A BIM building data processing method, system and storage medium based on data twin technology

Through data twin technology, the digital twin BIM model of steel structure buildings is built, the design deviations in the construction design drawings are analyzed, and the problem of insufficient data analysis before construction in the existing technology is solved, and the construction quality and management efficiency of steel structure buildings are improved.

CN114925422BActive Publication Date: 2024-11-22JINKE ARCHITECTURAL DECORATION ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210513269.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-05-11
Publication Date
2024-11-22
Estimated Expiration
2042-05-11

AI Technical Summary

Technical Problem

During the construction process of steel structure buildings, the existing technology ignores the design data analysis before construction, which makes it difficult to discover design deviations in a timely manner, affects the construction quality and cost rationality, and lacks an assessment of design rationality.

Method used

Using BIM building data processing method based on data twin technology, the number, length, quality and placement angle of steel components in the construction design drawings is built to build a digital twin construction BIM model, identify and evaluate design deviations, and judge the rationality of design parameters. sex.

Benefits of technology

Accurate analysis of the data before the construction of steel structure buildings is achieved, design deviations are discovered in a timely manner, construction quality is ensured, unreasonable cost is avoided, and project management is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114925422B_ABST
    Figure CN114925422B_ABST
Patent Text Reader

Abstract

The present invention discloses a BIM building data processing method, system and storage medium based on data twin technology. The method obtains the construction design drawings corresponding to the target building and builds the digital twin construction BIM model corresponding to the target building through the digital twin technology. The construction design drawings are used to judge the design deviation of the steel component length, the design deviation of the steel component quality and the design deviation of the steel component placement angle. The design rationality of the construction design drawings corresponding to the target building is judged, and the analysis and processing of the pre-construction building data corresponding to the steel structure building is realized, which makes up for the lack of building data utilization in the current steel structure building data analysis and processing process. The present invention can timely discover the design deviation in the construction design drawings through the analysis and processing of the pre-construction building data, thereby ensuring the actual construction quality of the steel structure building, and further improving the overall management level of the steel structure building project.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of building data processing, and specifically relates to a BIM building data processing method, system and storage medium based on data twin technology. Background Art

[0002] With the increasing acceleration of urbanization, the scale and number of construction projects are also increasing. This has led to the generation of a large amount of construction data in the process of construction project management, such as construction data before, during and after construction. For the construction industry, accurate data analysis is conducive to the control of the entire construction project.

[0003] The current rapid economic development has led to an improvement in people's living standards, making people's requirements for buildings higher and higher, and thus paying more and more attention to building structure design, resulting in a variety of building structures, such as brick-wood structures, concrete structures, steel structures, etc. Among them, steel structures have been increasingly widely used in the construction industry due to their advantages of light weight, high strength and durability. However, due to the complexity of the construction of steel structure buildings, in this case, accurate analysis of steel structure building data is crucial.

[0004] However, the building data currently used in the process of steel structure building data analysis and processing are basically the building data during and after construction, and the building data before construction is ignored, such as the design data in the construction design drawings. The current construction design drawings of steel structure buildings are used directly after the design is completed, and there is a lack of design rationality assessment of the design data in the construction design drawings before use. Since the construction design drawings play an important guiding reference role in the entire construction process, once there is a design deviation in the design data in the construction design drawings, not only can the actual construction quality of the steel structure building be unable to be guaranteed, but it will also affect the rationality of the cost of the steel structure building, which is not conducive to the overall management of the steel structure construction project. Summary of the invention

[0005] In view of the above-mentioned shortcomings, the present invention provides a BIM building data processing method, system and storage medium based on data twin technology for design data in construction design drawings, which can effectively solve the problems involved in the above-mentioned background technology.

[0006] The purpose of the present invention can be achieved by the following technical solutions:

[0007] One aspect of the present invention provides a BIM building data processing method based on data twin technology, comprising the following steps:

[0008] S1: Record the steel structure building to be constructed as the target building, and obtain the construction design drawings corresponding to the target building;

[0009] S2: Count the number of steel components for the target building design from the construction design drawings corresponding to the target building, number each steel component as 1, 2, ..., i, ..., n, and extract the design parameters corresponding to each steel component;

[0010] S3: Build a digital twin construction BIM model corresponding to the target building based on the number of steel components designed for the target building and the design parameters corresponding to each steel component;

[0011] S4: Enlarging the digital twin construction BIM model corresponding to the target building to identify the steel components with connection relationships, and recording the steel components with connection relationships as steel component connection groups, and then counting the number of steel component connection groups in the digital twin construction BIM model;

[0012] S5: focusing the digital twin construction BIM model corresponding to the target building on the area where each steel component connection group is located in turn, and then judging whether there is a steel component length design deviation in the construction design drawing corresponding to the target building, and if so, recording the number of deviation steel component connection groups;

