Oil well hanging tank gas processing device and method
By designing a hanging tank gas treatment device suitable for remote oil well environments, and using low temperature and automatic control technology, the problems of high cost and energy consumption in hanging tank gas treatment in remote oil wells are solved, and low-cost, low-energy gas consumption is achieved. processing effect.
Patent Information
- Application Number
- CN202111201286.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-10-15
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2041-10-15
AI Technical Summary
Existing technology is difficult to effectively process small molecular hydrocarbon gases in hanging tank gases from remote oil wells, and existing equipment is costly, bulky, and energy-consuming, and is not suitable for oil well environments in remote areas.
An oil well hanging tank gas treatment device is designed, including a support device, an absorption tank, a liquid well, an absorbent spray pump and a power control cabinet. The hanging tank gas is treated at low temperature by being buried underground, using check valves and sprays. The pump automatically controls gas processing, consumes low energy, and is suitable for remote oil well environments.
It realizes low-cost, low-energy-consuming hanging tank gas treatment, reduces management difficulty, and is suitable for remote oil wells and other small molecular hydrocarbon gases produced intermittently. It has a simple implementation process and strong operability.
Smart Images

Figure CN115970450B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of gas processing, and more particularly to an oil well hanging tank gas processing device and method. Background Art
[0002] The output liquid of most oil wells in oil fields is transported to the joint station for processing through pipelines. However, some oil wells in remote areas have no pipeline connection, so they can only build a temporary liquid storage tank at the oil well site to temporarily store the output liquid of the oil well, and the output liquid of the oil well is transported away by tank trucks at regular intervals. In order to facilitate unloading to the tank truck, this temporary liquid storage tank is usually placed on a bracket at a certain height, so it is called a hanging tank. If the oil produced by the oil well is heavy oil, an electric heating device is installed at the bottom of the hanging tank. It needs to be heated in winter to reduce the viscosity of the heavy oil and facilitate discharge and loading. Water is often produced during oil well production, so there is not only oil in the hanging tank, but also water. When the hanging tank is heated or breathed at ordinary times, gas will emerge from the upper opening, which is the hanging tank gas. The main component is water vapor of small molecular hydrocarbons. If it is directly discharged into the atmosphere, the volatilized oil and gas will diffuse into the surrounding air and be easily absorbed by human breathing, which can cause cancer and blood diseases, and will also lead to frequent instantaneous flash explosion accidents. GB31570-2015 "Petroleum Refining Industry Pollutant Emission Standard" and GB31571-2015 "Petrochemical Industry Pollutant Emission Standard" require that the non-methane total hydrocarbons should not exceed 120mg / m3, so they need to be treated to achieve standard emissions. Shengli Oilfield alone currently has more than 2,000 such oil wells, and there is a problem with hanging tank gas treatment.
[0003] A Chinese patent document (CN110467951A) discloses a device and method for treating the foul smell of an oil well overhead tank. In the specification, it is stated that "my country is rich in heavy oil resources, and steam stimulation is the main means of heavy oil development. During the thermal recovery of heavy oil, the sulfur-containing compounds in the crude oil will undergo a series of hydrothermal cracking reactions, which will not only produce hydrogen sulfide, but also methyl mercaptan, ethyl mercaptan and other sulfur-containing compounds with foul odors such as rotten vegetables and garlic. Since the olfactory threshold of methyl mercaptan and ethyl mercaptan is one order of magnitude lower than that of hydrogen sulfide, the olfactory threshold of hydrogen sulfide is 0.0067 mg / m 3 The olfactory thresholds of methyl mercaptan and ethyl mercaptan are 0.00073 mg / m 3 and 0.00083mg / m 3. Most of the wells in Shengli Oilfield are produced by overhead tank oil extraction. When unloading oil from overhead tanks, the foul smell of mercaptan can be easily smelled. According to statistics, Shengli Oilfield currently has more than 100 oil wells that are opened for production after steam huffing and puffing. When unloading oil from overhead tanks, there is an unpleasant odor around the well site, which has a significant impact on the lives of oil workers and surrounding residents. Some oil wells are forced to shut down due to severe odor. The foul odor of thermal wells has become an important factor affecting the development of heavy oil resources. At present, there are two main methods for treating malodorous gases in thermal wells such as methyl mercaptan and ethyl mercaptan: (1) Regularly wash the well with strong alkaline solution. Although this method can eliminate the malodorous gas in the wellbore, it can only be used for wellbore treatment before operation, with a short effective period, and cannot be used for the treatment of normal production wells; (2) Continuous dosing of the wellbore. Add a weak oxidizing agent to the casing of the oil well to convert mercaptan into odorless or low-odor substances at the bottom of the well. Although this method can achieve the treatment of odor in thermal wells, it has problems such as large dosage, high treatment cost, and high labor intensity of adding drugs. The dosage can usually reach 30-50kg / d, the annual drug cost is more than 100,000 yuan, the frequency of adding drugs is as high as 7-10 days / time, and the labor intensity is high. Therefore, it is urgent to develop a long-term treatment method. However, in actual operation and application, it cannot completely solve the problems of low management efficiency of oil tank treatment equipment, and requires more exhaust power and high energy consumption.
