Recyclable construction access road unit, construction access road and construction method thereof

By adopting pile-type structures of steel pipe piles and pavement panels in ecologically sensitive areas, the long construction period, high maintenance costs and environmental protection problems of traditional walkway construction in complex environments is solved, and an efficient and environmentally friendly construction walkway solution is achieved. It is suitable for Wetlands, marine tidal flats and other areas with complex geological conditions.

CN115058936BActive Publication Date: 2024-11-15THE THIRD CONSTRUCTION CO OF CCCC SECOND HARBOR ENGINEERING CO LTD +3
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210695286.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-06-20
Publication Date
2024-11-15
Estimated Expiration
2042-06-20

AI Technical Summary

Technical Problem

Traditional walkway construction has a long construction period, high maintenance cost, and low material reuse rate in complex environments. Especially when constructing in ecologically sensitive areas, environmental protection requirements are high and reclaiming is difficult, so conventional prefabricated roads are not suitable.

Method used

It adopts a circulating construction walkway unit, including steel pipe piles, pile caps and pavement panels, and is subjected to stress through a pile plate-type structure to provide high load-bearing capacity and stability. The pavement panel is installed on site and the force transmission connection between adjacent boards. Reduce damage to the original roadbed and can be removed and recycled after construction.

Benefits of technology

It has achieved efficient construction of construction walkways, saved construction periods and low energy consumption, and met the green construction requirements of ecologically sensitive areas, simplified roadbed treatment and post-construction reclamation, and reduced environmental pollution risks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115058936B_ABST
    Figure CN115058936B_ABST
Patent Text Reader

Abstract

The present disclosure relates to a recyclable construction access road unit, a construction access road and a construction method thereof. The recyclable construction access road unit includes a steel pipe pile, a pile cap and a road panel. The steel pipe pile is driven into the roadbed; the pile cap is installed on the pile top of the steel pipe pile; the road panel is arranged above the roadbed, including a body and the body has a first side and a second side. The body is provided with a first force transmission subunit on the first side and a second force transmission subunit on the second side. The bottom of the body is preset with a plurality of pile cap grooves. The road panel is buckled on the pile cap through the pile cap grooves so as to be vertically supported by the steel pipe pile, and the first side of one road panel and the second side of another road panel are horizontally spliced ​​via the corresponding first force transmission subunit and the second force transmission subunit. The recyclable construction access road structure provided by the present disclosure is particularly suitable for ecologically sensitive areas, and can solve the technical deficiencies of the prior art such as the difficulty of environmental protection and reclamation, and has little disturbance to the soil layer of the access roadbed, which is conducive to post-construction reclamation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of assembled construction access road structures, and in particular to a recyclable construction access road unit, a construction access road and a construction method thereof. Background Art

[0002] Traditional access road construction technology has problems such as long construction period, high maintenance cost and low material reuse rate in complex environments, which seriously affects the overall benefits of the project. Prefabricated roads have obvious advantages in environments with tight construction period and harsh construction conditions, and have been used in temporary parking lots, cargo yards and other projects.

[0003] For projects that cross ecologically sensitive areas, the red line construction conditions in the wetland are strict and have high environmental protection requirements. Due to environmental protection requirements, conventional prefabricated roads are not suitable for construction access roads that need to be reclaimed after construction. Conventional prefabricated construction access roads still require filling of the roadbed, and the filling soil layer still needs to be excavated for reclamation after construction. Lime is often used in filling materials, which not only pollutes the soil and water sources around the roadbed, but the lime soil excavated after reclamation is also difficult to handle. Summary of the invention

[0004] The purpose of the present invention is to solve the technical deficiencies of the prior art such as environmental protection and difficulty in reclamation, and to provide a recyclable construction access road structure that has little disturbance to the soil layer of the access roadbed, which can not only save construction time, but also facilitate post-construction reclamation, and is particularly suitable for ecologically sensitive areas. The construction access road structure disclosed in the present invention has low construction energy consumption and fully meets the green construction requirements of ecologically sensitive areas.

[0005] The present disclosure is implemented as follows:

