A method for restoring and constructing river channel submerged plant communities

By dividing the flow rate water area and improving the base of the river, combining the layout of submerged plant communities and building a water ecosystem, the problem of low survival rate of submerged plant communities in the river channel under high flow rate environment is solved, and the river water quality improvement and landscape are achieved promote.

CN116040806BActive Publication Date: 2024-12-03CHENGDU QINGYUAN WATER ENVIRONMENT TREATMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202211573073.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-12-08
Publication Date
2024-12-03
Estimated Expiration
2042-12-08

AI Technical Summary

Technical Problem

In river channels, submerged plant communities are difficult to recover and survive in high-flow velocity water flows, and existing submerged plant communities recovery technology in lake reservoirs cannot effectively deal with the problems of flood impact and water flow drag.

Method used

By dividing the flow rate waters of the river, the basal habitat conditions are improved, and submerged plant communities are arranged according to different flow rate waters, including adjustments in planting density and depth, and the deployment of functional fish and benthic organisms, a complete water ecosystem is built. Continue manual intervention to ensure system stability.

Benefits of technology

Improve the tolerance of submerged plant communities to different flow velocities, achieve long-term survival and water quality improvement in the river channel, do not affect the normal flooding of the river channel, reduce the impact of water flow on the riverbed, and form underwater forests and grasslands. landscape.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116040806B_ABST
    Figure CN116040806B_ABST
Patent Text Reader

Abstract

The invention discloses a method for restoring and constructing a river submerged plant community, comprising the following steps: step A, dividing the river where the submerged plant community is to be constructed into flow velocity water areas; step B, improving the base habitat conditions according to the flow velocity water areas divided in step A; step C, constructing and arranging the submerged plant community based on the flow velocity water areas divided in step A, wherein the planting density of the submerged plants does not exceed 220 plants / m 2 , the depth does not exceed 15cm; step D, functional fish, benthic organisms and zooplankton are released into the submerged plant community to build a complete water ecosystem, and continuous artificial intervention ensures the stability of the water ecosystem. The present invention can improve the tolerance of submerged plant communities in flood-carrying rivers to water flows of different flow rates, quickly restore submerged plant communities in flood-carrying rivers and ensure long-term survival, improve river water quality, and reduce the scouring effect on the riverbed, thereby increasing the recovery speed of submerged plant communities.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of water environment management and ecological environment restoration, and in particular to a method for restoring and constructing a river channel submerged plant community. Background Art

[0002] Submerged plant communities have many functions, such as photosynthesis, providing habitats for aquatic organisms, promoting sedimentation, absorbing nutrients in the water to purify water quality, etc. They are important core biological communities in aquatic ecosystems. At present, the construction and restoration of submerged plant communities are widely used in lakes and reservoirs, and the technology is relatively mature, but there are few successful cases in rivers. The fundamental reason is that when applied in rivers, the lake and reservoir submerged plant community restoration technology is still used. It can play a certain purification capacity in the initial stage of construction, but after a certain period of construction or flood season, especially when facing the impact of floods, the survival rate of submerged plant communities is low.

[0003] The main defects of restoring river submerged plant communities by using lake and reservoir submerged plant community restoration technology are as follows:

[0004] 1. The dragging effect of water flow in lakes and rivers on submerged plants is different. If the water flow in the river is too fast, the dragging force on submerged plants will be greater, which will cause the submerged plants to be uprooted, thus destroying the submerged plant community;

[0005] 2. The scouring force of water flow on the base of lakes and rivers is different, which makes it difficult for the roots of submerged plants to be fixed and eventually destroyed;

[0006] 3. Under existing technical measures, submerged plant communities can only survive in waters with a flow rate of less than 0.8 m / s, and their overall survival rate and biomass are low. However, the flow rate of flood-carrying rivers during flood season can usually reach more than 1.5 m / s. Therefore, it is impossible to guarantee the large-scale and long-term survival of submerged plants in flood-carrying rivers. Summary of the invention

[0007] In order to solve the technical problem that the above-mentioned submerged plant communities are difficult to restore and survive for a long time in flood-carrying rivers, the purpose of the present invention is to provide a method for restoring and constructing submerged plant communities in rivers, by dividing the river into flow velocity and water areas, improving the base habitat conditions according to the flow velocity and water area divisions, constructing submerged plant communities, and constructing a complete water ecosystem to restore the submerged plant communities in the river.

[0008] To achieve the above object, the present invention provides the following technical solutions:

[0009] A method for restoring and constructing a river submerged plant community comprises the following steps:

[0010] Step A, dividing the water area of ​​the river where the submerged plant community is to be constructed into still water area, medium and low flow water area, high flow water area and super-speed water area;

[0011] Step B, improving the base habitat conditions according to the velocity water area divided in step A;

[0012] Step C: Based on the velocity water area divided in step A, a submerged plant community is constructed and arranged on the basis of step B, wherein the planting density of submerged plants does not exceed 220 plants / m 2 , depth not exceeding 15cm;

[0013] Step D: Release functional fish, benthic organisms and zooplankton into the submerged plant community to build a complete aquatic ecosystem, and continue artificial intervention to ensure the stability of the aquatic ecosystem.

