By designing an automated fixture switching control system, the main control PC, production line PLC, fixture library and AGV trolley are used to realize automatic switching and storage of fixtures, which solves the problem in the existing technology that the production line is difficult to adapt to the needs of multiple models, and improves production efficiency and Multi-model production capacity.
Patent Information
- Application Number
- CN202210642756.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-06-08
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2042-06-08
AI Technical Summary
The existing automobile welding production line is difficult to meet the production needs of small batches and multiple models. It requires frequent removal and replacement of fixtures to adapt to the production of different models, resulting in low production efficiency.
A fixture switching control system is designed, including the main control PC, welding production line, production line PLC, fixture library, AGV trolley and fixture table. It realizes automatic switching and storage of fixtures through Ethernet communication, allowing the production line to produce multiple models at the same time.
It realizes that the automatic production line is not limited by the number of vehicle models, improves the fixture switching efficiency and the multi-model production capacity of the production line, and reduces the frequency of production line modifications.
Smart Images

Figure CN115070270B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of welding, and in particular relates to a fixture switching control system and method. Background Art
[0002] As people's pursuit of personalized products is formed, the automobile manufacturing field has gradually developed from a small variety of large-scale production to a small batch production. However, most of the existing automobile welding production lines can only produce a few models, generally 3-5, which is difficult to meet the production needs of small batches and multiple models. When the number of models on the production line increases, the fixtures of the existing models need to be removed, and replacement methods need to be adopted to transform the production line.
[0003] To this end, there is an urgent need to improve the multi-model production capacity of the production line, especially in the welding field. Summary of the invention
[0004] The purpose of the present invention is to provide a fixture switching control system and a fixture switching control method to solve the problem that a production line can produce multiple vehicle models at the same time, thereby realizing an automatic production line without limiting the number of vehicle models.
[0005] The objective of the present invention is achieved through the following technical solutions:
[0006] A fixture switching control system, including a main control PC, a welding production line 1, a production line PLC, a fixture 2, a fixture library 3, an AGV trolley 4, a fixture table 5, a fixture library control PC and a production planning PC;
[0007] The fixture 2 is installed on the fixture table 5 and can also be stored in the fixture library 3;
[0008] The AGV trolley 4 transports the fixture 2 between the fixture table 5 of the welding production line and the fixture warehouse 3;
[0009] The production planning PC is connected to the production line PLC, AGV scheduling PC and fixture library PLC respectively; Ethernet communication is adopted between the main control PC and the production planning PC and the fixture library control PC.
[0010] Furthermore, when the fixture 2 is used in the welding production line 1 , the fixture 2 is fixed on the fixture table 5 , and when the fixture 2 is not used in the welding production line 1 , it is stored in the fixture library 3 .
[0011] A fixture switching control method, wherein a main control PC controls the fixture 2 to move from the fixture table 5 into the welding production line 1 and out of the welding production line 1 to the fixture library according to the production plan and the vehicle model of the fixture table 5, specifically including the following steps:
[0012] A. Determine whether the network communication is normal; input the communication status signal of the workstation PLC, production plan PC, and fixture library PC. If the communication status signal is abnormal, an alarm will be issued;
[0013] B. Read the production plan data; apply to the production plan PC to read the production plan and store the production plan queue;
[0014] C. Read the fixture model data of fixture station 5 of the welding production line;
[0015] D. In the read production plan queue, find the first position where the fixture table does not have a new model;
[0016] E. Check whether the fixture table 5 of the production line is full. If it is not full, the new fixture is output and allowed to go online immediately; otherwise, proceed to the next step;
[0017] F. Start from the first position where there is no new model in fixture station 5, and go back in the production plan queue to the planned quantity of the first fixture model A and the planned quantity of the first fixture model B;
[0018] G. Start by searching for the first position on the fixture where there is no new model, and search forward in the production plan queue for the planned quantity without model A. Search forward in the production plan queue for the planned quantity without model A.
