A steel-concrete composite steel truss bridge construction method and steel truss bridge

During the construction of the steel-concrete composite bridge, the use of limiters and jacks to adjust the closing mouth combined with temperature changes solves the problems of cumbersome closing procedures and uneven stress, and achieves the uniformity of stress on the steel truss beams and the release of the internal force of the rods after closing. Deformation is avoided.

CN114457669BActive Publication Date: 2024-10-011ST ENG OF CHINA ZHONGTIE MAJORBRIDGE GROUP +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210032134.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-01-12
Publication Date
2024-10-01
Estimated Expiration
2042-01-12

AI Technical Summary

Technical Problem

The closing process of the steel-concrete composite bridge is cumbersome and the steel truss beams are unevenly stressed after closing, resulting in the problem of rod deformation.

Method used

Use limit devices and jacks in combination with temperature changes to adjust the width and position of the closure. Use temperature changes to make the width of the closure equal to the length of the connecting section to complete the closure. Shear nails and rubber strips are used when laying the concrete bridge deck. Make sure the connection is tight.

Benefits of technology

The closing process is simplified, the internal force of the steel truss beam is released, ensuring uniformity of stress under later loads and avoiding deformation of the members.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114457669B_ABST
    Figure CN114457669B_ABST
Patent Text Reader

Abstract

A construction method of a steel-concrete composite steel truss bridge and a steel truss bridge, which relate to the technical field of bridge construction, and include the following steps: erecting a steel truss on a main pier, and when the steel truss is erected to the joint opening, a limit device is respectively provided on both sides of a pad stone at the top of a main pier below each segment of the steel truss; in combination with temperature changes, the position of each segment of the steel truss is adjusted by a limit device and a jack, so that the width and position of each joint opening meet the design requirements; hoisting the connecting section to the joint opening, and when the width of the joint opening is the same as the length of the connecting section under the influence of the temperature, the connecting section is spliced ​​to complete the jointing. During the jointing construction, the present application has a simple procedure, and the jointing is achieved by using the temperature, which can release the internal force of the rods of the steel truss, and the steel truss is evenly stressed, avoiding deformation of the rods. Therefore, the present application can solve the problem that the jointing procedure of the steel-concrete composite steel truss is cumbersome, and the steel truss is unevenly stressed after the jointing.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of bridge construction, and in particular to a construction method for a steel-concrete composite steel truss bridge and a steel truss bridge. Background Art

[0002] At present, steel-concrete composite bridges are widely used in bridges. Steel-concrete composite beam bridges have the advantages of convenient construction, strong integrity, and good economic benefits. They are suitable for large-span bridges such as those across rivers. The construction of steel-concrete composite beam bridges is difficult, and most of them are thin-walled concrete high-altitude operations. Among them, for the closure of steel-concrete composite bridges, the existing technology requires the use of a jacking device to move the bridge longitudinally. The process is cumbersome and difficult, and there are internal forces in the rods of the steel trusses after the closure, which leads to uneven force on the steel trusses and even deformation of the rods when loads are applied to the steel trusses in the later stage. Summary of the invention

[0003] The embodiments of the present application provide a steel-concrete composite steel truss bridge construction method and a steel truss bridge to solve the problem that the jointing process of the steel-concrete composite steel truss is complicated and the steel truss is subjected to uneven force after jointing.

[0004] Provided is a construction method for a steel-concrete composite steel truss bridge, wherein the steel truss bridge has at least one closure during construction, and the construction method for the steel truss bridge comprises the following steps:

[0005] S1. Steel trusses are erected on the main piers, and a cushion stone is arranged on the top of each pier column of each main pier. When the steel trusses are erected to the joint, two limit devices are arranged on the top of each pier column of a main pier under each segment of the steel trusses, and the two limit devices are distributed on both sides of the cushion stone along the longitudinal direction of the bridge. The limit devices are fixedly connected to the bottom of the steel trusses and a preset distance is left between them and the cushion stone;

[0006] S2. At the highest temperature of the day, a jack is set between at least one limit device and the corresponding pad stone, and the jack is propped open as the temperature drops, so that the steel truss connected to the limit device is displaced;

[0007] S3. Repeat step S2 until the width and position of each closure meet the design requirements;

[0008] S4. Jacks are used to support the two limit devices and cushion stones at the top of each pier column of the same main pier, and the connecting section is hoisted to the joint. When the width of the joint is affected by the temperature and is the same as the length of the connecting section, the connecting section is spliced ​​to complete the joint.

[0009] Furthermore, the step S2 further includes:

[0010] When the width of the joint is smaller than the design requirement, a jack is arranged below the steel truss whose end face toward the joint exceeds the preset position and between the limit device and the pad stone away from the joint. The jack is opened and the steel truss moves in the direction away from the joint.

