A gas pressure regulator debugging platform and calibration method thereof
By providing a gas pressure regulator debugging platform, it realizes pre-checking on the in-service pipeline, solving the problem of long-term gas shutdown during the replacement of the gas pressure regulator, improving work efficiency and reducing user inconvenience.
Patent Information
- Application Number
- CN202211206626.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-09-30
- Publication Date
- 2025-02-07
- Estimated Expiration
- 2042-09-30
AI Technical Summary
The existing gas pressure regulator needs to be replaced for a long time, which leads to dissatisfaction with users. If an abnormality is found during the debugging process of the update equipment, further debugging and replacement is required to extend the shutdown time.
It provides a gas pressure regulator debugging platform, including a first pipeline and a fixing frame. By setting up a control valve, a test position and a sealing valve, it realizes pre-checking in advance before installing equipment on the in-service pipeline to avoid long-term gas supply stop.
Through pre-inspection in advance, long-term air shutdowns are avoided, work efficiency is improved, and there is no need to extend the air shutdown time when installing equipment on the pipeline, reducing user inconvenience.
Smart Images

Figure CN115452273B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of gas equipment regulation and testing, and in particular to a gas pressure regulator debugging platform and a calibration method thereof. Background Art
[0002] The gas pressure regulating system is a device used to adjust the gas supply pressure in the gas transmission and distribution system, so that the gas pressure in the gas supply system is reduced and stabilized at a safe, economical and efficient level, and the gas pressure at the user end does not fluctuate violently with the gas consumption and upstream pressure changes. Another function of the pressure regulator is overpressure relief cut-off. When the pressure regulator fails and the outlet pressure exceeds the set value, it may cause harm to the normal operation of the user-side equipment and public safety. The equipment starts the safety relief valve to reduce the pressure; if the gas pressure still cannot be reduced to normal, or even continues to rise, the cut-off valve will work to cut off the gas supply.
[0003] The current process for replacing a pressure regulator is to shut down the gas supply, install the replacement device directly on the pipeline, and then perform leak detection and debugging. This operation process requires a long gas outage, which causes user dissatisfaction. In addition, if an abnormality is found in the updated equipment during the debugging process, further debugging and replacement are required, which will greatly extend the gas outage time, leading to user complaints. Summary of the invention
[0004] The purpose of the present invention is to solve at least one of the technical problems existing in the prior art and to provide a gas pressure regulator debugging platform.
[0005] The present invention also provides a calibration method using the gas pressure regulator debugging platform.
[0006] According to the first aspect of the present invention, there is provided a gas pressure regulator debugging platform, comprising: a first pipeline and a fixed frame. Along the air inlet direction of the first pipeline, a first control valve, an inlet first test position and a relief valve test position are sequentially arranged; the fixed frame comprises a second pipeline and an adjustment frame, the input end of the second pipeline is connected to the output end of the first pipeline, the adjustment frame is connected to the second pipeline, the second pipeline and the adjustment frame form a pressure regulator placement position, along the air inlet direction of the second pipeline, a second control valve, an inlet second test position and an inlet sealing valve are sequentially arranged, and along the air inlet direction of the adjustment frame, an outlet sealing valve and an outlet test position are sequentially arranged.
[0007] Beneficial effect: This gas pressure regulator debugging platform includes: a first pipeline and a fixed frame. Along the air inlet direction of the first pipeline, a first control valve, a first inlet test position and a relief valve test position are arranged in sequence; the fixed frame includes a second pipeline and an adjusting frame, the input end of the second pipeline is connected to the output end of the first pipeline, the adjusting frame is connected to the second pipeline, the second pipeline and the adjusting frame form a pressure regulator placement position, along the air inlet direction of the second pipeline, a second control valve, a second inlet test position and an inlet sealing valve are arranged in sequence, and an outlet sealing valve and an outlet test position are arranged in sequence along the air inlet direction of the adjusting frame. The gas pressure regulator debugging platform provided in the implementation of the present invention can perform a pre-inspection before installing the equipment on the in-service pipeline by operating the second control valve, the second inlet test position and the outlet test position, so as to avoid a long-term gas supply outage, and if the updated equipment is abnormally debugged in advance, since it has not been installed on the pipeline, there is no need to further extend the gas outage time.
