Shear wall connector, assembled shear wall and assembly method

By using a combined system of embedded parts and connectors in the prefabricated concrete shear wall structure, the problems of large amounts of temporary supports and large amounts of wet work are solved, and the dry modular connection of the shear wall panels is realized, which improves the efficiency Construction efficiency and connection quality enhance structural integrity and economic benefits.

CN114562059BActive Publication Date: 2024-10-25SOUTHWEAT UNIV OF SCI & TECH
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210423326.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-04-21
Publication Date
2024-10-25
Estimated Expiration
2042-04-21

AI Technical Summary

Technical Problem

The existing prefabricated concrete shear wall structure uses a large amount of temporary supports during the construction process, the amount of wet work is large, and the connection quality is difficult to guarantee, resulting in high construction costs, slow progress, and lack of modular dry connection technology.

Method used

A shear wall connection system including embedded parts and connectors is adopted. Through components such as side panels, bolts, shear keys and H-shaped steel of the embedded parts, dry modular connection of wall panels is realized, reducing the need for temporary support. Ensure precise docking and strength of connectors and wall panels.

Benefits of technology

The dry modular construction of shear wall panels is realized, which reduces construction costs, improves construction efficiency and connection quality, and enhances the strength and economic benefits of the overall structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114562059B_ABST
    Figure CN114562059B_ABST
Patent Text Reader

Abstract

The present invention discloses a shear wall connector and an assembled shear wall and an assembly method in the field of building technology. The shear wall connector includes an embedded part and a connector. The embedded part includes a side panel, a stud and a shear key. The side panel is provided with a first through hole. The stud and the shear key are respectively arranged on the inner and outer sides of the side panel. The end of the stud connected to the side panel is provided with a threaded hole, and the threaded hole is aligned with the first through hole. The connector includes an H-shaped steel. The flange plate of the H-shaped steel is provided with a second through hole and a shear key adapter hole that match the first through hole and the shear key on the side panel. The embedded part is embedded in the surface of the concrete wall and assembled through the connector. During installation, the shear key is inserted into the shear key adapter hole to play a shearing role, and is connected and fixed by bolts. Compared with the existing assembly method, the connector of the present application does not require temporary support, can achieve dry modular construction, has high construction efficiency, and has better economic benefits.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of construction, and in particular to a shear wall connector, an assembled shear wall and an assembly method. Background Art

[0002] Prefabricated concrete shear wall structures are prefabricated in factories and assembled on site, which can greatly reduce labor costs, improve component quality, and have good economic benefits and application effects. At present, there are two main connection methods for prefabricated concrete shear wall structures: the first is to expose annular stirrups on both sides of the wall, insert longitudinal reinforcement in the middle of the stirrups after assembly, and pour concrete on site to connect the shear wall panels on the same layer; the second is to expose the steel bars on the top of the lower wall panel, embed sleeves at the lower part of the upper wall panel and the corresponding position of the reserved steel bars of the lower wall panel, install the prefabricated floor slab layer after the lower wall panel is installed in place, pour the cast-in-place floor slab layer, install the upper wall panel on the upper part of the floor slab elevation, and connect the upper and lower wall panels by grouting. The existing connection method of concrete shear wall panels has the disadvantages of large temporary support for fixing wall panels, large amount of wet work on site, difficult to ensure the quality of grouting in the sleeve, and slow construction progress. How to reduce on-site wet work, reduce the amount of temporary support, ensure connection quality, realize modular dry connection of shear wall panels, further reduce the construction cost of prefabricated shear walls, improve economic benefits, and innovate the connection technology of concrete prefabricated shear walls are issues that need to be solved urgently. Summary of the invention

[0003] In order to overcome the above-mentioned deficiencies of the existing assembled concrete shear walls, the technical problem to be solved by the present invention is to provide a shear wall connector, an assembled shear wall and an assembly method which can reduce construction costs and improve assembly efficiency.

[0004] The technical solution adopted by the present invention to solve its technical problem is:

[0005] A shear wall connector includes an embedded part and a connector, wherein the embedded part includes a side plate, a stud and a shear key, wherein a plurality of first through holes are arranged at intervals on the side plate, and the stud and the shear key also include a plurality of studs and are arranged at intervals on the inner and outer sides of the side plate, respectively, a threaded hole is provided at one end of the stud connected to the side plate, and the threaded hole is aligned with the first through hole, and the connector includes an H-shaped steel and a rib plate arranged at intervals between two flange plates of the H-shaped steel, and the flange plate of the H-shaped steel is provided with a second through hole and a shear key adaptation hole matching the first through hole and the shear key on the side plate.