[0019] 4. A fixture switching control method according to claim 3 is characterized in that step A specifically includes inputting the communication status signals of the workstation PLC, production plan PC, and fixture library PC, and first determining whether the communication status of the production line PLC is normal; if normal, reading the workstation fixture model and saving the workstation fixture model, A=X, B=Y; if the communication status signal is abnormal, a communication fault alarm signal is issued, wherein A and B represent the fixture, and X and Y represent the model of the fixture.
[0020] Further, step B is specifically as follows: determine whether the communication status of the production plan PC is normal; if normal, apply to the production plan PC to read the production plan data and store the production plan queue; reset counter 1, N1=0, read the production plan vehicle model information; add 1 to the counter, N0=N0+1, and read the N0 planned vehicle model.
[0021] Further, step C is specifically as follows: determine whether there is a planned model in the fixture model; if so, return to step 2, add 1 to the counter, N0=N0+1, and read the model information corresponding to the production plan queue pointer N0; if not, the fixture switching start time new fixture online model N10=N0; Ns=1, Na=N0, Nb=N0; the counter is reset, Na=NA+1, and the next model is read.
[0022] Further, step D is specifically as follows: determine whether the A fixture model is equal to 0; if so, the fixture start-up plan Ns=0; if not, determine whether the B fixture model is equal to 0; if so, the fixture start-up plan Ns=0; if not, Na=N0, Na=Na-1, and read the production plan queue Na model.
[0023] Further, step E is specifically as follows: determine whether the fixture station of the production line is full and whether Na is equal to 0; if it is not full, fixture A is taken offline, Nsa=Na, and the new fixture is output and allowed to go online immediately; if not, read the planned Na model.
[0024] Further, step F is specifically as follows: determine whether the planned vehicle model is equal to the fixture; if so, fixture A is offline Nsa=Na; Nb=N0; Nb=Nb-1, read the planned queue Nb vehicle model; determine whether Nb is equal to 0; if so, fixture B is offline Nsb=Nb; if not, read the planned queue Nb vehicle model; determine whether the planned vehicle model is equal to fixture B vehicle model; if so, fixture B is offline, Nsb=Nb; Nza=N0, Nzb=N0; Nza=Nza+1, read the planned queue Nza vehicle model.
[0025] Further, step G is specifically as follows: determine whether the vehicle model is equal to 0; if so, the interval for the B fixture vehicle model to go online again, Nzb=Nzb-1; if not, determine whether the planned vehicle model is equal to the fixture B vehicle model, if so, the interval for the B fixture vehicle model to go online again; determine whether Nza-Nsa is greater than or equal to Nzb-Nsb; if so, the A vehicle model fixture is offline, and the number of offline units is Nsa; if not, the B vehicle model fixture is offline, and the number of offline units is Nsb.
[0026] Compared with the prior art, the present invention has the following beneficial effects:
[0027] The clamp switching control method of the present invention adopts a clamp table in the automatic production line for welding white body, and four vehicle models can be produced simultaneously on the production line. Unused clamps are stored off-line and replaced as a whole, thereby realizing that the automatic production line has no limit on the number of vehicle models; the overall switching of clamps and offline storage of offline clamps are adopted, so that the vehicle models of the production line can be continuously increased, and the automatic conveying and storage of offline clamps is adopted to improve the efficiency of the overall switching of clamps. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for use in the embodiments are briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without creative work.
[0029] Figure 1 This is a connection diagram of the fixture switching control system;
[0030] Figure 2 This is the program control flow chart of the fixture switching control method.
[0031] In the figure, 1. Welding production line 2. Fixture 3. Fixture warehouse 4. AGV trolley 5. Tetrahedron fixture table. DETAILED DESCRIPTION
[0032] The present invention will be further described below in conjunction with embodiments:
[0033] The present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the present invention, rather than to limit the present invention. It should also be noted that, for ease of description, only parts related to the present invention, rather than all structures, are shown in the accompanying drawings.
[0034] It should be noted that similar reference numerals and letters represent similar items in the following drawings, so once an item is defined in one drawing, it does not need to be further defined and explained in the subsequent drawings. At the same time, in the description of the present invention, the terms "first", "second", etc. are only used to distinguish the description and cannot be understood as indicating or implying relative importance.