[0013] S6: identifying steel components with load-bearing relationships from the digital twin construction BIM model corresponding to the target building, and recording the steel components with load-bearing relationships as steel component load-bearing groups, and then counting the number of steel component load-bearing groups in the digital twin construction BIM model;

[0014] S7: focusing the digital twin construction BIM model corresponding to the target building on the area where each steel component bearing group is located in turn, and then judging whether there is a steel component quality design deviation in the construction design drawing corresponding to the target building, and if so, recording the number of deviation steel component bearing groups;

[0015] S8: construct a three-dimensional coordinate system on the digital twin construction BIM model corresponding to the target building, and locate the three-dimensional coordinates of the center of gravity from the digital twin construction BIM model, and then determine whether there is a steel component placement angle design deviation in the construction design drawing corresponding to the target building;

[0016] S9: Evaluate the design deviation coefficient of the design parameters in the construction design drawings corresponding to the target building, and compare it with the predefined allowable design deviation coefficient. If the design deviation coefficient of the design parameters in the construction design drawings is greater than the allowable design deviation coefficient, the construction design drawings corresponding to the target building are judged to be unreasonable.

[0017] In an achievable manner of one aspect of the present invention, the design parameters include a design length, a design mass, and a design placement angle.

[0018] In one embodiment of the present invention, the method for obtaining the design length of the design parameters corresponding to each steel member is as follows:

[0019] Extract the marked drawing scale from the construction design drawings, and extract the marked length of each steel component in the construction design drawings;

[0020] Import the length and scale of each steel component in the construction design drawings into the design

[0021]

[0022] In the length calculation formula, the corresponding design length of each steel component is obtained.

[0023] In one embodiment of the present invention, the process of determining whether the construction design drawing corresponding to the target building has a steel member length design deviation is as follows:

[0024] S5-1: Obtain the connection spacing of the steel members from the area where each steel member connection group is located;

[0025] S5-2: Compare the steel member connection spacing in each steel member connection group with the preset compliant connection spacing. If the steel member connection spacing in a certain steel member connection group is greater than the preset compliant connection spacing, it is determined that there is a steel member length design deviation in the construction design drawing corresponding to the target building. At this time, the steel member connection group is recorded as a deviation steel member connection group.

[0026] In one embodiment of the present invention, the judgment process of judging whether there is a steel component quality design deviation in the construction design drawing corresponding to the target building is as follows:

[0027] S7-1: Identify the load-bearing main steel member and the loaded steel member in the area where each steel member load-bearing group is located, and obtain the design mass corresponding to the load-bearing main steel member and the design mass corresponding to the loaded steel member according to the number of the load-bearing main steel member and the number of the loaded steel member respectively;

[0028] S7-2: in the area where each steel component bearing group is located in the digital twin construction BIM model corresponding to the target building, respectively simulate the load-bearing main steel components and the loaded steel components according to the design quality, and then after the simulation, collect the appearance images of the loaded steel components in each steel component bearing group;

[0029] S7-3: Analyze the appearance images of the loaded steel members in each steel member load-bearing group to identify whether there is appearance deformation. If there is appearance deformation of the loaded steel members in a certain steel member load-bearing group, it is determined that there is a steel member quality design deviation in the construction design drawings corresponding to the target building. In this case, the steel member load-bearing group is recorded as a deviation steel member load-bearing group.

[0030] In one embodiment of the present invention, the process of determining whether the construction design drawing corresponding to the target building has a steel member placement angle design deviation is as follows:

[0031] S8-1: Outline the three-dimensional shape corresponding to the digital twin construction BIM model based on the digital twin construction BIM model corresponding to the target building;

[0032] S8-2: Calculate the bearing capacity of the corresponding support surface of the target building based on the design quality and design placement angle of each steel component in the corresponding construction design drawings of the target building;

[0033] S8-3: Obtain the coordinates of the center of gravity of the target building in a structurally stable state based on the three-dimensional shape contour corresponding to the digital twin construction BIM model and the bearing capacity of the corresponding supporting surface of the target building;

[0034] S8-4: Compare the three-dimensional coordinates of the center of gravity position in the digital twin construction BIM model of the target building with the coordinates of the center of gravity position of the target building in a structurally stable state, and calculate the center of gravity offset distance of the digital twin construction BIM model of the target building. The calculation formula is: Δl represents the offset distance of the center of gravity of the digital twin construction BIM model of the target building, x, y, z represent the coordinate values ​​of the center of gravity position on the x-axis, y-axis, and z-axis in the digital twin construction BIM model of the target building, respectively, and x0, y0, z0 represent the coordinate values ​​of the center of gravity position on the x-axis, y-axis, and z-axis when the target building is in a stable structural state, respectively;

[0035] S8-5: Compare the center of gravity offset distance of the digital twin construction BIM model corresponding to the target building with the set allowable center of gravity offset distance. If the center of gravity offset distance of the digital twin construction BIM model corresponding to the target building is greater than the set allowable center of gravity offset distance, it is judged that there is a design deviation in the steel component placement angle in the construction design drawing corresponding to the target building.

