A method for advanced detection of fault structures by combining seismic and electrical methods in boreholes and tunnels
Through the advanced detection method of fault structures combined with holes and tunnels, the comprehensive use of seismic and electrical data is used to solve the problem that a single method in the existing technology is difficult to judge geological structures and water-containing areas, and the geological structures and water-containing areas are realized. Accurate judgment improves construction efficiency and data accuracy.
Patent Information
- Application Number
- CN202211088068.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-09-07
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2042-09-07
AI Technical Summary
The existing advance detection methods are single, making it difficult to comprehensively judge the properties of the geological structure and the water-containing area ahead, and it is difficult to obtain comprehensive information during construction, which affects production efficiency and safety.
Adopting the advanced detection method of fault structures combining earthquake and electricity from holes and tunnels, by laying seismic detectors in the tunnels and measuring electrodes in the drilling holes, comprehensively using seismic wave method and electrical data, the geological structure forms and Water-containing area information is detected in combination with the wave impedance difference value.
It realizes accurate judgment of the geological structure range and water-containing area ahead, improves construction efficiency and data accuracy, simplifies the construction process, and enhances the reliability and accuracy of detection.
Smart Images

Figure CN115390142B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a method for advanced detection of fault structures, in particular to a method for advanced detection of fault structures combining seismic and electrical detection in boreholes and tunnels, and belongs to the technical field of advanced detection of geological exploration. Background Art
[0002] During the tunnel excavation process, the geological structure ahead will affect the construction progress and personnel safety. Accurately measuring its properties can provide important support for production efficiency and safety. At present, most of the advanced detection methods are based on a single method, such as seismic wave method, electrical method, and electromagnetic method. Among them, the seismic wave method has significant advantages in the morphological identification of geological structures, while the electrical method and electromagnetic method have more advantages in solving the water content problem. Therefore, it is difficult for a single method to make a comprehensive judgment on the nature of the geological structure. At the same time, at present, only one of the tunnels or detection boreholes is used as the detection space for advanced detection during detection. Such a single method can often only obtain local information and is difficult to reflect the comprehensive situation of the structure ahead. It is impossible to provide data support for subsequent construction. In addition, the existing advanced detection technology still has the problems of limited accuracy and single function. Therefore, how to provide an advanced detection method that can combine the advantages of multiple detection methods, so as to not only accurately judge the scope of the geological structure ahead and whether there is a water-containing area inside it, but also simplify its construction process, is one of the research directions of this industry. Summary of the invention
[0003] In view of the problems existing in the above-mentioned prior art, the present invention provides a method for advance detection of fault structures in boreholes and tunnels by combining seismic and electrical detection, which can integrate the advantages of multiple detection methods, thereby not only accurately judging the scope of the geological structure ahead and whether there are water-containing areas inside it, but also having a simple construction process.
