An automatic monitoring instrument for the shrinkage of anchor static load test

By designing an automatic monitor, the problems of large errors in manual measurement and safety hazards in anchor static load tests are solved, and automated monitoring and accurate recording of anchor static load test process is realized, which improves the reliability and safety of the test.

CN115032060BInactive Publication Date: 2024-11-26YANGZHOU UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210703886.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-07-19
Publication Date
2024-11-26
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing anchor static load test machines have low automation, and require manual measurement of the shrinkage of the anchor clamp and steel strands multiple times, which has problems of large measurement errors and safety hazards.

Method used

Design an automatic internal shrinkage monitor for static load test of anchors, including internal shrinkage monitor, data transmission cable and monitor control box, and realize automatic data recording and monitoring through electromagnets, needle roller bearings, sensor components and control systems. , reduce manual intervention.

Benefits of technology

Automatic monitoring and accurate recording of the anchor static load test process is realized, the working strength of the test personnel is reduced, the reliability and safety of measurement is improved, and the safety risks caused by steel strand breakage are avoided.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115032060B_ABST
    Figure CN115032060B_ABST
Patent Text Reader

Abstract

The present invention provides an automatic shrinkage monitoring instrument for a static load test of an anchor, which mainly comprises two sets of shrinkage monitoring instruments fixed at two ends of a static load test machine of an anchor, to measure the displacement changes of a clip reflector and a steel strand reflector during the test; and transmit the measurement results to a monitoring instrument control box through a data transmission cable; wherein the shrinkage monitoring instrument mainly comprises four electromagnets evenly fixed at the bottom of a bracket, two needle bearings symmetrically fixed on a handle, and the handle is fixed on the top of the bracket; a Nylon rack is fixed on a rack fixing flange on the front end face of the bracket, an annular guide rail is fixed on the front end face of the bracket, an annular slider is fixed on the annular guide rail, a wire groove pressure ring is fixed on the side face of the annular slider, and a sensor assembly is fixed on the end face of the annular slider; the present invention can replace manual monitoring of the shrinkage of a static load tensile test of an anchor, solve the problems of large manual measurement errors and heavy measurement tasks, and avoid possible casualties during the measurement process.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of anchor static load test, and in particular relates to an automatic monitoring instrument which can automatically record the shrinkage value of the anchor during the anchor static load test process. Background Art

[0002] As a country with a long history of bridge construction, my country has possessed world-class bridge-building technology for thousands of years and is even known as the "Land of Bridges". In recent years, with the continuous advancement of science and technology, my country's bridge construction technology has made great strides, and has undertaken a large number of bridge construction projects around the world, constantly creating new world records. Today, bridge-building technology has become an important symbol of China in the international arena. Prestressed anchors are one of the most important structures of modern bridges. They are used to bear the deadweight of the rock and soil of the bridge itself and the traffic load transmitted from the anchor pad. They have the function of improving the compressive strength of the concrete behind the anchor and preventing local damage to the concrete under the anchor under the tensile stress. Their quality is also one of the key factors determining the reliability of modern bridges.

[0003] In order to ensure the construction quality and construction safety, before the actual construction, it is necessary to sample and test the anchoring performance of each batch of anchors used in the actual project on the steel strand through static load tests. The test uses an anchor static load tester to load the anchor that fixes the steel strand, and then measures the shrinkage of the anchor clip and the steel strand during the entire loading process to evaluate the anchoring performance of the anchor on the steel strand. However, the degree of automation of the anchor static load tester currently used in the project is generally low, and the test process still relies on manual multiple measurements of the shrinkage of the steel strand and the clip at both ends of the test machine. The manual measurement results are closely related to the operator's experience, the measurement error is large, and the operator needs to watch the whole process and perform regular measurements, which is a heavy measurement task. Secondly, the steel strand may suddenly break during the test, causing the clip and the steel strand to pop out instantly, which is easy to cause harm to the test operator and poses a major safety hazard. Summary of the invention

[0004] Based on the existing technical problems, the present invention provides an online monitoring instrument for the shrinkage of anchor static load test. In order to achieve the above-mentioned purpose, the specific technical solution of the present invention is as follows:

[0005] An automatic monitoring instrument for shrinkage during anchor static load test, comprising an anchor static load test machine 1, two sets of shrinkage monitors 2, a data transmission cable 3, and a monitoring instrument control box 4, characterized in that: the shrinkage monitors 2 are distributed at both ends of the anchor static load test machine 1, the needle bearings 12 on the shrinkage monitors 2 are in contact with the outer rings of the anchor pads 5 at both ends of the anchor static load test machine 1, the shrinkage monitor 2 is adsorbed on the end faces of the anchor pads 5 through the electromagnets 10 at the bottom thereof, the clip reflectors 7 are fixed on the anchor clips 6 at both ends of the anchor static load test machine 1, and the steel strand reflectors 8 are fixed on the steel strands 9 at both ends of the anchor static load test machine 1; the shrinkage monitor 2 is connected to the monitoring instrument control box 4 through the data transmission cable 3.

