A method for realizing digital acceptance of substation

Through the digital metering system and mobile applications, the problem of low efficiency in the substation acceptance process is solved, the entire process of electrical parameter detection and acceptance data management is realized, the weak network/no network environment is supported, and the acceptance efficiency and flexibility are improved.

CN115034925BActive Publication Date: 2024-10-01GUANGDONG POWER GRID CO LTD DONGGUAN POWER SUPPLY BUREAU
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202210709191.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-06-22
Publication Date
2024-10-01
Estimated Expiration
2042-06-22

AI Technical Summary

Technical Problem

During the acceptance process of substations, traditional paper-based operations lead to low management efficiency, the inability to effectively track problems and defects, a heavy workload for equipment acceptance, and a lack of support for online and mobile acceptance.

Method used

Using a digital metering system and mobile terminal application, data collection and comparison are carried out through standard voltage transformers and current transformers to realize the entire process of electrical parameter detection and evaluation, and acceptance data management and problem recording are carried out through mobile terminals, supporting weak network/no network Data synchronization and offline work in network environment.

Benefits of technology

It improves the efficiency of acceptance management, reduces the number of devices carried by staff, realizes full/incremental data synchronization, supports offline office, and improves the flexibility and compatibility of the system through responsive layout and lightweight framework.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

The present invention provides a method for realizing digital acceptance of substation, comprising the following steps: the control signal of the voltage and current signal output by the digital metering system tester is used to control the output of the voltage regulator, the output of the voltage regulator is given to the standard voltage transformer and the standard current transformer, and the required primary voltage and current are obtained through the boosting and current increasing devices provided by the standard voltage transformer and the standard current transformer. The business module page form can be dynamically configured and generated, and the forms and list displays of different business modules are configured according to business needs, which can quickly adapt to the changing needs of various terminals and achieve rapid adjustment. The user can edit and adjust the form content of the acceptance link through the mobile terminal. The self-developed data synchronization framework of the mobile terminal supports full / incremental synchronization of data on the mobile terminal, achieves high compatibility for work application scenarios with weak network / no network, supports offline office applications, and uploads synchronized data with one key when there is a network.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of power transformation digitization, and in particular to a method for realizing power transformation digitization acceptance. Background Art

[0002] Digital substation is built on the basis of networked secondary equipment and intelligent primary equipment, and is a modern substation that can realize information sharing of intelligent equipment in the power station. In actual operation, digital and low-power current and voltage transformers are used to replace conventional TV and TA, and large current and high voltage are converted into digital or low-level signals, while data transmission and collection are carried out through high-speed Ethernet.

[0003] At present, the Testing Institute of Dongguan Power Supply Bureau still uses traditional paper-based work in the acceptance of substation / DC equipment. During the acceptance of supervision and handover, there are a large number of project-related materials such as operation instructions and acceptance standards, which generate a large amount of paper documents. The workload of recording, searching, and archiving is large, and the management and efficiency of acceptance are low.

[0004] Traditional substations transmit the collected analog quantities of primary equipment to the protection and control device through cables. The device processes the data after converting the analog to digital, and then transmits the digital quantity to the background for control through the network cable. At the same time, in the acceptance of substation / DC equipment, traditional paper operations are still used. A large amount of acceptance materials need to be collected and sorted. The problems found in the acceptance cannot be effectively tracked. It is difficult for managers to control the progress of the problems and defects found in the acceptance process. The workload of equipment acceptance is very large. The front-line acceptance personnel and managers have an urgent need for online and mobile acceptance. There is a wide user base. In the acceptance of the supervision link and the handover link, there are a large number of project-related materials such as operation instructions and acceptance standards, which generate a large number of paper documents. The workload of recording, searching, and archiving is large, and the management and efficiency of acceptance are low. Summary of the invention

[0005] In order to solve the problems raised in the above background technology, the purpose of the present invention is to provide a method for realizing digital acceptance of substations. Data synchronization adopts the data synchronization framework independently developed by the company to realize full / incremental synchronization of business data. In order to adapt to the weak network / no network in specific work scenarios, the application also supports offline business scenarios.

