Construction method for wall body of green energy-saving prefabricated building
By using automated construction equipment during the installation of prefabricated building walls, including feeding, separation and positioning, lifting, clamping, alignment and height adjustment mechanisms, the problem of low automation in the existing technology is solved and efficient automatic installation of the wall is achieved.
Patent Information
- Application Number
- CN202211722615.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-12-30
- Publication Date
- 2025-06-20
- Estimated Expiration
- 2042-12-30
AI Technical Summary
The installation process of existing prefabricated building walls is low in degree and requires manual removal and installation of the walls one by one, resulting in cumbersome and inefficient.
A construction equipment for installation and construction of building walls is adopted, including feeding mechanisms, separation and positioning mechanisms, lifting mechanisms, clamping mechanisms, alignment mechanisms and height adjustment mechanisms. Through these equipment, the prefabricated building walls are automatically separated, lifted, clamped, aligned from the feeding mechanisms and finally manually installed.
The automatic installation of prefabricated building walls has been realized, construction efficiency has been improved, and the cumbersomeness and error rate of manual operation have been reduced.
Smart Images

Figure CN115898026B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of building wall installation, and particularly relates to a construction method for a green energy-saving prefabricated building wall. Background Art
[0002] A prefabricated building refers to a building in which a large amount of on-site work in the traditional construction method is transferred to a factory. Building components and fittings (such as floor slabs, wall panels, stairs, balconies, etc.) are processed and manufactured in the factory and transported to the building construction site, and then assembled and installed on-site through reliable connection methods. Building houses can be manufactured in batches and sets like machine production. As long as the prefabricated house components are transported to the construction site and assembled, the building is completed.
[0003] A Chinese patent with the publication number CN112459503B and the name of a construction method for installing a thermal insulation and energy-saving prefabricated building wall aims to solve the problem that "the installation of the current prefabricated building wall requires a hoisting machine to hoist each prefabricated building wall to the splicing and installation position respectively, and then the construction workers can hold the wall by hand to control the falling direction of the wall, and then clamp and fix it before carrying out the assembly and installation, and this process is cumbersome". This application places multiple walls through a feeding mechanism, then transports the walls to the main frame mechanism, and lifts the walls to the clamping mechanism through the main frame mechanism. Then, the clamping mechanism clamps the wall and transports it to the installation position. When the wall enters the main frame mechanism from the feeding mechanism, it is necessary to manually take out the single wall placed on the feeding mechanism first, and then place it on the lifting plate, and its degree of automation is relatively low. Therefore, this application proposes an installation construction device that can automatically transfer multiple stacked walls one by one to solve the above problems. Summary of the Invention
[0004] Based on the technical problem of the relatively low degree of automation in the prior art, the present invention proposes a construction method for a green energy-saving prefabricated building wall.
[0005] A construction method for a green energy-saving prefabricated building wall proposed by the present invention uses a building wall installation construction device. The construction device includes a feeding mechanism, a separation and positioning mechanism, a lifting mechanism, a clamping mechanism, an alignment mechanism, and a height adjustment mechanism. The specific method for installing the building wall using the above construction device is as follows:
[0006] S1. Positioning and placing - Place the prefabricated building wall on the feeding mechanism and arrange it neatly;
[0007] S2. Separating and positioning - Drive the feeding mechanism to move towards the position of the separation and positioning mechanism, and the separation and positioning mechanism automatically clamps the prefabricated building wall at the frontmost position on the feeding mechanism in S1;
[0008] S3. Active clamping: Drive the lifting mechanism to drive the separation and positioning mechanism to move upward, lift the single prefabricated building wall separated in S2 to the installation height, and at the same time, the clamping mechanism clamps the single prefabricated building wall in S2.
[0009] S4. Fixed-point unclamping: Drive the alignment mechanism to drive the single prefabricated building wall clamped in S3 to move close to the installation point. After reaching the installation point, the clamping mechanism releases.
[0010] S5. Wall installation: Manually install the single prefabricated building wall in S4.
