Method for controlling water purification and water purification device
By measuring and controlling the feed pump speed and discharge flow, the water purification device is automatically adjusted to cope with different water quality inputs, which solves the problems of water quality stability and water consumption costs, and achieves efficient and low-cost water quality output.
Patent Information
- Application Number
- CN202080062768.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Priority Date
- 2019-09-05
- Filing Date
- 2020-09-04
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2040-09-04
AI Technical Summary
The existing reverse osmosis water purification technology is difficult to provide stable water quality output under different water quality inputs, and the water consumption and cost are high, making it difficult to automatically adjust to meet different water quality needs.
By measuring the inlet quality and product water flow, controlling the feed pump speed and discharge flow, automatic adjustment of the water purification device is achieved, stable water quality output is ensured, and partially permeated water is recirculated to reduce water consumption and cost.
It realizes the provision of stable water quality output under different water quality inputs, reduces water consumption and operating costs, reduces dependence on the skills and experience of installers, and improves the flexibility and efficiency of the water purification system.
Smart Images

Figure CN114340767B_ABST
Abstract
Description
Technical Field
[0001] The present disclosure relates to the field of water purification using reverse osmosis. Background Art
[0002] Reverse Osmosis (RO) is a commonly used water purification technology. RO uses a membrane where the water to be purified is pushed through the membrane to produce purified permeate water. The membrane is semi-permeable, allowing water to pass through but retaining most of the dissolved salts, particles, bacteria and endotoxins in a concentrated solution. The concentrated solution is sent to a drain, or recycled to reduce water consumption. The purification efficiency can be calculated as the percentage rate of impurities removed from the feed water.
[0003] The resulting permeate water may be used directly in certain applications, or may require further purification to meet high demands for purity. In both cases, it is desirable to know and control the degree of purification of the permeate water to accurately meet the application needs or the requirements dictated by further downstream purification steps receiving the permeate water. The water to be purified is, for example, tap water. The quality of tap water may vary from place to place and also from time to time, thus posing a challenge to the control of the purification process. Furthermore, in some places, water is a scarce resource and must be used with care. Summary of the invention
[0004] The object of the present disclosure is to provide water purification with a stable water quality output for water inputs of different qualities. Another object is to provide stable water quality with low water consumption. Another object is to provide stable water quality at low cost.
[0005] These and other objects are at least partly achieved by a method according to the first aspect, by an apparatus according to the second aspect and by embodiments according to the dependent claims.
[0006] According to one aspect, the present disclosure relates to a method for controlling water purification of a water purification device. The water purification device includes a reverse osmosis membrane configured to receive feed water from a feed pump and produce permeate water and reject water. The method includes: measuring an inlet water quality C indicating the inlet water of the feed pump; inlet The method further comprises: determining a target recovery of water purification based on the characteristics indicating the quality of the influent water. inlet , control the feed pump speed to a predetermined speed, or control it to a speed based on the feed pump speed, the water quality C inlet and target permeate water quality C per The method further comprises: measuring an indication of the product water flow rate Q prod The method further comprises: recycling the first portion of the rejected water, and based on the product water flow rate Q prod Control the discharge flow Q from the second part to the discharge portdrain , in order to complete the target recycling.
[0007] The method provides water purification with stable water quality output (i.e., the quality of permeate water) for water input (i.e., water inlet) of different qualities. By controlling the speed of recovery and feed pump, the working point of water purification can be adjusted according to different water inlet qualities to continuously provide stable water quality output without manual intervention. Therefore, it is possible to achieve water production that automatically adjusts its product according to different input water qualities. Therefore, the water purification device is easy to use in different locations, or easy to use in the same location but with different input water sources, without reconfiguring water production. Therefore, the dependence of installation quality on the skills and experience of the installer becomes smaller. Based on input water quality and product water flow control recovery, water consumption can be controlled thereby, thereby maintaining low water consumption. In addition, based on water inlet quality, the feed pump speed is controlled to a working point that can be effectively operated at low cost, or is controlled to a feed pump speed that supports maintaining target recovery and still produces permeate water with stable water quality.
[0008] According to some aspects, the control includes based on the product water flow rate Q prod Estimate the discharge flow rate Q required to achieve the target recovery drain , and control the discharge flow to the estimated discharge flow Q drain Therefore, the recycling can be controlled to the target recycling.
[0009] According to some aspects, the method includes: per The target recovery is determined within the constraints of maintaining a predetermined permeate water quality, or maintaining it within a predetermined permeate water quality interval. Thus, the target recovery can be changed for different feed water qualities so that the predetermined permeate water quality can still be achieved.
[0010] According to some aspects, the method includes: recycling a portion of the permeate water from the recirculation point to the feed water, so that excess permeate water can be reused.
[0011] According to some aspects, the recycling includes measuring a flow rate Q of the product water downstream of the recycling point of the permeate water indicative of prod The predetermined flow rate of product water can be achieved by controlling the recirculation to meet the product water flow rate standard.
[0012] According to some aspects, feed pump speed, water quality C inlet and target permeate water quality C per The relationship between is a predetermined relationship, which gives the inlet water quality C inletand the feed pump speed required to produce permeate water with a target permeate quality at the target recovery. Thus, the feed pump speed required to cope with a varying feed water quality while achieving the target recovery can be estimated at the estimated feed water quality.
[0013] According to some aspects, controlling the feed pump includes: inlet When in the interval, the feed pump speed is controlled to the predetermined speed, and the feed water quality C inlet Outside the range, based on the feed pump speed and water quality C inlet and target permeate water quality C per The feed pump speed is controlled based on the relationship between . Thus, robust control of the feed pump can be achieved. The predetermined speed is, for example, a predetermined constant speed. The interval is, for example, an intermediate interval between the lower interval and the upper interval of the inlet conductivity. The intermediate interval may be directly following the lower interval, and the upper interval may be directly following the intermediate interval.
[0014] According to some aspects, the measurement indicates the incoming water quality C inlet The characteristics of a water meter include: measuring the conductivity of the influent water, the conductivity of the feed water, or the conductivity of the permeate water. Therefore, conductivity can be an indication of the quality of the water. In addition, the quality of the influent water can be measured directly in the influent water, or derived from another quality measurement of the feed water or the permeate water.
[0015] According to some aspects, the method includes estimating an initial discharge flow rate Q through a discharge valve when the discharge valve for delivering the discharge water to the discharge port is fully opened toward the discharge port. initial_drain , and wherein the control includes: based on the initial discharge flow Q initial_drain and the estimated discharge flow Q drain The ratio at which the discharge valve should be opened toward the discharge port is estimated, and the discharge valve is controlled based on the estimated ratio. Thus, a discharge valve control value for achieving target recovery can be automatically derived for various types of discharge valves regardless of the wear of the discharge valve.
[0016] According to some aspects, the predetermined speed is a nominal speed of the feed pump. Thus, the feed pump can be operated at an operating point that is known to work efficiently.
[0017] According to a second aspect, the present disclosure relates to a water purification device, the water purification device comprising a fluid path, a feed pump configured to receive influent water and provide water, and a reverse osmosis (RO) membrane, wherein the RO membrane is configured to receive the feed water from the feed pump and produce permeate water and reject water. The device also includes: a quality sensor configured to measure an indication of the quality of the influent water C inlet The flow sensor is configured to measure the indicated product water flow rate Q prodThe device further comprises: a recirculation path configured to recirculate the first portion of the rejected water; and a discharge valve configured to adjust a discharge flow rate Q from the second portion of the rejected water to the discharge port. drain The device also includes a control device. The control device is configured to obtain an indication of the influent quality C inlet The control device is also configured to determine the target recovery of water purification based on the quality of the influent water C inlet The feed pump speed is controlled to a predetermined speed, or to a speed based on the feed pump speed, the influent quality C inlet and target permeate water quality C per The relationship between the speed determined and the product water flow rate Q prod Control the discharge flow Q from the discharge valve to the discharge port drain , in order to complete the target recycling.
[0018] The same positive effects can be obtained using this device as using this method.
[0019] According to a third aspect, the present disclosure relates to a computer program comprising instructions for causing a water purification device according to the second aspect to perform any steps of the method according to the first aspect.
[0020] According to a fourth aspect, the present disclosure relates to a computer readable medium having stored thereon the computer program of the third aspect. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 A water purification device according to a first embodiment is shown.
[0022] Figure 2 A water purification device according to a second embodiment is shown.
