGC_0 , and the automatic generation control dispatching power P of the previous control cycle AGC_0 With the total power of the power station P a , telecontrol dispatch power P y In short, when the power generation is unlimited, the target power of new energy P sp The calculation method includes: according to the total power of the power station P a and the primary frequency modulation ΔP f , calculate the frequency modulation target power P f ; New energy target power P sp is the target power P for primary frequency modulation f .

[0111] It should be noted that in the response scheduling + primary frequency modulation parallel operation mode, the new energy target power P sp Power limit conditions and actual power conditions may also be considered, and their implementation method is the same as the mode of parallel operation of primary frequency modulation + response scheduling, which will not be repeated here.

[0112] Fig. 9 A flowchart of another implementation method of response scheduling + primary frequency modulation in parallel operation provided by an embodiment of the present invention. Fig. 9 In one embodiment of the present invention, optionally, in the process of the energy storage system responding to the dispatch, the control method includes the following steps:

[0113] S13A, determine whether the power station frequency is disturbed; if so, execute S13B, otherwise execute S13K.

[0114] S13B, based on the total rated capacity P N , rated frequency fN , the difference rate δ and the power station frequency difference to calculate the primary frequency regulation ΔP f .

[0115] S13C, dispatching power P according to automatic power generation control AGC and the primary frequency modulation ΔP f Calculate the target power P of a frequency modulation f .

[0116] S13D, according to the primary frequency modulation target power P f and telecontrol dispatch power P y Calculate the target power P of new energy sp .

[0117] S13E, according to the rated capacity of the sample machine L m and the total rated capacity of the power station to determine L a Determine the power upper limit value P max And the power lower limit P min .

[0118] S13F, determine the new energy target power P sp Is it between the upper limit value P max And the power lower limit P min If so, execute S13G, otherwise execute S13J.

[0119] S13G, issue new energy target power P sp To new energy power generation system.

[0120] S13H, the energy storage system continues to execute response scheduling.

[0121] S13J, according to the new energy target power P of the previous control cycle sp_0 Control the renewable energy power generation system to maintain primary frequency regulation.

[0122] Through S13A-S13J, when the energy storage system supports the grid response dispatch, if a frequency disturbance occurs, the energy storage system can continue to support the grid response dispatch power, and at the same time the new energy power generation system performs a frequency modulation, that is, the parallel operation of response dispatch + primary frequency modulation is realized.

[0123] The embodiment of the present invention further provides a control device for a new energy power station. The device is used to execute the control method for a new energy power station provided by any embodiment of the present invention, and has corresponding beneficial effects. Fig.10 A schematic diagram of the structure of a control device for a new energy power station provided by an embodiment of the present invention. Fig.10The device includes: a parameter acquisition module 21, a primary frequency regulation response energy storage dispatching module 22 and an energy storage dispatching execution primary frequency regulation module 23. The parameter acquisition module 21 is used to obtain the operating parameters of the power station; the primary frequency regulation response energy storage dispatching module 22 is used to control the energy storage system to perform energy storage dispatch according to the operating parameters when the new energy power generation system performs primary frequency regulation and receives a remote dispatching instruction, and at the same time controls the new energy power generation system to maintain primary frequency regulation; the energy storage dispatching execution primary frequency regulation module 23 is used to control the new energy power generation system to perform primary frequency regulation according to the operating parameters when the energy storage system performs energy storage dispatch and needs to perform primary frequency regulation, and at the same time controls the energy storage system to maintain energy storage dispatching.

[0124] Optionally, the primary frequency regulation response energy storage scheduling module 22 is also used to: calculate the new energy target power according to the telecontrol scheduling power; control the new energy power generation system to perform primary frequency regulation according to the new energy target power, and control the energy storage system to perform energy storage scheduling according to the telecontrol scheduling power.

[0125] Optionally, the primary frequency regulation response energy storage scheduling module 22 is also used to: after calculating the new energy target power, determine whether the new energy target power meets the power limit range; if so, execute the step of controlling the new energy power generation system to perform primary frequency regulation according to the new energy target power; otherwise, control the new energy power generation system to maintain primary frequency regulation according to the new energy target power of the previous control cycle.

[0126] Optionally, the power limit range includes an upper power limit value and a lower power limit value; wherein the upper power limit value is determined according to the rated capacity of the model machine and the total rated capacity of the power station, and the lower power limit value is determined according to the rated capacity of the model machine and the total rated capacity of the power station.

[0127] Optionally, the primary frequency regulation response energy storage scheduling module 22 is also used to: after calculating the new energy target power, determine whether the new energy power generation system meets the actual power generation; if so, execute the step of controlling the new energy power generation system to perform primary frequency regulation according to the new energy target power; otherwise, control the new energy power generation system to maintain primary frequency regulation according to the new energy target power of the previous control cycle.

