Mechanical and electrical construction method and system based on BIM technology
Using BIM technology to build and optimize construction models, assign priorities and perform simulations, the problem of construction plan coordination is solved, construction efficiency and cost control are improved, and construction conflicts are avoided.
Patent Information
- Application Number
- CN202111514602.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-12-13
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2041-12-13
AI Technical Summary
During the electromechanical construction process, since the construction plan is manually coordinated, deviations are prone to occur. Especially when there are a large number of construction parties, unpredictable construction problems are more common, resulting in increased construction efficiency and costs.
The electromechanical construction method based on BIM technology is used to build the initial BIM model through 3D scanning. After optimization and adjustment, it is combined with the planning data of the construction department to assign priorities, conduct construction simulation, analyze risks and adjust the planning data to avoid construction conflicts and conflict risks.
It effectively avoids most problems in construction, improves construction efficiency and cost control, and reduces construction conflicts and deviations, especially in the case of multiple construction parties.
Smart Images

Figure CN114444163B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of electromechanical construction technology, and in particular to an electromechanical construction method and system based on BIM technology. Background Art
[0002] The production workshop consists of two parts according to the independent functionality of the building space. The first part is the ventilation and air conditioning system; the second part is the production equipment system. During the electromechanical construction process of the production workshop, multiple construction parties will install and construct a large number of pipe network systems and equipment systems. In order to avoid construction conflicts during the construction process and save construction time and costs, it is necessary to summarize the construction plans of all construction parties for manual coordination and formulate a more reasonable overall construction plan.
[0003] Regarding the above-mentioned related technologies, the inventors believe that there are the following defects: since the construction plan is implemented by manpower, deviations from the construction plan are inevitable during the construction process. When the number of construction parties is large, the construction plan formulated through manual coordination will be more likely to have unpredictable construction problems during the manual construction process. Summary of the invention
[0004] In order to improve the defect that unpredictable construction problems are prone to occur during the manual construction process of the construction plan formulated through manual coordination, the present application provides a mechanical and electrical construction method and system based on BIM technology.
[0005] In a first aspect, the present application provides a mechanical and electrical construction method based on BIM technology, comprising the following steps:
[0006] Build an initial BIM model of the construction site based on 3D scanning technology;
[0007] Optimizing and adjusting the initial BIM model to obtain an on-site BIM model;
[0008] Obtain the planned construction data of all construction departments respectively, and assign construction priorities to all construction departments according to all the planned construction data;
[0009] Perform construction simulation based on the on-site BIM model and according to the planned construction data and the construction priority to obtain simulation results;
[0010] The construction risks are analyzed according to the simulation results, and the corresponding planned construction data are adjusted based on the construction risks.
[0011] By adopting the above technical solution, the construction site is 3D scanned by 3D scanning technology to construct an initial BIM model of the construction site. In order to reduce the errors of the BIM model in the subsequent construction simulation process, the initial BIM model needs to be optimized and adjusted before it is applied to obtain the on-site BIM model. Then, the construction priority is assigned to the construction department according to the planned construction data of the construction department, the planned construction data is imported into the on-site BIM model, and the construction simulation is performed in the BIM model according to the construction priority. The simulation results are analyzed for construction risks, and the planned construction data is adjusted in combination with the analyzed construction analysis. Therefore, even if there are many construction departments, the construction process can be simulated and the construction plan can be adjusted through BIM technology, thereby effectively avoiding most of the problems that arise in subsequent construction.
[0012] Optionally, the planned construction data includes the number of construction personnel, embedded parts construction data and equipment construction data, and the allocating construction priorities to all construction departments according to all planned construction data includes the following steps:
[0013] Counting the total amount of embedded parts in the embedded parts construction data;
[0014] Determining whether the total amount of the embedded parts is greater than a preset first total amount threshold;
[0015] If the total amount of the embedded parts is greater than the first total amount threshold, assigning a first construction priority to the corresponding construction department;
[0016] If the total amount of the embedded parts is not greater than the first total amount threshold, determining whether the total amount of the embedded parts is greater than a preset second total amount threshold, and the second total amount threshold is less than the first total amount threshold;
[0017] If the total amount of the embedded parts is greater than the second total amount threshold, a second construction priority is allocated to the corresponding construction department, and the second construction priority is lower than the first construction priority;
[0018] If the total amount of the embedded parts is not greater than the second total amount threshold, a third construction priority is allocated to the corresponding construction department, and the third construction priority is lower than the second construction priority;
[0019] The construction priority assigned by the construction department is adjusted in combination with the number of construction personnel and the equipment construction data.