[0036] In an achievable manner of one aspect of the present invention, the counting of the bearing capacity of the corresponding support surface of the target building according to the design quality and design placement angle of each steel member in the construction design drawing corresponding to the target building in S8-2 specifically includes:

[0037] S8-2-1: The design mass of each steel component in the construction design drawing of the target building is calculated by the gravity calculation formula G=mg to obtain the corresponding gravity of each steel component, recorded as G i ;

[0038] S8-2-2: Based on the design quality and design placement angle of each steel component in the construction design drawings of the target building, the bearing capacity of the corresponding support surface of the target building is calculated using the following calculation formula: F represents the bearing capacity of the corresponding supporting surface of the target building, G i Expressed as the gravity corresponding to the i-th steel component, θ i Expressed as the design placement angle of the i-th steel member.

[0039] In one embodiment of the present invention, the evaluation method corresponding to the design deviation coefficient of the design parameter in the construction design drawing of the evaluation target building refers to the following steps:

[0040] Step 1: Analyze the length design deviation corresponding to each deviation steel component connection group in the construction design drawings of the target building, denoted as ξ j , j represents the deviation steel member connection group number, j = 1, 2, ..., m;

[0041] Step 2: Analyze the quality design deviation corresponding to each deviation steel component bearing group in the construction design drawings of the target building, recorded as k represents the bearing group number of the deviation steel member, k = 1, 2, ..., r;

[0042] Step 3: Analyze the design deviation of the steel component placement angle of the target building corresponding to the construction design drawings. The calculation formula is: Δl′ represents the allowable center of gravity offset distance;

[0043] Step 4: Based on the design deviation of the steel member placement angle of the target building's corresponding construction design drawing, the design deviation of the length of each deviation steel member connection group, and the quality design deviation of each deviation steel member bearing group, the design deviation coefficient of the design parameters in the target building's corresponding construction design drawing is evaluated. The evaluation formula is: It is expressed as the design deviation coefficient of the design parameters in the construction design drawings of the target building, ξ j , σ represents the length design deviation corresponding to the j-th deviation steel component connection group in the construction design drawings corresponding to the target building, the mass design deviation corresponding to the k-th deviation steel component bearing group, and the steel component placement angle design deviation, respectively. A, B, and C represent the weight proportional coefficients corresponding to the length design, mass design, and placement angle design, respectively, and A+B+C=1. e represents a natural constant.

[0044] Another aspect of the present invention provides a BIM building data processing system based on data twin technology, comprising the following modules:

[0045] A construction design drawing acquisition module is used to record the steel structure building to be constructed as a target building and obtain the construction design drawings corresponding to the target building;

[0046] A steel component design parameter extraction module is used to count the number of steel components used to construct the target building from the construction design drawings corresponding to the target building, and to extract the design parameters corresponding to each steel component;

[0047] A digital twin construction BIM model building module is used to build a digital twin construction BIM model corresponding to the target building based on the number of steel components designed for the target building and the design parameters corresponding to each steel component;

[0048] A steel component connection group identification module is used to identify steel components with connection relationships from the digital twin construction BIM model corresponding to the target building, and record the steel components with connection relationships as a steel component connection group;

[0049] The steel component length design deviation judgment module is used to focus the digital twin construction BIM model corresponding to the target building on the area where each steel component connection group is located in turn, and then judge whether there is a steel component length design deviation in the construction design drawings corresponding to the target building;

[0050] A steel component bearing group identification module is used to identify steel components with bearing relationships from the digital twin construction BIM model corresponding to the target building, and record the steel components with bearing relationships as steel component bearing groups;

[0051] The steel component quality design deviation judgment module is used to focus the digital twin construction BIM model corresponding to the target building on the area where each steel component bearing group is located in turn, and then judge whether there is a steel component quality design deviation in the construction design drawings corresponding to the target building;

[0052] The steel component placement angle design deviation judgment module is used to construct a three-dimensional coordinate system on the digital twin construction BIM model corresponding to the target building, and locate the three-dimensional coordinates of the center of gravity from the digital twin construction BIM model, and then judge whether there is a steel component placement angle design deviation in the construction design drawing corresponding to the target building;

[0053] The construction design drawing evaluation module is used to evaluate the design deviation coefficient of the design parameters in the construction design drawings corresponding to the target building, and judge whether the construction design drawings corresponding to the target building are reasonably designed based on this.

[0054] Another aspect of the present invention provides a storage medium, which is burned with a computer program. When the computer program runs in the memory of a server, it implements the BIM building data processing method based on data twin technology described in the present invention.