[0006] In one aspect, the present disclosure first provides a recyclable construction access road unit, including steel pipe piles, pile caps and road panels, wherein: there are multiple steel pipe piles, which are driven into the roadbed according to the designed positions; the pile caps are installed on the pile tops of the steel pipe piles; the road panel is a prefabricated structure, arranged above the roadbed, including a main body and the main body has a first side and a second side, the main body is provided with a first force transmission sub-unit on the first side and a second force transmission sub-unit on the second side, a plurality of pile cap grooves are preset at the bottom of the main body, the number and positions of the pile cap grooves correspond to the steel pipe piles, the road panel is buckled on the pile cap through the pile cap grooves and is vertically supported by the steel pipe piles, and the first side of one road panel and the second side of another road panel are horizontally spliced ​​via the corresponding first force transmission sub-unit and second force transmission sub-unit. The present invention is used for construction access roads in ecologically sensitive areas such as wetland farmlands and marine tidal flats. It is used for driving vehicles and transporting construction materials during construction. The pile-slab structure cooperates with the roadbed to bear the load together. The road panels are assembled on site and connected by force transmission between adjacent road panels. It can provide a higher load-bearing capacity and has good overall stability. There is no need to do too much processing on the original roadbed structure, and the land in ecologically sensitive areas will not be seriously damaged due to temporary construction. It can not only save land, but also is beneficial to roadbed processing and post-construction reclamation.

[0007] In some embodiments, the first force transmission subunit includes a force transmission rod, and a plurality of force transmission rods are equidistantly distributed on the center line of the thickness of the road panel, and the second force transmission subunit includes a reserved hole, and a plurality of reserved holes are equidistantly distributed on the center line of the thickness of the road panel and are in the same position as the force transmission rod, and the diameter of the reserved hole is slightly larger than the diameter of the force transmission rod. It is easy to understand that by anchoring and extending the force transmission rod on the side of the plate, the force redistribution of adjacent road panels can be achieved while the adjacent road panels are horizontally spliced, the overall force of the road panels is coordinated, the overall strength and stability are enhanced, and unexpected damage and deformation at the splicing point are prevented.

[0008] In some embodiments, the front end of the dowel rod has a threaded segment, and an anchor hole is preset on the road surface plate at a position corresponding to the reserved hole, the anchor hole is connected to the reserved hole, the dowel rod passes through the reserved hole, and the threaded segment extends into the anchor hole. After connection, a high-strength anchoring agent is poured in the anchor hole or a nut is installed. It is easy to understand that by using the anchor hole to pour a high-strength anchoring agent to anchor the threaded segment or the nut to anchor the threaded segment, the connection strength of adjacent road panels at the joint is further enhanced to prevent the board surface from deforming and detaching at the joint under heavy load.

[0009] In some embodiments, the pile cap grooves are located at the four corners of the bottom of the road panel and do not penetrate the thickness of the road panel, and the diameter of the pile cap groove is slightly larger than the diameter of the pile cap. It is easy to understand that the present disclosure adopts a non-penetrating pile cap groove, and the preferred pile cap groove depth is only 1 cm, so that the pile cap can be inserted while avoiding excessive damage to the road panel structure at that location.

[0010] In some embodiments, the pile cap is welded by a circular steel plate, a cross steel plate and a triangular steel plate. The cross steel plate is welded at the lower center position of the circular steel plate, and four triangular steel plates are welded at the lower edge position of the circular steel plate and are respectively aligned with the four end faces of the cross steel plate. A slot is formed between the triangular steel plate and the cross steel plate, and the width of the slot is consistent with or slightly larger than the wall of the steel pipe.

[0011] In some embodiments, the triangular steel plate is an unequal-sided right-angled triangular steel plate, the short side of the right-angled triangle is welded to the lower surface of the circular steel plate, and the long side of the right-angled triangle is aligned with the end face of the cross steel plate. It is easy to understand that when the steel pipe wall is stuck in the slot, the cross steel plate and the triangular steel plate clamp the steel pipe wall from both inside and outside, and when the edge of the circular steel plate is subjected to a downward loading force, the edge of the circular steel plate presses the triangular steel plate downward, and the right-angled long side of the triangular steel plate moves slightly inward, and together with the inner cross steel plate, the steel pipe wall is tightly clamped, preventing the steel pipe pile from being squeezed and deformed at the pile end due to unilateral squeezing or uneven force.

[0012] In some embodiments, the road surface panel is provided with a plurality of hanging points, including hanging point grooves reserved on the road surface panel, hanging point steel plates are embedded in the concrete of the hanging point grooves, and hanging point slots are provided on the hanging point steel plates. It is easy to understand that the hanging point structure is built-in and does not protrude from the panel surface, which facilitates the stacking and transportation of the road surface panel and does not cause damage to the hanging point structure. After the assembly is completed, the built-in hanging point grooves can be filled with wedge-shaped wooden blocks or fine sand, which does not affect the normal use of the road surface panel.

[0013] In some embodiments, the suspension point steel plate includes a horizontal steel plate and a vertical steel plate, the horizontal steel plate is connected and fixed to the road panel steel bar, the vertical steel plate is formed by two steel plates welded in a herringbone shape on the horizontal steel plate, and a suspension point slot is provided on the vertical steel plate. It is easy to understand that the horizontal steel plate is anchored by the steel bar of the road panel itself, and the vertical steel plate is formed by two steel plates welded in a herringbone shape, so as to enhance the hanging strength of the node and prevent disengagement.