[0023] Figure 3 A valve arrangement according to some embodiments is shown.
[0024] Figure 4 is a first graph showing recovery versus inlet conductivity according to some embodiments.
[0025] Figure 5 is a second graph showing feed pump speed versus inlet conductivity according to some embodiments.
[0026] Figure 6 is a flow chart of a method according to some embodiments of the present disclosure. DETAILED DESCRIPTION
[0027] In the following, a method for purifying water and a water purification device will be described, which provide a stable quality of purified water for different qualities of influent water, while having a high recovery. "Recovery" may also be referred to as "water efficiency".
[0028] The feed water is purified using reverse osmosis (RO). Before being treated with RO, the feed water may be pre-treated in a pre-treatment module to remove, for example, larger particles and chlorine. The purified water from the RO process may be delivered directly for consumption or further treated in a post-treatment module before being delivered for consumption, depending on the requirements for the purified water quality. In any case, it is desirable to deliver a consistent water quality that meets the requirements from a consumption perspective or to meet the requirements of equipment still downstream of the RO so that these equipment can deliver purified water of the required quality without compromising their performance.
[0029] The operating point of the reverse osmosis process sets the purification efficiency with respect to rejection rate, recovery and power consumption. The pressure on the membrane is related to the permeate flow, so generally high pressure produces high permeate flow. Therefore, the permeate flow varies with the pressure on the membrane. The permeate flow also depends on the quality of the water fed to the reverse osmosis process. Water parameters that affect the permeate flow are, for example, conductivity and hardness. High conductivity reduces the permeate flow because the feed water contains more particles, which prevent water from penetrating the membrane, thereby increasing the osmotic pressure. In addition, high hardness reduces the permeate flow because the feed water contains more calcium, which increases scaling on the membrane.
[0030] The quality of the influent water may vary depending on the location and time of the year. The water purification described herein is performed based on the quality of the influent water, so as to achieve the target permeate water quality, while no excess water is sent to the discharge port during the RO process. Influent water of different qualities may require different membrane pressures and different recovery to obtain the target permeate water quality. Control recovery so that when the influent water quality is high, less water is sent to the discharge port than when the influent water quality is low. The feed pump pumps the feed water to the membrane, and the feed pump can be controlled to its most efficient working point. Thus purified water can be produced at low cost. Since the feed pump has a low noise level at its most efficient working point, the noise level to the surrounding environment can be kept low. When the quality of the influent water is low, the speed of the feed pump can be increased to increase the pressure on the membrane, thereby reducing the water that needs to be sent to the discharge port to achieve the target permeate quality.
[0031] In the following, different embodiments of a water purification device will be described, which controls water purification based on the quality of the incoming water.
[0032] Hereinafter, a method of producing purified water using, for example, any of the water purification apparatuses described below will be described.
[0033] Figure 1 The water purification device 1 according to the first embodiment is shown. The water purification device 1 includes a fluid path 50, an RO unit 3 including an RO membrane 3a, and a feed pump 5. The feed pump 5 is fed from a flow rate Q inlet The inlet water is received at an inlet point A (e.g., from a tap, a tank, or the like). An inlet path 20 connects the inlet point A with the feed pump 5. It should be understood that a "path" as used herein may include one or more fluid lines or paths. Thus, the fluid path 50 includes one or more fluid paths of the device 1, which will be described below. The inlet water may be pre-treated in a pre-treatment module 2 upstream of the feed pump 5. The pre-treatment module includes, for example, a mechanical filter for removing particles and / or one or more carbon beds for removing chlorine or chloramines. The quality of the inlet water is measured using a first quality sensor 17, which is configured to measure an amount indicative of the quality C of the inlet water. inlet The first quality sensor 17 is, for example, a conductivity cell, which is arranged to measure the conductivity of the inlet water. The first temperature sensor 18 is arranged to measure the temperature of the inlet water to temperature compensate the measurement result of the inlet conductivity. The water tank 6 or other kind of vessel or container can be arranged to collect the pretreated or non-pretreated inlet water. The first quality sensor 17 and the first temperature sensor 18 are arranged in the inlet path 20 downstream of any pretreatment module 2 but upstream of the feed pump 5. The water tank 6 is arranged downstream of the first quality sensor 17 and the first temperature sensor 18.
[0034] The feed pump 5 is configured to provide water flow from the inlet water. The feed pump 5 is, for example, a magnetically driven rotary vane pump. The feed pump 5 is arranged to be controlled to a certain speed (i.e., revolutions per minute (RPM)) and is powered by a power source (not shown) (e.g., a battery or a power grid). The power used by the feed pump 5 can be continuously monitored, for example, by monitoring the current or power consumed by the feed pump 5 or monitoring the current or power transmitted to the feed pump 5. The RO unit 3 and therefore the RO membrane 3a are configured to receive the feed water from the feed pump 5 and produce permeate water and drain water from the feed water. The feed path 21 connects the feed inlet of the feed pump 5 and the RO unit 3 to transport the feed water flow to the RO unit 3. The permeate path 22 connects the permeate outlet of the RO unit 3 with the consumption point B. The permeate water is transmitted from the RO unit 3 to the consumption point B in the permeate path 22. In some embodiments, the permeate water is further processed in the post-processing module 4 and then transported for consumption at the consumption point B. The post-processing module 4 includes, for example, a polisher. The polisher may include, for example, a deionizer using electrodeionization (EDI), capacitive deionization (CDI), electrodialysis reverse (EDR), or an ion exchange resin bed or mixed bed resin. In some embodiments, the polisher is configured to treat the permeate water so that it meets the quality requirements of water for injection with a conductivity of 1.3 μS / cm.
[0035] The purified water from the post-treatment module 4 may be referred to as product water. The product water is sent to a consumption point B for collection, further transport or use for other applications. If there is no post-treatment module 4, the permeate water leaving the RO unit 3 and sent to the consumption point B is referred to as product water.
[0036] The flow sensor 7 is configured to measure the permeate flow rate Q per The second quality sensor 8 is configured to measure the quality of the permeated water C per The second quality sensor 8 is, for example, a conductivity cell, which is arranged to measure the conductivity of the permeate water. As will be explained below, the measurement result of the second quality sensor 8 may also indicate the quality of the incoming water. The second temperature sensor 9 is arranged to measure the temperature of the permeate water to temperature compensate the measurement result of the conductivity of the permeate water.
[0037] The rejection rate of RO unit 3 is calculated as follows:
[0038]
[0039] The typical rejection of NaCl by the RO unit 3 is about 98% (0.98), with the rejection of other substances varying. The concentration in the permeate water is measured, for example, using a second mass sensor 8. The feed water concentration can be derived from the influent conductivity using recovery and mass balance equations.
[0040] In some embodiments, the apparatus 1 comprises: a permeate recirculation path 23 arranged to recirculate permeate water. The permeate recirculation path 23 is arranged between a recirculation point 10 located in the permeate path 22 and the inlet path 20. Thus, the permeate recirculation path 23 connects the permeate path 22 and the inlet path 20. The recirculation point 10 is located in the permeate path 22 downstream of the permeate flow sensor 7 and upstream of any post-treatment module 4. The permeate recirculation path 23 is connected to the inlet path 20 upstream of the feed pump 5, downstream of the first quality sensor 17 and downstream of the pre-treatment module 2 (if present). The control device 19 is arranged to control the flow rate of the permeate water recycled in the permeate recirculation path 23. The control device 19 is, for example, a controllable valve, such as an electric valve. The apparatus 1 is also provided with a flow sensor 11, which is configured to measure an indicative product water flow rate Q prod The flow sensor 11 is arranged to the permeate path 22 downstream of the recirculation point 10. The flow sensor 11 may be arranged upstream or downstream of any post-processing module 4. Product water is the portion of the permeate water that is not recirculated in the permeate recirculation path 23. Therefore, product water is water that continues in the permeate path 22 downstream of the recirculation point 10. In the case where the permeate water is post-processed in the post-processing module 4, the product water is purified water produced by the post-processing module 4. Based on the indication of the product water flow rate Q prodThe measured characteristics control the control device 19 so that the product water flow rate Q prod Corresponding to a predetermined flow rate. In some embodiments, the apparatus 1 includes a pressure sensor 12 configured to sense the pressure in the permeate fluid path 22 downstream of the recirculation point 10 and downstream of any post-processing module 4. Thus, the pressure sensor 12 monitors the pressure of the product water. The pressure sensor 12 monitors the pressure in the permeate path 22 downstream of the recirculation point 10 and downstream of any post-processing module 4 to ensure that the pressure in the permeate path remains within certain limits. Thus, the control device 19 may also be controlled so that the pressure in the permeate path 22 downstream of the recirculation point 10 and downstream of any post-processing module 4, for example, does not exceed an upper pressure limit.