[0014] A further technical solution is: in the step B, improving the substrate habitat conditions includes:

[0015] B1. On the basis of the original riverbed, a 30-50cm thick improved soil made of a mixture of low-nutrient planting soil and clay soil is prepared and backfilled in proportion, of which the low-nutrient planting soil does not exceed 70%;

[0016] B2. Use a soil disinfectant mixed with bleaching powder and niclosamide to disinfect the base of pathogens and harmful benthic organisms. The mixing ratio of bleaching powder and niclosamide is 1:0.5. The application requirements are: evenly spray the entire lake, with a dosage of 5g / m 2 ~10g / m 2 .

[0017] A further technical solution is: the method for preparing the improved soil is:

[0018] For still water areas with a flow rate of 0 to 0.2 m / s, the improved soil is a mixture of low-nutrient planting soil and clay soil, and the proportion of clay soil used is 40% to 43.3%; for medium- and low-velocity water areas with a flow rate of 0.2 to 0.8 m / s, the improved soil is a mixture of low-nutrient planting soil and clay soil, and the proportion of clay soil used is 43.3% to 53.2%;

[0019] In high-velocity waters with a flow rate of 0.8m / s to 1.8m / s, the improved soil is a mixture of low-nutrient planting soil and clay soil, and the proportion of clay soil is 53.2% to 69.7%.

[0020] A further technical solution is: when backfilling the high-velocity water area with improved soil, crushed stone / pebbles with a particle size of 2 to 3 cm are mixed into the prepared improved soil, and the ratio of crushed stone / pebbles to improved soil is 1:4.

[0021] A further technical solution is that in step B, when improving the substrate habitat conditions, it further includes:

[0022] B3. On the basis of B2, backfill an anti-erosion ecological layer with a thickness of not less than 10 cm on the improved soil in the medium and low flow velocity waters;

[0023] B4. On the basis of B2, install honeycomb cells in the high flow velocity waters, and fix the honeycomb cells to each other with anchor bolts; when installing the honeycomb cells, backfill low-nutrient planting soil with a thickness of 3 - 5 mm, rake and tamp the surface soil; after the installation of the honeycomb cells is completed, backfill an anti-erosion ecological layer with a thickness of not less than 10 cm.

[0024] A further technical solution is that the anti-erosion ecological layer is composed of pebbles / crushed stones and improved soil mixed in a ratio of 1:1, and the particle size of the pebbles / crushed stones in the anti-erosion ecological layer in the medium and low flow velocity waters is 2 - 3 cm, and the particle size of the pebbles / crushed stones in the anti-erosion ecological layer in the high flow velocity waters is 3 - 4 cm.

[0025] A further technical solution is that the mixing ratio formula of the low-nutrient planting soil and the cohesive soil is:

[0026] x = 16.5v + 40, x + y = 1, where v is the water flow velocity, y is the proportion of the low-nutrient planting soil, and x is the proportion of the cohesive soil.

[0027] A further technical solution is that the low-nutrient planting soil does not contain construction waste, weeds, tree roots, stones, gravel, and structures, and its porosity > 40%, and the organic matter content ≤ 20 g / kg; the clay porosity of the cohesive soil > 20%, the particle size range is 0.005 - 0.05 mm, the natural consistency index 0.25 < lc ≤ 0.75, and the organic matter content ≤ 20 g / kg.

[0028] A further technical solution is that in step C, the method of arranging the submerged plant community is:

[0029] C1. Plant Vallisneria natans, Myriophyllum verticillatum, and Hydrilla verticillata in the still water waters in a ratio of 3:1:1, with the plant heights of 1 - 1.5 m, 0.5 - 0.8 m, and 0.5 - 0.8 m respectively, and the planting density of 150 - 220 plants / m 2 , the planting depth of Vallisneria natans is 7 - 15 cm, and the planting depth of Hydrilla verticillata is 5 - 15 cm;

[0030] Or C2, for waters with medium and low flow rates, Potamogeton rubrum and Potamogeton malachium are mainly planted, with Vallisneria salsa, Myriophyllum truncatum and Hydrilla verticillata as auxiliary plants. The planting ratio is 3:3:1:1:0.5, and the plant heights are 0.7-1.2m, 0.7-1.2m, 0.3-0.7m, 0.5-0.7m and 0.5-0.6m respectively, and the planting density is 150-220 plants / m 2 , the planting depth of Potamogeton ricinus and Potamogeton malachite is 10-15cm;

[0031] Or C3, for high-velocity waters, plant Potamogeton comfrey and Potamogeton serrata, with a planting ratio of 1:1, plant height of 0.7-1.2m, and planting density of 200-220 plants / m 2 The planting depth of Potamogeton ricinus and Potamogeton malachite is 13 to 15 cm.