[0020] By adopting the above technical solution, during the on-site construction process, embedded parts need to be constructed first. Therefore, the total amount of embedded parts of each construction department is judged first, and a higher priority is temporarily assigned to the construction department with a large amount of embedded parts, while a lower priority is temporarily assigned to the construction department with a small amount of embedded parts. After the priority is temporarily assigned, it is necessary to adjust the priority in combination with the number of construction personnel and equipment construction data.
[0021] Optionally, the equipment construction data includes equipment type and total equipment quantity, and the adjusting the construction priority of the construction department in combination with the number of construction personnel and the equipment construction data includes the following steps:
[0022] Retrieving the equipment type through Internet technology to obtain historical construction data of the equipment type;
[0023] Taking the number of construction personnel as the calculation standard, the historical construction data is analyzed and calculated to obtain the historical average construction period;
[0024] Calculate the planned construction period based on the total amount of equipment and the number of construction personnel;
[0025] Determining whether the planned construction period is greater than the historical average construction period;
[0026] If the planned construction period is longer than the historical average construction period, the construction priority of the corresponding construction department is increased;
[0027] If the planned construction period is not greater than the historical average construction period, then the period difference between the planned construction period and the historical average construction period is calculated;
[0028] Determining whether the period difference is greater than a preset difference threshold;
[0029] If the period difference is greater than the difference threshold, the construction priority of the corresponding construction department is reduced;
[0030] If the cycle difference is not greater than the difference threshold, the construction priority of the corresponding construction department is not adjusted.
[0031] By adopting the above technical solution, the Internet is searched according to the type of equipment that each department needs to construct, and the historical construction data of the same equipment type is retrieved, so as to analyze and calculate the historical average construction period of the equipment type, and then calculate the planned construction period according to the total amount of equipment and the number of construction personnel in the planned construction data. If the difference between the planned construction period and the historical average construction period is large, it means that there is a serious deviation between the construction plan and the actual situation. Therefore, it is necessary to reduce the construction priority of the corresponding construction department to reduce the impact of the construction process of the construction department on the overall construction plan; if the difference between the planned construction period and the historical average construction period is small, it means that the construction plan of the corresponding construction department is more in line with reality, so there is no need to adjust the construction priority of the construction department.
[0032] Optionally, the retrieving the equipment type through Internet technology to obtain the historical construction data of the equipment type includes the following steps:
[0033] Create a crawler script using the device type as a keyword;
[0034] Retrieving associated data related to the device type from the Internet through the crawler script;
[0035] The associated data is filtered based on the equipment construction data corresponding to the equipment type to obtain the historical construction data of the equipment type.
[0036] By adopting the above technical solution, the associated data related to the equipment type is retrieved from the Internet through the crawler script. The associated data contains a large amount of data that is not related to the current construction. Therefore, it is necessary to filter the associated data according to the equipment construction data in the planned construction data, and use the filtered data as the historical construction data of the equipment type.
[0037] Optionally, performing construction simulation based on the on-site BIM model and according to the planned construction data and the construction priority to obtain a simulation result comprises the following steps:
[0038] Importing the planned construction data into the on-site BIM model;
[0039] creating an environment style and processing components based on the planned construction data;
[0040] calibrating a simulation order for the processing components according to the construction priority;
[0041] A simulation process is generated based on the environment style and the processing parts in the simulation order, and a construction simulation is performed in the on-site BIM model according to the simulation process to obtain a simulation result.