[0011] Furthermore, the step S2 further includes:

[0012] When the width of the joint is greater than the design requirement, a jack is set below the steel truss whose end face facing the joint has not reached the preset position and between the limit device and the pad stone adjacent to the joint. The jack is opened and the steel truss moves toward the joint.

[0013] Furthermore, the step S2 further includes:

[0014] When the width of the joint meets the design requirements, but the steel trusses at both ends of the joint are offset from the preset position, a jack is set below the steel truss whose end face facing the joint exceeds the preset position and between the limit device far away from the joint and the corresponding pad stone; at the same time, a jack is set below the steel truss whose end face facing the joint does not reach the preset position and between the limit device adjacent to the joint and the pad stone; the jacks are opened at the same time, and the two steel trusses move toward the preset position.

[0015] Furthermore, the step S1 further includes:

[0016] Before the steel trusses are erected, two temporary piers are set between the spans of each steel truss. When the steel trusses are erected to the temporary piers, the ends of the beams are placed on the tops of the temporary piers.

[0017] Furthermore, the method further comprises the steps of:

[0018] Through holes are provided in the multiple concrete bridge decks, and during the closure of the steel truss beams, multiple shear nails are provided on the top surface of the upper chord of the erected steel truss beam in the longitudinal direction of the bridge, and the positions and areas of the shear nails match those of the multiple through holes;

[0019] A pair of rubber strips are arranged on the top surface of each upper chord rod, the two rubber strips are arranged along the two side edges of the upper chord rod, and a plurality of shear nails are arranged between the two rubber strips;

[0020] A number of concrete bridge decks are laid, and a number of shear nails are inserted into a number of through holes. Mortar is first poured into the through holes to make the upper chord and the concrete bridge deck dense, and then concrete is poured into the through holes to form a steel-concrete composite steel truss bridge.

[0021] Furthermore, the steps also include:

[0022] When laying the concrete bridge deck, a distance is left between each two adjacent concrete bridge decks to form a wet joint. The pier tops in the negative bending moment area are lifted in turn, and the wet joints are poured to prestress the concrete bridge deck.

[0023] A steel-concrete composite steel truss bridge comprises:

[0024] Steel trusses are divided into multiple sections, each section includes multiple spans, and each section of the steel trusses is erected on the pad stone at the top of each pier column of the main pier, and there is a joint between each two adjacent sections of the steel trusses;

[0025] A limiting device, two of which are arranged on the top of each pier column of a main pier under each segment steel truss beam, and the two limiting devices are arranged on both sides of the pad stone along the longitudinal direction of the bridge, and each limiting device is fixedly connected to the bottom of the steel truss beam and has a preset distance between it and the pad stone;

[0026] A plurality of concrete bridge decks are laid on the top surface of the multi-segment steel trusses. Each concrete bridge deck is provided with at least one through hole, and concrete for connecting the steel trusses and the concrete bridge deck is poured in the through hole.

[0027] Furthermore, it also includes a plurality of temporary piers, which are arranged in pairs at the bottom of the steel trusses of different spans;

[0028] When the steel truss is erected to the temporary pier, the beam end is placed on the top of the temporary pier in the corresponding span.

[0029] Furthermore, the top surface of the upper chord of the steel truss girder in the longitudinal direction of the bridge is provided with a plurality of shear nails, each of which has a plurality of shear nails, and the positions and areas of the plurality of shear nails match the through holes of the plurality of concrete bridge decks;

[0030] Two pairs of rubber strips for positioning are provided on the upper chord in the longitudinal direction of the steel truss girder. One pair of rubber strips is provided on the top surface of one upper chord. The two rubber strips of each pair are provided along the two side edges of the upper chord and are respectively located outside the shear nails. Each rubber strip extends in the longitudinal direction of the bridge. Mortar for supporting the concrete bridge deck is poured between the two rubber strips.

[0031] When laying the concrete bridge deck, a plurality of shear nails are inserted into a plurality of through holes of the concrete bridge deck, and a wet joint is provided between every two adjacent concrete bridge decks.

[0032] The beneficial effects of the technical solution provided by this application include:

[0033] The embodiments of the present application provide a steel-concrete composite steel truss bridge construction method and a steel truss bridge. During the joint construction, the temperature changes are taken into consideration, and a limit device and a jack are used to make the width and position of each joint meet the design requirements. When installing the connecting section of the joint, the temperature changes are taken into consideration again to make the width of the joint equal to the length of the connecting section, and the joint is completed. Therefore, the steel-concrete composite steel truss bridge construction method and the steel-concrete composite steel truss bridge of the present application have simple procedures, and the joint is achieved by using the temperature, which can release the internal force of the rods of the steel truss, so that when a load is applied to the steel truss after the joint is later, the steel truss is evenly stressed, avoiding deformation of the rods. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0035] Figure 1 This is the overall structural diagram of the longitudinal bridge direction of this application;

[0036] Figure 2 This is a schematic diagram of the structure in the transverse direction of the bridge in this application;