[0004] A Chinese patent document (CN107161545A) discloses a multi-heating system and an integrated device for wellhead oil storage tanks, which states in the specification that "the viscosity of crude oil extracted from the wellhead at room temperature is relatively large and the fluidity is poor. When the oil enters the vehicle-mounted oil tank, it is necessary to heat the oil to reduce its viscosity and improve its fluidity. Therefore, a heating device must be installed on the wellhead oil tank. However, the current heating technology is still the in-tank coil heating technology, which has a long heating time, a large amount of heat medium consumption, and a low thermal utilization rate. In addition, after the heating coil is damaged, the crude oil in the tank needs to be drained before the coil can be inspected or replaced in the tank. Maintenance and repair require shutdown and production suspension, and the maintenance workload is large, the cost is high, and it is very complicated and cumbersome. Based on the above-mentioned problems existing in the prior art, there is an urgent need for a multi-heating system and an integrated device for wellhead oil storage tanks that can heat quickly." However, in actual operation and application, it cannot completely solve the problems of low management efficiency of oil tank processing equipment and difficulty in meeting the application requirements of different regions and sites.
[0005] In principle, the oil and gas VOCs emission treatment process can be divided into four types: condensation, adsorption, absorption and membrane separation, each with its own advantages and disadvantages. 3The hanging tank gas produced is small and continuous, so it is not suitable to use large VOCs treatment equipment. Generally, oil wells with hanging tanks are located in remote locations and are not concentrated. Therefore, there are no houses near the oil wells, and the hanging tank gas treatment equipment cannot be placed indoors. Therefore, a small treatment equipment with low treatment cost, small size, low energy consumption, safety, and no one is needed. Summary of the invention
[0006] In order to overcome the above-mentioned defects of the prior art, the present invention provides an oil well hanging tank gas processing device and method. The technical problem to be solved by the present invention is: since the volume of the hanging tank is not large, generally 20-50m 3 The hanging tank gas produced is small in quantity and continuous, so it is not suitable to use large-scale VOCs treatment equipment. Generally, oil wells with hanging tanks are because the oil wells are geographically remote and not concentrated. Therefore, there are no houses near the oil wells, and the hanging tank gas treatment equipment cannot be placed indoors.
[0007] To achieve the above-mentioned objectives, the present invention provides the following technical solutions: an oil well hanging tank gas processing device, comprising a supporting device, the upper surface of the supporting device is fixedly connected to the lower surface of the retaining seat, the inner wall of the retaining seat is connected to the outer surface of the positioning sleeve, the inner wall of the positioning sleeve is fixedly connected to the outer surface of the oil well hanging tank, the upper surface of the oil well hanging tank is connected to the bottom end of the gas pipe, the other end of the gas pipe is connected to the left end of the intake pipe through a tee, the outer surface of the intake pipe is provided with an intake valve, the other end of the gas pipe is connected to the left side of the liquid accumulation well through a first check valve, an absorbent spray pump is provided on the lower surface of the inner wall of the liquid accumulation well, an absorbent pipeline is provided on the upper surface of the absorbent spray pump, a plurality of absorbent spray heads are provided on the outer surface of the absorbent pipeline, the absorbent pipeline passes through the liquid accumulation well and is located in the absorption tank, the left side of the absorption tank and the right side of the liquid accumulation well are both provided with air inlet holes, and the two air inlet holes are connected.
[0008] As a preferred solution of an oil well hanging tank gas treatment device in the present invention: a filling groove is opened in the absorption tank, and a plurality of through holes are opened on the lower surface of the inner wall of the filling groove. The absorption tank is connected with the connecting shell through the through holes, and the absorption tank is connected with the liquid accumulation well through the connecting shell. The upper surface of the absorption tank is connected with the bottom end of the exhaust pipe, and the other end of the exhaust pipe is provided with a second check valve, and the second check valve is located above the absorption tank.
[0009] As a preferred solution of an oil well hanging tank gas treatment device in the present invention: the input and output of the absorbent spray pump are electrically connected to the output end of the cable arranged in the first cable protection tube, and the other end of the first cable protection tube passes through the liquid accumulation well and is fixedly connected to the right side of the power control cabinet.
