Method, device and storage medium for calculating cost of digital project in power industry
Through pre-set calculation models and project portrait models, the initial workload and workload impact factors are determined according to the project type, and the objective accuracy problem of relying on historical data in the existing technology is solved, and the accurate cost calculation of new digital projects is realized. Improved service capabilities.
Patent Information
- Application Number
- CN202210644744.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-06-08
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2042-06-08
AI Technical Summary
The existing method for calculating the cost of digital projects in the power industry relies on historical data and cannot issue objective and accurate calculation basis, making it difficult to adapt to new digital projects with fast changes in demand and high business complexity.
The pre-set calculation model and project portrait model are used to determine the initial workload and workload impact factors according to the project type, and the final total cost is determined through cross-validation to ensure the accuracy of the calculation results.
It improves the accuracy and reliability of the cost calculation of digital projects, is suitable for digital projects in the power industry under the new situation, covers all work types, and improves the cost calculation ability of new digital projects with fast changes in demand.
Smart Images

Figure CN115169808B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of cost calculation in the electric power industry, and in particular to a method, device and storage medium for calculating the cost of digital projects in the electric power industry. Background Art
[0002] With the advent of the Internet information age, the digitalization projects in the power industry cover an increasingly wide range of content, and the proportion of digitalization projects in the power industry projects is also increasing. The importance of cost estimation of digitalization projects in the power industry has become increasingly prominent. The original cost estimation method for digitalization projects in the power industry mainly stipulates two types of work: software development and system implementation. It is mainly based on WBS work decomposition and function point measurement. It is difficult to support non-software development and non-system implementation work included in digitalization projects. Faced with new digitalization projects with "fast demand changes, high business complexity, and strong innovation", the influencing factors of the original estimation model are difficult to play their due role, and can only rely on traditional methods such as analogy. Such methods are too dependent on the accuracy of cost estimation of industry / historical projects, and it is difficult to provide objective and accurate estimation basis.
[0003] With regard to the technical problem that the existing cost calculation method of the existing power industry digitalization project in the above-mentioned prior art relies on historical data and cannot provide an objective and accurate calculation basis, no effective solution has been proposed so far. Summary of the invention
[0004] The embodiments of the present disclosure provide a method, device and storage medium for calculating the cost of digital projects in the electric power industry, so as to at least solve the technical problem that the existing cost calculation method for digital projects in the electric power industry in the prior art relies on historical data and cannot provide an objective and accurate calculation basis.
[0005] According to another aspect of the embodiment of the present disclosure, a method for estimating the cost of digital projects in the power industry is also provided, including: using a preset estimation model to determine the initial workload of the digital project according to the project type of the digital project; determining the workload influencing factor of the digital project according to the project type, and determining the final workload of the digital project according to the workload influencing factor and the initial workload; determining the initial total cost of the digital project according to the final workload; and cross-validating the initial total cost using a preset project portrait model to determine the final total cost of the digital project.
[0006] According to another aspect of an embodiment of the present disclosure, a storage medium is further provided, the storage medium including a stored program, wherein when the program is running, a processor executes any one of the methods described above.
[0007] According to another aspect of the embodiment of the present disclosure, a device for estimating the cost of digital projects in the power industry is also provided, including: a first determination module, used to determine the initial workload of the digital project according to the project type of the digital project by using a preset calculation model; a second determination module, used to determine the workload influencing factor of the digital project according to the project type, and determine the final workload of the digital project according to the workload influencing factor and the initial workload; a third determination module, used to determine the initial total cost of the digital project according to the final workload; and a fourth determination module, used to cross-validate the initial total cost using a preset project portrait model to determine the final total cost of the digital project.
[0008] According to another aspect of the embodiment of the present disclosure, there is also provided a device for estimating the cost of digital projects in the power industry, including: a processor; and a memory connected to the processor, for providing the processor with instructions for processing the following processing steps: using a preset estimation model to determine the initial workload of the digital project according to the project type of the digital project; determining the workload influencing factor of the digital project according to the project type, and determining the final workload of the digital project according to the workload influencing factor and the initial workload; determining the initial total cost of the digital project according to the final workload; and cross-validating the initial total cost using a preset project portrait model to determine the final total cost of the digital project.
[0009] In the disclosed embodiment, the workload is determined by the project type of the digital project, and the final workload of the project is determined by the pre-set workload influencing factors of different project types, so that the workload is calculated more accurately. And the initial total cost is cross-validated by the pre-set project portrait model, so that the accuracy of the calculated final total cost is higher. Therefore, the above scheme is applicable to the cost calculation method of digital projects in the power industry under the new situation, covering all types of work in digital projects in the power industry, and can improve the cost calculation ability of new digital projects with fast-changing demands, and better serve industries and enterprises. It further solves the technical problem that the existing cost calculation method of digital projects in the power industry in the prior art relies on historical data and cannot provide objective and accurate calculation basis. BRIEF DESCRIPTION OF THE DRAWINGS
[0010] The drawings described herein are used to provide a further understanding of the present disclosure and constitute a part of the present disclosure. The illustrative embodiments of the present disclosure and their descriptions are used to explain the present disclosure and do not constitute an improper limitation on the present disclosure. In the drawings:
[0011] Figure 1 is a hardware structure block diagram of a computing device for implementing the method according to Embodiment 1 of the present disclosure;
[0012] Figure 2 It is a flowchart of a method for estimating costs of digital projects in the electric power industry according to the first aspect of Embodiment 1 of the present disclosure;
[0013] Figure 3 It is another flow chart of the method for estimating the cost of digital projects in the electric power industry according to Embodiment 1 of the present disclosure;
[0014] Figure 4 is a schematic diagram of a device for calculating the cost of digital projects in the electric power industry according to Embodiment 2 of the present disclosure;
[0015] Figure 5 It is a schematic diagram of a digital project cost calculation device for the electric power industry according to Example 3 of the present disclosure. DETAILED DESCRIPTION
[0016] In order to enable those skilled in the art to better understand the technical solutions of the present disclosure, the technical solutions in the embodiments of the present disclosure will be clearly and completely described below in conjunction with the drawings in the embodiments of the present disclosure. Obviously, the described embodiments are only embodiments of a part of the present disclosure, not all of the embodiments. Based on the embodiments in the present disclosure, all other embodiments obtained by ordinary technicians in this field without making creative work should fall within the scope of protection of the present disclosure.