[0032] A further technical solution is: in the step D, functional fish, benthic organisms and zooplankton are released into the submerged plant community, wherein the functional fish include sea bass, black carp, black snakehead and bighead carp; the benthic organisms include pear-shaped ring snails, toothless clams and river clams; and the zooplankton includes large Daphnia;

[0033] Methods of artificial intervention include: cleaning the water surface and seasonal harvesting of aquatic plants; setting up interception nets along the edge of submerged plant communities, with the grid size set to within 2cm×2cm; after the flood passes, cleaning up aquatic plant attachments, checking the damage of the interception nets and replacing them in time, and supplementing fish and benthic organisms according to the water state.

[0034] Compared with the prior art, the present invention has the following beneficial effects:

[0035] 1) It can improve the tolerance of submerged plant communities in flood-carrying rivers to water flows of different velocities, quickly restore submerged plant communities in flood-carrying rivers and ensure long-term survival, thereby improving river water quality.

[0036] 2) It does not affect the normal flow of the river. At the same time, it can reduce the water flow speed and weaken the scouring effect on the riverbed.

[0037] 3) Based on the restoration of submerged plant communities, it is possible to form underwater forest and underwater grassland landscape effects and improve the river landscape effects. BRIEF DESCRIPTION OF THE DRAWINGS

[0038] Figure 1 This is a flow chart of a method for restoring and constructing a river submerged plant community according to an embodiment of the present invention;

[0039] Figure 2 It is a plan view of the honeycomb cells in an embodiment of the present invention. DETAILED DESCRIPTION

[0040] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0041] See attached Figure 1-2 A method for restoring and constructing a river submerged plant community of the present invention comprises the following steps:

[0042] Step A, dividing the water area of ​​the river where the submerged plant community is to be constructed into still water area, medium and low flow water area, high flow water area and super-speed water area;

[0043] For example, the water areas with different flow rates in the same river channel can be divided into still water areas with a flow rate of 0 to 0.2 m / s, medium and low flow water areas with a flow rate of 0.2 to 0.8 m / s, high flow water areas with a flow rate of 0.8 to 1.8 m / s, and super-speed water areas with a flow rate of >1.8 m / s. Except for the super-speed water areas, the remaining water areas can be restored with submerged plant communities according to the technical means of the present invention.

[0044] As a preferred method, the velocity water area division of the river channel where the submerged plant community is to be constructed includes:

[0045] A1. Use electromagnetic wave rangefinder to measure the underwater topography of the repaired river section with a measurement accuracy of 0.5m.

[0046] A2. Import the measured terrain into CAD software, export it to DXF format file through CAD software, use dxf2xyz software to convert terrain data into xyz format file, import the file into fluid mechanics simulation software flow3d for stl file conversion, and finally generate a three-dimensional river terrain file.

[0047] A3. Use the square grid in flow3d to simulate the terrain. The roughness is the general roughness of the mountain river n = 0.04. The simulated working condition is the design flood standard of the study river section. The water temperature is T = 20℃. The model calculation grid division accuracy is 0.5m*0.5m, and the total number of grids is about 5 million.

[0048] A4. Velocity simulation is performed through the established three-dimensional model. The simulation scenario is the flood standard designed for the study river section, so as to obtain the velocity simulation results of the study river section under the flood standard. The simulation results can be visualized using the post-processing software flowsight provided by flow3d. The velocity display range is set according to the values ​​of still water area (0-0.2m / s), medium and low velocity water area (0.2-0.8m / s), high velocity water area (0.8-1.8m / s), and overspeed water area (>1.8m / s). Only the partition range is displayed, so as to obtain the velocity plane partition map of the study river section.

[0049] A5. Determine the scope of the submerged plant community restoration area: Based on the planar distribution map of flow velocity in the studied river section, the area with a flow velocity less than 2m / s is determined as the submerged plant community restoration area, thereby constructing the submerged plant community.

[0050] Step B, improving the base habitat conditions according to the flow rate water areas divided in step A; by improving the base soil structure and composition of the water areas with different flow rates, forming base habitat conditions suitable for submerged plant communities;

[0051] Before improving the base habitat conditions, temporary earth cofferdams need to be set up at the beginning and end of the river section to be repaired to facilitate the construction of the river section repair section. The cofferdam material is made of clay from both sides of the river.

[0052] Improve the substrate habitat conditions, including:

[0053] B1. On the basis of the original riverbed, a 30-50cm thick improved soil made of a mixture of low-nutrient planting soil and clay soil is prepared and backfilled in proportion, of which the low-nutrient planting soil does not exceed 70%;

[0054] Specifically, the method for preparing the improved soil is:

[0055] For still water areas with a flow rate of 0 to 0.2 m / s, the improved soil is a mixture of low-nutrient planting soil and clay soil, and the proportion of clay soil used is 40% to 43.3%;

[0056] For water areas with medium and low flow rates of 0.2 to 0.8 m / s, the improved soil is a mixture of low-nutrient planting soil and clay soil, and the proportion of clay soil used is 43.3% to 53.2%;

[0057] For high-velocity waters with a flow rate of 0.8m / s to 1.8m / s, the improved soil is a mixture of low-nutrient planting soil and clay soil, and the proportion of clay soil used is 53.2% to 69.7%. Preferably, when backfilling the improved soil in high-velocity waters, crushed stone / pebbles with a particle size of 2 to 3cm are added to the prepared improved soil, and the ratio of crushed stone / pebbles to improved soil is 1:4.