[0010] As a preferred solution of an oil well hanging tank gas treatment device in the present invention: the input and output of the absorbent spray pump are electrically connected to the output end of the power control cabinet through a cable arranged in the first cable protection tube, and a plurality of mounting shells are fixedly connected to the left side of the liquid accumulation well, and mounting grooves are provided in the mounting shells, and a slide groove is provided on the left side of the mounting shells.
[0011] As a preferred solution of an oil well hanging tank gas processing device in the present invention: the installation groove is connected with the slide groove, the installation groove is arranged in a circular shape, two sealing plates are clamped in the installation groove, and the opposite surface limit blocks of the two sealing plates are fixedly connected, and the shape of the sealing plate is adapted to the shape of the installation groove.
[0012] As a preferred solution of an oil well hanging tank gas processing device in the present invention: the outer surface of the limit block overlaps the inner wall of the limit groove, the limit groove is opened on the right side of the mounting strip, the mounting strip is clamped on the opposite sides of the two mounting plates, and the left side of the mounting strip is fixedly connected with an adjustment device.
[0013] As a preferred solution of an oil well hanging tank gas processing device in the present invention: the mounting strip is fixedly connected to the outer surface of the mounting sleeve through an adjusting device, and a plurality of mounting sleeves are sleeved on the outer surface of the first cable protection tube.
[0014] As a preferred solution of an oil well hanging tank gas processing device in the present invention: the lower surface of the power control cabinet is fixedly connected to the upper surface of the base plate located on the right side, the number of the base plates is two, and the upper surfaces of the two base plates are fixedly connected to the lower surface of the supporting device.
[0015] As a preferred solution of the oil well hanging tank gas processing device in the present invention: the lower surface of the bottom plate is provided with anti-slip textures, and the front and back of the power control cabinet are provided with a plurality of heat dissipation ports.
[0016] As a preferred solution of an oil well hanging tank gas processing device in the present invention: a second cable protection tube is fixedly connected to the outer surface of the first check valve, the other end of the second cable protection tube is fixedly connected to the right side of the power control cabinet, and the input end of the first check valve is electrically connected to the input end of the power control cabinet through a cable arranged in the second cable protection tube.
[0017] As a preferred solution of an oil well hanging tank gas treatment device in the present invention: a liquid accumulation well cover is provided on the upper surface of the liquid accumulation well through a pin shaft, and a positioning block is fixedly connected to the lower surface of the liquid accumulation well cover and the right side of the liquid accumulation well, and the same positioning screw is clamped in the two positioning blocks, and a screw nut is threadedly connected to the outer surface of the positioning screw, and the positioning screw is arranged in an L shape, and the front side of the screw nut is clamped with the back side of the positioning block located at the rear.
[0018] As a preferred solution of the oil well hanging tank gas processing device in the present invention: a liquid accumulation display device is arranged on the front of the liquid accumulation well, and an oil tank conduit is arranged on the left side of the oil well hanging tank.
[0019] As a preferred solution of an oil well hanging tank gas processing device in the present invention: the supporting device includes a supporting platform, the lower surface of the supporting platform is fixedly connected to the upper surfaces of the two base plates respectively, the upper surface of the supporting platform is fixedly connected to the lower surface of the supporting frame, and the upper surface of the supporting frame is fixedly connected to the lower surface of the retaining seat.
[0020] As a preferred solution of an oil well hanging tank gas processing device in the present invention: the adjusting device includes a slide cylinder, a slide rod is clamped in the slide cylinder, the right end of the slide rod is fixedly connected to the left side of the mounting bar, and the left end of the slide cylinder is fixedly connected to the outer surface of the mounting sleeve.
[0021] A method for treating oil well hanging tank gas comprises the following steps:
[0022] S1. Bury the hanging gas VOCs absorption tank underground. Depending on the local climate, the burial depth should be below the frozen soil.
[0023] S2. Seal the tank opening and connect the inlet of the absorption tank through the gas pipe; connect the signal line of the check valve A to the power control cabinet, and connect the power line of the power control cabinet to the absorbent spray pump. The power supply of the power control cabinet comes from the oil well power supply.
[0024] S3. Open the liquid accumulation well cover and inject a certain amount of absorbent to ensure that the absorbent submerges the spray pump and the connecting hole between the liquid accumulation well and the bottom of the suction tank.
[0025] S4. There are two situations in which hanging tank gas is generated. One is oil well production, when the output liquid enters the hanging tank and the liquid squeezes the gas out. In addition, the hanging tank is heated to produce gas, which includes some water vapor. The gas passes through the gas pipeline, pushes the check valve A, and enters the absorption tank. At the same time, the check valve A will send out a start signal to start the spray pump. When the gas stops producing, the check valve A will close and send out a closing signal. The power control cabinet will delay closing the spray pump. The delay time can be manually controlled.