[0037] Figure 3 This is a schematic diagram of the structure of the joint mouth of this application;

[0038] Figure 4 for Figure 4 A schematic diagram of the structure after the limit device is installed;

[0039] Figure 5 A top view schematic diagram of a concrete bridge deck in the transverse direction of the present application;

[0040] Figure 6 for Figure 1 Schematic diagram of the top view of the installation of shear nails and rubber strips on the top surface of the middle steel truss;

[0041] Reference numerals:

[0042] 1. Steel truss; 2. Main pier; 3. Closure; 4. Temporary pier; 5. Limiting device; 6. Concrete bridge deck; 61. Through hole; 7. Pad stone; 8. Rubber strip; 9. Wet joint; 10. Shear nail. DETAILED DESCRIPTION

[0043] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of this application.

[0044] The embodiment of the present application provides a construction method for a steel-concrete composite steel truss bridge, which can solve the problem that the jointing process of the steel-concrete composite steel truss is complicated and the steel truss is subjected to uneven force after the jointing.

[0045] like Figure 1 , Figure 2 , Figure 3 and Figure 4 As shown, a steel-concrete composite steel truss bridge according to an embodiment of the present application has at least one joint 3. The construction method of the steel-concrete composite steel truss bridge comprises the following steps:

[0046] S1. A steel truss 1 is erected on the main pier 2. A cushion stone 7 is arranged on the top of each pier column of each main pier 2. When the steel truss 1 is erected to the joint 3, two limit devices 5 are arranged on the top of each pier column of a main pier 2 under each segment of the steel truss 1. The two limit devices 5 are distributed on both sides of the cushion stone 7 along the longitudinal direction of the bridge. The limit devices 5 are fixedly connected to the bottom of the steel truss 1 and a preset distance is left between the limit devices 5 and the cushion stone 7. Specifically, the preset distance should be greater than the distance that the steel truss 1 deviates from the preset position, and the preset position is the design position of the steel truss 1.

[0047] S2. When the temperature is the highest in a day, a jack is arranged between at least one limiting device 5 and the corresponding pad stone 7. As the temperature drops, the jack is opened to cause displacement of the steel truss 1 connected to the limiting device 5.

[0048] S3, repeat the above step S2 until the width and position of each closure 3 meet the design requirements.

[0049] S4. Jacks are used to support the two limit devices 5 and the cushion stones 7 at the top of each pier column of the same main pier 2, and the connecting section is hoisted to the joint opening 3. When the width of the joint opening 3 is the same as the length of the connecting section due to the influence of temperature, the connecting section is spliced ​​to complete the joint.

[0050] Specifically, in the above step S1, the steel truss beam 1 can be erected symmetrically by means of a gantry crane cantilever, which ensures the balance of the mechanical properties of the steel truss beam 1 during the erection process.

[0051] Specifically, in the above step S1 , the steel truss beam 1 between each two adjacent main piers 2 is one span, and each segmental steel truss beam 1 includes multiple spans, that is, there may be multiple main piers 2 below each segmental steel truss beam 1 .

[0052] When the steel truss 1 has two sections and a joint 3, a limiting device 5 is provided on each pier column top of a main pier 2 below each section of the steel truss 1. The main pier 2 is preferably a main pier 2 adjacent to the joint 3, which can realize accurate positioning and adjustment of the steel truss 1 and the joint 3.

[0053] When the number of segments of the steel truss 1 is greater than two segments, for the steel truss 1 located in the two outermost segments, a limiting device 5 is installed on each pier column top of a main pier 2 below the steel truss 1 of the two segments. Similarly, the main pier 2 is preferably a main pier 2 adjacent to the joint 3, so that the steel truss 1 and the joint 3 can be accurately positioned and adjusted. For each segment of the steel truss 1 located in the middle, preferably, a limiting device 5 is installed on each pier column top of a main pier 2 in the middle position of each segment of the steel truss 1, so that during the adjustment of the steel truss 1 and the joint 3, the segment of the steel truss 1 maintains a balanced state.

[0054] Furthermore, in the above step S2, when the width of the closure opening 3 does not meet the design requirements, the specific adjustment steps further include the following:

[0055] When the width of the joint 3 is smaller than the design requirement, a jack is arranged under the steel truss 1 whose end face facing the joint 3 exceeds the preset position, and the jack is located between the limit device 5 and the cushion stone 7 away from the joint 3. The jack is opened and the steel truss 1 moves in the direction away from the joint 3.

[0056] When the width of the closure 3 is greater than the design requirement, a jack is set under the steel truss 1 whose end face facing the closure 3 has not reached the preset position, and the jack is located between the limit device 5 and the pad stone 7 adjacent to the closure 3. The jack is opened and the steel truss 1 moves toward the closure 3.