[0055] Combining all the above technical solutions, the advantages and positive effects of the present invention are as follows:

[0056] (1) The present invention obtains the construction design drawings corresponding to the target building, and respectively judges the design deviation of the steel member length, the steel member quality design deviation and the steel member placement angle design deviation, thereby judging the design rationality of the construction design drawings corresponding to the target building, and realizes the analysis and processing of the pre-construction building data corresponding to the steel structure building, which makes up for the lack of building data utilization in the current analysis and processing of steel structure building data. The present invention can timely discover the design deviation in the construction design drawings through the analysis and processing of the pre-construction building data, thereby being able to guarantee the actual construction quality of the steel structure building to a certain extent, avoiding the situation of unreasonable cost, reducing the difficulty of subsequent construction, and thus improving the overall management level of the steel structure building project.

[0057] (2) In the process of judging the steel component length design deviation, steel component quality design deviation and steel component placement angle design deviation of the construction design drawings corresponding to the target building, the present invention uses digital twin technology to build a digital twin construction BIM model corresponding to the target building based on the construction design drawings, and then makes the above judgment based on the constructed digital twin construction BIM model. This judgment method can effectively improve the accuracy and intuitiveness of the judgment result. BRIEF DESCRIPTION OF THE DRAWINGS

[0058] The present invention is further described using the accompanying drawings, but the embodiments in the accompanying drawings do not constitute any limitation to the present invention. A person skilled in the art can obtain other drawings based on the following drawings without creative work.

[0059] Figure 1 A flow chart of the steps for implementing the method of the present invention;

[0060] Figure 2 It is a schematic diagram of system module connection of the present invention. DETAILED DESCRIPTION

[0061] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0062] Reference Figure 1 As shown, one aspect of the present invention provides a BIM building data processing method based on data twin technology, comprising the following steps:

[0063] S1: Record the steel structure building to be constructed as the target building, and obtain the construction design drawings corresponding to the target building;

[0064] S2: Count the number of steel components for the target building design from the construction design drawings corresponding to the target building, and number each steel component as 1, 2, ..., i, ..., n, and extract the design parameters corresponding to each steel component, wherein the design parameters include design length, design mass and design placement angle;

[0065] It should be noted that the design placement angle mentioned in the present invention is the placement angle from the horizontal plane;

[0066] The method for obtaining the design length of the corresponding design parameters of each steel component mentioned above is as follows:

[0067] Extract the marked drawing scale from the construction design drawings, and extract the marked length of each steel component in the construction design drawings;

[0068] Import the marked length of each steel component in the construction design drawing and the drawing ratio into the design length calculation formula In this way, the design length of each steel component is obtained;

[0069] S3: Build a digital twin construction BIM model corresponding to the target building based on the number of steel components designed for the target building and the design parameters corresponding to each steel component;

[0070] In the process of judging the steel member length design deviation, steel member quality design deviation and steel member placement angle design deviation of the construction design drawings corresponding to the target building, the embodiment of the present invention uses the digital twin technology to build a digital twin construction BIM model corresponding to the target building based on the construction design drawings, and then makes the above judgment based on the built digital twin construction BIM model. This judgment method can effectively improve the accuracy and intuitiveness of the judgment result;

[0071] S4: Enlarging the digital twin construction BIM model corresponding to the target building to identify the steel components with connection relationships, and recording the steel components with connection relationships as steel component connection groups, and then counting the number of steel component connection groups in the digital twin construction BIM model;

[0072] S5: focusing the digital twin construction BIM model corresponding to the target building on the area where each steel component connection group is located in turn, and then judging whether there is a steel component length design deviation in the construction design drawing corresponding to the target building, and if so, recording the number of deviation steel component connection groups;

[0073] The above-mentioned judgment process of judging whether there is a steel member length design deviation in the construction design drawing corresponding to the target building refers to the following steps:

[0074] S5-1: Obtain the connection spacing of the steel members from the area where each steel member connection group is located;

[0075] S5-2: Compare the steel member connection spacing in each steel member connection group with the preset compliant connection spacing. If the steel member connection spacing in a certain steel member connection group is greater than the preset compliant connection spacing, it is determined that there is a steel member length design deviation in the construction design drawing corresponding to the target building. In this case, the steel member connection group is recorded as a deviation steel member connection group;

[0076] S6: identifying steel components with load-bearing relationships from the digital twin construction BIM model corresponding to the target building, and recording the steel components with load-bearing relationships as steel component load-bearing groups, and then counting the number of steel component load-bearing groups in the digital twin construction BIM model;

[0077] S7: focusing the digital twin construction BIM model corresponding to the target building on the area where each steel component bearing group is located in turn, and then judging whether there is a steel component quality design deviation in the construction design drawing corresponding to the target building, and if so, recording the number of deviation steel component bearing groups;

[0078] The judgment process for judging whether the construction design drawings corresponding to the target building have steel component quality design deviations in the above-mentioned manner refers to the following steps:

[0079] S7-1: Identify the load-bearing main steel members and the loaded steel members in the area where each steel member load-bearing group is located. The specific identification method is based on the placement orientation of the steel members, wherein the steel member placed on the upper side is the load-bearing main steel member, and the steel member placed on the lower side is the loaded steel member, and obtain the design mass corresponding to the load-bearing main steel member and the design mass corresponding to the loaded steel member according to the serial number of the load-bearing main steel member and the serial number of the loaded steel member respectively;