[0017] It should be noted that the terms "first", "second", etc. in the specification and claims of the present disclosure and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchangeable where appropriate, so that the embodiments of the present disclosure described herein can be implemented in an order other than those illustrated or described herein. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, method, system, product, or device that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products, or devices.
[0018] Example 1
[0019] According to this embodiment, an embodiment of a method for estimating the cost of digital projects in the power industry is also provided. It should be noted that the steps shown in the flowchart in the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and although a logical order is shown in the flowchart, in some cases, the steps shown or described may be executed in an order different from that shown here.
[0020] The method embodiment provided in this embodiment can be executed in a mobile terminal, a computer terminal, a server or a similar computing device. Figure 1 The hardware structure block diagram of a computing device for implementing a method for calculating the cost of digital projects in the power industry is shown. Figure 1 As shown, the computing device may include one or more processors (the processor may include but is not limited to a processing device such as a microprocessor MCU or a programmable logic device FPGA), a memory for storing data, and a transmission device for communication functions. In addition, it may also include: a display, an input / output interface (I / O interface), a universal serial bus (USB) port (which may be included as one of the ports of the I / O interface), a network interface, a power supply and / or a camera. It can be understood by those skilled in the art that Figure 1 The structure shown is only for illustration and does not limit the structure of the above electronic device. Figure 1 More or fewer components as shown, or with Figure 1 Different configurations are shown.
[0021] It should be noted that the one or more processors and / or other data processing circuits described above may generally be referred to herein as "data processing circuitry". The data processing circuitry may be embodied in whole or in part as software, hardware, firmware, or any other combination thereof. In addition, the data processing circuitry may be a single independent processing module, or may be incorporated in whole or in part into any of the other components of the computing device. As involved in the embodiments of the present disclosure, the data processing circuitry acts as a processor control (e.g., selection of a variable resistor terminal path connected to an interface).
[0022] The memory can be used to store software programs and modules of application software, such as the program instructions / data storage device corresponding to the method for calculating the cost of digital projects in the power industry in the embodiment of the present disclosure. The processor executes various functional applications and data processing by running the software programs and modules stored in the memory, that is, the method for calculating the cost of digital projects in the power industry of the above-mentioned application program is realized. The memory may include a high-speed random access memory, and may also include a non-volatile memory, such as one or more magnetic storage devices, flash memory, or other non-volatile solid-state memory. In some instances, the memory may further include a memory remotely arranged relative to the processor, and these remote memories may be connected to the computing device via a network. Examples of the above-mentioned network include, but are not limited to, the Internet, an intranet, a local area network, a mobile communication network, and combinations thereof.
[0023] The transmission device is used to receive or send data via a network. The specific example of the above network may include a wireless network provided by a communication provider of the computing device. In one example, the transmission device includes a network adapter (Network Interface Controller, NIC), which can be connected to other network devices through a base station so as to communicate with the Internet. In one example, the transmission device can be a radio frequency (Radio Frequency, RF) module, which is used to communicate with the Internet wirelessly.
[0024] The display may be, for example, a touch screen liquid crystal display (LCD) that may enable a user to interact with a user interface of the computing device.
[0025] It should be noted that, in some optional embodiments, the above Figure 1 The computing device shown may include hardware elements (including circuits), software elements (including computer code stored on a computer-readable medium), or a combination of both hardware elements and software elements. Figure 1 This is merely one example of a particular embodiment and is intended to illustrate the types of components that may be present in the computing devices described above.
[0026] In the above operating environment, according to the first aspect of this embodiment, a method for estimating the cost of digital projects in the power industry is provided. Figure 2 A schematic diagram showing the process of the method is shown in FIG. Figure 2 As shown, the method includes:
[0027] S201: using a preset calculation model, according to the project type of the digitization project, determining the initial workload of the digitization project;
[0028] S202: Determine a workload influencing factor of the digitization project according to the project type, and determine a final workload of the digitization project according to the workload influencing factor and the initial workload;
[0029] S203: Determine the initial total cost of the digitization project based on the final workload;
[0030] S204: Use a preset project portrait model to cross-validate the initial total cost to determine the final total cost of the digital project.
[0031] As described in the background technology, faced with new digital projects with "fast-changing demands, high business complexity, and strong innovation", the influencing factors of the original measurement model are difficult to play their due role, and can only rely on traditional methods such as analogy. Such methods are too dependent on the accuracy of cost estimates of industry / historical projects and are difficult to provide objective and accurate measurement basis.