[0042] By adopting the above technical solution, the model simulation environment style and the processing components required for simulation are created in the on-site BIM model according to the planned construction data of all construction departments. Each construction department has sorted the construction priorities according to the planned construction data. Therefore, the processing components required by each construction department are calibrated for simulation order according to the construction priority. Finally, a simulation process is generated in the on-site BIM model with the environment style and the processing components calibrated with the simulation order, and construction simulation is carried out according to the simulation process in the on-site BIM model to obtain a simulation result that simulates the entire construction process.
[0043] Optionally, analyzing the construction risk according to the simulation result and adjusting the corresponding planned construction data based on the construction risk includes the following steps:
[0044] Performing risk level assessment on component collision and / or equipment conflict in the simulation results to obtain a construction risk level;
[0045] Determining whether the construction risk level is greater than a preset level threshold;
[0046] If the construction risk level is greater than or equal to the level threshold, an adjustment plan is generated, and the planned construction data corresponding to the component collision and / or the equipment conflict is adjusted according to the adjustment plan;
[0047] If the construction risk level is less than the level threshold, the planned construction data is not adjusted.
[0048] By adopting the above technical solution, the planned construction data of each construction department is formulated based on the preliminary measurements conducted by their respective staff. In the preliminary measurements, the measurement results may have certain errors due to the different measurers, which may eventually lead to the situation that different equipment from different departments may be planned to be installed in the same location. During the construction simulation process, such component collisions and / or equipment conflicts will be detected, and risk assessment will be conducted based on dimensions such as the scope of the conflict or collision, the type of equipment in conflict, and the size of the equipment in conflict. The construction risk level is assessed and then the construction risk level is judged based on the preset level threshold. If the level threshold is exceeded, it means that the component collision and / or equipment conflict is more serious and may affect the normal progress of the construction. Therefore, an adjustment plan needs to be generated to adjust the planned construction data corresponding to the equipment in conflict or conflict. If the level threshold is not exceeded, it means that the impact of the collision or conflict is small, and the construction personnel can coordinate and resolve it on site, so there is no need to adjust the planned construction data.
[0049] Optionally, optimizing and adjusting the initial BIM model to obtain the on-site BIM model comprises the following steps:
[0050] importing site drawings of the construction site;
[0051] Optimizing the initial BIM model according to the on-site drawings;
[0052] The granularity of the initial BIM model after model optimization is adjusted to obtain the on-site BIM model.
[0053] By adopting the above technical solution and combining the on-site drawings of the construction site to further optimize the initial BIM model, it is beneficial to improve the accuracy of the BIM model in details. The granularity of the optimized BIM model is then adjusted so that the BIM model can meet the subsequent construction simulation conditions.
[0054] In the second aspect, the present application also provides a mechanical and electrical construction system based on BIM technology, including a memory, a processor, and a program stored on the memory and executable on the processor, which can implement the mechanical and electrical construction method based on BIM technology as described in the first aspect when loaded and executed by the processor.
[0055] By adopting the above technical solution, through the program call, the construction site is 3D scanned by 3D scanning technology to construct the initial BIM model of the construction site. In order to reduce the error of the BIM model in the subsequent construction simulation process, before applying the initial BIM model, it is necessary to optimize and adjust the initial BIM model to obtain the on-site BIM model. Then, the construction priority is assigned to the construction department according to the planned construction data of the construction department, the planned construction data is imported into the on-site BIM model, and the construction simulation is performed in the BIM model according to the construction priority. The simulation results are analyzed for construction risks, and the planned construction data is adjusted in combination with the analyzed construction analysis. Therefore, even if there are many construction departments, the construction process can be simulated and the construction plan can be adjusted through BIM technology, thereby effectively avoiding most of the problems that arise in subsequent construction.
[0056] In summary, the present application includes at least one of the following beneficial technical effects:
[0057] 1. Carry out construction simulation in the BIM model, conduct construction risk analysis on the simulation results, and adjust the planned construction data based on the analyzed construction analysis. Therefore, even if there are many construction departments, the construction process can be simulated and the construction plan can be adjusted through BIM technology, thus effectively avoiding most problems that may arise in subsequent construction.