[0080] S7-2: in the area where each steel component bearing group is located in the digital twin construction BIM model corresponding to the target building, respectively simulate the load-bearing main steel components and the loaded steel components according to the design quality, and then after the simulation, collect the appearance images of the loaded steel components in each steel component bearing group;

[0081] S7-3: Analyze the appearance images of the loaded steel members in each steel member load-bearing group to identify whether there is appearance deformation. If there is appearance deformation of the loaded steel members in a certain steel member load-bearing group, it is determined that there is a steel member quality design deviation in the construction design drawings corresponding to the target building. In this case, the steel member load-bearing group is recorded as a deviation steel member load-bearing group.

[0082] S8: Construct a three-dimensional coordinate system on the digital twin construction BIM model corresponding to the target building, and locate the three-dimensional coordinates of the center of gravity from the digital twin construction BIM model, and then determine whether there is a design deviation in the placement angle of the steel components in the construction design drawings corresponding to the target building. The specific judgment process is as follows:

[0083] S8-1: Outline the three-dimensional shape corresponding to the digital twin construction BIM model based on the digital twin construction BIM model corresponding to the target building;

[0084] S8-2: Calculate the bearing capacity of the corresponding support surface of the target building based on the design quality and design placement angle of each steel component in the construction design drawings of the target building. The specific statistical process includes:

[0085] S8-2-1: The design mass of each steel component in the construction design drawing of the target building is calculated by the gravity calculation formula G=mg to obtain the corresponding gravity of each steel component, recorded as G i , m represents the design mass of the steel member;

[0086] S8-2-2: Based on the design quality and design placement angle of each steel component in the construction design drawings of the target building, the bearing capacity of the corresponding support surface of the target building is calculated using the following calculation formula: F represents the bearing capacity of the corresponding supporting surface of the target building, G i Expressed as the gravity corresponding to the i-th steel component, θ i It is expressed as the design placement angle of the i-th steel member;

[0087] S8-3: Based on the three-dimensional shape contour corresponding to the digital twin construction BIM model and the bearing capacity of the corresponding support surface of the target building, the center of gravity position coordinates of the target building in a structurally stable state are obtained. The specific acquisition method is to import the three-dimensional shape contour corresponding to the digital twin construction BIM model into the constructed center of gravity algorithm model, and input the bearing capacity of the corresponding support surface of the target building into the center of gravity algorithm model, thereby obtaining the center of gravity position coordinates of the target building in a structurally stable state in the center of gravity algorithm model corresponding to the target building;

[0088] S8-4: Compare the three-dimensional coordinates of the center of gravity position in the digital twin construction BIM model of the target building with the coordinates of the center of gravity position of the target building in a structurally stable state, and calculate the center of gravity offset distance of the digital twin construction BIM model of the target building. The calculation formula is: Δl represents the offset distance of the center of gravity of the digital twin construction BIM model of the target building, x, y, z represent the coordinate values ​​of the center of gravity position on the x-axis, y-axis, and z-axis in the digital twin construction BIM model of the target building, respectively, and x0, y0, z0 represent the coordinate values ​​of the center of gravity position on the x-axis, y-axis, and z-axis when the target building is in a stable structural state, respectively;

[0089] S8-5: Compare the gravity center offset distance of the digital twin construction BIM model corresponding to the target building with the set allowable gravity center offset distance. If the gravity center offset distance of the digital twin construction BIM model corresponding to the target building is greater than the set allowable gravity center offset distance, it is determined that the construction design drawing corresponding to the target building has a steel component placement angle design deviation;

[0090] S9: Evaluate the design deviation coefficient of the design parameters in the construction design drawings corresponding to the target building, and compare it with the preset allowable design deviation coefficient. If the design deviation coefficient of the design parameters in the construction design drawings is greater than the preset allowable design deviation coefficient, the construction design drawings corresponding to the target building are judged to be unreasonable.

[0091] The evaluation method of the design deviation coefficient of the design parameters in the construction design drawings corresponding to the target building mentioned above refers to the following steps:

[0092] Step 1: Analyze the length design deviation corresponding to each deviation steel component connection group in the construction design drawings of the target building, denoted as ξ j , j represents the deviation steel member connection group number, j = 1, 2, ..., m, Δd j It is represented as the steel member connection spacing in the jth deviation steel member connection group in the construction design drawing corresponding to the target building, and Δd0 is represented as the preset compliance connection spacing;

[0093] Step 2: Analyze the quality design deviation corresponding to each deviation steel component bearing group in the construction design drawings of the target building, recorded as k represents the bearing group number of the deviation steel member, k = 1, 2, ..., r, α k It is represented by the appearance deformation angle of the steel member corresponding to the k-th deviation steel member bearing group in the construction design drawing of the target building, and α0 is represented by the reference appearance deformation angle;