[0006] Furthermore, the first through holes and the shear keys on the embedded component are arranged alternately and at intervals.

[0007] Furthermore, the shear key is a frustum structure, and the larger end is fixed to the side plate, and the shear key matching hole is an inverted cone hole adapted to the shear key.

[0008] Furthermore, the height of the shear key is 5-10 mm higher than the depth of the shear key matching hole.

[0009] Furthermore, the shear key adapting hole is arranged at a corner formed by the web and rib of the H-shaped steel.

[0010] Furthermore, a hemispherical top cap is provided at one end of the bolt away from the side plate, and the outer diameter of the hemispherical top cap is about 5 mm larger than the outer diameter of the bolt.

[0011] The assembled shear wall includes a prefabricated wall panel of reinforced concrete and a shear wall connector, wherein the side panel of the embedded part is arranged on the assembly surface of the prefabricated wall panel, and the wall panel steel bars in the prefabricated wall panel are welded and fixed to the inner side of the side panel, and the connector is located between the assembly surfaces of two adjacent prefabricated wall panels, and the embedded part and the connector are matched and connected and welded through a shear key and a shear key adapter hole, and are fixed together by bolts that pass through a second through hole, a first through hole and a threaded hole in sequence.

[0012] Furthermore, for the shear wall that needs to be built with floor slabs, a transverse connecting piece is provided at the top of the shear wall, and the floor slabs include prefabricated floor slabs and cast-in-place floor slabs. The overlapping ends of the prefabricated floor slabs are built on the lower flange plates of the H-shaped steel through exposed steel bars with bent hooks. The cast-in-place floor slabs are cast on the prefabricated floor slabs, and the ends of the negative bending moment steel bars are welded to the webs of the H-shaped steel.

[0013] Furthermore, the side plate of the embedded part is located at the center of the prefabricated wall panel assembly surface, and its two sides are 8-12 mm away from the two side surfaces of the prefabricated wall panel, and the width of the connecting part is equivalent to the width of the side plate.

[0014] The assembly method of the assembled shear wall comprises the following steps:

[0015] a. Make embedded parts and connectors according to the size of walls and floor slabs;

[0016] b. Use the embedded parts as the frame and weld the wall panel steel bars inside to form a steel mesh with a frame;

[0017] c. Pour concrete inside the steel mesh with a frame, prefabricate prefabricated wall panels with a frame, and also prefabricate prefabricated floor slabs with exposed steel bars with hooks;

[0018] d. Install multiple prefabricated wall panels through connectors to form I-shaped, L-shaped, T-shaped and cross-shaped lower-layer assembled shear walls, and ensure that there are horizontal connectors at the locations where floor slabs need to be erected;

[0019] e. Install the prefabricated floor slabs and place the exposed floor slab steel bars with hooks on the lower flange plate of the horizontal connecting piece H-shaped steel;

[0020] f. Tie negative bending moment reinforcement on the prefabricated floor slab, weld the ends of the negative bending moment reinforcement on the web of the H-shaped steel, and then cast the cast-in-place floor slab;

[0021] g. Install the upper prefabricated shear wall according to the installation method of the lower prefabricated shear wall. After the assembly is completed, use anti-rust paint to treat the exposed connectors and embedded connectors for rust prevention, then fill the gaps in the connectors with dry hard aerated concrete or rock wool, and finally paint with cement mortar.

[0022] The beneficial effects of the present invention are:

[0023] 1. Prefabricated wall panels are installed and connected through connectors and embedded parts, without the need for temporary support, and dry modular construction can be achieved, ensuring that the connectors and prefabricated wall panels transmit tension and shear forces safely and reliably, thus enhancing the integrity of the shear wall;

[0024] 2. The compatibility of embedded parts and connectors has been verified in the factory, which can ensure that the wall panels and connectors are accurately positioned during on-site installation, which is conducive to speeding up the construction progress, saving costs and having better economic benefits;

[0025] 3. The embedded parts can serve as frames to protect the prefabricated wall panels. During handling and transportation, they can reduce the occurrence of missing corners and falling blocks of prefabricated wall panels due to collisions.