[0128] Optionally, the energy storage scheduling execution primary frequency regulation module 23 is also used to calculate the primary frequency regulation amount according to the power station frequency difference; calculate the new energy target power according to the primary frequency regulation amount; control the new energy power generation system to execute primary frequency regulation according to the new energy target power, and at the same time control the energy storage system to maintain the execution of energy storage scheduling according to the remote scheduling power.

[0129] Optionally, the conditions for executing a frequency modulation when the energy storage system executes energy storage scheduling include: the real-time frequency of the power station is greater than the upper limit value; accordingly, the frequency difference of the power station is the difference between the real-time frequency of the power station and the upper limit value; or, the real-time frequency of the power station is lower than the lower limit value; accordingly, the frequency difference of the power station is the difference between the real-time frequency of the power station and the lower limit value.

[0130] Optionally, the energy storage scheduling execution primary frequency regulation module 23 is further used to calculate the primary frequency regulation amount according to the total rated capacity, the rated frequency, the regulation rate and the power station frequency difference.

[0131] Optionally, the energy storage scheduling execution primary frequency regulation module 23 is also used to calculate the primary frequency regulation target power according to the automatic power generation control scheduling power and the primary frequency regulation amount; and calculate the new energy target power according to the primary frequency regulation target power and the telecontrol scheduling power.

[0132] The embodiment of the present invention realizes that when the new energy power generation system performs a primary frequency modulation, the energy storage system responds to the scheduling requirements through the primary frequency modulation response energy storage scheduling module 22, that is, the parallel operation of primary frequency modulation + response scheduling is realized; the energy storage system performs a primary frequency modulation when the energy storage system responds to scheduling through the energy storage scheduling execution primary frequency modulation module 23, that is, when the energy storage system supports the power grid response scheduling, if a frequency disturbance occurs, the energy storage system can continue to support the power grid response scheduling power, and the new energy power generation system performs a primary frequency modulation at the same time, that is, the parallel operation of response scheduling + primary frequency modulation is realized. Therefore, the embodiment of the present invention realizes the primary frequency modulation and response scheduling of the new energy power generation system + energy storage, improves the utilization rate of the energy storage system and the auxiliary service function of supporting the power grid, and is conducive to the realization of clean energy acceptance, power system regulation and auxiliary services for the power grid. In addition, the embodiment of the present invention is conducive to meeting the assessment requirements for the energy storage response scheduling function in the power grid assessment requirements.

[0133] Note that the above are only preferred embodiments of the present invention and the technical principles used. Those skilled in the art will understand that the present invention is not limited to the specific embodiments described herein, and that various obvious changes, readjustments and substitutions can be made by those skilled in the art without departing from the scope of protection of the present invention. Therefore, although the present invention has been described in more detail through the above embodiments, the present invention is not limited to the above embodiments, and may include more other equivalent embodiments without departing from the concept of the present invention, and the scope of the present invention is determined by the scope of the appended claims.

Claims

1. A control method for a new energy power station, characterized in that: The power station includes a new energy power generation system and an energy storage system, and the method includes: Obtaining operating parameters of the power station; If the new energy power generation system performs primary frequency modulation and receives a telecontrol dispatch instruction, the energy storage system is controlled to perform energy storage dispatch according to the operating parameters, and the new energy power generation system is controlled to maintain primary frequency modulation at the same time; The operating parameters include telecontrol dispatching power and total power station power; Controlling the energy storage system to perform energy storage scheduling and controlling the new energy power generation system to maintain primary frequency modulation, including: Calculate the new energy target power according to the telecontrol dispatching power and the total power of the power station; Controlling the energy storage system to perform energy storage scheduling according to the telecontrol scheduling power, and controlling the new energy power generation system to maintain primary frequency modulation according to the new energy target power; If the energy storage system performs energy storage scheduling and needs to perform frequency modulation once, the new energy power generation system is controlled to perform frequency modulation once according to the operating parameters, and the energy storage system is controlled to maintain the energy storage scheduling at the same time; The operating parameters include power station frequency difference and telecontrol dispatching power; Controlling the new energy power generation system to perform a frequency modulation, and controlling the energy storage system to maintain energy storage scheduling, including: Calculating a primary frequency regulation amount according to the power station frequency difference; Calculate the new energy target power according to the primary frequency regulation amount and the telecontrol dispatching power; The new energy power generation system is controlled to perform a frequency modulation according to the new energy target power, and the energy storage system is controlled to maintain energy storage scheduling according to the remote scheduling power.