[0094] Step 3: Analyze the design deviation of the steel component placement angle of the target building corresponding to the construction design drawings. The calculation formula is: Δl′ represents the allowable center of gravity offset distance;

[0095] Step 4: Based on the design deviation of the steel member placement angle of the target building's corresponding construction design drawing, the design deviation of the length of each deviation steel member connection group, and the quality design deviation of each deviation steel member bearing group, the design deviation coefficient of the design parameters in the target building's corresponding construction design drawing is evaluated. The evaluation formula is: It is expressed as the design deviation coefficient of the design parameters in the construction design drawings of the target building, ξ j , σ represents the length design deviation corresponding to the j-th deviation steel component connection group in the construction design drawings corresponding to the target building, the mass design deviation corresponding to the k-th deviation steel component bearing group, and the steel component placement angle design deviation, respectively. A, B, and C represent the weight proportional coefficients corresponding to the length design, mass design, and placement angle design, respectively, and A+B+C=1. e represents a natural constant.

[0096] The embodiment of the present invention obtains the construction design drawings corresponding to the target building, and judges the design deviation of the steel member length, the steel member quality design deviation and the steel member placement angle design deviation respectively, thereby judging the design rationality of the construction design drawings corresponding to the target building, and realizes the analysis and processing of the pre-construction building data corresponding to the steel structure building, which makes up for the lack of building data utilization in the current analysis and processing of steel structure building data. The present invention can timely discover the design deviation in the construction design drawings through the analysis and processing of the pre-construction building data, thereby ensuring the actual construction quality of the steel structure building to a certain extent, avoiding the situation of unreasonable cost, reducing the subsequent construction difficulty, and thus improving the overall management level of the steel structure building project.

[0097] Reference Figure 2 As shown, another aspect of the present invention provides a BIM building data processing system based on data twin technology, comprising the following modules:

[0098] A construction design drawing acquisition module is used to record the steel structure building to be constructed as a target building and obtain the construction design drawings corresponding to the target building;

[0099] The steel component design parameter extraction module is connected to the construction design drawing acquisition module and is used to count the number of steel components for the construction of the target building from the construction design drawings corresponding to the target building and extract the design parameters corresponding to each steel component;

[0100] A digital twin construction BIM model building module is connected to the steel component design parameter extraction module and is used to build a digital twin construction BIM model corresponding to the target building based on the number of steel components designed for the target building and the design parameters corresponding to each steel component;

[0101] A steel component connection group identification module is connected to the digital twin construction BIM model building module, and is used to identify steel components with connection relationships from the digital twin construction BIM model corresponding to the target building, and record the steel components with connection relationships as steel component connection groups;

[0102] The steel component length design deviation judgment module is connected to the steel component connection group identification module, and is used to focus the digital twin construction BIM model corresponding to the target building on the area where each steel component connection group is located in turn, and then judge whether there is a steel component length design deviation in the construction design drawings corresponding to the target building;

[0103] The steel component bearing group identification module is connected to the digital twin construction BIM model building module, and is used to identify the steel components with bearing relationships from the digital twin construction BIM model corresponding to the target building, and record the steel components with bearing relationships as steel component bearing groups;

[0104] The steel component quality design deviation judgment module is connected to the steel component bearing group identification module, and is used to focus the digital twin construction BIM model corresponding to the target building on the area where each steel component bearing group is located in turn, and then judge whether there is a steel component quality design deviation in the construction design drawings corresponding to the target building;

[0105] The steel component placement angle design deviation judgment module is connected to the digital twin construction BIM model building module, and is used to construct a three-dimensional coordinate system on the digital twin construction BIM model corresponding to the target building, and locate the three-dimensional coordinates of the center of gravity position from the digital twin construction BIM model, and then judge whether there is a steel component placement angle design deviation in the construction design drawing corresponding to the target building;

[0106] The construction design drawing evaluation module is respectively connected with the steel component length design deviation judgment module, the steel component quality design deviation judgment module and the steel component placement angle design deviation judgment module, and is used to evaluate the design deviation coefficient of the design parameters in the construction design drawings corresponding to the target building, and judge whether the construction design drawings corresponding to the target building are reasonably designed.

[0107] Another aspect of the present invention provides a storage medium, which is burned with a computer program. When the computer program runs in the memory of a server, it implements the BIM building data processing method based on data twin technology described in the present invention.

[0108] The above contents are merely examples and explanations of the structure of the present invention. The technicians in this technical field may make various modifications or additions to the specific embodiments described or replace them in a similar manner. As long as they do not deviate from the structure of the invention or exceed the scope defined by the claims, they should all fall within the protection scope of the present invention.

