A method for drawing a groove in a chute

Through precise hole position marking and angle control, combined with the use of emulsified small roll charges and detonating cords, the problems of cumbersome chute grooving processes and safety risks are solved, and the rapid control of the chute opening and the improvement of scraper operating efficiency are achieved. promote.

CN114622913BActive Publication Date: 2024-10-22GANSU JIU STEEL GRP HONGXING IRON & STEEL CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210376010.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-04-11
Publication Date
2024-10-22
Estimated Expiration
2042-04-11

AI Technical Summary

Technical Problem

Among existing mining methods, the repetitive drilling and blasting process for sliding shafts is cumbersome, takes a long time to operate, is difficult to control the size of the opening, poses high safety risks, and the ore slide is not smooth enough, affecting the operating efficiency of the scraper.

Method used

A method of tunneling is adopted, including tunnel re-surveying, hole exploration, hole layout, perforation, blasting and other steps. Through precise hole position marking, angle control and multiple hole exploration adjustments, the penetration distance and hole depth are ensured. Use The emulsified small roll charge and the detonating cord are detonated in series to ensure the blasting quality, and through network laying and filling length optimization, one-time slotting is achieved and safety is improved.

Benefits of technology

It realizes the rapid putting into use of the chute, controls the opening size, reduces safety risks, improves the smoothness of the ore slide, and improves the operating efficiency of the scraper.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114622913B_ABST
    Figure CN114622913B_ABST
Patent Text Reader

Abstract

The present invention discloses a method for chute troughing, which includes the following steps: S1, tunnel re-measurement; S2, exploration hole; S3, hole arrangement; S4, perforation; S5, blasting: 1), blast hole flushing and inspection; 2), selection of detonator delay time; 3), charging; 4), gun mud filling; 5), charge quantity calculation; 6), network laying. After the charging is completed, 24 detonators in all charge holes are connected with networking cables, pulled to the horizontal detonation cable terminal for connection, and the network is rechecked again. The networking cables are required to be hung on the side of the lane along the vein to ensure network security and normal detonation. The present invention solves the problem of repeated drilling and blasting in chute troughing in the past. The method can pull the chute into place at one time and then put it into use.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of mining methods, and in particular to a method for drawing a chute. Background Art

[0002] At present, in mining, the current method of chute grooving is repetitive drilling and blasting, which makes the process cumbersome and the operation time long. At the same time, the size of the chute opening is difficult to control, the safety risk is relatively large, and the ore flow is not smooth, which affects the operating efficiency of the shovel loader. Summary of the invention

[0003] In view of the above technical problems, the present invention provides a method for chute grooving.

[0004] In order to achieve the above object, the technical solution of the present invention is as follows:

[0005] A method for chute drawing comprises the following steps:

[0006] S1. Re-survey of the tunnel: When the chute connecting tunnel is excavated to 2 meters from the chute wall, stop excavation and contact the surveying personnel for on-site re-survey;

[0007] S2, drilling holes. Before trenching, drill holes at each location to determine the penetration distance. If the penetration distance is greater than 2 meters, it is necessary to continue to dig forward. If the penetration distance is less than or equal to 2 meters, the conditions for trenching are met;

[0008] S3. Hole arrangement: Holes are arranged in the 3.6m×1.2m area below the center of the 4.2m×3.8m tunnel head. The technicians use red paint to mark the hole positions according to the design site. From top to bottom, three rows of deep holes are marked, with angles of 30 degrees, 35 degrees, and 45 degrees, respectively. The depths are 2.2m, 2.3m, and 2.8m, respectively. The hole spacing is 0.6m. The core is located in the center, including a center hole, four empty holes, and four auxiliary holes. The angle and depth are consistent with the second row of holes. A total of 28 holes are arranged, including four empty holes and 24 charging holes. The diameter of the center hole and the empty hole is 76mm, and the diameter of the remaining holes is 48mm.