[0011] Preferably, the feeding mechanism includes a shed, a T-shaped slide rail fixed to the inner wall of the bottom of the shed, and a placement plate slidably connected to the T-shaped slide rail. The upper part of the placement plate is of a U-shaped structure and the lower part is of a T-shaped structure. A plurality of uniformly distributed placement openings for placing prefabricated building walls are formed at the top of the placement plate. A strip plate is fixed to the side of the T-shaped structure of the placement plate, and a plurality of uniformly distributed convex columns are fixed to the outer side of the strip plate. A first motor is fixed to the outer side of the T-shaped slide rail, and the output shaft of the first motor is connected to a progressive push wheel that engages with the convex columns.
[0012] Preferably, the separation and positioning mechanism includes a support plate arranged between the prefabricated building wall and the placement plate. A pair of oppositely distributed brackets are fixedly connected to the front end of the support plate. A cushion block that abuts against the inner wall of the bottom of the placement plate is arranged at the bottom of the support plate. Two symmetrical openings are formed at the top of the support plate. Sliding grooves are formed on the inner walls on both sides of the openings. Sliders are slidably connected in the sliding grooves. The bottom end of the slider is fixed with a first spring whose other free end is fixed to the bottom of the sliding groove. A clamping block that is detachably connected to the slider is arranged between the two sliders. A clamping opening for clamping the prefabricated building wall is formed at the top of the clamping block, and an introduction inclined surface exposed above the opening is arranged on the rear end surface of the clamping block.
[0013] Preferably, through holes communicating with the sliding grooves are formed on both sides of the support plate. A round hole is formed on the clamping block. A screw rod passing through the through hole is commonly inserted into the round hole and the slider close to the through hole. A threaded groove threadedly connected to the screw rod is formed on the inner side surface of the other slider.
[0014] Preferably, the lifting mechanism includes a group of columns fixed to the top of the shed. The same frame is fixed to the tops of the two columns. A main shaft is rotatably connected in the frame. A group of first gears are sleeved on the main shaft. A second motor whose output shaft is connected to the end of the main shaft is fixed to one side of the frame. A first rack that is slidably connected to the frame and engages with the first gear is arranged on the inner wall of the front end of the frame, and the end of the first rack is fixed to the bracket.
[0015] Preferably, the clamping mechanism includes an orientation control plate disposed in front of the shed frame and above the pallet. At the front end of the orientation control plate, there are a pair of L-shaped clamping plates distributed oppositely. At the middle position of the orientation control plate, there is a secondary shaft rotatably connected thereto. At the front end of the secondary shaft, a first connecting rod is fixedly sleeved. Both free ends of the first connecting rod are rotatably connected to a second connecting rod whose end is rotatably connected to the clamping plate. At the front end of the orientation control plate, there is an installation opening located between the two clamping plates. A support bar with an arc-shaped front end is inserted into the installation opening. Guide grooves are provided on both sides of the support bar. The guide grooves are slidably connected to guide blocks fixed to the side wall of the installation opening. The front end of the guide block is fixed with a second spring whose other free end is fixed to the inner wall of the front end of the guide groove.
[0016] Preferably, a T-shaped sliding seat is provided at the rear end of the clamping plate, and a pair of docking grooves that form a sliding fit with the sliding seat are provided at the front end of the orientation control plate.
[0017] Preferably, a second gear is fixedly sleeved on the main shaft, a second rack that is slidably connected thereto is provided on the inner wall of the rear end of the frame, and a toothed bar that meshes with the second rack is fixedly sleeved on the secondary shaft.
[0018] Preferably, the alignment mechanism includes a pair of fixing plates fixed to the top of the shed frame. Insertion posts fixed to the orientation control plate are inserted into the fixing plates. At the rear ends of the two insertion posts, there is a same bridge plate fixed. A first push rod whose output shaft is fixed to the bridge plate is fixed to the top of the shed frame.
[0019] Preferably, the height adjustment mechanism is located on the bottom plate below the shed frame. Four second push rods whose output shafts are fixed to the shed frame are fixed at the corners of the top of the bottom plate.