[0057] Furthermore, in the above step S2, when the width of the closure opening 3 meets the design requirements, but the position of the closure opening 3 does not meet the design requirements, the specific adjustment steps further include the following:

[0058] When the width of the closure 3 meets the design requirements, but the steel trusses 1 at both ends of the closure 3 are offset from the preset position, a jack is set under the steel truss 1 whose end face facing the closure 3 exceeds the preset position, and the jack is located between the limit device 5 away from the closure 3 and the corresponding pad stone 7; at the same time, a jack is also set under the steel truss 1 whose end face facing the closure 3 has not reached the preset position, and the jack is located between the limit device 5 and the pad stone 7 adjacent to the closure 3; two jacks are opened at the same time, and the two steel trusses 1 move toward the preset position.

[0059] Similarly, the above-mentioned preset position refers to the design position of the steel truss 1 .

[0060] Specifically, when the number of segments of the steel truss 1 is greater than two segments and has at least two joints 3: for the two outermost segment steel trusses 1, adjustments can be made according to the above steps, and for each segment steel truss 1 located in the middle, it can be known that each end of each segment steel truss 1 has a joint 3. When a segment steel truss 1 is biased toward or deviates from the joint 3 at one end, the width of the joint 3 is less than or greater than the design value, and it can also be adjusted according to the above steps.

[0061] It can be known that the above steps can not only make the width and position of each joint 3 meet the design requirements, but also the position of each segment steel truss 1 is the same as the design position, ensuring the accuracy of the entire bridge assumption. At the same time, during the displacement of the steel truss 1, the internal force of the rod of the steel truss 1 is released to a certain extent, avoiding the large internal force of the rod affecting the performance of the steel truss 1 after the steel truss 1 is closed.

[0062] Specifically, Figure 3 As shown, in the above step S4, since the connecting section of the joint 3 is a prefabricated component, the length of the connecting section may not match the width of the joint 3 under the influence of factors such as temperature or construction error. Therefore, when the width of each joint 3 meets the design requirements, the two limit devices 5 and the cushion stone 7 are supported by jacks to lock the width of the joint 3. Under the influence of temperature, the steel trusses 1 at the left and right ends of the joint 3 will be deformed by elongation or shortening as the temperature rises or falls. When the width of the joint 3 is the same as the width of the connecting section, the joint is completed by splicing the connecting sections.

[0063] In the above steps, when the temperature is the lowest in a day, the limiting device 5 away from the joint 3 can be supported against the pad stone 7 by a jack. When the temperature rises, the steel truss 1 extends toward the joint 3.

[0064] Furthermore, before the steel truss 1 is erected, two temporary piers 4 are set between the spans of each span of the steel truss 1. When the steel truss 1 is erected to the temporary piers 4, the beam ends are placed on the tops of the temporary piers 4. Specifically, the two temporary piers 4 of each span are evenly distributed to ensure the stability of the steel truss 1. During the construction process, jacks can be set on the tops of the temporary piers 4 to adjust the line shape and elevation of the steel truss 1 in time to ensure the erection accuracy. In addition, the temporary piers 4 can reduce the construction span, solving the problem of large deflection during erection due to the large span of the steel truss 1.

[0065] Further, such as Figure 3 As shown, the construction method of the steel-concrete composite steel truss bridge of the embodiment of the present application further includes opening a through hole 61 that passes through from top to bottom in a plurality of concrete bridge decks 6, and a through hole 61 is a shear groove. During the closure of the steel truss 1, a plurality of concrete bridge decks 6 are laid on the top surface of the erected steel truss 1. After laying, concrete is poured in each through hole 61 to form a steel-concrete composite steel truss bridge.

[0066] Specifically, the erection process of the concrete bridge deck 6 can be carried out simultaneously with the erection of the steel truss 1. This method can improve the construction efficiency and shorten the construction period. The concrete bridge deck 6 is erected by using a gantry crane, and the construction is precisely positioned.

[0067] Further, such as Figure 5 and Figure 6 As shown, before laying the concrete bridge deck 6, a plurality of shear nails 10 are arranged on the top surface of the upper chord of the erected steel truss 1 in the longitudinal direction of the bridge, and the positions and areas of the shear nails 10 match the positions and areas of the plurality of through holes 61. The number of shear nails 10 in each shear nail 10 can be determined according to actual conditions.

[0068] A pair of rubber strips 8 are arranged on the top surface of each upper chord rod. The two rubber strips 8 are arranged along the two side edges of the upper chord rod. The plurality of shear nails 10 on the top surface of each upper chord rod are located between the two rubber strips 8 .

[0069] When laying multiple concrete bridge decks 6, multiple shear nails 10 are inserted into multiple through holes 61, and mortar is first poured into each through hole 61 to make the upper chord and the concrete bridge deck 6 dense, and then concrete is poured into each through hole 61. Specifically, concrete is poured into the through hole 61 to combine the concrete with the shear nails 10, thereby completing the combination of the concrete bridge deck 6 and the steel truss 1.