[0009] S4, Perforation:

[0010] 1) Use DD2710 trolley for construction drilling;

[0011] 2) During the construction process, strictly follow the given center line to avoid misalignment of the penetration position;

[0012] 3) During the construction process, the holes marked with red paint should be strictly followed, and the driving pressure of the trolley should be controlled during the drilling process to improve the construction quality and avoid missing holes or stringing holes;

[0013] 4) Before construction, multiple exploration holes are carried out according to the design. First, four empty holes are detected at the hollowing position, and then two holes are selected in each of the two gangs of the non-drilling area for detection. Due to the wear of the chute and the irregularity of the well wall, the hole depth is adjusted in time according to the detection depth of each exploration hole on site to avoid the charging hole from penetrating the inner wall of the chute (1);

[0014] 5) Perforation angle and hole depth: The first row of six holes has a construction angle of 30 degrees and a construction depth of 2.2m; the second row of six holes has a construction angle of 35 degrees and a construction depth of 2.3m; the third row of seven holes has a construction angle of 45 degrees and a construction depth of 2.8m. According to the actual situation of the on-site operation, if there is a perforation phenomenon, it should be reported to the on-site technicians in time, and the on-site technicians will adjust the hole depth, mark the perforation, and plug the hole before charging;

[0015] 6) During the perforation process, the inclination angle must be strictly controlled. Two people are required to perform the hole-changing operation, one is responsible for operating the trolley, and the other is responsible for angle measurement and determining the position of the trolley arm. During the operation, a protractor is used for repeated measurements to ensure that the angle is appropriate before drilling the hole;

[0016] 7) To avoid blockage of the eye holes during the bottom hole construction process, the holes should be constructed 10 cm from the ground and filled with explosive bags or special rubber plugs after the operation is completed;

[0017] S5, blasting:

[0018] 1) Blast hole flushing and inspection

[0019] Before blasting, use high-pressure air to blow away the rock debris and residual water in the hole and check whether there are any through holes. If there are any through holes, fill and plug the ends of the through holes.

[0020] 2) Detonator delay time selection

[0021] Digital electronic detonators are used for detonation. The core is detonated first, and then the surrounding holes are detonated. The total delay of the detonator is 1100ms.

[0022] 3) Charge

[0023] All blasting uses emulsified small roll charges, and detonating cords are connected in series in the hole, and the explosion is initiated by the bottom of the hole. The charge density is strictly controlled during the charging process;

[0024] 4) Filling with gun mud

[0025] All blastholes are filled with gun mud, with a filling length of 30 cm;

[0026] 5) Calculation of charge quantity:

[0027] All blasting uses emulsion small roll charges. The specifications of the emulsion small roll are: diameter 32mm, length 300mm, and the net weight of a single emulsion small roll is 300g. The charge amount is calculated based on the actual hole depth of each hole:

[0028] ⑴ The charge amount of the hollow hole Q = 1 × (2 / 0.3) × 0.6 = 4kg;

[0029] ⑵ Charge amount of hollowing auxiliary hole: Q = 4 × (2 / 0.3) × 0.3 = 8 kg;

[0030] ⑶ Charge amount of the first row of holes: Q = 6 × (1.9 / 0.3) × 0.3 = 11.4 kg;

[0031] (4) The charge of the second row of holes, excluding the hollowing holes: Q = 6 × (2 / 0.3) × 0.3 = 12 kg;

[0032] ⑸ Charge amount of the third row of holes: Q = 7 × (2.5 / 0.3) × 0.3 = 17.5 kg;

[0033] The total charge weight is: Q = Q + Q + Q + Q + Q = 52.9 kg. Taking into account the extrusion deformation of the emulsified small rolls and the explosive packaging during the charging process, the final explosive weight is determined to be 72 kg.

[0034] 6) Network laying

[0035] After the charging is completed, connect the 24 detonators in all the charging holes with a networking cable, pull them to the horizontal blasting cable terminal for connection, and conduct a network review again. The networking cables are required to be hung along the vein tunnel to ensure network security and normal detonation.

[0036] The beneficial effects of the present invention are:

[0037] 1. The present invention solves the problem of repeated drilling and blasting in the past for chute drawing. The method can pull the chute into place at one time and put it into use in the shortest time.