[0006] In order to solve the above technical problems, the present invention provides a technical solution: a method for realizing digital acceptance of substation, characterized in that it comprises the following steps:

[0007] (1) The control signal of the voltage and current signal output by the digital metering system tester is used to control the output of the voltage regulator, and the output of the voltage regulator is given to the standard voltage transformer and the standard current transformer. After the voltage and current boosting devices provided by the standard voltage transformer and the standard current transformer are passed, the required primary voltage and current are obtained, and the primary voltage and current are output to the transformer under test;

[0008] (2) The secondary standard outputs of the standard voltage transformer and the standard current transformer are given to the standard electric energy meter, and the outputs of the tested voltage transformer and the tested current transformer are given to the digital electric energy meter through the merging unit and the switch. Finally, the pulse outputs of the standard electric energy meter and the digital electric energy meter are given to the digital metering system tester for comparison to obtain the overall metering error;

[0009] (3) The output of each link will be sent to the digital metering system tester for analysis and comparison at the same time, including the standard voltage transformer, the standard current transformer, the voltage transformer under test, the current transformer under test, the merging unit, and the switch. In this way, the electrical parameters of each link in the whole process can be obtained in real time, thereby realizing the detection and evaluation of the whole link;

[0010] (4) The error of the transformer under test can be obtained by comparing the secondary output of the standard transformer with the secondary output of the transformer under test; the influence of the merging unit can be obtained by comparing the secondary output of the transformer under test with the output of the merging unit, including the absolute delay, error, message discreteness, etc. of the merging unit; the influence of the switch can be obtained by comparing the output of the merging unit with the output of the switch, including the delay, error, frame loss, message discreteness, etc. of the switch; the error of the digital energy meter can be obtained by comparing the output of the switch with the pulse output of the digital energy meter;

[0011] (5) At the equipment production or equipment handover site, the operation and inspection personnel hold a mobile terminal, browse the acceptance materials, and conduct standard inquiries and problem records for the supervision and handover links based on the standardized acceptance work card built into the system. They generate key point witness record forms and problem lists, and can export the problem lists through the background, leaving more process data for the equipment acceptance process. On the background end, the acceptance personnel can modify, edit, and manage basic data such as acceptance standards, work instructions, and acceptance problems based on the actual acceptance situation.

[0012] As an improvement, the mobile terminal adopts the mainstream Android platform for native APP application development, with good compatibility and powerful application functions that can achieve daily work needs such as GPS collection, photo taking, video recording, and recording, reducing the number of devices carried by staff. Data synchronization adopts the company's independently developed data synchronization framework to realize full / incremental synchronization of business data. In order to adapt to specific work scenarios with weak network / no network, the application also supports offline business scenarios.

[0013] As an improvement, the Java code-based development uses the JFinal lightweight framework as the backend framework, which has the characteristics of extremely fast development and supports WEB+ORM+AOP+TemplateEngine.

[0014] As an improvement, the backend page adopts a responsive layout to be compatible with multiple browser versions.

[0015] As an improvement, the acceptance of the digital substation automation system is divided into two stages: factory acceptance and on-site acceptance. Factory acceptance should be carried out after the production, commissioning and pre-acceptance of the equipment are completed and before the equipment leaves the factory. On-site acceptance should be carried out after the equipment is installed and commissioned on site and before it is put into operation.

[0016] The beneficial effects of the present invention are: a method for realizing digital acceptance of substations, the back-end page adopts a responsive layout that is compatible with multiple browser versions, and users can perform daily system management work without installing additional clients. The business module page form can be dynamically configured and generated, and the forms and list displays of different business modules can be configured according to business needs. It can quickly adapt to the changing needs of multiple terminals and make rapid adjustments. Users can edit and adjust the content of the acceptance link form through the mobile terminal. The self-developed data synchronization framework of the mobile terminal supports full / incremental synchronization of mobile terminal data, and is highly compatible with work application scenarios with weak network / no network, supports offline office applications, and uploads synchronized data with one click when there is a network.

[0017] Based on Java code development, the backend framework uses the JFinal lightweight framework, which has the characteristics of extremely fast development and supports WEB+ORM+AOP+TemplateEngine. On this basis, the dynamic configuration form function is independently realized to realize the rapid generation of development templates for forms / lists in different business scenarios. The backend application deployment implementation requirements are relatively low, and the server resources are less occupied, and it can be well transplanted to multiple server platforms.

[0018] At the equipment production or equipment handover site, the operation and inspection personnel can use the mobile terminal to browse the acceptance materials at any time, and conduct standard inquiries and problem records for the supervision and handover links based on the built-in standardized acceptance operation card of the system, generate key point witness record forms and problem lists, and export the problem lists through the background, so that the equipment acceptance process has more abundant process data. At the background end, the acceptance personnel can modify, edit, and manage basic data such as acceptance standards, operation instructions, and acceptance problems based on the actual acceptance situation.