[0004] In order to achieve the above-mentioned purpose, the technical solution adopted by the present invention is: a method for advanced detection of fault structures by combining seismic and electrical methods in boreholes and tunnels, the specific steps of which are:
[0005] A. Arrange multiple seismic detectors in a row in the tunnel. The multiple seismic detectors are connected to the while-drilling seismic host and the seismic base station through seismic data transmission lines. The acquisition parameters of each seismic detector are set through the while-drilling seismic host, thereby completing the deployment of the while-drilling seismic advance detection system;
[0006] B. Start the construction of exploratory drilling in front of the tunnel. During the drilling process, the seismic host controls each seismic detector to collect seismic data according to the set acquisition parameters. Each seismic detector receives the seismic wave data generated during drilling and transmits it to the seismic base station for storage until the construction of the exploratory drilling is completed. The lithology of each rock layer passed by the entire exploratory drilling can be determined based on the drill cuttings discharged during the exploratory drilling construction. The part of the exploratory drilling that passes through the same rock layer is set as a lithology segment, thereby dividing the exploratory drilling into multiple different lithology segments;
[0007] C. The seismic host extracts the seismic data stored in the seismic base station, converts the seismic data into pseudo-active source data through the interference method, and then inputs the observation system coordinates and performs empirical mode decomposition to eliminate the equipment vibration interference, obtains the main frequency of the while-drilling signal, and then extracts the reflected wave by picking up the first arrival of the longitudinal and transverse waves, and uses the velocity range determined by the direct wave as the velocity background value for depth migration, and according to the wave impedance difference between the rock layer where the current exploration borehole is located and its overlying stratum, because the rock layer is composed of dense rock mass and loose rock mass, the wave impedance difference between the dense rock area and the overlying stratum is determined as the primary wave impedance difference value, and the wave impedance difference between the loose rock area and the overlying stratum is determined as the secondary wave impedance difference value, and the secondary wave impedance difference value is smaller than the primary wave impedance difference value; then, on the basis of determining the propagation direction of the reflected wave by the three-component detector polarization analysis, the primary wave impedance difference value is used as the center, and the half wavelength of the main frequency is used as the diameter to circle the fault structure morphology contour within a certain range in front, and complete the preliminary geological structure detection process in front of the tunnel;
[0008] D. Multiple measuring electrodes are arranged in a row in the exploration borehole. Each measuring electrode is connected to the electrical acquisition base station outside the exploration borehole through an electrical data transmission line. The electrical acquisition base station is connected to the electrical host. According to the different lithology sections where each measuring electrode is located, the acquisition parameters of the measuring electrodes in different lithology sections are set through the electrical host, thereby completing the layout of the electrical advance detection system;
[0009] E. The electrical method host controls each measuring electrode to collect electrical method data in the hole according to the collection parameters set in step D. Each measuring electrode transmits the collected electrical method data to the electrical method collection base station for storage. The electrical method host extracts the electrical method data stored in the electrical method base station, obtains the apparent resistivity profile within a certain range in front of the exploration borehole through inversion, and then delineates the water-bearing area according to the apparent resistivity of each area in the apparent resistivity profile, thereby completing the process of advanced detection of water-rich areas;
[0010] F. Compare the fault structure morphology outline determined in step C with the water-bearing area determined in step E:
[0011] If the water-bearing area is completely within the contour of the fault structure, the overlapping area of the two is determined to be the water-bearing fault structure area;
[0012] If part of the water-bearing area is within the fault structural morphological contour, the seismic data is selected to re-delineate the structural morphological contour with the secondary wave impedance difference value as the center and the half wavelength of the main frequency as the diameter. Since the secondary wave impedance difference value is smaller than the primary wave impedance difference value, the structural morphological contour delineated with it as the standard is larger. The area where the re-delineated structural morphological contour overlaps with the water-bearing area is selected as the water-bearing fault structural area.
[0013] If the water-bearing area is not completely within the fault structural morphological contour, the fault structural morphological contour is determined to be a water-free fault structural area;
[0014] Through the above-mentioned comparison and analysis, a comprehensive detection can be carried out on the position and range of the fault structure in front of the tunnel, as well as whether there is a water-containing area within the range of the fault structure. After completing the detection, the tunnel is excavated forward for a distance and the exploration drilling is constructed again. Then the above steps are repeated, and the results of this detection are superimposed with the results of the previous detection. Since this detection is closer to the same detection range as the previous one, its detection accuracy is higher. Therefore, the areas with the same judgment are retained, and the different areas are updated based on the results of this detection. The detection results are repeatedly updated and corrected to effectively ensure the detection accuracy.
[0015] Furthermore, the seismic detector is a three-component velocity detector, and the spacing between adjacent seismic detectors in the tunnel is less than 5m.
[0016] Furthermore, the spacing between adjacent measuring electrodes in the exploration borehole is less than 2 m; and the measuring electrodes are copper wire electrodes.
[0017] Furthermore, the acquisition parameters of the seismic detector in step A include sampling frequency, number of sampling points, number of advance sampling points, magnification, and triggering mode.
