Sliding construction method and truss construction method having the same

By using hangers to connect the sliding units to the sliding rails of different heights during the sliding construction, and setting up brackets and rigid structures at the locations, the problem of mismatch between the span of the sliding unit and the track spacing is solved and achieved. The stable sliding of the sliding unit and the complete construction of the truss improve construction efficiency and stability.

CN114737769BActive Publication Date: 2024-10-29CHINA CONSTR SCI & IND CORP LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202210339239.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-04-01
Publication Date
2024-10-29
Estimated Expiration
2042-04-01

AI Technical Summary

Technical Problem

In the existing slip method construction, the span of the slip unit and the spacing of the slip track are not suitable, resulting in the inability to apply the slip construction method, and the problem that the track cannot be slid into place horizontally when the track is not on the same horizontal plane.

Method used

By assembling the sliding unit and the hanger, use the hanger to connect the two ends of the sliding unit on the sliding rails of different heights, slide it into place, and set brackets and rigid structures at the sliding place to form a complete structure. .

Benefits of technology

It solves the problem of mismatch between the span of the sliding unit and the spacing of the sliding track, realizes the stable sliding of the sliding unit and the complete construction of the truss scattered unit, and improves the construction efficiency and stability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114737769B_ABST
    Figure CN114737769B_ABST
Patent Text Reader

Abstract

The present invention discloses a sliding construction method and also discloses a truss construction method with the sliding construction method. The sliding construction method comprises the following steps: assembling a sliding unit; setting up a hanger; setting up one end of the sliding unit on a first sliding track and connecting the other end to a second sliding track through the hanger, wherein the sliding unit and the hanger can slide along the first sliding track and the second sliding track; sliding the sliding unit until it slides into place. The sliding construction method of the present invention can solve the problem of the mismatch between the span of the sliding unit and the interval of the sliding track.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of building construction, and in particular to a sliding construction method and a truss construction method having the same. Background Art

[0002] In the related technology, when parallel construction is required, especially when the site is narrow and the lifting machinery cannot enter and exit, the sliding method of construction is often used. The sliding method of construction means first using a lifting machinery to lift the sliding unit to the designed elevation at one end of the structure, and then using a traction device to slide the sliding unit to the designed position for installation. This new process is often used in the installation of large-span truss structures and grid structures. The sliding bracket is a temporary support structure used to assemble or slide the sliding unit in sliding construction. At the same time, it can ensure the longitudinal and lateral stability of the sliding unit, and can also be used as a traction measure.

[0003] In the sliding construction method, two parallel sliding rails are usually used to carry the two ends of the sliding unit respectively. However, when the interval between the two sliding rails does not match the span of the sliding unit, the sliding construction method cannot be applied. Summary of the invention

[0004] The present invention aims to solve at least one of the technical problems existing in the prior art. To this end, the present invention proposes a sliding construction method, which can solve the problem of the mismatch between the span of the sliding unit and the interval between two sliding tracks.

[0005] The present invention also provides a truss construction method having the above-mentioned sliding construction method.

[0006] According to the first aspect of the present invention, the sliding construction method includes the following steps: assembling a sliding unit; slidably placing one end of the sliding unit on a first sliding track, and slidably connecting the other end of the sliding unit to a second sliding track via a hanger; and sliding the sliding unit until it slides into place.

[0007] The sliding construction method according to the embodiment of the present invention has at least the following beneficial effects: first assemble or build the sliding unit and the hanger separately, then place one end of the assembled sliding unit on the first sliding track, and connect the other end to the second sliding track through the hanger, so that the sliding unit can slide on the first sliding track and the second sliding track through the connection of the hanger until the sliding unit slides into place, thereby solving the problem of incompatibility between the span of the sliding unit and the width of the sliding track, and also solving the problem that the first sliding track and the second sliding track are not in the same horizontal plane and the sliding unit cannot be slid horizontally into place.

[0008] According to some embodiments of the present invention, the following steps are also included: setting up a supporting tire frame; wherein the supporting tire frame is used to assemble the sliding unit.

[0009] According to some embodiments of the present invention, slidably connecting the other end of the sliding unit to the second sliding track via a hanger includes the following steps: disposing a sliding bracket on the second sliding track; wherein the sliding bracket is capable of sliding along the sliding track; connecting the sliding bracket to the hanger; and connecting the hanger to the other end of the sliding unit.