[0058] The mixing ratio of low-nutrient planting soil and clay can also be adjusted according to the specific flow velocity of the water body. Among them, the formula for the mixing ratio of low-nutrient planting soil and clay is:

[0059] x = 16.5v + 40, x + y = 1, where v is the water body flow velocity, y is the proportion of low-nutrient planting soil, and x is the proportion of clay.

[0060] Preferably, the low-nutrient planting soil does not contain construction waste, weeds, tree roots, stones, gravel and structures, and the porosity > 40%, and the organic matter content ≤ 20 g / kg; the clay porosity of the clay > 20%, the particle size range is 0.005 - 0.05 mm, the natural consistency index 0.25 < lc ≤ 0.75, and the organic matter content ≤ 20 g / kg.

[0061] B2. Use a soil disinfectant mixed with bleaching powder and niclosamide to disinfect the substrate for pathogens and harmful benthic organisms. The mixing ratio of bleaching powder and niclosamide is 1:0.5, and the application requirements are: evenly sprinkle the whole lake, and the dosage is 5 g / m 2 ~10 g / m 2 .

[0062] B3. On the basis of B2, backfill an anti-erosion ecological layer with a thickness of not less than 10 cm on the improved soil in the medium and low flow velocity waters;

[0063] Specifically, the anti-erosion ecological layer is composed of pebbles / gravels and improved soil in a ratio of 1:1, and the pebbles / gravels in the anti-erosion ecological layer in the medium and low flow velocity waters have a particle size of 2 - 3 cm, and the pebbles / gravels in the anti-erosion ecological layer in the high flow velocity waters have a particle size of 3 - 4 cm.

[0064] B4. On the basis of B2, install honeycomb cells in the high flow velocity waters, and the honeycomb cells are fixed by anchor bolts; when installing the honeycomb cells, backfill 3 - 5 mm thick low-nutrient planting soil, rake the surface soil and tamp it; after the installation of the honeycomb cells is completed, backfill an anti-erosion ecological layer with a thickness of not less than 10 cm.

[0065] Step C. According to the flow velocity waters divided in step A, construct and arrange a submerged plant community on the basis of step B, where the planting density of the submerged plants does not exceed 220 plants / m 2 , and the depth does not exceed 15 cm;

[0066] Among them, the method of arranging the submerged plant community is:

[0067] C1. Plant Vallisneria natans, Myriophyllum verticillatum and Hydrilla verticillata in the still water area in a ratio of 3:1:1, with the plant heights of 1 - 1.5 m, 0.5 - 0.8 m, and 0.5 - 0.8 m respectively, and the planting density of 150 - 220 plants / m2 , the planting depth of Vallisneria is 7 to 15 cm, and the planting depth of Hydrilla is 5 to 15 cm;

[0068] Or C2, for waters with medium and low flow rates, Potamogeton rubrum and Potamogeton malachium are mainly planted, with Vallisneria salsa, Myriophyllum truncatum and Hydrilla verticillata as auxiliary plants. The planting ratio is 3:3:1:1:0.5, and the plant heights are 0.7-1.2m, 0.7-1.2m, 0.3-0.7m, 0.5-0.7m and 0.5-0.6m respectively, and the planting density is 150-220 plants / m 2 , the planting depth of Potamogeton ricinus and Potamogeton malachite is 10-15cm;

[0069] Or C3, for high-velocity waters, plant Potamogeton comfrey and Potamogeton serrata, with a planting ratio of 1:1, plant height of 0.7-1.2m, and planting density of 200-220 plants / m 2 The planting depth of Potamogeton ricinus and Potamogeton malachite is 13 to 15 cm.

[0070] Scientifically and rationally select submerged plant varieties, planting density and depth under different flow velocities: According to the coupling relationship between the growth laws of different submerged plants and the flow velocity of the water body, select the submerged plant varieties, quantity and planting methods for waters with different flow velocities.

[0071] Step D: releasing functional fish, benthic organisms and zooplankton into the submerged plant community to build a complete aquatic ecosystem, and continuously perform artificial intervention to ensure the stability of the aquatic ecosystem;

[0072] Functional fish, benthic organisms and zooplankton are released into the submerged plant community. Functional fish include sea bass, black carp, snakehead and bighead carp; benthic organisms include pear-shaped ring snails, toothless clams and river clams; and zooplankton includes large Daphnia;

[0073] Methods of artificial intervention include: cleaning the water surface and seasonal harvesting of aquatic plants; setting up interception nets along the edge of submerged plant communities, with the grid size set to within 2cm×2cm; after the flood passes, cleaning up aquatic plant attachments, checking the damage of the interception nets and replacing them in time, and supplementing fish and benthic organisms according to the water state.

[0074] Build a complete aquatic ecosystem and ensure system stability through continuous human intervention: According to the characteristics of the water body, establish a complete underwater food web chain structure to promote the circulation of matter and energy, and then control the damage and interference of wild fish to submerged plant communities through moderate human intervention, so as to successfully complete the restoration of submerged plant communities, improve the structure of the water ecosystem, improve water quality and improve the underwater landscape effect.