[0006] The shrinkage monitor 2 includes: an electromagnet 10, an electromagnet fixing screw 11, a needle bearing 12, a bracket 13, a handle 14, a handle fixing screw 15, a Nylon rack 16, a wire groove pressure ring 17, an annular guide rail 18, an annular slider 19, a guide rail fixing screw 20, and a sensor assembly 21; wherein four of the electromagnets 10 are evenly fixed to the bottom of the bracket 13 by the electromagnet fixing screws 11, two needle bearings 12 are symmetrically fixed to the handle 14, and the handle 14 is fixed to the top of the bracket 13 by the handle fixing screws 15; the Nylon rack 16 is fixed to the rack fixing flange 41 on the front end face of the bracket 13, the annular guide rail 18 is fixed to the front end face of the bracket 13 by the guide rail fixing screws 20, the annular slider 19 is fixed to the annular guide rail 18, the wire groove pressure ring 17 is fixed to the side of the annular slider 19, and the sensor assembly 21 is fixed to the end face of the annular slider 19.

[0007] The sensor assembly 21 includes: a motor fixing screw 22, a connecting bracket 23, a gear 24, a driving motor 25, a bracket fixing screw 26, two torque hinges 27, a hinge connecting plate 28, a sensor bracket 29, and a displacement sensor 30; wherein the sensor assembly 21 is fixed to the end surface of the annular slider 19 by the connecting bracket 23 through the bracket fixing screw 26, the driving motor 25 is fixed to the connecting bracket 23 through the motor fixing screw 22, the gear 24 is fixed to the output shaft of the driving motor 25, and the gear 24 is meshed with the Nylon rack 16 for transmission; the torque hinge 27 is connected through the hinge connecting plate 28 to fix one end of it to the connecting bracket 23, and the other end of it is fixedly connected to the sensor bracket 29, and the displacement sensor 30 is fixed to the sensor bracket 29.

[0008] The monitor control box 4 is divided into two layers: a control system layer 35 and a monitor storage layer 36; wherein the human-computer interaction control system 31 is fixed at the lower left corner of the upper end surface of the control system layer 35, the aviation socket 32 ​​and the working indicator light 33 are fixed at the right rear position of the upper surface of the control system layer 35, and the micro printer 34 is fixed at the right position of the upper surface of the control system layer 35; wherein the monitor storage layer 36 is filled with foam, and the monitor storage layer 36 is symmetrically provided with two monitor fixing holes 40 in front and back, and the monitor storage layer 36 is symmetrically provided with two data line sorting slots 38 and two power line sorting slots 39 in left and right.

[0009] The bracket 13 is integrally made of aluminum alloy material, and a rack fixing flange 41 and a cable arrangement groove 42 are provided on the front end surface of the bracket 13 .

[0010] A universal roller 37 with a self-locking function is provided at the bottom of the monitoring instrument control box 4 .

[0011] Compared with the existing manual measurement method, the beneficial effects of the present invention are:

[0012] (1) The entire static load test process can be monitored, and the shrinkage of the anchor clip and the strand can be accurately recorded during the loading process. The data measurement is accurate, the test results are reliable, and the test data can be directly printed out;

[0013] (2) The present invention automatically records data during the entire implementation process, and no experimenter is required to supervise the experiment after the experiment begins, which reduces the workload of the experimenter and reduces the labor cost of the experiment;

[0014] (3) The use of the present invention to monitor the static load test of the anchor can avoid the life safety problems of the test personnel caused by the sudden breakage of the steel strand during the test;

[0015] (4) The present invention is easy to install and simple to operate. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is the overall schematic diagram of the on-site installation of the present invention;

[0017] Figure 2 This is a partial enlarged schematic diagram of the installation part of the present invention;

[0018] Figure 3 This is a disassembled diagram of the structure of the present invention;

[0019] Figure 4 This is a schematic diagram of disassembling the sensor assembly of the present invention;

[0020] Figure 5 This is a schematic diagram of the control box of the present invention;

[0021] Figure 6 This is a schematic diagram of the packaging of the present invention;

[0022] Figure 7 This is a schematic diagram of the structure of the bracket 13 of the present invention;

