A construction method for underground continuous hollow wall
Through the assembly method of foundation pit supporting wall slotting equipment and wall slot supporting frames, the problem of long construction period and high cost of underground continuous hollow wall has been solved, rapid and mechanized construction has been achieved, and the quality and stability of the wall have been improved. , reducing project costs.
Patent Information
- Application Number
- CN202110216075.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-02-26
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2041-02-26
AI Technical Summary
The existing underground continuous hollow wall construction method is easily affected by geology, has long construction period and high cost, and the quality of the wall is not high, and it is prone to problems of sinking, tilting and water leakage.
The foundation pit supporting wall grooving equipment is used to directly excavate the wall groove, and through the assembly method of wall groove support frame and prefabricated components, an underground continuous hollow wall section is formed, combined with self-compacting concrete connections, to improve construction efficiency and wall stability.
The construction period is shortened, the cost is reduced, the quality and stability of the wall are improved, a fast and mechanized construction process is achieved, the land occupied by the enclosure structure is reduced, and the project cost is reduced.
Smart Images

Figure CN114960620B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of building foundation pit construction, and in particular to a construction method of an underground continuous hollow wall. Background Art
[0002] With the development of urban construction in my country, high-rise buildings have been widely used, and urban land is becoming increasingly scarce. In order to make full use of underground space resources, the depth of foundation pits is becoming deeper and deeper. At present, the common support methods for deep foundation pits include bored cast-in-place pile retaining walls, underground continuous walls, steel sheet piles or SMW gravity retaining walls. Among these support methods, underground continuous walls are land-saving and material-saving, three-wall-in-one support structures, but the construction of underground continuous walls requires large-scale machinery and equipment; a large amount of mud will be generated during trenching, which needs to be handled separately; the quality of the wall concrete is not high, and sometimes mud and slag will be mixed, and even water leakage will occur in the wall. In response to these defects, the underground continuous hollow wall and its construction method disclosed in patents CN200610045573.1 and CN201320452987.1 have made improvements to the commonly used underground continuous walls.
[0003] However, the existing prefabricated or semi-prefabricated and semi-cast-in-place underground continuous hollow walls are constructed using the caisson construction method. This method is easily affected by geological factors during the construction process, causing the wall to sink and tilt, and it is difficult to connect the nodes between the wall sections. The construction technology requirements are high and the construction period is long, and the overall construction cost is high. Summary of the invention
[0004] The technical problem to be solved by the present invention is to provide a construction method for an underground continuous hollow wall, which adopts foundation pit support wall grooving equipment to directly dig out wall grooves and cooperates with wall groove support structures to form an assembly space for the underground continuous hollow wall, so that the underground continuous hollow wall can be constructed quickly, the construction period can be shortened, and the construction cost can be reduced.
[0005] In order to solve the above technical problems, the technical solution adopted by the present invention is:
[0006] A construction method for an underground continuous hollow wall comprises the following steps:
[0007] Step 1: First, the construction of the starting wall groove well is carried out. After the construction of the starting wall groove well is completed, the foundation pit support wall groove equipment is hoisted into the starting wall groove well and installed and debugged in place;
[0008] Step 2: hoist the first wall groove support frame by the hoisting equipment, the jack of the foundation pit retaining wall slotting equipment is used to support the first wall groove support frame, and pushes forward a support frame length, excavates while pushing forward, and the foundation pit retaining wall slotting equipment retracts the jack. At the same time, the hoisting equipment hoists the next wall groove support frame in the tail cabin of the foundation pit retaining wall slotting equipment and connects it with the previous wall groove support frame. The foundation pit retaining wall slotting equipment continuously pushes forward and hoists and connects the wall groove support frames until an assembly operation cabin of an underground continuous hollow wall section is formed;
[0009] Step 3: constructing a cushion layer and a foundation plate at the bottom of the assembly operation cabin;
[0010] Step 4: After the foundation plate is tightly against the wall groove support frame, the support of the wall groove support frame at the bottom of the assembly operation cabin is removed, and the first prefabricated component of a section of underground continuous hollow wall segment is hoisted onto the foundation plate by the hoisting equipment, and the first prefabricated component is cast and connected with the foundation plate;
[0011] Step 5: Remove the support of the upper wall groove support frame of the previous prefabricated component and hang down the next prefabricated component to the top of the previous prefabricated component so that the next prefabricated component is overlapped with the previous prefabricated component, and cast the next prefabricated component and the previous prefabricated component together;
[0012] Step 6: Repeat the above step 5 until all sections of underground continuous hollow wall in the assembly operation cabin are stacked and assembled to form a complete underground continuous hollow wall section, then recycle the wall groove support frame, and fill the gap between the hollow wall body and the wall groove side wall;
[0013] Step 7: Repeat the above steps 2 to 6, and after the construction of the next underground continuous hollow wall section is completed, the gap between the longitudinal walls of the two underground continuous hollow wall sections is poured and connected, so that the two underground continuous hollow wall sections are connected as one;
[0014] Step 8: Repeat the above step 7 until all underground continuous hollow wall sections are constructed, and move the foundation pit support wall grooving equipment out of the wall groove, and cast the gap between the last underground continuous hollow wall section and the longitudinal wall of the first hollow wall section to form a closed-loop underground continuous hollow wall.
