A method for calculating carbon emissions during the construction phase of a building

By comprehensively calculating the carbon emissions of construction machinery, material transportation, construction waste collection and transportation, and construction personnel, the problem of incomplete carbon emission calculations during the construction phase in the existing technology has been solved, and a complete carbon emission calculation system has been established to realize the analysis of buildings. Accurate assessment of carbon emissions during the construction phase.

CN114493957BActive Publication Date: 2024-10-18CHINA STATE CONSTRUCTION ACADEMY CORPERATION LTD +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202111627808.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-12-28
Publication Date
2024-10-18
Estimated Expiration
2041-12-28

AI Technical Summary

Technical Problem

The existing building carbon emission calculation standards fail to fully consider the carbon emissions during the construction phase, especially the carbon emissions from material transportation, construction machinery, construction waste collection, transportation and processing, and construction personnel, resulting in incomplete carbon emission calculations.

Method used

A method for calculating carbon emissions during the construction phase is proposed. By obtaining the carbon emissions of construction machinery, material transportation, construction waste collection, transportation and processing, and construction personnel, a specific formula is used to calculate the total carbon emissions during the construction phase, including the carbon emissions of construction machinery. Calculation of emissions, carbon emissions from material transportation, carbon emissions from construction waste collection, transportation and processing, and carbon emissions from construction personnel.

Benefits of technology

It has achieved a comprehensive and accurate calculation of carbon emissions during the building construction phase, established a sound carbon emission calculation system, and can more scientifically assess the total carbon emissions during the construction phase.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114493957B_ABST
    Figure CN114493957B_ABST
Patent Text Reader

Abstract

The present invention discloses a method for calculating carbon emissions during a construction phase, including: obtaining the amount of energy consumed by construction machinery, and calculating the carbon emissions of construction machinery; obtaining the transportation distances of materials from different departure places to the construction site, and calculating the carbon emissions of material transportation; obtaining the amount of garbage generated under the sub-projects, and calculating the carbon emissions of construction waste collection and transportation and treatment; obtaining the construction period and the number of construction personnel, and calculating the carbon emissions of construction personnel; and calculating the total carbon emissions during the construction phase based on the carbon emissions of construction machinery, the carbon emissions of material transportation, the carbon emissions of construction waste collection and transportation and treatment, and the carbon emissions of construction personnel. The present invention can perform comprehensive and effective calculations on carbon emissions during the construction phase of a building, so as to solve the problem of incomplete consideration of carbon emissions during the existing construction phase, and establish and improve a carbon emission calculation system during the construction phase.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of carbon emission calculation, and more particularly to a method for calculating carbon emission during a building construction phase. Background Art

[0002] Construction projects involve a large amount of resources, energy consumption, solid waste and greenhouse gas emissions during their construction and operation. Among them, the large amount of greenhouse gases emitted by building materials production and construction machinery are important factors causing climate warming and anomalies.

[0003] The existing national standard "Building Carbon Emission Calculation Standard" GB / T 51366-2019 lists the carbon emissions generated by the transportation of materials to the construction site under "Material Production and Transportation" and does not consider it as part of the total carbon emissions during the construction phase. This is unreasonable. Carbon emissions under "Material Production and Transportation" occur after the start of construction and should be included in the total emissions during the construction phase; construction units often decide where to purchase and ship materials, which are precisely the most important factors affecting carbon emissions from material transportation.

[0004] Therefore, there is an urgent need for a scientific, precise and efficient method for calculating carbon emissions during the construction phase to comprehensively calculate the carbon emissions generated during the construction process. Summary of the invention

[0005] In view of this, the present invention provides a method for calculating carbon emissions during the construction phase, which fully considers the carbon emissions of construction machinery, material transportation, construction waste collection and treatment, and construction personnel, and can comprehensively and effectively calculate the carbon emissions during the construction phase.

[0006] In order to achieve the above object, the present invention adopts the following technical solution:

[0007] A method for calculating carbon emissions during a building construction phase, comprising:

[0008] Obtain the amount of energy consumed by construction machinery and calculate the carbon emissions of construction machinery;

[0009] Obtain the transportation distance of materials from different departure points to the construction site, and calculate the carbon emissions of material transportation;

[0010] Obtain the amount of waste generated by each project and calculate the carbon emissions from the collection, transportation and treatment of construction waste;

[0011] Calculate the carbon emissions of construction workers based on the construction period and the number of construction workers;

[0012] The total carbon emissions during the construction phase are calculated based on the carbon emissions of the construction machinery, the carbon emissions of material transportation, the carbon emissions of the collection, transportation and treatment of construction waste, and the carbon emissions of the construction personnel.