[0032] In view of this, the method for calculating the cost of digital projects in the power industry provided by the embodiment of the present application first uses a pre-set calculation model to determine the initial workload of the digital project according to the project type of the digital project. Thus, the initial workload of the project is determined according to the project type, providing reliable calculation information for subsequent cost calculation, so that the calculation result is more reliable. Then, according to the project type, the workload influencing factor of the digital project is determined, and the final workload of the digital project is determined according to the workload influencing factor and the initial workload. By setting different workload influencing factors for different digital projects, the final workload is determined according to the initial workload of the project type, so that the workload is calculated more accurately. Then, according to the final workload, the initial total cost of the digital project is determined. The initial total cost is cross-validated using a pre-set project portrait model to determine the final total cost of the digital project. The project portrait model is obtained by learning using a machine learning algorithm based on the effective results of historical projects, so that the effectiveness and accuracy of the results of the calculation can be guaranteed by cross-validating the initial total cost using the project portrait model.
[0033] Therefore, through the above method, the workload is determined by the project type of the digital project, and the final workload of the project is determined by the pre-set workload influencing factors of different project types, so that the workload is calculated more accurately. And the initial total cost is cross-validated through the pre-set project portrait model, so that the accuracy of the calculated final total cost is higher. Therefore, the above scheme is applicable to the cost calculation method of digital projects in the power industry under the new situation, covering all types of work in digital projects in the power industry, and can improve the cost calculation ability of new digital projects with fast-changing demands, and better serve industries and enterprises. This solves the technical problem that the existing cost calculation method of digital projects in the power industry in the prior art relies on historical data and cannot provide objective and accurate calculation basis.
[0034] Optionally, a pre-set calculation model is used to determine the initial workload of the digitization project according to the project type of the digitization project, including: using a calculation model that combines the basic workload estimation method and the WBS decomposition method to calculate the digitization project according to the project type of the digitization project to determine the initial workload.
[0035] Specifically, a digital project cost calculation method is formed based on the workload base estimation method and WBS decomposition method, and a cost calculation method is formed for work types such as consulting design, system development, integration implementation, operation services, and data engineering, so as to expand the calculation scope and improve the accuracy of the calculation results.
[0036] Optionally, project types include consulting design, system development, integration implementation, operation services and data engineering, and based on the project type, operations of determining workload influencing factors of digital projects include: dividing the functions of digital projects based on the project type and determining the minimum number of functional units of the digital projects; and determining the workload influencing factors based on the minimum number of functional units of the digital projects.
[0037] Specifically, the system development functions are analyzed, and the minimum number of functional units corresponding to each function is scientifically determined according to the different construction difficulties. The influencing factors in the construction process of various types of work are analyzed, and corresponding workload influencing factors are formulated for consulting design, system development, integration implementation, operation services, and data engineering, so that the workload calculation can be closer to the actual situation of project construction.
[0038] Optionally, the operation of determining the initial total cost of the digitization project based on the final workload includes: determining the personnel information of the digitization project based on the project type, and determining the labor unit price corresponding to the personnel in the personnel information based on the personnel information; determining the initial total cost based on the personnel information, the labor unit price corresponding to the personnel information and the final workload.
[0039] Specifically, we analyze the personnel situation of various projects, combine the relevant personnel information released by the society, determine the unit price of labor for different types of work, and strive to make the cost estimation results closer to the actual situation.
[0040] Optionally, the initial total cost is cross-validated using a preset project portrait model to determine the final total cost of the digital project, including: judging whether the initial total cost conforms to a preset validation model based on cross-validation; and determining the initial total cost as the final total cost when the initial total cost conforms to the validation model.
[0041] Optionally, the initial total cost is cross-validated using a preset project portrait model to determine the final total cost of the digital project, and the operation also includes: if the initial total cost does not conform to the verification model, determining that the initial total cost is invalid.
[0042] Specifically, refer to Figure 3 As shown, the cost estimation result of the project, i.e. the initial total cost, is cross-validated with the project portrait model. If the estimation result meets the expectations of the project portrait model, the estimation result is deemed to be a valid result, and the cost estimation result and relevant basis of the project are issued; if the estimation result does not meet the expectations of the project portrait model, the estimation result is deemed to be an invalid result, and it is necessary to return to the third step for estimation and adjust the relevant model parameters.
[0043] Optionally, after determining that the initial total cost is invalid, the process further includes: adjusting the workload influencing factor to determine an updated initial total cost; and determining an updated final total cost based on the updated initial total cost.
[0044] Optionally, it also includes: storing the final total cost in a preset historical database, wherein the historical database is used to optimize the project portrait model.
[0045] Specifically, the project portrait model is implemented through data analysis and association mining. The input data can be the name, category, content, and cost information of the current project; the historical data is the project name, project classification, project content, project cost, etc. in recent years. The effective results are added to the historical database to continuously improve and optimize the project portrait model.
[0046] In addition, in the present invention, 1. the workload is calculated as follows:
[0047] (1) Consulting and design
[0048] The workload measurement model for consulting and design is as follows:
[0049] AE=ΣD×IFC
[0050] In the formula: AE——total workload;
[0051] ∑——the sum of the workload measurement values of each work task;
[0052] D——Consulting design task workload measurement value should be measured from the smallest subtask level according to the WBS decomposition results, and the workload base should be summarized from bottom to top to the consulting design task layer by layer, and matched with the consulting design basic workload table to obtain the corresponding workload value;
[0053] IFC – Influencing Factor of Consulting and Design Workload;
[0054] This calculation model is for a single consulting and design task. Projects involving multiple consulting and design tasks must be calculated separately and the results added together.