[0038] 2. The present invention solves the problem that the size of the chute opening is difficult to control in the past, which poses a great safety risk. After the chute is drawn, the size of the chute opening is only 1.2 meters.

[0039] 3. After using this method, the slope of the chute is 45 degrees, the ore flow is smoother, which is conducive to improving the operating efficiency of the scraper. BRIEF DESCRIPTION OF THE DRAWINGS

[0040] Figure 1 It is a schematic diagram of hole arrangement in step S3 of the present invention.

[0041] Figure 2 It is a schematic diagram of the perforation in step S4 of the present invention.

[0042] Figure 3It is a schematic diagram of the blasting hole in step S5 of the present invention.

[0043] Figure 4 This is a diagram showing the effect of the blasting of the present invention. DETAILED DESCRIPTION

[0044] In order to make the purpose, technical scheme and advantages of the present invention clearer, the present invention is further described in detail below in conjunction with specific embodiments and with reference to the accompanying drawings. It should be understood that these descriptions are only exemplary and are not intended to limit the scope of the present invention. In addition, in the following description, the description of well-known structures and technologies is omitted to avoid unnecessary confusion of the concept of the present invention.

[0045] A method for drawing a chute, characterized in that it comprises the following steps:

[0046] S1, tunnel re-survey, excavation of chute connection road 2 stopped at 2 meters away from the wall of chute 1, and contacted surveyors for on-site re-survey;

[0047] S2, drilling holes. Before trenching, drill holes at each location to determine the penetration distance. If the penetration distance is greater than 2 meters, it is necessary to continue to dig forward. If the penetration distance is less than or equal to 2 meters, the conditions for trenching are met;

[0048] S3, hole arrangement, such as Figure 1 As shown, holes are arranged in the 3.6m×1.2m area below the center of the 4.2m×3.8m heading of the excavation section (i.e., tunnel section 3). The technicians use red paint to mark the hole positions according to the design site. From top to bottom, three rows of deep holes are marked, with angles of 30 degrees, 35 degrees, and 45 degrees, respectively. The depths are 2.2m, 2.3m, and 2.8m, respectively. The hole spacing is 0.6m, and the core is located in the center, including a centering hole, four empty holes, and four auxiliary holes. The angle and depth are consistent with the second row of holes. A total of 28 holes are arranged, including four empty holes and 24 charging holes. The diameter of the centering hole and the empty hole is 76mm ( Figure 1 4 in the middle), the diameter of the remaining holes is 48mm ( Figure 1 5 in );

[0049] S4, perforation, e.g. Figure 2 As shown:

[0050] 1) Use DD2710 trolley for construction drilling;

[0051] 2) During the construction process, strictly follow the given center line to avoid misalignment of the penetration position;

[0052] 3) During the construction process, the holes marked with red paint should be strictly followed, and the driving pressure of the trolley should be controlled during the drilling process to improve the construction quality and avoid missing holes or stringing holes;

[0053] 4) Before construction, multiple exploration holes were carried out according to the design. First, four empty holes were detected at the hollowing position ( Figure 2 6), then select two holes in each of the two gangs of the non-drilling area for detection. Due to the wear of the chute 1 and the irregularity of the well wall, the hole depth is adjusted in time according to the detection depth of each exploration hole on site to avoid the charging hole from penetrating the inner wall of the chute 1;

[0054] 5) Punching angle and hole depth: The construction angle of the first row of six holes is 30 degrees ( Figure 2 5), the construction depth is 2.2m, and the construction angle of the second row of 6 holes is 35 degrees ( Figure 2 5), the construction depth is 2.3m, and the construction angle of the third row of 7 holes is 45 degrees ( Figure 2 5) The construction depth is 2.8m. According to the actual situation of the on-site operation, if there is a through hole phenomenon, it should be reported to the on-site technicians in time. The on-site technicians will adjust the hole depth, mark the through hole, and plug the hole before charging.

