A tower-type installation, disassembly and maintenance monitoring camera device and use method

Through the lifting and rotating functions of the tower-type installation, disassembly and maintenance surveillance camera device, the safety issues of high-altitude operations in the installation and maintenance of surveillance cameras are solved, and a safe and efficient construction process is achieved.

CN114321618BActive Publication Date: 2024-10-01NANJING YOUKUO ELECTRICAL TECH
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210133653.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-02-14
Publication Date
2024-10-01
Estimated Expiration
2042-02-14

AI Technical Summary

Technical Problem

There are safety risks in high-altitude operations during the installation and maintenance of existing surveillance cameras, and construction at night increases the risk of accidents, and it is difficult for existing technology to effectively protect operators and ensure construction safety.

Method used

A tower-type installation, disassembly, and maintenance surveillance camera device is adopted. The device includes a liftable vertical bobbin and a rotating flange. Through the cooperation of a hydraulic cylinder and an arc-shaped claw, the camera can be safely installed and repaired to avoid high-altitude operations and ensure safe operation at high altitudes. During the installation process, the camera pole can be rotated to a safe area.

Benefits of technology

It effectively avoids the risks of operators working at high altitudes, improves operating efficiency, ensures construction safety, and simplifies the installation and maintenance process of surveillance cameras.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114321618B_ABST
    Figure CN114321618B_ABST
Patent Text Reader

Abstract

The invention relates to a tower-type installation, disassembly and maintenance monitoring camera device and a method for using the device. The device comprises a tower frame and a rack mounted on the tower frame; a monitoring camera is mounted on the rack; the tower frame comprises a lower sleeve and an upper sleeve fixedly mounted on the lower sleeve, a lifting device for controlling the lifting of the rack is mounted in the upper sleeve, and supporting wheels are mounted at the bottom of the lower sleeve; the method comprises an installation method and a maintenance and disassembly method for the monitoring camera. The lifting device and a clamping device are mounted on the upper sleeve of the invention, and the reciprocating motion of the hydraulic cylinder of the lifting device and the arc-shaped claws of the clamping device allows the vertical tube to be raised and lowered, while preventing the vertical tube from tipping over.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a tower type installation, disassembly and maintenance monitoring camera device and a use method thereof, belonging to the technical field of municipal construction. Background Art

[0002] Video surveillance systems are widely used in many fields such as finance, roads and bridges, transportation, public security, security, education and medical care because of their intuitiveness, convenience and rich information content. In recent years, with the rapid development of digital image processing technology and digital circuit technology, the digitization and processing of image signals have become more common, and the use of digital image processing technology for dynamic monitoring and on-site monitoring has become a reality, and it has a very high sensitivity and reliability.

[0003] The cameras used in the video surveillance system can be roughly divided into two types. One is the traffic control camera, whose main function is to monitor the traffic conditions on the road in real time, including road monitoring, intersection violation monitoring and motor vehicle speed monitoring; the other is the public security monitoring camera, whose main function is to monitor the public security conditions of the road surface, construction sites, etc., so as to realize the dynamic and real-time management of roads and construction sites; and to effectively monitor the safety production, civilized construction, fire protection and other conditions at the construction site.

[0004] Currently, the installation location of the surveillance camera pole requires the use of concrete to build a pedestal on the ground, with a base set in the middle of the pedestal and bolts set on the base. After that, the mounting holes at the lower end of the pole correspond to the bolts on the base one by one and then fixed with nuts. This completes the installation of the pole and allows the surveillance camera on the pole to be suspended in the middle of the road.

[0005] The existing installation method requires the use of large-scale lifting machinery during installation, equipment replacement, regular maintenance or upgrading of related monitoring equipment and systems. At the same time, it is necessary to set up roadblocks, lane restrictions, and assign special personnel to maintain traffic, etc. This is not only not conducive to the normal passage of traffic, but also time-consuming and labor-intensive. At the same time, it cannot effectively protect the personal safety of related operators working at heights, and there are risks such as accidental falls of operators and accidental vehicle collisions, which poses safety risks.

[0006] In order to reduce the occurrence of related accidents, construction is often carried out at night. However, night construction not only reduces the effective construction time of operators, but also virtually increases the construction period of the entire project; and due to insufficient lighting at night, it increases the risk of accidental falls of operators and accidental vehicle collisions. If an accident unfortunately occurs, since the above-mentioned related operations are all carried out in the blind spot of monitoring, it is not convenient to verify the responsibility for the accident afterwards, so they cannot effectively protect the operators. Summary of the invention

[0007] In view of the above technical problems, the technical problem to be solved by the present invention is to provide a tower-type installation and maintenance monitoring camera device and a use method that is safe, reliable, and easy to install and disassemble.

[0008] The present invention adopts the following technical solution:

[0009] The tower-type installation, disassembly and maintenance monitoring camera device of the present invention comprises a tower frame and a rack mounted on the tower frame; a monitoring camera is mounted on the rack; the tower frame comprises a lower sleeve and an upper sleeve fixedly mounted on the lower sleeve, a lifting device for controlling the lifting of the rack is installed in the upper sleeve, and support wheels are installed at the bottom of the lower sleeve.

[0010] The upper sleeve frame of the device of the present invention includes a supporting frame symmetrically installed on both sides of the top of the lower sleeve frame, a connecting frame installed between the rear sides of the two supporting frames, a movable door installed between the front sides of the two supporting frames, and a guide rod symmetrically installed in the middle of the front and rear sides of each supporting frame; the lifting device includes a top plate slidably sleeved on the guide rod, a hydraulic cylinder vertically fixedly installed between the bottom of the top plate and the bottom plate of the supporting frame, a compression spring sleeved on each guide rod and a clamping device, wherein the compression spring is arranged above the top plate; the piston rod end of the hydraulic cylinder is fixed to the bottom of the top plate; the clamping device includes an upper double-push-rod cylinder horizontally symmetrically installed on the two top plates, an upper arc-shaped claw installed on the cylinder rod of the upper double-push-rod cylinder, a lower double-push-rod cylinder horizontally symmetrically installed between the top of the lower sleeve frame and the bottom of the supporting frame, and a lower arc-shaped claw installed on the cylinder rod of the lower double-push-rod cylinder; the two upper arc-shaped claws are arranged correspondingly, and the two lower arc-shaped claws are arranged correspondingly.

[0011] The lower sleeve frame of the device of the present invention is in the shape of a cone, which includes a square inner frame, a square reinforcement frame fixedly installed on the outside of the square inner frame, and a triangular support frame obliquely fixedly installed on the outside of each frame of the square reinforcement frame, and the bottom angles of each triangular support frame are right angles; the top frame and the bottom frame of the square inner frame and the square reinforcement frame are connected by horizontal connecting rods, and rib rods are installed in the frame on each side of the square inner frame and in the frame on each side of the square reinforcement frame; reinforcement rods are installed between the outer ends of two adjacent triangular support frames, and the frame rods, frame rods, rib rods and reinforcement rods of the square inner frame on the side corresponding to the movable door are all removable; the middle part of the square inner frame is a square cavity matching the middle cavity of the upper sleeve frame, and a counterweight block is arranged at the bottom between the triangular support frames on both sides of the square reinforcement frame, and the bottom of the counterweight block is arranged on a number of horizontal oblique support rods, and the support wheel is located on the outer end of the bottom of the triangular support frame.

[0012] The rack of the device of the present invention includes a horizontal tube, a vertical tube and a right-angle bend installed between the corresponding ends of the horizontal tube and the vertical tube, and a rotating flange is installed at the bottom of the vertical tube; the rotating flange is provided with a plurality of connecting screw holes corresponding to the preset bolts on the base; the vertical tube is an assembled structure of more than two sections, and the structure at the two opposite ends is as follows: sleeves are arranged at intervals along the circumference on the outside, and bolts are inserted into the sleeves; the lower sleeve and the upper sleeve have the same height, and their heights are greater than the height of each section of the vertical tube; an inwardly concave wire groove is arranged on the outer side wall of the vertical tube, and an arc-shaped clamping plate matching the outer wall of the vertical tube is arranged on the outside of the wire groove.

[0013] The wire trough and the arc-shaped clamping plate of the device of the present invention are clamped together by means of a clamping hook; and a stiffening rib is fixedly installed on the side wall of the vertical bobbin.