[0008] According to a gas pressure regulator debugging platform of an embodiment of one aspect of the present invention, the relief valve test position includes a plurality of connecting valves connected in sequence, the air inlet port diameter of each connecting valve is larger than the air outlet port diameter, and among two adjacent connecting valves, the air inlet port diameter of the connecting valve close to the air inlet end is larger than the air inlet port diameter of the connecting valve far from the air inlet end, and the air outlet port diameter of the connecting valve close to the air inlet end is larger than the air outlet port diameter of the connecting valve far from the air inlet end.
[0009] According to the gas pressure regulator debugging platform of one embodiment of the present invention, the regulating frame includes a hollow end and a solid end, and an outlet sealing valve and an outlet test position are sequentially arranged along the air inlet direction of the hollow end, and the solid end is movably connected to the second pipeline.
[0010] According to the gas pressure regulator debugging platform of an embodiment of the present invention, the adjustment frame further includes an adjustment bolt, which is arranged between the solid end and the second pipe and is used to adjust the position of the adjustment frame relative to the second pipe.
[0011] According to the gas pressure regulator debugging platform of an embodiment of one aspect of the present invention, the pressure regulator placement position is provided with a pressure regulator inclination adjustment component, and the pressure regulator inclination adjustment component is used to support the bottom of the pressure regulator and adjust the inclination of the pressure regulator placement.
[0012] According to the gas pressure regulator debugging platform of an embodiment of the present invention, a connecting rod group is arranged between the first pipeline and the regulating frame.
[0013] According to the gas pressure regulator debugging platform of an embodiment of one aspect of the present invention, a disc-shaped supporting base is provided at the gas inlet end of the first pipeline.
[0014] According to another embodiment of the present invention, a calibration method using a gas pressure regulator debugging platform according to any one of the above embodiments includes the following steps:
[0015] Relief valve leak test:
[0016] Check whether the first control valve and the second control valve are airtight: adjust the specification of the relief valve test position according to the size of the relief valve, and install a well-sealed ball valve at the relief valve test position;
[0017] Install a pressure gauge and a balloon at the first test position of the inlet, open the first control valve, perform an air tightness test on the first control valve, and close the first control valve after confirming that there is no leakage;
[0018] Dismantle the ball valve installed on the relief valve test position, and install the relief valve to be tested;
[0019] Open the first control valve, observe the value of the pressure gauge set on the first test position of the inlet, and after the value of the pressure gauge matches the operating pressure value of the pipeline network, pressurize the pressure regulator with the balloon set on the first test position;
[0020] After the pressurization value reaches 1.5 times the operating pressure of the pipeline network, the relief valve is tested for air tightness to prevent the relief valve that does not meet the requirements from being put into use.
[0021] According to another embodiment of the present invention, a calibration method using a gas pressure regulator debugging platform according to any one of the above embodiments includes the following steps:
[0022] Placing the voltage regulator on the voltage regulator placement position, and adjusting the inclined position of the voltage regulator according to the height of the voltage regulator;
[0023] Fitting the inlet of the pressure regulator to the inlet sealing valve, and fitting the outlet of the pressure regulator to the outlet sealing valve by adjusting the adjusting frame;
[0024] The pressure gauge and the balloon are installed at the second inlet test position and the outlet test position, and then the first control valve and the second control valve are opened in sequence, and the air tightness test is performed on the outlet test position, the first inlet test position, the second inlet test position, the inlet sealing valve and the outlet sealing valve to confirm that there is no leakage point;
[0025] The gas enters the pressure regulator through the first pipeline and the second pipeline in turn. The test pressure value of the pressure regulator inlet can be detected through the second test position of the inlet. The hexagonal nut on the top of the pressure regulator spring is adjusted to change the tightness of the spring, and the adjustment pressure of the pressure regulator is set. The value of the pressure gauge at the outlet test position is observed to determine that the pressure regulation is completed.