[0010] According to some embodiments of the present invention, the sliding unit and the bottom surface of the sliding bracket are both provided with a limiting structure for engaging with the sliding rail.

[0011] According to some embodiments of the present invention, the sliding bracket includes a bracket body, a high leg group and a low leg group, the high leg group includes at least two first legs and a second leg arranged in sequence along the sliding forward direction, and the low leg group includes at least one third leg arranged at the front end of the high leg group, and the length of the third leg is less than the length of the first leg and the length of the second leg. Sliding the sliding unit until it slides into place includes the following steps: the bracket body is carried by the first leg and the second leg to slide along the low-elevation sliding track on the second sliding track.

[0012] According to some embodiments of the present invention, the step of supporting the sliding of the bracket body by the first leg abutting against the low-elevation sliding track and the third leg abutting against the high-elevation sliding track further includes the following step: removing the second leg.

[0013] A truss construction method according to an embodiment of the second aspect of the present invention also includes the following steps: including the above-mentioned sliding construction method; wherein the sliding unit is a truss loose assembly unit; a rigid structure is arranged at the sliding position of the second sliding track; the rigid structure is connected to the truss loose assembly unit after sliding into place to form a complete truss.

[0014] The sliding construction method of the truss loose-assembly unit according to the embodiment of the present invention has at least the following beneficial effects: the connection between the span of the truss loose-assembly unit and the interval of the mismatched sliding track is realized by the hanger, and a rigid structure is arranged at the sliding position of the second sliding track so as to be connected with the truss loose-assembly unit after sliding into place to form a complete truss.

[0015] According to some embodiments of the present invention, the rigid structure is connected to the truss loose-assembly unit after sliding into place to form a complete truss, which includes the following steps: adding an embedding section between the truss loose-assembly unit and the rigid structure, and connecting the truss loose-assembly unit and the rigid structure via the embedding section.

[0016] According to some embodiments of the present invention, the following steps are included: a reinforcement section is provided at one end of the truss assembled unit for connecting to the hanger, so that the reinforcement section is connected between the upper chord and the lower chord of the truss assembled unit.

[0017] According to some embodiments of the present invention, the step of connecting the rigid structure with the truss loose-fitting units after sliding into place to form a complete truss comprises the following steps: cutting off the reinforcement segment.

[0018] Additional aspects and advantages of the present invention will be given in part in the following description and in part will be obvious from the following description, or will be learned through practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] The present invention will be further described below with reference to the accompanying drawings and embodiments, wherein:

[0020] Figure 1 A flow chart of a sliding construction method according to an embodiment of the first aspect of the present invention;

[0021] Figure 2 It is a flow chart of slidably connecting the other end of the sliding unit to the second sliding track through the hanger in the embodiment of the first aspect of the present invention;

[0022] Figure 3 A top view of the connection between the hanger and the sliding bracket of the present invention;

[0023] Figure 4 Flow chart of step S400 in the embodiment of the first aspect of the present invention;

[0024] Figure 5 It is a structural schematic diagram of the sliding support of the present invention sliding on a low-elevation sliding track;

[0025] Figure 6 It is a schematic diagram of the structure of the sliding bracket sliding across the elevation of the present invention.

[0026] Figure 7 A flow chart of a truss construction method according to an embodiment of the second aspect of the present invention;

[0027] Figure 8 It is a structural schematic diagram of the connection bracket of the sliding front truss loose assembly unit in the embodiment of the second aspect of the present invention;

[0028] Fig. 9 It is a structural schematic diagram of the rigid structure of the truss loose-spliced ​​units connected after sliding into place in the embodiment of the second aspect of the present invention;

[0029] Fig.10 It is a structural schematic diagram of a complete truss after the truss construction is completed in the embodiment of the second aspect of the present invention;

[0030] Reference numerals:

[0031] 100, complete truss; 110, truss loose assembly unit; 111, reinforcement section; 120, rigid structure; 130, patching section; 200, hanger; 300, first sliding track; 400, second sliding track; 500, supporting frame; 600, sliding bracket; 610, first leg; 620, second leg; 630, third leg; 700, low-elevation sliding track; 800, high-elevation sliding track. DETAILED DESCRIPTION

[0032] Embodiments of the present invention are described in detail below, examples of which are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and cannot be understood as limiting the present invention.