[0055] (2) System Development
[0056] The software functional scale workload measurement model is as follows:
[0057] S=Σ(F×C)
[0058] Where: S——software function scale, the unit is the smallest functional unit;
[0059] ∑——The sum of the functional scale of each level of software;
[0060] F——the number corresponding to the level coefficient of each software function item;
[0061] C——Grade coefficient of each software function item.
[0062] The development workload calculation model is shown below.
[0063] AE=(S×PDR)×IFD
[0064] Where: AE is the total workload, which covers three parts: demand analysis, system design (such as system outline design, detailed design, database design, use case diagram, etc.) and development (including system function development, database development, internal testing);
[0065] PDR – manual productivity rate;
[0066] IFD——Influencing Factor of System Development Workload.
[0067] (3) Integration Implementation
[0068] The workload measurement model for integrated implementation is as follows:
[0069] AE=Σ(D×SOI)×IFI
[0070] Where:
[0071] AE – total workload;
[0072] ∑——the sum of the workload measurement values of each work task;
[0073] D——The workload measurement value of the first-level work task should be measured from the smallest work task level according to the WBS decomposition results, and the workload base should be summarized from bottom to top to the first-level work task layer by layer, and matched with the integrated implementation basic workload table to obtain the corresponding workload value;
[0074] SOI – the number of implementation scopes involved in the work task;
[0075] IFI – Integrated Implementation Impact Factor.
[0076] (4) Business operations
[0077] The business operation workload measurement model is as follows:
[0078] AE=Σ(D×SOS)×IFO
[0079] Where:
[0080] AE – total workload;
[0081] ∑——the sum of the workload measurement values of each work task;
[0082] D——The workload measurement value of the first-level work task should be measured from the smallest work task level according to the WBS decomposition results, and the workload base should be summarized from bottom to top to the first-level work task layer by layer, and matched with the basic workload table of business operations to obtain the corresponding workload value;
[0083] SOS – the number of operational scopes involved in the work task;
[0084] IFO – Factor affecting business operations.
[0085] This calculation model is for a single business operation. Projects involving multiple business operations must be calculated separately and the results added together.
[0086] (5) Data Engineering
[0087] The data engineering workload measurement model is as follows:
[0088] AE=Σ(D×SOP)×IFP
[0089] Where:
[0090] AE – total workload;
[0091] ∑——the sum of the workload measurement values of each work task;
[0092] D——The workload measurement value of the first-level work task should be measured from the smallest work task level according to the WBS decomposition results, and the workload base should be summarized from bottom to top to the first-level work task layer by layer, and matched with the data engineering basic workload table to obtain the corresponding workload value;
[0093] SOP – the number of engineering scopes involved in the work task;
[0094] IFP – Impact Factor for Data Engineering.
[0095] This calculation model is for a single data engineering task. Projects involving multiple data engineering tasks must be calculated separately and the results added together.
[0096] 2. Cost calculation
[0097] Overall workload cost of the project = Σ(final workload of each type of work * labor rate)
[0098] Where:
[0099] Σ——The sum of the total workload costs of each type of work.
[0100] Cross-validate the project's cost estimation results and the project portrait model. If the estimation results are in line with the expectations of the project portrait model, the estimation results are deemed valid and the cost estimation results and related basis for the project are issued. If the estimation results do not meet the expectations of the project portrait model, the estimation results are deemed invalid and require recalculation and adjustment of relevant model parameters.
[0101] 3. Archive
[0102] Add effective results to the historical database and continuously improve and optimize the project portrait model
[0103] In addition, reference Figure 1 As shown, according to the second aspect of this embodiment, a storage medium is provided, wherein the storage medium includes a stored program, wherein when the program is run, a processor executes any one of the above methods.
[0104] Therefore, according to this embodiment, the workload is determined by the project type of the digital project, and the final workload of the project is determined by the pre-set workload influencing factors of different project types, so that the workload is calculated more accurately. And the initial total cost is cross-validated through the pre-set project portrait model, so that the accuracy of the calculated final total cost is higher. Therefore, the above scheme is applicable to the cost calculation method of digital projects in the power industry under the new situation, covering all types of work in digital projects in the power industry, and can improve the cost calculation ability of new digital projects with fast-changing demands, and better serve industries and enterprises. This solves the technical problem that the existing cost calculation method of digital projects in the power industry in the prior art relies on historical data and cannot provide objective and accurate calculation basis.
[0105] In addition, this cost calculation method covers five types of work in power grid digitalization projects: consulting design, system development, integrated implementation, business operations, and data engineering. For projects with "fast demand changes, high business complexity, strong innovation, high difficulty, high performance requirements, high user experience requirements, and good application results", or projects that require long-term technical or business support, this cost calculation model and system can accurately and reasonably calculate the costs of such digitalization projects.
[0106] In addition, reference Figure 3 As shown in the figure, the specific process of the cost calculation method for digital projects in the power industry is as follows:
[0107] The first step is to determine the type of digitization project.
[0108] The second step is that if the digitalization project is a business consulting, integration implementation, business operation, and data engineering digitalization project, use a measurement model that combines the basic workload estimation method and the WBS decomposition method to calculate the initial workload.
[0109] The third step is to determine the workload impact factor of each type of project based on the project situation and multiply it by the initial workload of each type of project to obtain the final workload of each type of project.
[0110] The fourth step is to multiply the labor rate of each project type by the final workload of each project type to get the cost of each project type. The sum of the costs of each project type is the total cost of the project.
