A construction positioning device and construction method for buried pipes under raft of ground source heat pump system
By designing the underground underground pipe construction positioning device under the raft slab of the ground source heat pump system, vertical pipes are fixed using components such as platforms, legs and insert rods, the problems of vertical pipe installation difficulty and safety hazards are solved, and construction efficiency and safety are improved.
Patent Information
- Application Number
- CN202211364864.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-11-02
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2042-11-02
AI Technical Summary
In the construction of ground source heat pumps, the installation of vertical pipes is difficult and poses safety risks, especially because the vertical pipes are long and require stable hand-held, resulting in low construction efficiency and safety risks.
A construction positioning device for underground pipes under raft slab of ground source heat pump system was designed, including platform, legs and insertion rods. Through the positioning sleeve, displacement rod and pipeline fixing components, the vertical pipeline is stable and fixed to ensure construction. Safety and efficiency.
It improves the installation efficiency of vertical pipelines, reduces construction difficulty and safety risks, and ensures the stability and interface quality of pipelines.
Smart Images

Figure CN115574148B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a vertical pipeline construction auxiliary device, and in particular to a construction positioning device and a construction method for an underground pipe under a raft of a ground source heat pump system. Background Art
[0002] When constructing a ground source heat pump, it is necessary to dig an underground trench and lay the pipeline. The pipeline is generally divided into horizontal pipes and vertical pipes. The horizontal pipe is used for laying the trench, while the vertical pipe is used for laying the connection at the end of the trench. When laying the vertical pipeline, there are the following disadvantages: ① Since the vertical pipeline is longer, it is in a vertical state with the underground trench during installation, and each pipeline requires a staff member to support it to ensure the stability of the vertical pipeline, which not only increases the difficulty of laying the pipeline, but also reduces the construction efficiency; ② Due to the influence of the construction environment, the construction platform is often a certain distance away from the laying position of the vertical pipeline. If the staff does not use their hands to hold the vertical pipeline for stability, it is also easy to step on empty space, which poses certain safety hazards. Summary of the invention
[0003] The technical problem to be solved by the present invention is to overcome the shortcomings of the prior art and provide a construction positioning device and a construction method for buried pipes under the raft of a ground source heat pump system, which can fix the vertical pipes according to the laying positions of the vertical pipes, thereby improving work efficiency, reducing construction difficulty and ensuring construction safety.
[0004] The technical solution adopted by the present invention to solve the technical problem is:
[0005] A device for positioning underground pipes under a raft in a ground source heat pump system comprises a platform, legs and an insertion rod, wherein the bottom of the platform is provided with legs, the right end of the platform is provided with a positioning sleeve, and the insertion rod passes through the positioning sleeve, first displacement rods are respectively sleeved at both ends of the insertion rod, and a second displacement rod is sleeved between the two first displacement rods, at least one pipeline fixing member is slidably connected to the second displacement rod, and a stabilizing component is provided at the bottom of the legs.
[0006] The insertion rod and the positioning sleeve are fixedly connected together by bolts, and the first displacement rod and the insertion rod are fixedly connected together by bolts.
[0007] Insertion holes are arranged at positions of both ends of the second displacement rod corresponding to the positions of the first displacement rod, and the second displacement rod is fixedly connected with the first displacement rod by bolts.
[0008] The pipeline fixing part is composed of a displacement block, a connecting column, a first arc plate and a second arc plate. The middle part of the displacement block is sleeved on the second displacement rod and fixed by bolts. The upper and lower ends of the displacement block are respectively provided with corresponding insertion holes, and connecting columns are inserted into the insertion holes. The connecting column is fixed to the displacement block by bolts. The right end of the connecting column is provided with a first arc plate, and a screw rod is provided on the extended plate of the first arc plate. The extended plate of the second arc plate is sleeved on the screw rod and fixed together by nuts.
[0009] The stabilizing component consists of a positioning ring, a U-shaped frame, an insert plate and a positioning pin. The positioning ring is sleeved on the support leg and fixedly connected to the support leg by bolts. The outer wall of the positioning ring is provided with at least one U-shaped frame, and an insert plate is inserted in the U-shaped frame. The bottom surface of the insert plate is inserted with a positioning pin.
[0010] There are four supporting legs, and reinforcing rods are arranged between the supporting legs on the left and right sides.