[0013] Preferably, the specific calculation formula for carbon emissions of construction machinery is:

[0014]

[0015] Among them, C1 represents the carbon emissions of construction machinery, E jx,i represents the total energy consumption of the construction machinery, EF i Represents the carbon emission factor of the i-th energy type.

[0016] Preferably, the specific calculation formula for carbon emissions from material transportation is:

[0017]

[0018] Among them, C2 represents the carbon emissions from material transportation, M i represents the consumption of the i-th material, D i,j represents the transportation distance of the i-th material by the j-th mode of transportation, T j It represents the carbon emission factor per unit weight and distance under the j-th mode of transportation, i represents the material type number, and j represents the mode of transportation number.

[0019] Preferably, the specific calculation formula for carbon emissions from construction waste collection, transportation and treatment is:

[0020] C3=C sj +C ys +C cl

[0021] Among them, C3 represents the carbon emissions from the collection, transportation and treatment of construction waste, C sj represents the carbon emissions from construction waste collection, C ys represents the carbon emissions from construction waste transportation, C cl Represents carbon emissions from construction waste treatment.

[0022] Preferably, the specific calculation formula for the carbon emissions of construction workers is:

[0023] C4=C bg +C sh

[0024] Among them, C4 represents the carbon emissions of construction workers, C bg represents the carbon emissions of office personnel, C sh Represents the carbon emissions of people in the living area.

[0025] Preferably, the total energy consumption of construction machinery is calculated as follows:

[0026] E jx =E fx +E cs

[0027] Among them, E jx represents the total energy consumption of construction machinery, E fx Indicates the total energy consumption of each part of the project, E cs Indicates the total energy usage of the measure project.

[0028] Optimally, the total energy consumption of each project is E fx The specific calculation formula is:

[0029]

[0030]

[0031] Among them, Q fx,i represents the engineering quantity of the ith item in the sub-item project, f fx,i It represents the energy consumption coefficient of the ith item in the sub-item project, T i,j R represents the j-type construction machinery unit consumption of the i-th project, j represents the energy consumption of the jth type of construction machinery in the i-th project, E jj,i Indicates that in the i-th project, small construction machinery is not included in the machine-shift consumption, but the energy it consumes is included in the partial energy consumption of materials, i represents the project number in the sub-project, and j represents the construction machinery number;

[0032] Total energy consumption of the project E cs The specific calculation formula is:

[0033]

[0034]

[0035] Among them, Q cs,i represents the engineering quantity of the ith project in the measure project, f cs,i represents the energy consumption coefficient of the i-th item in the measure project, T A,i,j R represents the j-type construction machinery unit consumption per unit of engineering quantity of the i-th measure project, j It represents the energy consumption per unit shift of the j-th type of construction machinery in the ith project.

[0036] Preferably, the carbon emissions from the collection, transportation and treatment of construction waste include carbon emissions from the collection of construction waste, carbon emissions from the transportation of construction waste and carbon emissions from the treatment of construction waste;

[0037] Carbon emissions from construction waste collection sj The specific calculation formula is:

[0038]

[0039] Among them, E sj,i,j represents the energy consumption of the jth type of garbage in the process of collecting construction waste, EF j It represents the carbon emission factor of the j-th type of energy, i represents the type number of construction waste, and j represents the type number of energy.

[0040] Carbon emissions from construction waste transportation ys The specific calculation formula is:

[0041]

[0042] Among them, M r,i represents the amount of garbage generated by the i-th type, D r,i,j T represents the transportation distance of the jth transportation mode of the i-th type of construction waste, r,j It represents the carbon emission factor per unit weight and distance under the j-th mode of transportation, i represents the type number of construction waste, and j represents the type number of the transportation mode.

[0043] Carbon emissions from construction waste treatment cl The specific calculation formula is:

[0044] C cl =C tm +C hs

[0045] Among them, C tm represents the carbon emissions from construction waste landfill, C hs Represents carbon emissions from construction waste recycling.

[0046] Preferably, the carbon emissions of the construction personnel include carbon emissions of personnel in the office area and carbon emissions of personnel in the living area;

[0047] Carbon emissions of office staff C bg The specific calculation formula is:

[0048]

[0049] Among them, E bg,i represents the total energy consumption of the i-th energy in the office area, EF i represents the carbon emission factor of the i-th energy type;

[0050] Carbon emissions of people in living area C sh The specific calculation formula is:

[0051]

[0052] Among them, E sh,i represents the total consumption of the i-th energy in the living area, EF i Represents the carbon emission factor of the i-th energy type.