[0111] The fifth step is to cross-validate the cost estimation results of the project with the project portrait model. If the estimation results meet the expectations of the project portrait model, the estimation results are deemed to be valid, and the cost estimation results and relevant basis of the project are issued. If the estimation results do not meet the expectations of the project portrait model, the estimation results are deemed to be invalid, and it is necessary to return to the third step for estimation and adjust the relevant model parameters.
[0112] The sixth step is to add effective results to the historical database and continuously improve and optimize the project portrait model.
[0113] It should be noted that, for the above-mentioned method embodiments, for the sake of simplicity, they are all described as a series of action combinations, but those skilled in the art should know that the present invention is not limited by the described action sequence, because according to the present invention, certain steps can be performed in other sequences or simultaneously. Secondly, those skilled in the art should also know that the embodiments described in the specification are all preferred embodiments, and the actions and modules involved are not necessarily required by the present invention.
[0114] Through the description of the above implementation methods, those skilled in the art can clearly understand that the method according to the above embodiment can be implemented by means of software plus a necessary general hardware platform, and of course can also be implemented by hardware, but in many cases the former is a better implementation method. Based on such an understanding, the technical solution of the present invention, or the part that contributes to the prior art, can be embodied in the form of a software product, which is stored in a storage medium (such as ROM / RAM, a magnetic disk, or an optical disk), and includes a number of instructions for enabling a terminal device (which can be a mobile phone, a computer, a server, or a network device, etc.) to execute the methods described in each embodiment of the present invention.
[0115] Example 2
[0116] Figure 4 The device 400 for calculating the cost of a digital project in the power industry according to this embodiment is shown. The device 400 corresponds to the method described in the first aspect of the embodiment 1. Figure 4As shown, the device 400 includes: a first determination module 410, which is used to determine the initial workload of the digitization project according to the project type of the digitization project by using a preset measurement model; a second determination module 420, which is used to determine the workload influencing factor of the digitization project according to the project type, and determine the final workload of the digitization project according to the workload influencing factor and the initial workload; a third determination module 430, which is used to determine the initial total cost of the digitization project according to the final workload; and a fourth determination module 440, which is used to cross-validate the initial total cost by using a preset project portrait model to determine the final total cost of the digitization project.
[0117] Optionally, the first determination module 410 includes: a first determination submodule, which is used to use a calculation model combining a basic workload estimation method and a WBS decomposition method to calculate the digitization project according to the project type of the digitization project and determine the initial workload.
[0118] Optionally, project types include consulting design, system development, integrated implementation, operational services and data engineering, and the second determination module 420 includes: a second determination sub-module, used to divide the functions of the digitization project according to the project type, and determine the minimum number of functional units of the digitization project; a third determination sub-module, used to determine the workload influencing factor according to the minimum number of functional units of the digitization project.
[0119] Optionally, the third determination module 430 includes: a fourth determination sub-module, used to determine the personnel information of the digital project according to the project type, and determine the labor unit price corresponding to the personnel in the personnel information based on the personnel information; a fifth determination sub-module, used to determine the initial total cost based on the personnel information, the labor unit price corresponding to the personnel information and the final workload.
[0120] Optionally, the fourth determination module 440 includes: a judgment submodule, used to judge whether the initial total cost meets the preset verification model based on cross-validation; and a sixth determination submodule, used to determine that the initial total cost is the final total cost when the initial total cost meets the verification model.
[0121] Optionally, the fourth determination module 440 further includes: a determination submodule, configured to determine that the initial total cost is invalid when the initial total cost does not conform to the verification model.
[0122] Optionally, after determining that the initial total cost is invalid, the device 400 further includes: a fifth determination module for adjusting the workload influencing factor to determine the updated initial total cost; and a sixth determination module for determining the updated final total cost based on the updated initial total cost.
[0123] Optionally, the device 400 also includes: a storage module, used to store the final total cost into a preset historical database, wherein the historical database is used to optimize the project portrait model.
[0124] Therefore, according to this embodiment, the workload is determined by the project type of the digital project, and the final workload of the project is determined by the pre-set workload influencing factors of different project types, so that the workload is calculated more accurately. And the initial total cost is cross-validated through the pre-set project portrait model, so that the accuracy of the calculated final total cost is higher. Therefore, the above scheme is applicable to the cost calculation method of digital projects in the power industry under the new situation, covering all types of work in digital projects in the power industry, and can improve the cost calculation ability of new digital projects with fast-changing demands, and better serve industries and enterprises. This solves the technical problem that the existing cost calculation method of digital projects in the power industry in the prior art relies on historical data and cannot provide objective and accurate calculation basis.
[0125] Example 3
[0126] Figure 5 The device 500 for calculating the cost of a digital project in the power industry according to this embodiment is shown. The device 500 corresponds to the method described in the first aspect of the embodiment 1. Figure 5 As shown, the device 500 includes: a processor 510; and a memory 520, which is connected to the processor 510 and is used to provide the processor 510 with instructions for processing the following processing steps: using a preset measurement model to determine the initial workload of the digitization project according to the project type of the digitization project; determining the workload influencing factor of the digitization project according to the project type, and determining the final workload of the digitization project according to the workload influencing factor and the initial workload; determining the initial total cost of the digitization project based on the final workload; cross-validating the initial total cost using a preset project portrait model to determine the final total cost of the digitization project.