[0019] The responsive layout adopted in the back-end page is compatible with multiple browser versions. Users can perform daily system management work without installing additional clients. The business module page forms can be dynamically configured and generated. The forms and list displays of different business modules can be configured according to business needs. It can quickly adapt to the changing needs of various terminals and make rapid adjustments. Users can edit and adjust the form content in the acceptance phase through the mobile terminal. The self-developed data synchronization framework for the mobile terminal supports full / incremental synchronization of mobile data, and is highly compatible with work application scenarios with weak network / no network, supports offline office applications, and can upload and synchronize data with one click when there is a network. DETAILED DESCRIPTION

[0020] The present invention is described below with specific embodiments, but is not intended to be limiting of the present invention.

[0021] Embodiment 1

[0022] A method for realizing digital acceptance of power transformation comprises the following steps:

[0023] The control signal of the voltage and current signal output by the digital metering system tester is used to control the output of the voltage regulator. The output of the voltage regulator is given to the standard voltage transformer and the standard current transformer. The required primary voltage and current are obtained through the boosting and current-raising devices provided by the standard voltage transformer and the standard current transformer. The primary voltage and current are output to the transformer under test.

[0024] The secondary standard outputs of the standard voltage transformer and the standard current transformer are given to the standard electric energy meter. The outputs of the tested voltage transformer and the tested current transformer are given to the digital electric energy meter through the merging unit and the switch. Finally, the pulse outputs of the standard electric energy meter and the digital electric energy meter are given to the digital metering system tester for comparison to obtain the overall metering error.

[0025] The output of each link will be sent to the digital metering system tester for analysis and comparison at the same time, including standard voltage transformer, standard current transformer, voltage transformer under test, current transformer under test, merging unit, and switch. In this way, the electrical parameters of each link in the whole process can be obtained in real time, thus realizing the detection and evaluation of the whole link.

[0026] By comparing the secondary output of the standard transformer with the secondary output of the transformer under test, the error of the transformer under test can be obtained; by comparing the secondary output of the transformer under test with the output of the merging unit, the influence of the merging unit can be obtained, including the absolute delay, error, message discreteness, etc. of the merging unit; by comparing the output of the merging unit with the output of the switch, the influence of the switch can be obtained, including the delay, error, frame loss error, message discreteness, etc. of the switch; by comparing the output of the switch with the pulse output of the digital electric energy meter, the error of the digital electric energy meter can be obtained.

[0027] At the equipment production or equipment handover site, the operation and inspection personnel can use the mobile terminal to browse the acceptance materials at any time, and conduct standard inquiries and problem records for the supervision and handover links based on the built-in standardized acceptance operation card of the system, generate key point witness record forms and problem lists, and export the problem lists through the background, so that the equipment acceptance process has more abundant process data. At the background end, the acceptance personnel can modify, edit, and manage basic data such as acceptance standards, operation instructions, and acceptance problems based on the actual acceptance situation.

[0028] The mobile terminal adopts the mainstream Android platform for native APP application development, which has good compatibility and powerful application functions. It can achieve GPS collection, photo taking, video recording, recording and other daily work needs, reducing the number of equipment carried by staff. Data synchronization adopts the company's independently developed data synchronization framework to realize full / incremental synchronization of business data. In order to adapt to the weak network / no network conditions in specific work scenarios, the application also supports offline business scenarios.

[0029] The acceptance of digital substation automation system is divided into two stages: factory acceptance and on-site acceptance. Factory acceptance should be carried out after the production, commissioning and pre-acceptance of the equipment are completed and before the equipment leaves the factory. On-site acceptance should be carried out after the equipment is installed and commissioned on site and before it is put into operation.

[0030] During factory acceptance, the test equipment that the integrator must provide includes: digital protection comprehensive tester (stations with conventional transformer joints and units must also provide traditional protection testers), SOE resolution tester, optical power meter, and optical attenuation meter.

[0031] On-site acceptance conditions: the system hardware equipment and software system have been installed and debugged on-site, the remote control channels with the dispatching master stations at all levels (including centralized control) have been opened and debugged, the substation information has been fully connected to the relevant systems, and the auxiliary equipment related to the system (power supply, grounding, lightning protection, etc.) has been installed and debugged. The on-site acceptance test must be carried out on the premise that the type test and factory acceptance test reports are complete, and the data and functions meet the technical agreement or corresponding standards. The equipment supplier, construction unit, and commissioning unit have submitted the on-site acceptance application report and commissioning report. The construction unit has completed the network wiring and secondary circuit wiring, and completed the commissioning of the installed equipment.

[0032] Based on Java code development, the back-end framework adopts the JFinal lightweight framework, which has the characteristics of extremely fast development and supports WEB+ORM+AOP+TemplateEngine. On this basis, it independently realizes the dynamic configuration form function to realize the rapid generation of development templates for forms / lists in different business scenarios. The back-end application deployment and implementation requirements are relatively low, and it takes up less server resources and can be well ported to multiple server platforms.

