A method for distributing power output of cascade hydropower stations based on segmentation constraints
Through the method based on segmented constraints, the output allocation of cascade hydropower stations is calculated and adjusted, the problem of uneven output allocation of cascade hydropower stations is solved, the stable operation of each hydropower station and the satisfaction of short-term power generation plans are achieved, and the calculation efficiency and result determination are improved. .
Patent Information
- Application Number
- CN202210608137.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-05-31
- Publication Date
- 2024-11-05
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing technology has failed to effectively achieve the reasonable and efficient allocation of cascade hydropower station output among various hydropower stations, resulting in the stable and reliable operation of cascade reservoir groups and the short-term power generation plan arrangements being difficult to meet.
The output distribution method of cascade hydropower stations based on segmented constraints is adopted. By calculating the initial output distribution of each hydropower station, the constraint failure matrix record, the output adjustment by time period and the error division, the output output of each hydropower station meets the maximum and minimum constraint boundary and meets the daily power generation and Requirements for power generation during the period.
It has achieved safe and stable operation of various hydropower stations, optimized output allocation, met short-term power generation planning arrangements, improved calculation efficiency and result certainty, and provided a reliable management reference for cascade reservoir scheduling.
Smart Images

Figure CN114881524B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to an output distribution method of a cascade hydropower station based on segmentation constraints, and belongs to the technical field of water conservancy and hydropower engineering. Background Art
[0002] With the advent of the "dual carbon" era, the energy system will transform towards clean, low-carbon, safe and efficient. Among them, my country is rich in hydropower resources and has a complete reserve of hydropower generation technology. It has formed an industrial cluster advantage. By 2020, my country's hydropower installed capacity and power generation will reach 3701.6 billion kW and 1355.2 billion kWh respectively. Hydropower continues to play a cornerstone role in the field of renewable energy. More and more river basin reservoir groups have achieved cascade hydropower joint dispatching and power generation. Generally, the short-term dispatching boundaries of each hydropower station are calculated through the long-term optimization dispatching of cascade reservoirs, so as to make full use of the long-term storage capacity of the reservoir, and further combine the day-ahead dispatching plan to formulate the short-term output mode of cascade hydropower. However, at present, based on the actual operation requirements of the hydropower station group, it has not yet been realized to reasonably and efficiently distribute the cascade output to each hydropower station to ensure the stable and reliable operation of the cascade reservoir group and meet the short-term power generation plan arrangement of the original cascade hydropower. Summary of the invention
[0003] In order to overcome the shortcomings of the prior art, the present invention provides a cascade hydropower station output allocation method based on segmented constraints, which allocates the cascade hydropower output within a short-term operating cycle to the power generation plan arrangement of each cascade hydropower station. On the one hand, it maintains the safe and stable operation of each hydropower station, and on the other hand, optimizes the output of each hydropower station and meets the short-term power generation plan arrangement of the original cascade hydropower.
[0004] The technical solution of the present invention:
[0005] The present invention provides a method for distributing the output of cascade hydropower stations based on segmentation constraints, comprising the following steps:
[0006] Step A: Known short-term planned cascade hydropower hourly output Average daily output of cascade hydropower stations Maximum output of each cascade hydropower station and minimum effort Constraints, the short-term operation mode uses days as the cycle and hours as the calculation step;
[0007] Step B: Calculate the initial output distribution of each hydropower station in the cascade Specifically:
[0008]
[0009]
[0010] In the formula, K iis the daily average output distribution coefficient of the i-th hydropower station in the cascade, is the initial output allocation result of the i-th hydropower station in the t-th period, i = 1...L, L is the number of hydropower stations in the cascade, t = 1...T, T is the number of time periods within a day, T = 24;
[0011] Step C: Calculate the constraint destruction matrix P of the output distribution results of each hydropower station in the cascade i,t , specifically:
[0012]
[0013]
[0014]
[0015] In the formula, the constraint destruction matrix P i,t Record the specific value of the output of the i-th hydropower station in the cascade that exceeds the maximum and minimum output constraint boundaries of the hydropower station. The mapping function relationship f1 can be expressed as x=(1,2,3L);P i is the error between the daily power generation of the ith hydropower station in the cascade and its given daily power generation, P t It is the error between the power generation of cascade hydropower in each period and its given period;
[0016] Step D: Adjust the output of each hydropower station in the cascade in each time period to ensure that the daily power generation of each hydropower station after adjustment is equal to its given daily power generation, specifically:
[0017]
[0018] In the formula, is the average daily output of the i-th hydropower station in the cascade, is the output allocation result of the i-th hydropower station in the t-th period after adjustment, Δt is the calculation step, h,i=1……L, L is the number of hydropower stations in the cascade, t=1……T, T is the number of time periods within a day, T=24;
[0019] Step E: Adjust the output of each hydropower station in the cascade in each time period to ensure that the adjusted power generation of the cascade hydropower in each time period is equal to its given power generation in the given time period, specifically:
[0020]
[0021] In the formula, For the short-term planned cascade hydropower output in period t, is the output allocation result of the i-th hydropower station in the t-th period after adjustment, Δt is the calculation step, h,i=1…L, L is the number of hydropower stations in the cascade, t=1…T, T is the number of time periods within a day, T=24.