[0055] 6) During the perforation process, the inclination angle must be strictly controlled. Two people are required to perform the hole-changing operation, one is responsible for operating the trolley, and the other is responsible for angle measurement and determining the position of the trolley arm. During the operation, a protractor is used for repeated measurements to ensure that the angle is appropriate before drilling the hole;

[0056] 7) To avoid blockage of the eye holes during the bottom hole construction process, the holes should be constructed 10 cm from the ground and filled with explosive bags or special rubber plugs after the operation is completed;

[0057] S5, blasting, such as Figure 3 As shown:

[0058] 1) Blast hole flushing and inspection

[0059] Before blasting, use high-pressure air to blow away the rock debris and residual water in the hole and check whether there are any through holes. If there are any through holes, fill and plug the ends of the through holes.

[0060] 2) Detonator delay time selection

[0061] Digital electronic detonators are used for detonation. The core is detonated first, and then the surrounding holes are detonated. The total delay of the detonator is 1100ms.

[0062] 3) Charge

[0063] All blasting uses emulsified small roll charges, and detonating cords are connected in series in the hole, and the explosion is initiated by the bottom of the hole. The charge density is strictly controlled during the charging process;

[0064] 4) Filling with gun mud

[0065] All blastholes are filled with gun mud, with a filling length of 30 cm;

[0066] 5) Calculation of charge quantity:

[0067] All blasting uses emulsion small roll charges. The specifications of the emulsion small roll are: diameter 32mm, length 300mm, and the net weight of a single emulsion small roll is 300g. The charge amount is calculated based on the actual hole depth of each hole:

[0068] ⑴ The charge amount of the hollow hole Q = 1 × (2 / 0.3) × 0.6 = 4kg;

[0069] (2) Charge amount of hollowing auxiliary hole 7: Q = 4 × (2 / 0.3) × 0.3 = 8 kg;

[0070] ⑶ Charge amount of the first row of holes: Q = 6 × (1.9 / 0.3) × 0.3 = 11.4 kg;

[0071] (4) The charge of the second row of holes, excluding the hollowing holes: Q = 6 × (2 / 0.3) × 0.3 = 12 kg;

[0072] ⑸ Charge amount of the third row of holes: Q = 7 × (2.5 / 0.3) × 0.3 = 17.5 kg;

[0073] The total charge weight is: Q = Q + Q + Q + Q + Q = 52.9 kg. Taking into account the extrusion deformation of the emulsified small rolls and the explosive packaging during the charging process, the final explosive weight is determined to be 72 kg.

[0074] 6) Network laying

[0075] After the charging is completed, connect the 24 detonators in all the charging holes with a networking cable, pull them to the horizontal blasting cable terminal for connection, and conduct a network review again. The networking cables are required to be hung along the vein tunnel to ensure network security and normal detonation.

[0076] Figure 4 This is the effect diagram after blasting. After setting up the vehicle-blocking ore pile and chute safety protection facilities according to the standards, it can be put into use.

[0077] It should be understood that the above specific embodiments of the present invention are only used to illustrate or explain the principles of the present invention, and do not constitute a limitation of the present invention. Therefore, any modifications, equivalent substitutions, improvements, etc. made without departing from the spirit and scope of the present invention should be included in the protection scope of the present invention. In addition, the appended claims of the present invention are intended to cover all changes and modifications that fall within the scope and boundaries of the appended claims, or the equivalent forms of such scope and boundaries.