[0023] Figure 8 For the present invention Figure 7 A cross-sectional view of

[0024] In the figure: 1. Anchor static load test machine; 2. Inward shrinkage monitor; 3. Data transmission cable; 4. Monitor control box; 5. Anchor pad; 6. Anchor clip; 7. Clip reflector; 8. Steel strand reflector; 9. Steel strand; 10. Electromagnet; 11. Electromagnet fixing screw; 12. Needle bearing; 13. Bracket; 14. Handle; 15. Handle fixing screw; 16. Nylon rack; 17. Wire trough pressure ring; 18. Annular guide rail; 19. Annular slider; 20. Guide rail fixing screw; 21. Sensor assembly; 22. Motor fixing screw 1. Fixing screw; 23. Connecting bracket; 24. Gear; 25. Driving motor; 26. Bracket fixing screw; 27. Torque hinge; 28. Hinge connecting plate; 29. ​​Sensor seat; 30. Displacement sensor; 31. Human-computer interaction control system; 32. Aviation socket; 33. Working indicator light; 34. Micro printer; 35. Control system layer; 36. Monitor storage layer; 37. Universal roller; 38. Data cable sorting slot; 39. Power cable sorting slot; 40. Monitor fixing position; 41. Rack fixing flange; 42. Cable trough. DETAILED DESCRIPTION

[0025] In order to make the purpose, technical scheme and advantages of the present invention clearer, the present invention is further described in detail below in conjunction with specific embodiments and with reference to the accompanying drawings. It should be understood that these descriptions are only exemplary and are not intended to limit the scope of the present invention. In addition, in the following description, the description of well-known structures and technologies is omitted to avoid unnecessary confusion of the concept of the present invention.

[0026] like Figure 1 , Figure 2As shown, an automatic monitoring instrument for shrinkage in a static load test of an anchor comprises an anchor static load test machine 1, two sets of shrinkage monitors 2, a data transmission cable 3, and a monitor control box 4, and is characterized in that: the shrinkage monitors 2 are distributed at both ends of the anchor static load test machine 1, the needle bearings 12 on the shrinkage monitors 2 fit with the outer rings of the anchor pads 5 at both ends of the anchor static load test machine 1, the shrinkage monitors 2 are adsorbed on the end faces of the anchor pads 5 at both ends of the anchor static load test machine 1 through the electromagnets 10 at the bottom thereof, the clip reflectors 7 are fixed on the anchor clips 6 at both ends of the anchor static load test machine 1, and the steel strand reflectors 8 are fixed On the steel strands 9 at both ends of the anchor static load test machine 1; the shrinkage monitor 2 is connected to the monitor control box 4 through the data transmission cable 3; its function is: two sets of the shrinkage monitors 2 are set to measure the shrinkage of the anchor clips 6 and the steel strands 9 at both ends of the anchor static load test machine 1 during the test, and the clip reflectors 7 and the steel strand reflectors 8 facilitate the displacement sensor 30 to measure data; the data transmission cable 3 is used to transmit the control signal of the human-computer interaction control system 31, provide power for the shrinkage monitor 2, and read the measurement data of the displacement sensor 30 in the shrinkage monitor 2 at the same time;

[0027] like Figure 3 As shown, the shrinkage monitor 2 includes: four electromagnets 10 are evenly fixed to the bottom of the bracket 13 by electromagnet fixing screws 11, two needle bearings 12 are symmetrically fixed on the handle 14, and the handle 14 is fixed to the outer ring of the circumference of the bracket 13 by the handle fixing screws 15. Its functions are: the needle bearings 12 are used to accurately position the shrinkage monitor 2 on the anchor pad 5 to ensure that the shrinkage monitor 2 is concentric with the anchor pad 5, the electromagnet 10 is used to reliably fix the shrinkage monitor 2 on the anchor pad 5, and the handle 14 facilitates the transportation and installation of the shrinkage monitor 2; the Nylon rack 16 is fixed to the rack fixing flange 41 on the front end face of the bracket 13, and the annular guide rail 18 is fixed by the guide rail fixing The fixed screw 20 is fixed on the front end face of the bracket 13, the annular slider 19 is fixed on the annular guide rail 18, the wire slot pressing ring 17 is fixed on the side of the annular slider 19, and the sensor assembly 21 is fixed on the end face of the annular slider 19, and its functions are: the Nylon rack 16 has a lighter weight and better wear resistance, the annular guide rail 18 is used to improve the rotational motion accuracy of the sensor assembly 21, ensure the accuracy of repeated measurements, and reduce system errors. The wire slot pressing ring 17 is used to close the wire slot 42 to ensure that the motor control line and the sensor acquisition line rotate together with the sensor assembly 21 in the wire slot 42, and the sensor assembly 21 is used to record the displacement of each of the clip reflective sheet 7 and the strand reflective sheet 8 during the test process;