[0075] Embodiment 1,

[0076] Set it as a still water area with a river channel flow velocity of 0 - 0.2 m / s, and implement a method for restoring and constructing a submerged plant community in the river channel;

[0077] On the basis of the original riverbed, backfill 30 - 50 cm thick improved soil 1 composed of a mixture of low-nutrient planting soil and clay soil. Among them, the proportion of clay soil is between 40% - 43.3%, which is selected according to the actual flow velocity of the project. The greater the flow velocity, the smaller the proportion of low-nutrient planting soil and the greater the proportion of clay soil, because clay soil has stronger erosion resistance. The greater the proportion of low-nutrient planting soil, the better the plant growth, but the low-nutrient planting soil should not exceed 70% to avoid water pollution caused by excessive nutrients. Therefore, in the actual project implementation, it is necessary to balance the plant growth state and erosion resistance. Among them, the low-nutrient planting soil is required to contain no construction waste, weeds, tree roots, stones and structures, no gravel, porosity greater than 40%, and organic matter ≤ 20 g / kg; among them, the clay soil is required to have a clay porosity greater than 20%, particle size range of 0.005 - 0.05 mm, natural consistency index of 0.25 < lc ≤ 0.75, and organic matter ≤ 20 g / kg. Use a mixed soil disinfectant of bleaching powder and niclosamide to disinfect the substrate for pathogens and harmful benthic organisms. The mixing ratio is 1:0.5, and its application technical requirements are: evenly sprinkle the whole lake, and the designed dosage is 5 g / m 2 ~10 g / m 2 .

[0078] The improved substrate has the following functions:

[0079] 1. The improved substrate soil contains appropriate nutrients and water permeability, which can meet the basic needs of the normal growth of the roots of submerged plants. The pore structure of the soil is conducive to forming suitable living conditions for aerobic and anaerobic microorganisms;

[0080] 2. The viscosity of the planting soil is insufficient. Therefore, the clay mixed in the improved soil can increase the viscosity of the substrate. The roots of submerged plants can be stably fixed in the substrate and can withstand the influence of intermittent low-flow velocity disturbances. The starting flow velocity of the clay is about 0.30 m / s, and its erosion resistance meets the requirements of the still water area.

[0081] In nature, different varieties of submerged plants have different tolerances to the influence of water flow. According to the plant structure and growth characteristics of submerged plants, different varieties of submerged plants are arranged in different flow velocity waters to improve the survival rate of submerged plants;

[0082] The greater the planting density of submerged plants, the stronger the overall resistance of the formed community to water flow impact, but the density should not be too large, not exceeding 220 plants / m2. On the one hand, the construction is more difficult, and on the other hand, the internal competition within the submerged plant community is too intense, resulting in poor overall growth and affecting the final water purification and landscape effects;

[0083] The greater the planting depth of submerged plants, but not exceeding 15cm, the stronger the plant's ability to resist scour and the higher the survival rate during the flood season. However, the planting depth should not be too large, as construction will be more difficult. At the same time, too large a depth will cause oxygen deprivation in the roots of submerged plants, resulting in root rot and reducing the overall survival rate.

[0084] Then, construct and arrange submerged plant communities in still water areas;

[0085] Selection of submerged plant species: In low-flow waters, you can choose plant species used in conventional lake and reservoir water ecological restoration: Vallisneria, Foxtail Algae, and Hydrilla. The planting ratio is about 3:1:1, and the plant heights range from 1 to 1.5m, 0.5 to 0.8m, and 0.5 to 0.8m, respectively.

[0086] Submerged plant planting density: The planting density of submerged plants in low-velocity waters is higher than that in general lakes and reservoirs, with a planting density of 150 to 220 plants / m 2 The formed community as a whole can resist the impact of water flow.

[0087] Planting depth of submerged plants: The planting depth of submerged plants in low-flow waters is greater than that in general lakes and reservoirs. The planting depth is 7 to 15 cm for Vallisneria and 5 to 15 cm for Hydrilla.

[0088] Reconstruct a complete water ecosystem and continue human intervention to ensure system stability;

[0089] Unlike lakes and reservoirs, rivers are in a state of overflow almost all year round, with frequent genetic exchanges between upstream and downstream and strong influences between biological communities. In particular, among the native fish in rivers, there are a large number of herbivorous or omnivorous fish, such as grass carp and crucian carp. Herbivorous and omnivorous fish mostly feed on aquatic plants, which can cause serious damage to submerged plant communities in the coastal zone. Therefore, the construction and maintenance of water ecosystems should focus on controlling the impact of herbivorous and omnivorous fish.

[0090] 1. After the submerged plant community is fully constructed, functional fish, benthic organisms, and zooplankton are released to ensure the integrity of the underwater ecological food web chain. The fish released are mainly local carnivorous fish to control the damage of wild fish to aquatic plants: 3kg / mu of sea bass, 3kg / mu of black carp, 4kg / mu of black snakehead, and 3kg / mu of bighead carp; benthic organisms: 5g / m2 of pear-shaped ring snails, 10g / m2 of toothless clams, and 10g / m2 of river clams; zooplankton: 5L / mu of large Daphnia (8-12 / L).