[0014] Another aspect of the present disclosure provides a recyclable construction access road, comprising a plurality of recyclable construction access road units.

[0015] On the other hand, the present disclosure provides a construction method for a recyclable construction access road, comprising the following steps: Step 1, roadbed treatment: the roadbed of the construction access road is treated accordingly according to the specific conditions of the ecologically sensitive area; Step 2, road panel prefabrication: the road panel is prefabricated according to the design requirements, and force transfer rods, reserved holes, pile cap grooves and hanging points are reserved; Step 3, steel pipe pile construction: the steel pipe piles are driven into the roadbed by a hammer sinking pile method; Step 4, pile cap installation: the pile cap is inserted into the steel pipe pile, the cross steel plate of the pile cap is inserted into the steel pipe pile, the steel pipe pile wall is inserted into the slot of the pile cap, and the triangular steel plate of the pile cap is clamped outside the steel pipe pile wall; Step 5, road panel installation: the road panel is hoisted, the road panel is hoisted onto the steel pipe pile, and the pile cap groove at the bottom of the road panel is tightly combined with the pile cap, and at the same time, it is ensured that the force transfer rod of the road panel is inserted into the reserved hole of the adjacent road panel; Step 6, post-construction removal: the road panel is hoisted and removed, and the steel pipe pile is pulled out and transported to other projects or retained for use.

[0016] Compared with the prior art, the recyclable construction access road structure provided by the present invention has the following advantages:

[0017] The prefabricated pile-slab construction access road adopted in the present invention can bear a large load and has a strong road surface integrity.

[0018] The construction disclosed in the present invention only requires filling a layer of plain soil on the original soil layer. The roadbed foundation treatment is simple and pollution-free, which fully meets the construction requirements of economy and green environmental protection.

[0019] The present invention adopts factory production of prefabricated road panels and prefabricated steel pipe piles, and the on-site organization and construction period are short.

[0020] Post-construction reclamation only requires the removal of the prefabricated road panels and the extraction of the steel pipe piles. The demolition construction is simple and the materials can be recycled.

[0021] The present invention is applicable to many ecologically sensitive projects with complex geological conditions and has relatively low requirements on geological conditions. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] In order to more clearly illustrate the embodiments of the present disclosure or the technical solutions in the prior art, the drawings required for the embodiments or the description of the prior art are briefly introduced below. Obviously, the drawings in the following description are only exemplary, and for ordinary technicians in this field, other implementation drawings can be derived from the provided drawings without creative work.

[0023] The structures, proportions, sizes, etc. illustrated in this specification are only used to match the contents disclosed in the specification so as to facilitate understanding and reading by persons familiar with this technology. They are not used to limit the conditions under which the present disclosure can be implemented, and therefore have no substantive technical significance. Any structural modification, change in proportion or adjustment of size shall still fall within the scope of the technical contents disclosed in the present disclosure without affecting the effects and purposes that can be achieved by the present disclosure.

[0024] Figure 1 This is a schematic diagram of the construction access road unit structure of an implementation method;

[0025] Figure 2 is a schematic diagram of a road panel plane structure of an implementation method;

[0026] Figure 3 is a schematic diagram of a cross-sectional structure of a road slab in one implementation mode;

[0027] Figure 4 It is a schematic diagram of the planar structure of a road panel according to another embodiment;

[0028] Figure 5 is a schematic diagram of a road panel cross-section structure (in splicing state) in another implementation mode;

[0029] Figure 6 is a schematic diagram of a pile cap structure in one embodiment;

[0030] Figure 7 is a schematic diagram of a pile cap installation state according to an implementation method;

[0031] Figure 8 It is a schematic diagram of the hanging point groove structure of an implementation method;

[0032] Fig. 9 It is a schematic diagram of the steel plate structure of the lifting point in one embodiment;

[0033] Fig.10 is a schematic diagram of a spreader structure in one embodiment;

[0034] Fig.11 The present invention is a schematic diagram of the construction access road structure of an implementation method. DETAILED DESCRIPTION

[0035] In order to make the purpose, technical solution and advantages of the embodiments of the present disclosure more clear, the present disclosure is further described in detail below in conjunction with the embodiments and drawings. Here, the illustrative embodiments of the present disclosure and their descriptions are used to explain the present disclosure, but are not intended to limit the present disclosure.

[0036] In the description of the present disclosure, it is to be understood that the terms "include / comprise", "consist of..." or any other variation thereof are intended to cover non-exclusive inclusion, so that a product, device, process or method including a series of elements includes not only those elements, but also other elements not explicitly listed when necessary, or also includes elements inherent to such product, device, process or method. In the absence of further restrictions, the elements defined by the sentences "include / comprise...", "consist of..." do not exclude the presence of other identical elements in the product, device, process or method including the elements.