[0058] 2. During the on-site construction process, embedded parts need to be constructed first. Therefore, we first judge based on the total amount of embedded parts of each construction department, and temporarily assign a higher priority to the construction department with a large amount of embedded parts, and temporarily assign a lower priority to the construction department with a small amount of embedded parts. After temporarily assigning the priority, we need to adjust the priority in combination with the number of construction personnel and equipment construction data. BRIEF DESCRIPTION OF THE DRAWINGS
[0059] Figure 1 It is a flow chart of a mechanical and electrical construction method based on BIM technology in one embodiment of the present application.
[0060] Figure 2 It is a flowchart of allocating construction priorities to construction departments according to planned construction data in one embodiment of the present application.
[0061] Figure 3 This is a flowchart of adjusting construction priority in combination with the number of construction personnel and equipment construction data according to one embodiment of the present application.
[0062] Figure 4 It is a flowchart of retrieving historical construction data of a device type according to one embodiment of the present application.
[0063] Figure 5 It is a flowchart of one of the embodiments of the present application for performing construction simulation through an on-site BIM model and obtaining simulation results.
[0064] Figure 6 It is a flowchart of analyzing construction risks and adjusting planned construction data according to simulation results in one embodiment of the present application.
[0065] Figure 7 It is a flowchart of optimizing and adjusting the initial BIM model according to one embodiment of the present application. DETAILED DESCRIPTION
[0066] The following is combined with Figure 1-7 This application is described in further detail.
[0067] The embodiment of the present application discloses a mechanical and electrical construction method based on BIM technology.
[0068] Reference Figure 1 , the electromechanical construction method based on BIM technology includes the following steps:
[0069] 101, build the initial BIM model of the construction site based on 3D scanning technology.
[0070] Among them, the scanning points are calibrated according to the structure of the construction site, and the scanning equipment is used to perform infrared 3D scanning of the construction site at the scanning points, and the initial BIM model of the construction site is constructed according to the 3D scanning results.
[0071] 102, optimizing and adjusting the initial BIM model to obtain an on-site BIM model.
[0072] 103, respectively obtain the planned construction data of all construction departments, and assign construction priorities to all construction departments according to all the planned construction data.
[0073] 104 , performing construction simulation based on the on-site BIM model and according to the planned construction data and the construction priority to obtain a simulation result.
[0074] 105. Analyze the construction risk according to the simulation result, and adjust the corresponding planned construction data based on the construction risk.
[0075] The implementation principle of this embodiment is:
[0076] The construction site is 3D scanned using 3D scanning technology to construct an initial BIM model of the construction site. In order to reduce the errors in the subsequent construction simulation process, the initial BIM model needs to be optimized and adjusted before it is applied to obtain the on-site BIM model. Then, construction priorities are assigned to the construction departments based on their planned construction data, and the planned construction data is imported into the on-site BIM model. Construction simulation is performed in the BIM model based on the construction priorities, and construction risk analysis is performed on the simulation results. The planned construction data is adjusted based on the analyzed construction analysis. Therefore, even if there are many construction departments, the construction process can be simulated and the construction plan can be adjusted through BIM technology, thereby effectively avoiding most of the problems that may arise in subsequent construction.
[0077] exist Figure 1 In step 103 of the illustrated embodiment, the planned construction data includes the number of construction personnel, embedded parts construction data, and equipment construction data. The construction priority is temporarily allocated according to the total number of embedded parts in the planned construction data of each construction department, and then the construction priority is subsequently adjusted in combination with the total number of construction personnel and equipment construction data in the planned construction data. Figure 2 The illustrated embodiment is described in detail.
[0078] Reference Figure 2 , allocating construction priorities to construction departments based on planned construction data includes the following steps:
[0079] 201, counting the total amount of embedded parts in the embedded parts construction data.
[0080] Among them, embedded parts include pipe network embedded parts, equipment embedded parts, line embedded parts, etc. The preset embedded parts keywords are used to search in the embedded parts construction data, the number of embedded parts of each type is retrieved, and then the total number of embedded parts is summarized.