[0020] Compared with the prior art, the present invention provides a construction method for a green energy-saving prefabricated building wall, having the following beneficial effects:
[0021] 1. For a construction method of a green energy-saving prefabricated building wall, place the prefabricated building walls neatly in the placement opening, and then start the first motor. The output shaft of the first motor drives the progressive push wheel to rotate. The progressive push wheel engages with the convex column, driving the pallet to move forward progressively. When the frontmost prefabricated building wall moves forward and contacts the guiding inclined surface, the clamping block is forced to move downward until the prefabricated building wall enters the clamping opening. The first spring pushes the slider and the whole clamping block to move upward and reset, that is, the prefabricated building wall is clamped through the clamping opening, and the single wall can be automatically separated from the feeding mechanism without manual transfer of the single wall.
[0022] 2. A construction method for a green energy-saving prefabricated building wall. Start the second motor. The output shaft of the second motor drives the main shaft and a set of first gears to rotate. The first gears engage to drive the first rack to move upward. Subsequently, the first rack synchronously drives the overall upward movement of the bracket and the support plate, lifting the clamped prefabricated building wall. The top of the prefabricated building wall contacts the arc structure of the support bar and squeezes the support bar into the installation opening. When the main shaft rotates, it synchronously drives the second gear to rotate. The second gear engages to drive the second rack to move downward. The second rack engages to drive the toothed bar and the auxiliary shaft to rotate counterclockwise. When the auxiliary shaft rotates, it synchronously drives the first connecting rod to rotate. Subsequently, the two second connecting rods respectively pull the two clamping plates inward until the clamping plates clamp the prefabricated building wall from both sides. At this time, the prefabricated building wall just moves above the support bar. The second spring pushes the support bar outwards to support the prefabricated building wall from the bottom. One side of the wall is attached to the direction control plate, and active clamping of the wall can be achieved during the lifting process.
[0023] 3. A construction method for a green energy-saving prefabricated building wall. Before starting the alignment mechanism, first start the second motor to rotate in the reverse direction, so that the clamping mechanism releases the clamping of the wall and drives the separation and positioning mechanism to move downward for reset. At this time, the wall is supported by the support bar on the direction control plate. Then start the first push rod. The output shaft of the first push rod pushes the bridge plate, the insertion post, the direction control plate and the wall towards the installation point, and then manual assembly can be carried out, thus realizing the fixed-point transportation of the wall. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 is a schematic flow chart of a construction method for a green energy-saving prefabricated building wall proposed by the present invention;
[0025] Figure 2 is a schematic structural diagram of a construction method for a green energy-saving prefabricated building wall proposed by the present invention from the first angle;
[0026] Figure 3 is a schematic structural diagram of a construction method for a green energy-saving prefabricated building wall proposed by the present invention from the second angle;
[0027] Figure 4 is a schematic structural diagram of the wall separation and positioning state of a construction method for a green energy-saving prefabricated building wall proposed by the present invention from the first angle;
[0028] Figure 5 is a schematic structural diagram of the wall separation and positioning state of a construction method for a green energy-saving prefabricated building wall proposed by the present invention from the second angle;
[0029] Figure 6 is a schematic structural diagram of the split structure of the clamping block and the support plate of a construction method for a green energy-saving prefabricated building wall proposed by the present invention;
[0030] Figure 7 Schematic diagram of the enlarged structure at A of the construction method of a green energy-saving prefabricated building wall proposed by the present invention;
[0031] Figure 8 Schematic diagram of the enlarged structure at B of the construction method of a green energy-saving prefabricated building wall proposed by the present invention;
[0032] Figure 9 Schematic diagram of the first-angle structure at the top of the shed of the construction method of a green energy-saving prefabricated building wall proposed by the present invention;
[0033] Figure 10 Schematic diagram of the second-angle structure at the top of the shed of the construction method of a green energy-saving prefabricated building wall proposed by the present invention;
[0034] Figure 11 Schematic diagram of the enlarged structure at C of the construction method of a green energy-saving prefabricated building wall proposed by the present invention;
[0035] Figure 12 Schematic diagram of the splint structure of the construction method of a green energy-saving prefabricated building wall proposed by the present invention;
[0036] Figure 13 Schematic diagram of the enlarged structure at D of the construction method of a green energy-saving prefabricated building wall proposed by the present invention;
[0037] Figure 14 Schematic diagram of the installation structure of the support bar of the construction method of a green energy-saving prefabricated building wall proposed by the present invention;
[0038] Figure 15 Schematic diagram of the enlarged structure at E of the construction method of a green energy-saving prefabricated building wall proposed by the present invention.