[0037] In the present disclosure, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to the specific circumstances.

[0038] It should also be understood that terms such as “upper”, “lower”, “front”, “back”, “left”, “right”, “top”, “bottom”, “inside” and “outside” to indicate directions or positional relationships are based on the directions or positional relationships shown in the accompanying drawings and are only for the convenience of describing the present disclosure and simplifying the description. They do not indicate or imply that the device, component or structure referred to must have a specific direction, be constructed or operate in a specific direction, and should not be understood as a limitation on the present disclosure.

[0039] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the present disclosure, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.

[0040] The implementation of the present disclosure is described in detail below in conjunction with preferred implementations.

[0041] See also Figure 1 The present invention first provides a recyclable construction access road unit, which is suitable for ecologically sensitive areas, including steel pipe piles 1, pile caps 2 and road panels 3. The force of the road panel with a pile-plate structure is mainly concentrated on the steel pipe piles, and the friction between the piles and the soil layer is used as the main load-bearing force of the roadbed. At the same time, in order to avoid local concentrated force on the steel pipe piles and enhance the reliability of the connection between the top of the steel pipe piles and the prefabricated road panel, a pile cap is added to the steel pipe pile to increase the contact area with the concrete road panel.

[0042] In some embodiments, there are multiple steel pipe piles 1, which are driven into the roadbed according to the designed position. The roadbed is especially ecologically sensitive areas such as wetland farmland and marine tidal flats. The use of driven steel pipe piles does not require excessive treatment of the original roadbed structure, and will not seriously damage the land in the ecologically sensitive area due to temporary construction. It can not only save land, but also is beneficial to roadbed treatment and post-construction reclamation.

[0043] The pile cap 2 is installed on the top of the steel pipe pile 1; the pile cap here can at least increase the contact area between the steel pipe pile and the concrete road slab, reduce the thickness of the concrete road slab as a whole, and at the same time protect the top of the steel pipe pile from damage due to local extrusion, which will be explained in detail later.

[0044] The road panel 3 is a prefabricated structure, which is arranged above the roadbed, that is, the bottom surface of the road panel is in contact with the roadbed soil, and firstly, a certain support is provided by the roadbed.

[0045] See also Figure 2 In one embodiment, the road panel 3 includes a body 300 and the body has a first side and a second side. The body 300 is provided with a first force transmission subunit 301 on the first side and a second force transmission subunit 302 on the second side. A plurality of pile cap grooves 303 are preset at the bottom of the body 300. The number and position of the pile cap grooves 303 correspond to the steel pipe pile 1. The road panel 3 is buckled on the pile cap 2 below through the pile cap grooves 303 at the bottom thereof, so as to be vertically supported by the steel pipe pile 1. The first side of one road panel and the second side of the other road panel are horizontally spliced ​​via the corresponding first force transmission subunit 301 and the second force transmission subunit 302. With the help of stable vertical support and reliable lateral force transmission connection, the effective bearing of multiple road panels on the roadbed is realized. It is used as an effective construction access road. The pile caps and steel pipe piles effectively transfer the upper load to the deep part of the roadbed. The force transmission sub-unit can transfer the force of the road panel laterally to the adjacent road panels, and multiple road panels are connected in the lateral direction to form an overall effect. As a whole structure, they bear the load together with the roadbed below, which facilitates the stable and reliable transportation and passage of construction equipment, especially heavy construction machinery, on the access road structure without damaging the roadbed structure in ecologically sensitive areas.

[0046] In some embodiments, the first force transmission subunit 301 includes force transmission rods, and a plurality of force transmission rods are equidistantly distributed on the center line of the thickness of the road panel 3, such as Figure 3 As shown, the second force transmission subunit 302 includes reserved holes, which are evenly distributed on the center line of the road panel thickness and are at the same position as the force transmission rod. The diameter of the reserved holes is slightly larger than the diameter of the force transmission rod to facilitate insertion during construction. Preferably, according to force calculation, the force transmission rod adopts For round steel bars, threaded steel bars or steel bars, the dowel rod is exposed 25-30cm, the reserved hole has a diameter of 20mm and a depth of 28-35cm, and the exposed section of the dowel rod is coated with asphalt for anti-corrosion treatment to prevent rust.