[0091] 2. After the water ecosystem is constructed, continuous human intervention is required to ensure that the ecosystem tends to be stable. The main intervention contents include:

[0092] ①. Water surface cleaning, seasonal harvesting of aquatic plants, etc.;

[0093] ② Wild fish interception nets should be set up along the edge of the submerged plant community area. The mesh size should be within 2cm×2cm. This mesh size allows young fish to pass through and blocks adult fish from passing through. On the one hand, it can ensure that functional fish in the restoration area escape and maintain the integrity of the ecosystem. On the other hand, it can prevent native wild fish in the river from entering the restoration area and causing damage to submerged plants. At the same time, it can form vicious competition with other fish and affect the integrity and functionality of the water ecosystem.

[0094] ③ After the flood passes, it is necessary to clean up the aquatic plants in time, check the damage of the interception net and replace it in time, and add fish and benthic organisms appropriately according to the water state.

[0095] Embodiment 2,

[0096] The water area is set to be a medium-low flow area with a flow velocity of 0.2 to 0.8 m / s, and a method for restoring and constructing a river submerged plant community is implemented;

[0097] On the basis of the original riverbed, backfill 30-50 cm thick low-nutrient planting soil and clay soil to form improved soil 2. Due to the increase in flow velocity, the proportion of clay soil increases to 43.3%-53.2% compared with that in static water areas. It is selected according to the actual flow velocity of the project. The larger the proportion of clay soil, the better the plant growth because clay soil has stronger resistance to erosion. However, low-nutrient planting soil should not exceed 70% to avoid water pollution caused by excess nutrition. In actual project implementation, it is necessary to take into account the growth status of plants and the ability to resist erosion. According to the results of a large number of experimental data, the distribution ratio formula of low-nutrient planting soil and clay soil is fitted as follows: x=16.5v+40, x+y=1, where v is the water flow velocity, y is the proportion of low-nutrient planting soil, and x is the proportion of clay soil. The anti-scouring ability of the base can be enhanced. Bleach and niclosamide are mixed with soil disinfectants to disinfect pathogens and harmful benthic organisms on the base. The mixing ratio is 1:0.5. The application technical requirements are: evenly spray the whole lake, and the designed dosage is 5g / m 2 ~10g / m 2 .

[0098] Then, a 10 cm thick anti-scour ecological layer 1 composed of a mixture of crushed stone / pebbles and improved soil is backfilled above the improved soil 2. Pebbles and crushed stone materials can be locally sourced according to the actual situation of the project site, and can be replaced by similar materials, including but not limited to gravel, volcanic stone, calcite, analcime and other materials. The mixing ratio of crushed stone / pebbles to improved soil is 1:1, and the particle size of the crushed stone and pebble layer is about 2 to 3 cm.

[0099] The improved substrate has the following functions:

[0100] 1. The improved base soil contains an appropriate amount of nutrients and water permeability, which can meet the basic needs of the normal growth of submerged plant roots. The pore structure of the soil is conducive to the formation of conditions suitable for the survival of aerobic and anaerobic microorganisms;

[0101] 2. The viscosity of the improved base soil is enhanced, and the anti-scouring ability is improved. At the same time, the anti-scouring ecological layer can further improve the anti-scouring ability of the base soil. The pebbles with a particle size of 2 to 3 cm start the flow rate of about 1m / s. The anti-scouring ability meets the needs of medium and low flow waters, allowing submerged plant communities to grow stably in medium and low flow waters;

[0102] 3. The gravel or pebbles in the anti-scour ecological layer have a large specific surface area, which can provide space for microorganisms to attach and grow, thereby forming a microbial protection layer at the bottom of the riverbed and improving the purification efficiency of bottom mud pollution.

[0103] Then, construct and arrange submerged plant communities in waters with medium and low flow rates;

[0104] Selection of submerged plant varieties: In waters with medium and low flow rates, the main submerged plant varieties with strong scour resistance found in natural rivers, such as Potamogeton ricinus and Potamogeton malachite, should be planted, supplemented by lake and reservoir varieties such as Vallisneria salsa, Foxtail algae, and Hydrilla verticillata. The planting ratio is approximately 3:3:1:1:0.5, and the plant height ranges are 0.7-1.2m, 0.7-1.2m, 0.3-0.7m, 0.5-0.7m, and 0.5-0.6m respectively.

[0105] Planting density of submerged plants: The planting density in waters with medium and low flow rates is 180 to 220 plants / m2. The community formed as a whole can resist the impact of medium and low flow rates.

[0106] Planting depth of submerged plants: The planting depth is 10-15cm for Potamogeton comfrey and 10-15cm for Potamogeton comfrey.

[0107] For example, in Example 1, a complete water ecosystem is constructed, and continuous human intervention ensures the stability of the system.