[0039] In the figure: 1, scaffolding; 2, T-shaped slide rail; 3, placement board; 4, placement opening; 5, support plate; 6, support; 7, opening; 8, chute; 9, first spring; 10, slider; 11, clamping block; 12, guiding inclined surface; 13, clamping opening; 14, through opening; 15, round hole; 16, threaded groove; 17, screw rod; 18, cushion block; 19, strip board; 20, convex column; 21, first motor; 22, progressive pushing wheel; 23, support column; 24, frame; 25, main shaft; 26, first gear; 27, second motor; 28, first rack; 29, fixing plate; 30, inserting column; 31, direction control board; 32, clamping plate; 33, auxiliary shaft; 34, connecting rod one; 35, connecting rod two; 36, toothed bar; 37, second gear; 38, second rack; 39, first push rod; 40, bridge board; 41, second push rod; 42, bottom plate; 43, supporting strip; 44, guiding groove; 45, guiding block; 46, second spring. Embodiment
[0040] Next, the technical solutions in the embodiments of the present invention will be clearly and completely described in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments.
[0041] In the description of the present invention, it should be understood that the orientation or positional relationship indicated by the terms "upper", "lower", "front", "rear", "left", "right", "top", "bottom", "inner", "outer", etc. is based on the orientation or positional relationship shown in the accompanying drawings, and is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be construed as a limitation to the present invention. Embodiment
[0042] Refer to Figure 1 , a construction method for a green energy-saving prefabricated building wall, which uses a building wall installation construction device. The construction device includes a feeding mechanism, a separating and positioning mechanism, a lifting mechanism, a clamping mechanism, a positioning mechanism, and a height adjusting mechanism. The specific method for installing the building wall using the above construction device is as follows:
[0043] S1. Positioning and placing - Place the prefabricated building wall on the feeding mechanism and arrange it neatly.
[0044] S2. Separating and positioning - Drive the feeding mechanism to move towards the position of the separating and positioning mechanism, and the separating and positioning mechanism automatically clamps the frontmost prefabricated building wall on the feeding mechanism in S1.
[0045] S3. Active clamping: Drive the lifting mechanism to drive the separation and positioning mechanism to move upward, lift the single prefabricated building wall separated in S2 to the installation height, and at the same time, the clamping mechanism clamps the single prefabricated building wall in S2.
[0046] S4. Fixed-point unclamping: Drive the alignment mechanism to drive the single prefabricated building wall clamped in S3 to move close to the installation point. After reaching the installation point, the clamping mechanism releases.
[0047] S5. Wall installation: Manually install the single prefabricated building wall in S4. Embodiment
[0048] Refer to Figures 2 - 15 , a construction method for a green energy-saving prefabricated building wall, which uses a building wall installation construction device. The construction device includes a feeding mechanism, a separation and positioning mechanism, a lifting mechanism, a clamping mechanism, an alignment mechanism, and a height adjustment mechanism. The feeding mechanism includes a shed 1, a T-shaped slide rail 2 fixed to the inner wall of the bottom of the shed 1, and a placement plate 3 slidably connected to the T-shaped slide rail 2. The upper part of the placement plate 3 is of a U-shaped structure, and the lower part is of a T-shaped structure. A plurality of uniformly distributed placement openings 4 for placing prefabricated building walls are opened at the top of the placement plate 3. A strip plate 19 is fixed to the side of the T-shaped structure of the placement plate 3, and a plurality of uniformly distributed convex columns 20 are fixed to the outside of the strip plate 19. A first motor 21 is fixed to the outside of the T-shaped slide rail 2, and the output shaft of the first motor 21 is connected to a progressive push wheel 22 that engages with the convex columns 20. Place the prefabricated building walls neatly in the placement openings 4, and then start the first motor 21. The output shaft of the first motor 21 drives the progressive push wheel 22 to rotate. The progressive push wheel 22 engages with the convex columns 20 to drive the pallet 5 to move forward progressively.