[0022] Preferably, step D specifically comprises:
[0023] Step D1: Calculate the output distribution coefficient of each stage in each period:
[0024]
[0025] In the formula, K t is the average output allocation coefficient of cascade hydropower in the tth period of the day;
[0026] Step D2: Calculate repeatedly until the error P between the adjusted daily power generation of each hydropower station and its given daily power generation is i Reduced to within a certain range, the cycle process is divided into two parts, specifically:
[0027] ①According to K t Adjust the hourly output process of the i-th hydropower station in the cascade to stabilize P i :
[0028]
[0029]
[0030]
[0031]
[0032] ② Adjust the average daily output of the i-th hydropower station in the cascade Comply with the maximum and minimum output constraints:
[0033]
[0034]
[0035]
[0036] …
[0037] until P i (2n) <Δ i ;
[0038] In the formula, F t,i is the output error distribution of the i-th hydropower station in the t-th period, is the first output allocation result of the i-th hydropower station in the t-th period in the n-th cycle calculation, is the second output allocation result of the i-th hydropower station in the t-th period in the n-th cycle calculation, Δ i is the error range.
[0039] Preferably, step E specifically comprises:
[0040] Step E1: Divide the error of cascade hydropower output by time period:
[0041]
[0042]
[0043] R t =P t 1 / D
[0044] In the formula, After the output distribution in step D2, the output of the cascade hydropower in period t is: Calculated in step D2, D is a constant, R t The output error of cascade hydropower in each period is divided into D parts;
[0045] Step E2: Adjust the output of each hydropower station within the variable output range, and stabilize P through cyclic calculation t , specifically:
[0046] m=0
[0047]
[0048]
[0049]
[0050]
[0051]
[0052]
[0053]
[0054] m=m+sum(Z i (n) )
[0055] …
[0056] until m≥D;
[0057] In the formula, is the output allocation result of the i-th hydropower station in the t-th period in the n-th cycle calculation, is the output that can be reduced by the i-th hydropower station in the t-th period, is the output that can be increased by the i-th hydropower station in the t-th period, is the output that needs to be reduced in period t, is the output required to be increased in period t, Y t,i =1 means that the output of the i-th hydropower station can be adjusted in the t-th period, Z i =1 means that the i-th hydropower station can adjust its output in all periods of the day, T is the number of periods within the day, T=24, m is the number of superimposed outputs recorded in the cycle calculation, and it ends when m≥D, and the output allocation result of the i-th hydropower station in the t-th period in the cascade is obtained
[0058] Beneficial Effects
[0059] According to the actual operation requirements of the cascade hydropower station groups, the present invention allocates the cascade hydropower output within a short-term operation cycle to the power generation plan arrangement of each cascade hydropower station, so that each power station meets three constraint sets: 1. output constraints of each power station; 2. the daily power generation of each hydropower station (the sum of the 24-hour output of the cascade output allocated to the station) is consistent with its given daily power generation (because it is a daily regulation hydropower station, the sum of the allocated daily power generation is equal to the initial daily average output multiplied by 24 hours, so that the initial and final water levels of the day can be kept consistent with the normal water level to the greatest extent, and the daily regulation reservoir can be kept stable in operation); 3. the adjusted power generation of the cascade hydropower in each time period (the sum of the outputs of 6 power stations in the time period) is equal to its given time period power generation (the planned power generation arrangement of the cascade hydropower in the time period); the present invention is a cascade hydropower station output allocation method based on segmented constraints, which, on the one hand, maintains the safe and stable operation of each hydropower station, and on the other hand, optimizes the output of each hydropower station and meets the short-term power generation plan arrangement of the original cascade hydropower. The example analysis calculation results are reliable and effective, and can provide a reference for the operation and management of the cascade reservoir scheduling project. BRIEF DESCRIPTION OF THE DRAWINGS