[0015] The beneficial effects of the present invention are: using the foundation pit support wall slotting equipment to dig the wall groove of the underground continuous hollow wall, the wall groove digging is fast and saves labor and large equipment, and cooperates with the wall groove support frame including the support plate and the brace to form an assembly operation cabin of the hollow wall segment, and then the assembly and connection of each prefabricated part of the underground continuous hollow wall segment is carried out in the assembly operation cabin, and finally the hollow wall segment is connected to form a closed-loop underground continuous hollow wall. The method is used to construct the underground continuous hollow wall, with a high degree of mechanization, easy docking between hollow wall segments, less manpower investment, simple construction process, green and environmentally friendly, fast construction speed and short construction period, effectively reducing the land occupied by the enclosure structure, reducing the project cost, and making the underground continuous hollow wall play the role of "three walls in one". BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 This is a flow chart of a construction method of an underground continuous hollow wall according to Embodiment 1 of the present invention;
[0017] Figure 2 A top view of an assembly operation cabin of a construction method for an underground continuous hollow wall according to a first embodiment of the present invention;
[0018] Figure 3 It is a structural schematic diagram of a section of a prefabricated hollow wall component of a construction method of an underground continuous hollow wall according to the first embodiment of the present invention;
[0019] Figure 4 It is a schematic diagram of the structure of the gap connection between the hollow wall segments of a construction method of an underground continuous hollow wall according to the first embodiment of the present invention;
[0020] Figure 5 A schematic diagram of a vertical connection structure of a construction method for an underground continuous hollow wall according to a first embodiment of the present invention Figure 1 ;
[0021] Figure 6 A schematic diagram of a vertical connection structure of a construction method for an underground continuous hollow wall according to a first embodiment of the present invention Figure 2 ;
[0022] Figure 7 The present invention is a schematic diagram of a section of underground continuous hollow wall structure with a horizontal plate in a construction method of an underground continuous hollow wall according to a first embodiment of the present invention. DETAILED DESCRIPTION
[0023] In order to explain the technical content, achieved objectives and effects of the present invention in detail, the following is an explanation in combination with the implementation modes and the accompanying drawings.
[0024] Please refer to Figures 1 to 7 , a construction method of an underground continuous hollow wall, comprising the following steps:
[0025] Step 1: First, the construction of the starting wall groove well is carried out. After the construction of the starting wall groove well is completed, the foundation pit support wall groove equipment is hoisted into the starting wall groove well and installed and debugged in place;
[0026] Step 2: The first wall groove support frame is hoisted by the hoisting equipment, and the jack of the foundation pit retaining wall slotting equipment is used to support the first wall groove support frame and push it forward by the length of a support frame, while excavating the earth while pushing forward, the foundation pit retaining wall slotting equipment retracts the jack, and at the same time, the hoisting equipment hoists the next wall groove support frame in the tail cabin of the foundation pit retaining wall slotting equipment and connects it with the previous wall groove support frame, and the foundation pit retaining wall slotting equipment continuously pushes forward and hoists and connects the wall groove support frames until an assembly operation cabin of an underground continuous hollow wall section is formed;
[0027] Step 3: construct the cushion layer and foundation plate at the bottom of the assembly cabin;
[0028] Step 4: After the foundation plate is tightly against the wall groove support frame, remove the support of the wall groove support frame at the bottom of the assembly operation cabin and hoist the first prefabricated component of a section of underground continuous hollow wall onto the foundation plate through the hoisting equipment, and cast the first prefabricated component and the foundation plate together;
[0029] Step 5: Remove the support of the upper wall groove support frame of the previous prefabricated component and hang down the next prefabricated component to the top of the previous prefabricated component so that the next prefabricated component is overlapped with the previous prefabricated component, and cast the next prefabricated component and the previous prefabricated component together;
[0030] Step 6: Repeat the above step 5 until all sections of underground continuous hollow wall in the assembly operation cabin are stacked and assembled to form a complete underground continuous hollow wall section, then recycle the wall groove support frame and fill the gap between the hollow wall and the side wall of the wall groove;
[0031] Step 7: Repeat the above steps 2 to 6, and after the construction of the next underground continuous hollow wall section is completed, the gap between the longitudinal walls of the two underground continuous hollow wall sections is poured and connected, so that the two underground continuous hollow wall sections are connected as one;
[0032] Step 8: Repeat the above step 7 until all underground continuous hollow wall sections are constructed, and move the foundation pit support wall grooving equipment out of the wall groove, and cast the gap between the last underground continuous hollow wall section and the longitudinal wall of the first hollow wall section to form a closed-loop underground continuous hollow wall.