[0035] like Figure 1 As shown, the fixture switching control system of the present invention includes a main control PC, a welding production line 1, a production line PLC, a fixture 2, a fixture library 3, an AGV trolley 4, a fixture table 5, a fixture library control PC and a production planning PC.
[0036] The fixture 2 is installed on the fixture table 5 and can also be stored in the fixture library 3. Specifically, when the fixture 2 is used in the welding production line 1, the fixture 2 is fixed on the fixture table 5, and when the fixture 2 is not used in the welding production line 1, it is stored in the fixture library 3.
[0037] The AGV trolley 4 transports the fixture 2 between the welding production line 1 and the fixture library 3 , specifically, transports the fixture 2 between the fixture table 5 and the fixture library 3 .
[0038] The production planning PC is connected to the production line PLC, AGV scheduling PC and fixture library PLC respectively. The main control PC communicates with the production planning PC and fixture library control PC using Ethernet.
[0039] The fixture table 5 is a tetrahedral fixture table.
[0040] like Figure 2As shown, the fixture switching control method of the present invention, the main control PC controls the fixture 2 from the fixture table 5 to the welding production line 1 and moves it out of the welding production line 1 to the fixture library according to the production plan and the vehicle model of the fixture table 5, and specifically includes the following steps:
[0041] Step 1: Determine whether the network communication is normal; input the communication status signal of the workstation PLC, production plan PC, and fixture library PC. If the communication status signal is abnormal, an alarm will be issued;
[0042] Step 2: Read the production plan data; apply to the production plan PC to read the production plan and store the production plan queue;
[0043] Step 3: Read the fixture model data of the fixture table of the welding production line;
[0044] Step 4: In the read production plan queue, find the first position where the fixture table does not have a new model;
[0045] Step 5: Check whether the fixture table of the production line is full. If it is not full, the new fixture is output and allowed to go online immediately; otherwise, proceed to the next step;
[0046] Step 6: Start from the first position where there is no new model on the fixture table, and go back in the production plan queue to the planned quantity of the first fixture model A and the planned quantity of the first fixture model B;
[0047] Step 7. Start by finding the first position on the fixture where there is no new model, and search the production plan queue forward for the planned quantity without model A. Search the production plan queue forward for the planned quantity without model A.
[0048] The main control PC sends the model and permission conditions of the fixture 2 offline to the production line PLC, the production line PLC controls the working fixture station 5, the main control PC outputs the model of the fixture on the line to the fixture library control PC, the fixture library 3 accesses the fixture 2 according to the model, and the main control PC sends control commands to the AGV system according to the production line offline workshop and time, production model and time.
[0049] Example 1
[0050] A fixture switching control system includes a main control PC, a welding production line 1, a production line PLC, multiple fixtures 2, a fixture library 3, an AGV trolley 4, a tetrahedral fixture table 5, a fixture library control PC and a production planning PC.
[0051] The part of the fixtures 2 is used in the welding production line 1 and installed on the fixture table 5 , and the other part is stored in the fixture library 3 when not in use in the welding production line 1 .
[0052] The AGV trolley 4 transports the fixture 2 between the fixture table 5 and the fixture library 3 .
[0053] The production planning PC is connected to the production line PLC, AGV scheduling PC and fixture library PLC respectively. The main control PC communicates with the production planning PC and fixture library control PC using Ethernet.
[0054] The main control PC sends the model and permission conditions of the fixture 2 offline to the production line PLC, the production line PLC controls the working fixture station 5, the main control PC outputs the model of the fixture on the line to the fixture library control PC, the fixture library 3 accesses the fixture 2 according to the model, and the main control PC sends control commands to the AGV system according to the production line offline workshop and time, production model and time.