[0026] S5. Due to the presence of water vapor in the hanging tank gas, the liquid level in the liquid well will rise with the extension of the use time. Therefore, when the hanging tank is pulling oil, the liquid level display should be checked at the same time. If the liquid level is too high, it is necessary to open the well cover to extract the absorbent.
[0027] S6. Replace the absorbent regularly. After absorbing a large amount of hydrocarbon VOCs and approaching saturation, the absorbent needs to be replaced in time. During replacement, the old absorbent is extracted from the liquid wellhead and new absorbent is added. The replacement cycle needs to be determined according to the specific oil well production, oil products and season.
[0028] S7. The only power part in the absorption tank is the spray pump. Due to its low lifting range, low power and low energy consumption, it can be taken out from the liquid accumulation wellhead during maintenance.
[0029] S8. When installing the second cable protection tube, extend the installation bar into the slide groove, clamp the limit groove on the surface of the limit block, and rotate the slide rod synchronously to make the installation bar drive the two sealing plates to rotate during the rotation. Stop rotating the slide rod after rotating ninety degrees. The installation effect can be achieved through the friction between the installation bar and the inside of the installation groove. When opening or closing the liquid accumulation manhole cover, the positioning screw can be removed or the positioning screw can be removed by rotating the screw nut forward or reversely, thereby realizing the opening and closing of the liquid accumulation manhole cover.
[0030] Compared with the prior art, the present invention has the following advantages and beneficial effects:
[0031] 1. The present invention provides a first check valve, a second check valve, a liquid accumulation well, an absorption tank and a connecting shell. There are two situations in which the hanging tank produces hanging tank gas. One is oil well production, the output liquid enters the hanging tank, and the liquid squeezes the gas out; the other is that the hanging tank is heated to produce gas, including part of water vapor; the gas passes through the gas pipeline, pushes the check valve A, and enters the absorption tank. At the same time, the check valve A will send out a start signal to start the spray pump. When the gas stops producing, the check valve A is closed and a closing signal is also sent. The power control cabinet will delay closing the spray pump. The delay time can be Artificial control, because the treatment device can be buried underground and can make use of the low temperature underground, and is easy to manage, the actual use effect of the treatment device is guaranteed, and the difficulty of management is reduced. Moreover, because the treatment device does not require power and has extremely low energy consumption, it is very suitable for the treatment of remote oil well hanging tank gas, and is also suitable for the treatment of other discontinuously produced small molecular hydrocarbon VOCs. At the same time, because the treatment device has the characteristics of simple implementation process, pertinence, strong operability and good on-site effect, therefore, the treatment device can be widely used in the treatment of oil well hanging tank gas;
[0032] 2. The present invention provides a slide bar, a sealing plate and a mounting strip. When installing the second cable protection tube, the mounting strip is extended into the slide groove, the limit groove is clamped on the surface of the limit block, and the slide bar is rotated synchronously, so that the mounting strip drives the two sealing plates to rotate during the rotation. When the slide bar is rotated ninety degrees, the rotation of the slide bar is stopped, and the installation effect can be achieved through the friction between the mounting strip and the inside of the mounting groove, so that the processing device can stabilize the line pipe inside it, and the stability of the line pipe can be guaranteed when it is buried underground. At the same time, under the action of the sealing plate, the map below can be effectively prevented from entering the installation groove through the slide groove, thereby reducing the situation where the slide bar is difficult to rotate due to soil blockage when disassembling the first cable protection tube, thereby ensuring the use effect of the processing device. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] Figure 1 It is a three-dimensional structural schematic diagram of the present invention;
[0034] Figure 2 It is a three-dimensional structural schematic diagram of the liquid accumulation well of the present invention;
[0035] Figure 3 It is a schematic diagram of the three-dimensional cross-sectional structure of the absorption tank of the present invention;
[0036] Figure 4 It is a schematic diagram of the exploded structure of the installation shell section of the present invention;
[0037] In the figure:
[0038] 1—Support device
[0039] 101-support platform 102-support frame,
[0040] 2—Retaining seat 3—Positioning sleeve 4—Oil well hanging tank
[0041] 5—air delivery pipe 6—air intake pipe 7—air intake valve
[0042] 8—First check valve 9—Liquid accumulation well 10—Absorbent spray pump