[0026] After the test is completed, close the first control valve and the second control valve in turn, open the ball valves on the second inlet test position and the outlet test position, and remove the pressure regulator after no gas is discharged.
[0027] Beneficial effects: The calibration method provided in the embodiment of the present invention improves the practicability of the device by detecting the relief valve; ensures the good performance of the gas pressure regulator debugging platform by performing airtightness detection on the outlet test position, the first inlet test position, the second inlet test position, the inlet sealing valve and the outlet sealing valve; and avoids inconvenience to users' lives caused by long-term gas supply suspension by pre-inspection before installing the equipment on the active pipeline.
[0028] According to a calibration method of another embodiment of the present invention, the gas in the second pipeline is pressurized by a balloon arranged at the second test position of the inlet, thereby setting the cut-off pressure of the pressure regulator, and adjusting the pressure regulator so that its cut-off valve closes the valve port of the pressure regulator; when setting the release pressure of the pressure regulator, the gas in the second pipeline is pressurized by the balloon on the second test position of the inlet, and the pressure regulator is adjusted to release the over-pressure gas to the outside. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] The present invention is further described below in conjunction with the accompanying drawings and embodiments;
[0030] Figure 1 This is an overall schematic diagram of the gas pressure regulator debugging platform of the present invention;
[0031] Figure 2 This is a schematic diagram of the adjustment frame of the gas pressure regulator debugging platform of the present invention;
[0032] Figure 3 It is a schematic diagram of the inclination adjustment assembly of the gas pressure regulator debugging platform of the present invention;
[0033] Figure 4 This is a schematic diagram of the test position of the relief valve of the gas pressure regulator debugging platform of the present invention;
[0034] Figure 5 This is a schematic diagram of the outlet sealing valve of the gas pressure regulator debugging platform of the present invention. DETAILED DESCRIPTION
[0035] This section will describe in detail the specific embodiments of the present invention. The preferred embodiments of the present invention are shown in the accompanying drawings. The purpose of the accompanying drawings is to supplement the description of the text part of the specification with graphics, so that people can intuitively and vividly understand each technical feature and the overall technical solution of the present invention, but it cannot be understood as a limitation on the scope of protection of the present invention.
[0036] In the description of the present invention, it should be understood that descriptions involving orientations, such as up, down, front, back, left, right, top, bottom, inside, outside, etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0037] In the description of the present invention, "several" means one or more, "more" means more than two, "greater than", "less than", "exceed" etc. are understood as not including the number itself, and "above", "below", "within" etc. are understood as including the number itself. If there is a description of "first" or "second", it is only used for the purpose of distinguishing the technical features, and cannot be understood as indicating or implying the relative importance or implicitly indicating the number of the indicated technical features or implicitly indicating the order of the indicated technical features.
[0038] In the description of the present invention, unless otherwise clearly defined, terms such as setting, installing, connecting, etc. should be understood in a broad sense, and technicians in the relevant technical field can reasonably determine the specific meanings of the above terms in the present invention based on the specific content of the technical solution.
[0039] The gas pressure regulating system is a device used to adjust the gas supply pressure in the gas transmission and distribution system, so that the gas pressure in the gas supply system is reduced and stabilized at a safe, economical and efficient level, and the gas pressure at the user end does not fluctuate violently with the gas consumption and upstream pressure changes. Another function of the pressure regulator is overpressure relief cut-off. When the pressure regulator fails and the outlet pressure exceeds the set value, it may cause harm to the normal operation of the user-end equipment and public safety. The equipment starts the safety relief valve to reduce the pressure; if the gas pressure still cannot be reduced to normal, or even continues to rise, the cut-off valve will work to cut off the gas supply. For this reason, the normal operation of the pressure regulating system is an important part of ensuring the safety of gas supply. The stability of the outlet pressure of the pressure regulator, the air tightness when closed, the relief pressure value, the pressure value of the cut-off valve, etc. are indicators to judge whether the gas pressure regulator can function normally.