[0014] A method for installing a camera according to the device of the present invention comprises the following steps:

[0015] Step 1: Pour a concrete cap on the roadside, set a base in the middle of the cap, the top surface of the base is flush with the road surface, and preset bolts on the base;

[0016] Assemble the horizontal tube, the right-angle bend and the vertical tube at the top. The vertical tube is assembled in multiple sections. Install the surveillance camera at the corresponding position of the horizontal tube. The signal line and power line connected to the surveillance camera pass through the horizontal tube and the inner cavity of the right-angle bend and enter the wire trough;

[0017] Step 2: temporarily fix the sleeve at the bottom of the vertical tube to the bolt on the base through a fixing nut, and the horizontal tube is located in a safe working area along the road outside the crosswalk;

[0018] Step 3: Open the movable door of the tower frame, dismantle the square inner frame rods, square reinforcing frame rods, rib rods and reinforcing rods on the side corresponding to the movable door, push the tower frame through the vertical bobbin to just above the base, so that the vertical bobbin is located inside the tower frame, adjust the support wheels to fix the tower frame and keep it in a horizontal state, close the movable door and install the rods removed from the lower sleeve, place several counterweights on the triangular support frames on both sides of the square reinforcing frame, and fix the tower frame;

[0019] Step 4: Start the lower double push rod cylinder and the upper double push rod cylinder at the same time, and extend the cylinder rods of the lower double push rod cylinder and the upper double push rod cylinder, so that the two corresponding upper arc-shaped claws and the two corresponding lower arc-shaped claws hold the vertical bobbin tightly, and then remove the bolts and nuts fixing the vertical bobbin and the base;

[0020] Step 5: Close the lower double push rod cylinder, the cylinder rod of the lower double push rod cylinder retracts, the two corresponding lower arc claws disengage from the vertical bobbin, and start the two hydraulic cylinders simultaneously. The piston rod of the hydraulic cylinder extends upward to lift the top plate upward so that the two upper arc claws drive the vertical bobbin to rise. At the same time, the compression spring is compressed upward. After the maximum stroke of the hydraulic cylinder piston rod is reached, the hydraulic cylinder stops, and the lower double push rod cylinder is started. The cylinder rod of the lower double push rod cylinder extends out to push the two corresponding lower arc claws to hold the vertical bobbin tightly. Close the upper double push rod cylinder, and the cylinder rod of the upper double push rod cylinder retracts. The two corresponding The upper arc-shaped claw is disengaged from the vertical barrel; the hydraulic cylinder is started again, the piston rod of the hydraulic cylinder is retracted, and at the same time, under the elastic force of the compression spring, the top plate drives the corresponding upper double-push rod cylinder to return to its original position; the working process of steps 4 and 5 is repeated, so that the vertical barrel is continuously lifted upward, wherein the stiffening rib fixedly installed on the side wall of the vertical barrel is helpful for the lifting of the hydraulic cylinder, and after the height of one section of the vertical barrel is lifted, the upper arc-shaped claw and the lower arc-shaped claw simultaneously hold the vertical barrel, and then another section of the vertical barrel is connected to the bottom of the original vertical barrel, and the two vertical barrels are fixed by sleeves and bolts;

[0021] Step 6: After the multi-section vertical bobbin is installed at the specified height, close the lower double push rod cylinder, retract the cylinder rod of the lower double push rod cylinder, and the two corresponding lower arc-shaped claws are separated from the vertical bobbin. Start the two hydraulic cylinders synchronously, and the piston rod of the hydraulic cylinder extends upward, lifting the top plate upward so that the two upper arc-shaped claws drive the vertical bobbin to rise. At the same time, the compression spring is compressed upward. When the height reaches 1.5 times that of the rotating flange, the hydraulic cylinder stops and starts the lower double push rod cylinder. The cylinder rod of the lower double push rod cylinder extends to push the two corresponding lower arc-shaped claws to hold the vertical bobbin tightly, and install the rotating flange at the bottom of the vertical bobbin. Adjust the screw holes of the rotating flange to correspond to the preset bolts on the base:

[0022] Subsequently, the lower double-push-rod cylinder is closed, the cylinder rod of the lower double-push-rod cylinder is retracted, and the two corresponding lower arc-shaped claws are disengaged from the vertical barrel, and the two hydraulic cylinders are started synchronously, and the piston rods of the hydraulic cylinders are retracted. At the same time, under the elastic force of the compression spring, the top plate drives the upper double-push-rod cylinder and the vertical barrel downward, so that the screw hole at the bottom of the rotating flange is inserted into the preset bolt on the base, and the nuts are installed and fixed, and the upper double-push-rod cylinder and the lower double-push-rod cylinder are closed, so that the cylinder rods of the upper double-push-rod cylinder and the lower double-push-rod cylinder are retracted, and the two corresponding upper arc-shaped claws and the two corresponding lower arc-shaped claws are disengaged from the vertical barrel, and the vertical barrel is rotated to rotate the horizontal barrel to the top of the road and perpendicular to the travel direction of the vehicle;

[0023] Step 7: Start the upper double push rod cylinder and the lower double push rod cylinder, and the cylinder rods of the upper double push rod cylinder and the lower double push rod cylinder extend out, so that the two corresponding upper arc claws and the two corresponding lower arc claws hold the vertical bobbin tightly, and then remove the nuts on the bottom of the rotating flange and the base bolts, and then close the lower double push rod cylinder, and the cylinder rod of the lower double push rod cylinder retracts, and the two corresponding lower arc claws disengage from the vertical bobbin, and start the two hydraulic cylinders synchronously, and the piston rods of the hydraulic cylinders extend upward to lift the top plate upward so that the two upper arc claws drive the vertical bobbin to rise, so that the screw holes at the bottom of the rotating flange are disengaged from the base bolts and then rise a distance greater than the bolt length. After that, the hydraulic cylinder stops, and then start the lower double push rod cylinder, and the lower double push rod The cylinder rod of the cylinder extends out to push the two corresponding lower arc-shaped claws to hold the vertical bobbin, and then the top of the rotating flange and the vertical bobbin are disassembled; the lower double-push-rod cylinder is closed to retract the cylinder rod, and the two corresponding lower arc-shaped claws are disengaged from the vertical bobbin, and the two hydraulic cylinders are started synchronously, and the piston rods of the hydraulic cylinders are retracted. At the same time, under the elastic force of the compression spring, the top plate drives the upper double-push-rod cylinder downward, so that the upper arc-shaped claws drive the vertical bobbin downward until its bottom contacts the top surface of the base, and at the same time, the lower double-push-rod cylinder is started, and the piston rod of the lower double-push-rod cylinder extends out to push the two corresponding lower arc-shaped claws to hold the vertical bobbin; the vertical bobbin is fixed to the base with preset bolts; the signal line is connected to the signal source, and the power line is connected to the power supply.

[0024] A method for repairing a camera according to the device of the present invention comprises the following steps:

[0025] Step 1: Open the movable door of the tower frame, dismantle the square inner frame rod, square reinforcement frame rod, rib rod and reinforcement rod on the side corresponding to the movable door, push the tower frame through the vertical bobbin to just above the base, so that the vertical bobbin is located inside the tower frame, adjust the support wheel to make the tower frame in a horizontal state, close the movable door and install the rods removed from the lower sleeve, place the counterweight blocks on the triangular support frames on both sides of the square reinforcement frame to fix the tower frame; remove the signal wires and power wires on the rods;

[0026] Step 2: Start the upper double push rod cylinder and the lower double push rod cylinder, extend the cylinder rods of the upper double push rod cylinder and the lower double push rod cylinder, so that the two corresponding upper arc-shaped claws and the two corresponding lower arc-shaped claws hold the vertical bobbin tightly, and then remove the bolts and nuts fixing the vertical bobbin and the base;

[0027] Step 3: Close the lower double-push-rod cylinder, the cylinder rod of the lower double-push-rod cylinder retracts, the two corresponding lower arc-shaped claws disengage from the vertical bobbin, and start the two hydraulic cylinders simultaneously. The piston rod of the hydraulic cylinder extends upward to lift the top plate upward so that the two upper arc-shaped claws drive the vertical bobbin to rise. At the same time, the compression spring is compressed upward. After the jacking reaches a height of 1.5 times that of the rotating flange, the hydraulic cylinder stops and starts the lower double-push-rod cylinder. The cylinder rod of the lower double-push-rod cylinder extends out to push the two corresponding lower arc-shaped claws to hold the vertical bobbin tightly; install the rotating flange at the bottom of the vertical bobbin, and adjust the screw holes at the bottom of the rotating flange to correspond to the preset bolts on the base: then close the lower double-push-rod cylinder, the cylinder rod of the lower double-push-rod cylinder retracts, the two corresponding lower arc-shaped claws disengage from the vertical bobbin, and start the two hydraulic cylinders simultaneously. The piston rod of the hydraulic cylinder retracts, and When the upper and lower cylinders are in operation, the upper and lower cylinders are in operation, and the upper and lower cylinders are in operation. When the upper and lower cylinders are in operation, the upper and lower cylinders are in operation, and the upper and lower cylinders are in operation. When the upper and lower cylinders are in operation, the upper and lower cylinders are in operation, and the upper and lower cylinders are in operation. When the upper and lower cylinders are in operation, the upper and lower cylinders are in operation, and the upper and lower cylinders are in operation. When the upper and lower cylinders are in operation, the upper and lower cylinders are in operation, and the upper and lower cylinders are in operation. When the upper and lower cylinders are in operation, the upper and lower cylinders are in operation, and the upper and lower cylinders are in operation.