[0081] 202, determine whether the total amount of the embedded parts is greater than a preset first total amount threshold, if so, execute step 203; if not, execute step 204.
[0082] 203, assigning a first construction priority to the corresponding construction department.
[0083] 204, determining whether the total amount of the embedded parts is greater than a preset second total amount threshold, if so, executing step 205; if not, executing step 206.
[0084] The second total amount threshold is smaller than the first total amount threshold.
[0085] 205, assigning a second construction priority to the corresponding construction department.
[0086] 206 , assigning the third construction priority to the corresponding construction department.
[0087] Among them, the first construction priority is the highest priority, the second construction priority is lower than the first construction priority, and the third construction priority is the lowest priority and lower than the second construction priority.
[0088] 207 , adjusting the construction priority assigned by the construction department in combination with the number of construction personnel and the equipment construction data.
[0089] The implementation principle of this embodiment is:
[0090] During the on-site construction process, embedded parts need to be constructed first. Therefore, we first judge based on the total amount of embedded parts of each construction department, and temporarily assign a higher priority to the construction department with a large amount of embedded parts, and temporarily assign a lower priority to the construction department with a small amount of embedded parts. After temporarily assigning the priority, we need to adjust the priority based on the number of construction personnel and equipment construction data.
[0091] exist Figure 2 In step 207 of the illustrated embodiment, the equipment construction data includes equipment type and total equipment quantity. The planned construction period of the corresponding equipment type is calculated based on the number of construction personnel and total equipment quantity in the planned construction data. The historical average construction period of the equipment type is analyzed and judged, so as to adjust the construction priority of the construction department corresponding to the equipment type. Figure 3 The illustrated embodiment is described in detail.
[0092] Reference Figure 3, adjusting the construction priority based on the number of construction personnel and equipment construction data includes the following steps:
[0093] 301, searching the equipment type through Internet technology to obtain historical construction data of the equipment type.
[0094] 302, using the number of construction personnel as a calculation standard, analyzing and calculating the historical construction data to obtain a historical average construction period.
[0095] Among them, the search results usually include multiple historical construction data, and the historical construction data mainly include construction period and number of construction personnel. The historical construction period of each historical construction data is calculated based on the number of construction personnel in the planned construction data corresponding to the equipment type. For example, assuming that the number of construction personnel X is 20, the construction period D1 of the historical construction data P1 is 30 days, and the number of construction personnel S1 is 10. Since the total construction volume remains unchanged, the historical construction period M1 of P1 calculated based on X can be calculated by the following formula: M1=D1S1 / X=15 days. According to the above method, the historical construction period of all historical construction data is calculated, and then the average value of all historical construction periods is calculated as the historical average construction period.
[0096] 303, calculating a planned construction period based on the total amount of equipment and the number of construction personnel.
[0097] Among them, the calculation of the planned construction period also requires the average daily construction volume of a single person, and the average daily construction volume of a single person is determined according to the construction standards of different equipment.
[0098] 304, determine whether the planned construction period is greater than the historical average construction period, if so, execute step 305; if not, execute step 306.
[0099] 305. Improve the construction priority of the corresponding construction department.
[0100] 306, calculating the period difference between the planned construction period and the historical average construction period.
[0101] Among them, the cycle difference is the absolute value of the difference between the planned construction cycle and the historical average construction cycle.
[0102] 307 , determining whether the period difference is greater than a preset difference threshold, if so, executing step 308 ; if not, executing step 309 .
[0103] 308, reduce the construction priority of the corresponding construction department.
[0104] 309, the construction priority of the corresponding construction department will not be adjusted.