[0040] The current process for replacing a pressure regulator is to shut down the gas supply, install the replacement device directly on the pipeline, and then perform leak detection and debugging. This operation process requires a long period of gas outage, which is likely to cause user complaints; if the updated equipment is found to be abnormal during the debugging process, further debugging and replacement will be required, which will greatly extend the gas outage time.
[0041] In order to shorten the gas outage time for replacing a pressure regulator, a gas pressure regulator debugging platform and a calibration method thereof are provided to facilitate pre-inspection before installation on an in-service pipeline and improve work efficiency.
[0042] Reference Figures 1 to 5The gas pressure regulator debugging platform includes: a first pipeline 100 and a fixing frame 200.
[0043] Specifically, along the air intake direction of the first pipeline 100, a first control valve 110, an inlet first test position 120 and a relief valve test position 130 are sequentially arranged.
[0044] In a specific embodiment, the relief valve test position 130 includes a plurality of connecting valves 131 connected in sequence, the inlet port diameter of each connecting valve 131 is larger than the outlet port diameter, and among two adjacent connecting valves 131, the inlet port diameter of the connecting valve 131 close to the inlet end is larger than the inlet port diameter of the connecting valve 131 far from the inlet end, and the outlet port diameter of the connecting valve 131 close to the inlet end is larger than the outlet port diameter of the connecting valve 131 far from the inlet end.
[0045] It is easy to understand that the multiple connecting valves 131 arranged in sequence have different caliber specifications and are used to adapt to different relief valves, so as to perform air tightness detection on the relief valves.
[0046] In a specific embodiment, the fixed frame 200 includes a second pipeline 210 and an adjusting frame 220, the input end of the second pipeline 210 is connected to the output end of the first pipeline 100, the adjusting frame 220 is connected to the second pipeline 210, the second pipeline 210 and the adjusting frame 220 form a pressure regulator placement position, along the air inlet direction of the second pipeline 210, the second control valve 211, the inlet second test position 212 and the inlet sealing valve 213 are arranged in sequence, and the outlet sealing valve and the outlet test position are arranged in sequence along the air inlet direction of the adjusting frame 220.
[0047] Further, the adjustment frame 220 includes a hollow end 221 and a solid end 222, and an outlet sealing valve 223 and an outlet test position 224 are sequentially arranged along the air inlet direction of the hollow end 221, and the solid end 222 is movably connected to the second pipeline 210. It is easy to understand that both the inlet sealing valve 213 and the outlet sealing valve 223 are provided with sealing gaskets.
[0048] In a specific embodiment, the adjustment frame 220 also includes an adjustment bolt 225, one end of the adjustment bolt 225 is fixedly connected to the solid end 222, and the other end of the adjustment bolt 225 is threadedly connected to the second pipe 210. The position of the adjustment frame 220 relative to the second pipe 210 is adjusted by rotating the adjustment bolt 225 to adapt to pressure regulators of different specifications.
[0049] It is easy to understand that the first control valve 110 , the second control valve 211 , the inlet sealing valve 213 , and the outlet sealing valve 223 may be flange ball valves.
[0050] In a specific embodiment, a voltage regulator inclination adjustment component is provided at the voltage regulator placement position, and the voltage regulator inclination adjustment component is used to support the bottom of the voltage regulator and adjust the inclination of the voltage regulator placement.