[0127] Optionally, a pre-set calculation model is used to determine the initial workload of the digitization project according to the project type of the digitization project, including: using a calculation model that combines the basic workload estimation method and the WBS decomposition method to calculate the digitization project according to the project type of the digitization project to determine the initial workload.
[0128] Optionally, project types include consulting design, system development, integration implementation, operation services and data engineering, and based on the project type, operations of determining workload influencing factors of digital projects include: dividing the functions of digital projects based on the project type and determining the minimum number of functional units of the digital projects; and determining the workload influencing factors based on the minimum number of functional units of the digital projects.
[0129] Optionally, the operation of determining the initial total cost of the digitization project based on the final workload includes: determining the personnel information of the digitization project based on the project type, and determining the labor unit price corresponding to the personnel in the personnel information based on the personnel information; determining the initial total cost based on the personnel information, the labor unit price corresponding to the personnel information and the final workload.
[0130] Optionally, the initial total cost is cross-validated using a preset project portrait model to determine the final total cost of the digital project, including: judging whether the initial total cost conforms to a preset validation model based on cross-validation; and determining the initial total cost as the final total cost when the initial total cost conforms to the validation model.
[0131] Optionally, the initial total cost is cross-validated using a preset project portrait model to determine the final total cost of the digital project, and the operation also includes: if the initial total cost does not conform to the verification model, determining that the initial total cost is invalid.
[0132] Optionally, after determining that the initial total cost is invalid, the memory 520 is further used to provide the processor 510 with instructions for processing the following processing steps: adjusting the workload impact factor to determine an updated initial total cost; and determining an updated final total cost based on the updated initial total cost.
[0133] Optionally, the memory 520 is also used to provide the processor 510 with instructions for processing the following processing steps: storing the final total cost in a preset historical database, wherein the historical database is used to optimize the project portrait model.
[0134] Therefore, according to this embodiment, the workload is determined by the project type of the digital project, and the final workload of the project is determined by the pre-set workload influencing factors of different project types, so that the workload is calculated more accurately. And the initial total cost is cross-validated through the pre-set project portrait model, so that the accuracy of the calculated final total cost is higher. Therefore, the above scheme is applicable to the cost calculation method of digital projects in the power industry under the new situation, covering all types of work in digital projects in the power industry, and can improve the cost calculation ability of new digital projects with fast-changing demands, and better serve industries and enterprises. This solves the technical problem that the existing cost calculation method of digital projects in the power industry in the prior art relies on historical data and cannot provide objective and accurate calculation basis.
[0135] The serial numbers of the above embodiments of the present invention are only for description and do not represent the advantages or disadvantages of the embodiments.
[0136] In the above embodiments of the present invention, the description of each embodiment has its own emphasis. For parts that are not described in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.
[0137] In the several embodiments provided by the present invention, it should be understood that the disclosed technical content can be implemented in other ways. Among them, the device embodiments described above are only schematic, for example, the division of the units is only a logical function division, and there may be other division methods in actual implementation, for example, multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point, the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of units or modules, which can be electrical or other forms.
[0138] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0139] In addition, each functional unit in each embodiment of the present invention may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of software functional units.
[0140] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, in essence, or the part that contributes to the prior art, or all or part of the technical solution can be embodied in the form of a software product, and the computer software product is stored in a storage medium, including a number of instructions for a computer device (which can be a personal computer, a server or a network device, etc.) to perform all or part of the steps of the method described in each embodiment of the present invention. The aforementioned storage medium includes: U disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), mobile hard disk, magnetic disk or optical disk and other media that can store program codes.
[0141] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.
Claims
1. A method for estimating the cost of digital projects in the power industry. It is characterized in that include: Determine the initial workload of the digitization project according to the project type of the digitization project by using a preset estimation model; Determine, according to the project type, a workload influencing factor of the digitization project, and determine, according to the workload influencing factor and the initial workload, a final workload of the digitization project; determining an initial total cost for the digitization project based on the final workload; The initial total cost is cross-validated using a preset project portrait model to determine the final total cost of the digital project, wherein: The project types include: consulting and design, system development, integration and implementation, business operation, and data engineering. According to the project types, the operation of determining the workload influencing factor of the digital project includes: According to the project type, the digital project is functionally divided to determine the minimum number of functional units of the digital project; Determining the workload impact factor according to the minimum number of functional units of the digital project; in, The workload of the consulting and design category is: AE 1 =ΣD 1 ×IFC In the formula, AE 1 is the total workload of consulting design; ∑ is the sum of the workload measurement values of each task; D 1 Design task workload metrics for consulting, D 1 It is measured from the smallest subtask level according to the WBS decomposition results, and the workload base is summarized from bottom to top to the consulting design tasks layer by layer, and matched with the consulting design basic workload table; IFC is the consulting design workload influencing factor; The workload of the system development category is: BUT 2 =(S×PDR)×IFD in, S=Σ(F×C) In the formula, AE 2 is the total workload of system development; PDR is the manual productivity; IFD is the influencing factor of system development workload; S is the software function scale, the unit is the minimum functional unit; ∑ is the sum of the software function scales of each level; F is the number corresponding to the level coefficient of each software function item; C is the level coefficient of each software function item; The workload of the integration implementation class is: AE 3 =Σ(D 2 ×SOI)×IFI In the formula, AE 3 is the total workload; ∑ is the sum of the workload measurement values of each task; D 2 is the workload measurement value of the first-level task, D 2 It is measured from the smallest work task level according to the WBS decomposition results, and the workload base is summarized from bottom to top to the first-level work task, and matched with the integrated implementation basic workload table; SOI is the number of implementation scopes involved in the work task; IFI is the integrated implementation influencing factor; The workload of the business operation category is: AE 4 =Σ(D 3 ×SOS)×IFO In the formula, AE 4 is the total workload; ∑ is the sum of the workload measurement values of each task; D 3 is the workload measurement value of the first-level task, D 3 It is measured from the smallest work task level according to the WBS decomposition results, and the workload base is summarized from bottom to top to the first-level work task, and matched with the basic workload