[0049] Further, the separation and positioning mechanism includes a pallet 5 disposed between the prefabricated building wall and the placement plate 3. A pair of oppositely distributed brackets 6 are fixedly connected to the front end of the pallet 5. A cushion block 18 that abuts against the inner wall of the bottom of the placement plate 3 is disposed at the bottom of the pallet 5. Two symmetrical openings 7 are opened at the top of the pallet 5. Sliding grooves 8 are opened on both inner walls of the openings 7. A slider 10 is slidably connected in the sliding grooves 8. A first spring 9 is fixed to the bottom end of the slider 10, and the other free end of the first spring 9 is fixed to the bottom of the sliding grooves 8. A clamping block 11 detachably connected to the slider 10 is disposed between the two sliders 10. A clamping opening 13 for clamping the prefabricated building wall is opened at the top of the clamping block 11. An introduction inclined surface 12 exposed above the opening 7 is provided on the rear end surface of the clamping block 11. When the frontmost prefabricated building wall moves forward, it contacts the introduction inclined surface 12, and the clamping block 11 moves downward under force until the prefabricated building wall enters the clamping opening 13. The first spring 9 pushes the slider 10 and the whole of the clamping block 11 to move upward and reset, that is, the prefabricated building wall is clamped through the clamping opening 13.
[0050] Furthermore, through holes 14 communicating with the sliding grooves 8 are formed on both sides of the pallet 5. A round hole 15 is formed on the clamping block 11. A screw rod 17 passing through the through hole 14 is inserted into both the round hole 15 and the slider 10 near the through hole 14. A threaded groove 16 threadedly connected to the screw rod 17 is formed on the inner side surface of the other slider 10.
[0051] Furthermore, the lifting mechanism includes a group of support columns 23 fixed to the top of the shed frame 1. The same frame 24 is fixed to the tops of the two support columns 23. A main shaft 25 is rotatably connected inside the frame 24. A group of first gears 26 are sleeved on the main shaft 25. A second motor 27 with its output shaft connected to the end of the main shaft 25 is fixed to one side of the frame 24. A first rack 28 slidably connected to the frame 24 and meshing with the first gears 26 is arranged on the front inner wall of the frame 24. The end of the first rack 28 is fixed to the support 6. By starting the second motor 27, the output shaft of the second motor 27 drives the main shaft 25 and the group of first gears 26 to rotate. The first gears 26 drive the first rack 28 to move upward by meshing, and then the first rack 28 synchronously drives the whole support 6 and the pallet 5 to move upward, so as to lift the clamped prefabricated building wall body.
[0052] Furthermore, the clamping mechanism includes an orientation control plate 31 arranged in front of the shed frame 1 and above the pallet 5. A pair of L-shaped clamping plates 32 distributed oppositely are arranged at the front end of the orientation control plate 31. A secondary shaft 33 rotatably connected to the orientation control plate 31 is arranged at the middle position of the orientation control plate 31. A connecting rod 34 is fixedly sleeved on the front end of the secondary shaft 33. Connecting rods 35 with their ends rotatably connected to the clamping plates 32 are rotatably connected to both free ends of the connecting rod 34. An installation opening located between the two clamping plates 32 is formed at the front end of the orientation control plate 31. A support bar 43 with an arc-shaped front end is inserted into the installation opening. Guide grooves 44 are formed on both sides of the support bar 43. Guide blocks 45 fixed to the side wall of the installation opening are slidably connected to the guide grooves 44. A second spring 46 with its other free end fixed to the front inner wall of the front end of the guide groove 44 is fixed to the front end of the guide block 45. When the prefabricated building wall body is lifted upward, the top of the prefabricated building wall body contacts the arc-shaped structure of the support bar 43 and presses the support bar 43 into the installation opening. When the secondary shaft 33 rotates, it synchronously drives the connecting rod 34 to rotate, and then the two connecting rods 35 respectively pull the two clamping plates 32 inward until the clamping plates 32 clamp the prefabricated building wall body from both sides. At this time, the prefabricated building wall body just moves above the support bar 43. The second spring 46 pushes the support bar 43 to move outwards to support the prefabricated building wall body from the bottom, and one side of the wall body is attached to the orientation control plate 31.