[0070] In the above steps, when laying the concrete bridge deck 6, the concrete bridge deck 6 is connected to the steel truss 1 through the shear nails 10 and the concrete, which ensures the tightness of the connection between the concrete bridge deck 6 and the steel truss 1, which is beneficial to improving the overall bearing capacity of the bridge, and ensures the precise alignment of the concrete bridge deck 6 during the erection. Laying the rubber strip 8 and pouring the mortar before erection can control the erection elevation of the concrete bridge deck 6, and during the installation process, it can provide positioning points for the steel truss 1 and the concrete bridge deck 6, and also ensure the straightness of each prestressed pipe in the concrete bridge deck 6.

[0071] Further, such as Figure 5 As shown, when laying the concrete bridge deck 6, a distance is left between each two adjacent concrete bridge decks 6 to form a wet joint 9. Subsequently, the pier tops in the negative bending moment area are successively lifted and the wet joints 9 are poured. Finally, the concrete bridge deck 6 is prestressed.

[0072] Specifically, in the above steps, the steel truss 1 in the negative bending moment area is lifted in rounds, and the wet joint 9 is cast. The construction of the wet joint 9 is an aerial operation and is constructed by a hanging formwork method, which is convenient for construction.

[0073] Specifically, in the above steps, the concrete bridge deck 6 can be an ultra-thin structure made of high-performance concrete of C60. The prestressing construction of the concrete bridge deck 6 is divided into transverse prestressing construction and longitudinal prestressing construction. Among them, the transverse prestressing construction is an external cantilever tensioning construction, which can be completed on an external tensioning operation platform. The "extension sleeve + jack" form is adopted to solve the problem of high-altitude cantilever transverse prestressing construction. The longitudinal prestressing construction can be completed in the wet joint 9, and the special jack tensioning is adopted, and the prestressing tensioning construction can be carried out in a thin-walled small space.

[0074] The construction steps of the embodiment of the present application are as follows:

[0075] Step 1: Considering the construction period and design requirements, the steel truss 1 is divided into three sections for construction and has two joints 3. Three erection points and four erection surfaces are set up in the entire construction project. The steel truss 1 is symmetrically cantilevered using a gantry crane.

[0076] Step 2: Set up two temporary piers 4 between every two adjacent main piers 2 to reduce the span of the steel truss 1. When the steel truss 1 is erected to the position of the temporary pier 4, the top of the temporary pier 4 is densely cushioned and no longer pre-lifted, and the erection is continued according to the natural deflection of the erection. The cushion can be made of steel plates or concrete round cakes.

[0077] Step 3: Set a cushion stone 7 on the top of each pier column of each main pier 2. When the steel truss 1 is erected to the position of the main pier 2, use a jack to lift the top, and the end of the steel truss 1 is placed on the cushion stone 7. After the cushion stone 7 is removed, the installation of the support is completed.

[0078] Step 4: When the steel truss beam 1 is erected to the joint opening 3, the temporary pier 4 at the joint opening 3 is lifted, and the top of the temporary pier 4 reaches the designed elevation. Two limit devices 5 are installed on both sides of the cushion stone 7 of each pier column top of a main pier 2 located below the two outermost segmental steel trusses 1 and adjacent to the joint opening 3, and two limit devices 5 are installed on both sides of the cushion stone 7 of each pier column top of a main pier 2 located below a segmental steel truss beam 1 located in the middle position and in the middle.

[0079] Step 5: Compare the width and position of each joint 3 with the design drawings, and displace the steel truss 1 through the jacks and limit devices 5 under each segment steel truss 1 so that the width and position of each joint 3 meet the design requirements.

[0080] Step six: Measure the length of the connecting section used to connect the joint mouth 3. Since the steel truss 1 coming out of the joint mouth 3 will expand and contract with the rise and fall of the temperature, when the width of the joint mouth 3 is the same as the length of the connecting section, the jointing of the joint mouth 3 is completed. When closing the connecting section, first close the lower chord, then close the upper chord, and finally close the diagonal rod. The specific steps are: first rely on the temperature to close the lower chord stress-free, requiring high measurement accuracy, and must ensure that the relative mileage deviation of each lower chord is small. Preferably, the jointing of the lower chord is completed within half an hour. At this time, it should be ensured that the construction bracket, the number of personnel, the shear bearing capacity of the connector, etc. meet the requirements. After the lower chord is closed, the limit device 5 is immediately released, and finally the upper chord and the diagonal rod are closed in the same way to complete the jointing of the connecting section.

[0081] Step 7: When the steel truss 1 is erected to a certain length, a plurality of shear nails 10 are arranged on the two upper chords on the top surface of the erected steel truss 1, and a rubber strip 8 is arranged on the two longitudinal side edges of each upper chord. Subsequently, a plurality of concrete bridge panels 6 with through holes 61 are laid synchronously on the top surface of the erected steel truss 1. The positions and sizes of the plurality of shear nails 10 are the same as the through holes 61 of the plurality of concrete bridge panels 6, and the plurality of shear nails 10 are inserted into the plurality of through holes 61. The entire bridge deck is divided into a left section and a right section. A gap extending in the longitudinal direction of the bridge is left between the plurality of concrete bridge panels 6 on the left section and the plurality of concrete bridge panels 6 on the right section, forming a longitudinal wet joint 9. A distance is left between each two adjacent concrete bridge panels 6 on the left section or the right section, forming a transverse wet joint 9.