[0028] Step 4: Start the upper double push rod cylinder and the lower double push rod cylinder, the cylinder rods of the upper double push rod cylinder and the lower double push rod cylinder extend, so that the two corresponding upper arc claws and the two corresponding lower arc claws hold the vertical bobbin tightly, and then remove the nuts on the bottom of the rotating flange and the base bolts, then close the lower double push rod cylinder, the cylinder rod of the lower double push rod cylinder retracts, and the two corresponding lower arc claws disengage from the vertical bobbin, and start the two hydraulic cylinders synchronously, the piston rods of the hydraulic cylinders extend upward to lift the top plate upward so that the two upper arc claws drive the vertical bobbin to rise, so that the screw holes at the bottom of the rotating flange are disengaged from the base bolts and then rise a distance greater than the length of the bolts, and then the hydraulic cylinders stop, and then start the lower double push rod cylinder, the cylinder rod of the lower double push rod cylinder extends out to push the two corresponding lower arc claws to hold the vertical bobbin tightly, and then the top of the rotating flange and the vertical bobbin are disassembled;

[0029] After removing the rotating flange, close the lower double push rod cylinder to retract the cylinder rod, and the two corresponding lower arc-shaped claws are separated from the vertical bobbin. The two hydraulic cylinders are started synchronously, and the piston rods of the hydraulic cylinders are retracted. At the same time, under the elastic force of the compression spring, the top plate drives the upper double push rod cylinder downward, so that the upper arc-shaped claw drives the vertical bobbin downward until its bottom contacts the top surface of the base. At the same time, start the lower double push rod cylinder, and the piston rod of the lower double push rod cylinder extends to push the two corresponding lower arc-shaped claws to hold the vertical bobbin tightly. Since the height of the lower sleeve is greater than the height of each section of the vertical bobbin, remove the vertical bobbin at the lowest end.

[0030] The upper double push rod cylinder is closed, the cylinder rod of the upper double push rod cylinder is retracted, and the two corresponding upper arc-shaped claws are separated from the vertical bobbin, and the two hydraulic cylinders are started synchronously. The piston rod of the hydraulic cylinder extends upward to lift the top plate upward to make the two upper arc-shaped claws rise, and the compression spring is compressed upward. After the hydraulic cylinder piston rod is lifted to the maximum stroke, the hydraulic cylinder stops, and the upper double push rod cylinder is started. The cylinder rod of the upper double push rod cylinder is extended, so that the two corresponding upper arc-shaped claws hold the vertical bobbin tightly, and the lower double push rod cylinder is closed. The piston rod of the lower double push rod cylinder is retracted, and the two corresponding lower arc-shaped claws are separated from the vertical bobbin. The two hydraulic cylinders are started synchronously, and the piston rod of the hydraulic cylinder is retracted. At the same time, under the elastic force of the compression spring, the top plate drives the upper double push rod cylinder and the vertical bobbin downward, and the piston rod of the hydraulic cylinder is retracted and stops; repeat the above operation process, so that the vertical bobbin continues to move downward, and it is removed after it drops to a vertical bobbin height;

[0031] Step 6: Repeat step 5 to lower the vertical tube to a height where it can be inspected, then fix the bottom of the vertical tube to the base and inspect the surveillance camera.

[0032] Compared with the prior art, the present invention has the following positive effects:

[0033] 1. The vertical bobbin of the present invention is a standard section, and two adjacent sections are connected by sleeves and bolts. When installing and repairing the monitoring camera, the vertical bobbin is lifted or lowered by the lifting device and the clamping device; it effectively avoids the operator from working at high altitude, reduces the risk of accidental injury, and enables the operator to complete related operations on the ground, thereby improving work efficiency.

[0034] 2. The present invention adopts a rotating flange rotating pole, so that the horizontal pole where the monitoring camera is located can be rotated in a horizontal plane; when the monitoring equipment needs to be replaced or repaired, the horizontal pole where the monitoring camera is located can be rotated from the center of the road to the side of a safe lane first, and then related operations can be performed, avoiding the setting of roadblocks, lane restrictions and other operations, and at the same time, allowing operators to have a safe working area.

[0035] 3. A detachable clamping plate is installed on the vertical frame rod of the present invention to form a wire threading trough, which can facilitate the construction workers to carry out the threading operation when installing the vertical bobbin, and can also prevent the internal wires from being damaged by rain, snow, impact from foreign objects, etc.

[0036] 4. The upper sleeve frame of the present invention is equipped with a lifting device and a clamping device. The reciprocating motion of the hydraulic cylinder of the lifting device and the arc-shaped claws of the clamping device can lift and lower the vertical bobbin and prevent the vertical bobbin from overturning. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for use in the embodiments are briefly introduced below. It should be understood that the following drawings only illustrate certain embodiments of the present invention and should not be regarded as limiting the scope of protection. For those skilled in the art, other relevant drawings can be obtained based on these drawings without creative work.

[0038] Attached Figure 1 It is a schematic diagram of the overall structure of the device of the present invention;

[0039] Attached Figure 2 It is a schematic diagram of the tower frame structure of the present invention;

[0040] Attached Figure 3 It is a schematic diagram of the supporting frame structure of the present invention;

[0041] Attached Figure 4 It is a schematic diagram of the structure of the lower sleeve frame of the present invention;

[0042] Attached Figure 5 It is a schematic diagram of the rack structure of the present invention;

[0043] Attached Figure 6 It is a schematic diagram of the vertical bobbin structure of the present invention;

[0044] Attached Figure 7 This is a schematic diagram of the cable duct structure of the present invention;

[0045] Attached Figure 8 This is a schematic diagram of the rotary flange structure of the present invention;

[0046] Attached Fig. 9 This is a schematic diagram of the structure of the upper and lower casing frames of the present invention being opened;

[0047] Attached Fig.10 This is a schematic diagram of the overall installation process structure of the surveillance camera of the present invention.

[0048] In the attached picture:

[0049] 1 tower frame,

[0050] 2 rack rods, 201 horizontal tubes, 202 vertical tubes, 203 right-angle bends, 204 rotating flanges, 205 sleeves, 206 bolts, 207 wire troughs, 208 cardboards, 209 stiffening ribs,

[0051] 3 surveillance cameras,

[0052] 4 lower sleeve frame, 401 square inner frame, 402 square reinforcement frame, 403 triangular support frame, 404 horizontal connecting rod, 405 rib rod, 406 counterweight, 407 reinforcement rod, horizontal oblique support rod 408,

[0053] 5 upper sleeve frame, 501 supporting frame, 502 connecting frame, 503 movable door, 504 guide rod, 505 top plate, 506 hydraulic cylinder, 507 compression spring, 508 upper double push rod cylinder, 509 upper arc claw, 510 lower double push rod cylinder, 511 lower arc claw,

[0054] 6 support wheels. DETAILED DESCRIPTION

[0055] As attached Figure 1 As shown, the tower-type installation, disassembly and maintenance monitoring camera device of the present invention comprises a tower frame 1 and a pole 2 mounted on the tower frame 1; a monitoring camera 3 is mounted on the pole 2; the tower frame 1 comprises a lower sleeve 4 and an upper sleeve 5 fixedly mounted on the lower sleeve 4, a lifting device for controlling the lifting of the pole 2 is installed in the upper sleeve 5, and a support wheel 6 is installed at the bottom of the lower sleeve 4. The support wheel 6 is a limited support caster, which can be both traveling and fixed. When the tower frame 1 is moved to a specified position, the entire tower frame 1 can be adjusted to a horizontal position on different road surfaces and then fixed, so as to facilitate the grabbing of the pole 2 during jacking.

[0056] As attached Figure 2 , 3As shown, the upper sleeve frame 5 of the present invention includes support frames 501 symmetrically installed on both sides of the top of the lower sleeve frame 4, a connecting frame 502 installed between the rear sides of the two support frames 501, a movable door 503 installed between the front sides of the two support frames 501, and a guide rod 504 symmetrically installed in the middle of the front and rear sides of each support frame 501; the lifting device includes a top plate 505 slidably sleeved on the guide rod 504, a hydraulic cylinder 506 vertically fixedly installed between the bottom of the top plate 505 and the bottom plate of the support frame 501, and a hydraulic cylinder 506 sleeved on each guide rod 504. 04 and a clamping device, the compression spring 507 is arranged above the top plate 505; the piston rod end of the hydraulic cylinder 506 is fixed to the bottom of the top plate 505; the clamping device includes an upper double-push rod cylinder 508 horizontally symmetrically installed on the two top plates 505, an upper arc-shaped claw 509 installed on the piston rod of the upper double-push rod cylinder 508, a lower double-push rod cylinder 510 horizontally symmetrically installed between the top of the lower sleeve 4 and the bottom of the support frame 501, and a lower arc-shaped claw 511 installed on the piston rod of the lower double-push rod cylinder 510; the two upper arc-shaped claws 509 are arranged correspondingly, and the two lower arc-shaped claws 511 are arranged correspondingly. The control switches of the hydraulic cylinder 506 of the lifting device and the double-push rod cylinder of the clamping device are installed on the upper sleeve 5 for easy control.