[0053] Furthermore, a T-shaped sliding seat is arranged at the rear end of the clamping plate 32. A pair of docking grooves forming a sliding fit with the sliding seat are formed at the front end of the orientation control plate 31, which can facilitate the assembly of the clamping plate 32 to the orientation control plate 31, so that the two form a sliding fit.
[0054] Further, a second gear 37 is fixedly sleeved on the main shaft 25, a second rack 38 which is slidably connected thereto is arranged on the inner wall of the rear end of the frame 24, a toothed bar 36 which meshes with the second rack 38 is fixedly sleeved on the auxiliary shaft 33. When the wall body of the prefabricated building is lifted, the main shaft 25 synchronously drives the second gear 37 to rotate, the second gear 37 meshes to drive the second rack 38 to move downward, and the second rack 38 meshes to drive the toothed bar 36 and the auxiliary shaft 33 to rotate counterclockwise.
[0055] Further, the alignment mechanism includes a pair of fixing plates 29 fixed to the top of the shed frame 1. Insertion columns 30 fixed to the control plate 31 are inserted into the fixing plates 29. The same bridge plate 40 is fixed to the rear ends of the two insertion columns 30. A first push rod 39 whose output shaft is fixed to the bridge plate 40 is fixed to the top of the shed frame 1. Before starting the alignment mechanism, first start the second motor 27 to rotate in the reverse direction, so that the clamping mechanism releases the clamping of the wall body and drives the separation and positioning mechanism to move downward to reset. At this time, the wall body is supported by the support bar 43 on the control plate 31. Then start the first push rod 39, and the output shaft of the first push rod 39 pushes the bridge plate 40, the insertion columns 30, the control plate 31 and the wall body to move towards the installation point, and then manual assembly can be carried out.
[0056] Further, the height adjustment mechanism is located on the bottom plate 42 below the shed frame 1. Four second push rods 41 whose output shafts are fixed to the shed frame 1 are fixed to the top of the bottom plate 42 at the four corners. By starting the second push rods 41, the output shafts of the second push rods 41 drive the whole shed frame 1 to move upward, so that the device can be adaptively adjusted according to the installation height of the wall body.
[0057] The above is only a preferred specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any person skilled in the art within the technical scope disclosed by the present invention, according to the technical solution and inventive concept of the present invention, makes equivalent substitutions or changes, and all should be covered within the protection scope of the present invention.
Claims
1. A construction method for a green energy-saving prefabricated building wall, characterized in that, It uses a construction wall installation construction device. The construction device includes a feeding mechanism, a separating and positioning mechanism, a lifting mechanism, a clamping mechanism, a positioning mechanism, and a height adjustment mechanism. The specific method for installing a construction wall using the above construction device is as follows: S1. Positioning and placing - Place the prefabricated building wall on the feeding mechanism and arrange it neatly. S2. Separating and positioning - Drive the feeding mechanism to move towards the position of the separating and positioning mechanism. The separating and positioning mechanism automatically clamps the frontmost prefabricated building wall on the feeding mechanism in S1. S3. Actively clamping - Drive the lifting mechanism to drive the separating and positioning mechanism to move upward, lift the single prefabricated building wall separated in S2 to the installation height, and at the same time, the clamping mechanism clamps the single prefabricated building wall in S2. S4. Fixed-point unclamping - Drive the positioning mechanism to drive the single prefabricated building wall clamped in S3 to move close to the installation point. After reaching the installation point, the clamping mechanism releases. S5. Wall installation - Manually install the single prefabricated building wall in S4. The feeding mechanism includes a shed frame (1), a T-shaped slide rail (2) fixed to the inner wall of the bottom of the shed frame (1), and a placement plate (3) slidably connected to the T-shaped slide rail (2). The upper part of the placement plate (3) is a U-shaped structure, and the lower part is a T-shaped structure. A plurality of uniformly distributed placement openings (4) for placing prefabricated building walls are opened at the top of the placement plate (3). A strip plate (19) is fixed to the side of the T-shaped structure of the placement plate (3), and a plurality of uniformly distributed convex columns (20) are fixed to the outside of the strip plate (19). A first motor (21) is fixed to the outside of the T-shaped slide rail (2), and the output shaft of the first motor (21) is connected to a