[0082] Step 6: After the steel trusses 1 are connected and the concrete bridge deck 6 is laid, the steel trusses 1 at the pier tops in the negative bending moment area are lifted in rounds, and the wet joints 9 in the negative bending moment area are constructed preferentially using the hanging formwork method.

[0083] Step 7: First, pour mortar into each through hole 61 to make the upper chord and the concrete bridge deck 6 dense, and then pour concrete into each through hole 61 to connect the concrete bridge deck 6 and the steel truss 1 into a whole, thereby completing the combination of the concrete bridge deck 6 and the steel truss 1.

[0084] Step 8: On the tensioning platform, the transverse prestressing is completed in the form of "jack + extension sleeve". In the longitudinal wet joint 9, a special jack is used to perform longitudinal prestressing to ensure that the concrete bridge deck 6 meets the requirements during the bridge construction phase.

[0085] The present application also provides a steel-concrete composite steel truss bridge, such as Figure 1 As shown, it includes a steel truss 1, a limiting device 5 and a concrete bridge deck 6.

[0086] The steel truss beam 1 has multiple sections, each section includes multiple spans, and the steel truss beam 1 of each span is erected on the pad stone 7 at the top of each pier column of the main pier 2. The steel truss beam 1 has at least one joint 3.

[0087] There are multiple limit devices 5, two of which are arranged on the top of each pier column of a main pier 2 under each segment steel truss 1, and two limit devices 5 are arranged on both sides of the pad stone 7 along the longitudinal bridge direction, and each limit device 5 is fixedly connected to the bottom of the steel truss 1 and has a preset distance from the pad stone 7. Specifically, the preset distance should be greater than the distance that the steel truss 1 deviates from the preset position, and the preset position refers to the design position of the steel truss 1.

[0088] There are multiple concrete bridge decks 6 laid on the top surface of the multi-segment steel truss 1. Each concrete bridge deck 6 is provided with at least one through hole 61. Concrete for connecting the steel truss 1 and the concrete bridge deck 6 is poured in the through hole 61.

[0089] Specifically, Figure 3 and Figure 4 As shown, the cushion stone 7 can be a cubic structure, and its bottom area can be smaller than the cross-sectional area of ​​the main pier 2. When it is necessary to adjust the width of the joint 3 and the position of the steel truss 1, the limit device 5 supports the cushion stone 7 through the jack to prevent the jack from damaging the main pier 2.

[0090] Specifically, when the steel truss 1 has two sections and a joint 3, a limiting device 5 is installed on each pier column top of a main pier 2 below each section of the steel truss 1. The main pier 2 is preferably a main pier 2 adjacent to the joint 3, which can realize accurate positioning and adjustment of the steel truss 1 and the joint 3.

[0091] When the number of segments of the steel truss 1 is greater than two segments, for the steel truss 1 located in the two outermost segments, a limiting device 5 is installed on each pier column top of a main pier 2 below them. Similarly, the main pier 2 is preferably a main pier 2 adjacent to the joint 3, which can achieve accurate positioning and adjustment of the steel truss 1 and the joint 3. For each segment of the steel truss 1 located in the middle, preferably, a limiting device 5 is installed on each pier column top of a main pier 2 in the middle of each segment of the steel truss 1, which can ensure the balance stability of the steel truss 1 in each segment.

[0092] Specifically, each of the above-mentioned limiting devices 5 can be a plate-shaped structure or a box-shaped structure, and each limiting device 5 has a stiffening plate to enhance the overall stability and firmness of the limiting device 5 .

[0093] Furthermore, it also includes a plurality of temporary piers 4, which are arranged in pairs at the bottom of the steel trusses 1 of different spans. When the steel trusses 1 are erected to the temporary piers 4, the beam ends are placed on the temporary piers 4 in the corresponding span. The two temporary piers 4 at the bottom of each span of the steel trusses 1 are evenly arranged to maintain the balance of the steel trusses 1. Specifically, a pad is provided at the top of each temporary pier 4, so that the bottom of the steel trusses 1 remains horizontal and the elevation of the steel trusses 1 can be adjusted. The pad can be a steel plate or a concrete cake, etc.

[0094] Further, such as Figure 5 and Figure 6 As shown, the top surface of the upper chord of the steel truss 1 in the longitudinal direction of the bridge is provided with a plurality of shear nails 10, each of which has a plurality of shear nails 10, and the positions and areas of the plurality of shear nails 10 match the through holes 61 of the plurality of concrete bridge decks 6. When laying the concrete bridge deck 6, the plurality of shear nails 10 are inserted into the plurality of through holes 61 of the concrete bridge deck 6.