2. The control method of the new energy power station according to claim 1, characterized in that: After calculating the new energy target power according to the telecontrol dispatching power and the total power of the power station, the method further includes: Determine whether the target power of the new energy source meets the power limit range; if so, execute the step of controlling the new energy power generation system to perform a frequency modulation according to the target power of the new energy source; Otherwise, the step of controlling the new energy power generation system to maintain a frequency regulation according to the new energy target power of the previous control cycle.

3. The control method of the new energy power station according to claim 2, characterized in that: The power limit range includes an upper power limit value and a lower power limit value; wherein, the upper power limit value is determined according to the rated capacity of the model machine and the total rated capacity of the power station, and the lower power limit value is determined according to the rated capacity of the model machine and the total rated capacity of the power station.

4. The control method of the new energy power station according to claim 1, characterized in that: After calculating the new energy target power according to the telecontrol dispatching power and the total power of the power station, the method further includes: Determine whether the renewable energy power generation system meets the power actual generation requirement; if so, execute the step of controlling the renewable energy power generation system to perform a frequency modulation according to the renewable energy target power; Otherwise, the step of controlling the new energy power generation system to maintain a frequency regulation according to the new energy target power of the previous control cycle.

5. The control method of the new energy power station according to claim 1, characterized in that: The conditions for controlling the new energy power generation system to perform a frequency modulation and controlling the energy storage system to maintain energy storage scheduling include: The real-time frequency of the power station is greater than the upper limit value; accordingly, the power station frequency difference is the difference between the real-time frequency of the power station and the upper limit value; Alternatively, the real-time frequency of the power station is lower than the lower limit; accordingly, the power station frequency difference is the difference between the real-time frequency of the power station and the lower limit.

6. The control method of the new energy power station according to claim 5, characterized in that: The new energy power generation system is controlled to perform a frequency modulation according to the operating parameters, and the energy storage system is controlled to maintain energy storage scheduling; The operating parameters also include the total rated capacity, rated frequency and regulation rate of the power station; The calculation method of the primary frequency modulation amount includes: The primary frequency regulation amount is calculated according to the total rated capacity, the rated frequency, the regulation rate and the power station frequency difference.

7. The control method of the new energy power station according to claim 1, characterized in that: The new energy power generation system is controlled to perform a frequency modulation according to the operating parameters, and the energy storage system is controlled to maintain energy storage scheduling; Wherein, the operating parameters also include automatic power generation control dispatching power; The calculation method of the new energy target power includes: Calculating a primary frequency regulation target power according to the automatic generation control dispatching power and the primary frequency regulation amount; The new energy target power is calculated according to the primary frequency regulation target power and the telecontrol dispatching power.

8. A control device for a new energy power station, characterized in that: The new energy power station includes a new energy power generation system and an energy storage system, and the device includes: A parameter acquisition module, used to acquire the operating parameters of the power station; A primary frequency regulation response energy storage dispatching module is used to control the energy storage system to perform energy storage dispatching according to the operating parameters when the new energy power generation system performs primary frequency regulation and receives a telecontrol dispatching instruction, and at the same time control the new energy power generation system to maintain primary frequency regulation; The operating parameters include telecontrol dispatching power and total power station power; The primary frequency regulation response energy storage dispatching module is also used to calculate the new energy target power according to the telecontrol dispatching power and the total power of the power station; Controlling the energy storage system to perform energy storage scheduling according to the telecontrol scheduling power, and controlling the new energy power generation system to maintain primary frequency modulation according to the new energy target power; The energy storage scheduling executes a frequency modulation module, which is used to control the new energy power generation system to execute a frequency modulation according to the operating parameters when the energy storage system executes energy storage scheduling and needs to execute a frequency modulation, and at the same time control the energy storage system to maintain the execution of energy storage scheduling; The operating parameters include power station frequency difference and telecontrol dispatching power; The energy storage scheduling executes a primary frequency modulation module; and is also used to calculate the primary frequency modulation amount according to the power station frequency difference; Calculate the new energy target power according to the primary frequency regulation amount and the telecontrol dispatching power; The new energy power generation system is controlled to perform a frequency modulation according to the new energy target power, and the energy storage system is controlled to maintain energy storage scheduling according to the remote scheduling power.

9. A new energy power station, characterized in that: include: A new energy power generation system, an energy storage system and a controller, wherein the controller is used to execute the control method of the new energy power station as described in any one of claims 1 to 7.

10. The new energy power station according to claim 9, characterized in that: The new energy power generation system includes at least one of a photovoltaic system, a wind power system, a biomass energy system, a geothermal energy power generation system, a wave energy power generation system, an ocean current energy power generation system, a tidal energy power generation system and a hydrogen energy power generation system.

Citation Information

Patent Citations

  • Graded energy storage method for frequency modulation of photovoltaic power station based on energy storage

    CN110808594A

  • Control strategy for assisting new energy power station to participate in system frequency modulation through energy storage

    CN110912155A