[0055] Example 2
[0056] A fixture switching control method comprises the following steps:
[0057] 1. Input the communication status signals of the workstation PLC, production plan PC, and fixture library PC, and first determine whether the communication status of the production line PLC is normal; if normal, read the workstation fixture model and save the workstation fixture model, A=X, B=Y; if the communication status signal is abnormal, a communication fault alarm signal is issued; among them, A and B represent the fixture, and X and Y represent the fixture model;
[0058] 2. Determine whether the communication status of the production plan PC is normal; if normal, apply to the production plan PC to read the production plan data and store the production plan queue; reset counter 1, N1 = 0, read the production plan vehicle model information; add 1 to the counter, N0 = N0 + 1, read the vehicle model information corresponding to the production plan queue pointer N0;
[0059] 3. Determine whether there is a planned model in the fixture model; if so, return to step 2, add 1 to the counter, N0=N0+1, and read the N0 planned model; if not, the new fixture online model N10=N0 at the fixture switching start time; Ns=1, Na=N0, Nb=N0; the counter is cleared, Na=NA+1, and the next model is read;
[0060] 4. Determine whether the model number of fixture A is equal to 0; if so, the fixture starts to go online plan Ns = 0; if not, determine whether the model number of fixture B is equal to 0; if so, the fixture starts to go online plan Ns = 0; if not, Na = N0, Na = Na-1, read the model number Na in the production plan queue, and find the first position of the fixture station without a new model number;
[0061] 5. Check whether the fixture table of the production line is full, and check whether Na is equal to 0; if it is not full, fixture A is offline, Nsa = Na, and the new fixture is output and allowed to go online immediately; if not, read the planned Na model;
[0062] 6. Determine whether the planned model is equal to the fixture; if so, the A fixture is offline Nsa=Na; Nb=N0; Nb=Nb-1, read the planned queue Nb model; determine whether Nb is equal to 0; if so, the B fixture is offline Nsb=Nb; if not, read the planned queue Nb model; determine whether the planned model is equal to the fixture B model; if so, the B fixture is offline, Nsb=Nb; Nza=N0, Nzb=N0; Nza=Nza+1, read the planned queue Nza model; start from the first position where there is no new model on the fixture table, and find it back in the production plan queue to the planned quantity of the first fixture A model and the planned quantity of the first fixture B model;
[0063] 7. Determine whether the vehicle model is equal to 0; if so, the interval for the B fixture vehicle model to go online again, Nzb = Nzb-1; if not, determine whether the planned vehicle model is equal to the fixture B vehicle model, if so, the interval for the B fixture vehicle model to go online again; determine whether Nza-Nsa is greater than or equal to Nzb-Nsb; if so, the A vehicle model fixture is offline, and the number of offline units is Nsa; if not, the B vehicle model fixture is offline, and the number of offline units is Nsb; start by finding the first position where there is no new vehicle model on the fixture table, and search the production plan queue forward for the planned number without the A vehicle model, and search the production plan queue forward for the planned number without the A vehicle model.
[0064] Note that the above are only preferred embodiments of the present invention and the technical principles used. Those skilled in the art will understand that the present invention is not limited to the specific embodiments described herein, and that various obvious changes, readjustments and substitutions can be made by those skilled in the art without departing from the scope of protection of the present invention. Therefore, although the present invention has been described in more detail through the above embodiments, the present invention is not limited to the above embodiments, and may include more other equivalent embodiments without departing from the concept of the present invention, and the scope of the present invention is determined by the scope of the appended claims.