[0105] The implementation principle of this embodiment is:
[0106] According to the equipment types that each department needs to carry out construction, a search is conducted on the Internet to retrieve the historical construction data of the same equipment type, so as to analyze and calculate the historical average construction period of the equipment type, and then calculate the planned construction period based on the total amount of equipment and the number of construction personnel in the planned construction data. If the difference between the planned construction period and the historical average construction period is large, it means that there is a serious deviation between the construction plan and the actual situation. Therefore, it is necessary to reduce the construction priority of the corresponding construction department to reduce the impact of the construction process of the construction department on the overall construction plan; if the difference between the planned construction period and the historical average construction period is small, it means that the construction plan of the corresponding construction department is more in line with reality, so there is no need to adjust the construction priority of the construction department.
[0107] exist Figure 3 In step 301 of the illustrated embodiment, a crawler script may be created according to the equipment type to retrieve data on the Internet, and the retrieved data may be screened to select historical construction data that is useful for data analysis. Figure 4 The illustrated embodiment is described in detail.
[0108] Reference Figure 4 , retrieving historical construction data of equipment type includes the following steps:
[0109] 401, creating a crawler script using the device type as a keyword.
[0110] 402 , retrieve associated data related to the device type from the Internet through the crawler script.
[0111] Among them, crawler scripts are mainly used to search from equipment-related web pages and engineering-related web pages.
[0112] 403 , filtering the associated data based on the equipment construction data corresponding to the equipment type, and obtaining the historical construction data of the equipment type.
[0113] Among them, the same equipment may be used in different project fields, and the equipment construction data in the planned construction data can reflect the core project category of the planned construction project. Therefore, by filtering the retrieved related data through the equipment construction data, the historical construction data related to the planned construction project can be filtered out.
[0114] The implementation principle of this embodiment is:
[0115] The associated data related to the equipment type is retrieved from the Internet through the crawler script. The associated data contains a large amount of data that is not related to the current construction. Therefore, it is necessary to filter the associated data according to the equipment construction data in the planned construction data, and use the filtered data as the historical construction data of the equipment type.
[0116] exist Figure 1 In step 104 of the illustrated embodiment, the environment and components required for construction simulation are created according to the planned construction data, and then the simulation order of the components is calibrated according to the construction priority. Finally, a simulation process is generated to perform construction simulation in the on-site BIM model to obtain a simulation result. Figure 5 The illustrated embodiment is described in detail.
[0117] Reference Figure 5 , the construction simulation and simulation results obtained through the on-site BIM model include the following steps:
[0118] 501, importing the planned construction data into the on-site BIM model.
[0119] 502 , creating an environment style and processing components based on the planned construction data.
[0120] 503 , calibrate a simulation order for the processing components according to the construction priority.
[0121] 504 , generating a simulation process in the simulation order based on the environment style and the processed parts, and performing construction simulation in the on-site BIM model according to the simulation process to obtain a simulation result.
[0122] The implementation principle of this embodiment is:
[0123] In the on-site BIM model, the model simulation environment style and the processing components required for simulation are created according to the planned construction data of all construction departments. Each construction department has sorted the construction priorities according to the planned construction data. Therefore, the processing components required by each construction department are calibrated for simulation order according to the construction priority. Finally, in the on-site BIM model, a simulation process is generated with the environment style and the processing components calibrated with the simulation order, and construction simulation is carried out according to the simulation process in the on-site BIM model to obtain a simulation result that simulates the entire construction process.
[0124] exist Figure 1 In step 105 of the illustrated embodiment, during the construction simulation, due to the conflict of planned construction data, component collision and / or equipment conflict may occur in the BIM model, and it is necessary to assess the risk level of the collision or conflict, and then determine whether it is necessary to generate an adjustment plan to adjust the planned construction data according to the size of the construction risk level. Figure 6 The illustrated embodiment is described in detail.
[0125] Reference Figure 6 , analyzing construction risks and adjusting planned construction data based on simulation results include the following steps:
[0126] 601 , assessing the risk level of component collision and / or equipment conflict in the simulation result to obtain a construction risk level.
[0127] During the construction simulation, such component collisions and / or equipment conflicts will be detected, and risk assessment will be conducted based on dimensions such as the scope of the conflict or collision, the type of equipment causing the conflict, and the size of the equipment causing the conflict, to determine the construction risk level.