[0041] In some embodiments, the device 1 comprises a tank 6 arranged in the inlet path 20 upstream of the feed pump 5. Then, the permeate recirculation path 23 may be fluidly connected to the tank 6, thereby recirculating the permeate water to the tank 6. Then, the pump 5 will pump water from the tank 6.
[0042] The apparatus 1 may include a third quality sensor (not shown) configured to measure a signal indicating the product water quality C prod The third quality sensor is, for example, a conductivity cell, arranged to measure the conductivity of the product water downstream of the post-processing module 4 (if present). Then a third temperature sensor (not shown) may be arranged to measure the temperature of the product water to perform temperature compensation on the measurement result of the product water conductivity.
[0043] The discharge path 24 connects the RO unit 3 with the first recirculation path 25 and the waste path 26. One end of the discharge path 24 is connected to the discharge outlet of the RO unit 3, and the other end is connected to the first recirculation path 25 and the waste path 26. The first recirculation path 25 is connected between the discharge path 24 and the inlet path 20. Therefore, one end of the first recirculation path 25 is connected to the discharge path 24, and the other end is connected to the inlet path 20. One end of the waste path 26 is connected to the discharge path 24, and the other end is connected to the discharge valve 13. The discharge valve 13 is a three-way valve here. The discharge path 27 is arranged to guide the discharge water from the discharge valve 13 to the discharge port 16. One end of the discharge path 27 is connected to the outlet of the three-way valve, and the other end is directed to the discharge port 16. The second recirculation path 28 is arranged to guide the discharge water from the discharge valve 13 to the inlet path 20 (here, the water tank 6). One end of the second recirculation path 28 is connected to the other outlet of the discharge valve 13, and the other end is connected to the water tank 6. The discharge valve 13 is arranged to selectively direct the drain water not recirculated through the first recirculation path 25 to the discharge port 16 and the inlet path 20. Thus, the drain water is both sent to the discharge port 16 and recirculated, however, the amount may be different.
[0044] The recirculation mechanism 15, here a valve such as a variable flow restriction valve or a manual or electric needle valve, is arranged to limit the flow in the first recirculation path 25. The recirculation mechanism 15 also ensures that the feed water does not enter the first recirculation path 25. The RO membrane recovery is usually set by a technician by configuring the recirculation mechanism 15 (which is a valve) so that the RO membrane recovery becomes a predetermined recovery when the speed of the feed pump 5 is driven, for example, at a nominal speed. Thus, the speed of the feed pump 5 also establishes a substantially constant discharge flow rate.
[0045] The discharge valve arrangement 14 is arranged to the waste path 26 to restrict the flow in the waste path 26 . Figure 3 One embodiment of the discharge valve arrangement 14 is shown. Figure 3 The discharge valve device 14 in the embodiment includes a flow device 65, which includes a first flow valve and a second flow valve downstream of the first flow valve. The pressure upstream and downstream of the first flow valve regulates the amount of flow allowed through the second flow valve. A bypass path 68 is arranged to bypass the flow device 65, and a controllable flow valve 66 (e.g., an on / off valve or a control valve) is arranged in the bypass path 68 to control the flow in the bypass path 68.
[0046] The device 1 also includes a control device 30. The control device 30 generally includes a control circuit, such as a processor and a memory. The processor includes, for example, one or more central processing units (CPUs). The memory includes, for example, one or more memory units. In some embodiments, the memory stores a computer program including instructions that cause the device 1 to execute a method for controlling the water purification device 1. Therefore, the computer program is stored on a computer-readable medium. The computer program can also be stored on an external memory (e.g., a flash memory, a cloud-based memory, or a memory on another computer). The control device 30 also includes a communication interface that can be wired or wireless so as to be able to communicate with the components (e.g., sensors, pumps, recycling mechanisms, valves, user interfaces, etc.) of the device 1. The control device 30 is, for example, configured to receive or collect information such as measured sensor values or data from components such as mass sensors, conductivity cells, temperature sensors, flow sensors, pressure sensors, pumps, valve devices, valves, etc. described. The control device 30 is also configured to send control signals or control data to components such as feed pumps, discharge valves, other valves, etc. described. In some embodiments, the control device 30 is configured to send a control signal or control data indicating a desired speed of the feed pump 5 to the feed pump 5. The feed pump 5 is configured to apply the desired speed upon receiving the desired speed. In some embodiments, the control device 30 is configured to send a control signal or control data indicating a specific opening / closing rate, opening degree, etc. to the discharge valve 13 to achieve a specific discharge flow rate Q drainThe control device 30 may also include a user interface so that a user can provide input to the device 1 and monitor the status of the device 1 and the purification process. The control device 30 may be arranged to automatically control the purification process, thus receiving the measured signals / data and making any required estimations, determinations, calculations, etc., and then automatically controlling the components of the device 1 (e.g., the feed pump 5, the discharge valve 13) to control the purification.
[0047] Figure 2 A water purification device according to a second embodiment is shown. The device 1 according to the second embodiment mainly corresponds to the device 1 according to the first embodiment, Figure 1 The same parts as those seen in the above are not described here. Figure 2 It can be seen that in the second embodiment, the first recirculation path 25 is connected between the discharge path 24 and the feed path 21, rather than between the discharge path 24 and the inlet path 5 as in the first embodiment. Therefore, the first recirculation path 25 is arranged to recirculate the discharge water to a point in the feed path 21 located between the feed pump 21 and the inlet of the RO unit 3. In addition, the recirculation mechanism 15 is a recirculation pump here, rather than a valve. The recirculation pump is, for example, a magnet-driven rotary vane pump. In addition, the discharge valve 13 is a controllable valve, which is arranged to the waste path 26. One end of the waste path 26 is connected to the discharge path 24, and the other end is connected to the discharge port 16. Therefore, in this second embodiment, there is no discharge path 27 or second recirculation path 28. The discharge valve 13 includes a controllable flow valve. The controllable flow valve is, for example, an on / off valve, which is arranged to change position between a fully open position and a fully closed position. The flow rate is controlled, for example, by controlling the frequency at which the switch valve changes state. That is, the time when the on / off valve is open is changed. Alternatively, the controllable flow valve is an electrically controllable flow valve configured to be controlled to multiple or infinite positions. The controllable discharge valve 13 is, for example, a needle valve or a proportional valve. The discharge valve 13 is set to provide a certain flow rate under a given pressure. For example, this setting is performed at the production site, during installation, or before water production begins. The setting can be performed manually or automatically. Afterwards, during the process of producing purified water, if the pressure on the discharge valve 13 increases, the flow rate through the discharge valve 13 will increase proportionally. In addition, if the pressure on the discharge valve 13 decreases, the flow rate through the discharge valve 13 will decrease proportionally.
[0048] By having a recirculation pump (in addition to the feed pump), the net driving pressure NDP and the discharge flow rate on both sides of the RO membrane 3a can be independently controlled. The feed pump 5 maintains the pressure on the RO membrane 3a, and the recirculation pump generates the necessary flow in the recirculation path 25 to maintain the predetermined RO membrane recovery rate. Therefore, it is not necessary to control the feed pump 5 to maintain the RO membrane recovery rate as in the previous system, instead, the feed pump 5 can be controlled to a certain speed to achieve a certain permeate conductivity. In addition, when using this dual pump system, the energy required to run the pump can be reduced compared to having only the feed pump 5 (without the recirculation pump). This is because it is easier for the feed pump 5 to achieve a high net driving pressure when using two pumps because the recirculation pump controls the recirculation flow rate. In addition, by using two pumps instead of only one feed pump, the noise level is reduced, as if only one pump is used, one pump needs to be driven at a higher RPM, thereby generating more noise.