[0047] In other embodiments, Figure 4 , Figure 5 As shown, the first force transmission subunit 301 includes a force transmission rod, and the second force transmission subunit 302 includes a reserved hole. Round steel bars, threaded steel bars or steel bars are embedded in the road panel for 30cm, exposed for 40cm, and contain at least 10cm thread segments 305, with reserved holes of 30cm×20mm. Anchor holes 304 are preset at the positions corresponding to the reserved holes on the road panel 3. The anchor holes 304 are connected to the reserved holes, and the force transmission rods pass through the reserved holes. The thread segments 305 extend into the anchor holes 304. After the connection, high-strength anchoring agents are poured into the anchor holes 304, or the anchor holes 304 are also used as operating holes. After the thread segments 305 extend into the anchor holes 304, 10cm×10cm×8mm thick gaskets with M16 nuts are placed in the anchor holes 304 to anchor the thread segments 305. It is easy to understand that by using the anchor holes 304 to pour high-strength anchoring agents to anchor the thread segments or nuts to anchor the thread segments, the adjacent road panels 3 are firmly connected to form a whole, which can prevent the board surface from deforming and detaching at the connection under heavy load conditions.

[0048] In some embodiments, Figure 1 , Figure 3 As shown, the pile cap grooves 303 are located at the four corners of the bottom of the road panel 3 and do not penetrate the thickness of the road panel. The diameter of the pile cap groove is slightly larger than the diameter of the pile cap 2. Preferably, the depth of the pile cap groove 303 of the present disclosure is 1 cm, and a shallow groove is used to embed the pile cap, so as to avoid damaging the thickness of the road panel here and its overall strength and integrity.

[0049] In some embodiments, Figure 6As shown, the pile cap 2 is welded by a circular steel plate 201, a cross steel plate 202 and a triangular steel plate 203. The cross steel plate 202 is welded at the lower center of the circular steel plate 201. Four triangular steel plates 203 are welded at the lower edge of the circular steel plate 201 and are respectively aligned with the four end faces of the cross steel plate 202. A slot 204 is formed between the triangular steel plate 203 and the cross steel plate 202. The width of the slot 204 is consistent with or slightly larger than the steel pipe wall. During installation, the pile cap 2 is directly inserted into the steel pipe pile 1, the pile cap cross steel plate 202 is directly inserted into the hollow steel pipe, the triangular steel plate 203 is inserted into the roadbed, and the slot 204 between the cross steel plate 202 and the triangular steel plate 203 clamps the steel pipe wall, so that the steel pipe pile and the pile cap are firmly fixed, bearing the upper road panel, and the triangular steel plate 203 is inserted into the roadbed, and the roadbed shares part of the load. It should be noted that the circular steel plate is only exemplary, and the corresponding pile cap shape can be configured according to the actual cross-section of the steel pipe pile.

[0050] Preferably, the triangular steel plate 203 is an unequal-sided right-angled triangular steel plate, for example, the smaller acute angle is 30° or even smaller, the short side of the right triangle is welded to the lower surface of the circular steel plate 201, and the long side of the right triangle is aligned with the end face of the cross steel plate 202, that is, the hypotenuse of the right triangle faces outward and contacts the roadbed soil, so as to facilitate insertion into the roadbed soil. In addition, such a setting is particularly characterized in that when the steel pipe wall is stuck in the slot 204, the thickness of the steel pipe wall is consistent with the width of the slot 204 or slightly smaller than the width of the slot 204, and the cross steel plate 202 and the triangular steel plate 203 clamp the steel pipe wall from both inside and outside, such as Figure 7 As shown, when the edge of the circular steel plate 201 is subjected to a downward loading force, the edge of the circular steel plate 201 presses the triangular steel plate 203 downward (as shown by the vertical arrow in the figure), and the right-angled long side of the triangular steel plate 203 moves slightly inward (as shown by the horizontal arrow in the figure), and together with the inner cross steel plate 202, it tightly clamps the steel pipe wall to prevent the steel pipe pile from being squeezed and deformed at the pile end due to unilateral squeezing or uneven force.

[0051] In some embodiments, a plurality of suspension points are provided on the road panel 3, and the plurality of suspension points are evenly distributed at the four corners of the road panel. Figure 8 , Fig. 9 As shown, a preferred hanging point structure includes a hanging point groove 306 reserved on the road panel, a hanging point steel plate 307 is embedded in the concrete of the hanging point groove, and a hanging point card groove 308 is provided on the hanging point steel plate 307. Preferably, the hanging point groove 306 adopts a triangular inclined groove, which is convenient for operating the hook to be clamped into the hanging point card groove 308, and the hanging point groove is used for the hanging hook to facilitate the hanging. A preferred embodiment of the hanging tool is shown in FIG. Fig.10, including a lifting ring and a hook-shaped lifting tool head, the hook-shaped lifting tool head can be easily extended from the lifting point groove 306 and inserted into the lifting point slot 308. Compared with the pre-buried bolt, hook, and lifting ring structure, the lifting point structure disclosed in the present invention does not protrude, which is convenient for pavement panel stacking and transportation, and will not cause damage to the lifting point structure. After the assembly is completed, the built-in lifting point groove can be filled with a wedge-shaped wooden block or fine sand, which does not affect the normal use of the pavement panel.