[0108] Embodiment 3,

[0109] It is set as a high-velocity water area with a river flow velocity of 0.8m / s to 1.8m / s, and a method for restoring and constructing a river submerged plant community is implemented;

[0110] On the basis of the original riverbed, backfill the improved soil 3, which is composed of a mixture of 30-50cm thick low-nutrient planting soil and clay soil, and mix the crushed stone / pebbles with a particle size of 2-3cm in the improved soil 3, and the ratio of crushed stone / pebbles to improved soil 3 is 1:4. Due to the increase in flow velocity, the proportion of clay soil increases to 53.2%-69.7% compared with the still water area. According to the actual flow velocity of the project, the larger the proportion of clay soil, the better the plant growth, because the clay soil has a stronger ability to resist scouring. However, the low-nutrient planting soil should not exceed 70% to avoid water pollution caused by excess nutrition. Therefore, in the actual project implementation, it is necessary to take into account the plant growth state and the ability to resist scouring. According to the results of a large number of experimental data, the distribution ratio formula of low-nutrient planting soil and clay soil is fitted as follows: x=16.5v+40, x+y=1, where v is the water flow velocity, y is the proportion of low-nutrient planting soil, and x is the proportion of clay soil. , use bleaching powder and niclosamide mixed soil disinfectant to disinfect pathogens and harmful benthic organisms on the base, the mixing ratio is 1:0.5, and the application technical requirements are: evenly spray the whole lake, the designed dosage is 5g / m 2 ~10g / m 2 .

[0111] Then, install the honeycomb cells, the cell height is 10-15cm, the cell size is 15-25cm, and every two cells are fixed by "J" type anchor nails. After the initial installation of the honeycomb cells, immediately backfill 3-5mm with low-nutrient planting soil, and manually rake the topsoil, and then tamp it manually or by machine to ensure stability. After the honeycomb cells are installed, the anti-scour ecological layer 2 is finally backfilled. The difference between the anti-scour ecological layer 1 and the anti-scour ecological layer 2 is that the particle size of the gravel or pebble is increased to 3-4cm compared with the medium and low flow waters.

[0112] In addition to having all the functions of the medium flow rate area, the improved base soil also has stronger anti-scouring ability and can withstand scouring at a maximum flow rate of 3m / s, meeting the anti-scouring requirements of high-flow waters.

[0113] Since the river flow velocity is over 1.8m / s in the overspeed water area, the flow velocity in this area is too large, exceeding the maximum flow velocity that submerged plants can withstand. In addition, this area is the main flood discharge channel, and large-scale restoration of submerged plant communities is not conducive to flood discharge. Therefore, submerged plant community restoration is not carried out.

[0114] Then, construct and arrange submerged plant communities in high-velocity waters;

[0115] Selection of submerged plant varieties: In waters with medium flow rates, the main submerged plant varieties with strong scour resistance that are common in natural rivers, such as Potamogeton crenata and Potamogeton malachite, should be planted in a planting ratio of about 1:1, and the plant height range should be 0.7 to 1.2 m.

[0116] Submerged plant planting density: The planting density in medium-velocity waters is 200 to 220 plants / m 2 The community formed as a whole can resist the impact of high-velocity water flow. Planting depth of submerged plants: The planting depth is 13-15cm for Potamogeton comfrey and 13-15cm for Potamogeton malachite.

[0117] As in Example 1, a complete water ecosystem is constructed, and continuous human intervention ensures system stability.

[0118] After the restoration was completed, the water quality was significantly improved. After three flood seasons, the maximum flow rate of the river section was monitored to be about 1.5m / s during the third flood season. The submerged plant community was not significantly damaged, and the survival area was about 7700m 2 , the survival rate reached 96%.

[0119] Changes in the area of ​​submerged plant communities before and after restoration:

[0120] time Repair Completed 1 year after restoration 2 years after restoration 3 years after restoration <![CDATA[Submerged plant area (m 2 )]]> 8000 7950 7900 7700

[0121] Changes in water quality during the dry season before and after restoration:

[0122] Water quality parameters Before repair 1 year after restoration 2 years after restoration 3 years after restoration Transparency(cm) 50 80~120 90~130 100~140 Total phosphorus (mg / L) 0.20 0.13 0.12 0.10 Total nitrogen (mg / L) 2.2 1.4 1.2 1.0

[0123] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A method for restoring and constructing a river submerged plant community, characterized in that: It includes the following steps: Step A: Divide the river channel where the submerged plant community needs to be constructed into static water areas, medium-low flow rate areas, high flow rate areas, and super-high flow rate areas according to the flow rate and water area; Step B: Improve the substrate habitat conditions according to the flow rate water areas divided in Step A; In the said Step B, improving the substrate habitat conditions includes: B1. On the basis of the original riverbed, backfill 30-50 cm thick improved soil composed of low-nutrient planting soil and clay soil in proportion, where the low-nutrient planting soil does not exceed 70%; The method for preparing the said improved soil is: For static water areas with a flow rate of 0-0.2 m / s, the improved soil is composed of low-nutrient planting soil and clay soil, and the proportion of the clay soil used is 40%-43.3%; For medium-low flow rate areas with a flow rate of 0.2-0.8 m / s, the improved soil is composed of low-nutrient planting soil and clay soil, and the proportion of the clay soil used is 43.3%-53.2%; For high flow rate areas with a flow rate of 0.8 m / s - 1.8 m / s, the improved soil is composed of low-nutrient planting soil and clay soil, and the proportion of the clay soil used is 53.2%-69.7%; B2. Use a soil disinfectant mixed with bleaching powder and niclosamide to disinfect the base of pathogens and harmful benthic organisms. The mixing ratio of bleaching powder and niclosamide is 1:0.