[0011] The construction method of the underground pipe positioning device under the raft of the ground source heat pump system comprises the following steps:
[0012] S1: Measure and lay out the lines, and dig the underground trench. First, lay the horizontal pipeline in the underground trench. After the horizontal pipeline is laid, set up a platform outside the end of the underground trench and prepare the vertical pipelines to be installed;
[0013] S2: According to the width of the underground pipe trench, a rod is inserted at the right end of the platform, so that both ends of the rod extend out of the underground pipe trench, and the rod is fixedly connected to the positioning sleeve by bolts;
[0014] S3: First displacement rods are respectively sleeved on both ends of the insertion rod, so that each first displacement rod is at the same distance from the outer end of the platform, and the first displacement rods are fixedly connected to the insertion rod by bolts;
[0015] S4: Worker A stands on the platform (1) and sets the required pipe fixing parts on the second displacement rod (6). According to the installation position of the vertical pipe, the second displacement rod (6) is moved until the position of the first arc plate (11) corresponds to the installation position of the vertical pipe. At this time, the second displacement rod (6) is fixedly connected to the first displacement rod (5) by bolts.
[0016] S5: Worker B stands in the underground pipe trench, installs a right-angle adapter at one end of the horizontal pipe, and connects the end of the horizontal pipe to the adapter by hot melting;
[0017] S6: Worker A cooperates with worker B to place the lower end of the vertical pipe at the upper port of the adapter joint, so that the outer wall of the vertical pipe is tightly attached to the inner wall of the first curved plate, and then the vertical pipe is fixedly connected to the pipe fixing piece through the second curved plate, and finally the right-angle joint is connected to the lower end of the vertical pipe by hot melting.
[0018] The length of the first displacement rod is greater than the distance between the platform and the vertical pipe.
[0019] The positive beneficial effects of the present invention are:
[0020] 1. The present invention can fix the legs to the ground by arranging a stabilizing component at the bottom of the legs, thereby ensuring the overall stability; by slidingly connecting the pipe fixing component on the second displacement rod, the vertical pipe to be installed can be clamped and fixed, which is beneficial for the staff to perform hot melt construction.
[0021] 2. The present invention inserts an insertion rod at the right end of the platform and sleeves a first displacement rod on both ends of the insertion rod. When in use, it can be freely adjusted according to the width of the trench, so that the pipeline fixing assembly can be moved within the width of the trench, which provides convenience for construction, is easy to use, and is simple to operate. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 It is a structural schematic diagram of the present invention;
[0023] Figure 2 It is a structural schematic diagram of the displacement block of the present invention;
[0024] Figure 3 It is a schematic diagram of the structure of the stabilizing assembly of the present invention;
[0025] Wherein: 1-platform, 2-leg, 3-positioning sleeve, 4-insertion rod, 5-first displacement rod, 6-second displacement rod, 7-displacement block, 8-connecting column, 9-first arc plate, 10-screw, 11-second arc plate, 12-nut, 13-positioning ring, 14-U-shaped frame, 15-insertion plate, 16-positioning drill. DETAILED DESCRIPTION
[0026] The present invention will be further explained and illustrated below in conjunction with the accompanying drawings:
[0027] Example 1, see Figure 1-Figure 3A construction positioning device for buried pipes under a raft of a ground source heat pump system comprises a platform 1, a leg 2 and a rod 4. The leg 2 is arranged at the bottom of the platform 1, a positioning sleeve 3 is arranged at the right end of the platform 1, and the rod 4 runs through the positioning sleeve 3. First displacement rods 5 are respectively sleeved at both ends of the rod 4, and a second displacement rod 6 is sleeved between the two first displacement rods 5. At least one pipeline fixing member is slidably connected to the second displacement rod 6, and a stabilizing component is arranged at the bottom of the leg 2.
[0028] The insertion rod 4 and the positioning sleeve 3 are fixedly connected together by bolts, and the first displacement rod 5 and the insertion rod 4 are fixedly connected together by bolts.
[0029] Insertion holes are provided at both ends of the second displacement rod 6 at positions corresponding to the first displacement rod 5 , and the second displacement rod 6 and the first displacement rod 5 are fixedly connected together by bolts.
[0030] The pipeline fixing part is composed of a displacement block 7, a connecting column 8, a first arc plate 9 and a second arc plate 11. The middle part of the displacement block 7 is sleeved on the second displacement rod 6 and fixed by bolts. The upper and lower ends of the displacement block 7 are respectively provided with corresponding insertion holes, and connecting columns are inserted into the insertion holes. The connecting column 8 is fixed to the displacement block 7 by bolts; the right end of the connecting column 8 is provided with a first arc plate 9, and a screw rod 10 is provided on the extended plate of the first arc plate 9, and the extended plate of the second arc plate 11 is sleeved on the screw rod 10, and they are fixed together by a nut 12.