progressive push wheel (22) that engages with the convex columns (20). The separating and positioning mechanism includes a support plate (5) disposed between the prefabricated building wall and the placement plate (3). A pair of oppositely distributed brackets (6) are fixedly connected to the front end of the support plate (5). A cushion block (18) that abuts against the inner wall of the bottom of the placement plate (3) is disposed at the bottom of the support plate (5). Two symmetrical openings (7) are opened at the top of the support plate (5). Sliding grooves (8) are opened on both inner walls of the openings (7). A slider (10) is slidably connected in the sliding grooves (8). A first spring (9) is fixed to the bottom end of the slider (10), and the other free end of the first spring (9) is fixed to the bottom of the sliding grooves (8). A clamping block (11) detachably connected to the slider (10) is disposed between the two sliders (10). A clamping opening (13) for clamping the prefabricated building wall is opened at the top of the clamping block (11). An introduction inclined surface (12) exposed above the opening (7) is provided on the rear end surface of the clamping block (11). The lifting mechanism includes a set of struts (23) fixed to the top of the shed frame (1). A same frame (24) is fixed to the tops of the two struts (23). A main shaft (25) is rotatably connected inside the frame (24). A set of first gears (26) is sleeved on the main shaft (25). A second motor (27) whose output shaft is connected to the end of the main shaft (25) is fixed to one side of the frame (24). A first rack (28) which is slidably connected to the frame (24) and meshes with the first gear (26) is arranged on the front inner wall of the frame (24). The end of the first rack (28) is fixed to the bracket (6). The clamping mechanism includes an orientation control plate (31) arranged in front of the shed frame (1) and above the support plate (5). A pair of L-shaped clamping plates (32) distributed oppositely are arranged at the front end of the orientation control plate (31). A secondary shaft (33) rotatably connected thereto is arranged at the middle position of the orientation control plate (31). A connecting rod one (34) is fixedly sleeved on the front end of the secondary shaft (33). Connecting rod two (35) whose ends are rotatably connected to the clamping plate (32) is rotatably connected to both free ends of the connecting rod one (34). An installation opening located between the two clamping plates (32) is formed at the front end of the orientation control plate (31). A support bar (43) with an arc-shaped front end is inserted into the installation opening. Guide grooves (44) are formed on both sides of the support bar (43). A guide block (45) fixed to the side wall of the installation opening is slidably connected to the guide grooves (44). A second spring (46) whose other free end is fixed to the front inner wall of the guide groove (44) is fixed to the front end of the guide block (45). A T-shaped sliding seat is arranged at the rear end of the clamping plate (32). A pair of docking grooves which form a sliding fit with the sliding seat are formed at the front end of the orientation control plate (31). A second gear (37) is fixedly sleeved on the main shaft (25). A second rack (38) slidably connected thereto is arranged on the rear inner wall of the frame (24). A toothed bar (36) meshing with the second rack (38) is fixedly sleeved on the secondary shaft (33). The alignment mechanism includes a pair of fixing plates (29) fixed to the top of the shed frame (1). A plug post (30) fixed to the orientation control plate (31) is inserted into the fixing plates (29). A same bridge plate (40) is fixed to the rear ends of the two plug posts (30). A first push rod (39) whose output shaft is fixed to the bridge plate (40) is fixed to the top of the shed frame (1).
2. The construction method for a green energy-saving prefabricated building wall according to claim 1, characterized in that, Through openings (14) communicating with the sliding grooves (8) are formed on both sides of the support plate (5). A round hole (15) is formed on the clamping block (11). A screw rod (17) passing through the through opening (14) is jointly inserted into the round hole (15) and the sliding block (10) close to the through opening (14). A threaded groove (16) threadedly connected to the screw rod (17) is formed on the inner side surface of the other sliding block (10).
3. The construction method for a green energy-saving prefabricated building wall according to claim 1, characterized in that, The height adjusting mechanism is located on the bottom plate (42) below the shed frame (1). Four second push rods (41) whose output shafts are fixed to the shed frame (1) are fixed to the top of the bottom plate (42) and distributed at the corners.
Citation Information
Patent Citations
A construction method for installing thermally insulated and energy-saving prefabricated building walls
CN112459503B
Thermal-insulation energy-saving fabricated building wall installation construction method
CN112459503A