[0043] 11—Absorbent pipeline 12—Absorbent spray head
[0044] 13—absorption tank 14—through hole 15—connecting shell
[0045] 16 - air inlet 17 - packing slot 18 - exhaust pipe
[0046] 19—Second check valve 20—First cable protection tube
[0047] 21—Mounting shell 22—Mounting slot 23—Slide slot
[0048] 24—sealing plate 25—limiting block 26—installation strip
[0049] 27—Limiting groove 28—Adjustment device
[0050] 281—slide cylinder 282 slide rod
[0051] 29—Installation sleeve 30—Second cable protection tube
[0052] 31—Power supply control cabinet 32—Heat dissipation outlet 33—Base plate
[0053] 34 - oil tank conduit 35 - liquid accumulation manhole cover 36 - positioning block
[0054] 37 - positioning screw rod 38 - screw rod nut 39 - liquid accumulation display device. DETAILED DESCRIPTION
[0055] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0056] like Figure 1-4 As shown, the present invention provides an oil well hanging tank gas processing device, comprising a supporting device 1, the upper surface of the supporting device 1 is fixedly connected to the lower surface of a retaining seat 2, the inner wall of the retaining seat 2 is fixedly connected to the outer surface of a positioning sleeve 3, the inner wall of the positioning sleeve 3 is fixedly connected to the outer surface of an oil well hanging tank 4, the upper surface of the oil well hanging tank 4 is connected to the bottom end of a gas pipeline 5, the other end of the gas pipeline 5 is connected to the left end of an air intake pipe 6 through a tee, the outer surface of the air intake pipe 6 is provided with an air suction valve 7, the other end of the gas pipeline 5 is connected to the left side of a liquid accumulation well 9 through a first check valve 8, and the lower surface of the inner wall of the liquid accumulation well 9 is provided with an absorption valve 7. An absorbent spray pump 10 is provided with an absorbent pipeline 11 on the upper surface of the absorbent spray pump 10, and a plurality of absorbent spray heads 12 are provided on the outer surface of the absorbent pipeline 11. The absorbent pipeline 11 passes through the liquid accumulation well 9 and is located in the absorption tank 13. Air inlet holes 16 are provided on the left side surface of the absorption tank 13 and the right side surface of the liquid accumulation well 9, and the two air inlet holes 16 are connected. A filling groove 17 is provided in the absorption tank 13, and a plurality of through holes 14 are provided on the lower surface of the inner wall of the filling groove 17. The absorption tank 13 is connected with a connecting shell 15 through the through holes 14, and the absorption tank 13 is connected with the liquid accumulation well 9 through the connecting shell 15.
[0057] As an embodiment of the present invention, the upper surface of the absorption tank 13 is connected to the bottom end of the exhaust pipe 18 , and a second check valve 19 is provided at the other end of the exhaust pipe 18 . The second check valve 19 is located above the absorption tank 13 .
[0058] The input and output of the absorbent spray pump 10 are electrically connected to the output end of the cable set in the first cable protection tube 20, and the other end of the first cable protection tube 20 passes through the liquid accumulation well 9 and is fixedly connected to the right side of the power control cabinet 31.
[0059] As an embodiment of the present invention, the input and output of the absorbent spray pump 10 are electrically connected to the output end of the power control cabinet 31 through a cable arranged in the first cable protection tube 20, and a plurality of mounting shells 21 are fixedly connected to the left side of the liquid accumulation well 9, and a mounting groove 22 is opened in the mounting shell 21, and a slide groove 23 is opened on the left side of the mounting shell 21.
[0060] The mounting groove 22 is connected to the slide groove 23 . The mounting groove 22 is set to be circular. Two sealing plates 24 are clamped in the mounting groove 22 . The opposite surfaces of the two sealing plates 24 are fixedly connected by limit blocks 25 . The shape of the sealing plates 24 is adapted to the shape of the mounting groove 22 .
[0061] As an embodiment of the present invention, the outer surface of the limit block 25 overlaps the inner wall of the limit groove 27, the limit groove 27 is opened on the right side of the mounting strip 26, the mounting strip 26 is clamped on the opposite sides of the two mounting plates, and the left side of the mounting strip 26 is fixedly connected with an adjustment device 28.
[0062] The mounting strip 26 is fixedly connected to the outer surface of the mounting sleeve 29 through the adjusting device 28 , and a plurality of mounting sleeves 29 are sleeved on the outer surface of the first cable protection tube 20 .
[0063] As an embodiment of the present invention, the lower surface of the power control cabinet 31 is fixedly connected to the upper surface of the base plate 33 located on the right side, there are two base plates 33, and the upper surfaces of the two base plates 33 are fixedly connected to the lower surface of the support device 1.
[0064] The lower surface of the bottom plate 33 is provided with anti-skid patterns, and a plurality of heat dissipation openings 32 are provided on the front and back of the power control cabinet 31 .