[0031] The stabilizing assembly consists of a positioning ring 13, a U-shaped frame 14, an insert plate 15 and a positioning drill 16. The positioning ring 13 is sleeved on the support leg 2 and fixedly connected to the support leg 2 by bolts. At least one U-shaped frame 14 is arranged on the outer wall of the positioning ring 13, and an insert plate 15 is inserted in the U-shaped frame 14. The bottom surface of the insert plate 15 is inserted with a positioning drill 16.
[0032] There are four supporting legs 2, and reinforcing rods are arranged between the supporting legs 2 on the left and right sides.
[0033] In the above description, since the ground at the construction site is a soil layer, a positioning ring is set on the support leg, and the positioning ring and the support leg are fixed by bolts, and then a plug plate is inserted into the socket formed by the U-shaped frame and the positioning ring, and the bottom of the plug plate is fixed to the soil ground with a positioning drill.
[0034] In the above description, the plug plate is composed of two L-shaped plates. When the plug plate is inserted into the socket formed by the U-shaped frame and the positioning ring, the bottom of the plug plate is located above the ground. At this time, the positioning ring is in contact with the ground, and the positioning ring is fixed to the support leg by bolts.
[0035] In the above description, the positioning pin is distributed in the shape of a spike at the lower end, and its length is sufficient to fix the plug plate to the ground.
[0036] In the above description, the upper end and the lower end of the displacement block are respectively provided with through holes, and a connecting column is respectively provided in each through hole, and the connecting column is fixed by bolts.
[0037] In the above description, the two connecting columns are respectively fixedly connected to the outer wall of the first arc-shaped plate.
[0038] Embodiment 2: The construction method of the above-mentioned ground source heat pump system raft buried pipe construction positioning device comprises the following steps:
[0039] S1: Measure and lay out, and dig underground trenches. First, lay horizontal pipelines in the underground trenches. After the horizontal pipelines are laid, set up platform 1 outside the end of the underground trenches, and prepare the vertical pipelines to be installed;
[0040] S2: According to the width of the underground pipe trench, insert the rod 4 at the right end of the platform 1, so that both ends of the rod 4 extend out of the underground pipe trench, and fix the rod 4 and the positioning sleeve 3 together by bolts;
[0041] S3: First displacement rods 5 are respectively sleeved on both ends of the insertion rod 4, so that each first displacement rod 5 is at the same distance from the outer end of the platform 1, and the first displacement rod 5 is fixedly connected to the insertion rod 4 by bolts;
[0042] S4: Worker A stands on the platform 1 and sets the required pipe fixing parts on the second displacement rod 6. According to the installation position of the vertical pipe, the second displacement rod 6 is moved until the position of the first arc plate 11 corresponds to the installation position of the vertical pipe. At this time, the second displacement rod 6 is fixedly connected with the first displacement rod 5 by bolts.
[0043] S5: Worker B stands in the underground pipe trench, installs a right-angle adapter at one end of the horizontal pipe, and connects the end of the horizontal pipe to the adapter by hot melting;
[0044] S6: Worker A cooperates with worker B to place the lower end of the vertical pipe at the upper port of the adapter joint, so that the outer wall of the vertical pipe is tightly attached to the inner wall of the first curved plate 9, and then the vertical pipe is fixedly connected to the pipe fixing piece through the second curved plate 11, and finally the right-angle joint is connected to the lower end of the vertical pipe by hot melting.
[0045] The length of the first displacement rod 5 is greater than the distance between the platform and the vertical pipeline.
[0046] In the above description, the length of the insertion rod is greater than the width of the pipe trench, so that the displacement block can move within the range of the pipe trench.
[0047] In the above description, the first arc plate and the second arc plate can clamp and fix the vertical pipeline.
[0048] The traditional construction method is: a worker stands on the platform and fixes the vertical pipe. During this process, since the vertical pipe is long and heavy, it is easy for the vertical pipe to shake. Hot melt construction is not used, and the pipe interface after hot melt is brittle. At this time, the worker on the platform takes his hand away from the vertical pipe, and the pipe mouth is very likely to break. In this way, the stability of the pipeline and the quality of the interface can be guaranteed by using the pipeline fixing assembly.