[0026] 4. The connectors and embedded parts located in the edge components increase the steel content of the edge components, which can achieve strong or super-strong connections with cast-in-place structures, and the integrity of the shear wall is good. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a structural schematic diagram of the shear wall connector of the present invention.

[0028] Figure 2 It is a schematic diagram of the bolt structure of the present invention.

[0029] Figure 3 It is a schematic diagram of the shear key installation structure of the present invention.

[0030] Figure 4 It is a structural schematic diagram of the assembled shear wall of the present invention.

[0031] Figure 5 It is a schematic diagram of the structure of the assembled shear wall steel mesh of the present invention.

[0032] Figure 6 It is a schematic diagram of the floor installation structure of the present invention.

[0033] Marked in the figure are, 1-embedded parts, 2-connecting parts, 3-precast wall panels, 4-precast floor panels, 5-cast-in-place floor panels, 11-side panels, 12-studs, 13-shear keys, 14-first through holes, 15-threaded holes, 16-hemispherical top caps, 21-H-shaped steel, 22-flange plates, 23-shear key adapter holes, 24-second through holes, 25-ribs, 26-webs, 31-wall panel reinforcement, 41-floor slab reinforcement, 51-negative bending moment reinforcement. DETAILED DESCRIPTION

[0034] The present invention is further described below in conjunction with the accompanying drawings.

[0035] like Figure 1-3 As shown, the shear wall connector of the present invention includes an embedded part 1 and a connector 2, the embedded part 1 includes a side plate 11, a stud 12 and a shear key 13, a plurality of first through holes 14 are arranged at intervals on the side plate 11, the stud 12 and the shear key 13 also include a plurality of and are arranged at intervals on the inner and outer sides of the side plate 11, a threaded hole 15 is provided at one end of the stud 12 connected to the side plate 11, and the threaded hole 15 is aligned with the first through hole 14, the connector 2 includes an H-shaped steel 21 and a rib plate 25 arranged at intervals between two flange plates 22 of the H-shaped steel 21, and a second through hole 24 and a shear key adaptation hole 23 matching the first through hole 14 and the shear key 13 on the side plate 11 are provided on the flange plate 22 of the H-shaped steel 21.

[0036] The embedded part 1 is embedded in the surface of the concrete wall to facilitate the assembly of the concrete wall through the connector 2. During installation, the shear key 13 on the embedded part 1 is inserted into the shear key adapter hole 23 to play a shearing role, and then connected and fixed by bolts passing through the second through hole 24, the first through hole 14 and the stud 12. Compared with the existing assembly method, the shear wall connector of the present application does not require temporary support, can achieve dry modular construction, ensure that the connector and the prefabricated wall panels transmit tension and shear force safely and reliably, and enhance the integrity of the shear wall; at the same time, the adaptability of the embedded parts and the connectors has been verified in the factory, which can ensure that the embedded parts and the connectors are accurately positioned during on-site installation, speeding up the construction progress, helping to save costs, and having better economic benefits.

[0037] In order to facilitate construction and ensure the reliability of assembly, this application provides the following preferred methods:

[0038] In order to achieve a good connection effect, the first through holes 14 and the shear keys 13 on the embedded part 1 are arranged alternately and at intervals.

[0039] In order to facilitate the alignment of the shear key 13 and the shear key adapter hole 23 during assembly, the shear key 13 is a frustum structure, and the larger end is fixed to the side plate 11 , and the shear key adapter hole 23 is an inverted cone hole adapted to the shear key 13 .

[0040] During the installation process, in order to achieve good shear and tensile resistance, the shear key 13 and the shear key adapter hole 23 need to be welded after the docking is completed. Therefore, in order to facilitate welding, the height of the shear key 13 is preferably 5-10mm higher than the depth of the shear key adapter hole 23 to ensure that the shear key 13 can pass through the shear key adapter hole 23 during installation, which is convenient for subsequent welding around the shear key 13.

[0041] Further, such as Figure 3 As shown, the shear key adapter hole 23 is preferably set at the corner formed by the web 26 and the rib 25 of the H-shaped steel 21, so that the web 26 and the rib 25 of the connecting member 2 can play a certain limiting and fixing role on the shear key 23, thereby improving the shear and tensile strength.