[0065] As an embodiment of the present invention, the outer surface of the first check valve 8 is fixedly connected to the second cable protection tube 30, the other end of the second cable protection tube 30 is fixedly connected to the right side of the power control cabinet 31, and the input end of the first check valve 8 is electrically connected to the input end of the power control cabinet 31 through the cable arranged in the second cable protection tube 30.
[0066] A liquid accumulation well 9 is provided with a liquid accumulation well cover 35 via a pin shaft, and a positioning block 36 is fixedly connected to the lower surface of the liquid accumulation well cover 35 and the right side surface of the liquid accumulation well 9, and the same positioning screw 37 is clamped in the two positioning blocks 36, and a screw nut 38 is threadedly connected to the outer surface of the positioning screw 37. The positioning screw 37 is arranged in an L shape, and the front side of the screw nut 38 is clamped with the back side of the positioning block 36 located at the rear.
[0067] A liquid accumulation display device 39 is provided on the front of the liquid accumulation well 9 , and an oil tank conduit 34 is provided on the left side of the oil well hanging tank 4 .
[0068] As an embodiment of the present invention, the supporting device 1 includes a supporting platform 101, the lower surface of the supporting platform 101 is fixedly connected to the upper surfaces of the two base plates 33 respectively, the upper surface of the supporting platform 101 is fixedly connected to the lower surface of the supporting frame 102, and the upper surface of the supporting frame 102 is fixedly connected to the lower surface of the retaining seat 2.
[0069] As an embodiment of the present invention, the adjusting device 28 includes a slide cylinder 281, in which a slide rod 282 is clamped, the right end of the slide rod 282 is fixedly connected to the left side of the mounting strip 26, and the left end of the slide cylinder 281 is fixedly connected to the outer surface of the mounting sleeve 29.
[0070] A method for treating oil well hanging tank gas comprises the following steps:
[0071] S1. The hanging gas VOCs absorption tank 13 is buried underground, and according to the local climate, the burial depth is below the frozen soil.
[0072] S2, seal the hanging tank mouth and connect the inlet of the absorption tank 13 through the gas pipe 5; connect the signal line of the check valve A to the power control cabinet 31, connect the power line of the power control cabinet 31 to the absorbent spray pump 10, and the power supply of the power control cabinet 31 comes from the oil well power supply.
[0073] S3, open the liquid accumulation well cover 35, inject a certain amount of absorbent, and ensure that the absorbent submerges the spray pump and the connecting hole 14 between the liquid accumulation well 9 and the bottom of the suction tank.
[0074] S4. There are two situations in which hanging tank gas is generated. One is oil well production, when the output liquid enters the hanging tank and the liquid squeezes the gas out. In addition, the hanging tank is heated to produce gas, including some water vapor. The gas passes through the gas pipeline 5, pushes the check valve A, and enters the absorption tank 13. At the same time, the check valve A will send out a start signal to start the spray pump. When the gas stops producing, the check valve A will close and send out a closing signal. The power control cabinet 31 will delay the closure of the spray pump. The delay time can be manually controlled.
[0075] S5. Since there is water vapor in the hanging tank gas, the liquid level in the liquid accumulation well 9 will rise with the extension of the use time. Therefore, when the hanging tank is pulling oil, the liquid level display is inspected at the same time. If the liquid level is too high, it is necessary to open the well cover to extract the absorbent.
[0076] S6. Replace the absorbent regularly. After absorbing a large amount of hydrocarbon VOCs and approaching saturation, the absorbent needs to be replaced in time. During replacement, the old absorbent is extracted from the 9 liquid wells and new absorbent is added. The replacement cycle needs to be determined according to the specific oil well production, oil products and season.
[0077] The only power part in S7 and absorption tank 13 is the spray pump, which can be taken out from liquid accumulation well 9 during maintenance due to its low lifting range, low power and low energy consumption.
[0078] S8. When installing the second cable protection tube 30, extend the installation strip 26 into the slide groove 23, and clamp the limit groove 27 on the surface of the limit block 25, and rotate the slide bar 282 synchronously, so that the installation strip 26 drives the two sealing plates 24 to rotate during the rotation. After rotating ninety degrees, stop rotating the slide bar 282. The installation effect can be achieved through the friction between the installation strip 26 and the inside of the installation groove 22. When opening or closing the liquid accumulation manhole cover 35, the positioning screw 37 can be removed or the positioning screw 37 can be removed by rotating the screw nut 38 forward or reversely, thereby realizing the opening and closing of the liquid accumulation manhole cover 35.