5. The application requirements are: evenly spray the entire lake, with a dosage of 5g / m 2 ~10g / m 2 ; B3. On the basis of B2, backfill an anti-erosion ecological layer with a thickness of not less than 10 cm on the improved soil in the medium-low flow rate areas; B4. On the basis of B2, install honeycomb cells in the high flow rate areas, and the honeycomb cells are fixed by anchor bolts; when installing the honeycomb cells, backfill 3-5 mm thick low-nutrient planting soil, rake and tamp the surface soil; after the installation of the honeycomb cells is completed, backfill an anti-erosion ecological layer with a thickness of not less than 10 cm; Step C: Based on the velocity water area divided in step A, a submerged plant community is constructed and arranged on the basis of step B, wherein the planting density of submerged plants does not exceed 220 plants / m 2 , depth not exceeding 15cm; Step D: Release functional fish, benthic organisms, and zooplankton into the submerged plant community to construct a complete water ecosystem, and continuously carry out artificial intervention to ensure the stability of the water ecosystem.

2. A method for restoring and constructing a river submerged plant community according to claim 1, characterized in that: When backfilling the improved soil in the high flow rate areas, also mix and add gravel / pebbles with a particle size of 2-3 cm into the prepared improved soil, and the ratio of gravel / pebbles to the improved soil is 1:

4.

3. A method for restoring and constructing a river submerged plant community according to claim 1, characterized in that: The said anti-erosion ecological layer is composed of pebbles / gravel and improved soil in a ratio of 1:1, and the particle size of the pebbles / gravel in the anti-erosion ecological layer in the medium-low flow rate areas is 2-3 cm, and the particle size of the pebbles / gravel in the anti-erosion ecological layer in the high flow rate areas is 3-4 cm.

4. The method for restoring and constructing a river submerged plant community according to claim 1, characterized in that: The mixing ratio formula of the low-nutrient planting soil and clay soil is: x = 16.5v + 40, x + y = 1, where v is the water flow rate, y is the proportion of the low-nutrient planting soil, and x is the proportion of the clay soil.

5. A method for restoring and constructing a river submerged plant community according to any one of claims 2 to 4, characterized in that: The said low-nutrient planting soil does not contain construction waste, weeds, tree roots, stones, gravel, and structures, and the porosity > 40%, and the organic matter content ≤ 20 g / kg; the clay soil of the said clay soil has a porosity > 20%, the particle size range is 0.005-0.05 mm, the natural consistency index 0.25 < lc ≤ 0.75, and the organic matter content ≤ 20 g / kg.

6. The method for restoring and constructing a river submerged plant community according to claim 1, characterized in that: In the said Step C, the method for arranging the submerged plant community is: C1. Vallisneria, Myriophyllum and Hydrilla are planted in a ratio of 3:1:1 in still water areas. The plant heights are 1-1.5m, 0.5-0.8m and 0.5-0.8m respectively, and the planting density is 150-220 plants / m 2 , the planting depth of Vallisneria is 7 to 15 cm, and the planting depth of Hydrilla is 5 to 15 cm; Or C2, for waters with medium and low flow rates, Potamogeton rubrum and Potamogeton malachium are mainly planted, with Vallisneria salsa, Myriophyllum truncatum and Hydrilla verticillata as auxiliary plants. The planting ratio is 3:3:1:1:0.5, and the plant heights are 0.7-1.2m, 0.7-1.2m, 0.3-0.7m, 0.5-0.7m and 0.5-0.6m respectively, and the planting density is 150-220 plants / m 2 , the planting depth of Potamogeton ricinus and Potamogeton malachite is 10-15cm; Or C3, for high-velocity waters, plant Potamogeton rubra and Potamogeton rapa at a planting ratio of 1:1, with plant heights of 0.7 to 1.2 m and a planting density of 200 to 220 plants / m 2 The planting depth of Potamogeton ricinus and Potamogeton malachite is 13 to 15 cm.

7. A method for restoring and constructing a river submerged plant community according to claim 6, characterized in that: In the said Step D, Functional fish, benthic organisms and zooplankton are released into the submerged plant community. Functional fish include sea bass, black carp, snakehead and bighead carp; benthic organisms include pear-shaped ring snails, toothless clams and river clams; and zooplankton includes large Daphnia; Methods of artificial intervention include: cleaning the water surface and seasonal harvesting of aquatic plants; setting up interception nets along the edge of submerged plant communities, with the grid size set to within 2cm×2cm; after the flood passes, cleaning up aquatic plant attachments, checking the damage of the interception nets and replacing them in time, and supplementing fish and benthic organisms according to the water state.