[0051] Specifically, the voltage regulator inclination adjustment assembly includes a support plate 310, a mounting plate 320 and an adjustment rod 330. The support plate 310 and the mounting plate 320 are connected by a rotating shaft. The mounting plate 320 is fixedly set on the fixing frame 200. A plurality of clamping positions 321 are set on the mounting plate 320. One end of the adjustment rod 330 is fixedly set on the support plate 310, and the other end of the adjustment rod 330 is fixed at the clamping position 321. By setting the adjustment rod 330 at different clamping positions 321, the change in the inclination angle of the support plate 310 relative to the mounting plate 320 can be achieved, thereby realizing the adjustment of the inclination angle of the voltage regulator.
[0052] In a specific embodiment, a connecting rod group is provided between the first pipeline 100 and the adjustment frame 220 .
[0053] Specifically, the connecting rod group includes a long rod 410 and a short rod 420, one end of the long rod 410 is fixedly arranged on the first pipe 100, and the other end of the long rod 410 is fixedly arranged on the solid end 222. One end of the short rod 420 is fixedly arranged on the fixing frame 200, and the other end of the short rod 420 is fixedly arranged in the middle of the long rod 410.
[0054] It is easy to understand that by providing the long rod 410 and the short rod 420 , the stability of the connection between the first pipe 100 and the fixing frame 200 can be enhanced.
[0055] In a specific embodiment, a disc-shaped support base 500 is provided at the air inlet end of the first pipeline 100. The disc-shaped support base 500 improves the strength of the support and disperses the force of the gas pressure regulator debugging platform.
[0056] In a specific embodiment, a calibration method is provided, using the gas pressure regulator debugging platform of any of the above embodiments, comprising the following steps:
[0057] Relief valve leak test:
[0058] Check whether the first control valve 110 and the second control valve 211 are airtight: adjust the specification of the relief valve test position according to the size of the relief valve, and install a well-sealed ball valve at the relief valve test position;
[0059] Install the pressure gauge and the balloon at the first test position 120 of the inlet, open the first control valve 110, perform air tightness test on the relief valve test position 130, and close the first control valve 110 after confirming that the air tightness is good;
[0060] Disassemble the ball valve installed on the relief valve test position 130, and install the relief valve to be tested;
[0061] Open the first control valve 110, observe the value of the pressure gauge set on the first inlet test position 120, and when the value of the pressure gauge matches the operating pressure value of the pipeline network, pressurize the pressure regulator with the balloon set on the first inlet test position 120;
[0062] After the pressurization value reaches 1.5 times the operating pressure of the pipeline network, the relief valve is tested for air tightness to prevent the relief valve that does not meet the requirements from being put into use.
[0063] In a specific embodiment, a calibration method is provided, using the gas pressure regulator debugging platform of any of the above embodiments, comprising the following steps:
[0064] Place the voltage regulator on the voltage regulator placement position, and adjust the tilt position of the voltage regulator according to the height of the voltage regulator;
[0065] The inlet of the pressure regulator is fitted with the inlet sealing valve 213, and the outlet of the pressure regulator is fitted with the outlet sealing valve 223 by adjusting the adjustment frame 220;
[0066] Install the pressure gauge and the balloon at the inlet second test position 212 and the outlet test position 224, then open the first control valve 110 and the second control valve 211 in sequence, and perform air tightness test on the outlet test position 224, the inlet first test position 120, the inlet second test position 212, the inlet sealing valve 213 and the outlet sealing valve 223 to confirm that there is no leakage point;
[0067] The gas enters the pressure regulator through the first pipeline 100 and the second pipeline 210 in sequence. The test pressure value at the inlet of the pressure regulator can be detected through the second inlet test position 212. The hexagonal nut on the top of the spring of the pressure regulator is adjusted to change the tightness of the spring, set the adjustment pressure of the pressure regulator, and observe the value of the pressure gauge at the outlet test position 224 to determine that the pressure regulation is completed.
[0068] After the test is completed, close the first control valve 110 and the second control valve 211 in sequence, open the ball valves on the inlet second test position 212 and the outlet test position 224, and disassemble the pressure regulator after no gas is discharged.