[0095] Two pairs of rubber strips 8 for positioning the concrete bridge deck 6 are also provided on the top surface of the upper chord in the longitudinal direction of the steel truss 1. A pair of rubber strips 8 is provided on the top surface of an upper chord. The two rubber strips 8 of each pair are provided along the two side edges of the upper chord and are respectively located on the outside of a plurality of shear nails 10. Each rubber strip 8 extends in the longitudinal direction of the bridge. Mortar for positioning the concrete bridge deck 6 is poured between the two rubber strips 8.

[0096] During the process of laying a plurality of concrete bridge decks 6 , a wet joint 9 is provided between each two adjacent concrete bridge decks 6 , and concrete for connecting each two adjacent concrete bridge decks 6 is poured in the wet joint 9 .

[0097] Specifically, each shear nail 10 is located in the top surface of the corresponding upper chord and has a distance from the longitudinal edge of the upper chord. The number of shear nails 10 on each shear nail 10 can be set according to actual conditions. When laying the concrete bridge deck 6, the reserved through hole 61 is accurately aligned with the shear nail 10, and then concrete is poured in the through hole 61, so that the connection between the concrete bridge deck 6 and the steel truss 1 is more firmly established, and the precise alignment of the concrete bridge deck 6 during erection is ensured, and the corrugated pipe inside the concrete bridge deck 6 can be accurately aligned.

[0098] Specifically, laying rubber strips 8 and pouring mortar before erection can control the erection elevation of the concrete bridge deck 6. During the installation process, positioning points can be provided for the steel truss 1 and the concrete bridge deck 6, while also ensuring the straightness of the prestressed pipes in the concrete bridge deck 6.

[0099] Specifically, in this embodiment, the entire bridge deck is divided into a left span and a right span, and a gap extending in the longitudinal direction of the bridge is left between the multiple concrete bridge decks 6 located on the left span and the multiple concrete bridge decks 6 located on the right span, forming a longitudinal wet joint 9. And a distance is left between each two adjacent concrete bridge decks 6 located on the left span or the right span, forming a transverse wet joint 9. The wet joint 9 can help the concrete bridge deck 6 overcome the adverse effects of factors such as temperature shrinkage and uneven structural settlement. In other embodiments, the specific positions of the multiple concrete bridge decks 6 can be arranged according to actual needs or design requirements.

[0100] In the description of the present application, it should be noted that the terms "upper", "lower", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present application. Unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be a connection between the two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present application can be understood according to the specific circumstances.

[0101] It should be noted that, in this application, relational terms such as "first" and "second" are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the presence of other identical elements in the process, method, article or device including the elements.

[0102] The above description is only a specific implementation of the present application, so that those skilled in the art can understand or implement the present application. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein can be implemented in other embodiments without departing from the spirit or scope of the present application. Therefore, the present application will not be limited to the embodiments shown herein, but will conform to the widest range consistent with the principles and novel features applied for herein.