[0057] As attached Figure 4 As shown, the lower sleeve frame 4 of the present invention is in the shape of a cone, which includes a square inner frame 401, a square reinforcement frame 402 fixedly installed on the outside of the square inner frame 401, and a triangular support frame 403 fixedly installed on the outside of each frame of the square reinforcement frame 402 at an angle, and the bottom angles of each triangular support frame 403 are right angles; the top frames and bottom frames of the square inner frame 401 and the square reinforcement frame 402 are connected by horizontal connecting rods 404, and rib rods 405 are installed in the frames on each side of the square inner frame 401 and in the frames on each side of the square reinforcement frame 402; reinforcing rods 407 are installed between the outer ends of two adjacent triangular support frames 403, and the frame rods of the square inner frame 401 and the square reinforcement frame 402 on the side corresponding to the movable door 503 are connected. The frame rod 402, the rib rod 405 and the reinforcing rod 407 are all removable; the middle part of the square inner frame 401 is a square cavity that matches the middle cavity of the upper sleeve frame 5, and a counterweight block 406 is arranged at the bottom between the triangular support frames 403 on both sides of the square reinforcing frame 402, and the bottom of the counterweight block 406 is arranged on a plurality of horizontal oblique support rods 408 to facilitate the placement of the counterweight block 406, one end of the oblique support rod 408 is fixed to the inner side of the reinforcing rod 407, and the other end of the oblique support rod 408 is fixed to the corresponding bottom end of the square reinforcing frame 402; the support wheel 6 is located on the outer end of the bottom of the triangular support frame 403; the counterweight block 406 prevents the frame rod 2 from overturning as a whole during operations such as lifting, lowering, and rotating, thereby causing personal injury.

[0058] As attached Figure 5 , 8As shown, the rack 2 of the present invention includes a horizontal tube 201, a vertical tube 202 and a right-angle bend 203 installed between the corresponding ends of the horizontal tube 201 and the vertical tube 202, and a rotating flange 204 is installed at the bottom of the vertical tube 202; the rotating flange 204 facilitates the rotation of the monitoring camera 3 on the horizontal tube 201 from the construction safety operation area to the specified position, and a plurality of connecting screw holes are opened on the rotating flange 204 to facilitate the bolt connection between the vertical tube 202 and the rotating flange 204.

[0059] As attached Figure 5 , 6 As shown in Figures 7 and 10, the vertical bobbin 202 of the present invention is an assembled structure of more than two sections, at the two opposite ends: sleeves 205 are arranged at intervals along the circumference of the outer side, and bolts 206 are inserted into the sleeves 205; the lower sleeve frame 4 and the upper sleeve frame 5 have the same height, which is greater than the height of each section of the vertical bobbin 202, so as to facilitate the disassembly and assembly of the bottom section of the vertical bobbin 202 in the lower sleeve frame 4; an inwardly concave wire groove 207 is arranged on the outer side wall of the vertical bobbin 202, and an arc-shaped clamping plate 208 matching the outer wall of the vertical bobbin 202 is arranged on the outer side of the wire groove 207. The wire groove 207 and the arc-shaped clamping plate 208 are clamped by a hook; a stiffening rib 209 is fixedly installed on the side wall of the vertical bobbin 202, and the stiffening rib 209 helps the lifting of the hydraulic cylinder 506.

[0060] As attached Figure 6 , 7 As shown, the vertical bobbin 202 of the present invention is a standard section, and two adjacent sections are connected by a sleeve 205 and a bolt 206. When installing and repairing the surveillance camera, the vertical bobbin 202 is lifted or lowered by a lifting device and a clamping device; it effectively avoids the operator from working at high altitude, reduces the risk of accidental injury, and enables the operator to complete related operations on the ground, thereby improving work efficiency. The detachable clamping plate 208 on the vertical bobbin 202 can facilitate the construction personnel to perform threading operations when installing the vertical bobbin 202.

[0061] As attached Figure 1-10 As shown, the present invention provides a method for installing a camera according to a tower type installation and maintenance device, which adopts the following steps:

[0062] Step 1: Pour a concrete cap on the roadside, set a base in the middle of the cap, the top surface of the base is flush with the road surface, and preset bolts on the base;

[0063] Assemble the horizontal tube 201, the right-angle bend 203 and the vertical tube 202 at the top, assemble the vertical tube 202 in multiple sections, install the monitoring camera 3 at the corresponding position of the horizontal tube 201, and insert the signal line and power line connected to the monitoring camera 3 into the wire groove 207 through the inner cavity of the horizontal tube 201 and the right-angle bend 203;

[0064] Step 2: temporarily fix the sleeve 205 at the bottom of the vertical tube 202 to the bolts on the base through fixing nuts, and the horizontal tube 201 is located in the safe working area along the road outside the crosswalk;

[0065] Step 3: Open the movable door 503 of the tower frame 1, dismantle the square inner frame 401 frame rods, the square reinforcing frame 402 frame rods, the rib rods 405 and the reinforcing rods 407 on the side corresponding to the movable door 503, push the tower frame 1 through the vertical bobbin 202 to just above the base, so that the vertical bobbin 202 is located in the tower frame 1, adjust the support wheel 6 to fix the tower frame 1 and keep it in a horizontal state, close the movable door 503 and install the rods removed from the lower sleeve 4, place the counterweights 406 on the triangular support frames 403 on both sides of the square reinforcing frame 402, and fix the tower frame 1;

[0066] Step 4: Start the lower double push rod cylinder 510 and the upper double push rod cylinder 508 at the same time, and the cylinder rods of the lower double push rod cylinder 510 and the upper double push rod cylinder 508 are extended, so that the two corresponding upper arc-shaped claws 509 and the two corresponding lower arc-shaped claws 511 hold the vertical bobbin 202 tightly, and then remove the bolts and nuts fixing the vertical bobbin 202 to the base;

[0067] Step 5: Close the lower double push rod cylinder 510, the cylinder rod of the lower double push rod cylinder 510 retracts, the two corresponding lower arc-shaped claws 511 disengage from the vertical barrel 202, and synchronously start the two hydraulic cylinders 506. The piston rod of the hydraulic cylinder 506 extends upward to lift the top plate 505 upward so that the two upper arc-shaped claws 509 drive the vertical barrel 202 to rise. At the same time, the compression spring 507 is compressed upward. After the maximum stroke of the piston rod of the hydraulic cylinder 506 is reached, the hydraulic cylinder 506 stops, and the lower double push rod cylinder 510 is started. The cylinder rod of the lower double push rod cylinder 510 extends out to push the two corresponding lower arc-shaped claws 511 to hold the vertical barrel 202 tightly. Close the upper double push rod cylinder 508, the cylinder rod of the upper double push rod cylinder 508 retracts, and the two corresponding upper arc-shaped claws 511 are disengaged from the vertical barrel 202. The clamping claw 509 disengages from the vertical tube 202; the hydraulic cylinder 506 is started again, and the piston rod of the hydraulic cylinder 506 is retracted. At the same time, under the elastic force of the compression spring 507, the top plate 505 drives the corresponding upper double push rod cylinder 508 to return to its original position; the working process of steps 4 and 5 is repeated, so that the vertical tube 202 is continuously lifted upward, wherein the stiffening rib 209 fixedly installed on the side wall of the vertical tube 202 facilitates the lifting of the hydraulic cylinder 506. After the height of one section of the vertical tube 202 is lifted, the upper arc clamping claw 509 and the lower arc clamping claw 511 simultaneously hold the vertical tube 202, and then another section of the vertical tube 202 is connected to the bottom of the original vertical tube 202, and the two vertical tubes 202 are fixed by the sleeve 205 and the bolt 206;