[0049] The present invention can maintain the stability of the platform by arranging a stabilizing component at the bottom of the support leg, and can clamp and fix the vertical pipeline to be installed by slidingly connecting at least one pipe fixing member on the second displacement rod, which is beneficial for the staff to perform hot-melt construction and also ensures the construction quality. It is easy to use and simple to operate.
Claims
1. A construction positioning device for underground pipes under a raft of a ground source heat pump system, comprising a platform (1), legs (2) and a plug rod (4), Features: The platform (1) is provided with a support leg (2) at the bottom, a positioning sleeve (3) is provided at the right end of the platform (1), and a plug rod (4) is passed through the positioning sleeve (3), first displacement rods (5) are respectively sleeved on both ends of the plug rod (4), and a second displacement rod (6) is sleeved between the two first displacement rods (5), and at least one pipeline fixing member is slidably connected to the second displacement rod (6), and the pipeline fixing member is used to fix the vertical pipeline, and a stabilizing component is provided at the bottom of the support leg (2); the plug rod (4) and the positioning sleeve (3) are fixedly connected together by bolts, and the first displacement rod (5) and the plug rod (4) are fixedly connected together by bolts; insertion holes are provided at both ends of the second displacement rod (6) at positions corresponding to the first displacement rod (5), and the second displacement rod (6) and the first displacement rod (5) are fixedly connected together by bolts; the pipeline fixing member consists of a displacement block (7), a connecting column (8), a first arc plate (9) and a second arc plate (11), and the middle part of the displacement block (7) is sleeved on the second displacement rod (6) and is connected through The displacement block (7) is fixed by bolts, and the upper and lower ends of the displacement block (7) are respectively provided with corresponding insertion holes, and a connecting column (8) is inserted into the insertion hole, and the connecting column (8) is fixed to the displacement block (7) by bolts; the right end of the connecting column (8) is provided with a first arc plate (9), and a screw rod (10) is provided on the extension plate of the first arc plate (9), and the extension plate of the second arc plate (11) is sleeved on the screw rod (10) and fixedly connected together by a nut (12); the stabilizing component is composed of a positioning ring (1 3), a U-shaped frame (14), an insert plate (15) and a positioning pin (16), the positioning ring (13) is sleeved on the supporting leg (2), and the positioning ring (13) and the supporting leg (2) are fixedly connected together by bolts, at least one U-shaped frame (14) is arranged on the outer wall of the positioning ring (13), and an insert plate (15) is inserted in the U-shaped frame (14), and a positioning pin (16) is inserted on the bottom surface of the insert plate (15); the supporting leg (2) is four, and a reinforcing rod is arranged between the supporting legs (2) on the left and right sides.
2. A construction method for a construction positioning device for underground pipes under a raft of a ground source heat pump system according to claim 1, It is characterized in that The steps include: S1: Survey and lay out the lines, and dig the underground trench. First, lay the horizontal pipeline in the underground trench. After the horizontal pipeline is laid, set up a platform (1) outside the end of the underground trench, and prepare the vertical pipelines to be installed; S2: According to the width of the underground pipe trench, a rod (4) is inserted at the right end of the platform (1), so that both ends of the rod (4) extend out of the underground pipe trench, and the rod (4) is fixedly connected to the positioning sleeve (3) by bolts; S3: first displacement rods (5) are respectively sleeved on both ends of the insertion rod (4), so that each first displacement rod (5) is at the same distance from the outer end of the platform (1), and the first displacement rod (5) is fixedly connected to the insertion rod (4) by bolts; S4: Worker A stands on the platform (1) and sets the required pipe fixing parts on the second displacement rod (6). According to the installation position of the vertical pipe, the second displacement rod (6) is moved until the position of the first arc plate (11) corresponds to the installation position of the vertical pipe. At this time, the second displacement rod (6) is fixedly connected to the first displacement rod (5) by bolts. S5: Worker B stands in the underground pipe trench, installs a right-angle adapter at one end of the horizontal pipe, and connects the end of the horizontal pipe to the adapter by hot melting; S6: Worker A cooperates with worker B to place the lower end of the vertical pipe at the upper end of the adapter joint so that the outer wall of the vertical pipe and the inner wall of the first curved plate (9) are tightly attached to each other. The vertical pipe and the pipe fixing member are then fixedly connected together by the second curved plate (11). Finally, the right-angle joint and the lower end of the vertical pipe are connected together by hot melting.
3. The construction method of the underground pipe positioning device under the raft of a ground source heat pump system according to claim 2, Features: The length of the first displacement rod (5) is greater than the distance between the platform and the vertical pipeline.