[0049] In the first embodiment, i.e., in the single pump approach (with a feed pump 5 but no recirculation pump), the feed pump 5 generates both flow and pressure, so these parameters are coupled to each other and therefore cannot be changed independently. The net driving pressure is generated by the resistance in the RO membrane 3 which is also in the valve. Therefore, the feed pump 5 must deliver a large amount of water to build up the pressure required to push the water through the RO membrane 3a. By replacing the valve with a recirculation pump, the feed pump 5 can pressurize the recirculation path 25 without high water flow. Therefore, the feed pump 5 can be run at a much lower speed. The recirculation pump generates a recirculation flow but does not have to generate any pressure because the recirculation path 25 is pressurized by the feed pump 5.
[0050] The following will refer to Figure 6 The flowchart of FIG. 1 describes a method for controlling a water purification device (e.g., according to reference Figures 1 to 3 A method for a water purification device 1 of any of the embodiments described. The purpose of the method is to control the water purification device to produce purified water of a predetermined quality from influent water of different qualities in an effective manner. The method is usually loaded into the memory of the control device 30 of the device 1 as a computer program, and the computer program, when executed by the processor of the control device 30 of the device 1, causes the device 1 to execute the instructions of the computer program. It should be understood that the steps of the method can be performed in another order (i.e., an order derived from the numbering of the steps), and therefore, a step with a higher number can be performed before, at the same time, or after the step with a lower number compared to another step with a lower number.
[0051] Before the method starts, the device 1 is connected to a water source at a connection point A. The water source is, for example, a tap. The water is turned on and water flows into the inlet path 20 at the connection point A. Optionally, the water is pre-treated in the pre-treatment module 2. The method comprises measuring S1 indicating the inlet water quality C of the inlet water to the feed pump 5. inletThe characteristic is, for example, a conductivity measurement of the inlet water, a conductivity measurement of the feed water, or a conductivity measurement of the permeate water. Therefore, the quality of the inlet water can be measured using a conductivity cell (e.g., a first mass sensor 17) that is arranged to measure the conductivity of the inlet water or the feed water. The quality of the inlet water can be determined by measuring the conductivity of the feed water and deriving the conductivity of the inlet water based on the recovery and mass balance equations. In some embodiments, the conductivity of the feed water is approximately equal to the conductivity of the inlet water multiplied by the rejection rate / (1-recovery rate). Alternatively, the quality of the inlet water can be determined using a conductivity cell (e.g., a second mass sensor 9) that is arranged to measure the conductivity of the permeate water. Therefore, the conductivity C of the permeate water can be determined from the following relationship: per Derived inlet water conductivity c in :
[0052]
[0053] For NaCl, the exclusion ratio in the numerator can be approximated as "1" because it is very close to "1" (about 0.98). Therefore, the measured characteristic indicates the quality of the influent water. In other words, the quality of the influent water is, for example, related to or a function of the measured characteristic. Therefore, the measurement S1 indicates the influent water quality C inlet The characteristic of the inlet water quality comprises measuring the conductivity of the inlet water, the conductivity of the feed water, or the conductivity of the permeate water. In some embodiments, the step of measuring S1 a characteristic indicative of the inlet water quality comprises determining or estimating the inlet water quality based on one or more measurements of the inlet water conductivity, the feed water conductivity, and / or the permeate water conductivity.
[0054] The method also includes determining a target recovery for the S2 water purification based on characteristics indicative of the quality of the influent water. Thus, the influent water quality is used to determine the target recovery, i.e., how much water should be sent to the drain and how much water should be recycled. It should be understood that the target recovery is a target for system recovery, not a target for RO membrane recovery. In some embodiments, the step of determining the S2 target recovery includes determining or estimating the influent water quality based on one or more measurements of influent water conductivity, feed water conductivity, and / or permeate water conductivity. Recovery adjusts how much of the contaminants and impurities accumulated in the removal path 24 are sent to the drain 16. High recovery is used for high quality influent water. In the case of a large amount of impurities, more removal water needs to be sent to the drain 16. In some embodiments, determining S2 includes: perThe target recovery is determined under the constraint of maintaining a predetermined permeate water quality, or maintaining it within a predetermined permeate water quality interval. This also assumes that there is a constraint on the feed water quality, that is, the feed water quality is maintained at a predetermined feed water quality, or within a predetermined feed water quality interval. Therefore, the recovery is controlled so that the feed water quality is substantially maintained at a predetermined feed water quality or within a predetermined feed water quality interval. The recycled reject water includes concentrated water, and some should be sent to the drain to avoid over-concentrating the water provided to the RO unit 3. The higher the feed water quality, the more reject water can be recycled instead of being sent to the drain. The target recovery is calculated using, for example, the following equation:
[0055]
[0056] Equation (3) is derived experimentally and gives an estimate of a feasible target recovery for the current inlet water conductivity. Equation (3) relies on the linear relationship between the target recovery and the inlet water conductivity. Therefore, determining S2 includes determining the target recovery based on the linear relationship between the target recovery and the inlet water conductivity. Equation (3) is intended to give the target recovery as a percentage value between 0 and 100. "0" means that all feed water is sent to the drain. "100" means that all drain water is recycled. For example, the target recovery is allowed to vary between 50% and 90%. 50% means that 50% of the inlet water is sent to the drain, and 90% means that only 10% of the inlet water is sent to the drain. X is here a number determined based on the interval in which the inlet water conductivity is allowed to vary. For example, the inlet water conductivity is allowed to vary between 100μS / cm and 500μS / cm. By setting X = 10, the target recovery can be varied between 50% and 90% for inlet conductivity varying between 100 μS / cm and 500 μS / cm.
[0057] The method also includes controlling S3 the feed pump speed. In some embodiments, controlling S3 includes controlling the feed pump speed to a predetermined speed. Therefore, the feed pump speed can be set to a constant predetermined speed or a predetermined speed within a predetermined interval. The constant predetermined speed is, for example, the nominal speed of the feed pump 5. The predetermined interval is, for example, the nominal speed interval of the feed pump 5. The nominal speed or nominal speed interval of the speed pump 5 is, for example, the speed or speed interval in which the feed pump 5 is known to work most efficiently. If the feed pump speed is within its nominal speed interval, it is considered to be running at the nominal speed. However, in some cases, when the quality of the influent water becomes too low, it is impossible to keep the feed pump 5 at the nominal speed without delivering (excessive) rejected water to the discharge port. In addition, in some embodiments, since the pressure on the membrane should be increased to improve the quality of the permeate water, the feed pump speed is increased to achieve an increase in the pressure on the membrane. Therefore, in some embodiments, the method includes controlling S3 the feed pump speed to a predetermined speed based on the feed pump speed, the quality of the influent water C inlet and target permeate water quality Cper For example, when the feed water quality changes so that the target recovery cannot be maintained within the desired interval, the speed (pump speed) is changed to help deliver water with the target permeate water quality. In some embodiments, the feed pump speed, feed water quality C inlet and target permeate water quality C per is a predetermined relationship, which gives the inlet and the feed pump speed required to produce permeate water having a target permeate quality at a target recovery. For example, the relationship is a linear relationship between feed pump speed and feed water quality, which gives a target permeate quality for a predetermined constant recovery. Figure 5 This linear relationship is shown in the diagram of , which will be explained further below. Therefore, the feed pump speed may be a dynamic feed pump speed, in particular determined based on the feed water quality.
[0058] The method also includes measuring S4 indicating the product water flow rate Q prod The characteristic is, for example, measured by the first flow sensor 11. The characteristic is, for example, the flow rate of the product water in the permeate path downstream of the recirculation point 10 (i.e., the product water flow rate Q prod ).
[0059] The method further comprises recycling the first portion of the rejected water S5.