[0068] Step 6: After the multi-section vertical bobbin 202 is installed at the specified height, the lower double push rod cylinder 510 is closed, the cylinder rod of the lower double push rod cylinder 510 is retracted, and the two corresponding lower arc-shaped claws 511 are separated from the vertical bobbin 202, and the two hydraulic cylinders 506 are started synchronously. The piston rods of the hydraulic cylinders 506 extend upward, and the top plate 505 is lifted upward to make the two upper arc-shaped claws 509 drive the vertical bobbin 202 to rise. At the same time, the compression spring 507 is compressed upward. After reaching 1.5 times the height of the rotating flange 204, the hydraulic cylinder 506 stops, and the lower double push rod cylinder 510 is started. The cylinder rod of the lower double push rod cylinder 510 extends out to push the two corresponding lower arc-shaped claws 511 to hold the vertical bobbin 202 tightly, and the rotating flange 204 is installed at the bottom of the vertical bobbin 202. The screw holes of the rotating flange 204 are adjusted to correspond to the preset bolts on the base:

[0069] Subsequently, the lower double push rod cylinder 510 is closed, the cylinder rod of the lower double push rod cylinder 510 is retracted, and the two corresponding lower arc-shaped claws 511 are disengaged from the vertical barrel 202, and the two hydraulic cylinders 506 are started synchronously, and the piston rods of the hydraulic cylinders 506 are retracted. At the same time, under the elastic force of the compression spring 507, the top plate 505 drives the upper double push rod cylinder 508 and the vertical barrel 202 to move downward, so that the screw hole at the bottom of the rotating flange 204 is inserted into the bolt preset on the base, and the nuts are installed and fixed, and the upper double push rod cylinder 508 and the lower double push rod cylinder 510 are closed, so that the cylinder rods of the upper double push rod cylinder 508 and the lower double push rod cylinder 510 are retracted, so that the two corresponding upper arc-shaped claws 509 and the two corresponding lower arc-shaped claws 511 are disengaged from the vertical barrel 202, and the vertical barrel 202 is rotated to rotate the horizontal barrel 201 to the top of the road and perpendicular to the direction of travel of the vehicle;

[0070] 202, and the bottom screw thread 504 is lifted and the bottom screw thread 504 is lifted. The cylinder rod of the cylinder 510 extends out to push the two corresponding lower arc-shaped claws 511 to hold the vertical bobbin 202 tightly, and then the top of the rotating flange 204 is disassembled from the vertical bobbin 202; the lower double-push-rod cylinder 510 is closed to retract the cylinder rod, and the two corresponding lower arc-shaped claws 511 are disengaged from the vertical bobbin 202, and the two hydraulic cylinders 506 are started synchronously, and the piston rods of the hydraulic cylinders 506 are retracted. At the same time, under the elastic force of the compression spring 507, the top plate 505 drives the upper double-push-rod cylinder 508 downward, so that the upper arc-shaped claws 509 drive the vertical bobbin 202 downward until its bottom contacts the top surface of the base, and at the same time, the lower double-push-rod cylinder 510 is started, and the piston rod of the lower double-push-rod cylinder 510 extends out to push the two corresponding lower arc-shaped claws 511 to hold the vertical bobbin 202 tightly; the vertical bobbin 202 is fixed to the preset bolts of the base; the signal line is connected to the signal source, and the power line is connected to the power supply.

[0071] As attached Figure 1-10 As shown, the present invention provides a method for repairing a camera according to a tower-type installation and repair device, which is characterized by adopting the following steps:

[0072] Step 1: Open the movable door 503 of the tower frame 1, dismantle the square inner frame 401 frame rod, the square reinforcement frame 402 frame rod, the rib rod 405 and the reinforcement rod 407 on the side corresponding to the movable door 503, push the tower frame 1 through the vertical bobbin 202 to just above the base, so that the vertical bobbin 202 is located in the tower frame 1, adjust the support wheel 6 to make the tower frame 1 in a horizontal state, close the movable door 503 and install the rods removed from the lower sleeve 4, place the counterweight 406 on the triangular support frames 403 on both sides of the square reinforcement frame 402, and fix the tower frame 1; remove the signal line and power line on the frame rod 2;

[0073] Step 2: Start the upper double push rod cylinder 508 and the lower double push rod cylinder 510, and extend the cylinder rods of the upper double push rod cylinder 508 and the lower double push rod cylinder 510, so that the two corresponding upper arc-shaped claws 509 and the two corresponding lower arc-shaped claws 511 hold the vertical bobbin 202 tightly, and then remove the bolts and nuts fixing the vertical bobbin 202 to the base;

[0074] Step 3: Close the lower double push rod cylinder 510, retract the cylinder rod of the lower double push rod cylinder 510, and the two corresponding lower arc-shaped claws 511 are separated from the vertical tube 202. The two hydraulic cylinders 506 are started synchronously. The piston rods of the hydraulic cylinders 506 extend upward to lift the top plate 505 upward so that the two upper arc-shaped claws 509 drive the vertical tube 202 to rise. At the same time, the compression spring 507 is compressed upward. After the hydraulic cylinder 506 is lifted to a height 1.5 times that of the rotating flange 204, it stops and the lower double push rod cylinder 510 is started. , the cylinder rod of the lower double push rod cylinder 510 extends out to push the two corresponding lower arc-shaped claws 511 to hold the vertical barrel 202 tightly; the rotating flange 204 is installed at the bottom of the vertical barrel 202, and the screw holes at the bottom of the rotating flange 204 are adjusted to correspond to the preset bolts on the base: then the lower double push rod cylinder 510 is closed, the cylinder rod of the lower double push rod cylinder 510 is retracted, and the two corresponding lower arc-shaped claws 511 are separated from the vertical barrel 202, and the two hydraulic cylinders 506 are started synchronously, and the piston rods of the hydraulic cylinders 506 are retracted, and at the same time At this time, under the elastic force of the compression spring 507, the top plate 505 drives the upper double push rod cylinder 508 and the vertical barrel 202 downward, so that the screw hole at the bottom of the rotating flange 204 is inserted into the preset bolt on the base, and then the lower double push rod cylinder 510 is started, and the cylinder rod of the lower double push rod cylinder 510 extends out to push the two corresponding lower arc-shaped claws 511 to hold the vertical barrel 202, and then the nut is installed to fix the rotating flange 204; after the installation is completed, the upper double push rod cylinder 508 and the lower double push rod cylinder 510 are closed, The cylinder rods of the upper double push rod cylinder 508 and the lower double push rod cylinder 510 are retracted, and the two corresponding upper arc claws 509 and the two corresponding lower arc claws 511 are disengaged from the vertical tube 202. At the same time, the hydraulic cylinder 506 is started, and the piston rod of the hydraulic cylinder 506 is retracted. Under the elastic force of the compression spring 507, the top plate 505 drives the corresponding upper arc claws 509 to return to their original positions; the vertical tube 202 is rotated to rotate the horizontal tube 201 to the construction safety operation area along the road on one side of the pedestrian crossing;

[0075] Step 4: Start the upper double push rod cylinder 508 and the lower double push rod cylinder 510, and the cylinder rods of the upper double push rod cylinder 508 and the lower double push rod cylinder 510 are extended, so that the two corresponding upper arc claws 509 and the two corresponding lower arc claws 511 hold the vertical bobbin 202 tightly, and then remove the nuts on the bottom of the rotating flange 204 and the base bolts, and then close the lower double push rod cylinder 510, and the cylinder rod of the lower double push rod cylinder 510 is retracted, and the two corresponding lower arc claws 511 are separated from the vertical bobbin 202, and the two are started synchronously. The hydraulic cylinder 506, the piston rod of the hydraulic cylinder 506 extends upward, lifts the top plate 505 upward so that the two upper arc-shaped claws 509 drive the vertical tube 202 to rise, so that the bottom screw hole of the rotating flange 204 is separated from the base bolt and then rises a distance greater than the length of the bolt. After that, the hydraulic cylinder 506 stops, and then the lower double-push-rod cylinder 510 is started. The cylinder rod of the lower double-push-rod cylinder 510 extends out to push the two corresponding lower arc-shaped claws 511 to hold the vertical tube 202 tightly, and then the top of the rotating flange 204 and the vertical tube 202 are disassembled;

[0076] After removing the rotating flange 204, the lower double push rod cylinder 510 is closed to retract the cylinder rod, and the two corresponding lower arc-shaped claws 511 are separated from the vertical bobbin 202, and the two hydraulic cylinders 506 are started synchronously, and the piston rods of the hydraulic cylinders 506 are retracted. At the same time, under the elastic force of the compression spring 507, the top plate 505 drives the upper double push rod cylinder 508 downward, so that the upper arc-shaped claws 509 drive the vertical bobbin 202 downward until its bottom contacts the top surface of the base, and at the same time, the lower double push rod cylinder 510 is started, and the piston rod of the lower double push rod cylinder 510 extends to push the two corresponding lower arc-shaped claws 511 to hold the vertical bobbin 202 tightly; since the height of the lower sleeve 4 is greater than the height of each section of the vertical bobbin 202, the vertical bobbin 202 at the lowest end can be removed;