[0060] Figure 1 It is the short-term water level regulation and output process of the hydropower station;
[0061] Figure 2 It is the short-term water level regulation and output process of the hydropower station;
[0062] Figure 3 It is the short-term water level regulation and output process of the hydropower station③;
[0063] Figure 4 It is the short-term water level regulation and output process of the hydropower station;
[0064] Figure 5 It is the short-term water level regulation and output process of the hydropower station;
[0065] Figure 6 It is the short-term water level regulation and output process of the hydropower station⑥. DETAILED DESCRIPTION
[0066] The present application will be further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the relevant invention, rather than to limit the invention. It should also be noted that, for ease of description, only the parts related to the relevant invention are shown in the accompanying drawings.
[0067] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments. The following embodiments are used to illustrate the present invention, but are not intended to limit the scope of the present invention.
[0068] Example
[0069] The short-term operation mode uses the day as the cycle and the hour as the calculation step. The short-term plan cascade hydropower output is hourly Average daily output of cascade hydropower stations Maximum output of each cascade hydropower station and minimum effort The constraint-related data are shown in Tables 1 and 2, taking six hydropower stations as an example:
[0070] Table 1 Relevant data of cascade hydropower stations
[0071]
[0072] Calculate the initial output distribution of each hydropower station in the cascade Specifically:
[0073]
[0074]
[0075] In the formula, K i is the daily average output distribution coefficient of the i-th hydropower station in the cascade. The calculation results are shown in Table 1. is the initial output allocation result of the i-th hydropower station in the t-th period, i=1...L, L is the number of hydropower stations in the cascade, t=1...T, T is the number of time periods in a day, T=24, and the calculation results are shown in Table 2:
[0076] Table 2 Initial output distribution of cascade hydropower stations
[0077]
[0078] Calculate the output distribution result of each hydropower station in the cascade and the constraint destruction matrix P i,t , specifically:
[0079]
[0080]
[0081]
[0082] In the formula, the constraint destruction matrix P i,t Record the specific value of the output of the i-th hydropower station in the cascade that exceeds the maximum and minimum output constraint boundaries of the hydropower station. The mapping function relationship f1 can be expressed as x=(1,2,3L);P i is the error between the daily power generation of the ith hydropower station in the cascade and its given daily power generation, P t is the error between the power generation of cascade hydropower in each period and its given period; taking Table 2 as an example, the output values that violate the output constraints of each hydropower station are marked in dark colors, and the constraint violation matrix obtained based on this is shown in Table 3:
[0083] Table 3 Constraint failure matrix of cascade hydropower station group
[0084]
[0085] Calculate the output distribution coefficient of each stage in each period
[0086]
[0087] In the formula, K t is the average output allocation coefficient of cascade hydropower in the t period of the day. The calculation results are shown in the last column of Table 2;
[0088] The calculation is repeated until the error P between the daily power generation of each hydropower station after adjustment and its given daily power generation is i Reduced to within a certain range, the cycle process is divided into two parts, specifically:
[0089] ①According to K t Adjust the hourly output process of the i-th hydropower station in the cascade to stabilize P i :
[0090]
[0091]
[0092]
[0093]
[0094] ② Adjust the average daily output of the i-th hydropower station in the cascade Comply with the maximum and minimum output constraints:
[0095]
[0096]
[0097]
[0098] …
[0099] until P i (2n) <Δ i