[0033] From the above description, it can be seen that the beneficial effects of the present invention are: using foundation pit support wall grooving equipment to excavate the wall grooves of underground continuous hollow walls, the wall groove excavation is fast and saves labor and equipment, and cooperates with the wall groove support frame including support plates and braces to form an assembly operation cabin for a section of hollow walls, and then the various prefabricated parts of the underground continuous hollow walls are assembled and connected in the assembly operation cabin. The construction of underground continuous hollow walls using this method has a high degree of mechanization, a simple construction process, less manpower investment, a fast construction speed and a shortened construction period, thereby reducing construction costs.
[0034] Furthermore, during the construction of the cushion layer and the foundation plate in step three, the soil at the bottom of the wall groove is first compacted, then the sand and gravel cushion layer is evenly laid and compacted and leveled, and finally the concrete foundation plate is poured.
[0035] From the above description, it can be seen that laying a sand and crushed cushion layer first can improve the bearing capacity of the foundation under the shallow foundation. Using relatively strong sand and gravel instead of soil can avoid damage to the foundation, reduce settlement, and make the foundation more stable. Then laying a concrete cushion layer can provide a flat and stable foundation for the underground continuous hollow wall.
[0036] Furthermore, in step 4, the pouring connection between the first prefabricated component and the foundation plate includes: arranging pin-jointed reinforcement at the connection between the first prefabricated component and the foundation plate, and pouring self-compacting concrete into the inner cavity of the first prefabricated component.
[0037] Furthermore, in step five, the pouring connection of the next prefabricated component with the previous prefabricated component includes: arranging pin-jointed reinforcement between the previous prefabricated component and the next prefabricated component, and then pouring self-compacting concrete in the inner cavity and gap between the two prefabricated components.
[0038] Furthermore, the gap casting connection in step seven and step eight includes: arranging pin-jointed reinforcement at the gap, and then casting self-compacting concrete.
[0039] From the above description, it can be seen that the connection points of each part are relatively fixed using vertical steel bars, pin-jointed bars and axillary corner bars similar to those of the stacked integrated pipeline corridor and poured with self-compacting concrete. The connection points after splicing have good stress performance and are spliced quickly, which improves construction efficiency.
[0040] Furthermore, the method also includes step nine: constructing a horizontal plate in the outer cavity of the underground continuous hollow wall.
[0041] Furthermore, in step nine, constructing the horizontal plate in the outer cavity of the underground continuous hollow wall includes: supporting formwork at the connection between the horizontal plate and the underground continuous hollow wall, laying steel bars, connecting wall embedded parts, and pouring concrete.
[0042] From the above description, it can be known that a horizontal plate is constructed in the cavity of the hollow wall, and the horizontal plate corresponds to the basement floor slab so as to connect the basement main frame beam and the floor slab; an "I"-shaped beam can also be formed as the crown and waist beam of the internal support.
[0043] Furthermore, the lifting equipment is a crawler crane or a gantry crane.
[0044] From the above description, it can be seen that the crawler crane is flexible and convenient to move, which is convenient for hoisting over a longer construction distance. The gantry crane can be set across the wall groove to facilitate the hoisting of the hollow wall foundation plate, exterior wall prefabricated components and top plate in the wall groove.