[0018] Furthermore, the acquisition parameters of the measuring electrode in step D include power supply time and power supply voltage.
[0019] Compared with the prior art, the present invention collects seismic data while drilling during the construction of exploratory drilling. At this time, the main source of the signal is the construction of the exploratory drilling. Compared with other passive seismic data, the interference is relatively small and there is no need to stop the excavation specifically for data collection, which improves the construction efficiency; after the exploratory drilling construction is completed, the existing exploratory drilling is used to collect in-hole electrical data. Compared with the metal interference of anchor nets, machines and the like in the tunnel, the metal interference in the borehole is less, which can ensure the validity of the electrical data, and the exploratory drilling hole is closer to the fault, which can improve the accuracy of the data; finally, the comprehensive analysis and comparison of the tunnel and hole data are carried out, and the fault structure morphological contour is overlapped and compared with the water-bearing area. The situation of the detection area is determined according to different situations, and two wave impedance difference values are used for processing in different situations. Finally, the influence range of the fault structure can be delineated and the fault structure contour can be accurately determined, thereby effectively improving the data reliability. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 It is a schematic diagram of the layout structure of the present invention during detection;
[0021] Figure 2 It is a diagram of seismic wave data obtained by the present invention through seismic while drilling;
[0022] Figure 3 This is a diagram of electrical data obtained by the in-hole electrical method of the present invention.
[0023] In the figure: 1- seismic host while drilling, 2- seismic data transmission line, 3- seismic detector, 4- seismic base station, 5- electrical method host, 6- electrical method acquisition base station, 7- electrical method data transmission line, 8- measuring electrode. DETAILED DESCRIPTION
[0024] The present invention will be further described below.
[0025] like Figure 1 As shown, the specific steps of the present invention are:
[0026] A. Arrange multiple geophones 3 in a row in the tunnel. The multiple geophones 3 are connected to the while-drilling seismic host 1 and the seismic base station 4 respectively through the seismic data transmission line 2. Set the acquisition parameters of each geophone 3 through the while-drilling seismic host 1, which include sampling frequency, number of sampling points, number of advanced sampling points, magnification, triggering mode, etc. The geophone 3 is a three-component velocity geophone. The spacing between adjacent geophones 3 in the tunnel is less than 5m. Thus, the arrangement of the while-drilling seismic advanced detection system is completed;
[0027] B. Start the construction of exploratory drilling in front of the tunnel. During the drilling process, the seismic host 1 controls each seismic detector 3 to collect seismic data according to the set acquisition parameters. Each seismic detector 3 receives the seismic wave data generated during drilling and transmits it to the seismic base station 4 for storage until the construction of the exploratory drilling is completed. The lithology of each rock layer passed by the entire exploratory drilling can be determined based on the drill cuttings discharged during the exploratory drilling construction. The part of the exploratory drilling that passes through the same rock layer is set as a lithology segment, thereby dividing the exploratory drilling into multiple different lithology segments;
[0028] C. Figure 2 As shown, the seismic host 1 extracts the seismic data stored in the seismic base station 4, converts the seismic data into quasi-active source data through the interference method, and then inputs the observation system coordinates and performs empirical mode decomposition to eliminate the interference of equipment vibration, obtains the main frequency of the while-drilling signal, and then extracts the reflection wave by picking up the first arrival of the longitudinal and transverse waves, and uses the velocity range determined by the direct wave as the velocity background value for depth migration, and according to the wave impedance difference between the rock layer where the current exploration borehole is located and the overlying layer, because the rock layer is composed of dense rock mass and loose rock mass (for example, the rock layer is sandstone, then the rock layer is sandstone). The layer is composed of dense sandstone and loose sandstone), so the wave impedance difference between the dense rock area and the overlying stratum is determined as the primary wave impedance difference value, and the wave impedance difference between the loose rock area and the overlying stratum is determined as the secondary wave impedance difference value, and the secondary wave impedance difference value is smaller than the primary wave impedance difference value; then, on the basis of determining the propagation direction of the reflected wave by the three-component detector polarization analysis, the primary wave impedance difference value is used as the center, and the half wavelength of the main frequency is used as the diameter to circle the fault structure morphology contour within a certain range ahead, thus completing the preliminary geological structure detection process ahead of the tunnel;
[0029] D. Arrange multiple measuring electrodes 8 in a row in the exploration borehole. Each measuring electrode 8 is connected to an electrical acquisition base station 6 outside the exploration borehole through an electrical data transmission line 7. The electrical acquisition base station 6 is connected to an electrical host 5. The spacing between adjacent measuring electrodes 8 in the exploration borehole is less than 2m. The measuring electrodes 8 are copper wire electrodes. According to the different lithology sections where each measuring electrode 8 is located, the acquisition parameters of the measuring electrodes 8 in different lithology sections are set separately through the electrical host 5, including power supply time and power supply voltage, so as to complete the layout of the electrical advance detection system.