[0052] In some embodiments, see Fig. 9 The suspension point steel plate 307 includes a horizontal steel plate and a vertical steel plate. The horizontal steel plate is connected and fixed to the road panel steel bar 309. The vertical steel plate is welded to the horizontal steel plate in a herringbone shape by two steel plates, and a suspension point slot 308 is provided on the vertical steel plate. The suspension point steel plate 307 is anchored by the steel bar of the road panel itself, and the vertical steel plate is welded in a herringbone shape by two steel plates to enhance the hanging strength of the node and prevent disengagement.

[0053] Another aspect of the present disclosure provides a recyclable construction access road suitable for ecologically sensitive areas, comprising a plurality of recyclable construction access road units, wherein the plurality of recyclable construction access road units are horizontally spliced ​​and connected through a first force transmission subunit 301 and a second force transmission subunit 302, such as Fig.11 shown.

[0054] Another aspect of the present disclosure provides a construction method for a recyclable construction access road suitable for ecologically sensitive areas, which is described in detail below in conjunction with specific embodiments.

[0055] Example 1: Construction application on wetland farmland that needs to be reclaimed after construction

[0056] Roadbed treatment: According to the designed route, bulldozers and excavators are used to remove the surface soil containing weeds, tree roots, etc., and then rollers are used to compact the original ground. Side ditches are excavated on both sides of the access road for drainage. The cross-sectional dimensions of the side ditches are: 1.8m wide at the top, 0.6m wide at the bottom, and 0.6m deep. For areas with high groundwater levels or serious waterlogging, the cross-sectional area of ​​the drainage ditch should be appropriately increased according to actual conditions.

[0057] Pile slab prefabrication: The prefabricated road slab is designed as a reinforced concrete slab with a length of 3.5m, a width of 2m, and a thickness of 0.3m, with reserved force transfer rods, reserved holes, pile cap grooves and hanging points. The pile foundation adopts Φ800×10mm steel pipe piles.

[0058] The geometric characteristics of the components are shown in the following table:

[0059] Table 1 Component geometric characteristics

[0060]

[0061] The main material mechanical properties are as follows:

[0062] Table 2 Mechanical properties of main materials

[0063]

[0064] According to the deadweight of the slab, the hoisting force simulation calculation is carried out to determine the structure and installation position of the lifting point. The lifting point is set at X×X distance from the edge of the slab (where X is 0.2m, 0.3m, 0.4m, and 0.5m). According to the simulation calculation model and results of the deadweight of the slab (taken as 5.5 tons) and live load (mainly 70 tons of concrete tank trucks), the steel bars are configured. At the same time, the compressive bearing capacity of the steel pipe pile is calculated according to the geological conditions to determine the pile length. The road slab is prefabricated according to the reinforcement diagram obtained by calculation.

[0065] Lifting mechanics simulation results at different lifting point positions:

[0066] Table 3 Maximum stress and displacement of the hanging point at different distances from the plate corner

[0067]

[0068]

[0069] Mechanical calculation results of component load simulation:

[0070] Table 4 Calculation results of main structures

[0071]

[0072] According to the above table, the stress of the dowel rod is 90.4MPa≤f=270MPa, and the strength of the dowel rod meets the requirements; the concrete slab is subjected to a compressive stress of 2.7MPa≤f c =14.3MPa, meets the requirements; concrete tensile stress 2.2MPa≥f t =1.43MPa, which does not meet the requirements, so it is necessary to verify the reinforcement of the slab; the reinforcement calculation is based on the formula in the Concrete Code.

[0073] According to the simulation results, the maximum pile end reaction force design value is 161.0kN. According to the wetland farmland geological conditions and the "Port Engineering Pile Foundation Specifications", the single pile ultimate bearing capacity design value is calculated: It can be seen that the bearing capacity requirement is met when the pile is buried 3.5m into the soil.

[0074] Table 5 Geological conditions of wetland farmland

[0075]

[0076] According to the above calculation results, the reinforcement used in this embodiment is: the upper part of the plate is reinforced with Φ16@150mm (HRB400), arranged along the 3.5m direction, the lower part of the plate is reinforced with Φ20@150mm (HRB400), arranged along the 3.5m direction, and the reinforcement along the 2m direction can be the same size and spacing as the 3.5m direction. The hanging point is set at 0.5m×0.5m away from the edge of the plate, and the concrete is C30 concrete. According to the geological conditions of wetland farmland, the pile is buried 3.5m deep.