[0100] In the formula, F t,i is the output error distribution of the i-th hydropower station in the t-th period, is the first output allocation result of the i-th hydropower station in the t-th period in the n-th cycle calculation, is the second output allocation result of the i-th hydropower station in the t-th period in the n-th cycle calculation, Δ i As the error range, 0.0001 kW is taken, and the output distribution results are shown in Table 4:
[0101] Table 4 Output distribution of cascade hydropower stations - smoothing out the error in daily power generation of each hydropower station
[0102]
[0103]
[0104] Carry out time-period error division of cascade hydropower output
[0105]
[0106]
[0107] R t =P t 1 / D
[0108] In the formula, After the output distribution in step D2, the output of the cascade hydropower in period t is: Calculated in step D2, D is a constant, take 10000, R t The output error of cascade hydropower in each period is divided into D parts;
[0109] Adjust the output within the variable range of each hydropower station, and stabilize P through cyclic calculation t , specifically:
[0110] m=0
[0111]
[0112]
[0113]
[0114]
[0115]
[0116]
[0117]
[0118]
[0119] …
[0120] until m≥D
[0121] In the formula, is the output allocation result of the i-th hydropower station in the t-th period in the n-th cycle calculation, is the output that can be reduced by the i-th hydropower station in the t-th period, is the output that can be increased by the i-th hydropower station in the t-th period, is the output that needs to be reduced in period t, is the output required to be increased in period t, Y t,i =1 means that the output of the i-th hydropower station can be adjusted in the t-th period, Z i =1 means that the i-th hydropower station can adjust its output in all periods of the day, T is the number of periods within the day, T=24, m is the number of superimposed outputs recorded in the cycle calculation, when m≥D, it indicates that the error output has been fully included in the space where each hydropower station can adjust its output, and the output distribution result of the i-th hydropower station in the cascade in the t-th period is obtained See Table 5:
[0122] Table 5 Output distribution of cascade hydropower stations - smoothing out the hourly power generation error of cascade hydropower stations
[0123]
[0124]
[0125] Through the above cascade hydropower output allocation, the output constraints of each hydropower station are met, and at the same time, the daily hydropower of each hydropower station is consistent with the hydropower of the long-term dispatch boundary. The hydropower of the cascade hydropower in each period is consistent with the short-term planned power generation. In the process of adjusting the output of each hydropower station, the constraint destruction matrix P is proposed. i,t , Daily average output distribution coefficient K of each hydropower station i , Average output distribution coefficient K of cascade hydropower in each period t , and then, according to the distribution coefficient K i To smooth out the daily power generation error of each hydropower station, according to the allocation coefficient K tSmoothing out the errors in power generation of the cascade at each time period can, on the one hand, increase the calculation speed and obtain deterministic output allocation results; on the other hand, it can maintain the output attributes of each power station in the original cascade to the greatest extent, thus providing guarantee for the reasonable operation of each hydropower station.
[0126] like Figures 1 to 6 As shown in the figure, the actual operation process of the cascade hydropower station group is obtained by back-calculating the water level process based on the output of each hydropower station in each period. Among them, power station ② is an annual regulation reservoir power station, and the rest are daily regulation reservoir power stations. Under the output allocation result, they all meet the water level and discharge flow constraints. The initial and final node errors of the water level of the daily regulation hydropower station are both within 0.05m, which meets the long-term stable operation conditions.
[0127] The above is only a preferred specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that can be easily thought of by a person skilled in the art within the technical scope disclosed in the embodiments of the present invention should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.