[0060] Recirculation is performed to achieve a predetermined RO membrane recovery continuously or continuously. RO membrane recovery is the RO recovery rate multiplied by 100, resulting in a percentage of RO recovery. RO membrane recovery rate is the ratio of permeate flow to feed flow rate. RO membrane recovery rate is determined as how much of the feed water becomes permeate water (i.e., how much of the feed water permeates through the RO membrane 3a into the permeate path 22). The maximum recovery rate of the RO membrane 3a is typically a design parameter set by the manufacturer of the RO equipment. If the RO membrane recovery exceeds its design value, the reject water will be saturated with salts and scale will begin to form on the membrane surface because some of the reject water will be recycled into the feed water. To avoid this, the RO membrane recovery is, for example, set by the manufacturer to a maximum recovery, for example, between 15-25% (equal to a maximum recovery rate of 0.15-0.25), for example, 20%. The RO membrane recovery is typically continuously monitored and controlled. The predetermined recovery is, for example, set to a maximum recovery. Alternatively, the predetermined recovery ratio is allowed to vary within an interval, with the maximum recovery rate defining the upper limit of the interval. The recovery rate of the RO membrane 3a can be calculated as Among them, Q per is the permeate flow rate upstream of the recirculation point 10, Q feed is the feed flow rate. Feed flow rate Q feedis the feed water flow rate in the feed path 21 downstream of any connection point of the recirculation path 25. In some embodiments, the recirculation S5 includes measuring the permeate flow rate Q of the permeate water per The permeate flow rate is measured, for example, using a permeate flow rate sensor 7. The recirculation S5 may also include providing a feed flow rate Q feed Estimation of feed flow Q feed According to Q feed =Q per +Q reject =Q per +Q re +Q drain Estimate, where Q re is the flow rate of the recirculated drainage water (Q re1 and Q re2 (if any)), Q re1 It can be estimated from the speed of the circulation pump, or when the feed pump 5 is running at a specific (e.g. nominal) speed, Q re1 It may be a known flow rate from the configuration of the valve in the first recirculation path 25 (to a certain system pressure). The drain valve arrangement 14 converts Q re2 regulated to a constant, predetermined flow rate. When a valve is used in the recirculation flow path, Q re1 and Q re2 The value of Q (if any) is known to the control device 30. drain Q is the flow rate of the drain water (also called drainage) sent to the drain. As known to those skilled in the art, Q drain It can be estimated based on the amount of time and / or degree to which the discharge valve 13 is open to the discharge port 16. Therefore, the recycling S5 includes calculating the RO membrane recovery rate, and controlling the recycling to obtain a predetermined recovery rate. For example, the recycling S5 includes using a feedback controller, wherein the error between the calculated recovery and the desired (e.g., target) recovery is minimized. Figure 1 In the case of the first embodiment, the speed of the feed pump 5 is controlled to achieve a predetermined RO membrane recovery. In the case of the second embodiment, the speed of the recirculation pump is controlled to achieve a predetermined RO membrane recovery. It has been found that the flow from each pump can be estimated based on the flow of the same pump, and therefore, the flow is proportional to the speed of the pump (e.g. rpm) because the pump displacement is known. Therefore, the flow from the pump can be determined from the mapping between the flow from the pump and the rpm of the same pump. Therefore, the flow Q from the feed pump 5 feed_pump It can be estimated from the speed of the feed pump 5. The recirculation flow rate Q in the first recirculation path 25 re1 It can be estimated based on the speed of the recirculation mechanism 15 (eg, a recirculation pump). Figure 2 The feed flow rate Q in the second embodiment feedThe estimated recirculation flow Q rec1 and the estimated flow rate Q from the feed pump 5 feed_pump The speed can be measured using an embedded Hall sensor in the pump motor. Alternatively, the feed flow rate Q feed is measured by a feed flow sensor (not shown) arranged to measure the feed flow in the feed path 21 downstream of the connection point of the recirculation path 25 ( Figure 2 ). Therefore, the RO membrane recovery rate can be calculated as Therefore, the speed of the recirculation pump is controlled so as to maintain a predetermined RO membrane recovery.
[0061] The method also includes a step of prod Control S6 to discharge water from the second part to the discharge port 16. drain , to achieve the target recovery. Therefore, a first portion of the reject water is recycled in the first recirculation path 25, and a second portion is sent to the waste path 26. Therefore, the total reject water is divided into a first portion and a second portion. The system recovery is determined based on how much water is consumed when using the purification method. Therefore, how much of the water input to the device 1 becomes product water (percentage). In other words, the recovery is 100 times the recovery rate, which is the ratio of the product water flow rate to the inlet water flow rate. For Figure 1 and Figure 2 For the example shown, the system recovery rate can be calculated as follows:
[0062]
[0063] Since the inlet water flow rate (i.e., the flow rate of water entering the device 1) is equal to the flow rate of water leaving the device 1 (i.e., the product water flow rate Q prod and discharge flow Q drain According to equation (4), the discharge flow rate Q drain can be calculated as:
[0064]
[0065] Therefore, in some embodiments, the control S6 discharge flow Q drain The indicated product water flow rate Q determined in step S4 is used prod The target recovery determined in step S2 is used as the “recovery rate” in equation (5), and the discharge flow rate Q is calculated based on equation (5): drain The target value Q drain_calc Then, use the calculated target value Q drain_calc Control S6 discharge flow Q drain , so that the discharge flow Q drainEqual to the calculated target value Q of the discharge flow drain_calc In other words, control S6 includes based on the product water flow rate Q prod Estimate the discharge flow rate Q required to achieve the target recovery drain , and control the discharge flow to the estimated discharge flow Q drain .
[0066] In some embodiments, the method includes estimating the exhaust flow rate Q when the exhaust valve 13 is open drain_open This estimate can then be used to determine the target discharge flow rate Q drain The required opening ratio of the discharge valve 13, for example, the opening degree or percentage, can be obtained by dividing equation (5) by the discharge flow rate Q drain_open To calculate:
[0067]
[0068] In other words, the discharge flow rate Q when the discharge valve 13 is open is drain_open The discharge flow rate Q through the discharge valve 13 when the discharge valve 13 is fully opened to the discharge port 16 can be estimated by S0. drain_open The discharge valve 13 is used to transmit the discharged water to the discharge port 16. Then, the control S6 includes a discharge flow rate Q drain_open and the estimated discharge flow Q drain The opening ratio that the discharge valve 13 should be opened toward the discharge port 16 is estimated, and the discharge valve 13 is controlled based on the estimated opening ratio. In one embodiment, step S0 includes opening the discharge valve 13 so that it is fully opened toward the discharge port 16, closing the control device 19, closing the recirculation mechanism 15, and pumping water using the feed pump 5. The flow rate through the discharge valve 13 can then be estimated by monitoring the relationship between the water level in the water tank 6 and time. Alternatively, the flow rate through the discharge valve 13 can be estimated by estimating the flow rate provided by the feed pump 5. The flow rate provided by the feed pump 5 should correspond to the flow rate through the discharge valve 13.
[0069] In some embodiments, the method includes recycling S7 a portion of the permeate water from the recycling point 10 to the inlet water. Recycling S7 includes recycling the permeate water from the recycling point 10 in the permeate path 22 to a point in the inlet path 20, which is typically located upstream of the feed pump 5 but downstream of the water tank 6 and the pretreatment module 2 (if present). The portion of the permeate water that is recycled is typically excess pretreated water that cannot be consumed. By recycling the permeate water to the inlet path 20, the excess permeate water can be reused. The inlet water is diluted with cleaner permeate water, thereby enhancing purification. In particular, since the quality of the permeate water is controlled by changing the speed of the feed pump 5, the permeate flow rate can be varied. By recycling the permeate water, the product flow rate can be controlled to a target product flow rate. In some embodiments, recycling S7 includes measuring a flow rate Q of the product water downstream of the recycling point 10 of the permeate water. prod The characteristics of the product water are measured and the recirculation is controlled to meet the product water flow rate standard. Indicates the product water flow rate Q prod The characteristic is, for example, the product flow rate Q prod This characteristic is measured, for example, by means of the first flow sensor 11. The product water flow rate criterion includes, for example, that the product water flow rate is equal to or nearly equal to a predetermined product water flow rate.
[0070] Figure 4 and Figure 5 Adaptive set points for system recovery and feed pump speeds are shown to achieve target recovery within appropriate ranges, e.g. for pre-treatment or consumption. The maximum conductivity of the feed water here is 1000 μS / cm. Figure 4 is the first graph, wherein the Y-axis is recovery (in percent) and the X-axis is influent conductivity (in μS / cm). Figure 5 is the second graph, where the Y-axis is the pump speed (in percent) and the X-axis is the influent conductivity (in μS / cm). Therefore, 100% is the maximum speed. The system recovery is allowed to vary between 75% and 50%. When the influent conductivity is between 0 and 249 μS / cm, the recovery is maintained at a constant value of 75%. Go to Figure 5 In the second figure in FIG. 1 , at the same time, the feed pump speed is increased from 50% to 60%. Here 60% is the nominal speed of the feed pump 5. Therefore, during the lower interval of inlet conductivity between 0 and 249 μS / cm, the feed pump speed changes to cope with the changing inlet conductivity, while the recovery remains unchanged. This is because the cost of running the speed pump 5 in this lower interval is very low, and the speed pump 5 has not yet reached its nominal speed. In addition, it is desirable to save water, and in the case of high recovery, more water can be saved. Therefore, in the control process to achieve the target permeate water quality, in order to achieve high quality of the inlet water, if the inlet water conductivity increases, the feed pump speed is increased, while the recovery is kept at a constant high level. Thereby, water can be saved. The lower interval defines the interval of low values of inlet conductivity.