[0033] At the same time, the back-end page adopts a responsive layout that is compatible with multiple browser versions. Users can perform daily system management work without installing additional clients. The business module page forms can be dynamically configured and generated, and the forms and list displays of different business modules can be configured according to business needs. It can quickly adapt to changing needs and make rapid adjustments. Users can edit and adjust the form content in the acceptance stage through the mobile terminal.

[0034] The self-developed data synchronization framework for mobile terminals supports full / incremental synchronization of data on mobile terminals, is highly compatible with work application scenarios with weak / no network, supports offline office applications, and can upload and synchronize data with one click when there is a network.

[0035] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A method for realizing digital acceptance of power transformation, characterized in that: The following steps are involved: (1) The control signal of the voltage and current signal is output by the digital metering system tester to control the output of the voltage regulator. The output of the voltage regulator is given to the standard voltage transformer and the standard current transformer. The required primary voltage and current are obtained through the boosting and current boosting devices of the standard voltage transformer and the standard current transformer. The primary voltage and current are output to the transformer under test; (2) The secondary standard outputs of the standard voltage transformer and the standard current transformer are given to the standard electric energy meter, and the outputs of the tested voltage transformer and the tested current transformer are given to the digital electric energy meter through the merging unit and the switch. Finally, the pulse outputs of the standard electric energy meter and the digital electric energy meter are given to the digital metering system tester for comparison to obtain the overall metering error; (3) The output of each link will be sent to the digital metering system tester for analysis and comparison at the same time, including the standard voltage transformer, standard current transformer, the voltage transformer under test, the current transformer under test, the merging unit, and the switch. In this way, the electrical parameters of each link in the whole process can be obtained in real time, thereby realizing the detection and evaluation of the whole link; (4) The error of the tested transformer can be obtained by comparing the secondary output of the standard transformer with the secondary output of the tested transformer; the influence of the tested transformer can be obtained by comparing the secondary output of the tested transformer with the output of the merging unit, including the absolute delay, error, and message discreteness of the merging unit; the influence of the switch can be obtained by comparing the output of the merging unit with the output of the switch, including the delay, error, frame loss, and message discreteness of the switch; the error of the digital energy meter can be obtained by comparing the output of the switch with the pulse output of the digital energy meter; (5) At the equipment production or equipment handover site, the operation and inspection personnel hold a mobile terminal, browse the acceptance materials, and conduct standard inquiries and problem records for the supervision and handover links based on the standardized acceptance work card built into the system. They generate key point witness record forms and problem lists, and can export the problem lists through the background, leaving more abundant process data for the equipment acceptance process. On the background end, the acceptance personnel can modify, edit, and manage the acceptance standards, work instructions, and basic data of acceptance problems based on the actual acceptance situation.

2. A method for realizing digital acceptance of power transformation according to claim 1, characterized in that: The mobile terminal adopts the mainstream Android platform for native APP application development, which has good compatibility and powerful application functions. It can achieve GPS collection, photo taking, video recording, and recording for daily work, reducing the number of equipment carried by staff. Data synchronization adopts the company's independently developed data synchronization framework to realize full / incremental synchronization of business data. In order to adapt to weak network / no network conditions in specific work scenarios, the application also supports offline business scenarios.

3. A method for realizing digital acceptance of power transformation according to claim 1, characterized in that: Based on Java code development, the backend framework adopts the JFinal lightweight framework, which has the characteristics of extremely fast development and supports WEB+ORM+AOP+TemplateEngine.

4. A method for realizing digital acceptance of power transformation according to claim 1, characterized in that: The backend page adopts a responsive layout and is compatible with multiple browser versions.

5. A method for realizing digital acceptance of power transformation according to claim 1, characterized in that: The acceptance of digital substation automation is divided into two stages: factory acceptance and on-site acceptance. Factory acceptance should be carried out after the production, commissioning and pre-acceptance of the equipment are completed and before the equipment leaves the factory. On-site acceptance should be carried out after the equipment is installed and commissioned on site and before it is put into operation.

Citation Information

Patent Citations

  • Converting station standardization inspection and acceptance auxiliary method based on workflow engine

    CN103065213A

  • Error test system and method for digitized metering device

    CN103792508A

  • Intelligent transformer station monitoring information step-by-step checking and accepting method based on three-layer double-network structure

    CN106570781A

  • Project quality acceptance management system and method based on field positioning

    CN112396302A

  • Transformer substation and main station intelligent joint debugging platform and joint debugging method thereof

    CN112701790A