[0077] Steel pipe pile construction: After measurement and layout according to the design drawings, the steel pipe piles are driven into the roadbed using the hammer pile driving method. The penetration of the piles is strictly controlled during the hammering process to ensure that the axis and elevation of the piles meet the construction requirements.

[0078] After the steel pipe pile construction is completed, the pile cap is installed. The pile cap is inserted into the steel pipe pile, the pile wall is inserted into the slot of the pile cap, the cross steel plate of the pile cap is inserted into the steel pipe pile, and the triangular steel plate of the pile cap is stuck on the outer wall of the steel pipe pile. After the pile cap is installed, the plain soil is filled, and the compacted thickness of the fill is equal to the elevation of the pile cap.

[0079] Installation of road panels: After the pile foundation construction is completed, the prefabricated road panels are hoisted. To hoist the road panels, first tie the lifting strap to the lifting ring of the lifting device, and insert the lifting device head into the lifting point slot of the lifting point steel plate and clamp it. During the hoisting process, the installation accuracy must be strictly controlled to ensure that the pile cap groove at the bottom of the prefabricated panel is tightly combined with the pile cap, and at the same time ensure that the force transmission rod of the panel can be smoothly inserted into the reserved hole of the adjacent road panel.

[0080] After the installation of the road panels, polyvinyl chloride cement is placed in the gap between two adjacent prefabricated road panels to fill the gap. At the same time, a wooden block of the same size as the groove of the prefabricated road panel hanging point is placed in the groove of the prefabricated road panel hanging point, or fine sand is filled to prevent the groove from being blocked.

[0081] Post-construction reclamation: The prefabricated road panels are hoisted and dismantled, the steel pipe piles are pulled out and transported to other projects, and the original roadbed can be reclaimed after deep plowing.

[0082] Example 2: Construction and application in marine tidal flats

[0083] Roadbed treatment: To avoid environmental pollution, the roadbed is not over-treated, and the steel pipe piles are directly inserted into the mudflat soil layer. It should be noted that since the load on the outer side of the prefabricated slab at the start and end of the construction access road is greater than that in the middle part, the foundation here needs to be hardened to avoid damage to the end.

[0084] Pile-slab prefabrication: The prefabricated road panel is designed to be a reinforced concrete slab with a length of 3.5m, a width of 2m, and a thickness of 0.03m. The pile foundation adopts Φ600×10mm steel pipe piles. The construction access road is a 7m double-lane road. The hoisting force simulation calculation is performed according to the deadweight of the board to determine the structure and installation position of the lifting point. According to the simulation calculation model and results of the deadweight and live load of the board (mainly a fully loaded muck truck of 20 tons), the steel bars are configured, and the compressive bearing capacity of the steel pipe piles is calculated according to the geological conditions to determine the pile length. The road panel is prefabricated according to the reinforcement diagram obtained by calculation. The reinforcement used in this embodiment is: the upper reinforcement of the board is Φ16@100mm (HRB335), arranged along the 3.5m direction, the lower reinforcement of the board is Φ20@100mm (HRB335), arranged along the 3.5m direction, and the reinforcement of the same size and spacing of the steel bars in the 2m direction can be used as in the 3.5m direction. According to the geological conditions of the marine mudflats, a pile depth of 8.0 meters can meet the bearing requirements.

[0085] Steel pipe pile construction: After measuring and setting out according to the design drawings, the steel pipe pile is driven into the tidal flat by hammering pile sinking method. During the hammering process, the penetration of the pile is strictly controlled to ensure that the axis and elevation of the pile meet the construction requirements. After the pile is sunk, fine cutting is performed to control the elevation of the pile.

[0086] After the steel pipe pile construction is completed, the pile cap is installed, the pile cap is inserted into the steel pipe pile, the pile wall is inserted into the slot of the pile cap, the cross steel plate of the pile cap is inserted into the steel pipe pile, and the triangular steel plate of the pile cap is stuck in the outer wall of the steel pipe pile.

[0087] Installation of road panels: After the pile foundation construction is completed, the prefabricated road panels are hoisted. To hoist the road panels, first tie the lifting strap to the lifting ring of the lifting device, and insert the lifting device head into the lifting point slot of the lifting point steel plate and clamp it. During the hoisting process, the installation accuracy must be strictly controlled to ensure that the pile cap groove at the bottom of the prefabricated panel is tightly combined with the pile cap, and at the same time ensure that the force transmission rod of the panel can be smoothly inserted into the reserved hole of the adjacent road panel.

[0088] After the installation of the road panel is completed, a wooden block of the same size as the prefabricated road panel hanging point groove is placed in the prefabricated road panel hanging point groove to prevent the groove from being blocked.