Claims

1. A BIM building data processing method based on data twin technology, characterized in that: The following steps are involved: S1: Record the steel structure building to be constructed as the target building, and obtain the construction design drawings corresponding to the target building; S2: Count the number of steel components for the target building design from the construction design drawings corresponding to the target building, and number each steel component as 1, 2, ..., i, ..., n, and extract the design parameters corresponding to each steel component; S3: Build a digital twin construction BIM model corresponding to the target building based on the number of steel components designed for the target building and the design parameters corresponding to each steel component; S4: Enlarging the digital twin construction BIM model corresponding to the target building to identify steel components with connection relationships, and recording the steel components with connection relationships as steel component connection groups, and then counting the number of steel component connection groups in the digital twin construction BIM model; S5: focusing the digital twin construction BIM model corresponding to the target building on the area where each steel component connection group is located in turn, and then judging whether there is a steel component length design deviation in the construction design drawing corresponding to the target building, and if so, recording the number of deviation steel component connection groups; S6: identifying steel components with load-bearing relationships from the digital twin construction BIM model corresponding to the target building, and recording the steel components with load-bearing relationships as steel component load-bearing groups, and then counting the number of steel component load-bearing groups in the digital twin construction BIM model; S7: focusing the digital twin construction BIM model corresponding to the target building on the area where each steel component bearing group is located in turn, and then judging whether there is any steel component quality design deviation in the construction design drawing corresponding to the target building, and if so, recording the number of deviation steel component bearing groups; S8: construct a three-dimensional coordinate system on the digital twin construction BIM model corresponding to the target building, and locate the three-dimensional coordinates of the center of gravity from the digital twin construction BIM model, and then determine whether there is a steel component placement angle design deviation in the construction design drawing corresponding to the target building; S9: Evaluate the design deviation coefficient of the design parameters in the construction design drawing corresponding to the target building, and compare it with the predefined allowable design deviation coefficient. If the design deviation coefficient of the design parameters in the construction design drawing is greater than the allowable design deviation coefficient, the construction design drawing corresponding to the target building is judged to be unreasonable; the design parameters include design length, design mass and design placement angle; The method for obtaining the design length of each steel component corresponding to the design parameters is as follows: Extract the marked drawing scale from the construction design drawings, and extract the marked length of each steel component in the construction design drawings; Import the marked length of each steel component in the construction design drawing and the drawing ratio into the design length calculation formula In this way, the design length of each steel component is obtained; The process of judging whether the construction design drawing corresponding to the target building has a steel member length design deviation is as follows: S5-1: Obtain the connection spacing of the steel members from the area where each steel member connection group is located; S5-2: Compare the steel member connection spacing in each steel member connection group with the preset compliant connection spacing. If the steel member connection spacing in a certain steel member connection group is greater than the preset compliant connection spacing, it is determined that there is a steel member length design deviation in the construction design drawing corresponding to the target building. In this case, the steel member connection group is recorded as a deviation steel member connection group; The process of judging whether the construction design drawings corresponding to the target building have steel component quality design deviations is as follows: S7-1: Identify the load-bearing main steel member and the loaded steel member in the area where each steel member load-bearing group is located, and obtain the design mass corresponding to the load-bearing main steel member and the design mass corresponding to the loaded steel member according to the number of the load-bearing main steel member and the number of the loaded steel member respectively; S7-2: in the area where each steel component bearing group is located in the digital twin construction BIM model corresponding to the target building, respectively simulate the load-bearing main steel components and the loaded steel components according to the design quality, and then after the simulation, collect the appearance images of the loaded steel components in each steel component bearing group; S7-3: Analyze the appearance images of the loaded steel members in each steel member load-bearing group to identify whether there is appearance deformation. If there is appearance deformation of the loaded steel members in a certain steel member load-bearing group, it is determined that there is a steel member quality design deviation in the construction design drawings corresponding to the target building. In this case, the steel member load-bearing group is recorded as a deviation steel member load-bearing group. The process of judging whether the construction design drawing corresponding to the target building has a design deviation of the steel component placement angle is as follows: S8-1: Outline the three-dimensional shape corresponding to the digital twin construction BIM model based on the digital twin construction BIM model corresponding to the target building; S8-2: Calculate the bearing capacity of the corresponding support surface of the target building based on the design quality and design placement angle of each steel component in the corresponding construction design drawings of the target building; S8-3: Obtain the coordinates of the center of gravity of the target building in a structurally stable state based on the three-dimensional shape contour corresponding to the digital twin construction BIM model and the bearing capacity of the corresponding supporting surface of the target building; S8-4: Compare the three-dimensional coordinates of the center of gravity position in the digital twin construction BIM model of the target building with the coordinates of the center of gravity position of the target building in a structurally stable state, and calculate the center of gravity offset distance of the digital twin construction BIM model of the target building. The calculation formula is: Δl represents the offset distance of the center of gravity of the digital twin construction BIM model of the target building, x, y, z represent the coordinate values ​​of the center of gravity position on the x-axis, y-axis, and z-axis in the digital twin construction BIM model of the target building, respectively, and x0, y0, z0 represent the coordinate values ​​of the center of gravity position on the x-axis, y-axis, and z-axis when the target building is in a stable structural state, respectively; S8-5: Compare the center of gravity offset distance of the digital twin construction BIM model corresponding to the target building with the set allowable center of gravity offset distance. If the center of gravity offset distance of the digital twin construction BIM model corresponding to the target building is greater than the set allowable center of gravity offset distance, it is judged that there is a design deviation in the steel component placement angle in the construction design drawing corresponding to the target building.