[0053] Preferably, the specific calculation formula for the total carbon emissions during the construction phase is:

[0054] C sum =C1+C2+C3+C4

[0055] Among them, C sum It represents the total carbon emissions during the construction phase, C1 represents the carbon emissions from construction machinery, C2 represents the carbon emissions from material transportation, C3 represents the carbon emissions from the collection, transportation and treatment of construction waste, and C4 represents the carbon emissions from construction personnel.

[0056] It can be seen from the above technical solution that, compared with the prior art, the present invention discloses a method for calculating carbon emissions during the construction phase of a building, which includes carbon emissions from construction machinery, carbon emissions from material transportation, carbon emissions from the collection and treatment of construction waste, and carbon emissions from construction personnel. It can comprehensively and effectively calculate the carbon emissions during the construction phase of a building, so as to solve the problem of incomplete consideration of carbon emissions during the existing construction phase, and establish a sound carbon emissions calculation system for the construction phase. BRIEF DESCRIPTION OF THE DRAWINGS

[0057] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying creative work.

[0058] Figure 1 The accompanying drawing is a schematic diagram of carbon emission calculation during the construction phase of the present invention. DETAILED DESCRIPTION

[0059] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0060] The embodiment of the present invention discloses a method for calculating carbon emissions during a building construction phase, comprising the following steps:

[0061] Step 1: Calculate and analyze the energy consumed by construction machinery and calculate the carbon emissions C1 of construction machinery.

[0062]

[0063] Where: C1 represents the carbon emissions of construction machinery (kgCO2); Ejx,i represents the total energy consumption of the construction machinery, EF i represents the carbon emission factor of the i-th energy type;

[0064] The total energy consumption during the construction phase is calculated using the energy consumption estimation method for the construction process. The energy consumption for the construction process energy consumption estimation method should be calculated as follows:

[0065] E jx =E fx +E cs (2)

[0066] Where: E jx Indicates the total energy consumption of construction machinery (kWh / kg / L), E fx Indicates the total energy consumption of each part of the project (kWh / kg / L), E cs Indicates the total energy consumption of the measure project (kWh / kg / L).

[0067] The calculation method for carbon emissions of sub-projects and measures is as follows.

[0068] (1) The total energy consumption of each project should be calculated according to formula (3) and formula (4):

[0069]

[0070]

[0071] Where: Q fx,i represents the engineering quantity of the ith item in the sub-item project, f fx,i It represents the energy consumption coefficient of the ith item in the sub-item project (kwh / unit of engineering quantity), T i,j represents the consumption of the jth type of construction machinery per unit of engineering work in the i-th project (machine-shift), R j represents the energy consumption of the jth type of construction machinery in the ith project (kwh / shift); E jj,i It means that in the i-th project, small-scale construction machinery is not included in the machine-shift consumption, but the energy it consumes is included in the partial energy consumption of materials (kwh). i represents the project number in the sub-project, and j represents the construction machinery number.

[0072] (2) The energy consumption calculation of the measures project shall comply with the following provisions.

[0073] 1) For scaffolding, formwork and support, vertical transportation, building superelevation and other measures for which the engineering quantities can be calculated, the energy consumption shall be calculated according to formula (5) and formula (6):

[0074]

[0075]

[0076] Where: Q cs,i represents the engineering quantity of the ith project in the measure project; f cs,i represents the energy consumption coefficient of the ith item in the measure project (kWh / unit of engineering quantity); T A,i,j R represents the j-type construction machinery unit consumption per unit engineering quantity of the i-th measure project (unit); j It represents the energy consumption per unit shift of the j-th type of construction machinery in the ith project (kWh / shift), where i represents the project number in the sub-project; j represents the construction machinery number.

[0077] 2) Drainage and drainage should include two stages: well completion and use. Its energy consumption should be calculated based on the project's special drainage and drainage plan.

[0078] 3) The energy consumed by temporary construction facilities should be determined based on the temporary facilities layout plan and construction period calculated by the construction company.

[0079] Step 2: Calculate the transportation distance of materials from different departure points to the construction site and calculate the carbon emissions C2 from material transportation.

[0080]

[0081] Where: C2 represents the carbon emission of material transportation (kgCO2), M i represents the consumption of the i-th material, D i,j represents the transportation distance of the i-th material by the j-th mode of transportation, T j It represents the carbon emission factor per unit weight of transportation distance under the jth mode of transportation [kgCO2 / (t·km)].

[0082] Step 3: Calculate the amount of garbage generated under normal circumstances of each project and the carbon emissions caused by treating this part of the garbage C3.