[0071] When the feed pump speed has reached a predetermined speed (e.g., a nominal speed), control of the purification process enters an intermediate interval of inlet conductivity. During the intermediate interval, where the inlet conductivity is here between 250 μS / cm and 450 μS / cm, the recovery is varied to cope with the varying inlet water quality, while the feed pump speed is maintained at a constant level of 60% of the maximum speed. This is because the feed pump 5 operates at its nominal rate and thus works most efficiently. This interval of inlet conductivity may be referred to as an intermediate interval. Thus, the intermediate interval of inlet conductivity is an interval in which the inlet conductivity value is higher than the inlet conductivity value of the lower interval but lower than the inlet conductivity value of the subsequent upper interval. Thus, when the inlet conductivity is in the intermediate interval, the recovery varies in relation to the change in inlet conductivity to continue to produce permeate water that reaches the target permeate conductivity, while the feed pump speed remains constant. The intermediate interval defines an interval of intermediate values of inlet conductivity.
[0072] When the recovery has dropped to a predetermined lower limit value (here 50%), control of the purification process enters the upper interval of inlet conductivity. In the upper interval, where the inlet conductivity is, for example, between 451 μS / cm and 600 μS / cm, the feed pump speed is varied to cope with the varying inlet conductivity increase, while the recovery is kept at a constant level of 50%. Thus for increasing inlet water conductivity, less water may be wasted, but the feed pump 5 must work harder and therefore use more power. The upper interval defines an interval of high values of inlet conductivity.
[0073] Thus, the apparatus 1 can be controlled to different adaptive set points for feed pump speed and recovery. The adaptive set points are adjusted based on the feed water quality. Different thresholds of feed water quality (e.g., conductivity) determine the feed pump speed and recovery of the apparatus 1. Thus, in the above reference Figure 4 and Figure 5 In the example of FIG. 1 , during the lower interval, the set point for recovery is 75%. Therefore, the determining step S2 here includes determining the target recovery to be 75%. According to the feed pump speed control S3 to the feed pump speed based on the feed pump speed, the indicated feed water quality C inlet Characteristics and target permeate water quality C per The feed pump speed is controlled based on the speed determined by the relationship between the conductivity and the first threshold. The lower interval is bounded by zero conductivity and the first threshold. Therefore, as long as the conductivity of the inlet water is below the first threshold, the recovery set point is determined to be a predetermined first value (e.g., 75%). In addition, the feed pump speed is controlled based on the relationship.
[0074] During the intermediate interval, determining S2 includes determining a target recovery according to, for example, equation (3). The intermediate interval is bounded by a first threshold and a second threshold. As long as the conductivity of the inlet water is at or above the first threshold and below or at the second threshold, the target recovery is calculated using, for example, equation (3), or determined based on another linear relationship between the inlet water conductivity and the set recovery, so that the set recovery remains in the intermediate interval. Generally, as the inlet water conductivity increases, the recovery decreases. During the intermediate interval, controlling S3 includes controlling the feed pump speed to a set point, which is a predetermined speed of 60% of the maximum speed, for example, a nominal speed.
[0075] During the upper interval, determining S2 includes determining the target recovery to be a predetermined second value (here 50%). The upper interval is bounded by a second threshold value (and 1000 μS / cm or infinite conductivity). As long as the conductivity of the influent water is above the second threshold value, the recovery set point is the predetermined second value (e.g., 50%). The predetermined second value is lower than the predetermined first value. During the upper interval, the feed pump speed is controlled to a value based on the feed pump speed, the influent water quality C, and the influent water quality C. inlet Characteristics and target permeate water quality C per The relationship between the speeds determined is used to control the feed pump speed.
[0076] In other words, the control S3 of the feed pump includes the following steps: inlet The feed pump speed is controlled to a predetermined speed when in the intermediate interval (at or at), where the intermediate interval is 250 μS / cm to 450 μS / cm. The intermediate interval includes endpoints, here 250 μS / cm and 450 μS / cm, which also define the first threshold and the second threshold, respectively. In addition, control S3 includes a control based on the feed pump speed, the influent quality C inlet and target permeate water quality C per The relationship between controls the feed pump speed. Thus, fast and efficient control can be achieved.
[0077] The value of the first threshold is less than the value of the second threshold. These thresholds defining the intermediate interval can be determined based on the characteristics of the RO membrane 3a or certain characteristics of the influent or feed water (hardness, specific ion concentration, etc.). Characteristics of the RO membrane are, for example, the average pore size, the size of the membrane area, and the ability to handle heat. The RO membrane 3a is a semipermeable membrane. The average pore size of the RO membrane is typically between 0.1 nanometers and 10 nanometers, depending on the filter type. In some embodiments, the threshold starts with an initial value, which is determined based on the characteristics of the RO membrane, for example, given by the manufacturer. These thresholds can be updated to reflect changes in the RO membrane, such as wear and blockage. These changes can be reflected by the resulting permeate water quality, thereby indicating an exchange of the current configuration of the device 1. For example, if the target permeate water quality is not achieved, the threshold is adjusted so that the target permeate water quality is continuously achieved while producing purified water. Therefore, in some embodiments, the method includes, for example, measuring an indication of the permeate water quality C using a second quality sensor 8. per The method also includes the evaluation of the permeate quality C per Whether the target permeate water quality has been achieved, and based on this assessment, the threshold is adjusted so that the permeate water quality C per Achieve target permeate water quality C per Therefore, if this assessment indicates that the permeate water quality measured as conductivity C per If the evaluation indicates that the permeate water quality C measured as conductivity is above the target permeate water quality determined as conductivity, one or more thresholds are adjusted to achieve the target permeate water quality. per If the permeate water quality C is below or at the target permeate water quality determined as conductivity, the threshold is not adjusted. per The target permeate water quality is achieved. This process may include repeated measurements, evaluations, and threshold adjustments until the permeate water quality C per The process can be performed regularly according to the usage, for example, once each time the device 1 is used, once a week, once a month, etc. As explained, the device 1 includes a control device 30. The control device 30 is configured to Figure 1 to Figure 2 ) is executed in the device 1 of the invention and automatically executes the method according to any embodiment of the present invention. In more detail, the control device 30 is configured to obtain an indication of the influent quality C inlet The characteristic is obtained, for example, from the first quality sensor 17. The control device 30 is also configured to determine a target recovery of the water purification based on the characteristic indicative of the quality of the influent water. Thus, the target recovery can be determined by the control device 30 as described above. The control device 30 is also configured to determine a target recovery of the water purification based on the quality of the influent water C inlet The feed pump speed of the feed pump 5 is controlled to a predetermined speed, or to a speed based on the feed pump speed, the influent quality C inlet and target permeate water quality Cper The control device 30 is also configured to determine the speed based on the product water flow rate Q prod Control the discharge flow Q from the discharge valve to the discharge port drain , to achieve the target recovery. In some embodiments, the predetermined speed is the nominal speed of the feed pump. Therefore, the control of the feed pump speed may depend on the quality of the influent water. For example, if the influent water quality is within, for example, the middle interval of the influent water quality, the feed pump speed is controlled to a predetermined speed, for example, the nominal speed. If the influent water quality is outside the middle interval, the feed pump speed is controlled based on the relationship. The control device 30 is also configured to control the product water flow rate Q based on the product water flow rate Q. prod Estimate the discharge flow rate Q required to achieve the target recovery drain , and the discharge flow rate is controlled to the estimated discharge flow rate. The discharge flow rate is controlled by means of the discharge valve 13.
[0078] According to some embodiments, the control device 30 is configured to per The target recovery is determined while maintaining a predetermined permeate water quality, or within the constraints of a predetermined permeate water quality interval.
[0079] According to some embodiments, the water purification device 1 comprises a permeate water recirculation path 23 arranged between the recirculation point 10 and the inlet path 20 in the permeate path 22 to recirculate part of the permeate water from the recirculation point 10 to the inlet water.