[0028] like Figure 4 As shown, the sensor assembly 21 includes: the sensor assembly 21 is fixed to the end surface of the annular slider 19 by a connecting bracket 23 through a bracket fixing screw 26, the drive motor 25 is fixed to the connecting bracket 23 through a motor fixing screw 22, and the gear 24 is fixed to the output shaft of the drive motor 25. The gear 24 is meshed with the Nylon rack 16 for transmission. Its function is: the drive motor 25 is meshed with the Nylon rack 16 through the gear 24 to drive the sensor assembly 21 to make a circular motion around the annular guide rail 18; two torque hinges 27 are hinged After the chain connecting plate 28 is connected, one end is fixed to the connecting bracket 23, and the other end is fixed to the connecting sensor bracket 29. The displacement sensor 30 is fixed to the sensor bracket 29. Its function is: the torque hinge 27 is used to adjust the position of the displacement sensor 30 to ensure that the displacement sensor 30 is within the effective range for all the clip reflectors 7 and the steel strand reflectors 8. The displacement sensor 30 is used to record the displacement of all the clip reflectors 7 and the steel strand reflectors 8 on the circumference during the test together with the clips and the steel strands.

[0029] like Figure 5 , Figure 6 As shown, the monitor control box 4 is divided into two layers: a control system layer 35 and a monitor storage layer 36; wherein the human-machine interaction control system 31 is fixed at the lower left corner of the upper end surface of the control system layer 35, the aviation socket 32 ​​and the working indicator light 33 are fixed at the right rear position of the upper surface of the control system layer 35, and the micro printer 34 is fixed at the right position of the upper surface of the control system layer 35, and its functions are: the human-machine interaction control system 31 is used to control the operation of the shrinkage monitor 2, the aviation socket 32 ​​is used to connect the shrinkage monitor 2, and the working indicator light 33 is used to display the entire monitor working condition, the micro printer 34 is used to output the final measurement result; wherein the monitor storage layer 36 is filled with foam, and the monitor storage layer 36 is symmetrically provided with two monitor fixing holes 40 in front and back, and the monitor storage layer 36 is symmetrically provided with two data line sorting grooves 38 and two power line sorting grooves 39 in left and right, and its function is: the filling foam can protect the shrinkage monitor 2 during transportation, the monitor fixing hole 40 is used to fix the shrinkage monitor 2, the data line sorting groove 38 is used to place the data transmission cable 3, and the power line sorting groove 39 is used to place the power line.

[0030] like Figure 7 , Figure 8As shown, the bracket 13 is integrally processed from aluminum alloy, and the front end face of the bracket 13 is provided with a rack fixing flange 41 and a cable groove 42, whose functions are: the integral processing of the aluminum alloy material can make the shrinkage monitor light in weight, high in rigidity, and convenient for installation and use, the rack fixing flange 41 is provided to facilitate the installation of the Nylon rack, and the cable groove 42 is provided to facilitate the layout of the control line of the drive motor 25 and the data line of the displacement sensor 30 during the rotation process of the sensor assembly 21.

[0031] like Figure 5 , Figure 6 As shown, a universal roller 37 with a self-locking function is provided at the bottom of the monitoring instrument control box 4, and its function is: the universal roller 37 can facilitate the movement and transportation of the entire monitoring instrument control box 4.

[0032] The above is only one of the preferred embodiments of the present invention and is not intended to limit the present invention in any other form. Any modification or equivalent change made based on the technical essence of the present invention still falls within the scope of protection required by the present invention.

[0033] The specific implementation of the present invention can be further described as the following steps:

[0034] Step 1: After the preparation work for the anchor static load test is completed, open the monitor control box 4, take out the two sets of shrinkage monitors 2 from the monitor fixing holes 40 of the monitor storage layer 36, hold the handle 14 and hang the shrinkage monitors 2 on the anchor pads 5 at both ends of the anchor static load test machine 1, ensure that the needle bearing 12 fits the outer ring of the anchor pad 5, randomly select the monitoring point position, and install the clip reflector 7 and the steel strand reflector 8;

[0035] Step 2: Adjust the angle of the torque hinge 27, the position of the clip reflector 7 and the steel strand reflector 8, so that all the clip reflectors 7 and the steel strand reflectors 8 are within the effective range of the displacement sensor 30;