[0069] In a specific embodiment, the gas in the second pipeline 210 is pressurized by a balloon provided at the second test position 212 of the inlet, thereby setting the cut-off pressure of the pressure regulator, and adjusting the pressure regulator so that its cut-off valve closes the valve port of the pressure regulator; when setting the release pressure of the pressure regulator, the gas in the second pipeline 210 is pressurized by the balloon on the second test position 212 of the inlet, and the pressure regulator is adjusted to release the over-pressure gas to the outside.
[0070] It is easy to understand that the air tightness test involved in the embodiments of the present application can be tested with soapy water. If the soapy water bubbles, it proves that there is a leak; if there is no bubbling, it can be used normally.
[0071] It is easy to understand that the first inlet test position 120 is set because the leak test of the relief valve requires a test pressure greater than the working pressure. Therefore, a balloon can be set at the first inlet test position 120 for pressurization; and a pressure gauge is set to display the pressure value.
[0072] It is easy to understand that the relief valve is installed in the valve well. When the operation needs to discharge the gas in a certain pipe section, the buried valve can be closed to cut off the upstream gas supply, and the relief valve can be opened to discharge it to the outside.
[0073] In a specific embodiment, the outlet sealing valve includes a main frame, a connecting pipe 610 and a direction and gap adjustment mechanism 620. The main frame includes a flange blind plate 630, a main clamping column 640, a force-bearing support frame 650, and a reinforcement frame 660. The flange blind plate 630 is used for sealing, the force-bearing support frame 650 is used for auxiliary load bearing, and the reinforcement frame 660 is used to strengthen the stability of the main frame. The connecting pipe 610 is used to connect the pipeline leading to the outlet test position.
[0074] It is easy to understand that the outlet sealing valve can use a flange. When the flange clamps an object, a gap will appear, and the contact surface is prone to uneven contact. The direction and gap adjustment mechanism 620 can use a tightening sleeve, combined with bolt tightening parts, to make the clamping contact uniform and allow the outlet sealing valve to fit.
[0075] The technical solution of this application has the following advantages:
[0076] 1. Provide a debugging platform for gas pressure regulators so that the equipment can be pre-inspected before installation on the in-service pipeline to improve work efficiency;
[0077] 2. The debugging platform of the gas pressure regulator provided in the embodiment of the present application is applicable to pressure regulating devices of different sizes;
[0078] 3. The debugging platform of the gas pressure regulator provided in the embodiment of the present application can be used for the detection of the venting ball valve, thereby improving the practicality;
[0079] 4. The debugging platform for the gas pressure regulator provided in the embodiment of the present application can also be used for daily pressure regulator maintenance training, which can intuitively display the entire operation process so that operators can understand the principles, processes and technical specifications of the operation.
[0080] The embodiments of the present invention are described in detail above with reference to the accompanying drawings, but the present invention is not limited to the above embodiments, and various changes can be made within the knowledge scope of ordinary technicians in the relevant technical field without departing from the purpose of the present invention.
Claims
1. A gas pressure regulator debugging platform, characterized in that: include: A first pipeline, along the air inlet direction of the first pipeline, is provided with a first control valve, an inlet first test position and a relief valve test position in sequence; The fixing frame includes a second pipeline and an adjusting frame, wherein the input end of the second pipeline is connected to the output end of the first pipeline, the adjusting frame is connected to the second pipeline, the second pipeline and the adjusting frame form a pressure regulator placement position, and along the air inlet direction of the second pipeline, a second control valve, an inlet second test position and an inlet sealing valve are sequentially arranged, and along the air inlet direction of the adjusting frame, an outlet sealing valve and an outlet test position are sequentially arranged; The relief valve test position includes a plurality of connecting valves connected in sequence, the diameter of the air inlet port of each connecting valve is larger than the diameter of the air outlet port, and among two adjacent connecting valves, the diameter of the air inlet port of the connecting valve close to the air inlet end is larger than the diameter of the air inlet port of the connecting valve far from the air inlet end, and the diameter of the air outlet port of the connecting valve close to the air inlet end is larger than the diameter of the air outlet port of the connecting valve far from the air inlet end; The adjustment frame includes a hollow end and a solid end, an outlet sealing valve and an outlet test position are sequentially arranged along the air inlet direction of the hollow end, and the solid end is movably connected to the second pipeline; The adjustment frame further includes an adjustment bolt, which is disposed between the solid end and the second pipe and is used to adjust the position of the adjustment frame relative to the second pipe; The voltage regulator placement position is provided with a voltage regulator inclination adjustment component, and the voltage regulator inclination adjustment component is used to support the bottom of the voltage regulator and adjust the inclination of the voltage regulator placement.