[0033] In the description of the present invention, it should be understood that descriptions involving orientations, such as up, down, front, back, left, right, etc., and orientations or positional relationships indicated are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.

[0034] In the description of the present invention, "several" means more than one, "many" means more than two, "greater than", "less than", "exceed", etc. are understood to exclude the number itself, and "above", "below", "within", etc. are understood to include the number itself. If there is a description of "first" or "second", it is only used for the purpose of distinguishing the technical features, and cannot be understood as indicating or implying the relative importance or implicitly indicating the number of the indicated technical features or implicitly indicating the order of the indicated technical features.

[0035] In the description of the present invention, unless otherwise clearly defined, terms such as setting, installing, connecting, etc. should be understood in a broad sense, and technicians in the relevant technical field can reasonably determine the specific meanings of the above terms in the present invention based on the specific content of the technical solution.

[0036] In the description of the present invention, the description with reference to the terms "one embodiment", "some embodiments", "illustrative embodiments", "examples", "specific examples", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.

[0037] Reference below Figures 1 to 10 A sliding construction method according to an embodiment of the present invention and a sliding construction method of a truss loose assembly unit 110 having the same are described.

[0038] refer to Figure 1 As shown, according to a sliding construction method of an embodiment of the first aspect of the present invention, the sliding construction method comprises the following steps:

[0039] S200: Assembling sliding units;

[0040] S300; one end of the sliding unit can be slidably mounted on the first sliding track 300, and the other end of the sliding unit can be slidably connected to the second sliding track 400 through the hanger 200;

[0041] S400: Slide the sliding unit until it slides into place.

[0042] It can be understood that the sliding unit and the hanger 200 are first assembled or built separately, and then one end of the assembled sliding unit is slidably placed on the first sliding rail 300, and the other end is slidably connected to the second sliding rail 400 through the hanger 200, so that the sliding unit can slide on the first sliding rail 300 and the second sliding rail 400 through the connection of the hanger 200 until the sliding unit slides into place, thereby solving the problem of incompatibility between the span of the sliding unit and the interval of the sliding rail.

[0043] It should be understood that the sliding unit may be a building construction unit that needs to slide, such as a truss, a grid or a bridge.

[0044] refer to Figure 1 and Figure 5 , and also includes the following steps:

[0045] S100: Setting up a supporting frame 500; wherein the supporting frame 500 is used to assemble the sliding unit.

[0046] It is understandable that by setting up a supporting frame 500 and assembling the sliding unit and the hanger 200 on the supporting frame 500, it is convenient to directly connect the sliding unit and the hanger 200 to the first sliding rail 300 and the second sliding rail 400 having a certain height.

[0047] It should be understood that the support tire frame 500 is also a temporary support structure. After all the sliding units sliding on the first sliding track 300 and the second sliding track 400 have slid into place, the support tire frame 500 can be removed.

[0048] refer to Figure 2 , Figure 5 and Figure 8In step S300, the other end of the sliding unit is slidably connected to the second sliding track 400 through the hanger 200, which includes the following steps:

[0049] S310: a sliding bracket 600 is arranged on the second sliding track 400; wherein the sliding bracket 600 can slide along the sliding track;

[0050] S320: Connect the sliding bracket 600 to the hanger 200;

[0051] S330: Connect the hanger 200 to the other end of the sliding unit.

[0052] As shown in the figure, a sliding bracket 600 that can slide is respectively arranged on the second sliding track 400, and a hanger 200 is set on the supporting tire frame 500, the hanger 200 is connected to the sliding bracket 600, and the other end of the sliding unit is connected to the hanger 200, thereby realizing the connection between the other end of the sliding unit and the second sliding track 400, and making the entire sliding connection more secure.

[0053] It should be understood that there is no order between step S320 and step S330.