[0045] Please refer to Figures 1 to 7 Embodiment 1 of the present invention is: a construction method of an underground continuous hollow wall, comprising the following steps:
[0046] Step 1: First, the construction of the starting wall groove well is carried out. After the construction of the starting wall groove well is completed, the foundation pit support wall groove equipment is hoisted into the starting wall groove well and installed and debugged in place;
[0047] Step 2: The first wall groove support frame is hoisted by the hoisting equipment, and the jack of the foundation pit retaining wall slotting equipment is used to support the first wall groove support frame and push it forward by the length of a support frame, while excavating the earth while pushing forward, the foundation pit retaining wall slotting equipment retracts the jack, and at the same time, the hoisting equipment hoists the next wall groove support frame in the tail cabin of the foundation pit retaining wall slotting equipment and connects it with the previous wall groove support frame, and the foundation pit retaining wall slotting equipment continuously pushes forward and hoists and connects the wall groove support frames until an assembly operation cabin of an underground continuous hollow wall section is formed;
[0048] Step 3: construct the cushion layer and foundation plate at the bottom of the assembly cabin;
[0049] Step 4: After the foundation plate is tightly against the wall groove support frame, remove the support of the wall groove support frame at the bottom of the assembly operation cabin and hoist the first prefabricated component of a section of underground continuous hollow wall onto the foundation plate through the hoisting equipment, and cast the first prefabricated component and the foundation plate together;
[0050] Step 5: Remove the support of the upper wall groove support frame of the previous prefabricated component and hang down the next prefabricated component to the top of the previous prefabricated component so that the next prefabricated component is overlapped with the previous prefabricated component, and cast the next prefabricated component and the previous prefabricated component together;
[0051] Step 6: Repeat the above step 5 until all sections of underground continuous hollow wall in the assembly operation cabin are stacked and assembled to form a complete underground continuous hollow wall section, then recycle the wall groove support frame and fill the gap between the hollow wall and the side wall of the wall groove;
[0052] Step 7: Repeat the above steps 2 to 6, and after the construction of the next underground continuous hollow wall section is completed, the gap between the longitudinal walls of the two underground continuous hollow wall sections is poured and connected, so that the two underground continuous hollow wall sections are connected as one;
[0053] Step 8: Repeat the above step 7 until all underground continuous hollow wall sections are constructed, and move the foundation pit support wall slotting equipment out of the wall slot, and cast the gap between the last underground continuous hollow wall section and the first hollow wall section to form a closed loop underground continuous hollow wall;
[0054] Step 9: Support formwork at the connection between the horizontal slab and the underground continuous hollow wall, lay out steel bars, connect the embedded wall parts, and pour concrete.
[0055] Among them, the cushion layer construction first compacts the bottom of the wall groove, then evenly lays sand and gravel, compacts and levels the sand and gravel cushion layer again, and finally pours the concrete cushion layer.
[0056] like Figures 3 to 7 As shown, when the precast components are connected to the foundation plate, pin-jointed reinforcement and axillary corner reinforcement are arranged at the connection between the first section of the precast components and the foundation plate; when the next section of the precast components is connected to the previous section of the precast components, the vertical reinforcement between the previous section of the precast components and the next section of the precast components is connected; when the node construction joints are cast and connected, pin-jointed reinforcement is arranged at the node construction joints, and then self-compacting concrete is used for casting and connection; the lifting equipment can be a crawler crane or a gantry crane.
[0057] The wall groove support frame in this embodiment includes two support plates for supporting the two side walls of the wall groove for retaining soil. The support plates can be made of steel plates. A plurality of braces and purlins are arranged in the middle of the support plates to horizontally support the two support plates. When the position of the braces hinders the continued assembly of prefabricated components, the braces can be removed or moved; the underground continuous hollow wall includes four parts, namely the foundation plate, the outer wall prefabricated components from the bottom of the basement to the hollow wall foundation plate, the outer wall prefabricated components above the bottom of the basement, and the top plate. The outer wall prefabricated components above the bottom of the basement include the outer walls on both sides in contact with the wall groove, the horizontal partition between the outer walls on both sides, and a part of the longitudinal plate corresponding to the basement floor slab. The longitudinal plate is used to provide a construction platform for pouring and assembling the prefabricated components above.
[0058] In summary, the present invention provides a construction method for an underground continuous hollow wall, which uses a foundation pit support wall grooving device to excavate the wall groove of the underground continuous hollow wall. The wall groove excavation is fast and saves labor and large equipment. In combination with a wall groove support frame including a support plate and a brace, an assembly operation cabin of a section of the hollow wall is formed, and then the prefabricated parts of the underground continuous hollow wall are assembled and connected in the assembly operation cabin; and in the assembly of the prefabricated components of the underground continuous hollow wall section, vertical steel bars, pin joints and axillary corner bars similar to those of the stacked integrated pipeline corridor are used for each vertical connection point and self-compacting concrete is poured for connection. The force performance of the connection point is good and the assembly is rapid, thereby improving the construction efficiency. The construction of the underground continuous hollow wall using this method has a high degree of mechanization, and the hollow wall sections are easy to connect with each other, with less manpower input, simple construction process, green and environmentally friendly, fast construction speed and short construction period, which effectively reduces the land occupied by the enclosure structure, reduces the project cost, and enables the underground continuous hollow wall to play the role of "three walls in one".