[0042] For the bolt 12, in order to facilitate the processing of the threaded hole 15, a threaded sleeve structure can be used. However, in order to prevent concrete from entering the threaded hole during the production of the prefabricated wall panel, a hemispherical top cap 16 can be provided at the end of the bolt 12 away from the side plate 11, such as Figure 2 As shown, the outer diameter of the hemispherical top cap 16 is about 5 mm larger than the outer diameter of the bolt 12, which can prevent concrete from entering the threaded hole 15 and prevent the embedded part 1 from loosening and detaching from the precast concrete wall.

[0043] The assembled shear wall made by the above shear wall connector is as follows: Figure 4 , Figure 5 As shown, the prefabricated wall panel 3 including reinforced concrete also includes a shear wall connector, wherein the side panel 11 of the embedded part 1 is arranged on the assembly surface of the prefabricated wall panel 3, and the wall panel reinforcement 31 in the prefabricated wall panel 3 is welded and fixed to the inner side of the side panel 11, and the connector 2 is located between the assembly surfaces of two adjacent prefabricated wall panels 3, and the embedded part 1 and the connector 2 are matched and docked and welded through the shear key 13 and the shear key adapter hole 23, and are fixed together by bolts passing through the second through hole 24, the first through hole 14 and the threaded hole 15 in sequence. By reasonably setting the positions of the embedded part 1 and the connector 2, the installation of the shear wall panel in the shape of a straight line, an L-shaped, a T-shaped or a connecting beam can be realized, and the versatility is strong.

[0044] Furthermore, in order to adapt to the construction of the floor, a transverse connector 2 is provided on the top of the shear wall where the floor needs to be erected. According to the requirements of the Technical Specifications for Prefabricated Concrete Structures (JGJ 1-2014), the floor of the prefabricated concrete frame structure must be provided with a cast-in-place layer to ensure the integrity of the structure. Therefore, the floor includes a prefabricated floor 4 and a cast-in-place floor 5. The lapped end of the prefabricated floor 4 is erected on the lower flange plate of the H-shaped steel 21 through an exposed floor steel bar 41 with a hook. The cast-in-place floor 5 is cast on the prefabricated floor 4, and the end of its negative bending steel bar 51 is welded to the web 26 of the H-shaped steel 21.

[0045] In order to prevent the steel structure from being exposed and rusted, the side plate 11 of the embedded part 1 is located at the center of the assembly surface of the prefabricated wall panel 3, and its two sides are 8-12mm away from the two side surfaces of the prefabricated wall panel 3. The width of the connecting part 2 is equivalent to the width of the side plate 11. In this way, a gap can be left after the assembly is completed, which is convenient for subsequent painting with cement mortar to ensure the flatness of the wall surface.

[0046] For the specific assembly method of prefabricated shear wall, such as Figure 5 , Figure 6 As shown, the following steps are included:

[0047] a. Make embedded parts and connectors according to the size of walls and floor slabs;

[0048] b. Use the embedded parts as the frame and weld the wall panel steel bars inside to form a steel mesh with a frame;

[0049] c. Pour concrete inside the steel mesh with a frame, prefabricate prefabricated wall panels with a frame, and also prefabricate prefabricated floor slabs with exposed steel bars with hooks;

[0050] d. Install multiple prefabricated wall panels through connectors to form I-shaped, L-shaped, T-shaped and cross-shaped lower-layer assembled shear walls, and ensure that there are horizontal connectors at the locations where floor slabs need to be erected;

[0051] e. Install the prefabricated floor slabs and place the exposed floor slab steel bars with hooks on the lower flange plate of the horizontal connecting piece H-shaped steel;

[0052] f. Tie negative bending moment reinforcement on the prefabricated floor slab, weld the ends of the negative bending moment reinforcement on the web of the H-shaped steel, and then cast the cast-in-place floor slab;

[0053] g. Install the upper prefabricated shear wall according to the installation method of the lower prefabricated shear wall. After the assembly is completed, use anti-rust paint to treat the exposed connectors and embedded connectors for rust prevention, then fill the gaps in the connectors with dry hard aerated concrete or rock wool, and finally paint with cement mortar.

[0054] By adopting the shear wall connector and the assembly method of the present invention, dry modular construction of assembled shear walls can be achieved, thereby enhancing the integrity of the shear walls, accelerating the construction progress, saving costs, and achieving better economic benefits.