[0054] It is understandable that the bottom surfaces of the sliding unit and the sliding bracket 600 are both provided with a limiting structure for engaging with the sliding track. For example, in this embodiment, a limiting structure is provided on the bottom surface of one end of the sliding unit mounted on the first sliding track 300, and a limiting structure is also provided on the bottom surface of the sliding bracket 600, so that the sliding unit and the connected sliding bracket 600 can slide along the direction of the sliding track without deviation. Figure 3 , Fig. 9 and Fig.10 It can be understood that the sliding bracket includes a bracket body, a high leg group and a low leg group, the high leg group includes at least two first legs 610 and a second leg 620 arranged in sequence along the sliding forward direction, and the low leg group includes at least one third leg 630 arranged at the front end of the high leg group, and the length of the third leg 630 is less than the length of the first leg 610 and the length of the second leg 620;

[0055] Wherein, step S400 includes the following steps:

[0056] S410: The first supporting leg 610 and the second supporting leg 620 support the support body to slide along the low-elevation sliding track 700 on the second sliding track 400;

[0057] S420: When the sliding track base surface on the second sliding track 400 rises, the first leg 610 abutting on the low-elevation sliding track 700 and the third leg 630 abutting on the high-elevation sliding track 800 support the bracket body to slide.

[0058] It can be understood that the sliding bracket 600 includes a bracket body and legs. When the low-elevation sliding track 700 slides, the bracket body is supported by the first leg 610 and the second leg 620 and slides along the low-elevation sliding track 700. When crossing the elevation, the third leg 630 located at the front end of the first leg 610 and the second leg 620 first touches the base surface of the high-elevation sliding track 800, and the third leg 630 and the first leg 610 located behind the second leg 620 carry the bracket body to slide. Therefore, the length of the third leg 630 needs to be smaller than the length of the first leg 610 and the second leg 620, so as to achieve sliding of the sliding track across the elevation.

[0059] refer to Fig. 9 and Fig.10 In step S420, the first leg 610 abutting on the low-elevation sliding track 700 and the third leg 630 abutting on the high-elevation sliding track 800 support the support body to slide, and the following steps are also included:

[0060] S421: remove the second leg 620.

[0061] It is understandable that after removing the second leg 620, the support body and the sliding unit completely rely on the first leg 610 and the third leg 630 to achieve sliding across the elevation until the sliding unit slides into place. Due to the support of the first leg 610 and the third leg 630, the height of the support body itself does not change during the elevation crossing process and can slide across the elevation steadily, and it is very stable and safe even in the process of removing the second leg 620.

[0062] Specifically, the support body is a triangular structure. Figures 9 and 10 As shown, in this embodiment, the bracket body is a triangular structure, thereby improving the stability of the sliding unit during the sliding process.

[0063] It should be understood that the sliding unit in the embodiment of the present invention is driven by a driving mechanism to achieve sliding on the sliding track.

[0064] like Figures 4 to 5 As shown, a truss construction method according to an embodiment of the second aspect of the present invention includes the following steps:

[0065] S1000: The sliding construction method of the first embodiment described above; wherein the sliding unit is a truss loose assembly unit 110;

[0066] S2000: Arranging a stiffening structure 120 at the sliding position of the second sliding track 400;

[0067] S3000: Connect the rigid structure 120 to the truss loose assembly units 110 that have been slid into place to form a complete truss 100.

[0068] It can be understood that the connection between the span of the truss loose-assembly unit 110 and the mismatched sliding track interval is achieved through the hanger 200, and a rigid structure 120 is set at the sliding position of the second sliding track 400 to connect with the truss loose-assembly unit 110 after sliding into place to form a complete truss 100.

[0069] It should be understood that there is no order of precedence between step S100, step S200, step S310, step S320, step S330, step S410, step S420, step S421 and step S2000 in step 1000.

[0070] refer to Figure 6 and Figure 7 , wherein step S3000 includes the following steps:

[0071] S3100 : adding an inlay segment 130 between the truss loose-assembly unit 110 and the rigid structure 120 , and connecting the truss loose-assembly unit 110 and the rigid structure 120 via the inlay segment 130 .

[0072] It can be understood that a certain amount of avoidance space is left between the truss loose-assembly unit 110 and the rigid structure 120 to avoid interference between the truss loose-assembly unit 110 and the rigid structure 120 during the sliding process. Finally, the avoidance space is filled by the embedded segment 130 to achieve the connection between the truss loose-assembly unit 110 and the rigid structure 120.

[0073] refer to Figures 4 to 5 , including the following steps:

[0074] S4000 : a reinforcement section 111 is provided at one end of the truss assembly unit 110 for connecting to the hanger 200 , so that the reinforcement section 111 is connected between the upper chord and the lower chord of the truss assembly unit 110 .