[0030] E. The electrical method host 5 controls each measuring electrode 8 to collect electrical method data in the hole according to the collection parameters set in step D. Each measuring electrode 8 transmits the collected electrical method data to the electrical method collection base station 6 for storage. The electrical method host 5 extracts the electrical method data stored in the electrical method base station 6 and obtains the apparent resistivity profile within a certain range in front of the exploration borehole through inversion, such as Figure 3As shown, the water-bearing area is then delineated using the existing judgment criteria according to the apparent resistivity of each area in the apparent resistivity profile, thereby completing the process of advanced detection of the water-rich area;
[0031] F. Compare the fault structure morphology outline determined in step C with the water-bearing area determined in step E:
[0032] If the water-bearing area is completely within the contour of the fault structure, the overlapping area of the two is determined to be the water-bearing fault structure area;
[0033] If part of the water-bearing area is within the fault structural morphological contour, the seismic data is selected to re-delineate the structural morphological contour with the secondary wave impedance difference value as the center and the half wavelength of the main frequency as the diameter. Since the secondary wave impedance difference value is smaller than the primary wave impedance difference value, the structural morphological contour delineated with it as the standard is larger. The area where the re-delineated structural morphological contour overlaps with the water-bearing area is selected as the water-bearing fault structural area.
[0034] If the water-bearing area is not completely within the fault structural morphological contour, the fault structural morphological contour is determined to be a water-free fault structural area;
[0035] Through the above-mentioned comparison and analysis, a comprehensive detection can be carried out on the position and range of the fault structure in front of the tunnel, as well as whether there is a water-containing area within the fault structure. After completing the detection, the tunnel is excavated forward for a distance and the exploration drilling is constructed again. Then the above steps are repeated, and the results of this detection are superimposed with the previous detection results. Since this detection is closer to the same detection range as the previous one, its detection result is higher. Therefore, the areas with the same judgment are retained, and the different areas are updated based on the results of this detection, so that the detection accuracy is effectively guaranteed by continuously updating and correcting the detection results.
[0036] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.