[0128] 602, determine whether the construction risk level is greater than a preset level threshold, if so, execute step 603; if not, execute step 604.
[0129] 603 , generating an adjustment plan, and adjusting the planned construction data corresponding to the component collision and / or the equipment conflict according to the adjustment plan.
[0130] Among them, the target of the adjustment plan is the parts or equipment that have collision conflicts. Through adjustment, the scope and size of the collision conflicts can be reduced, thereby reducing the construction risk level.
[0131] 604: Do not adjust the planned construction data.
[0132] The implementation principle of this embodiment is:
[0133] The planned construction data of each construction department is formulated based on the preliminary measurements conducted by their respective staff. In the preliminary measurements, the measurement results may have certain errors due to the different surveyors, which may eventually lead to the situation that different equipment from different departments may be planned to be installed in the same location. During the construction simulation process, such component collisions and / or equipment conflicts will be detected, and risk assessment will be conducted based on dimensions such as the scope of the conflict or collision, the type of equipment in conflict, and the size of the equipment in conflict. The construction risk level will be assessed and then judged based on the preset level threshold. If the level threshold is exceeded, it means that the component collision and / or equipment conflict is more serious, which may affect the normal progress of the construction. Therefore, an adjustment plan needs to be generated to adjust the planned construction data corresponding to the equipment in conflict or conflict; if the level threshold is not exceeded, it means that the impact of the collision or conflict is small, and the construction personnel can coordinate and resolve it on site, so there is no need to adjust the planned construction data.
[0134] exist Figure 1In step 102 of the illustrated embodiment, before the BIM model is used for construction simulation, the BIM model needs to be optimized and adjusted to meet the conditions for construction simulation. Figure 7 The illustrated embodiment is described in detail.
[0135] Reference Figure 7 , optimizing and adjusting the initial BIM model includes the following steps:
[0136] 701, importing the on-site drawings of the construction site.
[0137] 702 : Optimize the initial BIM model according to the on-site drawing.
[0138] 703, adjusting the granularity of the initial BIM model after the model optimization to obtain the on-site BIM model.
[0139] The implementation principle of this embodiment is:
[0140] Further optimization of the initial BIM model in combination with the on-site drawings of the construction site is conducive to improving the accuracy of the BIM model in details. The granularity of the optimized BIM model is then adjusted so that the BIM model can meet the subsequent construction simulation conditions.
[0141] The present application also discloses a BIM-based electromechanical construction system, including a memory, a processor, and a program stored in the memory and executable on the processor, wherein the program can be loaded and executed by the processor to implement the following Figure 1-7 Mechanical and electrical construction method based on BIM technology.
[0142] The implementation principle of this embodiment is:
[0143] Through the program call, the construction site is 3D scanned by 3D scanning technology to build the initial BIM model of the construction site. In order to reduce the errors of the BIM model in the subsequent construction simulation process, the initial BIM model needs to be optimized and adjusted before it is applied to obtain the on-site BIM model. Then, the construction priority is assigned to the construction department according to the planned construction data of the construction department, and the planned construction data is imported into the on-site BIM model. The construction simulation is performed in the BIM model according to the construction priority, and the construction risk analysis is performed on the simulation results. The planned construction data is adjusted in combination with the analyzed construction analysis. Therefore, even if there are many construction departments, the construction process can be simulated and the construction plan can be adjusted through BIM technology, thereby effectively avoiding most of the problems that arise in subsequent construction.