[0059] The above descriptions are merely embodiments of the present invention and are not intended to limit the patent scope of the present invention. Any equivalent transformations made using the contents of the present invention's specification and drawings, or directly or indirectly applied in related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. A construction method for an underground continuous hollow wall, characterized in that: The following steps are involved: Step 1: First, the construction of the starting wall groove well is carried out. After the construction of the starting wall groove well is completed, the foundation pit support wall groove equipment is hoisted into the starting wall groove well and installed and debugged in place; Step 2: hoist the first wall groove support frame by the hoisting equipment, the jack of the foundation pit retaining wall slotting equipment is used to support the first wall groove support frame, and pushes forward a support frame length, excavates while pushing forward, and the foundation pit retaining wall slotting equipment retracts the jack. At the same time, the hoisting equipment hoists the next wall groove support frame in the tail cabin of the foundation pit retaining wall slotting equipment and connects it with the previous wall groove support frame. The foundation pit retaining wall slotting equipment continuously pushes forward and hoists and connects the wall groove support frames until an assembly operation cabin of an underground continuous hollow wall section is formed; Step 3: constructing a cushion layer and a foundation plate at the bottom of the assembly operation cabin; Step 4: After the foundation plate is tightly against the wall groove support frame, the support of the wall groove support frame at the bottom of the assembly operation cabin is removed, and the first prefabricated component of a section of underground continuous hollow wall segment is hoisted onto the foundation plate by the hoisting equipment, and the first prefabricated component is cast and connected with the foundation plate; Step 5: Remove the support of the upper wall groove support frame of the previous prefabricated component and hang down the next prefabricated component to the top of the previous prefabricated component so that the next prefabricated component is overlapped with the previous prefabricated component, and cast the next prefabricated component and the previous prefabricated component together; Step 6: Repeat the above step 5 until all sections of underground continuous hollow wall in the assembly operation cabin are stacked and assembled to form a complete underground continuous hollow wall section, then recycle the wall groove support frame, and fill the gap between the hollow wall body and the wall groove side wall; Step 7: Repeat the above steps 2 to 6, and after the construction of the next underground continuous hollow wall section is completed, the gap between the longitudinal walls of the two underground continuous hollow wall sections is poured and connected, so that the two underground continuous hollow wall sections are connected as one; Step 8: Repeat the above step 7 until all underground continuous hollow wall sections are constructed, and move the foundation pit support wall slotting equipment out of the wall slot, and cast and connect the gap between the last underground continuous hollow wall section and the longitudinal wall of the first hollow wall section to form a closed loop underground continuous hollow wall; The pouring connection between the first prefabricated component and the foundation plate in step 4 includes: arranging pinned reinforcement at the connection between the first prefabricated component and the foundation plate, and pouring self-compacting concrete into the inner cavity of the first prefabricated component; The pouring connection of the next prefabricated component with the previous prefabricated component in step 5 includes: arranging pinned reinforcement between the previous prefabricated component and the next prefabricated component, and then pouring self-compacting concrete in the inner cavity and gap of the two prefabricated components; The gap casting connection in step seven and step eight includes: arranging pin-jointed reinforcement at the gap, and then casting self-compacting concrete.
2. The construction method of an underground continuous hollow wall according to claim 1, characterized in that: When constructing the cushion layer and foundation plate in step three, first tamp the soil at the bottom of the wall groove, then evenly lay the sand and gravel cushion layer, tamp and level it, and finally pour the concrete foundation plate.
3. The construction method of an underground continuous hollow wall according to claim 1, characterized in that: The method also includes step nine: constructing a horizontal plate in the outer cavity of the underground continuous hollow wall.
4. The construction method of an underground continuous hollow wall according to claim 3, characterized in that: The construction of the horizontal plate in the outer cavity of the underground continuous hollow wall in step nine includes: supporting formwork at the connection between the horizontal plate and the underground continuous hollow wall, laying steel bars, connecting wall embedded parts, and pouring concrete.
5. The construction method of an underground continuous hollow wall according to claim 1, characterized in that: The hoisting equipment is a crawler crane or a gantry crane.
Citation Information
Patent Citations
Semi-prefabricated semi-cast-in-situ underground continuous wall
CN203498862U
Underground pipe gallery construction method of machine performing open excavation on upper portion and tunneling on lower portion
CN105298507A
Underground diaphragm wall construction method
CN107130585A
Vertical spliced type underground diaphragm wall and construction method thereof
CN108221959A
Construction method of fully-prefabricated assembly overlapped type hollow wallboard underground utility tunnel
CN108755758A