[0077] Step 5: Close the upper double push rod cylinder 508, the cylinder rod of the upper double push rod cylinder 508 retracts, and the two corresponding upper arc-shaped claws 509 are separated from the vertical barrel 202, and the two hydraulic cylinders 506 are started synchronously. The piston rod of the hydraulic cylinder 506 extends upward to lift the top plate 505 upward to make the two upper arc-shaped claws 509 rise, and at the same time, the compression spring 507 is compressed upward. After the hydraulic cylinder 506 piston rod reaches the maximum stroke, the hydraulic cylinder 506 stops, and the upper double push rod cylinder 508 is started. The cylinder rod of the upper double push rod cylinder 508 extends, so that the two corresponding upper arc-shaped claws 509 are tightly clamped. The vertical barrel 202 is closed, the lower double push rod cylinder 510 is closed, the piston rod of the lower double push rod cylinder 510 is retracted, and the two corresponding lower arc-shaped claws 511 are separated from the vertical barrel 202, and the two hydraulic cylinders 506 are started synchronously, and the piston rods of the hydraulic cylinders 506 are retracted. At the same time, under the elastic force of the compression spring 507, the top plate 505 drives the upper double push rod cylinder 508 and the vertical barrel 202 downward, and the piston rod of the hydraulic cylinder 506 is retracted to the position and then stops; repeat the above operation process, so that the vertical barrel 202 is continuously moved downward, and it is removed after it descends to a height of the vertical barrel 202;

[0078] Step 6: Repeat the operation of step 5, lower the vertical tube 202 to a height where it can be inspected, fix the bottom of the vertical tube 202 to the base, and inspect the monitoring camera 3.

[0079] The present invention adopts a rotating flange 204 to rotate the frame rod, so that the horizontal tube 201 where the monitoring camera 3 is located can be rotated in a horizontal plane; when the monitoring camera 3 needs to be replaced or repaired, the horizontal tube 201 where the monitoring camera 3 is located can be preferentially rotated from the center of the road to the safe side of the pedestrian crossing, and then related operations are performed, avoiding the setting of roadblocks, lane restrictions and other operations, and at the same time, allowing operators to have a safe working area; a lifting device and a clamping device are installed on the upper sleeve 5, and the reciprocating motion of the hydraulic cylinder 506 of the lifting device and the arc-shaped claws of the clamping device can make the vertical tube 202 rise and fall, and at the same time prevent the vertical tube 202 from overturning.

[0080] Although the embodiments of the present invention have been described in detail by way of examples, it should be understood by those skilled in the art that the above examples are for illustration only and are not intended to limit the scope of the present invention. It is not necessary and impossible to list all embodiments exhaustively here. It should be understood by those skilled in the art that the above embodiments may be modified without departing from the scope and spirit of the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention shall be included in the scope of protection of the claims of the present invention; the scope of the present invention is defined by the appended claims.