Claims
1. A method for advanced fault structure detection combining seismic and electrical detection in boreholes and tunnels, characterized in that: The specific steps are: A. Arrange multiple seismic detectors in a row in the tunnel. The multiple seismic detectors are connected to the while-drilling seismic host and the seismic base station through seismic data transmission lines. The acquisition parameters of each seismic detector are set through the while-drilling seismic host, thereby completing the deployment of the while-drilling seismic advance detection system; B. Start the construction of exploratory drilling in front of the tunnel. During the drilling process, the seismic host controls each seismic detector to collect seismic data according to the set acquisition parameters. Each seismic detector receives the seismic wave data generated during drilling and transmits it to the seismic base station for storage until the construction of the exploratory drilling is completed. The lithology of each rock layer passed by the entire exploratory drilling can be determined based on the drill cuttings discharged during the exploratory drilling construction. The part of the exploratory drilling that passes through the same rock layer is set as a lithology segment, thereby dividing the exploratory drilling into multiple different lithology segments; C. The seismic host extracts the seismic data stored in the seismic base station, converts the seismic data into pseudo-active source data through the interference method, and then inputs the observation system coordinates and performs empirical mode decomposition to eliminate equipment vibration interference, obtains the main frequency of the while-drilling signal, and then extracts the reflected wave by picking up the first arrival of the longitudinal and transverse waves, uses the velocity range determined by the direct wave as the velocity background value for depth migration, and determines the primary wave impedance difference value and the secondary wave impedance difference value respectively according to the wave impedance difference between the rock layer where the current exploration borehole is located and its overlying layer. Then, based on the three-component detector polarization analysis to determine the propagation direction of the reflected wave, the primary wave impedance difference value is used as the center and the half wavelength of the main frequency is used as the diameter to circle the fault structure morphology contour within a certain range in front, completing the preliminary geological structure detection process in front of the tunnel; D. Multiple measuring electrodes are arranged in a row in the exploration borehole. Each measuring electrode is connected to the electrical acquisition base station outside the exploration borehole through an electrical data transmission line. The electrical acquisition base station is connected to the electrical host. According to the different lithology sections where each measuring electrode is located, the acquisition parameters of the measuring electrodes in different lithology sections are set through the electrical host, thereby completing the layout of the electrical advance detection system; E. The electrical method host controls each measuring electrode to collect electrical method data in the hole according to the collection parameters set in step D. Each measuring electrode transmits the collected electrical method data to the electrical method collection base station for storage. The electrical method host extracts the electrical method data stored in the electrical method base station, obtains the apparent resistivity profile within a certain range in front of the exploration borehole through inversion, and then delineates the water-bearing area according to the apparent resistivity of each area in the apparent resistivity profile, thereby completing the process of advanced detection of water-rich areas; F. Compare the fault structure morphology outline determined in step C with the water-bearing area determined in step E: If the water-bearing area is completely within the contour of the fault structure, the overlapping area of the two is determined to be the water-bearing fault structure area; If part of the water-bearing area is within the fault structural morphological contour, the seismic data is centered on the secondary wave impedance difference value and the half wavelength of the main frequency is used as the diameter to re-delineate the structural morphological contour, and the area where the re-delineated structural morphological contour overlaps with the water-bearing area is selected as the water-bearing fault structural area; If the water-bearing area is not completely within the fault structural morphological contour, the fault structural morphological contour is determined to be a water-free fault structural area; Through the above-mentioned comparison and analysis, a comprehensive detection can be carried out on the position and range of the fault structure in front of the tunnel, as well as whether there is a water-containing area within the range of the fault structure. After completing the detection, the tunnel is excavated forward for a certain distance and the exploration drilling is constructed again. Then the above steps are repeated, and the results of this detection are superimposed with the previous detection results. The areas with the same judgments are retained, and the different areas are updated based on the current detection results. This is repeated by continuously updating and correcting the detection results to effectively ensure the detection accuracy.
2. The method for advanced fault structure detection combining seismic and electrical detection in boreholes and tunnels according to claim 1 is characterized in that: The seismic geophone is a three-component velocity geophone, and the distance between adjacent seismic geophones in the tunnel is less than 5m.
3. The method for advanced fault structure detection combining seismic and electrical detection in boreholes and tunnels according to claim 1 is characterized in that: The distance between adjacent measuring electrodes in the exploration borehole is less than 2m; the measuring electrodes are copper wire electrodes.
4. The method for advanced fault structure detection combining seismic and electrical detection in boreholes and tunnels according to claim 1 is characterized in that: The acquisition parameters of the seismic detector in step A include sampling frequency, number of sampling points, number of advance sampling points, magnification, and triggering mode.
5. The method for advanced fault structure detection combining seismic and electrical detection in boreholes and tunnels according to claim 1 is characterized in that: The acquisition parameters of the measuring electrode in step D include power supply time and power supply voltage.