Claims

1. An assembled shear wall comprising a prefabricated reinforced concrete wall panel (3), characterized in that: It also includes a shear wall connector, the shear wall connector includes an embedded part (1) and a connector (2), the embedded part (1) includes a side plate (11), a stud (12) and a shear key (13), the side plate (11) is provided with a plurality of first through holes (14) at intervals, the stud (12) and the shear key (13) also include a plurality of studs and are respectively arranged at intervals on the inner and outer sides of the side plate (11), a threaded hole (15) is provided at one end of the stud (12) connected to the side plate (11), and the threaded hole (15) is aligned with the first through hole (14), and the connector (2) includes an H-shaped steel (21) and a rib plate (25) arranged at intervals between two flange plates (22) and a web plate (26) of the H-shaped steel (21); the flange plate (22) of the H-shaped steel (21) is provided with a second through hole (24) and a shear key matching hole (23) matching the first through hole (14) and the shear key (13) on the side plate (11); the first through hole (14) and the shear key (13) on the embedded part (1) are arranged alternately and at intervals; the shear key (13) is a frustum structure, and the larger end is fixed to the side plate; the shear key matching hole (23) is an inverted conical hole adapted to the shear key (13); The side plate (11) of the embedded part (1) is arranged on the assembly surface of the prefabricated wall panel (3), and the wall panel steel bars (31) in the prefabricated wall panel (3) are welded and fixed to the inner side of the side plate (11); the connecting part (2) is located between the assembly surfaces of two adjacent prefabricated wall panels (3); the embedded part (1) and the connecting part (2) are matched and butt-jointed and welded via the shear key (13) and the shear key adapting hole (23); and the embedded part (1) and the connecting part (2) are sequentially passed through the second through hole (24), the first through hole (14) and the threaded hole ( 15) are fixed together; for a shear wall that needs to be built with a floor slab, a transverse connecting piece (2) is provided at the top of the shear wall, the floor slab comprises a prefabricated floor slab (4) and a cast-in-place floor slab (5), the overlapping end of the prefabricated floor slab (4) is built on the lower flange plate of the H-shaped steel (21) through an exposed floor slab steel bar (41) with a hook, the cast-in-place floor slab (5) is cast on the prefabricated floor slab (4), and the end of its negative bending moment steel bar (51) is welded to the web (26) of the H-shaped steel (21).

2. The assembled shear wall according to claim 1, characterized in that: The height of the shear key (13) is 5-10 mm higher than the depth of the shear key matching hole (23).

3. The assembled shear wall according to claim 1, characterized in that: The shear key adapting hole (23) is arranged at a corner formed by the web (26) and the rib (25) of the H-shaped steel (21).

4. The assembled shear wall according to claim 1, characterized in that: A hemispherical top cap (16) is provided at one end of the bolt (12) away from the side plate (11), and the outer diameter of the hemispherical top cap (16) is greater than the outer diameter of the bolt (12).

5. The assembled shear wall according to claim 1, characterized in that: The side plate (11) of the embedded part (1) is located at the center of the assembly surface of the prefabricated wall panel (3), and its two sides are 8-12 mm away from the two side surfaces of the prefabricated wall panel (3). The width of the connecting part (2) is equivalent to the width of the side plate (11).

6. A method for assembling a prefabricated shear wall according to claim 5, characterized in that: The following steps are involved: a. Make embedded parts and connectors according to the size of walls and floor slabs; b. Use the embedded parts as the frame and weld the wall panel steel bars inside to form a steel mesh with a frame; c. Pour concrete inside the steel mesh with a frame, prefabricate prefabricated wall panels with a frame, and also prefabricate prefabricated floor slabs with exposed steel bars with hooks; d. Install multiple prefabricated wall panels through connectors to form I-shaped, L-shaped, T-shaped and cross-shaped lower-layer assembled shear walls, and ensure that there are horizontal connectors at the locations where floor slabs need to be erected; e. Install the prefabricated floor slabs and place the exposed floor slab steel bars with hooks on the lower flange plate of the horizontal connecting piece H-shaped steel; f. Tie negative bending moment reinforcement on the prefabricated floor slab, weld the ends of the negative bending moment reinforcement on the web of the H-shaped steel, and then cast the cast-in-place floor slab; g. Install the upper prefabricated shear wall according to the installation method of the lower prefabricated shear wall. After the assembly is completed, use anti-rust paint to treat the exposed connecting parts and embedded parts, then fill the gaps in the connecting parts with dry hard aerated concrete or rock wool, and finally paint with cement mortar.