Claims

1. A method for installing a camera in a tower type surveillance camera installation and maintenance device, characterized in that: The tower-type installation, disassembly and maintenance monitoring camera device comprises a tower frame (1) and a rack (2) mounted on the tower frame (1); a monitoring camera (3) is mounted on the rack (2); The tower frame (1) comprises a lower sleeve frame (4) and an upper sleeve frame (5) fixedly mounted on the lower sleeve frame (4); a lifting device for controlling the lifting of the frame rod (2) is mounted in the upper sleeve frame (5); and a support wheel (6) is mounted at the bottom of the lower sleeve frame (4); The upper sleeve frame (5) comprises support frames (501) symmetrically mounted on both sides of the top of the lower sleeve frame (4), a connecting frame (502) mounted between the rear sides of the two support frames (501), a movable door (503) mounted between the front sides of the two support frames (501), and a guide rod (504) symmetrically mounted in the middle of the front and rear sides of each support frame (501); The lifting device comprises a top plate (505) slidably mounted on the guide rod (504), a hydraulic cylinder (506) vertically fixedly mounted between the bottom of the top plate (505) and the bottom plate of the support frame (501), a compression spring (507) mounted on each guide rod (504), and a clamping device, wherein the compression spring (507) is arranged above the top plate (504); the piston rod end of the hydraulic cylinder (506) is fixed to the bottom of the top plate (505); The clamping device comprises an upper double push rod cylinder (508) horizontally symmetrically mounted on two top plates (505), an upper arc-shaped claw (509) mounted on the cylinder rod of the upper double push rod cylinder (508), a lower double push rod cylinder (510) horizontally symmetrically mounted between the top of the lower sleeve frame (4) and the bottom of the support frame (501), and a lower arc-shaped claw (511) mounted on the cylinder rod of the lower double push rod cylinder (510); the two upper arc-shaped claws (509) are arranged correspondingly, and the two lower arc-shaped claws (511) are arranged correspondingly; The lower sleeve frame (4) is in the shape of a cone, comprising a square inner frame (401), a square reinforcement frame (402) fixedly mounted on the outside of the square inner frame (401), and a triangular support frame (403) fixedly mounted obliquely on the outside of each frame of the square reinforcement frame (402), wherein the bottom angle of each triangular support frame (403) is a right angle; The top frames and bottom frames of the square inner frame (401) and the square reinforcing frame (402) are connected by horizontal connecting rods (404); reinforcing rods (405) are installed in each side frame of the square inner frame (401) and each side frame of the square reinforcing frame (402); reinforcing rods (407) are installed between the outer ends of two adjacent triangular support frames (403); the frame rods of the square inner frame (401), the frame rods of the square reinforcing frame (402), the reinforcing rods (405) and the reinforcing rods (407) on the side corresponding to the movable door (503) are all detachable; The middle part of the square inner frame (401) is a square cavity matching the middle cavity of the upper sleeve frame (5); a counterweight block (406) is arranged at the bottom between the triangular support frames (403) on both sides of the square reinforcement frame (402); the bottom of the counterweight block (406) is arranged on a plurality of horizontal oblique support rods (408); and the support wheel (6) is located on the outer end of the bottom of the triangular support frame (403); The rack rod (2) comprises a horizontal tube (201), a vertical tube (202), and a right-angle bend (203) installed between corresponding ends of the horizontal tube (201) and the vertical tube (202); a rotating flange (204) is installed at the bottom of the vertical tube (202); the rotating flange (204) is provided with a plurality of connection screw holes corresponding to the bolts preset on the base; The vertical tube (202) is an assembled structure of more than two sections, and the structure at the two opposite ends is as follows: sleeves (205) are arranged at intervals along the circumference of the outer side, and bolts (206) are inserted into the sleeves (205); the lower sleeve frame (4) and the upper sleeve frame (5) have the same height, and the height thereof is greater than the height of each section of the vertical tube (202); An inwardly concave wire groove (207) is provided on the outer side wall of the vertical bobbin (202), and an arc-shaped clamping plate (208) matching the outer side wall of the vertical bobbin (202) is provided on the outer side of the wire groove (207); The wire trough (207) and the arc-shaped clamping plate (208) are clamped together by means of a clamping hook; A stiffening rib (209) is fixedly installed on the side wall of the vertical tube (202); The method of installing the camera uses the following steps: Step 1: Pour a concrete cap on the roadside, set a base in the middle of the cap, the top surface of the base is flush with the road surface, and preset bolts on the base; Assemble the horizontal tube (201), the right-angle bend (203) and the vertical tube (202) at the top, wherein the vertical tube (202) is assembled in multiple sections, install the monitoring camera (3) at the corresponding position of the horizontal tube (201), and pass the signal line and power line connected to the monitoring camera (3) through the inner cavity of the horizontal tube (201) and the right-angle bend (203) into the wire groove (207); Step 2: temporarily fix the sleeve (205) at the bottom of the vertical tube (202) to the bolts on the base through fixing nuts, and the horizontal tube (201) is located in a safe working area along the road outside the pedestrian crossing; Step 3: Open the movable door (503) of the tower frame (1), remove the square inner frame (401) frame rod, the square reinforcement frame (402) frame rod, the rib rod (405) and the reinforcement rod (407) on the side corresponding to the movable door (503), push the tower frame (1) through the vertical tube (202) to the top of the base, so that the vertical tube (202) is located in the tower frame (1), adjust the support wheel (6) to fix the tower frame (1) and keep it in a horizontal state, close the movable door (503) and install the removed rods of the lower sleeve frame (4), place a plurality of counterweights (406) on the triangular support frames (403) on both sides of the square reinforcement frame (402), and fix the tower frame (1); Step 4: Start the lower double push rod cylinder (510) and the upper double push rod cylinder (508) at the same time, and extend the cylinder rods of the lower double push rod cylinder (510) and the upper double push rod cylinder (508) so that the two corresponding upper arc-shaped claws (509) and the two corresponding lower arc-shaped claws (511) hold the vertical tube (202), and then remove the bolts and nuts fixing the vertical tube (202) to the base; Step 5: Close the lower double push rod cylinder (510), the cylinder rod of the lower double push rod cylinder (510) retracts, and the two corresponding lower arc-shaped claws (511) are separated from the vertical tube (202), and the two hydraulic cylinders (506) are started synchronously. The piston rods of the hydraulic cylinders (506) extend upward to lift the top plate (505) upward so that the two upper arc-shaped claws (509) drive the vertical tube (202) to rise. At the same time, the compression spring (507) is compressed upward. After the maximum stroke of the piston rod of the hydraulic cylinder (506) is reached, the hydraulic cylinder (506) stops, and the lower double push rod cylinder (510) is started. The cylinder rod of the lower double push rod cylinder (510) extends to push the two corresponding lower arc-shaped claws (511) to hold the vertical tube (202), and the upper double push rod cylinder (508) is closed. The cylinder rod of the upper double push rod cylinder (508) retracts, and the two corresponding upper arc-shaped claws (509) is separated from the vertical barrel (202); the hydraulic cylinder (506) is started again, the piston rod of the hydraulic cylinder (506) is retracted, and at the same time, under the elastic force of the compression spring (507), the top plate (505) drives the corresponding upper double push rod cylinder (508) to return to its original position; the working process of steps 4 and 5 is repeated, so that the vertical barrel (202) is continuously lifted upward, wherein the stiffening rib (209) fixedly installed on the side wall of the vertical barrel (202) helps the lifting of the hydraulic cylinder (506), and after the height of one section of the vertical barrel (202) is lifted, the upper arc-shaped claw (509) and the lower arc-shaped claw (511) simultaneously hold the vertical barrel (202), and then another section of the vertical barrel (202) is connected to the bottom of the original vertical barrel (202), and the two vertical barrels (202) are fixed by the sleeve (205) and the bolt (206); Step 6: After the multi-section vertical tube (202) is installed at the specified height, the lower double push rod cylinder (510) is closed, the cylinder rod of the lower double push rod cylinder (510) is retracted, and the two corresponding lower arc-shaped claws (511) are separated from the vertical tube (202), and the two hydraulic cylinders (506) are started synchronously. The piston rods of the hydraulic cylinders (506) extend upward, and the top plate (505) is lifted upward so that the two upper arc-shaped claws (509) drive the vertical tube (202) to rise. At the same time, the compression spring (507) is compressed upwards, and when the height reaches 1.5 times of the rotating flange (204), the hydraulic cylinder (506) stops, and the lower double push rod cylinder (510) is started. The cylinder rod of the lower double push rod cylinder (510) extends and pushes two corresponding lower arc-shaped claws (511) to hold the vertical tube (202). The rotating flange (204) is installed at the bottom of the vertical tube (202), and the screw holes of the rotating flange (204) are adjusted to correspond to the preset bolts on the base: After that, the lower double push rod cylinder (510) is closed, the cylinder rod of the lower double push rod cylinder (510) is retracted, and the two corresponding lower arc-shaped claws (511) are separated from the vertical barrel (202), and the two hydraulic cylinders (506) are started synchronously, and the piston rods of the hydraulic cylinders (506) are retracted. At the same time, under the elastic force of the compression spring (507), the top plate (505) drives the upper double push rod cylinder (508) and the vertical barrel (202) downward, so that the bottom screw hole of the rotating flange (204) is opened. Insert the bolts preset on the base, install the nuts to fix, close the upper double push rod cylinder (508) and the lower double push rod cylinder (510), retract the cylinder rods of the upper double push rod cylinder (508) and the lower double push rod cylinder (510), disengage the two corresponding upper arc-shaped claws (509) and the two corresponding lower arc-shaped claws (511) from the vertical tube (202), rotate the vertical tube (202) to rotate the horizontal tube (201) above the road and perpendicular to the direction of travel of the vehicle; Step 7: Start the upper double push rod cylinder (508) and the lower double push rod cylinder (510), and the cylinder rods of the upper double push rod cylinder (508) and the lower double push rod cylinder (510) are extended, so that the two corresponding upper arc-shaped claws (509) and the two corresponding lower arc-shaped claws (511) hold the vertical barrel (202), and then remove the nuts on the bottom of the rotating flange (204) and the base bolts, and then close the lower double push rod cylinder (510), and the cylinder rod of the lower double push rod cylinder (510) is retracted. , the two corresponding lower arc-shaped claws (511) are separated from the vertical barrel (202), and the two hydraulic cylinders (506) are started synchronously. The piston rods of the hydraulic cylinders (506) extend upward to lift the top plate (505) upward, so that the two upper arc-shaped claws (509) drive the vertical barrel (202) to rise, so that the bottom screw hole of the rotating flange (204) is separated from the base bolt and then rises a distance greater than the length of the bolt. After that, the hydraulic cylinder (506) stops, and then the lower double push rod cylinder (510) is started, and the lower double push rod The cylinder rod of the cylinder (510) extends to push the two corresponding lower arc-shaped claws (511) to hold the vertical barrel (202), and then the top of the rotating flange (204) is disassembled from the vertical barrel (202); the lower double-push-rod cylinder (510) is closed to retract the cylinder rod, and the two corresponding lower arc-shaped claws (511) are separated from the vertical barrel (202), and the two hydraulic cylinders (506) are started synchronously, and the piston rods of the hydraulic cylinders (506) are retracted. At the same time, under the elastic force of the compression spring (507), the vertical barrel (202) is disassembled. The top plate (505) drives the upper double push rod cylinder (508) downward, so that the upper arc-shaped claw (509) drives the vertical tube (202) downward until its bottom contacts the top surface of the base. At the same time, the lower double push rod cylinder (510) is started, and the piston rod of the lower double push rod cylinder (510) extends to push two corresponding lower arc-shaped claws (511) to hold the vertical tube (202); the vertical tube (202) is fixed to the base with bolts preset; the signal line is connected to the signal source, and the power line is connected to the power supply.