[0079] By arranging the first check valve 8, the second check valve 19, the liquid accumulation well 9, the absorption tank 13 and the connecting shell 15, since the treatment device can be buried underground and can utilize the low temperature underground and is easy to manage, the actual use effect of the treatment device is guaranteed and the difficulty of management is reduced. Moreover, since the treatment device does not require power and has extremely low energy consumption, it is very suitable for the treatment of gas in remote oil well hanging tanks, and is also suitable for the treatment of other discontinuously produced small molecular hydrocarbon VOCs. At the same time, since the treatment device has the characteristics of simple implementation process, pertinence, strong operability and good on-site effect, the treatment device can be widely used in the treatment of gas in oil well hanging tanks.
[0080] By setting the slide bar 282, the sealing plate 24 and the mounting strip 26, the processing device can stabilize the line pipe inside it, and can ensure the stability of the line pipe when buried underground. At the same time, under the action of the sealing plate 24, it can effectively prevent the map below from passing through the slide groove 23 into the mounting groove 22, thereby reducing the situation where the slide bar 282 is difficult to rotate due to soil blockage when disassembling the first cable protection tube 20, thereby ensuring the use effect of the processing device.
[0081] Finally, a few points should be explained: First, in the description of this application, it should be noted that, unless otherwise specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, which may refer to mechanical connection or electrical connection, or internal communication between two components, or direct connection. "upper", "lower", "left", "right", etc. are only used to indicate relative positional relationships. When the absolute position of the object being described changes, the relative positional relationship may change;
[0082] Secondly: In the drawings of the embodiments disclosed in the present invention, only the structures related to the embodiments disclosed in the present invention are involved, and other structures can refer to the general design. In the absence of conflict, the same embodiment and different embodiments of the present invention can be combined with each other;
[0083] Finally: The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. An oil well hanging tank gas processing device, comprising a supporting device, characterized in that: The upper surface of the supporting device is fixedly connected to the lower surface of the retaining seat, the inner wall of the retaining seat is fixedly connected to the outer surface of the positioning sleeve, the inner wall of the positioning sleeve is fixedly connected to the outer surface of the oil well hanging tank, the upper surface of the oil well hanging tank is connected to the bottom end of the gas pipe, the other end of the gas pipe is connected to the left end of the air inlet pipe through a tee, an air suction valve is provided on the outer surface of the air inlet pipe, the other end of the gas pipe is connected to the left side of the liquid accumulation well through the first check valve, an absorbent spray pump is provided on the lower surface of the inner wall of the liquid accumulation well, an absorbent pipeline is provided on the upper surface of the absorbent spray pump, a plurality of absorbent spray heads are provided on the outer surface of the absorbent pipeline, the absorbent pipeline passes through the liquid accumulation well and is located in the absorption tank, the left side of the absorption tank and the right side of the liquid accumulation well are both provided with air inlet holes, and the two air inlet holes are connected; A filling groove is provided in the absorption tank, and a plurality of through holes are provided on the lower surface of the inner wall of the filling groove. The absorption tank is connected with the connecting shell through the through holes, and the absorption tank is connected with the liquid accumulation well through the connecting shell. The upper surface of the absorption tank is connected with the bottom end of the exhaust pipe, and a second check valve is provided at the other end of the exhaust pipe, and the second check valve is located above the absorption tank; The input and output of the absorbent spray pump are electrically connected to the output end of the cable set in the first cable protection tube, and the other end of the first cable protection tube passes through the liquid accumulation well and is fixedly connected to the right side of the power control cabinet; The input and output of the absorbent spray pump are electrically connected to the output end of the power control cabinet through a cable arranged in the first cable protection tube, and a plurality of mounting shells are fixedly connected to the left side of the liquid accumulation well, and mounting grooves are provided in the mounting shells, and a slide groove is provided on the left side of the mounting shells; The installation groove is connected to the slide groove, the installation groove is set to be circular, two sealing plates are clamped in the installation groove, and the limiting blocks on the opposite surfaces of the two sealing plates are fixedly connected, and the shape of the sealing plate is adapted to the shape of the installation groove; The outer surface of the limit block overlaps the inner wall of the limit groove, the limit groove is arranged on the right side of the mounting strip, the mounting strip is clamped on the opposite sides of the two sealing plates, and the left side of the mounting strip is fixedly connected with an adjusting device; The installation strip is fixedly connected to the outer surface of the installation sleeve through the adjustment device, and the plurality of installation sleeves are sleeved on the outer surface of the first cable protection tube; The adjusting device comprises a slide cylinder, a slide rod is clamped in the slide cylinder, the right end of the slide rod is fixedly connected to the left side of the mounting strip, and the left end of the slide cylinder is fixedly connected to the outer surface of the mounting sleeve.
2. The oil well hanging tank gas processing device according to claim 1 is characterized in that: The lower surface of the power control cabinet is fixedly connected to the upper surface of the bottom plate located on the right side. There are two bottom plates, and the upper surfaces of the two bottom plates are fixedly connected to the lower surface of the supporting device.