[0144] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A mechanical and electrical construction method based on BIM technology, characterized in that: The steps include: Build an initial BIM model of the construction site based on 3D scanning technology; Optimizing and adjusting the initial BIM model to obtain an on-site BIM model; Obtain the planned construction data of all construction departments respectively, and assign construction priorities to all construction departments according to all the planned construction data; Perform construction simulation based on the on-site BIM model and according to the planned construction data and the construction priority to obtain simulation results; Analyzing construction risks according to the simulation results, and adjusting corresponding planned construction data based on the construction risks; The planned construction data includes the number of construction personnel, embedded parts construction data and equipment construction data, and the allocation of construction priorities to all construction departments according to all planned construction data includes the following steps: Counting the total amount of embedded parts in the embedded parts construction data; Determining whether the total amount of the embedded parts is greater than a preset first total amount threshold; If the total amount of the embedded parts is greater than the first total amount threshold, assigning a first construction priority to the corresponding construction department; If the total amount of the embedded parts is not greater than the first total amount threshold, determining whether the total amount of the embedded parts is greater than a preset second total amount threshold, and the second total amount threshold is less than the first total amount threshold; If the total amount of the embedded parts is greater than the second total amount threshold, a second construction priority is allocated to the corresponding construction department, and the second construction priority is lower than the first construction priority; If the total amount of the embedded parts is not greater than the second total amount threshold, a third construction priority is allocated to the corresponding construction department, and the third construction priority is lower than the second construction priority; Adjusting the construction priority assigned by the construction department in combination with the number of construction personnel and the equipment construction data; The equipment construction data includes equipment type and total equipment quantity, and the adjusting the construction priority of the construction department in combination with the number of construction personnel and the equipment construction data includes the following steps: Retrieving the equipment type through Internet technology to obtain historical construction data of the equipment type; Taking the number of construction personnel as the calculation standard, the historical construction data is analyzed and calculated to obtain the historical average construction period; Calculate the planned construction period based on the total amount of equipment and the number of construction personnel; Determining whether the planned construction period is greater than the historical average construction period; If the planned construction period is longer than the historical average construction period, the construction priority of the corresponding construction department is increased; If the planned construction period is not greater than the historical average construction period, then the period difference between the planned construction period and the historical average construction period is calculated; Determining whether the period difference is greater than a preset difference threshold; If the period difference is greater than the difference threshold, the construction priority of the corresponding construction department is reduced; If the cycle difference is not greater than the difference threshold, the construction priority of the corresponding construction department is not adjusted.
2. The electromechanical construction method based on BIM technology according to claim 1 is characterized in that: The searching of the equipment type by Internet technology to obtain the historical construction data of the equipment type comprises the following steps: Create a crawler script using the device type as a keyword; Retrieving associated data related to the device type from the Internet through the crawler script; The associated data is filtered based on the equipment construction data corresponding to the equipment type to obtain the historical construction data of the equipment type.
3. The electromechanical construction method based on BIM technology according to claim 1 is characterized in that: The construction simulation is performed based on the on-site BIM model and according to the planned construction data and the construction priority to obtain the simulation result, which comprises the following steps: Importing the planned construction data into the on-site BIM model; creating an environment style and processing components based on the planned construction data; calibrating a simulation order for the processing components according to the construction priority; A simulation process is generated based on the environment style and the processed parts in the simulation order, and a construction simulation is performed in the on-site BIM model according to the simulation process to obtain a simulation result.
4. The electromechanical construction method based on BIM technology according to claim 1, characterized in that: Analyzing the construction risk according to the simulation result and adjusting the corresponding planned construction data based on the construction risk includes the following steps: Performing risk level assessment on component collision and / or equipment conflict in the simulation results to obtain a construction risk level; Determining whether the construction risk level is greater than a preset level threshold; If the construction risk level is greater than or equal to the level threshold, an adjustment plan is generated, and the planned construction data corresponding to the component collision and / or the equipment conflict is adjusted according to the adjustment plan; If the construction risk level is less than the level threshold, the planned construction data is not adjusted.
5. The electromechanical construction method based on BIM technology according to claim 1 is characterized in that: Optimizing and adjusting the initial BIM model to obtain the on-site BIM model comprises the following steps: importing site drawings of the construction site; Optimizing the initial BIM model according to the on-site drawings; The granularity of the initial BIM model after model optimization is adjusted to obtain the on-site BIM model.
6. A mechanical and electrical construction system based on BIM technology, characterized in that: It includes a memory, a processor, and a program stored in the memory and executable on the processor. When the program is loaded and executed by the processor, the electromechanical construction method based on BIM technology as described in any one of claims 1 to 5 can be implemented.