2. The gas pressure regulator debugging platform according to claim 1, characterized in that: A connecting rod group is arranged between the first pipeline and the adjusting frame.
3. The gas pressure regulator debugging platform according to claim 1, characterized in that: The air inlet end of the first pipeline is provided with a disc-shaped supporting base.
4. A calibration method, using the gas pressure regulator debugging platform according to any one of claims 1 to 3, characterized in that: The steps include: Relief valve leak test: Check whether the first control valve and the second control valve are airtight: adjust the specification of the relief valve test position according to the size of the relief valve, and install a well-sealed ball valve at the relief valve test position; Install a pressure gauge and a balloon at the first test position of the inlet, open the first control valve, perform an air tightness test on the first control valve, and close the first control valve after confirming that there is no leakage; Dismantle the ball valve installed on the relief valve test position, and install the relief valve to be tested; Open the first control valve, observe the value of the pressure gauge set on the first test position of the inlet, and after the value of the pressure gauge matches the operating pressure value of the pipeline network, pressurize the pressure regulator with the balloon set on the first test position; After the pressurization value reaches 1.5 times the operating pressure of the pipeline network, the air tightness of the relief valve is tested to prevent air leakage from the relief valve.
5. A calibration method, using the gas pressure regulator debugging platform according to any one of claims 1 to 3, characterized in that: The steps include: Placing the voltage regulator on the voltage regulator placement position, and adjusting the inclined position of the voltage regulator according to the height of the voltage regulator; Fitting the inlet of the pressure regulator to the inlet sealing valve, and fitting the outlet of the pressure regulator to the outlet sealing valve by adjusting the adjusting frame; The pressure gauge and the balloon are installed at the second inlet test position and the outlet test position, and then the first control valve and the second control valve are opened in sequence, and the air tightness test is performed on the outlet test position, the first inlet test position, the second inlet test position, the inlet sealing valve and the outlet sealing valve to confirm that there is no leakage point; The gas enters the pressure regulator through the first pipeline and the second pipeline in turn, and the test pressure value of the pressure regulator inlet can be detected through the second test position of the inlet, the hexagonal nut on the top of the pressure regulator spring is adjusted, the spring is changed, the adjustment pressure of the pressure regulator is set, and the value of the pressure gauge at the outlet test position is observed to determine that the pressure regulation is completed; After the test is completed, close the first control valve and the second control valve in turn, open the ball valves on the second inlet test position and the outlet test position, and remove the pressure regulator after no gas is discharged.
6. The calibration method according to claim 5, characterized in that: The gas in the second pipeline is pressurized by the balloon arranged at the second test position of the inlet, so as to set the cut-off pressure of the pressure regulator, and the pressure regulator is adjusted so that its cut-off valve closes the valve port of the pressure regulator; when setting the release pressure of the pressure regulator, the gas in the second pipeline is pressurized by the balloon on the second test position of the inlet, and the pressure regulator is adjusted to release the over-pressure gas to the outside.
Citation Information
Patent Citations
Gas pressure regulator debugging system
CN209622483U
Natural gas pressure regulating equipment and operating methods of it
KR1020100058939A