[0083] The amount of construction waste generated is classified and counted according to construction debris, construction mud, construction waste, demolition waste and decoration waste. Construction waste, demolition waste and decoration waste should include metal, concrete, bricks and tiles, ceramics, glass, wood, plastic, plaster, paint, soil, etc.

[0084] Before entering the collection system, construction waste is pre-treated by crushing, dehydration, compression, etc. according to the needs of the collection and transportation vehicles and methods.

[0085] The carbon emissions C3 from the collection, transportation and treatment of construction waste are composed of three parts, as shown in formula (8).

[0086] C3=C sj +C ys +C cl(8)

[0087] Where: C3 represents the carbon emissions from the collection, transportation and treatment of construction waste (kgCO2); C sj represents the carbon emission of construction waste collection (kgCO2); C ys represents the carbon emission of construction waste transportation (kgCO2); C cl It represents the carbon emission of construction waste treatment (kgCO2).

[0088] The calculation of carbon emissions from construction waste collection, transportation and treatment is shown below.

[0089] The calculation method of carbon emissions from construction waste collection is shown in formula (9).

[0090]

[0091] Among them, E sj,i,j represents the energy consumption of the jth type of garbage in the process of collecting construction waste, EF j It represents the carbon emission factor of the j-th type of energy, i represents the energy type number; j represents the garbage type number.

[0092] The calculation method of carbon emissions from construction waste transportation is shown in formula (10).

[0093]

[0094] Where: M r,i represents the amount of garbage generated by the i-th type, D r,i,j T represents the transportation distance of the jth transportation mode of the i-th type of construction waste, r,j It represents the carbon emission factor per unit weight and distance under the jth mode of transportation [kgCO2 / (t·km)], i represents the type number of construction waste, and j represents the type number of transportation mode

[0095] (3) The calculation method of carbon emissions from construction waste treatment is shown in formula (11).

[0096] C cl =C tm +C hs (11)

[0097] Where: C tm represents the carbon emission of construction waste landfill (kgCO2), C hs It represents the carbon emission of construction waste recycling (kgCO2);

[0098] The carbon emissions from landfilling and recycling of construction waste are calculated as follows.

[0099] 1) The calculation method of carbon emissions from construction waste landfill is shown in formula (12).

[0100]

[0101] Where: M tm,i represents the landfill volume of the i-th type of garbage; L i It expresses the carbon emission factor per unit weight of landfill waste (kgCO2) / t.

[0102] 2) The calculation method of carbon emissions from construction waste recycling is shown in formula (13).

[0103]

[0104] M hs,i represents the amount of recyclable construction waste of type i; R i It indicates the carbon emission factor per unit weight of recyclable construction waste (kgCO2) / t.

[0105] Step 4: According to the project duration and the number of construction personnel, calculate the electricity consumption, gas consumption, fuel consumption, etc. of the office area and living area during the project construction phase, and then calculate the carbon emissions C4 of the construction personnel. The calculation method is shown in formula (14).

[0106] C4=C bg +C sh (14)

[0107] Where: C bg Indicates carbon emissions of the office area (kgCO2); C sh Indicates carbon emissions in living areas (kgCO2).

[0108] The calculation method of carbon emissions of office area and living area is as follows.

[0109] (1) The calculation method of carbon emissions in the office area is shown in formula (15).

[0110]

[0111] E sh,i It represents the total consumption of the i-th energy in the office area (kWh / kg / L).

[0112] (2) The calculation method of carbon emissions in living areas is shown in formula (16).

[0113]

[0114] E sh,i It represents the total consumption of the ith energy in the living area (kWh / kg / L).

[0115] Step 5: Add the results of the above four steps to get the total carbon emissions during the construction phase C sum, as shown in formula (17).

[0116] C sum =C1+C2+C3+C4 (17).

[0117] In this specification, each embodiment is described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the embodiments can be referred to each other. For the device disclosed in the embodiment, since it corresponds to the method disclosed in the embodiment, the description is relatively simple, and the relevant parts can be referred to the method part.