[0080] According to some embodiments, the control device 30 is configured to indicate the flow rate Q of the product water based on prod The characteristics of the recirculation are controlled to meet the product water flow standards.
[0081] According to some embodiments, the feed pump speed, the inlet water quality C inlet and target permeate water quality C per The relationship between is a predetermined relationship, which gives the inlet water quality C inlet and the feed pump speed required to produce permeate water with target permeate quality at target recovery.
[0082] According to some embodiments, the control device 30 is configured to inlet In the middle range, the feed pump speed is controlled to a predetermined constant speed, and the feed water quality C inlet Outside the middle range, based on the feed pump speed, water quality C inlet and target permeate water quality C per The relationship between controls the feed pump speed.
[0083] According to some embodiments, the quality sensors 9, 17 are conductivity cells, indicating the incoming water quality C inletThe characteristic is the conductivity of the inlet water, the conductivity of the feed water or the conductivity of the permeate water.
[0084] According to some embodiments, the control device 30 is configured to estimate an initial discharge flow Q through the discharge valve 13 when the discharge valve 13 is fully opened toward the discharge port 16. initial_drain , based on the initial discharge flow Q initial_drain and the estimated discharge flow Q drain The ratio by which the discharge valve should be opened toward the discharge port is estimated, and the discharge valve 13 is controlled based on the estimated ratio.
[0085] While the invention has been described in connection with what are presently considered to be the most practical and preferred embodiments, it is to be understood that the invention is not limited to the disclosed embodiments, but on the contrary, the invention is intended to cover various modifications and equivalent arrangements included within the purview of the appended claims.
Claims
1. A method for controlling water purification of a water purification device (1) to provide a stable permeate conductivity, the water purification device (1) comprising a reverse osmosis membrane (3a), the reverse osmosis membrane (3a) being configured to receive feed water from a feed pump (5) and to produce permeate water and reject water, the method comprising: - measuring (S1) the inlet water conductivity C of the inlet water of the feed pump (5) inlet The conductivity of - determining (S2) a target recovery for water purification based on said conductivity indicative of the conductivity of the influent water, wherein said target recovery defines a product water flow rate Q prod With the water flow rate Q inlet The target ratio, and wherein the water inlet flow rate Q inlet is defined as the product water flow rate Q prod With the discharge flow Q drain sum; -Based on the inlet water conductivity C inlet , the feed pump speed is controlled (S3) to a predetermined speed at which the feed pump operates most efficiently, or is controlled (S3) to a speed based on the feed pump speed, the feed water conductivity C inlet and target permeate water conductivity C per a speed determined by a relationship between and achieving a target permeate water conductivity for the determined target recovery at said feed pump speed; -Measurement (S4) indicates product water flow Q prod characteristics, wherein the product water is permeate water that is delivered for consumption; - recirculating (S5) the first part of the discharged water to the inlet or feed water; -Based on the product water flow Q prod Control (S6) the discharge flow rate Q of the water discharged from the second part to the discharge port drain , to achieve the recycling target, Wherein, the method further comprises: The conductivity of permeate water C per Maintaining the predetermined permeate water conductivity, or maintaining the permeate water conductivity within a predetermined range, determining (S2) the target recovery, Among them, the feed pump speed, the inlet water conductivity C inlet and the target permeate water conductivity C per is a predetermined relationship, and the predetermined relationship gives the relationship between the inlet water conductivity C inlet and the feed pump speed required to produce permeate water having a target permeate conductivity at the target recovery.
2. The method according to claim 1, wherein: The control (S6) includes based on the product water flow Q prod according to Determine the discharge flow rate Q required to achieve the target recovery drain , and control the discharge flow rate to the determined discharge flow rate Q drain .
3. The method according to claim 1 or 2, comprising: Part of the permeate water is recycled (S7) from the recycling point (10) to the feed water.
4. The method according to claim 3, wherein: The recycling (S7) includes measuring a flow rate Q of the product water downstream of the recycling point (10) of the permeate water. prod and controlling the recirculation to meet a product water flow rate standard, wherein the product water flow rate standard includes a product water flow rate being equal to, or nearly equal to, a predetermined product water flow rate.
5. The method according to any one of claims 1, 2 and 4, wherein: Determine (S2) the target recovery including: When the inlet water conductivity C inlet When the target recovery is lower than a first threshold, the target recovery is determined as a predetermined first value; When the inlet water conductivity C inlet above a second threshold, determining the target recycling to be a predetermined second value, wherein the first threshold has a lower value than the second threshold, and wherein the predetermined second value is less than the predetermined first value; and When the inlet water conductivity C inlet When the target recovery is equal to or higher than the first threshold and equal to or lower than the second threshold, the target recovery is determined according to a linear relationship between the target recovery and the inlet water conductivity.
6. The method according to claim 3, wherein: Determine (S2) the target recovery including: When the inlet water conductivity C inlet When the target recovery is lower than a first threshold, the target recovery is determined as a predetermined first value; When the inlet water conductivity C inlet above a second threshold, determining the target recycling to be a predetermined second value, wherein the first threshold has a lower value than the second threshold, and wherein the predetermined second value is less than the predetermined first value; and When the inlet water conductivity C inlet When the target recovery is equal to or higher than the first threshold and equal to or lower than the second threshold, the target recovery is determined according to a linear relationship between the target recovery and the inlet water conductivity.
7. The method according to claim 5, wherein: Controlling (S3) the feed pump comprises: inlet When the feed pump speed is equal to or higher than the first threshold and equal to or lower than the second threshold, the feed pump speed is controlled to the predetermined speed at which the feed pump operates most efficiently, and when the feed water conductivity C inlet When the feed pump speed is lower than the first threshold or higher than the second threshold, the feed water conductivity C inlet and the target permeate water conductivity C per The relationship between controls the feed pump speed.
8. The method according to claim 6, wherein: Controlling (S3) the feed pump comprises: inlet When the feed pump speed is equal to or higher than the first threshold and equal to or lower than the second threshold, the feed pump speed is controlled to the predetermined speed at which the feed pump operates most efficiently, and when the feed water conductivity C inlet When the feed pump speed is lower than the first threshold or higher than the second threshold, the feed water conductivity C inlet and the target permeate water conductivity C per The relationship between controls the feed pump speed.
9. The method according to any one of claims 1, 2, 4, 6, 7, and 8, wherein: The measurement (S1) indicates the influent conductivity C inlet Conductivity includes: measuring the conductivity of inlet water, the conductivity of feed water or the conductivity of permeate water.
10. The method according to claim 3, wherein: The measurement (S1) indicates the influent conductivity C inlet Conductivity includes: measuring the conductivity of inlet water, the conductivity of feed water or the conductivity of permeate water.
11. The method according to claim 5, wherein: The measurement (S1) indicates the influent conductivity C inlet Conductivity includes: measuring the conductivity of inlet water, the conductivity of feed water or the conductivity of permeate water.
12. The method according to any one of claims 1, 2, 4, 6, 7, 8, 10, 11, comprising: Determine (S0) the initial discharge flow rate Q through the discharge valve (13) when the discharge valve (13) is fully opened to the discharge port (16) initial_drain , wherein the discharge valve (13) is used to transmit the discharged water to the discharge port (16), and wherein the control (S6) includes: based on the initial discharge flow rate Q initial_drain and the determined discharge flow Q drain The ratio at which the discharge valve should open toward the discharge port is determined, and the discharge valve (13) is controlled based on the determined ratio.
13. The method according to claim 3, comprising: Determine (S0) the initial discharge flow rate Q through the discharge valve (13) when the discharge valve (13) is fully opened to the discharge port (16) initial_drain , wherein the discharge valve (13) is used to transmit the discharged water to the discharge port (16), and wherein the control (S6) includes: based on the initial discharge flow rate Q initial_drain and the determined discharge flow Q drain The ratio at which the discharge valve should open toward the discharge port is determined, and the discharge valve (13) is controlled based on the determined ratio.
14. The method according to claim 5, comprising: Determine (S0) the initial discharge flow rate Q through the discharge valve (13) when the discharge valve (13) is fully opened to the discharge port (16) initial_drain , wherein the discharge valve (13) is used to transmit the discharged water to the discharge port (16), and wherein the control (S6) includes: based on the initial discharge flow rate Q initial_drain and the determined discharge flow Q drain The ratio at which the discharge valve should open toward the discharge port is determined, and the discharge valve (13) is controlled based on the determined ratio.