2. According to claim 1, a BIM building data processing method based on data twin technology is characterized in that: The calculation of the bearing capacity of the corresponding support surface of the target building according to the design quality and design placement angle of each steel component in the construction design drawing of the target building in S8-2 specifically includes: S8-2-1: The design mass of each steel component in the construction design drawing of the target building is calculated by the gravity calculation formula G=mg to obtain the corresponding gravity of each steel component, recorded as G i ; S8-2-2: Based on the design quality and design placement angle of each steel component in the construction design drawings of the target building, the bearing capacity of the corresponding support surface of the target building is calculated using the following calculation formula: F represents the bearing capacity of the corresponding supporting surface of the target building, G i Expressed as the gravity corresponding to the i-th steel component, θ i Expressed as the design placement angle of the i-th steel member.

3. According to claim 1, a BIM building data processing method based on data twin technology is characterized in that: The evaluation method corresponding to the design deviation coefficient of the design parameters in the construction design drawings of the evaluation target building refers to the following steps: Step 1: Analyze the length design deviation corresponding to each deviation steel component connection group in the construction design drawings of the target building, denoted as ξ j , j represents the deviation steel member connection group number, j = 1, 2, ..., m; Step 2: Analyze the quality design deviation corresponding to each deviation steel component bearing group in the construction design drawings of the target building, recorded as k represents the bearing group number of the deviation steel member, k = 1, 2, ..., r; Step 3: Analyze the design deviation of the steel component placement angle of the target building corresponding to the construction design drawings. The calculation formula is: Δl′ represents the allowable center of gravity offset distance; Step 4: Based on the design deviation of the steel member placement angle of the target building's corresponding construction design drawing, the design deviation of the length of each deviation steel member connection group, and the quality design deviation of each deviation steel member bearing group, the design deviation coefficient of the design parameters in the target building's corresponding construction design drawing is evaluated. The evaluation formula is: It is expressed as the design deviation coefficient of the design parameters in the construction design drawings of the target building, ξ j , σ represents the length design deviation corresponding to the j-th deviation steel component connection group in the construction design drawings corresponding to the target building, the mass design deviation corresponding to the k-th deviation steel component bearing group, and the steel component placement angle design deviation, respectively. A, B, and C represent the weight proportional coefficients corresponding to the length design, mass design, and placement angle design, respectively, and A+B+C=1. e represents a natural constant.

4. A BIM building data processing system based on data twin technology, characterized in that: The method comprises the following modules to execute the processing method described in any one of claims 1 to 3: A construction design drawing acquisition module is used to record the steel structure building to be constructed as a target building and obtain the construction design drawings corresponding to the target building; A steel component design parameter extraction module is used to count the number of steel components used to construct the target building from the construction design drawings corresponding to the target building, and to extract the design parameters corresponding to each steel component; A digital twin construction BIM model building module is used to build a digital twin construction BIM model corresponding to the target building based on the number of steel components designed for the target building and the design parameters corresponding to each steel component; A steel component connection group identification module is used to identify steel components with connection relationships from the digital twin construction BIM model corresponding to the target building, and record the steel components with connection relationships as a steel component connection group; The steel component length design deviation judgment module is used to focus the digital twin construction BIM model corresponding to the target building on the area where each steel component connection group is located in turn, and then judge whether there is a steel component length design deviation in the construction design drawings corresponding to the target building; A steel component bearing group identification module is used to identify steel components with bearing relationships from the digital twin construction BIM model corresponding to the target building, and record the steel components with bearing relationships as steel component bearing groups; The steel component quality design deviation judgment module is used to focus the digital twin construction BIM model corresponding to the target building on the area where each steel component bearing group is located in turn, and then judge whether there is a steel component quality design deviation in the construction design drawings corresponding to the target building; The steel component placement angle design deviation judgment module is used to construct a three-dimensional coordinate system on the digital twin construction BIM model corresponding to the target building, and locate the three-dimensional coordinates of the center of gravity from the digital twin construction BIM model, and then judge whether there is a steel component placement angle design deviation in the construction design drawing corresponding to the target building; The construction design drawing evaluation module is used to evaluate the design deviation coefficient of the design parameters in the construction design drawings corresponding to the target building, and judge whether the construction design drawings corresponding to the target building are reasonably designed based on this.

5. A storage medium, characterized in that: The storage medium is burned with a computer program, and when the computer program is executed in the memory of the server, the method described in any one of claims 1 to 3 is implemented.