Claims

1. A method for chute drawing, characterized in that: The following steps are involved: S1. Re-survey of the tunnel. When the chute connecting tunnel (2) is excavated to a point 2 meters away from the wall of the chute (1), the excavation is stopped and the surveying personnel are contacted to conduct on-site re-survey. S2, drilling holes. Before trenching, drilling holes are conducted at each location to determine the penetration distance. If the penetration distance is greater than 2 meters, it is necessary to continue to dig forward. If the penetration distance is less than or equal to 2 meters, the conditions for grooving are met; S3. Hole arrangement: Holes are arranged in the 3.6m×1.2m area below the center of the 4.2m×3.8m tunnel head. The technicians use red paint to mark the hole positions according to the design site. From top to bottom, three rows of deep holes are marked, with angles of 30 degrees, 35 degrees, and 45 degrees, respectively. The depths are 2.2m, 2.3m, and 2.8m, respectively. The hole spacing is 0.6m. The core is located in the center, including a center hole, four empty holes, and four auxiliary holes. The angle and depth are consistent with the second row of holes. A total of 28 holes are arranged, including four empty holes and 24 charging holes. The diameter of the center hole and the empty hole is 76mm, and the diameter of the remaining holes is 48mm. S4, Perforation: 1) Use a trolley for construction drilling; 2) During the construction process, strictly follow the given center line to avoid misalignment of the penetration position; 3) During the construction process, the holes marked with red paint should be strictly followed, and the driving pressure of the trolley should be controlled during the drilling process to improve the construction quality and avoid missing holes or stringing holes; 4) Before construction, multiple exploration holes are carried out according to the design. First, four empty holes are detected at the hollowing position, and then two holes are selected in each of the two gangs of the non-drilling area for detection. Since the chute (1) is worn and the well wall is irregular, the hole depth is adjusted in time according to the detection depth of each exploration hole on site to avoid the charging hole from penetrating the inner wall of the chute (1); 5) Perforation angle and hole depth: The first row of six holes has a construction angle of 30 degrees and a construction depth of 2.2m; the second row of six holes has a construction angle of 35 degrees and a construction depth of 2.3m; the third row of seven holes has a construction angle of 45 degrees and a construction depth of 2.8m. According to the actual situation of the on-site operation, if there is a perforation phenomenon, it should be reported to the on-site technicians in time, and the on-site technicians will adjust the hole depth, mark the perforation, and plug the hole before charging; 6) During the perforation process, the inclination angle must be strictly controlled. Two people are required to perform the hole-changing operation, one is responsible for operating the trolley, and the other is responsible for angle measurement and determining the position of the trolley arm. During the operation, a protractor is used for repeated measurements to ensure that the angle is appropriate before drilling the hole; 7) To avoid blockage of the eye holes during the bottom hole construction process, the holes should be constructed 10 cm from the ground and filled with explosive bags or special rubber plugs after the operation is completed; S5, blasting: 1) Blast hole flushing and inspection Before blasting, use high-pressure air to blow away the rock debris and residual water in the hole and check whether there are any through holes. If there are any through holes, fill and plug the ends of the through holes. 2) Detonator delay time selection Digital electronic detonators are used for detonation. The core is detonated first, and then the surrounding holes are detonated. The total delay of the detonator is 1100ms. 3) Charge All blasting uses emulsified small roll charges, and detonating cords are connected in series in the hole. The bottom of the hole is used for detonation, and the charge density is strictly controlled during the charging process. 4) Filling with gun mud All blastholes are filled with gun mud, with a filling length of 30 cm; 5) Calculation of charge quantity: All blasting uses emulsion small roll charges. The specifications of the emulsion small roll are: diameter 32mm, length 300mm, and the net weight of a single emulsion small roll is 300g. According to the following formula, Q n = Number of holes × (hole depth / length of a single section of drug roll) × net weight of a single section of drug roll. Calculate the charge amount based on the actual hole depth of each hole: ⑴ The charge amount of the hollow hole Q1 = 1 × (2 / 0.3) × 0.6 = 4kg; ⑵ Charge amount of hollowing auxiliary hole: Q2 = 4 × (2 / 0.3) × 0.3 = 8kg; ⑶ Charge amount of the first row of holes: Q3 = 6 × (1.9 / 0.3) × 0.3 = 11.4 kg; (4) The charge of the second row of holes, excluding the hollowing holes: Q4 = 6 × (2 / 0.3) × 0.3 = 12 kg; ⑸ Charge amount of the third row of holes: Q5 = 7 × (2.5 / 0.3) × 0.3 = 17.5 kg; The total charge weight is: Q = Q1 + Q2 + Q3 + Q4 + Q5 = 52.9kg. Taking into account the extrusion deformation of the emulsified small rolls and the explosive packaging factors during the charging process, the final explosive weight is determined to be 72kg; 6) Network laying After the charging is completed, connect the 24 detonators in all the charging holes with a networking cable, pull them to the horizontal blasting cable terminal for connection, and conduct a network review again. The networking cables are required to be hung along the vein tunnel to ensure network security and normal detonation.