table of business operations; SOS is the number of operation scopes involved in the work task; IFO is the business operation influencing factor; The workload of the data engineering category is: AE 5 =Σ(D 4 ×SOP)×IFP In the formula, AE 5 is the total workload; ∑ is the sum of the workload measurement values of each task; D 4 is the workload measurement value of the first-level task, D 4 It is measured from the smallest work task level according to the WBS decomposition results, and the workload base is summarized from bottom to top to the first-level work task layer by layer, and matched with the basic workload table of data engineering; SOP is the number of engineering scopes involved in the work task; IFP is the data engineering impact factor; The operation of cross-validating the initial total cost by using a preset project portrait model to determine the final total cost of the digital project includes: Determining whether the initial total cost conforms to a preset validation model according to the cross validation; In the case where the initial total cost meets the verification model, determining the initial total cost as the final total cost; The operation of cross-validating the initial total cost by using a preset project portrait model to determine the final total cost of the digital project also includes: If the initial total cost does not conform to the verification model, determining that the initial total cost is invalid; After determining that the initial total cost is invalid, the process further includes: Adjusting the workload impact factor to determine the initial total cost of the update; Determining a final total cost of updating based on the initial total cost of updating; The operation of determining the initial workload of the digitization project according to the project type of the digitization project by using a preset calculation model includes: The calculation model combining the basic workload estimation method and the WBS decomposition method is used to calculate the digitization project according to the project type of the digitization project to determine the initial workload.
2. The method according to claim 1, It is characterized in that The operation of determining the initial total cost of the digitization project based on the final workload includes: Determine personnel information of the digitization project according to the project type, and determine a labor unit price corresponding to the personnel in the personnel information according to the personnel information; The initial total cost is determined according to the personnel information, the labor unit price corresponding to the personnel information, and the final workload.
3. The method according to claim 1, It is characterized in that Also includes: The final total cost is stored in a preset historical database, wherein the historical database is used to optimize the project portrait model.
4. A computer-readable storage medium, It is characterized in that The storage medium includes a stored program, wherein when the program is executed, the processor executes the method according to any one of claims 1 to 3.
5. A digital project cost calculation device for the power industry, It is characterized in that include: A first determination module is used to determine the initial workload of the digitization project according to the project type of the digitization project by using a preset calculation model; A second determination module is used to determine the workload impact factor of the digitization project according to the project type, and determine the final workload of the digitization project according to the workload impact factor and the initial workload; A third determination module, configured to determine the initial total cost of the digitization project according to the final workload; The fourth determination module is used to cross-validate the initial total cost using a preset project portrait model to determine the final total cost of the digital project, wherein: The project types include: consulting and design, system development, integration and implementation, business operation, and data engineering. The second determination module includes: A second determination submodule is used to divide the digital project into functions according to the project type and determine the minimum number of functional units of the digital project; A third determination submodule is used to determine the workload impact factor according to the minimum number of functional units of the digital project; in, The workload of the consulting and design category is: AE 1 =ΣD 1 ×IFC In the formula, AE 1 is the total workload of consulting design; ∑ is the sum of the workload measurement values of each task; D 1 Design task workload metrics for consulting, D 1 It is measured from the smallest subtask level according to the WBS decomposition results, and the workload base is summarized from bottom to top to the consulting design tasks layer by layer, and matched with the consulting design basic workload table; IFC is the consulting design workload influencing factor; The workload of the system development category is: BUT 2 =(S×PDR)×IFD in, S=Σ(F×C) In the formula, AE 2 is the total workload of system development; PDR is the manual productivity; IFD is the influencing factor of system development workload; S is the software function scale, the unit is the minimum functional unit; ∑ is the sum of the software function scales of each level; F is the number corresponding to the level coefficient of each software function item; C is the level coefficient of each software function item; The workload of the integration implementation class is: AE 3 =Σ(D 2 ×SOI)×IFI In the formula, AE 3 is the total workload; ∑ is the sum of the workload measurement values of each task; D 2 is the workload measurement value of the first-level task, D 2 It is measured from the smallest work task level according to the WBS decomposition results, and the workload base is summarized from bottom to top to the first-level work task, and matched with the integrated implementation basic workload table; SOI is the number of implementation scopes involved in the work task; IFI is the integrated implementation influencing factor; The workload of the business operation category is: AE 4 =Σ(D 3 ×SOS)×IFO In the formula, AE 4 is the total workload; ∑ is the sum of the workload measurement values of each task; D 3 is the workload measurement value of the first-level task, D 3 It is measured from the smallest work task level according to the WBS decomposition results, and the workload base is summarized from bottom to top to the first-level work task, and matched with the basic workload table of business operations; SOS is the number of operation scopes involved in the work task; IFO is the business operation influencing factor; The workload of the data engineering category is: AE 5 =Σ(D 4 ×SOP)×IFP In the formula, AE 5 is the total workload; ∑ is the sum of the workload measurement values of each task; D 4 is the workload measurement value of the first-level task, D 4 It is measured from the smallest work task level according to the WBS decomposition results, and the workload base is summarized from bottom to top to the first-level work task layer by layer, and matched with the basic workload table of data engineering; SOP is the number of engineering scopes involved in the work task; IFP is the data engineering impact factor; The third determination module includes: A fourth determination submodule is used to determine the personnel information of the digitization project according to the project type, and determine the labor unit price corresponding to the personnel in the personnel information according to the personnel information; A fifth determination submodule, configured to determine the initial total cost according to the personnel information, the labor unit price corresponding to the personnel information, and the final workload; The fourth determination module includes: A judgment submodule, used for judging whether the initial total cost conforms to a preset verification model according to the cross-validation; A sixth determination submodule, configured to determine the initial total cost as the final total cost if the initial total cost conforms to the verification model; The fourth determination module further includes: A determination submodule, configured to determine that the initial total cost is invalid if the initial total cost does not conform to the verification model; After determining that the initial total cost is invalid, the process further includes: A fifth determination module, used to adjust the workload impact factor and determine the initial total cost of the update; A sixth determination module, configured to determine a final total cost of updating according to the initial total cost of updating; The first determination module includes: The first determination submodule is used to use the calculation model that combines the basic workload estimation method and the WBS decomposition method to calculate the digitization project according to the project type of the digitization project and determine the initial workload.