Claims
1. A fixture switching control method, characterized in that: The main control PC controls the movement of the fixture (2) from the fixture table (5) into the welding production line (1) and out of the welding production line (1) to the fixture library (3) according to the production plan and the vehicle model of the fixture table (5), specifically including the following steps: A. Determine whether the network communication is normal; input the communication status signals of the workstation PLC, production plan PC, and fixture library PC, and issue an alarm if the communication status signals are abnormal; specifically, input the communication status signals of the workstation PLC, production plan PC, and fixture library PC, and first determine whether the communication status of the production line PLC is normal; if normal, read the workstation fixture model and save the workstation fixture model, A=X, B=Y; if the communication status signal is abnormal, issue a communication fault alarm signal, where A and B represent the fixture, and X and Y represent the fixture model; B. Read the production plan data; apply to the production plan PC to read the production plan and store the production plan queue; specifically: determine whether the communication status of the production plan PC is normal; if normal, apply to the production plan PC to read the production plan data and store the production plan queue; reset counter 1, N1=0, read the production plan vehicle model information; add 1 to the counter, N0=N0+1, read the N0 plan vehicle model; C. Read the fixture model data of the welding production line fixture station (5); specifically: determine whether there is a planned model in the fixture model; if so, return to step B, add 1 to the counter, N0=N0+1, and read the model information corresponding to the production plan queue pointer N0; if not, the fixture switching start time new fixture on-line model N10=N0; Ns=1, Na=N0, Nb=N0; reset the counter, Na=NA+1, and read the next model; D. In the production plan queue, find the first position of the fixture station (5) without a new model; specifically: determine whether the A fixture model is equal to 0; if so, the fixture start online plan Ns=0; if not, determine whether the B fixture model is equal to 0; if so, the fixture start online plan Ns=0; if not, Na=N0, Na=Na-1, read the production plan queue Na model; E. Check whether the fixture station (5) of the production line is full. If not, output that the new fixture is allowed to go online immediately. Otherwise, proceed to the next step. Specifically, check whether the fixture station of the production line is full and whether Na is equal to 0. If not, fixture A is offline, Nsa=Na, and output that the new fixture is allowed to go online immediately. If not, read the planned Na model. F. Start from the first position where there is no new model in the fixture station (5), and go back in the production plan queue to the planned quantity of the first fixture model A and the planned quantity of the first fixture model B; specifically: determine whether the planned model is equal to the fixture; if so, fixture A is offline Nsa=Na; Nb=N0; Nb=Nb-1, read the model Nb in the planned queue; determine whether Nb is equal to 0; if so, fixture B is offline Nsb=Nb; if not, read the model Nb in the planned queue; determine whether the planned model is equal to fixture B model; if so, fixture B is offline, Nsb=Nb; Nza=N0, Nzb=N0; Nza=Nza+1, read the model Nza in the planned queue; G. Find the fixture station (5) Starting from the first position where there is no new model, the production plan queue searches forward for the planned quantity without model A. The production plan queue searches forward for the planned quantity without model A. Specifically: determine whether the model is equal to 0; if so, the interval for the B fixture model to go online again, Nzb=Nzb-1; if not, determine whether the planned model is equal to the fixture B model; if so, the interval for the B fixture model to go online again; determine whether Nza-Nsa is greater than or equal to Nzb-Nsb; if so, the A model fixture is offline, and the offline quantity is Nsa; if not, the B model fixture is offline, and the offline quantity is Nsb.
2. A fixture switching control system used in the fixture switching control method according to claim 1, characterized in that: It includes main control PC, welding production line (1), production line PLC, fixture (2), fixture library (3), AGV trolley (4), fixture table (5), fixture library control PC and production planning PC; Wherein, the fixture (2) is installed on a fixture table (5) or stored in a fixture library (3); The AGV trolley (4) transports the fixture (2) between the fixture table (5) of the welding production line and the fixture library (3); The production planning PC is connected to the production line PLC, AGV scheduling PC and fixture library PLC respectively; Ethernet communication is adopted between the main control PC and the production planning PC and the fixture library control PC.
3. The fixture switching control system used in the fixture switching control method according to claim 2 is characterized in that: When the clamp (2) is used in a welding production line, the clamp (2) is fixed on a clamp table (5); when the clamp (2) is not used in the welding production line, it is stored in a clamp library (3).
Citation Information
Patent Citations
Automatic flexible welding production line oriented to multiple classes of small assemblies and control method of production line
CN105252179A
Universal flexible welding work station and automobile production line
CN109604855A
Multi-vehicle-type flexible manufacturing method and device
CN109676279A
Intelligent scheduling method in whole vehicle manufacturing field
CN112183939A
Automobile side wall assembly welding method
CN113385844A