3. The oil well hanging tank gas processing device according to claim 2 is characterized in that: The lower surface of the bottom plate is provided with anti-skid patterns, and the front and back sides of the power control cabinet are provided with a plurality of heat dissipation openings.
4. The oil well hanging tank gas processing device according to claim 1 is characterized by: A second cable protection tube is fixedly connected to the outer surface of the first check valve, and the other end of the second cable protection tube is fixedly connected to the right side of the power control cabinet. The input end of the first check valve is electrically connected to the input end of the power control cabinet through a cable arranged in the second cable protection tube.
5. The oil well hanging tank gas processing device according to claim 1 is characterized by: A liquid accumulation well cover is provided on the upper surface of the liquid accumulation well through a pin shaft, and a positioning block is fixedly connected to the lower surface of the liquid accumulation well cover and the right side surface of the liquid accumulation well, and the same positioning screw is clamped in the two positioning blocks, and a screw nut is threadedly connected to the outer surface of the positioning screw, and the positioning screw is arranged in an L shape, and the front side of the screw nut is clamped with the back side of the positioning block located at the rear.
6. The oil well hanging tank gas processing device according to claim 1, characterized in that: A liquid accumulation display device is arranged on the front of the liquid accumulation well, and an oil tank conduit is arranged on the left side of the oil well hanging tank.
7. The oil well hanging tank gas processing device according to claim 1 is characterized by: The support device includes a support platform, the lower surface of the support platform is fixedly connected to the upper surfaces of the two base plates respectively, the upper surface of the support platform is fixedly connected to the lower surface of the support frame, and the upper surface of the support frame is fixedly connected to the lower surface of the retaining seat.
8. A method for treating hanging tank gas according to the oil well hanging tank gas treatment device according to any one of claims 1 to 7, characterized in that: The following steps are involved: S1. Bury the hanging gas VOCs absorption tank underground. Depending on the local climate, the burial depth should be below the frozen soil. S2, seal the hanging tank opening and connect the inlet of the absorption tank through the gas pipeline; connect the first check valve signal line to the power control cabinet, connect the power line of the power control cabinet to the absorbent spray pump, and the power supply of the power control cabinet comes from the oil well power supply; S3. Open the liquid accumulation well cover and inject a certain amount of absorbent to ensure that the absorbent submerges the spray pump and the connecting hole between the liquid accumulation well and the bottom of the suction tank; S4. There are two situations in which hanging tank gas is generated. One is oil well production, the output liquid enters the hanging tank, and the liquid squeezes the gas out. In addition, the hanging tank is heated and produces gas, including some water vapor. The gas passes through the gas pipeline and pushes the first check valve to enter the absorption tank. At the same time, the first check valve will send out a start signal to start the spray pump. When the gas stops producing, the first check valve will close and send out a closing signal. The power control cabinet will delay closing the spray pump. The delay time can be manually controlled. S5. Since there is water vapor in the hanging tank gas, the liquid level in the liquid well will rise with the extension of the use time. Therefore, when the hanging tank is pulling oil, the liquid level display should be inspected at the same time. If the liquid level is too high, it is necessary to open the well cover to extract the absorbent; S6. Regularly replace the absorbent. When the absorbent absorbs a large amount of hydrocarbon VOCs and approaches saturation, it needs to be replaced in time. When replacing, the old absorbent is extracted from the wellhead of the accumulated liquid and the new absorbent is added. The replacement cycle needs to be determined according to the specific oil well production, oil products and seasons; S7. The only power part in the absorption tank is the spray pump. Due to its low lifting range, low power and low energy consumption, it can be taken out from the liquid accumulation wellhead during maintenance; S8. When installing the first cable protection tube, extend the installation bar into the slide groove, clamp the limit groove on the surface of the limit block, and rotate the slide rod synchronously to make the installation bar drive the two sealing plates to rotate during the rotation. Stop rotating the slide rod after rotating ninety degrees. The installation effect can be achieved through the friction between the installation bar and the inside of the installation groove. When opening or closing the liquid accumulation manhole cover, the positioning screw can be removed by rotating the screw nut forward or reversely, thereby realizing the opening and closing of the liquid accumulation manhole cover.
Citation Information
Patent Citations
Multi-heating system and wellhead oil storage tank integrated device
CN107161545A
Device and method for treatment of foul odor of overhead tank in oil well
CN110467951A
Intelligent auto-regeneration gas treatment system for VOCs (volatile organic chemicals)
CN106000098A
Equipment and technological method capable of realizing secondary purification and self-circulation treatment of VOCs (Volatile Organic Compounds)
CN107261822A