15. The method according to claim 9, comprising: Determine (S0) the initial discharge flow rate Q through the discharge valve (13) when the discharge valve (13) is fully opened to the discharge port (16) initial_drain , wherein the discharge valve (13) is used to transmit the discharged water to the discharge port (16), and wherein the control (S6) includes: based on the initial discharge flow rate Q initial_drain and the determined discharge flow Q drain The ratio at which the discharge valve should open toward the discharge port is determined, and the discharge valve (13) is controlled based on the determined ratio.
16. A water purification device (1) configured to provide a stable permeate conductivity, the water purification device (1) comprising: a fluid path (50); a feed pump (5) arranged to the fluid path (50) and configured to receive inlet water and provide water; A reverse osmosis membrane (3a), wherein the reverse osmosis membrane (3a) is configured to receive feed water from the feed pump (5) and generate permeate water and reject water; Conductivity sensors (9, 17) are configured to measure the conductivity C of the influent water. inlet The conductivity of The flow sensor (7, 11) is configured to measure the indicated product water flow Q prod characteristics, wherein the product water is permeate water that is delivered for consumption; a recirculation path (25) configured to recirculate the first portion of the reject water to an inlet or feed water; The discharge valve (13) is configured to adjust the discharge flow rate Q of the water discharged from the second part to the discharge port (16) drain ; The control device (30) is configured to: Obtain an indication of the influent conductivity C inlet The conductivity of A target recovery for water purification is determined based on the conductivity indicative of the influent water conductivity, wherein the target recovery defines a product water flow rate Q prod The target ratio of the inlet flow rate to the product water flow rate Q prod With the discharge flow Q drain sum; Based on the inlet water conductivity C inlet , controlling the feed pump speed of the feed pump (5) to a predetermined speed at which the feed pump operates most efficiently, or to a speed based on the feed pump speed, the influent conductivity C inlet and target permeate water conductivity C per a speed determined by a relationship between and achieving a target permeate water conductivity for the determined target recovery at said feed pump speed; The flow rate Q of the product water is measured by using flow sensors (7, 11) prod characteristics; and Based on the product water flow Q prod Control the discharge flow Q from the discharge valve (13) to the discharge port drain , to achieve the recycling target, The control device (30) is configured to control the conductivity of the permeated water to per The target recovery is determined by maintaining the permeate water conductivity at a predetermined value, or maintaining the permeate water conductivity within a predetermined range. Among them, the feed pump speed, the inlet water conductivity C inlet and the target permeate water conductivity C per is a predetermined relationship, and the predetermined relationship gives the relationship between the inlet water conductivity C inlet and the feed pump speed required to produce permeate water having a target permeate conductivity at the target recovery.
17. The water purification device (1) according to claim 16, wherein: The control device (30) is configured to prod according to Determine the discharge flow rate Q required to achieve the target recovery drain , and controlling the discharge flow rate to the determined discharge flow rate.
18. The water purification device (1) according to claim 16 or 17, comprising: A permeate recirculation path (23) is arranged between a recirculation point (10) in the permeate path (22) and the inlet path (20) to recirculate part of the permeate water from the recirculation point (10) to the inlet water.
19. The water purification device (1) according to claim 18, wherein: The control device (30) is configured to indicate the flow rate Q of the product water based on prod The recirculation is controlled to meet a product water flow rate standard, wherein the product water flow rate standard includes the product water flow rate being equal to, or nearly equal to, a predetermined product water flow rate.
20. The water purification device (1) according to any one of claims 16, 17 and 19, wherein: The control device (30) is configured to determine the target recovery as follows, including: When the inlet water conductivity C inlet When the target recovery is lower than a first threshold, the target recovery is determined as a predetermined first value; When the inlet water conductivity C inlet above a second threshold, determining the target recycling to be a predetermined second value, wherein the first threshold has a lower value than the second threshold, and wherein the predetermined second value is less than the predetermined first value; and When the inlet water conductivity C inlet When the target recovery is equal to or higher than the first threshold and equal to or lower than the second threshold, the target recovery is determined according to a linear relationship between the target recovery and the inlet water conductivity.
21. The water purification device (1) according to claim 18, wherein: The control device (30) is configured to determine the target recovery as follows, including: When the inlet water conductivity C inlet When the target recovery is lower than a first threshold, the target recovery is determined as a predetermined first value; When the inlet water conductivity C inlet above a second threshold, determining the target recycling to be a predetermined second value, wherein the first threshold has a lower value than the second threshold, and wherein the predetermined second value is less than the predetermined first value; and When the inlet water conductivity C inlet When the target recovery is equal to or higher than the first threshold and equal to or lower than the second threshold, the target recovery is determined according to a linear relationship between the target recovery and the inlet water conductivity.
22. The water purification device (1) according to claim 20, wherein: The control device (30) is configured to: inlet When the feed pump speed is equal to or higher than the first threshold value and equal to or lower than the second threshold value, the feed pump speed is controlled to the predetermined speed at which the feed pump operates most efficiently, and when the feed water conductivity C inlet When the feed pump speed is lower than the first threshold or higher than the second threshold, the feed water conductivity C inlet and the target permeate water conductivity C per The relationship between controls the feed pump speed.
23. The water purification device (1) according to claim 21, wherein: The control device (30) is configured to: inlet When the feed pump speed is equal to or higher than the first threshold value and equal to or lower than the second threshold value, the feed pump speed is controlled to the predetermined speed at which the feed pump operates most efficiently, and when the feed water conductivity C inlet When the feed pump speed is lower than the first threshold or higher than the second threshold, the feed water conductivity C inlet and the target permeate water conductivity C per The relationship between controls the feed pump speed.
24. A water purification device (1) according to any one of claims 16, 17, 19, 21, 22, 23, wherein: The conductivity sensor (9, 17) is a conductivity cell and indicates the inlet water conductivity C inlet The conductivity is the conductivity of the inlet water, the conductivity of the feed water or the conductivity of the permeate water.
25. The water purification device (1) according to claim 18, wherein: The conductivity sensor (9, 17) is a conductivity cell and indicates the inlet water conductivity C inlet The conductivity is the conductivity of the inlet water, the conductivity of the feed water or the conductivity of the permeate water.
26. The water purification device (1) according to claim 20, wherein: The conductivity sensor (9, 17) is a conductivity cell and indicates the inlet water conductivity C inlet The conductivity is the conductivity of the inlet water, the conductivity of the feed water or the conductivity of the permeate water.
27. A water purification device (1) according to any one of claims 16, 17, 19, 21, 22, 23, 25, 26, wherein: The control device (30) is configured to: Determine the initial discharge flow rate Q through the discharge valve (13) when the discharge valve (13) is fully opened toward the discharge port (16) initial_drain , Based on the initial discharge flow Q initial_drain and determine the discharge flow Q drain determining the proportion by which the discharge valve (13) should open towards the discharge port, and The discharge valve (13) is controlled based on the determined ratio.
28. The water purification device (1) according to claim 18, wherein: The control device (30) is configured to: Determine the initial discharge flow rate Q through the discharge valve (13) when the discharge valve (13) is fully opened toward the discharge port (16) initial_drain , Based on the initial discharge flow Q initial_drain and determine the discharge flow Q drain determining the proportion by which the discharge valve (13) should open towards the discharge port, and The discharge valve (13) is controlled based on the determined ratio.
29. The water purification device (1) according to claim 20, wherein: The control device (30) is configured to: Determine the initial discharge flow rate Q through the discharge valve (13) when the discharge valve (13) is fully opened toward the discharge port (16) initial_drain , Based on the initial discharge flow Q initial_drain and determine the discharge flow Q drain determining the proportion by which the discharge valve (13) should open towards the discharge port, and The discharge valve (13) is controlled based on the determined ratio.
30. The water purification device (1) according to claim 24, wherein: The control device (30) is configured to: Determine the initial discharge flow rate Q through the discharge valve (13) when the discharge valve (13) is fully opened toward the discharge port (16) initial_drain , Based on the initial discharge flow Q initial_drain and determine the discharge flow Q drain determining the proportion by which the discharge valve (13) should open towards the discharge port, and The discharge valve (13) is controlled based on the determined ratio.
31. A computer program product comprising instructions for causing a water purification device (1) according to any one of claims 16 to 30 to perform the steps of the method according to any one of claims 1 to 15.
32. A computer-readable medium having stored thereon the computer program product of claim 31.