[0075] It is understandable that since one end of the truss loose-assembly unit 110 connected to the hanger 200 needs to be connected to the rigid structure 120 to form a complete truss 100, in order to prevent the lower chord from falling and deforming, a reinforcement section 111 is connected between the upper chord and the lower chord, thereby increasing the stability of the truss loose-assembly unit 110 structure.

[0076] It should be understood that step S4000 should be any step before step S400.

[0077] refer to Figure 4 , Figure 6 and Figure 7 , wherein step S3000 includes the following steps:

[0078] S3200: Cut off the reinforcement section 111.

[0079] It is understandable that after the truss loose-assembly unit 110 and the rigid structure 120 are connected, the reinforcement section 111 can be cut off, and after the cutting, a complete truss 100 is formed.

[0080] It should be understood that after sliding into place, the limiting structure at the bottom of one end of the truss loose assembly unit 110 connected to the first sliding track 300 can be removed, and this end can be fixed to the existing structure in place through a hinge support, thereby achieving the fixation of the complete truss 100.

[0081] The embodiments of the present invention are described in detail above in conjunction with the accompanying drawings, but the present invention is not limited to the above embodiments. Various changes can be made within the knowledge of ordinary technicians in the relevant technical field without departing from the purpose of the present invention. In addition, the embodiments of the present invention and the features in the embodiments can be combined with each other without conflict.

Claims

1. The sliding construction method is characterized in that: The sliding construction method comprises the following steps: Set up support frame; Assembling a sliding unit on the supporting tire frame; One end of the sliding unit is slidably mounted on the first sliding track, and the other end of the sliding unit is slidably connected to the second sliding track through a hanger; Slide the sliding unit until it slides into place; wherein, The method of slidably connecting the other end of the sliding unit to the second sliding track via a hanger comprises the following steps: A sliding bracket is arranged on the second sliding track; wherein the sliding bracket can slide along the sliding track direction, and comprises a bracket body, a high leg group and a low leg group, wherein the high leg group comprises at least two first legs and a second leg arranged in sequence along the sliding forward direction, and the low leg group comprises at least one third leg arranged at the front end of the high leg group, and the length of the third leg is less than the length of the first leg and the length of the second leg; Connecting the sliding bracket to the hanger; Connect the hanger to the other end of the sliding unit; wherein, The step of sliding the sliding unit until it is in place comprises the following steps: The support body is carried by the first support leg and the second support leg to slide along the low-elevation sliding track on the second sliding track; When the sliding track base surface on the second sliding track rises, the bracket body slides supported by the first leg abutting on the low-elevation sliding track and the third leg abutting on the high-elevation sliding track.

2. The sliding construction method according to claim 1, characterized in that: The bottom surfaces of the sliding unit and the sliding bracket are both provided with limiting structures for engaging with the sliding rail.

3. The sliding construction method according to claim 1, characterized in that: The first leg abutting on the low-elevation sliding track and the third leg abutting on the high-elevation sliding track carry the support body to slide, and further comprises the following steps: Remove the second leg.

4. A truss construction method, characterized in that: The following steps are included: The sliding construction method according to any one of claims 1 to 3; wherein the sliding unit is a truss loose assembly unit; A stiff structure is provided at the sliding position of the second sliding track; The rigid structure is connected to the loosely assembled truss units after sliding into place to form a complete truss.

5. The truss construction method according to claim 4, characterized in that: Connecting the rigid structure with the truss loose assembly unit after sliding into place to form a complete truss includes the following steps: An inlay section is added between the truss loose-assembly unit and the rigid structure, and the truss loose-assembly unit and the rigid structure are connected via the inlay section.

6. The truss construction method according to claim 4, characterized in that: The following steps are included: A reinforcement section is arranged at one end of the truss loose-assembly unit for connecting with the hanger, so that the reinforcement section is connected between the upper chord and the lower chord of the truss loose-assembly unit.

7. The truss construction method according to claim 6, characterized in that: The method of connecting the rigid structure with the truss loose assembly units after sliding into place to form a complete truss includes the following steps: The reinforcement section is cut away.

Citation Information

Patent Citations

  • Large-span square steel pipe truss and accumulative sliding construction method thereof

    CN104929373A

  • Ring truss high-altitude in-situ scattered splicing construction method

    CN111945891A

  • A auxiliary device for varying construction of sliding of long truss

    CN207110478U