2. A method for repairing a camera in a tower-type installation and repair monitoring camera device, characterized in that: The tower-type installation, disassembly and maintenance monitoring camera device comprises a tower frame (1) and a rack (2) mounted on the tower frame (1); a monitoring camera (3) is mounted on the rack (2); The tower frame (1) comprises a lower sleeve frame (4) and an upper sleeve frame (5) fixedly mounted on the lower sleeve frame (4); a lifting device for controlling the lifting of the frame rod (2) is mounted in the upper sleeve frame (5); and a support wheel (6) is mounted at the bottom of the lower sleeve frame (4); The upper sleeve frame (5) comprises support frames (501) symmetrically mounted on both sides of the top of the lower sleeve frame (4), a connecting frame (502) mounted between the rear sides of the two support frames (501), a movable door (503) mounted between the front sides of the two support frames (501), and a guide rod (504) symmetrically mounted in the middle of the front and rear sides of each support frame (501); The lifting device comprises a top plate (505) slidably mounted on the guide rod (504), a hydraulic cylinder (506) vertically fixedly mounted between the bottom of the top plate (505) and the bottom plate of the support frame (501), a compression spring (507) mounted on each guide rod (504), and a clamping device, wherein the compression spring (507) is arranged above the top plate (504); the piston rod end of the hydraulic cylinder (506) is fixed to the bottom of the top plate (505); The clamping device comprises an upper double push rod cylinder (508) horizontally symmetrically mounted on two top plates (505), an upper arc-shaped claw (509) mounted on the cylinder rod of the upper double push rod cylinder (508), a lower double push rod cylinder (510) horizontally symmetrically mounted between the top of the lower sleeve frame (4) and the bottom of the support frame (501), and a lower arc-shaped claw (511) mounted on the cylinder rod of the lower double push rod cylinder (510); the two upper arc-shaped claws (509) are arranged correspondingly, and the two lower arc-shaped claws (511) are arranged correspondingly; The lower sleeve frame (4) is in the shape of a cone, comprising a square inner frame (401), a square reinforcement frame (402) fixedly mounted on the outside of the square inner frame (401), and a triangular support frame (403) fixedly mounted obliquely on the outside of each frame of the square reinforcement frame (402), wherein the bottom angle of each triangular support frame (403) is a right angle; The top frames and bottom frames of the square inner frame (401) and the square reinforcement frame (402) are connected via horizontal connecting rods (404); reinforcing rods (405) are installed in each side frame of the square inner frame (401) and each side frame of the square reinforcement frame (402); and reinforcement rods (407) are installed between the outer ends of two adjacent triangular support frames (403). The frame rods of the square inner frame (401), the frame rods of the square reinforcement frame (402), the rib rods (405) and the reinforcement rods (407) on the side corresponding to the movable door (503) are all detachable; The middle part of the square inner frame (401) is a square cavity matching the middle cavity of the upper sleeve frame (5); a counterweight block (406) is arranged at the bottom between the triangular support frames (403) on both sides of the square reinforcement frame (402); the bottom of the counterweight block (406) is arranged on a plurality of horizontal oblique support rods (408); and the support wheel (6) is located on the outer end of the bottom of the triangular support frame (403); The rack rod (2) comprises a horizontal tube (201), a vertical tube (202), and a right-angle bend (203) installed between corresponding ends of the horizontal tube (201) and the vertical tube (202); a rotating flange (204) is installed at the bottom of the vertical tube (202); the rotating flange (204) is provided with a plurality of connection screw holes corresponding to the bolts preset on the base; The vertical tube (202) is an assembled structure of more than two sections, and the structure at the two opposite ends is as follows: sleeves (205) are arranged at intervals along the circumference of the outer side, and bolts (206) are inserted into the sleeves (205); the lower sleeve frame (4) and the upper sleeve frame (5) have the same height, and the height thereof is greater than the height of each section of the vertical tube (202); An inwardly concave wire groove (207) is provided on the outer side wall of the vertical bobbin (202), and an arc-shaped clamping plate (208) matching the outer side wall of the vertical bobbin (202) is provided on the outer side of the wire groove (207); The wire trough (207) and the arc-shaped clamping plate (208) are clamped together by means of a clamping hook; A stiffening rib (209) is fixedly installed on the side wall of the vertical tube (202); The method for repairing the camera uses the following steps: Step 1: Open the movable door (503) of the tower frame (1), remove the square inner frame (401) frame rod, the square reinforcement frame (402) frame rod, the rib rod (405) and the reinforcement rod (407) on the side corresponding to the movable door (503), push the tower frame (1) through the vertical tube (202) to the top of the base, so that the vertical tube (202) is located in the tower frame (1), adjust the support wheel (6) to make the tower frame (1) in a horizontal state, close the movable door (503) and install the removed rods of the lower sleeve frame (4), place the counterweight (406) on the triangular support frames (403) on both sides of the square reinforcement frame (402), so that the tower frame (1) is fixed; remove the signal line and power line on the frame rod (2); Step 2: Start the upper double push rod cylinder (508) and the lower double push rod cylinder (510), and extend the cylinder rods of the upper double push rod cylinder (508) and the lower double push rod cylinder (510), so that the two corresponding upper arc-shaped claws (509) and the two corresponding lower arc-shaped claws (511) hold the vertical tube (202), and then remove the bolts and nuts fixing the vertical tube (202) and the base; Step 3: Close the lower double push rod cylinder (510), retract the cylinder rod of the lower double push rod cylinder (510), and the two corresponding lower arc-shaped claws (511) are separated from the vertical tube (202). The two hydraulic cylinders (506) are started synchronously, and the piston rods of the hydraulic cylinders (506) extend upward to lift the top plate (505) upward so that the two upper arc-shaped claws (509) drive the vertical tube (202) to rise. At the same time, the compression spring (507) is compressed upward. After the top plate (509) reaches a height of 1.5 times that of the rotating flange (204), the hydraulic cylinder (506) stops and the lower double push rod cylinder (506) is started. 510), the cylinder rod of the lower double push rod cylinder (510) extends to push the two corresponding lower arc-shaped claws (511) to hold the vertical tube (202); the rotating flange (204) is installed at the bottom of the vertical tube (202), and the screw holes at the bottom of the rotating flange (204) are adjusted to correspond to the preset bolts on the base; then the lower double push rod cylinder (510) is closed, the cylinder rod of the lower double push rod cylinder (510) is retracted, and the two corresponding lower arc-shaped claws (511) are separated from the vertical tube (202), and the two hydraulic cylinders (506) are started synchronously, and the piston rods of the hydraulic cylinders (506) are retracted. The top plate (505) drives the upper double push rod cylinder (508) and the vertical tube (202) downward under the elastic force of the compression spring (507), so that the bottom screw hole of the rotating flange (204) is inserted into the bolt preset on the base, and then the lower double push rod cylinder (510) is started, and the cylinder rod of the lower double push rod cylinder (510) extends to push the two corresponding lower arc-shaped claws (511) to hold the vertical tube (202), and then the nut is installed to fix the rotating flange (204); after the installation is completed, the upper double push rod cylinder (508) and the lower double push rod cylinder (510) are closed. , the cylinder rods of the upper double push rod cylinder (508) and the lower double push rod cylinder (510) are retracted, and the two corresponding upper arc-shaped claws (509) and the two corresponding lower arc-shaped claws (511) are separated from the vertical tube (202). At the same time, the hydraulic cylinder (506) is started, and the piston rod of the hydraulic cylinder (506) is retracted. Under the elastic force of the compression spring (507), the top plate (505) drives the corresponding upper arc-shaped claws (509) to return to their original positions; the vertical tube (202) is rotated to rotate the horizontal tube (201) to the construction safety operation area on the side of the pedestrian crossing in the direction of the road; Step 4: Start the upper double push rod cylinder (508) and the lower double push rod cylinder (510), the cylinder rods of the upper double push rod cylinder (508) and the lower double push rod cylinder (510) are extended, so that the two corresponding upper arc-shaped claws (509) and the two corresponding lower arc-shaped claws (511) hold the vertical barrel (202), and then remove the nuts on the bottom of the rotating flange (204) and the base bolts, and then close the lower double push rod cylinder (510), the cylinder rod of the lower double push rod cylinder (510) is retracted, and the two corresponding lower arc-shaped claws (511) are separated from the vertical barrel (202), and the two hydraulic cylinders are started synchronously. The hydraulic cylinder (506) is pressed, and the piston rod of the hydraulic cylinder (506) extends upward to lift the top plate (505) upward, so that the two upper arc-shaped claws (509) drive the vertical tube (202) to rise, so that the bottom screw hole of the rotating flange (204) is separated from the base bolt and the hydraulic cylinder (506) rises a distance greater than the length of the bolt, and then stops, and then the lower double push rod cylinder (510) is started, and the cylinder rod of the lower double push rod cylinder (510) extends to push the two corresponding lower arc-shaped claws (511) to hold the vertical tube (202), and then the top of the rotating flange (204) and the vertical tube (202) are disassembled; After removing the rotating flange (204), the lower double push rod cylinder (510) is closed to retract the cylinder rod, and the two corresponding lower arc-shaped claws (511) are separated from the vertical barrel (202). The two hydraulic cylinders (506) are started synchronously, and the piston rods of the hydraulic cylinders (506) are retracted. At the same time, under the elastic force of the compression spring (507), the top plate (505) drives the upper double push rod cylinder (508) downward, so that the upper arc-shaped claw (509) drives the vertical barrel (202) downward until its bottom contacts the top surface of the base. At the same time, the lower double push rod cylinder (510) is started, and the piston rod of the lower double push rod cylinder (510) extends to push the two corresponding lower arc-shaped claws (511) to hold the vertical barrel (202). Since the height of the lower sleeve (4) is greater than the height of each section of the vertical tube (202), the vertical tube (202) at the lowest end is removed; Step 5: Close the upper double push rod cylinder (508), the cylinder rod of the upper double push rod cylinder (508) retracts, and the two corresponding upper arc-shaped claws (509) are separated from the vertical barrel (202), and the two hydraulic cylinders (506) are started synchronously. The piston rod of the hydraulic cylinder (506) extends upward to lift the top plate (505) upward to make the two upper arc-shaped claws (509) rise. At the same time, the compression spring (507) is compressed upward. After the hydraulic cylinder (506) piston rod reaches the maximum stroke, the hydraulic cylinder (506) stops, and the upper double push rod cylinder (508) is started. The cylinder rod of the upper double push rod cylinder (508) extends, so that the two corresponding upper arc-shaped claws (509) are tightly clamped. The vertical barrel (202) is closed, the lower double push rod cylinder (510) is closed, the piston rod of the lower double push rod cylinder (510) is retracted, and the two corresponding lower arc-shaped claws (511) are separated from the vertical barrel (202), and the two hydraulic cylinders (506) are started synchronously, and the piston rods of the hydraulic cylinders (506) are retracted. At the same time, under the elastic force of the compression spring (507), the top plate (505) drives the upper double push rod cylinder (508) and the vertical barrel (202) downward, and the piston rod of the hydraulic cylinder (506) is retracted and stops; the above operation process is repeated, so that the vertical barrel (202) is continuously moved downward, and it is removed after it descends to the height of a vertical barrel (202); Step 6: Repeat the operation of step 5, lower the vertical tube (202) to a height where it can be inspected, fix the bottom of the vertical tube (202) to the base, and inspect the monitoring camera (3).