6. The device according to claim 5, It is characterized in that Also includes: A storage module is used to store the final total cost into a preset historical database, wherein the historical database is used to optimize the project portrait model.
7. A digital project cost calculation device for the power industry, It is characterized in that include: processor; as well as A memory, connected to the processor, configured to provide the processor with instructions for processing the following processing steps: Determine the initial workload of the digitization project according to the project type of the digitization project by using a preset estimation model; Determine, according to the project type, a workload influencing factor of the digitization project, and determine, according to the workload influencing factor and the initial workload, a final workload of the digitization project; determining an initial total cost for the digitization project based on the final workload; Cross-validating the initial total cost using a preset project portrait model to determine the final total cost of the digital project; The project types include: consulting and design, system development, integration and implementation, business operation, and data engineering. According to the project types, the operation of determining the workload influencing factor of the digital project includes: According to the project type, the digital project is functionally divided to determine the minimum number of functional units of the digital project; Determining the workload impact factor according to the minimum number of functional units of the digital project; in, The workload of the consulting and design category is: AE 1 =ΣD 1 ×IFC In the formula, AE 1 is the total workload of consulting design; ∑ is the sum of the workload measurement values of each task; D 1 Design task workload metrics for consulting, D 1 It is measured from the smallest subtask level according to the WBS decomposition results, and the workload base is summarized from bottom to top to the consulting design tasks layer by layer, and matched with the consulting design basic workload table; IFC is the consulting design workload influencing factor; The workload of the system development category is: BUT 2 =(S×PDR)×IFD in, S=Σ(F×C) In the formula, AE 2 is the total workload of system development; PDR is the manual productivity; IFD is the influencing factor of system development workload; S is the software function scale, the unit is the minimum functional unit; ∑ is the sum of the software function scales of each level; F is the number corresponding to the level coefficient of each software function item; C is the level coefficient of each software function item; The workload of the integration implementation class is: AE 3 =Σ(D 2 ×SOI)×IFI In the formula, AE 3 is the total workload; ∑ is the sum of the workload measurement values of each task; D 2 is the workload measurement value of the first-level task, D 2 It is measured from the smallest work task level according to the WBS decomposition results, and the workload base is summarized from bottom to top to the first-level work task, and matched with the integrated implementation basic workload table; SOI is the number of implementation scopes involved in the work task; IFI is the integrated implementation influencing factor; The workload of the business operation category is: AE 4 =Σ(D 3 ×SOS)×IFO In the formula, AE 4 is the total workload; ∑ is the sum of the workload measurement values of each task; D 3 is the workload measurement value of the first-level task, D 3 It is measured from the smallest work task level according to the WBS decomposition results, and the workload base is summarized from bottom to top to the first-level work task, and matched with the basic workload table of business operations; SOS is the number of operation scopes involved in the work task; IFO is the business operation influencing factor; The workload of the data engineering category is: AE 5 =Σ(D 4 ×SOP)×IFP In the formula, AE 5 is the total workload; ∑ is the sum of the workload measurement values of each task; D 4 is the workload measurement value of the first-level task, D 4 It is measured from the smallest work task level according to the WBS decomposition results, and the workload base is summarized from bottom to top to the first-level work task layer by layer, and matched with the basic workload table of data engineering; SOP is the number of engineering scopes involved in the work task; IFP is the data engineering impact factor; The operation of cross-validating the initial total cost by using a preset project portrait model to determine the final total cost of the digital project includes: Determining whether the initial total cost conforms to a preset validation model according to the cross validation; In the case where the initial total cost meets the verification model, determining the initial total cost as the final total cost; The operation of cross-validating the initial total cost by using a preset project portrait model to determine the final total cost of the digital project also includes: If the initial total cost does not conform to the verification model, determining that the initial total cost is invalid; After determining that the initial total cost is invalid, the process further includes: Adjusting the workload impact factor to determine the initial total cost of the update; Determining a final total cost of updating based on the initial total cost of updating; The operation of determining the initial workload of the digitization project according to the project type of the digitization project by using a preset calculation model includes: The calculation model combining the basic workload estimation method and the WBS decomposition method is used to calculate the digitization project according to the project type of the digitization project to determine the initial workload.