[0118] The above description of the disclosed embodiments enables one skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to one skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but rather to the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. A method for calculating carbon emissions during the construction phase of a building. It is characterized in that include: Obtain the amount of energy consumed by construction machinery and calculate the carbon emissions of construction machinery; Obtain the transportation distance of materials from different departure points to the construction site, and calculate the carbon emissions of material transportation; Obtain the amount of waste generated by each project and calculate the carbon emissions from the collection, transportation and treatment of construction waste; Calculate the carbon emissions of construction workers based on the construction period and the number of construction workers; Calculate the total carbon emissions during the construction phase based on the carbon emissions of the construction machinery, the carbon emissions of the material transportation, the carbon emissions of the construction waste collection, transportation and treatment, and the carbon emissions of the construction personnel; The specific calculation formula for carbon emissions from construction machinery is: Among them, C 1 represents the carbon emissions of construction machinery, E jx,i represents the total energy consumption of the construction machinery, EF i represents the carbon emission factor of the i-th energy type; The specific calculation formula for carbon emissions from material transportation is: Among them, C 2 Represents the carbon emissions from material transportation, M i represents the consumption of the i-th material, D i,j represents the transportation distance of the jth mode of transportation of the i-th material, T j It represents the carbon emission factor per unit weight and distance under the j-th mode of transportation, i represents the material type number, and j represents the mode of transportation number; The specific calculation formula for carbon emissions from construction waste collection, transportation and treatment is: C 3 =C sj +C ys +C cl Among them, C 3 represents the carbon emissions from the collection, transportation and treatment of construction waste, C sj represents the carbon emissions from construction waste collection, C ys represents the carbon emissions from construction waste transportation, C cl represents the carbon emissions from construction waste treatment; The specific calculation formula for carbon emissions of construction workers is: C 4 =C bg +C sh Among them, C 4 represents the carbon emissions of construction workers, C bg represents the carbon emissions of office personnel, C sh It represents the carbon emission of people in the living area; The calculation formula for total energy consumption of construction machinery is: AND jx =And fx +E cs Among them, E jx represents the total energy consumption of construction machinery, E fx Indicates the total energy consumption of each part of the project, E cs Indicates the total energy usage of the measure project; Total energy consumption of each project E fx The specific calculation formula is: Among them, Q fx,i represents the engineering quantity of the ith item in the sub-item project, f fx,i It represents the energy consumption coefficient of the ith item in the sub-item project, T i,j R represents the j-type construction machinery unit consumption of the i-th project, j represents the energy consumption of the jth type of construction machinery in the i-th project, E jj,i Indicates that in the i-th project, small construction machinery is not included in the machine-shift consumption, but the energy it consumes is included in the partial energy consumption of materials, i represents the project number in the sub-project, and j represents the construction machinery number; Total energy consumption of the project E cs The specific calculation formula is: Among them, Q cs,i represents the engineering quantity of the ith project in the measure project, f cs,i represents the energy consumption coefficient of the i-th item in the measure project, T A,i,j R represents the j-type construction machinery unit consumption per unit of engineering quantity of the i-th measure project, j It represents the energy consumption per unit shift of the jth type of construction machinery in the i-th project; The carbon emissions from the collection, transportation and treatment of construction waste include carbon emissions from the collection of construction waste, carbon emissions from the transportation of construction waste and carbon emissions from the treatment of construction waste; Carbon emissions from construction waste collection sj The specific calculation formula is: Among them, E sj,i,j represents the energy consumption of the jth type of garbage in the process of collecting construction waste, EF j represents the carbon emission factor of the j-th energy type, i represents the serial number of the construction waste type, and j represents the serial number of the energy type; Carbon emissions from construction waste transportation ys The specific calculation formula is: Among them, M r,i represents the amount of garbage generated by the i-th type, D r,i,j T represents the transportation distance of the jth transportation mode of the i-th type of construction waste, r,j It represents the carbon emission factor per unit weight and distance under the jth mode of transportation, i represents the type number of construction waste, and j represents the type number of the transportation mode; Carbon emissions from construction waste treatment cl The specific calculation formula is: C cl =C tm +C hs Among them, C tm represents the carbon emissions from construction waste landfill, C hs represents the carbon emissions from construction waste recycling; The carbon emissions of construction personnel include carbon emissions of personnel in office areas and personnel in living areas; Carbon emissions of office staff C bg The specific calculation formula is: Among them, E bg,i represents the total energy consumption of the i-th energy in the office area, EF i represents the carbon emission factor of the i-th energy type; Carbon emissions of people in living area C sh The specific calculation formula is: Among them, E sh,i represents the total consumption of the i-th energy in the living area, EF i represents the carbon emission factor of the i-th energy type; The specific calculation formula for the total carbon emissions during the construction phase is: C sum =C 1 +C 2 +C 3 +C 4 Among them, C sum represents the total carbon emissions during the construction phase, C 1 represents the carbon emissions of construction machinery, C 2 represents the carbon emissions from material transportation, C 3 represents the carbon emissions from the collection, transportation and treatment of construction waste, C 4 Represents the carbon emissions of construction workers.

Citation Information

Patent Citations

  • Method and system for estimating carbon emission from construction site based on bill of quantities

    CN109299523A

  • Carbon emission calculation method and system for blasting demolition

    CN109408879A