Claims

1. A construction method for a steel-concrete composite steel truss bridge, characterized in that: The steel truss bridge has at least one closure (3) during construction, and the method comprises the steps of: S1. A steel truss (1) is erected on the main pier (2), and a cushion stone (7) is arranged on the top of each pier column of each main pier (2). When the steel truss (1) is erected to the joint (3), two limit devices (5) are arranged on the top of each pier column of a main pier (2) below each segment of the steel truss (1), and the two limit devices (5) are distributed on both sides of the cushion stone (7) along the longitudinal direction of the bridge. The limit devices (5) are fixedly connected to the bottom of the steel truss (1) and a preset distance is left between the limit devices (5) and the cushion stone (7); S2. When the temperature is the highest in a day, a jack is set between at least one limit device (5) and the corresponding pad stone (7), and the jack is opened as the temperature decreases, so that the steel truss (1) connected to the limit device (5) is displaced; S3. Repeat step S2 until the width and position of each closure (3) meet the design requirements; S4. The two stoppers (5) and the cushion stone (7) at the top of each pier column of the same main pier (2) are supported by jacks, and the connecting section is hoisted to the joint opening (3). When the width of the joint opening (3) is the same as the length of the connecting section due to the influence of the temperature, the connecting section is spliced ​​to complete the joint; The method further comprises the steps of: A plurality of concrete bridge decks (6) are provided with through holes (61) which penetrate vertically, and during the process of closure of the steel truss beam (1), a plurality of shear nails (10) are arranged on the top surface of the upper chord of the erected steel truss beam (1) in the longitudinal direction of the bridge, wherein the positions and areas of the shear nails (10) match those of the plurality of through holes (61); A pair of rubber strips (8) are arranged on the top surface of each upper chord rod, the two rubber strips (8) are arranged along the two side edges of the upper chord rod, and a plurality of shear nails (10) are located between the two rubber strips (8); Laying a plurality of concrete bridge decks (6), and inserting a plurality of shear nails (10) into a plurality of through holes (61), first pouring mortar into the through holes (61) to make the upper chord and the concrete bridge deck (6) compact, and then pouring concrete into the through holes (61) to form a steel-concrete composite steel truss bridge; The splicing and connecting sections are completed by closure, specifically including: The lower chord is closed without stress by temperature, and the closing of the lower chord is completed within half an hour; After the lower chord is closed, the limiting device (5) is immediately released; The upper chord and the diagonal bars are connected in turn without stress by temperature, and the connection of the upper chord and the diagonal bars is completed within half an hour; The step S2 further comprises: When the width of the joint opening (3) is smaller than the design requirement, a jack is arranged between a limit device (5) and a cushion stone (7) below the steel truss (1) whose end surface facing the joint opening (3) exceeds the preset position and is away from the joint opening (3), and the jack is opened, and the steel truss (1) moves in a direction away from the joint opening (3); When the width of the joint opening (3) is greater than the design requirement, a jack is arranged below the steel truss (1) whose end surface facing the joint opening (3) has not reached the preset position and between the limit device (5) and the cushion stone (7) adjacent to the joint opening (3), and the jack is opened, so that the steel truss (1) moves toward the joint opening (3); When the width of the joint (3) meets the design requirements, but the steel trusses (1) at both ends of the joint (3) deviate from the preset position, a jack is set below the steel truss (1) whose end face toward the joint (3) exceeds the preset position and between the limiting device (5) far away from the joint (3) and the corresponding cushion stone (7); at the same time, a jack is set below the steel truss (1) whose end face toward the joint (3) does not reach the preset position and between the limiting device (5) and the cushion stone (7) adjacent to the joint (3); the jacks are simultaneously opened, and the two steel trusses (1) move toward the preset position.

2. The steel-concrete composite steel truss bridge construction method according to claim 1, characterized in that: The step S1 further comprises: Before the steel truss beam (1) is erected, two temporary piers (4) are arranged between the spans of each steel truss beam (1); when the steel truss beam (1) is erected to the temporary pier (4), the beam end is placed on the top of the temporary pier (4).

3. The steel-concrete composite steel truss bridge construction method according to claim 1, characterized in that: The steps also include: When laying the concrete bridge deck (6), a distance is left between each two adjacent concrete bridge decks (6) to form a wet joint (9), and the pier tops in the negative bending moment area are successively lifted and the wet joints (9) are poured to perform prestressing construction on the concrete bridge deck (6).

4. A steel-concrete composite steel truss bridge based on the method of claim 1, characterized in that: include: The steel truss beam (1) has a plurality of sections, each section includes a plurality of spans, each section of the steel truss beam (1) is erected on a pad stone (7) at the top of each pier column of the main pier (2), and a joint (3) is provided between each two adjacent sections of the steel truss beam (1); A limiting device (5), two limiting devices (5) are arranged on the top of each pier column of a main pier (2) below each segment steel truss beam (1), and the two limiting devices (5) are arranged on both sides of the cushion stone (7) along the longitudinal direction of the bridge, and each limiting device (5) is fixedly connected to the bottom of the steel truss beam (1) and a preset distance is left between the limiting device (5) and the cushion stone (7); A plurality of concrete bridge decks (6) are laid on the top surface of the multi-segment steel truss (1), each of the concrete bridge decks (6) being provided with at least one through hole (61), and concrete for connecting the steel truss (1) and the concrete bridge deck (6) is poured in the through hole (61); The top surface of the upper chord of the steel truss (1) in the longitudinal direction of the bridge is provided with a plurality of shear nails (10), each of which has a plurality of shear nails (10), and the positions and areas of the plurality of shear nails (10) match the through holes (61) of the plurality of concrete bridge decks (6); The upper chord of the steel truss (1) in the longitudinal direction of the bridge is provided with two pairs of rubber strips (8) for positioning, wherein one pair of rubber strips (8) is provided on the top surface of one upper chord, and the two rubber strips (8) of each pair are provided along the two side edges of the upper chord and are respectively located outside the shear nails (10), and each rubber strip (8) extends in the longitudinal direction of the bridge, and mortar for supporting the concrete bridge deck (6) is poured between the two rubber strips (8); When laying the concrete bridge deck (6), a plurality of shear nails (10) are inserted into a plurality of through holes (61) of the concrete bridge deck (6), and a wet joint (9) is provided between every two adjacent concrete bridge decks (6).

5. The steel-concrete composite steel truss bridge according to claim 4, characterized in that: It also includes a plurality of temporary piers (4), which are arranged in pairs at the bottom of steel trusses (1) of different spans; When the steel truss beam (1) is erected to the temporary pier (4), the beam end is placed on the top of the temporary pier (4) at the corresponding span.