Claims
1. A method for distributing the output of cascade hydropower stations based on segmented constraints, characterized in that: The following steps are involved: Step A: Known short-term planned cascade hydropower hourly output Average daily output of cascade hydropower stations Maximum output of each cascade hydropower station and minimum effort Constraints, the short-term operation mode uses days as the cycle and hours as the calculation step; Step B: Calculate the initial output distribution of each hydropower station in the cascade Specifically: In the formula, K i is the daily average output distribution coefficient of the i-th hydropower station in the cascade, is the initial output allocation result of the i-th hydropower station in the t-th period, i = 1...L, L is the number of hydropower stations in the cascade, t = 1...T, T is the number of time periods within a day, T = 24; Step C: Calculate the constraint destruction matrix P of the output distribution results of each hydropower station in the cascade i,t , specifically: In the formula, the constraint destruction matrix P i,t Record the specific value of the output of the i-th hydropower station in the cascade that exceeds the maximum and minimum output constraint boundaries of the hydropower station. The mapping function relationship f1 can be expressed as x=(1,2,3…);P i is the error between the daily power generation of the ith hydropower station in the cascade and its given daily power generation, P t It is the error between the power generation of cascade hydropower in each period and its given period; Step D: Adjust the output of each hydropower station in the cascade in each time period to ensure that the daily power generation of each hydropower station after adjustment is equal to its given daily power generation, specifically: In the formula, is the average daily output of the i-th hydropower station in the cascade, is the output allocation result of the i-th hydropower station in the t-th period after adjustment, Δt is the calculation step, h,i=1……L, L is the number of hydropower stations in the cascade, t=1……T, T is the number of time periods within a day, T=24; Step D1: Calculate the output distribution coefficient of each stage in each period In the formula, K t is the average output allocation coefficient of cascade hydropower in the tth period of the day; Step D2: Calculate repeatedly until the error P between the adjusted daily power generation of each hydropower station and its given daily power generation is i Reduced to within a certain range, the cycle process is divided into two parts, specifically: ①According to K t Adjust the hourly output process of the i-th hydropower station in the cascade to stabilize P i : ② Adjust the average daily output of the i-th hydropower station in the cascade Comply with the maximum and minimum output constraints: …… untilP i (2n) <Δ i In the formula, F t,i is the output error distribution of the i-th hydropower station in the t-th period, is the first output allocation result of the i-th hydropower station in the t-th period in the n-th cycle calculation, is the second output allocation result of the i-th hydropower station in the t-th period in the n-th cycle calculation, Δ i is the error range; Step E: Adjust the output of each hydropower station in the cascade in each time period to ensure that the adjusted power generation of the cascade hydropower in each time period is equal to its given power generation in the given time period, specifically: In the formula, For the short-term planned cascade hydropower output in period t, is the output allocation result of the i-th hydropower station in the t-th period after adjustment, Δt is the calculation step, h,i=1……L, L is the number of hydropower stations in the cascade, t=1……T, T is the number of time periods within a day, T=24; Step E1: Divide the error of cascade hydropower output by time period: R t =P t 1 / D; In the formula, After the output distribution in step D2, the output of the cascade hydropower in period t is: Calculated in step D2, D is a constant, R t The output error of cascade hydropower in each period is divided into D parts; Step E2: Adjust the output of each hydropower station within the variable output range, and stabilize P through cyclic calculation t , specifically: m=0 …… until m ≥ D; In the formula, is the output allocation result of the i-th hydropower station in the t-th period in the n-th cycle calculation, is the output that can be reduced by the i-th hydropower station in the t-th period, is the output that can be increased by the i-th hydropower station in the t-th period, is the output that needs to be reduced in period t, is the output required to be increased in period t, Y t,i =1 means that the output of the i-th hydropower station can be adjusted in the t-th period, Z i =1 means that the i-th hydropower station can adjust its output in all periods of the day, T is the number of periods within the day, T=24, m is the number of superimposed outputs recorded in the cycle calculation, and it ends when m≥D, and the output allocation result of the i-th hydropower station in the t-th period in the cascade is obtained
Citation Information
Patent Citations
Short-term optimization scheduling method for cascade hydropower station groups
CN104239980A
Electric quantity control-based stair-step hydropower short-term peak-regulating model and solving method
CN106655280A
A short-term optimal dispatching model considering cascade dynamic flow hysteresis
CN109190819A
Cascade hydropower station group power generation index distribution method
CN112581310A
Water system planning apparatus and water system planning method
JP2015125665A