[0036] Step 3: Take out the data transmission cable 3 from the data cable arrangement slot 39, connect the shrinkage monitor 2 to the monitor control box 4, take out the power cable from the power cable arrangement slot 38, connect the power of the monitor control box 4, and the electromagnet 10 at the bottom of the shrinkage monitor 2 is energized to adsorb the shrinkage monitor 2 on the anchor pad 5;

[0037] Step 4: Turn on the human-machine interactive control system 31, check whether the indication signal of the working indicator light 33 is normal, and check whether the adsorption of the electromagnet 10 at the bottom of the shrinkage monitor 2 is reliable;

[0038] Step 5: Set the test parameters, monitoring point locations, and measurement time information in the human-computer interaction control system 31, and click to start measurement;

[0039] Step 6: After the test, save the measurement data and print the experimental result report;

[0040] Step 7: Turn off the power, disconnect the data transmission cable, remove the shrinkage monitor 2 and install it back into the monitor control box 4.

Claims

1. An automatic monitoring instrument for shrinkage of anchor static load test, comprising an anchor static load test machine (1), two sets of shrinkage monitoring instruments (2), a data transmission cable (3), and a monitoring instrument control box (4), characterized in that: The shrinkage monitor (2) is distributed at both ends of the anchor static load test machine (1), the needle bearing (12) on the shrinkage monitor (2) fits with the outer ring of the anchor pads (5) at both ends of the anchor static load test machine (1), the shrinkage monitor (2) is adsorbed on the end surface of the anchor pad (5) through the electromagnet (10) at its bottom, the clip reflector (7) is fixed on the anchor clips (6) at both ends of the anchor static load test machine (1), and the steel strand reflector (8) is fixed on the steel strand (9) at both ends of the anchor static load test machine (1); the shrinkage monitor (2) is connected to the monitor control box (4) through the data transmission cable (3); The shrinkage monitor (2) mainly comprises: an electromagnet (10), a bracket (13), a handle (14), a Nylon rack (16), an annular guide rail (18), an annular slider (19), and a sensor assembly (21); wherein four electromagnets (10) are evenly fixed to the bottom of the bracket (13) by means of electromagnet fixing screws (11); two needle bearings (12) are symmetrically fixed to the handle (14); and the handle (14) is fixed to the outer circumference of the bracket (13) by means of handle fixing screws (15); the Nylon rack (16) is fixed to the rack fixing flange (41) on the front end face of the bracket (13); the annular guide rail (18) is fixed to the front end face of the bracket (13) by means of guide rail fixing screws (20); the annular slider (19) is fixed to the annular guide rail (18); a wire groove pressure ring (17) is fixed to the side face of the annular slider (19); and the sensor assembly (21) is fixed to the end face of the annular slider (19); The sensor assembly (21) mainly comprises: a connecting bracket (23), a driving motor (25), two torque hinges (27), and a displacement sensor (30); wherein the sensor assembly (21) is fixed to the end surface of the annular slider (19) by the connecting bracket (23) through a bracket fixing screw (26), the driving motor (25) is fixed to the connecting bracket (23) through a motor fixing screw (22), the gear (24) is fixed to the output shaft of the driving motor (25), and the gear (24) is meshed with the Nylon rack (16) for transmission; the torque hinge (27) is connected through a hinge connecting plate (28) to fix one end thereof to the connecting bracket (23), and the other end thereof is fixedly connected to the sensor bracket (29), and the displacement sensor (30) is fixed to the sensor bracket (29).

2. The automatic monitoring instrument for shrinkage of anchor static load test according to claim 1, characterized in that: The monitoring instrument control box (4) is divided into two layers, namely a control system layer (35) and a monitoring instrument storage layer (36); wherein the human-machine interaction control system (31) is fixed at the lower left corner of the upper end surface of the control system layer (35); the aviation socket (32) and the working indicator light (33) are fixed at the right rear position of the upper surface of the control system layer (35); and the micro printer (34) is fixed at the right position of the upper surface of the control system layer (35); wherein the monitoring instrument storage layer (36) is filled with foam, and the monitoring instrument storage layer (36) is symmetrically provided with two monitoring instrument fixing holes (40) in front and back, and the monitoring instrument storage layer (36) is symmetrically provided with two data line sorting slots (38) and two power line sorting slots (39) in left and right.

3. The automatic monitoring instrument for shrinkage of anchor static load test according to claim 1, characterized in that: The bracket (13) is integrally made of an aluminum alloy material, and a rack fixing flange (41) and a cable arrangement groove (42) are provided on the front end surface of the bracket (13).

4. The automatic monitoring instrument for shrinkage of anchor static load test according to claim 1, characterized in that: A universal roller (37) with a self-locking function is provided at the bottom of the monitoring instrument control box (4).