[0089] Post-construction demolition: hoist and dismantle the prefabricated road panels, pull out the steel pipe piles and transport them to other projects.

[0090] It is easy for those skilled in the art to understand that, under the premise of no conflict, the above-mentioned preferred solutions can be freely combined and superimposed.

[0091] The above description is only a preferred embodiment of the present disclosure and is not intended to limit the present disclosure. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present disclosure should be included in the protection scope of the present disclosure.

Claims

1. A recyclable construction access road, characterized in that: It comprises a plurality of recyclable construction access road units, wherein the recyclable construction access road units comprise steel pipe piles, pile caps and road panels, wherein: There are multiple steel pipe piles, which are driven into the roadbed according to the designed positions; The pile cap is installed on the top of the steel pipe pile; The road panel is a prefabricated structure, arranged above the roadbed, including a body, and the body has a first side and a second side, the body is provided with a first force transmission subunit on the first side and a second force transmission subunit on the second side, a plurality of pile cap grooves are preset at the bottom of the body, the number and position of the pile cap grooves correspond to the steel pipe piles, the road panel is buckled on the pile cap through the pile cap grooves so as to be vertically supported by the steel pipe piles, and the first side of one road panel and the second side of another road panel are horizontally spliced ​​via the corresponding first force transmission subunit and second force transmission subunit; and The pile cap grooves are located at the four corners of the bottom of the road panel and do not penetrate the thickness of the road panel. The diameter of the pile cap groove is slightly larger than the diameter of the pile cap. The pile cap is welded by a circular steel plate, a cross steel plate and a triangular steel plate. The cross steel plate is welded at the center of the bottom of the circular steel plate. Four triangular steel plates are welded at the bottom edge of the circular steel plate and are aligned with the four end faces of the cross steel plate respectively. A slot is formed between the triangular steel plate and the cross steel plate. The width of the slot is consistent with or slightly larger than the wall of the steel pipe. The triangular steel plate is an unequal right-angled triangle steel plate, the short side of the right-angled triangle is welded to the lower surface of the circular steel plate, and the long side of the right-angled triangle is aligned with the end surface of the cross steel plate; The construction method of the recyclable construction access road comprises the following steps: Step 1: Roadbed treatment: Treat the roadbed of the construction access road accordingly according to the specific conditions of the ecologically sensitive area; Step 2: Prefabrication of road panels: prefabricate road panels according to design requirements, and reserve dowel bars, reserved holes, pile cap grooves and hanging points; Step 3: Steel pipe pile construction: Use hammer pile sinking method to drive steel pipe piles into the roadbed; Step 4: Pile cap installation: insert the pile cap into the steel pipe pile, insert the cross steel plate of the pile cap into the steel pipe pile, insert the steel pipe pile wall into the slot of the pile cap, and the triangular steel plate of the pile cap is stuck outside the steel pipe pile wall; Step 5, road panel installation: hoist the road panel onto the steel pipe pile, and make sure that the pile cap groove at the bottom of the road panel is tightly combined with the pile cap, and at the same time ensure that the force transmission rod of the road panel is inserted into the reserved hole of the adjacent road panel; Step 6: Post-construction dismantling: hoist and dismantle the road slab, pull out the steel pipe piles and transport them to other projects or keep them for future use.

2. The recyclable construction access road according to claim 1 is characterized in that: The first force transmission subunit includes force transmission rods, and a plurality of force transmission rods are equidistantly distributed on the center line of the thickness of the road panel. The second force transmission subunit includes reserved holes, and a plurality of reserved holes are equidistantly distributed on the center line of the thickness of the road panel and are in the same position as the force transmission rods. The diameter of the reserved holes is slightly larger than the diameter of the force transmission rods.

3. The recyclable construction access road according to claim 2 is characterized in that: The front end of the force transmission rod is provided with a threaded section, and an anchor hole is preset on the pavement plate at a position corresponding to the reserved hole. The anchor hole is connected to the reserved hole, the force transmission rod passes through the reserved hole, and the threaded section extends into the anchor hole. After connection, a high-strength anchoring agent is poured in the anchor hole or a nut is installed.

4. The recyclable construction access road according to claim 1 is characterized in that: The pavement panel is provided with a plurality of hanging points, including hanging point grooves reserved on the pavement panel, hanging point steel plates are embedded in concrete in the hanging point grooves, and hanging point card slots are provided on the hanging point steel plates.

5. The recyclable construction access road according to claim 4 is characterized in that: The hanging point steel plate comprises a horizontal steel plate and a vertical steel plate. The horizontal steel plate is connected and fixed to the road slab reinforcement. The vertical steel plate is formed by welding two steel plates in a herringbone shape and connected to the horizontal steel plate. The vertical steel plate is provided with a hanging point slot.